  "fields": [{"id":"_id","type":"int"},{"id":"No_","type":"numeric"},{"id":"Funding Programme","type":"text"},{"id":"LA","type":"text"},{"id":"Scheme/Project Name","type":"text"},{"id":"No_ of Units","type":"numeric"},{"id":"Approved Housing Body","type":"text"},{"id":"Stage 1 Capital Appraisal","type":"text"},{"id":"Stage 2 Pre Planning","type":"text"},{"id":"Stage 3 Pre Tender design","type":"text"},{"id":"Stage 4 Tender Report or Final Turnkey/CALF approval","type":"text"},{"id":"On Site","type":"text"},{"id":"Completed","type":"text"}],
  "records": [
    [1,1,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",6,"*N/A","","","","","","Q3-2019"],
    [2,2,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",6,"*N/A","","","","","","Q3-2019"],
    [3,3,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",12,"*N/A","","","","","","Q3-2020"],
    [4,4,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",10,"*N/A","","","","","","Q4-2020"],
    [5,5,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",16,"*N/A","","","","","Q4-2017",""],
    [6,6,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",13,"*N/A","","","","","","Q2-2021"],
    [7,7,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Father Flood Avenue, Rathvilly",8,"*N/A","","","","","","Q4-2019"],
    [8,8,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","St. Oliver's Crescent, Myshall",4,"*N/A","","","","","","Q4-2019"],
    [9,9,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","St. Mary's Court & Dereen Heights, Tullow",6,"*N/A","","","","","","Q4-2020"],
    [10,10,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Crowsgrove, Kildavin",1,"*N/A","","","","","","Q1-2020"],
    [11,11,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Ardattin",6,"*N/A","","","","","Q1-2020",""],
    [12,12,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Brownbog, Hackettstown",1,"*N/A","","","","","Q1-2020",""],
    [13,13,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Spahill, Borris",1,"*N/A","","","","","","Q4-2020"],
    [14,14,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","St. Maryï¿½s Court, Carlow",4,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [15,15,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Drumphea, Garryhill, Bagenalstown",1,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [16,16,"SHIP CONSTRUCTION SINGLE STAGE","Carlow","Lackabeg, Kildavin",3,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [17,17,"SHIP CONSTRUCTION","Carlow","The Laurels, Carlow Town",5,"*N/A","","","","","","Q2-2018"],
    [18,18,"SHIP CONSTRUCTION","Carlow","Ard na Greine, Tullow",16,"*N/A","","","","","","Q4-2018"],
    [19,19,"SHIP CONSTRUCTION","Carlow","Dublin Road, Tullow",21,"*N/A","","","","","","Q3-2019"],
    [20,20,"SHIP CONSTRUCTION","Carlow","Bagenalstown",20,"*N/A","","","","","","Q3-2020"],
    [21,21,"SHIP CONSTRUCTION","Carlow","Bilboa",2,"*N/A","","","","","","Q3-2018"],
    [22,22,"SHIP CONSTRUCTION","Carlow","Slate Row, Hacketstown",4,"*N/A","","","","","","Q4-2018"],
    [23,23,"SHIP CONSTRUCTION","Carlow","Mount Leinster Park, Carlow",4,"*N/A","","","","","","Q4-2017"],
    [24,24,"SHIP CONSTRUCTION","Carlow","Myshall",4,"*N/A","","","","","","Q1-2018"],
    [25,25,"SHIP CONSTRUCTION","Carlow","Pound Lane, Borris",4,"*N/A","","","","","","Q3-2017"],
    [26,26,"SHIP CONSTRUCTION","Carlow","Rathvilly",10,"*N/A","","","","","","Q2-2017"],
    [27,27,"SHIP CONSTRUCTION","Carlow","Moneybeg, Bagenalstown",24,"*N/A","","","","","","Q3-2017"],
    [28,28,"SHIP CONSTRUCTION","Carlow","Paulville, Tullow (SRD)",1,"*N/A","","","","","","Q3-2017"],
    [29,29,"SHIP CONSTRUCTION","Carlow","Maryborough St., Carlow",5,"*N/A","","","","","","Q1-2018"],
    [30,30,"SHIP CONSTRUCTION","Carlow","Drumin, St. Mullins (SRD)",1,"*N/A","","","","","","Q1-2019"],
    [31,31,"SHIP CONSTRUCTION","Carlow","Pound Lane, Borris",9,"*N/A","","","","","","Q2-2021"],
    [32,32,"SHIP CONSTRUCTION","Carlow","Barrack Street, Carlow",7,"*N/A","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [33,33,"SHIP CONSTRUCTION","Carlow","Gleann na Bearu, Bagenalstown",22,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [34,34,"CAS CONSTRUCTION TURNKEY","Carlow","Pollerton Big, Carlow",6,"Tintean Housing Association Ltd","","","","","","Q4-2020"],
    [35,35,"CAS CONSTRUCTION","Carlow","Gleann na Bearu, Royal Oak Road, Bagenalstown",6,"Respond","","","","","Q4-2020",""],
    [36,36,"CAS CONSTRUCTION","Carlow","Ballincarrig, Wexford Road",6,"Tintean Housing Association Ltd","","","","","","Q4-2016"],
    [37,37,"CAS CONSTRUCTION","Carlow","Homefield, Blackbog Road, Carlow",3,"Carlow Voluntary Housing Association","","","","","","Q2-2021"],
    [38,38,"CALF Turnkey","Carlow","7 units, Rivercourt, Carlow (Phase 1)",3,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2019"],
    [39,39,"CALF Turnkey","Carlow","7 units, Rivercourt, Carlow (Phase 2)",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [40,40,"CALF Turnkey","Carlow","Ballickmoyler, Graigcullen, Carlow (Phase 1)",22,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [41,41,"CALF Turnkey","Carlow","Ballickmoyler, Graigcullen, Carlow (Phase 2)",35,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2019",""],
    [42,42,"CALF Turnkey","Carlow","Barrett Street, Bagnalstown, Co. Carlow (Phase 1)",10,"Tintean Housing Association Ltd","","","","","","Q1-2018"],
    [43,43,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 1)",15,"Tuath Housing Association","","","","","","Q4-2018"],
    [44,44,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 2)",12,"Tuath Housing Association","","","","","","Q2-2019"],
    [45,45,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 3)",10,"Tuath Housing Association","","","","","","Q2-2019"],
    [46,46,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 4)",6,"Tuath Housing Association","","","","","","Q3-2019"],
    [47,47,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 5)",16,"Tuath Housing Association","","","","","","Q4-2019"],
    [48,48,"CALF Turnkey","Carlow","Browneshill Wood, Browneshill Road, Chapelstown, Carlow (Phase 1)",14,"Tuath Housing Association","","","","","","Q4-2018"],
    [49,49,"CALF Turnkey","Carlow","Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 1)*",17,"Tuath Housing Association","","","","","","Q3-2021"],
    [50,50,"CALF Turnkey","Carlow","Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 2)*",12,"Tuath Housing Association","","","","","Q2-2019",""],
    [51,51,"CALF Turnkey","Carlow","Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 3)*",34,"Tuath Housing Association","","","","","Q2-2019",""],
    [52,52,"CALF Turnkey","Carlow","Greenhills, Leighlin Road, Graiguecullen, Carlow (Phase 1)",8,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [53,53,"CALF Turnkey","Carlow","Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 1)",3,"Tuath Housing Association","","","","","","Q4-2020"],
    [54,54,"CALF Turnkey","Carlow","Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 2)",6,"Tuath Housing Association","","","","","","Q2-2021"],
    [55,55,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 1)",28,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [56,56,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 2)*",19,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2018",""],
    [57,57,"CALF Turnkey","Carlow","Sleaty Street, Graigcullen, Carlow  (Phase 1)",26,"Clï¿½id Housing","","","","","","Q1-2019"],
    [58,58,"CALF Turnkey","Carlow","Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 1)",7,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [59,59,"CALF Turnkey","Carlow","Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 2)*",12,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [60,60,"CALF Turnkey","Carlow","Tanner Hall, Athy Road, Carlow (Phase 1)",9,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [61,61,"CALF Turnkey","Carlow","The Millrace, Burrin, Co. Carlow (Phase 1)*",22,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [62,62,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff",3,"*N/A","","","","","","Q4-2019"],
    [63,63,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff",4,"*N/A","","","","","","Q3-2020"],
    [64,64,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff",3,"*N/A","","","","","","Q4-2020"],
    [65,65,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff",4,"*N/A","","","","","Q2-2019",""],
    [66,66,"SHIP CONSTRUCTION TURNKEY","Cavan","Woodlands, Killyfinla, Ballyjamesduff ",4,"*N/A","","","","","Q1-2021",""],
    [67,67,"SHIP CONSTRUCTION TURNKEY","Cavan","Woodlands, Killyfinla, Ballyjamesduff",8,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [68,68,"SHIP CONSTRUCTION TURNKEY","Cavan","Woodlands, Killyfinla, Ballyjamesduff",10,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [69,69,"SHIP CONSTRUCTION TURNKEY","Cavan","Woodlands, Killyfinla, Ballyjamesduff",10,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [70,70,"SHIP CONSTRUCTION TURNKEY","Cavan","Lakeland Close, Swellan, Cavan Town",2,"*N/A","","","","","","Q4-2020"],
    [71,71,"SHIP CONSTRUCTION TURNKEY","Cavan","Mullaghduff, Ballyconnell, Co. Cavan",8,"*N/A","","","","","Q2-2021",""],
    [72,72,"SHIP CONSTRUCTION TURNKEY","Cavan","Mullaghduff, Ballyconnell, Co. Cavan",12,"*N/A","","","","","Q2-2021",""],
    [73,73,"SHIP CONSTRUCTION TURNKEY","Cavan","Mullaghduff, Ballyconnell, Co. Cavan",11,"*N/A","","","","","Q2-2021",""],
    [74,74,"SHIP CONSTRUCTION TURNKEY","Cavan","Mullaghduff, Ballyconnell, Co. Cavan",12,"*N/A","","","","","Q2-2021",""],
    [75,75,"SHIP CONSTRUCTION TURNKEY","Cavan","Clankee Court, Lisdrumskea, Shercock",2,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [76,76,"SHIP CONSTRUCTION TURNKEY","Cavan","Abhainn Dubh, Rosehill, Mullagh",4,"*N/A","","","","","Q3-2021",""],
    [77,77,"SHIP CONSTRUCTION","Cavan","Rosehill, Mullagh (Phase 6)",8,"*N/A","","","","","","Q1-2019"],
    [78,78,"SHIP CONSTRUCTION","Cavan","Butlersbridge",4,"*N/A","","","","","","Q1-2018"],
    [79,79,"SHIP CONSTRUCTION","Cavan","Woodlands, Ballyhaise",8,"*N/A","","","","","","Q4-2018"],
    [80,80,"SHIP CONSTRUCTION","Cavan","Butlersbridge",2,"*N/A","","","","","","Q2-2017"],
    [81,81,"SHIP CONSTRUCTION","Cavan","Clones Road, Butlersbridge",2,"*N/A","","","","","","Q3-2020"],
    [82,82,"SHIP CONSTRUCTION","Cavan","Corstruce, Ballinagh",4,"*N/A","","","","","","Q2-2021"],
    [83,83,"SHIP CONSTRUCTION","Cavan","Main Street, Mullagh",19,"*N/A","","","","","Q4-2020",""],
    [84,84,"SHIP CONSTRUCTION","Cavan","Elm Grove, Main St, Cavan Town",13,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [85,85,"SHIP CONSTRUCTION","Cavan","Cavan Road, Ballinagh",15,"*N/A","","","","","Q2-2021",""],
    [86,86,"SHIP CONSTRUCTION","Cavan","Main St., Butlersbridge",6,"*N/A","","","","","Q2-2021",""],
    [87,87,"SHIP CONSTRUCTION","Cavan","Cluain Dara, Kingscourt",3,"*N/A","","","","","Q1-2021",""],
    [88,88,"SHIP CONSTRUCTION","Cavan","Fairymount Close, Kingscourt, Co. Cavan",3,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [89,89,"SHIP CONSTRUCTION","Cavan","St. Bridgets Terrace, Cavan Town (Infill)",12,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [90,90,"SHIP CONSTRUCTION","Cavan","Beckscourt, Eastboro, Bailieborough",47,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [91,91,"SHIP CONSTRUCTION","Cavan","Duckin Stool, Main Street, Belturbet",3,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [92,92,"SHIP CONSTRUCTION","Cavan","The Widow's Row, Widow's House Lane, Belturbet",8,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [93,93,"CAS CONSTRUCTION TURNKEY","Cavan","Castlemanor Village, Cavan Town",29,"Tï¿½ath Housing Association Ltd","","","","","","Q3-2019"],
    [94,94,"CAS CONSTRUCTION","Cavan","St. Killian's Housing Association Ltd., Mullagh, Co. Cavan",4,"St. Killian's Housing Association, Mullagh, Co. Cavan","","","","","Q1-2021",""],
    [95,95,"CALF Turnkey","Cavan","16 Units, Fairgreen Park, Mullagh, Co. Cavan (Phase 1)",16,"Clanmil Housing Association Ireland","","","","","Q1-2020",""],
    [96,96,"CALF Turnkey","Cavan","Cluain Dara, Kingscourt, Co Cavan (Phase 1)",16,"Clï¿½id Housing","","","","","","Q4-2016"],
    [97,97,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 1)",4,"Tuath Housing Association","","","","","","Q2-2018"],
    [98,98,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 2)",5,"Tuath Housing Association","","","","","","Q3-2018"],
    [99,99,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 3)",2,"Tuath Housing Association","","","","","","Q4-2018"],
    [100,100,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Co. Cavan (Phase 1)",12,"Tuath Housing Association","","","","","Q2-2021",""],
    [101,101,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Co. Cavan (Phase 2)",13,"Tuath Housing Association","","","","","Q2-2021",""],
    [102,102,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 1)",2,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2019"],
    [103,103,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 2)",6,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [104,104,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 3)",6,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [105,105,"CALF Turnkey","Cavan","The Gallops, Cavan Town, Co. Cavan (Phase 1)",12,"Clï¿½id Housing","","","","","","Q4-2020"],
    [106,106,"CALF Turnkey","Cavan","The Gallops, Cavan Town, Co. Cavan (Phase 2)*",22,"Clï¿½id Housing","","","","","Q4-2019",""],
    [107,107,"SHIP CONSTRUCTION TURNKEY","Clare","River View, School Road, Corofin",2,"*N/A","","","","","","Q4-2018"],
    [108,108,"SHIP CONSTRUCTION TURNKEY","Clare","Cloughleigh Road + Shallee Drive, Ennis",4,"*N/A","","","","","","Q4-2020"],
    [109,109,"SHIP CONSTRUCTION TURNKEY","Clare","Shantraud Woods, Killaloe",4,"*N/A","","","","","Q3-2020",""],
    [110,110,"SHIP CONSTRUCTION SINGLE STAGE","Clare","Cappagh Lodge, Sixmilebridge",2,"*N/A","","","","","","Q4-2020"],
    [111,111,"SHIP CONSTRUCTION SINGLE STAGE","Clare","St. Michaels Place, Kilmihil",2,"*N/A","","","","","","Q4-2020"],
    [112,112,"SHIP CONSTRUCTION SINGLE STAGE","Clare","Madden's Terrace, Clarecastle",2,"*N/A","","","","","Q2-2021",""],
    [113,113,"SHIP CONSTRUCTION SINGLE STAGE","Clare","Dun na Mara, Doonbeg",2,"*N/A","","","","","","Q2-2021"],
    [114,114,"SHIP CONSTRUCTION SINGLE STAGE","Clare","St Senanï¿½s Terrace, Kilrush",2,"*N/A","","","","","","Q3-2021"],
    [115,115,"SHIP CONSTRUCTION","Clare","Roslevan, Ennis",8,"*N/A","","","","","","Q2-2020"],
    [116,116,"SHIP CONSTRUCTION","Clare","Feakle",13,"*N/A","","","","","","Q4-2019"],
    [117,117,"SHIP CONSTRUCTION","Clare","Glor Srutha, Knockbrack Lower, Clonlara",9,"*N/A","","","","","","Q4-2019"],
    [118,118,"SHIP CONSTRUCTION","Clare","Seaview Park, Quilty",18,"*N/A","","","","","","Q4-2020"],
    [119,119,"SHIP CONSTRUCTION","Clare","Ashline, Kilrush Road, Ennis",40,"*N/A","","","","","Q3-2020",""],
    [120,120,"SHIP CONSTRUCTION","Clare","Miltown Malbay",27,"*N/A","","","","","Q3-2020",""],
    [121,121,"SHIP CONSTRUCTION","Clare","Doonaun, Tulla",25,"*N/A","","","","","Q4-2020",""],
    [122,122,"SHIP CONSTRUCTION","Clare","Boheraroan, Newmarket-on-Fergus",18,"*N/A","","","","","Q4-2020",""],
    [123,123,"SHIP CONSTRUCTION","Clare","Feakle Rd., Scariff",18,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [124,124,"SHIP CONSTRUCTION","Clare","Kilkee Road, Doonbeg",8,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [125,125,"SHIP CONSTRUCTION","Clare","Tulla Road, Roslevan, Ennis",8,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [126,126,"SHIP CONSTRUCTION","Clare","7, 8, 17 St Senan's Terrace, Kilrush ",3,"*N/A","","","","","","Q4-2019"],
    [127,127,"SHIP CONSTRUCTION","Clare","Drumcliffe Road, Ennis",26,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [128,128,"SHIP CONSTRUCTION","Clare","Deerpark, Ennistymon",30,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [129,129,"SHIP CONSTRUCTION","Clare","Ballyliddan West, Sixmilebridge",16,"*N/A","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [130,130,"CAS CONSTRUCTION TURNKEY","Clare","Haggard View, Clarecastle",2,"Anvers Housing Association Ltd","","","","","","Q2-2018"],
    [131,131,"CAS CONSTRUCTION TURNKEY","Clare","Haggard View, Clarecastle",2,"Anvers Housing Association Ltd","","","","","","Q1-2018"],
    [132,132,"CAS CONSTRUCTION","Clare","Cahercalla, Ennis (Phase 2)",15,"Cuan an Chlair Ltd","","","","","","Q4-2020"],
    [133,133,"CAS CONSTRUCTION","Clare","Laurel Lodge, Clare Road, Ennis",3,"Society of Saint Vincent de Paul","","","","","","Q4-2016"],
    [134,134,"CAS CONSTRUCTION","Clare","Monaskeha Heights",4,"Newgrove Housing Association Ltd","","","","","","Q3-2019"],
    [135,135,"CAS CONSTRUCTION","Clare","Roo East",4,"Thomond Housing Association Ltd","","","","","","Q4-2018"],
    [136,136,"CAS CONSTRUCTION","Clare","9 Elmwood, Ballycannon Heights, Meelick",4,"Thomond Housing Association Ltd","","","","","","Q1-2019"],
    [137,137,"CAS CONSTRUCTION","Clare","Teach Rua, Edenvale Ennis",4,"Newgrove Housing Association Ltd","","","","","","Q2-2021"],
    [138,138,"CALF Turnkey","Clare","Abbey View, Limerick Road, Ennis, Co. Clare (Phase 1)",9,"Clï¿½id Housing","","","","Q3-2021","",""],
    [139,139,"CALF Turnkey","Clare","Abbey View, Limerick Road, Ennis, Co. Clare (Phase 2)*",15,"Clï¿½id Housing","","","","Q3-2021","",""],
    [140,140,"CALF Turnkey","Clare","Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 1)",12,"Clï¿½id Housing","","","","","","Q2-2018"],
    [141,141,"CALF Turnkey","Clare","Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 2)",18,"Clï¿½id Housing","","","","","","Q4-2018"],
    [142,142,"CALF Turnkey","Clare","Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 1)*",2,"Clï¿½id Housing","","","","","","Q4-2020"],
    [143,143,"CALF Turnkey","Clare","Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 2)*",2,"Clï¿½id Housing","","","","","Q2-2019",""],
    [144,144,"CALF Turnkey","Clare","Cluain Fia, Crusheen, Co. Clare (Phase 1)*",2,"Clï¿½id Housing","","","","","","Q2-2020"],
    [145,145,"CALF Turnkey","Clare","Cluain Fia, Crusheen, Co. Clare (Phase 2)*",2,"Clï¿½id Housing","","","","","","Q4-2020"],
    [146,146,"CALF Turnkey","Clare","Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 1)",3,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [147,147,"CALF Turnkey","Clare","Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 2)",2,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2019"],
    [148,148,"CALF Turnkey","Clare","Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 1)*",29,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [149,149,"CALF Turnkey","Clare","Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 2)*",2,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2021"],
    [150,150,"CALF Turnkey","Clare","Lios Anama, Sixmilebridge, Clare (Phase 1)",28,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2017"],
    [151,151,"CALF Construction","Clare","Revised - Bruachlan, Westbury, Co Clare (Phase 1)",22,"Co - Operative Housing Ireland Society Limited","","","","Q2-2021","",""],
    [152,152,"CALF Turnkey","Clare","Roslevan, Tulla Road, Ennis, County Clare (Phase 1)",14,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [153,153,"CALF Turnkey","Clare","Roslevan, Tulla Road, Ennis, County Clare (Phase 2)*",15,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [154,154,"CALF Turnkey","Clare","Roslevan, Tulla Road, Ennis, County Clare (Phase 3)*",19,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [155,155,"CALF Turnkey","Clare","Roslevan, Tulla Road, Ennis, County Clare (Phase 4)*",21,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [156,156,"CALF Turnkey","Clare","Sycamore Drive, Ennis, Co. Clare (Phase 1)*",3,"Clï¿½id Housing","","","","","","Q4-2019"],
    [157,157,"CALF Turnkey","Clare","Sycamore Drive, Ennis, Co. Clare (Phase 2)*",2,"Clï¿½id Housing","","","","","","Q4-2020"],
    [158,158,"CALF Turnkey","Clare","Tullyvarraga, Shannon, Co. Clare (Phase 1)*",31,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [159,159,"CALF Turnkey","Clare","Tullyvarraga, Shannon, Co. Clare (Phase 2)",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [160,160,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Clare","Shannon East (Phase 1)",20,"*N/A","","","","","","Q2-2021"],
    [161,161,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Clare","Shannon East (Phase 2)",31,"*N/A","","","","","","Q3-2021"],
    [162,162,"SHIP DIALOG","Cork City","Arus Mhuire",30,"*N/A","","","","","","Q4-2018"],
    [163,163,"SHIP DIALOG","Cork City","Barrack Street",32,"*N/A","","","","","Q1-2019",""],
    [164,164,"SHIP DIALOG","Cork City","FaranFerris",5,"*N/A","","","","","","Q4-2019"],
    [165,165,"SHIP DIALOG","Cork City","High Street",9,"*N/A","","","","","","Q4-2019"],
    [166,166,"SHIP DIALOG","Cork City","Tramore Road",4,"*N/A","","","","","","Q4-2018"],
    [167,167,"SHIP DIALOG","Cork City","Whites Street",43,"*N/A","","","","","","Q4-2019"],
    [168,168,"SHIP DIALOG","Cork City","Woods Street",16,"*N/A","","","","","Q1-2019",""],
    [169,169,"SHIP DIALOG","Cork City","Church Road, Blackrock",43,"*N/A","","","","","","Q3-2018"],
    [170,170,"SHIP DIALOG","Cork City","1-5, Ard Aoibhinn, Banduff, Mayfield",5,"*N/A","","","","","","Q3-2018"],
    [171,171,"SHIP DIALOG","Cork City","Corcorans Quay",3,"*N/A","","","","","Q2-2018",""],
    [172,172,"SHIP DIALOG","Cork City","Blarney Street",25,"*N/A","","","","","","Q4-2019"],
    [173,173,"SHIP DIALOG","Cork City","Ballinure Road, Cork City",5,"*N/A","","","","","","Q4-2020"],
    [174,174,"SHIP DIALOG","Cork City","Moss Lane, Riverway, Cork",5,"*N/A","","","","","Q1-2019",""],
    [175,175,"SHIP DIALOG","Cork City","Gerald Griffin Street, Cork",13,"*N/A","","","","","","Q4-2020"],
    [176,176,"SHIP DIALOG","Cork City","Lower John Street, Cork",17,"*N/A","","","","","","Q4-2020"],
    [177,177,"SHIP DIALOG","Cork City","Skehard Road, Blackrock, Cork",16,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [178,178,"SHIP DIALOG","Cork City","Coach Street, Cork",13,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [179,179,"SHIP DIALOG","Cork City","Shanakiel Road, Cork",20,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [180,180,"SHIP DIALOG","Cork City","Spring Lane, Blackpool, Cork",8,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [181,181,"SHIP DIALOG","Cork City","Glen Ryan Road, Cork",9,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [182,182,"SHIP DIALOG","Cork City","Pouladuff Road, Cork ",11,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [183,183,"SHIP DIALOG","Cork City","Watercourse Road, Blackpool, Cork",37,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [184,184,"SHIP DIALOG","Cork City","Denroche's Cross, Glasheen Road, Cork",43,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [185,185,"SHIP DIALOG","Cork City","Wolsey Court, Blackpool, Cork",49,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [186,186,"SHIP DIALOG","Cork City","Sunview, South Douglas Road, Douglas, Cork",25,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [187,187,"SHIP DIALOG","Cork City","Former Bolands Mill, Old Mallow Road",57,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [188,188,"SHIP CONSTRUCTION TURNKEY","Cork City","1-4 Marble Lane",4,"*N/A","","","","","","Q4-2017"],
    [189,189,"SHIP CONSTRUCTION TURNKEY","Cork City","Sheridan Park, Tramore Road",28,"*N/A","","","","","","Q4-2016"],
    [190,190,"SHIP CONSTRUCTION TURNKEY","Cork City","37-39 Dublin Street, Blackpool, Cork",5,"*N/A","","","","","","Q2-2018"],
    [191,191,"SHIP CONSTRUCTION TURNKEY","Cork City","6-10, Ard Aoibhinn, Banduff, Mayfield",5,"*N/A","","","","","","Q4-2018"],
    [192,192,"SHIP CONSTRUCTION TURNKEY","Cork City","2 Deanrock Cottages, Togher",4,"*N/A","","","","","","Q4-2018"],
    [193,193,"SHIP CONSTRUCTION TURNKEY","Cork City","258 & 259 Blarney Street, Cork",2,"*N/A","","","","","","Q1-2018"],
    [194,194,"SHIP CONSTRUCTION TURNKEY","Cork City","1 & 2 The Groves, Skehard Road, Cork",2,"*N/A","","","","","","Q2-2018"],
    [195,195,"SHIP CONSTRUCTION TURNKEY","Cork City","3B & 9B South Terrace Court, South Terrace, Cork",2,"*N/A","","","","","","Q4-2018"],
    [196,196,"SHIP CONSTRUCTION TURNKEY","Cork City","Ballinlough Road / Knockrea Lawn, Ballinlough, Cork",6,"*N/A","","","","","","Q2-2019"],
    [197,197,"SHIP CONSTRUCTION TURNKEY","Cork City","Ard na Ri, Banduff Road, Cork",10,"*N/A","","","","","","Q4-2019"],
    [198,198,"SHIP CONSTRUCTION TURNKEY","Cork City","Gearney's Boreen, Commons Road, Cork",3,"*N/A","","","","","","Q4-2019"],
    [199,199,"SHIP CONSTRUCTION TURNKEY","Cork City","Ard na Ri, Banduff Road, Cork",10,"*N/A","","","","","","Q4-2019"],
    [200,200,"SHIP CONSTRUCTION TURNKEY","Cork City","Eagle Valley, Sarsfield Road",1,"*N/A","","","","","","Q4-2019"],
    [201,201,"SHIP CONSTRUCTION TURNKEY","Cork City","Knockfree Avenue, Glengarriff Road, Fairhill, Cork",2,"*N/A","","","","","","Q4-2019"],
    [202,202,"SHIP CONSTRUCTION TURNKEY","Cork City","3-10 Herbert Lawn, Belmont, Rochestown, Cork",8,"*N/A","","","","","","Q4-2019"],
    [203,203,"SHIP CONSTRUCTION TURNKEY","Cork City","Elton Wood & Herbert Lawn, Rochestown, Cork ",8,"*N/A","","","","","","Q4-2019"],
    [204,204,"SHIP CONSTRUCTION TURNKEY","Cork City","Aspen Drive, Maryborough Hill, Cork ",29,"*N/A","","","","","","Q4-2019"],
    [205,205,"SHIP CONSTRUCTION TURNKEY","Cork City","5 Fairfield Heights, Upper Fairhill, Cork ",3,"*N/A","","","","","","Q4-2020"],
    [206,206,"SHIP CONSTRUCTION TURNKEY","Cork City","Ringcroft Avenue, Ringmahon Road, Mahon",2,"*N/A","","","","","","Q4-2020"],
    [207,207,"SHIP CONSTRUCTION TURNKEY","Cork City","Cluain Ard, Waterloo Road, Blarney, Cork",3,"*N/A","","","","","","Q4-2020"],
    [208,208,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Cork City","Clover Hill Court, Bessboro Road, Mahon, Cork",51,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [209,209,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Cork City","Westside, Model Farm Road, Cork",32,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [210,210,"SHIP CONSTRUCTION","Cork City","Poulavone, Ballincollig",64,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [211,211,"SHIP CONSTRUCTION","Cork City","The Meadows, Knocknacullen",1,"*N/A","","","","","","Q3-2016"],
    [212,212,"SHIP CONSTRUCTION","Cork City","Boyces Street",14,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [213,213,"SHIP CONSTRUCTION","Cork City","Shandon Street/John Philpott Curran Street",9,"*N/A","","","","","","Q4-2020"],
    [214,214,"SHIP CONSTRUCTION","Cork City","St. Johns Well",6,"*N/A","","","","","","Q4-2019"],
    [215,215,"SHIP CONSTRUCTION","Cork City","Churchfield Place East",3,"*N/A","","","","","","Q4-2018"],
    [216,216,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher",8,"*N/A","","","","","","Q4-2018"],
    [217,217,"SHIP CONSTRUCTION","Cork City","Gerald Griffin Street",43,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [218,218,"SHIP CONSTRUCTION","Cork City","Cappanoole",2,"*N/A","","","","","","Q4-2016"],
    [219,219,"SHIP CONSTRUCTION","Cork City","Madonna House, Ballincollig (Phase 2)",6,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [220,220,"SHIP CONSTRUCTION","Cork City","Bramble Cottages",4,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [221,221,"SHIP CONSTRUCTION","Cork City","Errigal Heights, The Glen, Cork City",28,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [222,222,"SHIP CONSTRUCTION","Cork City","Glenamoy Lawn, Mayfield, Cork",3,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [223,223,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher",7,"*N/A","","","","","","Q1-2019"],
    [224,224,"SHIP CONSTRUCTION","Cork City","Hollywood Estate Infill Housing, Blarney Road, Cork",7,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [225,225,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher",50,"*N/A","","","","","","Q3-2019"],
    [226,226,"SHIP CONSTRUCTION","Cork City","Gerald Griffin Apartments - Block 7, North Monastery Road / St. Vincent's Road, Cork",6,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [227,227,"SHIP CONSTRUCTION","Cork City","16A Kerry Road (former Slï¿½ Gartan), Mayfield, Cork ",1,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [228,228,"SHIP CONSTRUCTION","Cork City","21A Carrigmore Park, Ballinlough, Cork",1,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [229,229,"SHIP CONSTRUCTION","Cork City","Boyces street",37,"*N/A","","","Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.","","",""],
    [230,230,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 1B",29,"*N/A","","","","","","Q4-2017"],
    [231,231,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 2A",47,"*N/A","","","","","","Q4-2019"],
    [232,232,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 1C",41,"*N/A","","","Stage 3 approved Q2-2020, the scheme is now approved to proceed to tender.","","",""],
    [233,233,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 2B",38,"*N/A","","","Stage 3 approved Q2-2020, the scheme is now approved to proceed to tender.","","",""],
    [234,234,"REGENERATION","Cork City","CNWQR Knocknaheeney Phase 2C",24,"*N/A","","","","","","Q4-2020"],
    [235,235,"REGENERATION","Cork City","Foyle Avenue Infill Housing Development, Knocknaheeny, Cork",2,"*N/A","","","Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.","","",""],
    [236,236,"REGENERATION","Cork City","Ardmore Avenue, Knocknaheeny, Cork",1,"*N/A","","","Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.","","",""],
    [237,237,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 3B",62,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [238,238,"REGENERATION","Cork City","CNWQR Knocknaheeny Phase 4A",43,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [239,239,"CAS CONSTRUCTION","Cork City","Edel House, Grattan Street",37,"Good Shepherd Services Ltd","","","","","","Q4-2020"],
    [240,240,"CAS CONSTRUCTION","Cork City","Saint Vincent's Convent, Vincent's Ave/St. Mary's Street",25,"Respond","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [241,241,"CAS CONSTRUCTION","Cork City","Thomas Davis Street (Phase 1)",28,"Respond","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [242,242,"CAS CONSTRUCTION","Cork City","Ceanncora Lawn, Ballinlough",1,"Cork Mental Health Voluntary Housing Association Ltd","","","","","","Q3-2018"],
    [243,243,"CAS CONSTRUCTION","Cork City","St. Joachim & Anne's, Anglesea Street",8,"Simon Community : Cork Simon","","","","","","Q4-2020"],
    [244,244,"CAS CONSTRUCTION","Cork City","27-29 Dublin Street, Blackpool",10,"Respond","","","","","","Q3-2018"],
    [245,245,"CAS CONSTRUCTION","Cork City","Ard na Ri, Closes Green, Farranree, Cork",20,"Farranree Sheltered Housing Association","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [246,246,"CAS CONSTRUCTION","Cork City","Apts 2 & 3 Cois Coille, Tivoli, Cork",2,"Galtan Ltd","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [247,247,"CAS CONSTRUCTION","Cork City","Aras Lean, Murphyï¿½s Farm, Bishopstown, Co. Cork",25,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [248,248,"CALF Turnkey","Cork City","12,14,15 Model Quarters, Tower, Blarney, Co Cork  (Phase 1)",3,"Circle Voluntary Housing Association Ltd","","","","","Q2-2019",""],
    [249,249,"CALF Turnkey","Cork City","20 and 21 Kyle Street  (Phase 1)",6,"Focus Housing Association CLG","","","","Q2-2021","",""],
    [250,250,"CALF Turnkey","Cork City","40-41 Grand Parade, Cork City (Phase 1)",7,"Focus Housing Association CLG","","","","","Q2-2021",""],
    [251,251,"CALF Turnkey","Cork City","5 units, Shandon Street, Cork (Phase 1)",5,"Circle Voluntary Housing Association Ltd","","","","","","Q3-2019"],
    [252,252,"CALF Turnkey","Cork City","Barters Wood, Tower, Cork (Phase 1)*",2,"Tuath Housing Association","","","","","Q1-2020",""],
    [253,253,"CALF Turnkey","Cork City","Barters Wood, Tower, Cork (Phase 2)*",2,"Tuath Housing Association","","","","","Q1-2020",""],
    [254,254,"CALF Turnkey","Cork City","Barters Wood, Tower, Cork (Phase 3)*",2,"Tuath Housing Association","","","","","Q1-2020",""],
    [255,255,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 1)*",37,"Tuath Housing Association","","","","","","Q4-2019"],
    [256,256,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 2)*",49,"Tuath Housing Association","","","","","","Q4-2020"],
    [257,257,"CALF Turnkey","Cork City","Block 10 Jacobs Island, Mahon, Cork (Phase 1)",59,"Respond","","","","Q2-2021","",""],
    [258,258,"CALF Turnkey","Cork City","Boherboy Road, Silversprings Hill, Cork City  (Phase 1)*",15,"Respond","","","","Q1-2021","",""],
    [259,259,"CALF Turnkey","Cork City","Convent Gardens, Blackrock Villas, Blackrock, Co. Cork (Phase 1)",1,"Tuath Housing Association","","","","","","Q4-2019"],
    [260,260,"CALF Turnkey","Cork City","Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 1)",4,"Tuath Housing Association","","","","","","Q4-2020"],
    [261,261,"CALF Turnkey","Cork City","Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 2)",2,"Tuath Housing Association","","","","","","Q4-2020"],
    [262,262,"CALF Turnkey","Cork City","Croppy Boy, Fairhill, Cork (Phase 1)",7,"Tuath Housing Association","","","","","","Q3-2020"],
    [263,263,"CALF Turnkey","Cork City","Croppy Boy, Fairhill, Cork (Phase 2)*",14,"Tuath Housing Association","","","","","","Q4-2020"],
    [264,264,"CALF Turnkey","Cork City","Emerald View, Old Mallow Road, Cork City (Phase 1)",6,"Focus Housing Association CLG","","","","","Q1-2021",""],
    [265,265,"CALF Turnkey","Cork City","Evergreen Road, Turners Cross, Cork  (Phase 1)*",28,"Respond","","","","","Q1-2021",""],
    [266,266,"CALF Turnkey","Cork City","Fairfield Meadows, Upper Fair Hill, Cork (Phase 1)*",18,"Focus Housing Association CLG","","","","Q3-2021","",""],
    [267,267,"CALF Turnkey","Cork City","Glanmire Village, Glanmire, Cork (Phase 1)",3,"Focus Housing Association CLG","","","","","Q2-2020",""],
    [268,268,"CALF Construction","Cork City","Green Lane, Blackpool, Cork City (Phase 1)",112,"Clï¿½id Housing","","","","Q1-2021","",""],
    [269,269,"CALF Turnkey","Cork City","Haig Gardens, Boreenamanna Road and Wallace Avenue, Ballintemple (Phase 1)*",27,"Respond","","","","","Q2-2021",""],
    [270,270,"CALF Turnkey","Cork City","Hereford Place, Ballymacthomas Street, Cork City (Phase 1)*",19,"Respond","","","","","Q1-2020",""],
    [271,271,"CALF Turnkey","Cork City","Lancaster Gate, Western Road, Cork (Phase 1)",15,"Clï¿½id Housing","","","","","Q3-2021",""],
    [272,272,"CALF Turnkey","Cork City","Leeside Apartments, Bachelors Quay, Cork City (Phase 1)",72,"Clï¿½id Housing","","","","","","Q4-2018"],
    [273,273,"CALF Turnkey","Cork City","Leeside Apartments, Bachelors Quay, Cork City (Phase 2)",6,"Clï¿½id Housing","","","","","","Q3-2019"],
    [274,274,"CALF Turnkey","Cork City","Lios Cara, Rathpeacon, Killeens, Cork (Phase 1)",12,"Clï¿½id Housing","","","","Q2-2021","",""],
    [275,275,"CALF Construction","Cork City","Lower Glanmire Road, Cork City (Phase 1)",8,"Galtan Ltd","","","","","","Q4-2019"],
    [276,276,"CALF Construction","Cork City","Lr. Glanmire Road & 2 Braemer, Cork (Phase 1)",3,"Galtan Ltd","","","","","","Q1-2018"],
    [277,277,"CALF Construction","Cork City","Lr. Glanmire Road & 2 Braemer, Cork (Phase 2)",3,"Galtan Ltd","","","","","","Q4-2018"],
    [278,278,"CALF Turnkey","Cork City","Maryborough Ridge & Blackrock  Villas\\n (Phase 1)*",57,"Tuath Housing Association","","","","","","Q4-2019"],
    [279,279,"CALF Turnkey","Cork City","Miles Stream, Shanakiel, Cork (Phase 1)",14,"Tuath Housing Association","","","","","Q3-2021",""],
    [280,280,"CALF Turnkey","Cork City","Miles Stream, Shanakiel, Cork (Phase 2)",14,"Tuath Housing Association","","","","","Q3-2021",""],
    [281,281,"CALF Turnkey","Cork City","Miles Stream, Shanakiel, Cork (Phase 3)",14,"Tuath Housing Association","","","","","Q3-2021",""],
    [282,282,"CALF Turnkey","Cork City","Millerd Street, Cork (Phase 1)",25,"Respond","","","","","","Q4-2020"],
    [283,283,"CALF Turnkey","Cork City","North Abbey Street, Cork City  (Phase 1)",6,"Respond","","","","","","Q4-2018"],
    [284,284,"CALF Turnkey","Cork City","Redforge Road, Blackpool, Cork City (Phase 1)",18,"Respond","","","","","","Q4-2020"],
    [285,285,"CALF Turnkey","Cork City","Redforge Road, Blackpool, Cork City (Phase 2)*",62,"Respond","","","","","Q1-2020",""],
    [286,286,"CALF Turnkey","Cork City","Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 1)",31,"Tuath Housing Association","","","","","","Q4-2018"],
    [287,287,"CALF Turnkey","Cork City","Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 2)",21,"Tuath Housing Association","","","","","","Q4-2019"],
    [288,288,"CALF Turnkey","Cork City","Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 1)*",22,"Respond","","","","","Q4-2020",""],
    [289,289,"CALF Turnkey","Cork City","Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 2)*",19,"Respond","","","","","Q4-2020",""],
    [290,290,"CALF Turnkey","Cork City","Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 3)",24,"Respond","","","","","Q4-2020",""],
    [291,291,"CALF Turnkey","Cork City","Springville House, Bulls Lane, Blackrock Road, Cork (Phase 1)",35,"Tuath Housing Association","","","","","Q4-2020",""],
    [292,292,"CALF Turnkey","Cork City","The Meadows (Phase 2) Gurranabraher, Cork City  (Phase 1)",17,"Tuath Housing Association","","","","","","Q4-2019"],
    [293,293,"CALF Turnkey","Cork City","The Oaks, Frankfield, Douglas, Cork City (Phase 1)*",2,"Tuath Housing Association","","","","","Q4-2019",""],
    [294,294,"CALF Turnkey","Cork City"," Tower Street, Cork City (Phase 1)",2,"Threshold Ltd","","","","Q2-2021","",""],
    [295,295,"CALF Turnkey","Cork City","Woodside, Kerry Pike, Cork (Phase 1)*",22,"Clï¿½id Housing","","","","","","Q4-2020"],
    [296,296,"SHIP CONSTRUCTION TURNKEY","Cork County","Church Road/Station Road, Carrigtwohill",18,"*N/A","","","","","","Q2-2018"],
    [297,297,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis Alainn & Castleoaks, Bandon",11,"*N/A","","","","","","Q4-2017"],
    [298,298,"SHIP CONSTRUCTION TURNKEY","Cork County","Gleann Tuairigh, Youghal",3,"*N/A","","","","","","Q4-2018"],
    [299,299,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk",11,"*N/A","","","","","","Q4-2019"],
    [300,300,"SHIP CONSTRUCTION TURNKEY","Cork County","Clondulane, Fermoy",2,"*N/A","","","","","","Q4-2017"],
    [301,301,"SHIP CONSTRUCTION TURNKEY","Cork County","College Wood, Cobh",31,"*N/A","","","","","","Q4-2017"],
    [302,302,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas",12,"*N/A","","","","","","Q4-2017"],
    [303,303,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy",4,"*N/A","","","","","","Q4-2019"],
    [304,304,"SHIP CONSTRUCTION TURNKEY","Cork County","CulAird Carraigtwohill",29,"*N/A","","","","","","Q4-2017"],
    [305,305,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas",12,"*N/A","","","","","","Q1-2017"],
    [306,306,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas",16,"*N/A","","","","","","Q1-2017"],
    [307,307,"SHIP CONSTRUCTION TURNKEY","Cork County","Claragh Road, Millstreet",5,"*N/A","","","","","","Q2-2021"],
    [308,308,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Maryï¿½s Road, Dunmanway",7,"*N/A","","","","","","Q3-2020"],
    [309,309,"SHIP CONSTRUCTION TURNKEY","Cork County","Glanworth, Fermoy",13,"*N/A","","","","","Q1-2020",""],
    [310,310,"SHIP CONSTRUCTION TURNKEY","Cork County","Quartertown, Mallow",5,"*N/A","","","","","","Q4-2019"],
    [311,311,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",8,"*N/A","","","","","","Q4-2019"],
    [312,312,"SHIP CONSTRUCTION TURNKEY","Cork County","Beacon Point, Baltimore",6,"*N/A","","","","","","Q2-2019"],
    [313,313,"SHIP CONSTRUCTION TURNKEY","Cork County","Corrin View, Fermoy",6,"*N/A","","","","","","Q2-2019"],
    [314,314,"SHIP CONSTRUCTION TURNKEY","Cork County","No. 43 & No. 50 Chapel Court, Skibbereen ",2,"*N/A","","","","","","Q3-2018"],
    [315,315,"SHIP CONSTRUCTION TURNKEY","Cork County","Cul Na Smear, Bandon",14,"*N/A","","","","","","Q4-2018"],
    [316,316,"SHIP CONSTRUCTION TURNKEY","Cork County","Glen Dara, Ard Cashel, Watergrasshill",6,"*N/A","","","","","","Q4-2018"],
    [317,317,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas",9,"*N/A","","","","","","Q2-2019"],
    [318,318,"SHIP CONSTRUCTION TURNKEY","Cork County","Sweetfields, Youghal",15,"*N/A","","","","","","Q4-2020"],
    [319,319,"SHIP CONSTRUCTION TURNKEY","Cork County","Lismire",4,"*N/A","","","","","","Q4-2018"],
    [320,320,"SHIP CONSTRUCTION TURNKEY","Cork County","Rylane, Mount Rivers",3,"*N/A","","","","","","Q4-2020"],
    [321,321,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas",17,"*N/A","","","","","","Q4-2020"],
    [322,322,"SHIP CONSTRUCTION TURNKEY","Cork County","Seafield, Bantry, ",3,"*N/A","","","","","Q3-2018",""],
    [323,323,"SHIP CONSTRUCTION TURNKEY","Cork County","Parklands, Youghal",13,"*N/A","","","","","","Q4-2018"],
    [324,324,"SHIP CONSTRUCTION TURNKEY","Cork County","Oliver Plunkett Place, Doneraile",2,"*N/A","","","","","","Q4-2019"],
    [325,325,"SHIP CONSTRUCTION TURNKEY","Cork County","No.9 and No.10  Chapel Court, Skibbereen,",2,"*N/A","","","","","","Q4-2018"],
    [326,326,"SHIP CONSTRUCTION TURNKEY","Cork County","Tir Cluain, Midleton",8,"*N/A","","","","","","Q4-2018"],
    [327,327,"SHIP CONSTRUCTION TURNKEY","Cork County","College Mews, Cobh",6,"*N/A","","","","","","Q4-2018"],
    [328,328,"SHIP CONSTRUCTION TURNKEY","Cork County","Rathcormac",4,"*N/A","","","","","","Q4-2018"],
    [329,329,"SHIP CONSTRUCTION TURNKEY","Cork County","Fairgreen, Mallow",10,"*N/A","","","","","","Q4-2019"],
    [330,330,"SHIP CONSTRUCTION TURNKEY","Cork County","Tir Cluain, Midleton",14,"*N/A","","","","","","Q3-2019"],
    [331,331,"SHIP CONSTRUCTION TURNKEY","Cork County","Church Road/Station Road, Carrigtwohill",7,"*N/A","","","","","","Q3-2018"],
    [332,332,"SHIP CONSTRUCTION TURNKEY","Cork County","Canon St, Rathcormac",3,"*N/A","","","","","Q1-2019",""],
    [333,333,"SHIP CONSTRUCTION TURNKEY","Cork County","Percival St, Kanturk",2,"*N/A","","","","","","Q4-2018"],
    [334,334,"SHIP CONSTRUCTION TURNKEY","Cork County","9 & 9a Main Street, Boherbue",2,"*N/A","","","","","","Q4-2018"],
    [335,335,"SHIP CONSTRUCTION TURNKEY","Cork County","Parklands, Youghal",6,"*N/A","","","","","","Q2-2019"],
    [336,336,"SHIP CONSTRUCTION TURNKEY","Cork County","Rathcormac",4,"*N/A","","","","","","Q2-2019"],
    [337,337,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis Fï¿½il, Curraclough, Bandon",13,"*N/A","","","","","","Q4-2019"],
    [338,338,"SHIP CONSTRUCTION TURNKEY","Cork County","Maple Woods, Midleton",6,"*N/A","","","","","","Q4-2018"],
    [339,339,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy",8,"*N/A","","","","","Q4-2017",""],
    [340,340,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Maryï¿½s Road, Dunmanway",6,"*N/A","","","","","","Q3-2020"],
    [341,341,"SHIP CONSTRUCTION TURNKEY","Cork County","Sweetfields, Youghal",10,"*N/A","","","","","Q1-2019",""],
    [342,342,"SHIP CONSTRUCTION TURNKEY","Cork County","Copper Point, Schull",7,"*N/A","","","","","Q2-2019",""],
    [343,343,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore, Bloomfield, Midleton",12,"*N/A","","","","","","Q4-2020"],
    [344,344,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore, Bloomfield, Midleton",11,"*N/A","","","","","","Q1-2021"],
    [345,345,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore, Bloomfield, Midleton",17,"*N/A","","","","","","Q2-2021"],
    [346,346,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",2,"*N/A","","","","","","Q3-2019"],
    [347,347,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",6,"*N/A","","","","","","Q2-2020"],
    [348,348,"SHIP CONSTRUCTION TURNKEY","Cork County","Gleann Orga, Ballinhassig",4,"*N/A","","","","","","Q4-2019"],
    [349,349,"SHIP CONSTRUCTION TURNKEY","Cork County","Lios Ard, Ballyhooly",8,"*N/A","","","","","","Q4-2020"],
    [350,350,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Ard, Cobh",6,"*N/A","","","","","","Q3-2019"],
    [351,351,"SHIP CONSTRUCTION TURNKEY","Cork County","Baltimore, West Cork",12,"*N/A","","","","","","Q4-2019"],
    [352,352,"SHIP CONSTRUCTION TURNKEY","Cork County","Chapel Court, Skibbereen",2,"*N/A","","","","","","Q4-2019"],
    [353,353,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Ard, Freemount",4,"*N/A","","","","","","Q4-2019"],
    [354,354,"SHIP CONSTRUCTION TURNKEY","Cork County","Glengarriff",5,"*N/A","","","","","","Q4-2019"],
    [355,355,"SHIP CONSTRUCTION TURNKEY","Cork County","The Cove, Glandore",4,"*N/A","","","","","","Q4-2019"],
    [356,356,"SHIP CONSTRUCTION TURNKEY","Cork County","Copper Point, Schull",7,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [357,357,"SHIP CONSTRUCTION TURNKEY","Cork County","An Tui, Lisgoold, Leamlara",3,"*N/A","","","","","","Q4-2019"],
    [358,358,"SHIP CONSTRUCTION TURNKEY","Cork County","Millstreet Road, Macroom",12,"*N/A","","","","","","Q4-2020"],
    [359,359,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas",14,"*N/A","","","","","","Q4-2019"],
    [360,360,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",12,"*N/A","","","","","","Q4-2020"],
    [361,361,"SHIP CONSTRUCTION TURNKEY","Cork County","Glenbeg The Beeches, Boherbue",4,"*N/A","","","","","","Q4-2019"],
    [362,362,"SHIP CONSTRUCTION TURNKEY","Cork County","Chapel Court, Skibbereen",3,"*N/A","","","","","","Q4-2019"],
    [363,363,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk",4,"*N/A","","","","","","Q1-2021"],
    [364,364,"SHIP CONSTRUCTION TURNKEY","Cork County","An Tui, Lisgoold, Leamlara",1,"*N/A","","","","","","Q2-2020"],
    [365,365,"SHIP CONSTRUCTION TURNKEY","Cork County","Bruhenny, Churchtown",6,"*N/A","","","","","","Q4-2019"],
    [366,366,"SHIP CONSTRUCTION TURNKEY","Cork County","Ard Bhaile, Buttevant",6,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [367,367,"SHIP CONSTRUCTION TURNKEY","Cork County","Cecilstown, Mallow",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [368,368,"SHIP CONSTRUCTION TURNKEY","Cork County","Ballymacmoy, Killavullen, Co. Cork",13,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [369,369,"SHIP CONSTRUCTION TURNKEY","Cork County","Meenane, Watergrasshill",4,"*N/A","","","","","","Q2-2021"],
    [370,370,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",8,"*N/A","","","","","","Q3-2019"],
    [371,371,"SHIP CONSTRUCTION TURNKEY","Cork County","Gortnaclohy, Skibbereen, Co. Cork",34,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [372,372,"SHIP CONSTRUCTION TURNKEY","Cork County","Castle Heights, Carrigaline",3,"*N/A","","","","","","Q4-2020"],
    [373,373,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",7,"*N/A","","","","","","Q4-2019"],
    [374,374,"SHIP CONSTRUCTION TURNKEY","Cork County","The Court, Ard Cashel, Watergrasshill",4,"*N/A","","","","","","Q4-2019"],
    [375,375,"SHIP CONSTRUCTION TURNKEY","Cork County","Kilmoney, Carrigaline",12,"*N/A","","","","","Q1-2021",""],
    [376,376,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk",10,"*N/A","","","","","","Q4-2020"],
    [377,377,"SHIP CONSTRUCTION TURNKEY","Cork County","Glenbeg, The Beeches, Boherbue",8,"*N/A","","","","","","Q4-2020"],
    [378,378,"SHIP CONSTRUCTION TURNKEY","Cork County","Oliver Plunkett Place, Doneraile",3,"*N/A","","","","","","Q4-2020"],
    [379,379,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy",14,"*N/A","","","","","Q4-2017",""],
    [380,380,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis Fï¿½il, Curraclough, Bandon",17,"*N/A","","","","","","Q3-2020"],
    [381,381,"SHIP CONSTRUCTION TURNKEY","Cork County","Caherdaniel, Bantry",10,"*N/A","","","","","Q1-2020",""],
    [382,382,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Maryï¿½s Road, Dunmanway",7,"*N/A","","","","","","Q4-2019"],
    [383,383,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",7,"*N/A","","","","","","Q4-2020"],
    [384,384,"SHIP CONSTRUCTION TURNKEY","Cork County","An Goritin Rua, Millstreet Road, Macroom",14,"*N/A","","","","","","Q2-2021"],
    [385,385,"SHIP CONSTRUCTION TURNKEY","Cork County","King St, Mitchelstown",2,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [386,386,"SHIP CONSTRUCTION TURNKEY","Cork County","Lyraneag, Rockchapel,",2,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [387,387,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Reidh, Ballyvourney",1,"*N/A","","","","","","Q4-2019"],
    [388,388,"SHIP CONSTRUCTION TURNKEY","Cork County","Curragh, Upper Aghada",2,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [389,389,"SHIP CONSTRUCTION TURNKEY","Cork County","Glebe Manor, Whitegate",12,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [390,390,"SHIP CONSTRUCTION TURNKEY","Cork County","Eyeries, Castletownbere",6,"*N/A","","","","","Q4-2020",""],
    [391,391,"SHIP CONSTRUCTION TURNKEY","Cork County","Kilmorna, Mallow",1,"*N/A","","","","","","Q4-2020"],
    [392,392,"SHIP CONSTRUCTION TURNKEY","Cork County","Lios Ard, Ballyhooly",6,"*N/A","","","","","","Q1-2021"],
    [393,393,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",20,"*N/A","","","","","","Q4-2020"],
    [394,394,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",18,"*N/A","","","","","","Q2-2021"],
    [395,395,"SHIP CONSTRUCTION TURNKEY","Cork County","Drakes Point, Knocknagore, Crosshaven",5,"*N/A","","","","","","Q3-2021"],
    [396,396,"SHIP CONSTRUCTION TURNKEY","Cork County","Abbeyfort, Kinsale",14,"*N/A","","","","","","Q4-2020"],
    [397,397,"SHIP CONSTRUCTION TURNKEY","Cork County","Caherdaniel, Bantry",6,"*N/A","","","","","Q1-2020",""],
    [398,398,"SHIP CONSTRUCTION TURNKEY","Cork County","Caherdaniel, Bantry",18,"*N/A","","","","","Q1-2020",""],
    [399,399,"SHIP CONSTRUCTION TURNKEY","Cork County","Abbeyfort, Kinsale",19,"*N/A","","","","","Q4-2019",""],
    [400,400,"SHIP CONSTRUCTION TURNKEY","Cork County","Oliver Plunkett Place, Doneraile",1,"*N/A","","","","","","Q3-2020"],
    [401,401,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",8,"*N/A","","","","","","Q3-2020"],
    [402,402,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas",4,"*N/A","","","","","","Q1-2021"],
    [403,403,"SHIP CONSTRUCTION TURNKEY","Cork County","Abbeyfort, Kinsale, Phase 2, Co. Cork",17,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [404,404,"SHIP CONSTRUCTION TURNKEY","Cork County","Ard Cashel, Watergrasshill, Co. Cork",6,"*N/A","","","","","Q3-2021",""],
    [405,405,"SHIP CONSTRUCTION TURNKEY","Cork County","Lios Ard, Ballyhooly",6,"*N/A","","","","","","Q2-2021"],
    [406,406,"SHIP CONSTRUCTION TURNKEY","Cork County","Courtbrack, Tower",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [407,407,"SHIP CONSTRUCTION TURNKEY","Cork County","Sweetfields, Youghal",10,"*N/A","","","","Stage 4 approved Q2-2018, the scheme is fully approved.","",""],
    [408,408,"SHIP CONSTRUCTION TURNKEY","Cork County","An Tui, Liosgoold",2,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [409,409,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy",26,"*N/A","","","","Stage 4 approved Q3-2016, the scheme is fully approved.","",""],
    [410,410,"SHIP CONSTRUCTION TURNKEY","Cork County","The Pastures, Charleville, Co. Cork",4,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [411,411,"SHIP CONSTRUCTION TURNKEY","Cork County","Meenane, Watergrasshill",7,"*N/A","","","","","","Q2-2021"],
    [412,412,"SHIP CONSTRUCTION TURNKEY","Cork County","Meenane, Watergrasshill",10,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [413,413,"SHIP CONSTRUCTION TURNKEY","Cork County","The Pastures, Charleville, Co. Cork",12,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [414,414,"SHIP CONSTRUCTION TURNKEY","Cork County","Kilmoney, Carrigaline",21,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [415,415,"SHIP CONSTRUCTION TURNKEY","Cork County","Kilmoney, Carrigaline",11,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [416,416,"SHIP CONSTRUCTION TURNKEY","Cork County","Kilmoney, Carrigaline",14,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [417,417,"SHIP CONSTRUCTION TURNKEY","Cork County","Derrymihin, Castletownbere, Co. Cork",16,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [418,418,"SHIP CONSTRUCTION TURNKEY","Cork County","Meenane, Watergrasshill",4,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [419,419,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Model Village, Dripsey",6,"*N/A","","","","","","Q4-2020"],
    [420,420,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Castletreasure Grove, Douglas",2,"*N/A","","","","","","Q4-2019"],
    [421,421,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Seaview Cottages, Derrymihan, Castletownbere",3,"*N/A","","","","","","Q4-2020"],
    [422,422,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Curraleigh, Inniscarra",1,"*N/A","","","","","","Q3-2019"],
    [423,423,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Cuirt Na Slini, Cloyne, East Cork ",2,"*N/A","","","","","Q3-2021",""],
    [424,424,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Main St. Dunmanway",1,"*N/A","","","","","Q4-2020",""],
    [425,425,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Thomas Kent Street, Cobh",1,"*N/A","","","","","","Q4-2020"],
    [426,426,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Croke Place, Garranmacgarrett, Kilbrin, kanturk",2,"*N/A","","","","","Q3-2020",""],
    [427,427,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","High St., Sleaveen Hill, Macroom, Co. Cork",1,"*N/A","","","","","Q2-2021",""],
    [428,428,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","49 Masseytown, Macroom, Co. Cork ",1,"*N/A","","","","","Q2-2021",""],
    [429,429,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","Fana Na gCann, Co. Cork",2,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [430,430,"SHIP CONSTRUCTION SINGLE STAGE","Cork County","3 Knockbrogan Park, Bandon",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [431,431,"SHIP CONSTRUCTION","Cork County","Downeen Cross, Rosscarbery",7,"*N/A","","","","","","Q4-2019"],
    [432,432,"SHIP CONSTRUCTION","Cork County","Ard Na Greine, Cortmacsherry",17,"*N/A","","","","","Q3-2019",""],
    [433,433,"SHIP CONSTRUCTION","Cork County","Station Road, Blarney",18,"*N/A","","","","","","Q4-2020"],
    [434,434,"SHIP CONSTRUCTION","Cork County","Bluepool, Kanturk",12,"*N/A","","","","","","Q4-2020"],
    [435,435,"SHIP CONSTRUCTION","Cork County","Tower View/Cï¿½irt na Silï¿½nï¿½, Cloyne, East Cork",7,"*N/A","","","","","","Q3-2019"],
    [436,436,"SHIP CONSTRUCTION","Cork County","Beechgrove, Clonakilty",57,"*N/A","","","","","Q3-2019",""],
    [437,437,"SHIP CONSTRUCTION","Cork County","Newtown House , Bantry",1,"*N/A","","","","","Q3-2020",""],
    [438,438,"SHIP CONSTRUCTION","Cork County","Fairfield, Masseytown, Macroom",7,"*N/A","","","","","","Q4-2018"],
    [439,439,"SHIP CONSTRUCTION","Cork County","12 & 14 Droum, Castletownbere",2,"*N/A","","","","","","Q4-2018"],
    [440,440,"SHIP CONSTRUCTION","Cork County","Kilnagleary, Carrigaline (Phase 4)",15,"*N/A","","","","","Q4-2019",""],
    [441,441,"SHIP CONSTRUCTION","Cork County","Oliver Plunkett Hill, Fermoy",10,"*N/A","","","","","","Q2-2017"],
    [442,442,"SHIP CONSTRUCTION","Cork County","Townsend Street, Skibbereen",6,"*N/A","","","","","Q3-2019",""],
    [443,443,"SHIP CONSTRUCTION","Cork County","Forest View, Mallow",10,"*N/A","","","","","","Q4-2020"],
    [444,444,"SHIP CONSTRUCTION","Cork County","11/10 Harbour Hill, Cobh",1,"*N/A","","","","","","Q2-2018"],
    [445,445,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline",10,"*N/A","","","","","","Q4-2018"],
    [446,446,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline",16,"*N/A","","","","","","Q1-2019"],
    [447,447,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline",18,"*N/A","","","","","","Q1-2019"],
    [448,448,"SHIP CONSTRUCTION","Cork County","Kearney's field Dunmanway",5,"*N/A","","","","","Q3-2020",""],
    [449,449,"SHIP CONSTRUCTION","Cork County","Richmond Court, Bandon",6,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [450,450,"SHIP CONSTRUCTION","Cork County","Brigown Road, Mitchelstown",8,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [451,451,"SHIP CONSTRUCTION","Cork County","Sleaveen East, Macroom",8,"*N/A","","","","","Q4-2019",""],
    [452,452,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline",5,"*N/A","","","","","","Q4-2018"],
    [453,453,"SHIP CONSTRUCTION","Cork County","Tudor Grove, Ballincollig",16,"*N/A","","","","","","Q4-2019"],
    [454,454,"SHIP CONSTRUCTION","Cork County","Pound Lane, Kilworth ",7,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [455,455,"SHIP CONSTRUCTION","Cork County","24 Glenview Terrace Lyre Co Cork",1,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [456,456,"SHIP CONSTRUCTION","Cork County","Knocknagown, Rylane",1,"*N/A","","","","","","Q3-2021"],
    [457,457,"SHIP CONSTRUCTION","Cork County","Uplands (Phase 2), College Road,  Fermoy",11,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [458,458,"SHIP CONSTRUCTION","Cork County","Lissoran, Ballinspittle",4,"*N/A","","","","","Q4-2020",""],
    [459,459,"SHIP CONSTRUCTION","Cork County","Convent Road, Doneraile",17,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [460,460,"SHIP CONSTRUCTION","Cork County","Kearney's field Dunmanway",13,"*N/A","","","","","Q3-2020",""],
    [461,461,"SHIP CONSTRUCTION","Cork County","Carrig Rossa Phase 2, Rossmore",2,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [462,462,"SHIP CONSTRUCTION","Cork County","Chapel Lane, Ballydehob, Co. Cork",12,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [463,463,"SHIP CONSTRUCTION","Cork County","Sleaveen East, Macroom",16,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [464,464,"SHIP CONSTRUCTION","Cork County","Coastguard Cottages, Lower Roads, Crosshaven, Co. Cork",27,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [465,465,"CAS CONSTRUCTION TURNKEY","Cork County","Ardmanagh, Schull",12,"Tï¿½ath Housing Association Ltd","","","","","Q1-2021",""],
    [466,466,"CAS CONSTRUCTION","Cork County","Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay",18,"Cluid Housing Association","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [467,467,"CAS CONSTRUCTION","Cork County","Cuan Barra, Kilmore, Ballingeary",3,"Coiste Tithe Uibh Laoire Teoranta","","","","","","Q3-2018"],
    [468,468,"CAS CONSTRUCTION","Cork County","Caim Hill, Townlands, Rosscarbery",9,"Rosscarbery Housing Association Ltd","","","","","","Q1-2019"],
    [469,469,"CAS CONSTRUCTION","Cork County","Avenue House, Bandon",9,"Bandon Geriatric ? Community Council","","","","","","Q1-2018"],
    [470,470,"CAS CONSTRUCTION","Cork County","Church View, Love Lane, Charleville",4,"Charleville Care Project Ltd","","","","","","Q4-2019"],
    [471,471,"CAS CONSTRUCTION","Cork County","Fellowship House, Togher",31,"Tabor Lodge Addiction ? Housing Services Ltd","","","","","","Q2-2018"],
    [472,472,"CAS CONSTRUCTION","Cork County","Masseytown, Macroom",14,"Tï¿½ath Housing Association Ltd","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [473,473,"CAS CONSTRUCTION","Cork County","Baile Bhuire, Macroom",3,"*N/A","","","","","Q2-2020",""],
    [474,474,"CAS CONSTRUCTION","Cork County","Charleville, Church View, Love Lane, Charleville",9,"Charleville Care Project Ltd","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [475,475,"CAS CONSTRUCTION","Cork County","St. Michaels, 36 Main Street, Bandon, Co. Cork",6,"Bandon Geriatric ? Community Council","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [476,476,"CAS CONSTRUCTION","Cork County","Distillery Lane, Distillery Walk, Midleton",7,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [477,477,"CAS CONSTRUCTION","Cork County","Mardyke, Skibbereen",4,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [478,478,"CAS CONSTRUCTION","Cork County","Daniel Oï¿½Brien Terrace, Buttevant",7,"Tï¿½ath Housing Association Ltd","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [479,479,"CAS CONSTRUCTION","Cork County","Lisheen Field, Kilbarry Road, Dunmanway, Co. Cork",16,"Cluid Housing Association","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [480,480,"CALF Turnkey","Cork County","21 units, Brookhill, Carrigaline, Cork (Phase 1)",21,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [481,481,"CALF Turnkey","Cork County","3 units, Mullavale, Castletownroche, Co. Cork (Phase 1)",3,"Respond","","","","","","Q2-2019"],
    [482,482,"CALF Turnkey","Cork County","Beach Road, Passage West, Co. Cork (Phase 1)",3,"Clï¿½id Housing","","","","","","Q4-2017"],
    [483,483,"CALF Turnkey","Cork County","Brookhill (5 Units), Carrigaline, Cork (Phase 1)",5,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [484,484,"CALF Turnkey","Cork County","Brookhill, Carrigaline, Co. Cork (Phase 1)",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [485,485,"CALF Turnkey","Cork County","Brookhill, Carrigaline, Co. Cork (Phase 1)*",31,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2020"],
    [486,486,"CALF Turnkey","Cork County","Brookhill, Carrigaline, Co. Cork (Phase 2)",8,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [487,487,"CALF Turnkey","Cork County","Cascade Apartments, Castlelake, Carrigtwohill, Cork (Phase 1)",95,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2021",""],
    [488,488,"CALF Turnkey","Cork County","Castle Heights, Kilmoney, Carrigaline, Co Cork (Phase 1)",12,"Clï¿½id Housing","","","","","Q2-2021",""],
    [489,489,"CALF Turnkey","Cork County","Chapel Court, Skibbereen, Cork (Phase 1)",8,"Clï¿½id Housing","","","","","Q3-2021",""],
    [490,490,"CALF Turnkey","Cork County","Chapel Court, Skibbereen, Cork (Phase 2)",8,"Clï¿½id Housing","","","","","Q3-2021",""],
    [491,491,"CALF Turnkey","Cork County","Church Hill, Carrigaline, Co Cork (Phase 1)*",37,"Respond","","","","","Q3-2021",""],
    [492,492,"CALF Turnkey","Cork County","Cluain Reidh, Ballymakeera, Co. Cork (Phase 1)",10,"Clï¿½id Housing","","","","","","Q3-2020"],
    [493,493,"CALF Turnkey","Cork County","College Manor, Cobh (Phase 1)",10,"Tuath Housing Association","","","","","","Q4-2016"],
    [494,494,"CALF Turnkey","Cork County","Coolroe, Ballincollig, Co. Cork (Phase 1)*",24,"Respond","","","","","","Q4-2020"],
    [495,495,"CALF Turnkey","Cork County","Coolroe, Ballincollig, Co. Cork (Phase 2)",20,"Respond","","","","","","Q1-2021"],
    [496,496,"CALF Construction","Cork County","Duntahane, Fermoy, Co. Cork (Phase 1)",46,"Respond","","","","","","Q4-2020"],
    [497,497,"CALF Construction","Cork County","Firgrove Harrisons lane (Phase 1)",6,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2017"],
    [498,498,"CALF Turnkey","Cork County","Harbour Heights, Passage West, Co Cork (Phase 1)",14,"Clï¿½id Housing","","","","","Q4-2020",""],
    [499,499,"CALF Turnkey","Cork County","Harbour Heights, Passage West, Co Cork (Phase 2)",13,"Clï¿½id Housing","","","","","Q4-2020",""],
    [500,500,"CALF Turnkey","Cork County","Market Green, Knockgriffin, Midleton, Co. Cork (Phase 1)",20,"Respond","","","","","","Q4-2019"],
    [501,501,"CALF Turnkey","Cork County","Market Green, Knockgriffin, Midleton, Co. Cork (Phase 2)*",22,"Respond","","","","","","Q4-2020"],
    [502,502,"CALF Turnkey","Cork County","Mullavale, Castletownroche, Co. Cork (Phase 1)",6,"Respond","","","","","","Q4-2018"],
    [503,503,"CALF Construction","Cork County","Post Tender - Radharc An tSaile, Cappagh, Ballynacubby, Kinsale, Co Cork (Phase 1)",40,"Clï¿½id Housing","","","","","","Q3-2020"],
    [504,504,"CALF Turnkey","Cork County","Radharc Na Tuaithe, Knockraha, Cork (Phase 1)*",7,"Focus Housing Association CLG","","","","","Q3-2020",""],
    [505,505,"CALF Turnkey","Cork County","Sunville, Church Road, Carrigaline, Co. Cork (Phase 1)",6,"Focus Housing Association CLG","","","","","","Q4-2020"],
    [506,506,"CALF Turnkey","Cork County","Tanners Field, Bandon, Co Cork  (Phase 1)",11,"Tuath Housing Association","","","","","","Q3-2019"],
    [507,507,"CALF Turnkey","Cork County","The Miles, Clonakilty, Co Cork  (Phase 1)",38,"Clï¿½id Housing","","","","Q3-2021","",""],
    [508,508,"CALF Turnkey","Cork County","Ticknock, Cobh, Cork (Phase 1)",8,"Respond","","","","","","Q4-2018"],
    [509,509,"CALF Turnkey","Cork County","Togher Cross, Lehenaghmore, Co. Cork (Phase 1)",9,"Clï¿½id Housing","","","","","","Q4-2019"],
    [510,510,"CALF Turnkey","Cork County","Weston, Carrigaline, Co. Cork (Phase 1)",7,"Respond","","","","","","Q2-2018"],
    [511,511,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","The Miles, Clonakilty (Phase 1)",20,"*N/A","","","","","","Q2-2021"],
    [512,512,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","The Miles, Clonakilty (Phase 2)",32,"*N/A","","","","","Q4-2019",""],
    [513,513,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Poundhill, Skibbereen (Phase 1)",35,"*N/A","","","","","","Q2-2021"],
    [514,514,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Poundhill, Skibbereen (Phase 2)",15,"*N/A","","","","","Q4-2019",""],
    [515,515,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Oakwood, Macroom (Phase 1)",37,"*N/A","","","","","","Q2-2021"],
    [516,516,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Oakwood, Macroom (Phase 2)",13,"*N/A","","","","","","Q3-2021"],
    [517,517,"SHIP CONSTRUCTION TURNKEY","DLR","Hazelbrook, Nutgrove, Churchtown",28,"*N/A","","","","","","Q4-2017"],
    [518,518,"SHIP CONSTRUCTION TURNKEY","DLR","Dunedin Terrace, Monkstown",14,"*N/A","","","","","","Q4-2018"],
    [519,519,"SHIP CONSTRUCTION TURNKEY","DLR","Kilternan Close",22,"*N/A","","","","","","Q1-2021"],
    [520,520,"SHIP CONSTRUCTION TURNKEY","DLR","Kilternan Close",16,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [521,521,"SHIP CONSTRUCTION TURNKEY","DLR","George's Street Upper, Dun Laoghaire",5,"*N/A","","","","","","Q1-2021"],
    [522,522,"SHIP CONSTRUCTION TURNKEY","DLR","HazelBrook Square, Nutgrove, Churchtown",2,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [523,523,"SHIP CONSTRUCTION TURNKEY","DLR","Kilternan Close",17,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [524,524,"SHIP CONSTRUCTION RAPID","DLR","Rockville Green (Glenamuck Cottages)",13,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [525,525,"SHIP CONSTRUCTION RAPID","DLR","George's Place",12,"*N/A","","","","","","Q2-2018"],
    [526,526,"SHIP CONSTRUCTION RAPID","DLR","Ballyogan Square, Ballyogan",67,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [527,527,"SHIP CONSTRUCTION","DLR","Park House, 66 George's Street, Dun Laoghaire",4,"*N/A","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [528,528,"SHIP CONSTRUCTION","DLR","132 Pottery Road, Dun Laoghaire",4,"*N/A","","","","","","Q3-2018"],
    [529,529,"SHIP CONSTRUCTION","DLR","Temple Road",3,"*N/A","","","","","","Q2-2018"],
    [530,530,"SHIP CONSTRUCTION","DLR","Assistant Harbour Master House",2,"*N/A","","","","","","Q3-2017"],
    [531,531,"SHIP CONSTRUCTION","DLR","The Brambles Park Close Sallynoggin",10,"*N/A","","","","","","Q2-2018"],
    [532,532,"SHIP CONSTRUCTION","DLR","49 The Mews Sallynoggin Park",4,"*N/A","","","","","","Q4-2017"],
    [533,533,"SHIP CONSTRUCTION","DLR","Shanganagh Park Lodge",1,"*N/A","","","","","","Q2-2016"],
    [534,534,"SHIP CONSTRUCTION","DLR","Rosemount Court",44,"*N/A","","","","","","Q4-2018"],
    [535,535,"SHIP CONSTRUCTION","DLR","Broadford Rise",21,"*N/A","","","","","Q3-2017",""],
    [536,536,"SHIP CONSTRUCTION","DLR","Fitzgerald Park",33,"*N/A","","","","","","Q4-2018"],
    [537,537,"SHIP CONSTRUCTION","DLR","Rochestown House (Phase 3)",14,"*N/A","","","","","","Q3-2018"],
    [538,538,"SHIP CONSTRUCTION","DLR","St Michael's Terrace",4,"*N/A","","","","","","Q3-2017"],
    [539,539,"SHIP CONSTRUCTION","DLR","Clontibret House",4,"*N/A","","","","","","Q4-2016"],
    [540,540,"SHIP CONSTRUCTION","DLR","Cromlech Close",15,"*N/A","","","","","","Q3-2016"],
    [541,541,"SHIP CONSTRUCTION","DLR","Rochestown House (Phase 2)",34,"*N/A","","","","","","Q3-2016"],
    [542,542,"SHIP CONSTRUCTION","DLR","Ballyogan Avenue, Ballyogan",2,"*N/A","","","","","","Q2-2021"],
    [543,543,"SHIP CONSTRUCTION","DLR","St. Laurenceï¿½s Park, Stillorgan",89,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [544,544,"SHIP CONSTRUCTION","DLR","Fitzgerald Park",17,"*N/A","","","","","","Q1-2019"],
    [545,545,"SHIP CONSTRUCTION","DLR","Moyola Court, Churchtown Lower, Dublin 14",4,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [546,546,"SHIP CONSTRUCTION","DLR","Shanganagh Castle",200,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [547,547,"SHIP CONSTRUCTION","DLR","37A Rollins Villas, Sallynoggin, Co. Dublin ",1,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [548,548,"SHIP CONSTRUCTION","DLR","Old Coastguard Cottages, Coal Harbour, Harbour Road",4,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [549,549,"CAS CONSTRUCTION","DLR","30 Obelisk Walk, Blackrock",4,"St. John of God Housing Association Ltd","","","","","Q2-2021",""],
    [550,550,"CALF Construction","DLR","Abbeyview House, Monkstown, Dublin (Phase 1)",11,"Clï¿½id Housing","","","","","","Q4-2020"],
    [551,551,"CALF Turnkey","DLR","Ardilea Crescent, Ardilea, Clonskeagh, Dublin 14, Co. Dublin (Phase 1)*",2,"Tuath Housing Association","","","","","Q3-2019",""],
    [552,552,"CALF Turnkey","DLR","Ardilea Crescent, Clonskeagh, Dublin 14 (Phase 1)*",8,"Tuath Housing Association","","","","","","Q4-2018"],
    [553,553,"CALF Turnkey","DLR","Ballybetagh Road, Kilternan, Co Dublin (Phase 1)*",22,"Clanmil Housing Association Ireland","","","","","Q3-2021",""],
    [554,554,"CALF Turnkey","DLR","Belarmine Drive, Belarmine, Stepaside, Dublin 18 (Phase 1)*",6,"Clï¿½id Housing","","","","","","Q4-2019"],
    [555,555,"CALF Turnkey","DLR","Bishops Gate, Enniskerry Rd., Dublin 18 (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q4-2019"],
    [556,556,"CALF Turnkey","DLR","Bishops Gate, Kilternan, Dublin 18  (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q3-2018"],
    [557,557,"CALF Turnkey","DLR","Bishops Gate, Kilternan, Dublin 18  (Phase 2)*",2,"Clï¿½id Housing","","","","","","Q3-2018"],
    [558,558,"CALF Turnkey","DLR","Block C, Abbey Road, Monkstown, (Phase 1)*",3,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [559,559,"CALF Turnkey","DLR","Cherrywood Town Centre, Dublin 18 (Phase 1)*",80,"Clï¿½id Housing","","","","","Q4-2019",""],
    [560,560,"CALF Turnkey","DLR","Cherrywood Town Centre, Dublin 18 (Phase 2)*",61,"Clï¿½id Housing","","","","","Q4-2019",""],
    [561,561,"CALF Turnkey","DLR","Clay Farm (Block E3), Ballyogan Road, Leopardstown, Dublin 18 (Phase 1)*",24,"The Iveagh Trust","","","","","","Q4-2019"],
    [562,562,"CALF Turnkey","DLR","Clays Farm, Ballyogan Road (Phase 1)  (Phase 1)*",44,"The Iveagh Trust","","","","","","Q2-2019"],
    [563,563,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 18 (Phase 1)",9,"Respond","","","","","Q3-2019",""],
    [564,564,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 18 (Phase 2)",22,"Respond","","","","","Q3-2019",""],
    [565,565,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 18 (Phase 3)",22,"Respond","","","","","Q3-2019",""],
    [566,566,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 19, (Phase 1)",18,"Tuath Housing Association","","","","","Q3-2019",""],
    [567,567,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 19, (Phase 2)",16,"Tuath Housing Association","","","","","Q3-2019",""],
    [568,568,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 19, (Phase 3)",18,"Tuath Housing Association","","","","","Q3-2019",""],
    [569,569,"CALF Turnkey","DLR","Eustace Court, Upper Glenageary Road, Dun Laoghaire, Rathdown, Co. Dublin (Phase 1)",4,"St John of God Housing Association Ltd","","","","","","Q4-2019"],
    [570,570,"CALF Turnkey","DLR","Garrison Mews, The Ramparts, Cabinteely, Co. Dublin (Phase 1)*",5,"Focus Housing Association CLG","","","","","","Q4-2020"],
    [571,571,"CALF Turnkey","DLR","Greenbank House, Upper Glenageary Road, Dun Laoghaire, Co. Dublin (Phase 1)",1,"St John of God Housing Association Ltd","","","","","","Q4-2018"],
    [572,572,"CALF Turnkey","DLR","Hyde Road, Belmont, Stepaside, Co. Dublin (Phase 1)*",8,"Respond","","","","","","Q4-2018"],
    [573,573,"CALF Turnkey","DLR","Johnstown Court, Cabinteely, Dublin 18 (Phase 1)*",51,"Clï¿½id Housing","","","","","","Q2-2021"],
    [574,574,"CALF Turnkey","DLR","Johnstown Court, Cabinteely, Dublin 18 (Phase 2)*",50,"Clï¿½id Housing","","","","","Q2-2019",""],
    [575,575,"CALF Turnkey","DLR","Knockrabo, Mount Anville Road, Goatstown, Dublin 14 (Phase 1)*",6,"Oaklee Housing","","","","","","Q4-2020"],
    [576,576,"CALF Construction","DLR","Loughlinstown View(formerly Cromlech Fields) Loughlinstown, Ballybrack, Dublin (Phase 1)",34,"Co - Operative Housing Ireland Society Limited","","","","Q2-2021","",""],
    [577,577,"CALF Turnkey","DLR","Marine Walk, Marine Road, Dun Laoghaire (Phase 1)*",2,"Oaklee Housing","","","","","","Q4-2020"],
    [578,578,"CALF Turnkey","DLR","Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 1)*",14,"Tuath Housing Association","","","","","","Q1-2021"],
    [579,579,"CALF Turnkey","DLR","Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 2)*",18,"Tuath Housing Association","","","","","","Q2-2021"],
    [580,580,"CALF Turnkey","DLR","Our Ladys Grove, Goatstown, Dublin 14 (Phase 1)*",2,"Respond","","","","","","Q4-2018"],
    [581,581,"CALF Turnkey","DLR","Rockville Hall, Glenamuck Road, Dunlaoghaire, Dublin 18 (Phase 1)*",12,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [582,582,"CALF Turnkey","DLR","Stillorgan Gate, Kilmacud Road Upper, Co Dublin  (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q4-2017"],
    [583,583,"CALF Turnkey","DLR","Stillorgan Gate, Kilmacud Road Upper, Stillorgan, Co. Dublin (Phase 1)*",2,"Clï¿½id Housing","","","","","","Q4-2018"],
    [584,584,"CALF Turnkey","DLR","The Avenue, Glenside,  Carrickmines Green, Dublin 18 (Phase 1)*",5,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [585,585,"CALF Turnkey","DLR","The Glen, Glenamuck Road, Carrickmines, Dublin 18 (Phase 1)*",48,"Respond","","","","","Q1-2021",""],
    [586,586,"CALF Turnkey","DLR","Whinsfield, Sandyford Road, Dublin 18 (Phase 1)",59,"Respond","","","","","Q3-2020",""],
    [587,587,"CALF Turnkey","DLR","Whinsfield, Sandyford Road, Dublin 18 (Phase 1)*",6,"Respond","","","","","Q3-2020",""],
    [588,588,"CALF Turnkey","DLR","Woodbank, Dublin Rd, Shankill, Co Dublin  (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q3-2017"],
    [589,589,"SHIP DIALOG","Donegal","Drumrooske West",36,"*N/A","","","","","Q2-2021",""],
    [590,590,"SHIP DIALOG","Donegal","Convent Road, Carndonagh",21,"*N/A","","","","","Q1-2021",""],
    [591,591,"SHIP DIALOG","Donegal","Meadowfield, Convoy",12,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [592,592,"SHIP DIALOG","Donegal","Donegal Road, Ballybofey",14,"*N/A","","","","","Q1-2021",""],
    [593,593,"SHIP DIALOG","Donegal","Admiran, Stranorlar",52,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [594,594,"SHIP DIALOG","Donegal","Rockview, Carrickboy, Ballyshannon",5,"*N/A","","","","","Q1-2021",""],
    [595,595,"SHIP DIALOG","Donegal","Ardaravan, Buncrana",4,"*N/A","","","","","Q4-2020",""],
    [596,596,"SHIP DIALOG","Donegal","Glencrow, Moville",35,"*N/A","","","","","Q2-2021",""],
    [597,597,"SHIP DIALOG","Donegal","Ballyraine, Letterkenny",25,"*N/A","","","","","Q3-2021",""],
    [598,598,"SHIP DIALOG","Donegal","Lough Fern Heights, Milford",17,"*N/A","","","","","Q1-2021",""],
    [599,599,"SHIP DIALOG","Donegal","Convent Road, Carndonagh",18,"N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [600,600,"SHIP DIALOG","Donegal","Convent Road, Carndonagh",14,"N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [601,601,"SHIP DIALOG","Donegal","Meadowfield, Convoy",12,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [602,602,"SHIP CONSTRUCTION TURNKEY","Donegal","Gleann Na Greine, Mullindrait, Stranorlar",21,"*N/A","","","","","","Q2-2018"],
    [603,603,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny",18,"*N/A","","","","","","Q4-2018"],
    [604,604,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny",8,"*N/A","","","","","","Q1-2019"],
    [605,605,"SHIP CONSTRUCTION TURNKEY","Donegal","Carnamuggagh, Letterkenny",30,"*N/A","","","","","","Q4-2020"],
    [606,606,"SHIP CONSTRUCTION TURNKEY","Donegal","Heathhill, Newtowncunningham",10,"*N/A","","","","","","Q4-2019"],
    [607,607,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny",10,"*N/A","","","","","","Q2-2019"],
    [608,608,"SHIP CONSTRUCTION TURNKEY","Donegal","Hattersly Park, Carndonagh",21,"*N/A","","","","","Q3-2021",""],
    [609,609,"SHIP CONSTRUCTION TURNKEY","Donegal","Brookfield, Donegal Town",8,"*N/A","","","","","Q4-2020",""],
    [610,610,"SHIP CONSTRUCTION TURNKEY","Donegal","Stï¿½isiï¿½n an Chï¿½irt, Falcarragh",6,"*N/A","","","","","","Q4-2019"],
    [611,611,"SHIP CONSTRUCTION TURNKEY","Donegal","Stï¿½isiï¿½n an Chï¿½irt, Falcarragh",6,"*N/A","","","","","","Q4-2020"],
    [612,612,"SHIP CONSTRUCTION TURNKEY","Donegal","Heathhill, Newtowncunningham",7,"*N/A","","","","","","Q3-2020"],
    [613,613,"SHIP CONSTRUCTION TURNKEY","Donegal","Brookfield, Donegal Town",12,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [614,614,"SHIP CONSTRUCTION TURNKEY","Donegal","Brookfield, Donegal Town",14,"*N/A","","","","","Q4-2020",""],
    [615,615,"SHIP CONSTRUCTION SINGLE STAGE","Donegal","Figart, Dunfanaghy",8,"*N/A","","","","","","Q4-2019"],
    [616,616,"SHIP CONSTRUCTION SINGLE STAGE","Donegal","SRD Loughanure Annagry",1,"*N/A","","","","","Q1-2021",""],
    [617,617,"SHIP CONSTRUCTION SINGLE STAGE","Donegal","SRD Meenderrynasloe, Annagry",1,"*N/A","","","","","Q1-2021",""],
    [618,618,"SHIP CONSTRUCTION SINGLE STAGE","Donegal","Knockamany Malin",1,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [619,619,"SHIP CONSTRUCTION","Donegal","Meadow Hill, Raphoe",11,"*N/A","","","","","Q3-2020",""],
    [620,620,"SHIP CONSTRUCTION","Donegal","Radharc na Tra Breige, Malin (Phase 3)",8,"*N/A","","","","","","Q4-2019"],
    [621,621,"SHIP CONSTRUCTION","Donegal","Cois Abhainn, St Johnston (Phase 2)",6,"*N/A","","","","","","Q4-2020"],
    [622,622,"SHIP CONSTRUCTION","Donegal","Emerald Drive, Killybegs (Phase 6)",9,"*N/A","","","","","","Q4-2019"],
    [623,623,"SHIP CONSTRUCTION","Donegal","Long Lane, Letterkenny",29,"*N/A","","","","","","Q2-2021"],
    [624,624,"SHIP CONSTRUCTION","Donegal","Rockytown, Buncrana (Phase 1)",21,"*N/A","","","","","Q4-2019",""],
    [625,625,"SHIP CONSTRUCTION","Donegal","Manorcunningham (Phase 2)",8,"*N/A","","","","","","Q4-2018"],
    [626,626,"SHIP CONSTRUCTION","Donegal","Abbots Wood, Carndonagh (Ph 2)",4,"*N/A","","","","","","Q4-2018"],
    [627,627,"SHIP CONSTRUCTION","Donegal","Pound Street, Dunfanaghy",4,"*N/A","","","","","Q3-2020",""],
    [628,628,"SHIP CONSTRUCTION","Donegal","Ardara (Phase 3)",8,"*N/A","","","","","","Q2-2017"],
    [629,629,"SHIP CONSTRUCTION","Donegal","Newtoncunningham",7,"*N/A","","","","","","Q4-2018"],
    [630,630,"SHIP CONSTRUCTION","Donegal","Railway Park, Drumrooske, Donegal Town",24,"*N/A","","","","","","Q2-2021"],
    [631,631,"SHIP CONSTRUCTION","Donegal","Ard Connell, Ardara (SRD)",1,"*N/A","","","","","","Q1-2017"],
    [632,632,"SHIP CONSTRUCTION","Donegal","Manorcunningham (Phase 1)",2,"*N/A","","","","","","Q2-2017"],
    [633,633,"SHIP CONSTRUCTION","Donegal","Railway Park, Drumrooske, Donegal Town",24,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [634,634,"SHIP CONSTRUCTION","Donegal","Trusk Road, Ballybofey",19,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [635,635,"SHIP CONSTRUCTION","Donegal","Crana Crescent, Buncrana",16,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [636,636,"SHIP CONSTRUCTION","Donegal","Drumacrin, Bundoran",42,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [637,637,"SHIP CONSTRUCTION","Donegal","Gallow's Lane, Lifford",29,"*N/A","","Stage 2 approved Q1-2020, full design/tender being prepared.","","","",""],
    [638,638,"SHIP CONSTRUCTION","Donegal","Chapel Road, Dungloe",45,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [639,639,"SHIP CONSTRUCTION","Donegal","Kilmacrennan, Letterkenny",34,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [640,640,"CAS CONSTRUCTION TURNKEY","Donegal","Ballaghderg, Letterkenny",14,"Respond","","","","","","Q4-2020"],
    [641,641,"CAS CONSTRUCTION","Donegal","Glenrowan House, Drumkeen, Stranorlar",5,"Apex Housing Association","","","","","Q4-2020",""],
    [642,642,"CAS CONSTRUCTION","Donegal","Cois Locha, Meenmore, Dungloe",15,"County Donegal Parents and Friends Housing Association Ltd","","","","","Q3-2020",""],
    [643,643,"CAS CONSTRUCTION","Donegal","Railway Park, Drumrooske, Donegal Town",10,"Oaklee Housing Trust","","","","","","Q4-2020"],
    [644,644,"CAS CONSTRUCTION","Donegal","Dunshenny House, Derry Road, Carndonagh",5,"Apex Housing Association","","","","","","Q2-2018"],
    [645,645,"CAS CONSTRUCTION","Donegal","Raphoe Road, Castlefinn",34,"Habinteg Housing Association (Ireland) Ltd","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [646,646,"CALF Turnkey","Donegal","Ballaghderg, Letterkenny, Co Donegal  (Phase 1)*",33,"Respond","","","","","","Q1-2021"],
    [647,647,"CALF Turnkey","Donegal","Forge Road, Donegal (Phase 1)",4,"Clï¿½id Housing","","","","","","Q3-2016"],
    [648,648,"CALF Construction","Donegal","Post Tender - Ernedale Ballyshannon (Phase 1)",11,"Clï¿½id Housing","","","","","","Q4-2018"],
    [649,649,"SHIP CONSTRUCTION TURNKEY","Dublin City","Prospect Hill",58,"*N/A","","","","","","Q4-2017"],
    [650,650,"SHIP CONSTRUCTION TURNKEY","Dublin City","Parkside, Balgriffin, Dublin 13",16,"*N/A","","","","","","Q4-2018"],
    [651,651,"SHIP CONSTRUCTION TURNKEY","Dublin City","Hampton Wood, Finglas",47,"*N/A","","","","","","Q4-2018"],
    [652,652,"SHIP CONSTRUCTION TURNKEY","Dublin City","Hampton Wood, Finglas",45,"*N/A","","","","","","Q4-2019"],
    [653,653,"SHIP CONSTRUCTION TURNKEY","Dublin City","88-89 Drimnagh Road Dublin 12",24,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [654,654,"SHIP CONSTRUCTION TURNKEY","Dublin City","St. Pancras, Harolds Cross, Dublin 6",4,"*N/A","","","","","","Q2-2021"],
    [655,655,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Belcamp B, Dublin 17",12,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [656,656,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Bunratty Road",78,"*N/A","","","","","Q4-2019",""],
    [657,657,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Bonham Street Dublin  8",57,"*N/A","","","","","Q4-2019",""],
    [658,658,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Cork Street/Chamber Street Dublin 8",55,"*N/A","","","","","Q1-2020",""],
    [659,659,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Springvale Chapelizod Dublin 8",71,"*N/A","","","","","Q1-2020",""],
    [660,660,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Cromcastle & Woodville, Coolock, Dublin 5",156,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [661,661,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","Crumlin Road - Rafters Lane, Dublin 12",47,"*N/A","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [662,662,"SHIP CONSTRUCTION RAPID VOLUMETRIC","Dublin City","St. Andrews Court, Dublin 2",37,"*N/A","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [663,663,"SHIP CONSTRUCTION RAPID","Dublin City","Belcamp H, Dublin 17",38,"*N/A","","","","","","Q4-2017"],
    [664,664,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot",24,"*N/A","","","","","","Q4-2017"],
    [665,665,"SHIP CONSTRUCTION RAPID","Dublin City","Mourne Road, Drimnagh",29,"*N/A","","","","","","Q4-2017"],
    [666,666,"SHIP CONSTRUCTION RAPID","Dublin City","St Helena's Drive, Finglas",39,"*N/A","","","","","","Q3-2017"],
    [667,667,"SHIP CONSTRUCTION RAPID","Dublin City","Poppintree, Ballymun",22,"*N/A","","","","","","Q2-2016"],
    [668,668,"SHIP CONSTRUCTION RAPID","Dublin City","Rapids at Ballyfermot, Rathvilly, Woodbank Drive",53,"*N/A","","","","","","Q4-2018"],
    [669,669,"SHIP CONSTRUCTION RAPID","Dublin City","Rapids at Ballyfermot, Rathvilly, Woodbank Drive",13,"*N/A","","","","","","Q3-2018"],
    [670,670,"SHIP CONSTRUCTION RAPID","Dublin City","Rapids at Ballyfermot, Rathvilly, Woodbank Drive",3,"*N/A","","","","","","Q3-2018"],
    [671,671,"SHIP CONSTRUCTION RAPID","Dublin City","Rapids at Ballyfermot, Rathvilly, Woodbank Drive",19,"*N/A","","","","","","Q4-2019"],
    [672,672,"SHIP CONSTRUCTION","Dublin City","Hampton Wood",25,"*N/A","","","","","","Q4-2016"],
    [673,673,"SHIP CONSTRUCTION","Dublin City","Cornamona, Ballyfermot, Dublin 12",61,"*N/A","","","","","Q2-2019",""],
    [674,674,"SHIP CONSTRUCTION","Dublin City","Infirmary Road, Dublin 7",38,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [675,675,"SHIP CONSTRUCTION","Dublin City","North King Street, - Sean Foster Place, Dublin 7",30,"*N/A","","","","","Q2-2019",""],
    [676,676,"SHIP CONSTRUCTION","Dublin City","Ballybough Road, Dublin 1",5,"*N/A","","","","","","Q4-2018"],
    [677,677,"SHIP CONSTRUCTION","Dublin City","St. Finbar's Court, Kilkieran Road, Dublin 7",46,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [678,678,"SHIP CONSTRUCTION","Dublin City","Dominick Street (East side)",72,"*N/A","","","","","Q1-2018",""],
    [679,679,"SHIP CONSTRUCTION","Dublin City","Sackville Avenue Cottages",14,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [680,680,"SHIP CONSTRUCTION","Dublin City","O'Devaney Gardens - Phase 1A",56,"*N/A","","","","","Q3-2018",""],
    [681,681,"SHIP CONSTRUCTION","Dublin City","Priory Hall",9,"*N/A","","","","","","Q1-2017"],
    [682,682,"SHIP CONSTRUCTION","Dublin City","Priory Hall",24,"*N/A","","","","","","Q4-2019"],
    [683,683,"SHIP CONSTRUCTION","Dublin City","Ballybough Road, Dublin 1",2,"*N/A","","","","","","Q4-2019"],
    [684,684,"SHIP CONSTRUCTION","Dublin City","Glin Court, Coolock, Dublin 17",32,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [685,685,"SHIP CONSTRUCTION","Dublin City","Kildonan Road",75,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [686,686,"SHIP CONSTRUCTION","Dublin City","Lands at Emmet Road",109,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [687,687,"SHIP CONSTRUCTION","Dublin City","Slademore Avenue, Ayrfield, Dublin 13",39,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [688,688,"SHIP CONSTRUCTION","Dublin City","Bluebell Phase 1A",140,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [689,689,"SHIP CONSTRUCTION","Dublin City","Liberties Cluster Phase 1, School Street, The Liberties, Dublin 8",115,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [690,690,"SHIP CONSTRUCTION","Dublin City","St. Anne's Court, All Saints Drive, Raheny, Dublin 5",102,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [691,691,"REGENERATION","Dublin City","St Teresa's Gardens Margaret Kennedy Road Project",54,"*N/A","","","","","","Q4-2020"],
    [692,692,"REGENERATION","Dublin City","Dolphin House, Dublin 8",100,"*N/A","","","","","","Q3-2018"],
    [693,693,"REGENERATION","Dublin City","Charlemont",79,"*N/A","","","","","","Q4-2017"],
    [694,694,"REGENERATION","Dublin City","Maxwell Road",9,"*N/A","","","","","","Q2-2016"],
    [695,695,"REGENERATION","Dublin City","Buttercup, Darndale",19,"*N/A","","","","","","Q4-2017"],
    [696,696,"REGENERATION","Dublin City","Buttercup, Darndale",9,"*N/A","","","","","","Q1-2018"],
    [697,697,"REGENERATION","Dublin City","Buttercup, Darndale",7,"*N/A","","","","","","Q2-2018"],
    [698,698,"REGENERATION","Dublin City","St. Bricins Park",11,"*N/A","","","","","","Q4-2018"],
    [699,699,"REGENERATION","Dublin City","Dorset Street, Dublin 7",97,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [700,700,"REGENERATION","Dublin City","Matt Talbot Court",92,"*N/A","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [701,701,"REGENERATION","Dublin City","Constitution Hill Dublin 7",130,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [702,702,"REGENERATION","Dublin City","Pearse House, Sandwith Street Lower, Dublin 2 (Blocks L,M,N &P)",75,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [703,703,"CAS CONSTRUCTION TURNKEY","Dublin City","Block 70, The Plaza, Parkwest, Dublin 12 ",43,"Tï¿½ath Housing Association Ltd","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [704,704,"CAS CONSTRUCTION TURNKEY","Dublin City","Apartments 1-3, 42 North Strand Road, Dublin 3",3,"Peter McVerry Trust Ltd","","","","","","Q4-2020"],
    [705,705,"CAS CONSTRUCTION TURNKEY","Dublin City","5A & 5B Willow Park Crescent",2,"Tï¿½ath Housing Association Ltd","","","","","","Q3-2020"],
    [706,706,"CAS CONSTRUCTION SINGLE STAGE","Dublin City","61 & 63 Rathoath Avenue, Finglas, Dublin 11",6,"Arlington Novas Ireland Ltd","","","","","Q4-2020",""],
    [707,707,"CAS CONSTRUCTION SINGLE STAGE","Dublin City","13A Casement Drive / 307A Casement Road, Finglas, Dublin 11",4,"Arlington Novas Ireland Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [708,708,"CAS CONSTRUCTION SINGLE STAGE","Dublin City","88 Lower Drumcondra Road, Dublin 9 ",6,"Peter McVerry Trust Ltd","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [709,709,"CAS CONSTRUCTION","Dublin City","Beech Hill",19,"Royal Hospital Donnybrook Voluntary Housing Association Ltd","","","","","","Q4-2018"],
    [710,710,"CAS CONSTRUCTION","Dublin City","Ellis Court, Dublin",22,"Tï¿½ath Housing Association Ltd","","","","","Q3-2019",""],
    [711,711,"CAS CONSTRUCTION","Dublin City","Martanna House, High Park, Grace Park Road,Dublin 9",8,"Respond","","","","","","Q4-2018"],
    [712,712,"CAS CONSTRUCTION","Dublin City","1 - 2 Rafter's Lane, Dublin 12",11,"Walkinston Housing Association Ltd (WALK)","","","","","","Q4-2019"],
    [713,713,"CAS CONSTRUCTION","Dublin City","180-187 Townsend Street, Dublin 2",18,"Peter McVerry Trust Ltd","","","Stage 3 approved Q4-2018, the scheme is now approved to proceed to tender.","","",""],
    [714,714,"CAS CONSTRUCTION","Dublin City","26 New Street South, Dublin 8",8,"Peter McVerry Trust Ltd","","","","","","Q1-2021"],
    [715,715,"CAS CONSTRUCTION","Dublin City","Broome Lodge, Dunmanus, Dublin 7",10,"Cluid Housing Association","","","","","","Q4-2017"],
    [716,716,"CAS CONSTRUCTION","Dublin City","St Agatha's Court, North William Street, Dublin 1",11,"Peter McVerry Trust Ltd","","","","","","Q2-2017"],
    [717,717,"CAS CONSTRUCTION","Dublin City","55B Arbour Hill, Dublin 7",14,"Simon Community : Dublin Simon","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [718,718,"CAS CONSTRUCTION","Dublin City","St. Michael's Estate, Inchicore, Dublin 8 - Housing Pilot Project ",52,"Circle Voluntary Housing Association Ltd","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [719,719,"CAS CONSTRUCTION","Dublin City","Shaw Street, Dublin 2",12,"Peter McVerry Trust Ltd","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [720,720,"CAS CONSTRUCTION","Dublin City","Sarsfield Road, Ballyfermot, Dublin 10",6,"Respond","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [721,721,"CAS CONSTRUCTION","Dublin City","25-26 Ushers Island Ushers Quay Dublin 8",0,"Simon Community : Dublin Simon","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [722,722,"CAS CONSTRUCTION","Dublin City","53a Keeper Road, Drimnagh, Dublin 12",9,"Respond","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [723,723,"CALF Construction","Dublin City","3 units, Block A Jamestown Court, Dublin 8 (Phase 1)",3,"ALONE","","","","","","Q4-2020"],
    [724,724,"CALF Turnkey","Dublin City","9 units Dorset Street, Dublin 1 (Phase 1)",9,"Clanmil Housing Association Ireland","","","","","","Q4-2020"],
    [725,725,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 1)",14,"Tuath Housing Association","","","","","","Q4-2016"],
    [726,726,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 2)",21,"Tuath Housing Association","","","","","","Q1-2017"],
    [727,727,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 3)",10,"Tuath Housing Association","","","","","","Q2-2017"],
    [728,728,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 4)",3,"Tuath Housing Association","","","","","","Q3-2017"],
    [729,729,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 5)",1,"Tuath Housing Association","","","","","","Q4-2018"],
    [730,730,"CALF Construction","Dublin City","Annamore Court, Ballyfermot (Phase 1)",70,"The Iveagh Trust","","","","","","Q2-2017"],
    [731,731,"CALF Turnkey","Dublin City","Aughrim Street, Stoneybatter, Dublin 7 (Phase 1)",4,"Clanmil Housing Association Ireland","","","","","","Q2-2021"],
    [732,732,"CALF Turnkey","Dublin City","Balfe Road, Crumlin, Dublin 12 (Phase 1)*",16,"Respond","","","","","","Q4-2018"],
    [733,733,"CALF Construction","Dublin City","Ballygall Road East Phase 2 (Phase 1)",11,"Fold Housing Association Ireland Ltd","","","","","","Q1-2016"],
    [734,734,"CALF Construction","Dublin City","Bethany House, Gilford Road, Sandymount, Dublin 4 (Phase 1)",62,"Clï¿½id Housing","","","","Q2-2021","",""],
    [735,735,"CALF Turnkey","Dublin City","Blackbanks View, 754 Howth Road, Raheny, Dublin 5 (Phase 1)*",40,"Clï¿½id Housing","","","","","","Q1-2021"],
    [736,736,"CALF Turnkey","Dublin City","Block A Northbank, Castleforbes, Dublin 1  (Phase 1)*",26,"Tuath Housing Association","","","","","","Q2-2018"],
    [737,737,"CALF Construction","Dublin City","Block A, Jamestown Court, Dublin 8 (Phase 1)",9,"ALONE","","","","","","Q4-2020"],
    [738,738,"CALF Turnkey","Dublin City","Bluebell Avenue, Bluebell, Dublin 12 (Phase 1)*",52,"Respond","","","","","Q4-2019",""],
    [739,739,"CALF Turnkey","Dublin City","Bluebell Avenue, Dublin 12 (Phase 1)",7,"Tuath Housing Association","","","","","","Q4-2018"],
    [740,740,"CALF Construction","Dublin City","Broome Lodge,\\nDunmanus Court, Cabra (Phase 1)",33,"Clï¿½id Housing","","","","","","Q4-2017"],
    [741,741,"CALF Turnkey","Dublin City","Camac Park, Bluebell, Dublin 12 (Phase 1)",5,"Tuath Housing Association","","","","","","Q2-2020"],
    [742,742,"CALF Turnkey","Dublin City","Camac Park, Bluebell, Dublin 12 (Phase 1)",3,"Tuath Housing Association","","","","","Q1-2021",""],
    [743,743,"CALF Turnkey","Dublin City","Canal Meadows, Bluebell, Dublin 12 (Phase 1)",4,"Tuath Housing Association","","","","","","Q1-2019"],
    [744,744,"CALF Turnkey","Dublin City","Chanel College, Coolock Village, Malahide Road, Dublin 5  (Phase 1)*",16,"Respond","","","","","","Q4-2017"],
    [745,745,"CALF Turnkey","Dublin City","Chanel Manor Apartments, Coolock, Dublin 5. (Phase 1)*",65,"Respond","","","","","Q2-2019",""],
    [746,746,"CALF Turnkey","Dublin City","Chanel Manor, Coolock, Dublin 5 (Phase 1)*",22,"Respond","","","","","Q4-2020",""],
    [747,747,"CALF Turnkey","Dublin City","Clongriffin, Dublin 13 (Phase 1)*",84,"The Iveagh Trust","","","","","","Q2-2019"],
    [748,748,"CALF Turnkey","Dublin City","Connaught Street, Phibsborough, Dublin 7 (Phase 1)",20,"Focus Housing Association CLG","","","","","Q2-2021",""],
    [749,749,"CALF Turnkey","Dublin City","Cromwellsfort Court, Cromwellsfort Road, Walkinstown, Dublin 12 (Phase 1)*",12,"Oaklee Housing","","","","","","Q3-2020"],
    [750,750,"CALF Turnkey","Dublin City","Crumlin Village, Dublin 12 (Phase 1)",3,"Clï¿½id Housing","","","","","","Q2-2017"],
    [751,751,"CALF Turnkey","Dublin City","Crumlin Village, Dublin 12 (Phase 2)",2,"Clï¿½id Housing","","","","","","Q3-2017"],
    [752,752,"CALF Construction","Dublin City","Dolphin Park, Rialto, Dublin 8 (Phase 1)",43,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [753,753,"CALF Turnkey","Dublin City","Donnybrook Gardens, Lands of Greenfield Park, Donnybrook, Dublin 4 (Phase 1)*",4,"RHD Housing","","","","","","Q2-2021"],
    [754,754,"CALF Turnkey","Dublin City","Elanora Court, Long Mile Road, Walkinstown, Dublin 12 (Phase 1)*",153,"Respond","","","","","Q3-2020",""],
    [755,755,"CALF Construction","Dublin City","Harolds Cross, Dublin 6 (Phase 1)",28,"Focus Housing Association CLG","","","","","","Q4-2016"],
    [756,756,"CALF Turnkey","Dublin City","Lough Conn Road, Ballyfermot, Dublin 10 (Phase 1)",1,"Tuath Housing Association","","","","","","Q4-2019"],
    [757,757,"CALF Turnkey","Dublin City","Lough Conn Road, Ballyfermot, Dublin 10 (Phase 2)",4,"Tuath Housing Association","","","","","","Q4-2020"],
    [758,758,"CALF Turnkey","Dublin City","Merville Court, Merville Avenue, Fairview (Phase 1)",5,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2017"],
    [759,759,"CALF Turnkey","Dublin City","Millrose House, Bluebell Avenue, Dublin 12 (Phase 1)",8,"Clï¿½id Housing","","","","","","Q4-2017"],
    [760,760,"CALF Turnkey","Dublin City","Mountjoy Square North, Dublin 1 (Phase 1)",31,"Respond","","","","","","Q4-2019"],
    [761,761,"CALF Turnkey","Dublin City","Newtown Cottages Malahide Road Coolock Dublin 17 (Phase 1)",3,"Clanmil Housing Association Ireland","","","","","Q3-2020",""],
    [762,762,"CALF Construction","Dublin City","North King Street, Dublin 7  (Phase 1)",30,"Co - Operative Housing Ireland Society Limited","","","","","Q4-2019",""],
    [763,763,"CALF Turnkey","Dublin City","Old School House Lane, Magenta Crescent, Santry, Dublin 9 (Phase 1)",8,"Tuath Housing Association","","","","","","Q4-2019"],
    [764,764,"CALF Construction","Dublin City","Orchard Lawns, Ballyfermot (Phase 1)",36,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2018"],
    [765,765,"CALF Construction","Dublin City","Orchard Lawns, Ballyfermot (Phase 2)",36,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [766,766,"CALF Turnkey","Dublin City","Park West Campus, Kileen Road, Dublin 12 (Phase 1)",41,"Tuath Housing Association","","","","","Q4-2020",""],
    [767,767,"CALF Construction","Dublin City","Post Tender - Wad River Close Phase 2, Ballymun, Dublin 9  (Phase 1)",9,"Clï¿½id Housing","","","","","","Q4-2019"],
    [768,768,"CALF Construction","Dublin City","Post Tender Johns Lane West Dublin 8 (Phase 1)",31,"Focus Housing Association CLG","","","","","","Q4-2018"],
    [769,769,"CALF Construction","Dublin City","POST TENDER, Poplar Row, Ballybough, Dublin 3 (Phase 1)",29,"Oaklee Housing","","","","","","Q4-2019"],
    [770,770,"CALF Turnkey","Dublin City","Ravensdale Court, Kimmage, Dublin 12. (Phase 1)",12,"Tuath Housing Association","","","","","Q4-2020",""],
    [771,771,"CALF Construction","Dublin City","Revised - Dominic Place, Dublin (Phase 1)",9,"The Paddy McGrath Housing Project","","","","","","Q3-2020"],
    [772,772,"CALF Construction","Dublin City","Revised Post Tender - Raleigh Square, Crumlin (Phase 1)",33,"Tuath Housing Association","","","","","","Q4-2019"],
    [773,773,"CALF Construction","Dublin City","Revised, St Maryï¿½s Mansions, Dublin 1 (Phase 1)",80,"Clï¿½id Housing","","","","","","Q4-2019"],
    [774,774,"CALF Construction","Dublin City","Richmond Road, Dublin 9 (Phase 1)",40,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [775,775,"CALF Turnkey","Dublin City","Royal Canal Crescent, Rathborne Park, Rathborne, Dublin15 (Phase 1)*",16,"Clï¿½id Housing","","","","","","Q4-2020"],
    [776,776,"CALF Turnkey","Dublin City","Royal Canal Park, Ashtown, Dublin 15 (Phase 1)*",46,"Respond","","","","","","Q4-2020"],
    [777,777,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)",44,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [778,778,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)",6,"Fold Housing Association Ireland Ltd","","","","","","Q4-2020"],
    [779,779,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 2)",42,"Fold Housing Association Ireland Ltd","","","","","","Q2-2020"],
    [780,780,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 3)",11,"Fold Housing Association Ireland Ltd","","","","","","Q4-2020"],
    [781,781,"CALF Turnkey","Dublin City","St Caniceï¿½s Hall, Ballygall Road West, Finglas, Dublin 11 (Phase 1)*",32,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [782,782,"CALF Turnkey","Dublin City","Stormanstown Hall, Ballymun Road, (revised) (Phase 1)",42,"Oaklee Housing","","","","","","Q3-2018"],
    [783,783,"CALF Turnkey","Dublin City","Sundrive Mews, Kimmage, Dublin 12 (Phase 1)",9,"Clï¿½id Housing","","","","","","Q4-2019"],
    [784,784,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 1)",28,"Tuath Housing Association","","","","","","Q2-2016"],
    [785,785,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 2)",18,"Tuath Housing Association","","","","","","Q4-2016"],
    [786,786,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 3)",14,"Tuath Housing Association","","","","","","Q1-2017"],
    [787,787,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 4)",8,"Tuath Housing Association","","","","","","Q1-2017"],
    [788,788,"CALF Turnkey","Dublin City","Tonlegee Road, Dublin 5  (Phase 1)",47,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [789,789,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Dublin City","Ayrfield, Malahide Road",150,"*N/A","","","","","","Q2-2021"],
    [790,790,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Dublin City","Scribblestown",70,"*N/A","","","","","","Q4-2020"],
    [791,791,"SHIP CONSTRUCTION TURNKEY","Fingal","Blackmills Grove, Blakestown Road, Mulhuddard",10,"*N/A","","","","","","Q2-2017"],
    [792,792,"SHIP CONSTRUCTION TURNKEY","Fingal","Balgriffin Grove, Malahide Road, Balgriffin",6,"*N/A","","","","","","Q1-2017"],
    [793,793,"SHIP CONSTRUCTION TURNKEY","Fingal","Hansfield, Ongar, Dublin 15",36,"*N/A","","","","","","Q3-2017"],
    [794,794,"SHIP CONSTRUCTION TURNKEY","Fingal","Hansfield, Ongar, Dublin 15",16,"*N/A","","","","","","Q1-2018"],
    [795,795,"SHIP CONSTRUCTION TURNKEY","Fingal","Hansfield, Ongar, Dublin 15",16,"*N/A","","","","","","Q2-2018"],
    [796,796,"SHIP CONSTRUCTION TURNKEY","Fingal","Ravenswood, North Road, Finglas",2,"Peter McVerry Trust Ltd","","","","","","Q4-2018"],
    [797,797,"SHIP CONSTRUCTION TURNKEY","Fingal","Boroimhe, Swords",6,"*N/A","","","","","","Q3-2018"],
    [798,798,"SHIP CONSTRUCTION TURNKEY","Fingal","Cnoc Dubh, Ballyboughal",6,"*N/A","","","","","","Q4-2018"],
    [799,799,"SHIP CONSTRUCTION TURNKEY","Fingal","Kenure Gate, Park Road, Rush",4,"*N/A","","","","","","Q4-2018"],
    [800,800,"SHIP CONSTRUCTION TURNKEY","Fingal","Glaslinn, Donabate",3,"*N/A","","","","","","Q4-2018"],
    [801,801,"SHIP CONSTRUCTION TURNKEY","Fingal","Bremore Pastures Park, Balbriggan",4,"*N/A","","","","","","Q4-2018"],
    [802,802,"SHIP CONSTRUCTION TURNKEY","Fingal","Northwood Green, Santry, Dublin 9",37,"*N/A","","","","","","Q4-2018"],
    [803,803,"SHIP CONSTRUCTION TURNKEY","Fingal","Hollytown Cottages",4,"*N/A","","","","","","Q4-2019"],
    [804,804,"SHIP CONSTRUCTION TURNKEY","Fingal","Cnoc Dubh Ballyboughal Co. Dublin",5,"*N/A","","","","","","Q3-2019"],
    [805,805,"SHIP CONSTRUCTION TURNKEY","Fingal","Rahillion, Donabate",1,"*N/A","","","","","","Q4-2019"],
    [806,806,"SHIP CONSTRUCTION TURNKEY","Fingal","Bay Meadows Avenue/Square, Hollystown Dublin 15",12,"*N/A","","","","","","Q4-2020"],
    [807,807,"SHIP CONSTRUCTION TURNKEY","Fingal","Bay Meadows, Hollystown, Dublin 15",10,"*N/A","","","","","","Q3-2020"],
    [808,808,"SHIP CONSTRUCTION TURNKEY","Fingal","Killhedge Lane, Dun Emer, Lusk",7,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [809,809,"SHIP CONSTRUCTION SINGLE STAGE","Fingal","Outlands, Rathbeale Road, Swords",11,"*N/A","","","","","Q3-2021",""],
    [810,810,"SHIP CONSTRUCTION RAPID","Fingal","Avondale, Mulhuddart, Dublin 15",42,"*N/A","","","","","","Q4-2019"],
    [811,811,"SHIP CONSTRUCTION RAPID","Fingal","Pinewood, Balbriggan",20,"*N/A","","","","","","Q2-2018"],
    [812,812,"SHIP CONSTRUCTION RAPID","Fingal","Wellview, Mulhuddart",20,"*N/A","","","","","","Q4-2017"],
    [813,813,"SHIP CONSTRUCTION RAPID","Fingal","Church Road, Mulhuddart, Dublin 15",22,"*N/A","","","","","","Q4-2019"],
    [814,814,"SHIP CONSTRUCTION RAPID","Fingal","Church Fields, Phase 2B, Mulhuddart, Dublin 15.",67,"*N/A","","","","","Q1-2021",""],
    [815,815,"SHIP CONSTRUCTION","Fingal","Rivermeade, St. Margarets",2,"*N/A","","","","","","Q2-2019"],
    [816,816,"SHIP CONSTRUCTION","Fingal","Rowlestown",10,"*N/A","","","","","","Q2-2019"],
    [817,817,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",5,"*N/A","","","","","","Q2-2018"],
    [818,818,"SHIP CONSTRUCTION","Fingal","Castlelands, Park View, Balbriggan (Phase 3)",24,"*N/A","","","","","","Q1-2019"],
    [819,819,"SHIP CONSTRUCTION","Fingal","Rathbeale Road, Swords",24,"*N/A","","","","","","Q2-2020"],
    [820,820,"SHIP CONSTRUCTION","Fingal","The Grange, Ballyboughal",2,"*N/A","","","","","","Q3-2017"],
    [821,821,"SHIP CONSTRUCTION","Fingal","Cappaghfinn (Phase 1)",14,"*N/A","","","","","","Q2-2016"],
    [822,822,"SHIP CONSTRUCTION","Fingal","St. Cronan's Green, Swords",14,"*N/A","","","","","","Q2-2016"],
    [823,823,"SHIP CONSTRUCTION","Fingal","St. Cronan's Cottages, Swords - Infill",1,"*N/A","","","","","","Q2-2016"],
    [824,824,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",25,"*N/A","","","","","","Q4-2017"],
    [825,825,"SHIP CONSTRUCTION","Fingal","The Grange, Ballyboughal",6,"*N/A","","","","","","Q4-2018"],
    [826,826,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",15,"*N/A","","","","","","Q1-2018"],
    [827,827,"SHIP CONSTRUCTION","Fingal","Redevelopment of Community Centre, Pinewood, Balbriggan",2,"*N/A","","","","","","Q3-2019"],
    [828,828,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",4,"*N/A","","","","","","Q3-2018"],
    [829,829,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",25,"*N/A","","","","","","Q4-2018"],
    [830,830,"SHIP CONSTRUCTION","Fingal","Tucketts Lane, Howth",8,"*N/A","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [831,831,"SHIP CONSTRUCTION","Fingal","Wellview",20,"*N/A","","","","","Q3-2020",""],
    [832,832,"SHIP CONSTRUCTION","Fingal","Rowlestown",6,"*N/A","","","","","","Q4-2019"],
    [833,833,"SHIP CONSTRUCTION","Fingal","Rowlestown",6,"*N/A","","","","","","Q4-2019"],
    [834,834,"SHIP CONSTRUCTION","Fingal","Cappaghfinn, Cappagh Road Finglas - Phase 3",69,"*N/A","","","","","Q4-2020",""],
    [835,835,"SHIP CONSTRUCTION","Fingal","Rowlestown",4,"*N/A","","","","","","Q3-2019"],
    [836,836,"SHIP CONSTRUCTION","Fingal","Leonards Garage, Lusk",10,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [837,837,"SHIP CONSTRUCTION","Fingal","Katie Hunt's Cottage, Church Road, Lusk",5,"*N/A","","","","","Q3-2021",""],
    [838,838,"CAS CONSTRUCTION","Fingal","Killhedge Lane Dun Emer",31,"Tï¿½ath Housing Association Ltd","","","","","Q3-2021",""],
    [839,839,"CAS CONSTRUCTION","Fingal","Ravenswood, North Road, Finglas",6,"Peter McVerry Trust Ltd","","","","","","Q4-2018"],
    [840,840,"CAS CONSTRUCTION","Fingal","22 College Street, Baldoyle",4,"Cluid Housing Association","","","","","Q3-2020",""],
    [841,841,"CAS CONSTRUCTION","Fingal","Darcystown, Ringfort, Balrothery",9,"North ? East Housing Association Ltd","","","","","","Q3-2017"],
    [842,842,"CAS CONSTRUCTION","Fingal","Estuary Road, Malahide",8,"Society of Saint Vincent de Paul","","","","","","Q2-2018"],
    [843,843,"CAS CONSTRUCTION","Fingal","Garristown",6,"North ? East Housing Association Ltd","","","","","Q3-2021",""],
    [844,844,"CALF Turnkey","Fingal","4 units, Taylor Hill, Balbriggan, Co. Dublin (Phase 1)",4,"Clï¿½id Housing","","","","","","Q4-2018"],
    [845,845,"CALF Turnkey","Fingal","Allendale Square, Clonsilla, Dublin 15 (Phase 1)*",28,"Respond","","","","","","Q2-2020"],
    [846,846,"CALF Turnkey","Fingal","An Muileann, Kettles Lane, Swords, Dublin (Phase 1)",24,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [847,847,"CALF Turnkey","Fingal","Barnwell Woods, Hansfield, Dublin 15 (Phase 1)*",12,"Tuath Housing Association","","","","","","Q4-2018"],
    [848,848,"CALF Turnkey","Fingal","Barnwell Woods, Hansfield, Dublin 15 (Phase 2)*",12,"Tuath Housing Association","","","","","","Q4-2018"],
    [849,849,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 1)",10,"Tuath Housing Association","","","","","Q4-2019",""],
    [850,850,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 2)",10,"Tuath Housing Association","","","","","Q4-2019",""],
    [851,851,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 3)",29,"Tuath Housing Association","","","","","Q4-2019",""],
    [852,852,"CALF Turnkey","Fingal","Bellingsmore, Hollywoodrath, Dubin 15 (Phase 1)",29,"Tuath Housing Association","","","","","","Q4-2020"],
    [853,853,"CALF Turnkey","Fingal","Bellingsmore, Hollywoodrath, Dubin 15 (Phase 2)",12,"Tuath Housing Association","","","","","","Q4-2020"],
    [854,854,"CALF Turnkey","Fingal","Bellingsmore, Hollywoodrath, Dublin 15  (Phase 1)*",17,"Tuath Housing Association","","","","","","Q2-2021"],
    [855,855,"CALF Turnkey","Fingal","Bellingsmore, Hollywoodrath, Dublin 15  (Phase 2)",21,"Tuath Housing Association","","","","","Q4-2019",""],
    [856,856,"CALF Turnkey","Fingal","Beresford, Oakstown, Donabate, Co. Dublin (Phase 1)*",36,"Tuath Housing Association","","","","","Q3-2020",""],
    [857,857,"CALF Turnkey","Fingal","Beresford, Oakstown, Donabate, Co. Dublin (Phase 2)*",4,"Tuath Housing Association","","","","","Q3-2020",""],
    [858,858,"CALF Turnkey","Fingal","Carrs Lane, Malahide Road, Dublin 17 (Phase 1)*",29,"Respond","","","","","","Q2-2021"],
    [859,859,"CALF Turnkey","Fingal","Carrs Lane, Malahide Road, Dublin 17 (Phase 2)*",30,"Respond","","","","","Q4-2019",""],
    [860,860,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 1)",5,"Tuath Housing Association","","","","","","Q2-2016"],
    [861,861,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 2)",7,"Tuath Housing Association","","","","","","Q3-2016"],
    [862,862,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 3)",7,"Tuath Housing Association","","","","","","Q4-2016"],
    [863,863,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 4)",21,"Tuath Housing Association","","","","","","Q1-2017"],
    [864,864,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 5)",8,"Tuath Housing Association","","","","","","Q2-2017"],
    [865,865,"CALF Turnkey","Fingal","Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 1)*",90,"Respond","","","","","Q3-2019",""],
    [866,866,"CALF Turnkey","Fingal","Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 2)*",48,"Respond","","","","","Q3-2019",""],
    [867,867,"CALF Turnkey","Fingal","Cois Sruthan, Ballyboughal, Co.Dublin (Phase 1)*",17,"Oaklee Housing","","","","","","Q3-2020"],
    [868,868,"CALF Turnkey","Fingal","Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 1)",11,"Tuath Housing Association","","","","","","Q4-2019"],
    [869,869,"CALF Turnkey","Fingal","Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 2)*",6,"Tuath Housing Association","","","","","","Q2-2021"],
    [870,870,"CALF Turnkey","Fingal","Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin\\n\\n (Phase 1)*",10,"Clï¿½id Housing","","","","","","Q2-2020"],
    [871,871,"CALF Turnkey","Fingal","Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin\\n\\n (Phase 2)*",5,"Clï¿½id Housing","","","","","","Q4-2020"],
    [872,872,"CALF Turnkey","Fingal","Dunsoghly, Dublin 11 (Phase 1)*",19,"Clï¿½id Housing","","","","","","Q4-2020"],
    [873,873,"CALF Turnkey","Fingal","Knightsgate, Rush, Co. Dublin (Phase 1)*",38,"Clï¿½id Housing","","","","","","Q4-2019"],
    [874,874,"CALF Turnkey","Fingal","Knightsgate, Rush, Co. Dublin (phase 2) (Phase 1)",19,"Clï¿½id Housing","","","","","","Q3-2020"],
    [875,875,"CALF Construction","Fingal","Ladyswell Road & Church Road, Mulhuddart, Dublin 15  (Phase 1)",65,"Clï¿½id Housing","","","","","Q4-2018",""],
    [876,876,"CALF Turnkey","Fingal","Lanesborough Close, Finglas, Dublin 11 (Phase 1)*",21,"Clï¿½id Housing","","","","","","Q4-2018"],
    [877,877,"CALF Turnkey","Fingal","Martello Place, Balbriggan, Co Dublin  (Phase 1)",18,"Respond","","","","","","Q3-2018"],
    [878,878,"CALF Turnkey","Fingal","Millers Glen, Oldtown, Swords, Co. Dublin (Phase 1)*",28,"The Iveagh Trust","","","","","","Q4-2020"],
    [879,879,"CALF Turnkey","Fingal","Millers Glen, Phase 3, Oldtown, Swords (Phase 1)*",14,"The Iveagh Trust","","","","","","Q4-2019"],
    [880,880,"CALF Turnkey","Fingal","Norseman's Court, Norseman's Walk, Lusk Village, Lusk, Co. Dublin (Phase 1)*",18,"Clï¿½id Housing","","","","","","Q4-2020"],
    [881,881,"CALF Turnkey","Fingal","Northwood Avenue, Ballymun Cross, Santry, Dublin 9 (Phase 1)*",12,"Respond","","","","Q2-2021","",""],
    [882,882,"CALF Turnkey","Fingal","Northwood Green, Santry, Dublin 9 (Phase 1)*",6,"Respond","","","","","","Q4-2018"],
    [883,883,"CALF Turnkey","Fingal","Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 1)",48,"Respond","","","","","","Q4-2019"],
    [884,884,"CALF Turnkey","Fingal","Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 2)*",7,"Respond","","","","","","Q2-2020"],
    [885,885,"CALF Construction","Fingal","Old Coolock Lane, Santry, Dublin 9 (Phase 1)",28,"Circle Voluntary Housing Association Ltd","","","","Q1-2019","",""],
    [886,886,"CALF Turnkey","Fingal","Old Corduff Road, Blanchardstown, Dublin 15 (Phase 1)",17,"Respond","","","","","","Q4-2020"],
    [887,887,"CALF Turnkey","Fingal","Old Corduff Road, Blanchardstown, Dublin 15 (Phase 2)*",10,"Respond","","","","","","Q2-2021"],
    [888,888,"CALF Turnkey","Fingal","Oldtown, Swords, Co Dublin (Phase 1)",30,"Respond","","","","Q3-2021","",""],
    [889,889,"CALF Turnkey","Fingal","Oldtown, Swords, Co Dublin (Phase 2)",30,"Respond","","","","Q3-2021","",""],
    [890,890,"CALF Turnkey","Fingal","Oldtown, Swords, Co Dublin (Phase 3)",39,"Respond","","","","Q3-2021","",""],
    [891,891,"CALF Turnkey","Fingal","Pappan Grove, Northwood, Santry, Dublin 9 (Phase 1)*",35,"Tuath Housing Association","","","","","","Q3-2019"],
    [892,892,"CALF Turnkey","Fingal","Phoenix Park Avenue, Castleknock, Dublin 15 (Phase 1)*",31,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [893,893,"CALF Turnkey","Fingal","Riverwood Square, Porterstown, Dublin 15 (Phase 1)*",24,"Clï¿½id Housing","","","","","","Q3-2021"],
    [894,894,"CALF Turnkey","Fingal","Semple Woods, Donabate, Co. Dublin (Phase 1)*",7,"Tuath Housing Association","","","","","","Q4-2020"],
    [895,895,"CALF Turnkey","Fingal","Semple Woods, Donabate, Co. Dublin (Phase 2)*",3,"Tuath Housing Association","","","","","Q4-2019",""],
    [896,896,"CALF Turnkey","Fingal","Semple Woods, Donabate, North County Dublin (Phase 1)*",30,"Tuath Housing Association","","","","","","Q4-2019"],
    [897,897,"CALF Turnkey","Fingal","St Josephs, Clonsilla, Dublin 15 (Phase 1)*",28,"Clï¿½id Housing","","","","","Q2-2019",""],
    [898,898,"CALF Turnkey","Fingal","St Marnockï¿½s Bay, Portmarnock, Co Dublin   (Phase 1)*",10,"Clï¿½id Housing","","","","","","Q4-2017"],
    [899,899,"CALF Turnkey","Fingal","St Werburghs Court Drynam Rd Swords Co Dublin (Phase 1)*",18,"Tuath Housing Association","","","","","","Q4-2017"],
    [900,900,"CALF Turnkey","Fingal","Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [901,901,"CALF Turnkey","Fingal","Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 2)*",8,"Circle Voluntary Housing Association Ltd","","","","","Q4-2017",""],
    [902,902,"CALF Turnkey","Fingal","Taylor Hill Crescent, Balbriggan, Co. Dublin (Phase 1)",4,"Clï¿½id Housing","","","","","","Q4-2018"],
    [903,903,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)",21,"Clï¿½id Housing","","","","","","Q2-2020"],
    [904,904,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*",31,"Clï¿½id Housing","","","","","","Q4-2018"],
    [905,905,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*",24,"Clï¿½id Housing","","","","","","Q4-2019"],
    [906,906,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*",7,"Clï¿½id Housing","","","","","Q3-2020",""],
    [907,907,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 2)",1,"Clï¿½id Housing","","","","","","Q4-2020"],
    [908,908,"CALF Turnkey","Fingal","The Forge, Lusk, Co. Dublin (Phase 1)",8,"Oaklee Housing","","","","","","Q4-2019"],
    [909,909,"CALF Turnkey","Fingal","The Hermitage, Balgriffin, Co Dublin  (Phase 1)*",54,"Clï¿½id Housing","","","","","","Q4-2017"],
    [910,910,"CALF Turnkey","Fingal","Waterside, Malahide, Dublin (Phase 1)",5,"Clï¿½id Housing","","","","","","Q4-2020"],
    [911,911,"CALF Turnkey","Fingal","Weavers Wood, Clonsilla Road, Clonsilla, Dublin 15  (Phase 1)*",33,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2018"],
    [912,912,"CALF Turnkey","Fingal","Weston, Feltrim Road, Swords, North County Dublin (Phase 1)",24,"Oaklee Housing","","","","","","Q4-2019"],
    [913,913,"CALF Turnkey","Fingal","Weston, Feltrim Road, Swords, North County Dublin (Phase 2)*",10,"Oaklee Housing","","","","","","Q3-2020"],
    [914,914,"CALF Turnkey","Fingal"," Wrens Hill, (Formerly The Galleries),  Donabate, Co. Dublin (Phase 1)",43,"Oaklee Housing","","","","","","Q4-2019"],
    [915,915,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Grï¿½ine, (Glasshouse Site) Monivea Road",6,"*N/A","","","","","","Q3-2019"],
    [916,916,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Grï¿½ine, (Glasshouse Site) Monivea Road",16,"*N/A","","","","","","Q4-2019"],
    [917,917,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Grï¿½ine, (Glasshouse Site) Monivea Road",7,"*N/A","","","","","","Q4-2019"],
    [918,918,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Grï¿½ine, (Glasshouse Site) Monivea Road",13,"*N/A","","","","","","Q3-2020"],
    [919,919,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Grï¿½ine, (Glasshouse Site) Monivea Road",8,"*N/A","","","","","","Q4-2020"],
    [920,920,"SHIP CONSTRUCTION TURNKEY","Galway City","Garraï¿½ Caol, (Coast Road Site) Dublin Road",26,"*N/A","","","","","Q1-2020",""],
    [921,921,"SHIP CONSTRUCTION TURNKEY","Galway City","Garraï¿½ Caol, (Coast Road Site) Dublin Road",22,"*N/A","","","","","Q1-2020",""],
    [922,922,"SHIP CONSTRUCTION","Galway City","Ard Crï¿½, Ballymoneen Road (Phase 2)",78,"*N/A","","","","","","Q4-2020"],
    [923,923,"SHIP CONSTRUCTION","Galway City","Ard Crï¿½, Ballymoneen Road (Phase 1)",14,"*N/A","","","","","","Q2-2018"],
    [924,924,"SHIP CONSTRUCTION","Galway City","Monivea Road, Ballybaan More",15,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [925,925,"SHIP CONSTRUCTION","Galway City","Garraï¿½ Beag, Monivea Road, Ballybaan More",58,"*N/A","","","","","Q1-2020",""],
    [926,926,"SHIP CONSTRUCTION","Galway City","Headford Road, Castlegar",24,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [927,927,"SHIP CONSTRUCTION","Galway City","Keeraun, Ballymoneen Road",63,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [928,928,"SHIP CONSTRUCTION","Galway City","Tirellan Heights, Headford Road",1,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [929,929,"SHIP CONSTRUCTION","Galway City","Merlin Park Lands, Galway City",18,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [930,930,"SHIP CONSTRUCTION","Galway City","1 Munster Avenue, Galway city",4,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [931,931,"CAS CONSTRUCTION","Galway City","97/98 Rockfield",4,"Carraig Dubh Housing Association","","","","","","Q1-2018"],
    [932,932,"CAS CONSTRUCTION","Galway City","Cul Garrai, Rahoon",6,"Peter Triest Housing Association Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [933,933,"CAS CONSTRUCTION","Galway City","47 Forster Street, Galway City (Domestic Violence Refuge)",9,"Cope Galway","","","","","","Q4-2019"],
    [934,934,"CAS CONSTRUCTION","Galway City","Doughiska, Galway City",7,"Respond","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [935,935,"CAS CONSTRUCTION","Galway City","111 Upper Newcastle Road, Galway City",10,"Simon Community : North West Simon","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [936,936,"CALF Turnkey","Galway City","Ballybanemor Road, Ballybrit, Galway (Phase 1)*",52,"Respond","","","","","Q2-2021",""],
    [937,937,"CALF Turnkey","Galway City","Ballybanemor Road, Ballybrit, Galway (Phase 2)",49,"Respond","","","","","Q2-2021",""],
    [938,938,"CALF Turnkey","Galway City","Belmont, Renmore, Galway City (Phase 1)*",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [939,939,"CALF Turnkey","Galway City","Block C, Sraith Fhada, Doughiska, Galway (Phase 1)",11,"Tuath Housing Association","","","","","","Q4-2020"],
    [940,940,"CALF Turnkey","Galway City","Block D, Sraith Fhada, Doughiska, Galway (Phase 1)",14,"Tuath Housing Association","","","","","","Q4-2019"],
    [941,941,"CALF Turnkey","Galway City","Boireann Beag, Ros Cam, Galway (Phase 1)",16,"Clï¿½id Housing","","","","","","Q4-2016"],
    [942,942,"CALF Turnkey","Galway City","Breacan, Letteragh Road, Galway City (Phase 1)*",2,"Tuath Housing Association","","","","","","Q4-2019"],
    [943,943,"CALF Turnkey","Galway City","Briar Hill, Old Monivea Road, Ballybrit, Galway (Phase 1)",7,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [944,944,"CALF Turnkey","Galway City","Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 1)",7,"Respond","","","","","","Q4-2019"],
    [945,945,"CALF Turnkey","Galway City","Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 2)*",8,"Respond","","","","","","Q3-2020"],
    [946,946,"CALF Turnkey","Galway City","Caireal Mor, Castlegar Road, Galway (Phase 1)",10,"Respond","","","","","","Q4-2019"],
    [947,947,"CALF Turnkey","Galway City","Caireal Mor, Castlegar Road, Galway (Phase 2)",71,"Respond","","","","","","Q4-2020"],
    [948,948,"CALF Turnkey","Galway City","Cnoc na Ri, Clybaun Road, Galway  (Phase 1)*",2,"Clï¿½id Housing","","","","","","Q3-2017"],
    [949,949,"CALF Turnkey","Galway City","Creig Ard, Roscam, Galway City  (Phase 1)",9,"Clï¿½id Housing","","","","","","Q4-2020"],
    [950,950,"CALF Turnkey","Galway City","Creig Ard, Roscam, Galway City  (Phase 2)",10,"Clï¿½id Housing","","","","","","Q2-2021"],
    [951,951,"CALF Turnkey","Galway City","Creig Ard, Roscam, Galway City, Co. Galway (Phase 1)*",17,"Clï¿½id Housing","","","","","Q4-2019",""],
    [952,952,"CALF Turnkey","Galway City","Cuirt Bhoirne, Roscam, Co Galway (Phase 1)*",12,"Clï¿½id Housing","","","","","Q3-2020",""],
    [953,953,"CALF Turnkey","Galway City","Fanan, Letteragh Road, Galway (Phase 1)*",2,"Tuath Housing Association","","","","","","Q3-2021"],
    [954,954,"CALF Turnkey","Galway City","Fanan, Letteragh Road, Galway (Phase 2)*",2,"Tuath Housing Association","","","","","Q4-2019",""],
    [955,955,"CALF Turnkey","Galway City","Fanan, Letteragh Road, Galway (Phase 3)*",6,"Tuath Housing Association","","","","","Q4-2019",""],
    [956,956,"CALF Turnkey","Galway City","Gaelcarrig, Letteragh, Galway City (Phase 1)",43,"Respond","","","","","Q3-2020",""],
    [957,957,"CALF Turnkey","Galway City","Gaelcarrig, Letteragh, Galway City (Phase 2)*",40,"Respond","","","","","Q3-2020",""],
    [958,958,"CALF Turnkey","Galway City","Leana Theas, Cappagh Road, Galway City (Phase 1)*",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [959,959,"CALF Turnkey","Galway City","Letteragh Road, Rahoon, Galway City (Phase 1)*",10,"Clï¿½id Housing","","","","","","Q3-2021"],
    [960,960,"CALF Turnkey","Galway City","Letteragh Road, Rahoon, Galway City (Phase 2)",13,"Clï¿½id Housing","","","","","Q3-2020",""],
    [961,961,"CALF Turnkey","Galway City","Letteragh Road, Rahoon, Galway City (Phase 3)*",41,"Clï¿½id Housing","","","","","Q3-2020",""],
    [962,962,"CALF Turnkey","Galway City","Maigh Rua, Doughiska, Galway  (Phase 1)",23,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2017"],
    [963,963,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Galway (Phase 1)*",2,"Tuath Housing Association","","","","","","Q1-2017"],
    [964,964,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Galway (Phase 2)*",4,"Tuath Housing Association","","","","","","Q4-2017"],
    [965,965,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Knocknacarra, Galway CIty (Phase 1)*",3,"Tuath Housing Association","","","","","","Q3-2018"],
    [966,966,"CALF Turnkey","Galway City","Reilean, Roscam, Block 5 Galway (Phase 1)*",12,"Tuath Housing Association","","","","","","Q2-2017"],
    [967,967,"CALF Turnkey","Galway City","Reilean, Roscam,Block 4 Galway (Phase 1)*",12,"Tuath Housing Association","","","","","","Q2-2017"],
    [968,968,"CALF Turnkey","Galway City","Revised Murrough, Renmore, Galway  (Phase 1)*",20,"Clï¿½id Housing","","","","","","Q1-2019"],
    [969,969,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Galway City","Ballyburke (Phase 1)",56,"*N/A","","","","","","Q2-2021"],
    [970,970,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Galway City","Ballyburke (Phase 2)",18,"*N/A","","","","","","Q3-2021"],
    [971,971,"SHIP CONSTRUCTION TURNKEY","Galway County","Lorro Gate, Prospect, Athenry",14,"*N/A","","","","","","Q4-2017"],
    [972,972,"SHIP CONSTRUCTION TURNKEY","Galway County","Arvough, Kinvara",6,"*N/A","","","","","","Q4-2017"],
    [973,973,"SHIP CONSTRUCTION TURNKEY","Galway County","Castlecourt, Abbey Street, Portumna",10,"*N/A","","","","","","Q4-2017"],
    [974,974,"SHIP CONSTRUCTION TURNKEY","Galway County","Ashthorn Avenue, Headford",10,"*N/A","","","","","","Q4-2018"],
    [975,975,"SHIP CONSTRUCTION TURNKEY","Galway County","Cuirt na hAbhann, Claregalway ",8,"*N/A","","","","","","Q4-2018"],
    [976,976,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",19,"*N/A","","","","","","Q4-2019"],
    [977,977,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",17,"*N/A","","","","","","Q4-2019"],
    [978,978,"SHIP CONSTRUCTION TURNKEY","Galway County","Arvough, Kinvara",4,"*N/A","","","","","","Q4-2019"],
    [979,979,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",10,"*N/A","","","","","","Q4-2020"],
    [980,980,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",15,"*N/A","","","","","","Q4-2020"],
    [981,981,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",8,"*N/A","","","","","","Q4-2020"],
    [982,982,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",10,"*N/A","","","","","","Q4-2020"],
    [983,983,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",7,"*N/A","","","","","","Q4-2020"],
    [984,984,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",9,"*N/A","","","","","","Q1-2021"],
    [985,985,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",10,"*N/A","","","","","","Q1-2021"],
    [986,986,"SHIP CONSTRUCTION TURNKEY","Galway County","Garraï¿½ Mhic Aodha, Tubber Road, Gort (Phase 1)",9,"*N/A","","","","","Q2-2020",""],
    [987,987,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",9,"*N/A","","","","","Q3-2018",""],
    [988,988,"SHIP CONSTRUCTION TURNKEY","Galway County","Limehill, Dunlo, Ballinasloe",17,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [989,989,"SHIP CONSTRUCTION TURNKEY","Galway County","Garraï¿½ Mhic Aodha, Tubber Road, Gort (Phase 2)",18,"*N/A","","","","","Q2-2020",""],
    [990,990,"SHIP CONSTRUCTION TURNKEY","Galway County","Cullairbaun, Athenry",58,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [991,991,"SHIP CONSTRUCTION TURNKEY","Galway County","Limehill, Dunlo, Ballinasloe",15,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [992,992,"SHIP CONSTRUCTION TURNKEY","Galway County","Garraï¿½ Mhic Aodha, Tubber Road, Gort  (Phase 3)",4,"*N/A","","","","","Q2-2020",""],
    [993,993,"SHIP CONSTRUCTION SINGLE STAGE","Galway County","Corralough, Williamstown (SRD)",1,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [994,994,"SHIP CONSTRUCTION","Galway County","Esker Fields, Ballinasloe",2,"*N/A","","","","","","Q4-2019"],
    [995,995,"SHIP CONSTRUCTION","Galway County","Garbally Drive, Ballinasloe",10,"*N/A","","","","","","Q3-2019"],
    [996,996,"SHIP CONSTRUCTION","Galway County","Weir Road, Tuam",30,"*N/A","","","Stage 3 approved Q3-2017, the scheme is now approved to proceed to tender.","","",""],
    [997,997,"SHIP CONSTRUCTION","Galway County","Na Clocha Rua, An Cheathrï¿½ Rua",4,"*N/A","","","","","","Q4-2019"],
    [998,998,"SHIP CONSTRUCTION","Galway County","Ardrahan (SRD)",1,"*N/A","","","","","","Q4-2017"],
    [999,999,"SHIP CONSTRUCTION","Galway County","Callowfinish, Carna (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [1000,1000,"SHIP CONSTRUCTION","Galway County","Waterdale, Claregalway (SRD)",1,"*N/A","","","","","","Q4-2018"],
    [1001,1001,"SHIP CONSTRUCTION","Galway County","Corndulla (SRD)",1,"*N/A","","","","","","Q1-2019"],
    [1002,1002,"SHIP CONSTRUCTION","Galway County","Cill Ciarï¿½n (SRD)",1,"*N/A","","","","","","Q3-2018"],
    [1003,1003,"SHIP CONSTRUCTION","Galway County","Kinvara (SRD)",1,"*N/A","","","","","","Q3-2018"],
    [1004,1004,"SHIP CONSTRUCTION","Galway County","Cnoc na Carraige, Roundstone",8,"*N/A","","","","","","Q4-2020"],
    [1005,1005,"SHIP CONSTRUCTION","Galway County","Gort na gCloch, Hospital Road, Clifden",16,"*N/A","","","","","Q4-2020",""],
    [1006,1006,"SHIP CONSTRUCTION","Galway County","Bridge Court, Ahascragh, Ballinasloe",18,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1007,1007,"SHIP CONSTRUCTION","Galway County","Caisleï¿½n Raithlï¿½n, Ardrahan",12,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1008,1008,"SHIP CONSTRUCTION","Galway County","Barrack Street, Loughrea",5,"*N/A","","","","","","Q3-2021"],
    [1009,1009,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam",24,"*N/A","","","","","","Q3-2019"],
    [1010,1010,"SHIP CONSTRUCTION","Galway County","Cartron, Kinvara",10,"*N/A","","","","","Q3-2021",""],
    [1011,1011,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam",16,"*N/A","","","","","","Q4-2018"],
    [1012,1012,"SHIP CONSTRUCTION","Galway County","Fï¿½na Bhuï¿½, Tuam (Phase 1 )",16,"*N/A","","","","","Q4-2020",""],
    [1013,1013,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam",19,"*N/A","","","","","","Q4-2019"],
    [1014,1014,"SHIP CONSTRUCTION","Galway County","Cnoc na Carraige, Roundstone",6,"*N/A","","","","","","Q1-2021"],
    [1015,1015,"SHIP CONSTRUCTION","Galway County","Ballyglass, Ardrahan (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1016,1016,"SHIP CONSTRUCTION","Galway County","Woodpark, Portumna (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1017,1017,"SHIP CONSTRUCTION","Galway County","Carrowmore West, Clontuskert, Ballinasloe (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1018,1018,"SHIP CONSTRUCTION","Galway County","Woodfield, Dunmore (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1019,1019,"SHIP CONSTRUCTION","Galway County","Knockaloura West, Brownsgrove, Tuam (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1020,1020,"SHIP CONSTRUCTION","Galway County","Creggaturlough, Craughwell (SRD)",1,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1021,1021,"SHIP CONSTRUCTION","Galway County","Gort na gCloch, Hospital Road, Clifden",10,"*N/A","","","","","Q4-2020",""],
    [1022,1022,"SHIP CONSTRUCTION","Galway County","Fï¿½na Bhuï¿½, Tuam (Phase 2)",11,"*N/A","","","","","Q4-2020",""],
    [1023,1023,"SHIP CONSTRUCTION","Galway County","Fï¿½na Bhuï¿½, Tuam (Phase 3)",22,"*N/A","","","","","Q4-2020",""],
    [1024,1024,"SHIP CONSTRUCTION","Galway County","Ballymoe",8,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1025,1025,"SHIP CONSTRUCTION","Galway County","Droim na Gaoithe, Baile Chlï¿½ir (Claregalway)",45,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1026,1026,"SHIP CONSTRUCTION","Galway County","Cosmona, Loughrea",60,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1027,1027,"SHIP CONSTRUCTION","Galway County","Dunlo Hill, Ballinasloe",11,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1028,1028,"CAS CONSTRUCTION","Galway County","Letterfrack (Phase 2)",11,"Cluid Housing Association","","","","","Q4-2020",""],
    [1029,1029,"CAS CONSTRUCTION","Galway County","Rossaveal Cottages, Ros a Mhï¿½l, South Connemara",8,"Tearmann Eanna Teoranta","Stage 1 approved Q4-2016, outline design and costs being prepared.","","","","",""],
    [1030,1030,"CAS CONSTRUCTION","Galway County","Cregboy, Claregalway",14,"Claregalway and District Day Care Centre","","","","","","Q3-2019"],
    [1031,1031,"CAS CONSTRUCTION","Galway County","Eanach Mheain, Carraroe",13,"Tearmann Eanna Teoranta","","Stage 2 approved Q4-2018, full design/tender being prepared.","","","",""],
    [1032,1032,"CAS CONSTRUCTION","Galway County","Mountbellew",5,"Tï¿½ath Housing Association Ltd","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1033,1033,"CAS CONSTRUCTION","Galway County","Springfield, Parkmore, Ballinasloe",4,"Peter Triest Housing Association Ltd","Stage 1 approved Q2-2017, outline design and costs being prepared.","","","","",""],
    [1034,1034,"CAS CONSTRUCTION","Galway County","Letterfrack (Phase 1)",13,"Cluid Housing Association","","","","","","Q2-2016"],
    [1035,1035,"CAS CONSTRUCTION","Galway County","Dunlo Hill, Ballinasloe",18,"Cluid Housing Association","","","","","","Q3-2020"],
    [1036,1036,"CAS CONSTRUCTION","Galway County","Aggard More, Craughwell",4,"Peter Triest Housing Association Ltd","","","","","","Q4-2019"],
    [1037,1037,"CAS CONSTRUCTION","Galway County","The Old Post Office, Inverin",4,"Tearmann Eanna Teoranta","","","","","","Q4-2020"],
    [1038,1038,"CAS CONSTRUCTION","Galway County","Shannon Road, Portumna",4,"Carraig Dubh Housing Association","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1039,1039,"CALF Turnkey","Galway County","Cnoc na Si, Portumna, Co Galway (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2018"],
    [1040,1040,"CALF Turnkey","Galway County","Dunloe Street, Ballinasloe, Co. Galway (Phase 1)",9,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1041,1041,"CALF Turnkey","Galway County","Oranhill, Oranmore, Co. Galway (Phase 1)*",22,"Clï¿½id Housing","","","","Q1-2021","",""],
    [1042,1042,"CALF Turnkey","Galway County","Riveroaks, Claregalway, Co Galway  (Phase 1)",11,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1043,1043,"CALF Turnkey","Galway County","Riveroaks, Claregalway, Co Galway  (Phase 2)",12,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1044,1044,"CALF Turnkey","Galway County","Riveroaks, Claregalway, Co Galway  (Phase 3)*",16,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1045,1045,"CALF Construction","Galway County","Spiddal Cottages, Co Galway (Phase 1)",23,"Clï¿½id Housing","","","","","","Q3-2017"],
    [1046,1046,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole",2,"*N/A","","","","","","Q1-2018"],
    [1047,1047,"SHIP CONSTRUCTION TURNKEY","Kerry","1-4 Steeple Meadow View, Milltown",4,"*N/A","","","","","","Q4-2017"],
    [1048,1048,"SHIP CONSTRUCTION TURNKEY","Kerry","Meadow Park, Milltown",9,"*N/A","","","","","","Q2-2018"],
    [1049,1049,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole",5,"*N/A","","","","","","Q3-2018"],
    [1050,1050,"SHIP CONSTRUCTION TURNKEY","Kerry","Ardmoniel Heights, Killorglin",3,"*N/A","","","","","","Q4-2018"],
    [1051,1051,"SHIP CONSTRUCTION TURNKEY","Kerry","47 Woodview, Cahirdown, Listowel",1,"*N/A","","","","","","Q2-2018"],
    [1052,1052,"SHIP CONSTRUCTION TURNKEY","Kerry","Dromin Upper, Listowel",8,"*N/A","","","","","","Q4-2020"],
    [1053,1053,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole",3,"*N/A","","","","","","Q4-2018"],
    [1054,1054,"SHIP CONSTRUCTION TURNKEY","Kerry","Ardmoniel Heights, Killorglin - Phase 2",1,"*N/A","","","","","","Q2-2019"],
    [1055,1055,"SHIP CONSTRUCTION TURNKEY","Kerry","Ballygologue, Road, Listowel",2,"*N/A","","","","","","Q4-2019"],
    [1056,1056,"SHIP CONSTRUCTION SINGLE STAGE","Kerry","Pinewood Estate, Killarney",6,"*N/A","","","","","","Q4-2019"],
    [1057,1057,"SHIP CONSTRUCTION SINGLE STAGE","Kerry","Glannagilliagh, Caragh Lake, Killorglin (SRD)",1,"*N/A","","","","","Q2-2021",""],
    [1058,1058,"SHIP CONSTRUCTION SINGLE STAGE","Kerry","Carrigcannon, Lyreacrumpane (SRD)",1,"*N/A","","","","","Q2-2021",""],
    [1059,1059,"SHIP CONSTRUCTION SINGLE STAGE","Kerry","Rahinnane, Ventry (SRD)",1,"*N/A","","","","","Q2-2021",""],
    [1060,1060,"SHIP CONSTRUCTION RAPID","Kerry","Rathmore/Barraduff",20,"*N/A","","","","","","Q2-2021"],
    [1061,1061,"SHIP CONSTRUCTION","Kerry","Cois Gallain, Killorglin",14,"*N/A","","","","","","Q4-2019"],
    [1062,1062,"SHIP CONSTRUCTION","Kerry","Ardbhearna, Kenmare",22,"*N/A","","","","","","Q4-2018"],
    [1063,1063,"SHIP CONSTRUCTION","Kerry","Bill Kinnerk Road, Tralee",4,"*N/A","","","","","","Q1-2018"],
    [1064,1064,"SHIP CONSTRUCTION","Kerry","Cuirt Eaglaise, Milltown",8,"*N/A","","","","","","Q4-2019"],
    [1065,1065,"SHIP CONSTRUCTION","Kerry","Killeen, Tralee",21,"*N/A","","","","","","Q3-2019"],
    [1066,1066,"SHIP CONSTRUCTION","Kerry","Lixnaw",4,"*N/A","","","","","","Q4-2017"],
    [1067,1067,"SHIP CONSTRUCTION","Kerry","The Park, Killarney",20,"*N/A","","","","","","Q1-2018"],
    [1068,1068,"SHIP CONSTRUCTION","Kerry","Courthouse Lawn, Listowel",7,"*N/A","","","","","","Q4-2019"],
    [1069,1069,"SHIP CONSTRUCTION","Kerry","Dreenagh, Ballyheigue (SRD)",1,"*N/A","","","","","","Q1-2017"],
    [1070,1070,"SHIP CONSTRUCTION","Kerry","Glenach, Ballybunion",20,"*N/A","","","","","","Q1-2021"],
    [1071,1071,"SHIP CONSTRUCTION","Kerry","Callinafercy, Milltown",1,"*N/A","","","","","","Q4-2018"],
    [1072,1072,"SHIP CONSTRUCTION","Kerry","Cahernaboshina, Ventry",1,"*N/A","","","","","","Q4-2018"],
    [1073,1073,"SHIP CONSTRUCTION","Kerry","An Carrigin, Tralee",28,"*N/A","","","","","","Q4-2020"],
    [1074,1074,"SHIP CONSTRUCTION","Kerry","Pinewood Estate, Killarney",1,"*N/A","","","","","","Q4-2018"],
    [1075,1075,"SHIP CONSTRUCTION","Kerry","Drom West, Glenbeigh",1,"*N/A","","","","","","Q4-2020"],
    [1076,1076,"SHIP CONSTRUCTION","Kerry","Meanus, Killorglin",1,"*N/A","","","","","","Q3-2019"],
    [1077,1077,"SHIP CONSTRUCTION","Kerry","Tullig Beg, Killorglin",1,"*N/A","","","","","","Q3-2019"],
    [1078,1078,"SHIP CONSTRUCTION","Kerry","Owngarry, Killorglin",1,"*N/A","","","","","","Q4-2019"],
    [1079,1079,"SHIP CONSTRUCTION","Kerry","Lohercannon, Tralee",61,"*N/A","","","","","Q3-2020",""],
    [1080,1080,"SHIP CONSTRUCTION","Kerry","BallinaKilly Lower, Glenbeigh",1,"*N/A","","","","","","Q4-2020"],
    [1081,1081,"SHIP CONSTRUCTION","Kerry","Ashgrove, Listowel",1,"*N/A","","","","","","Q3-2017"],
    [1082,1082,"SHIP CONSTRUCTION","Kerry","Cullenagh Upper, Beaufort",1,"*N/A","","","","","","Q1-2021"],
    [1083,1083,"SHIP CONSTRUCTION","Kerry","Farranwilliam, Ardfert",22,"*N/A","","","","","","Q3-2021"],
    [1084,1084,"SHIP CONSTRUCTION","Kerry","Ballyrickard, Tralee",21,"*N/A","","","","","Q3-2020",""],
    [1085,1085,"SHIP CONSTRUCTION","Kerry","Croogorts, Tralee",30,"*N/A","","","","","Q3-2020",""],
    [1086,1086,"SHIP CONSTRUCTION","Kerry","Rock Rd., Killarney",10,"*N/A","","","","","Q3-2020",""],
    [1087,1087,"SHIP CONSTRUCTION","Kerry","Gortamullin, Kenmare (Phase 4)",14,"*N/A","","","","","","Q1-2021"],
    [1088,1088,"SHIP CONSTRUCTION","Kerry","Baile an Gharraï¿½, Lixnaw (Phase 2)",10,"*N/A","","","","","","Q2-2021"],
    [1089,1089,"SHIP CONSTRUCTION","Kerry","Woodview Place, Tarbert",22,"*N/A","","","","","Q2-2021",""],
    [1090,1090,"SHIP CONSTRUCTION","Kerry","Marconi South, Ballybunion",14,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1091,1091,"SHIP CONSTRUCTION","Kerry","Rahoonane, Tralee (New Site)",8,"*N/A","","","","","Q2-2021",""],
    [1092,1092,"SHIP CONSTRUCTION","Kerry","Rusheen, Ballylongford",7,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1093,1093,"SHIP CONSTRUCTION","Kerry","Gortamullin, Kenmare (Phase 5)",14,"*N/A","","","Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.","","",""],
    [1094,1094,"SHIP CONSTRUCTION","Kerry","Matt Talbot Road, Tralee",27,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1095,1095,"SHIP CONSTRUCTION","Kerry","Locke's Shop, Mitchel's Rd, Tralee",8,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1096,1096,"SHIP CONSTRUCTION","Kerry","Marian Terrace, Ballyheigue",9,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1097,1097,"REGENERATION","Kerry","Croilar Na Mistaelach, Tralee",11,"*N/A","","","","","","Q4-2018"],
    [1098,1098,"REGENERATION","Kerry","Urban Terrace, Tralee",2,"*N/A","","","","","","Q4-2016"],
    [1099,1099,"REGENERATION","Kerry","Clonmore Road, Tralee",3,"*N/A","","","","","","Q4-2016"],
    [1100,1100,"REGENERATION","Kerry","St Martin's Park, Tralee",4,"*N/A","","","","","","Q4-2018"],
    [1101,1101,"REGENERATION","Kerry","Dingle Road, Tralee",1,"*N/A","","","","","","Q2-2018"],
    [1102,1102,"CAS CONSTRUCTION","Kerry","Armagh House, Killarney",6,"Cluid Housing Association","","","","","","Q1-2021"],
    [1103,1103,"CAS CONSTRUCTION","Kerry","22 College Road, Castleisland",4,"Kerry Emigrant Support Housing Association Ltd","","","","","","Q4-2018"],
    [1104,1104,"CAS CONSTRUCTION","Kerry","Chamfers Place (Mitchels road, Tralee)",18,"Cluid Housing Association","","","","","Q2-2021",""],
    [1105,1105,"CAS CONSTRUCTION","Kerry","The Parsonage, Caherciveen",5,"Caherciveen Social Services (Housing) Ltd","","","","","","Q4-2018"],
    [1106,1106,"CAS CONSTRUCTION","Kerry","The Presentation Convent, Rathmore",4,"Social Action Group Rathmore","","","","","","Q3-2020"],
    [1107,1107,"CALF Turnkey","Kerry","Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 1)*",54,"Clï¿½id Housing","","","","","Q4-2020",""],
    [1108,1108,"CALF Turnkey","Kerry","Barraduff, Killarney, Co Kerry (Phase 1)*",3,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2021",""],
    [1109,1109,"CALF Turnkey","Kerry","Barraduff, Killarney, Co. Kerry (Phase 1)*",15,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1110,1110,"CALF Turnkey","Kerry","Barraduff, Killarney, Co. Kerry (Phase 2)*",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1111,1111,"CALF Turnkey","Kerry","Barraduff, Killarney, Co. Kerry (Phase 3)",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1112,1112,"CALF Turnkey","Kerry","Barraduff, Killarney, Co. Kerry (Phase 4)*",13,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2021"],
    [1113,1113,"CALF Turnkey","Kerry","Cahirdown Wood, Listowel, Co. Kerry (Phase 1)*",12,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1114,1114,"CALF Turnkey","Kerry","Cahirdown Wood, Listowel, Co. Kerry (Phase 2)",26,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1115,1115,"CALF Turnkey","Kerry","Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 1)",16,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2021",""],
    [1116,1116,"CALF Turnkey","Kerry","Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 2)",23,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2021",""],
    [1117,1117,"CALF Turnkey","Kerry","Cathair Lakes Farrantoreen Road, Killorglin, Co Kerry (Phase 1)",5,"Clï¿½id Housing","","","","","","Q2-2016"],
    [1118,1118,"CALF Turnkey","Kerry","Deerpark Avenue, Tralee, Co. Kerry (Phase 1)",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [1119,1119,"CALF Turnkey","Kerry","Derreen, Killarney, Co Kerry  (Phase 1)*",61,"Clï¿½id Housing","","","","","","Q3-2020"],
    [1120,1120,"CALF Turnkey","Kerry","Doon Road, Lisloose, Tralee, Co. Kerry (Phase 1)*",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2020"],
    [1121,1121,"CALF Turnkey","Kerry","Dromcairn, Tralee, Co. Kerry (Phase 1)",12,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1122,1122,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 1)",14,"Respond","","","","","","Q4-2018"],
    [1123,1123,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 2)",2,"Respond","","","","","","Q4-2019"],
    [1124,1124,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 3)",5,"Respond","","","","","","Q2-2020"],
    [1125,1125,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 4)",1,"Respond","","","","","","Q2-2021"],
    [1126,1126,"CALF Turnkey","Kerry","Fortfield, Tralee, Co. Kerry (Phase 1)*",15,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1127,1127,"CALF Turnkey","Kerry","Hunters Lodge, Hunters Wood, Ballyseedy, Tralee, Co. Kerry (Phase 1)",10,"Clï¿½id Housing","","","","Q2-2021","",""],
    [1128,1128,"CALF Turnkey","Kerry","Killeen, Abbeydorney Road, Tralee, Co. Kerry (Phase 1)*",17,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1129,1129,"CALF Turnkey","Kerry","Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 1)*",12,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2021"],
    [1130,1130,"CALF Turnkey","Kerry","Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 2)",8,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1131,1131,"CALF Turnkey","Kerry","Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 3)",10,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1132,1132,"CALF Turnkey","Kerry","Lios Ard, Lisloose, Tralee, Co. Kerry (Phase 1)",28,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1133,1133,"CALF Turnkey","Kerry","Moanmore, Pound Road, Castleisland, Co. Kerry (Phase 1)*",14,"Clï¿½id Housing","","","","","Q2-2020",""],
    [1134,1134,"CALF Turnkey","Kerry","Oakwood, Coolegrean, Killarney, Co. Kerry (Coill na Darach) (Phase 1)",59,"Clï¿½id Housing","","","","","","Q3-2019"],
    [1135,1135,"CALF Turnkey","Kerry","Orglan Heights, Ardmoneel, Killorglin (Phase 1)*",30,"Clï¿½id Housing","","","","Q3-2021","",""],
    [1136,1136,"CALF Turnkey","Kerry","Sruthan na Saili, Derreen, Co. Kerry (Phase 1)*",22,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1137,1137,"CALF Turnkey","Kerry","The Grove, Dingle, Co. Kerry (Phase 1)*",20,"Clï¿½id Housing","","","","","","Q3-2020"],
    [1138,1138,"SHIP CONSTRUCTION TURNKEY","Kildare","Bodkin Place, Kilmeague",16,"*N/A","","","","","","Q4-2017"],
    [1139,1139,"SHIP CONSTRUCTION TURNKEY","Kildare","Drogheda Street, Monasterevin",6,"*N/A","","","","","","Q4-2017"],
    [1140,1140,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town",8,"*N/A","","","","","","Q3-2018"],
    [1141,1141,"SHIP CONSTRUCTION TURNKEY","Kildare","Moore Abbey Court, Monasterevin",2,"*N/A","","","","","","Q1-2018"],
    [1142,1142,"SHIP CONSTRUCTION TURNKEY","Kildare","Drogheda Street, Monasterevin",7,"*N/A","","","","","","Q1-2018"],
    [1143,1143,"SHIP CONSTRUCTION TURNKEY","Kildare","Moss Brook, Prosperous",2,"*N/A","","","","","","Q1-2018"],
    [1144,1144,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",2,"*N/A","","","","","","Q4-2018"],
    [1145,1145,"SHIP CONSTRUCTION TURNKEY","Kildare","Whitethorn Park, Allenwood",2,"*N/A","","","","","","Q3-2018"],
    [1146,1146,"SHIP CONSTRUCTION TURNKEY","Kildare","The Pike, Castledermot",6,"*N/A","","","","","","Q4-2018"],
    [1147,1147,"SHIP CONSTRUCTION TURNKEY","Kildare","Grove Lane, Robertstown",3,"*N/A","","","","","","Q1-2020"],
    [1148,1148,"SHIP CONSTRUCTION TURNKEY","Kildare","Brookes Mill, Prosperous",5,"*N/A","","","","","","Q4-2018"],
    [1149,1149,"SHIP CONSTRUCTION TURNKEY","Kildare","The Green, Elsmore Naas",5,"*N/A","","","","","","Q4-2018"],
    [1150,1150,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",10,"*N/A","","","","","","Q1-2019"],
    [1151,1151,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",16,"*N/A","","","","","","Q3-2020"],
    [1152,1152,"SHIP CONSTRUCTION TURNKEY","Kildare","Beech Park Wood, Leixlip",4,"*N/A","","","","","","Q3-2019"],
    [1153,1153,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town",18,"*N/A","","","","","","Q2-2019"],
    [1154,1154,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",10,"*N/A","","","","","","Q3-2019"],
    [1155,1155,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town",20,"*N/A","","","","","","Q3-2019"],
    [1156,1156,"SHIP CONSTRUCTION TURNKEY","Kildare","Cluain Dara, Derrinturn, Kildare",1,"*N/A","","","","","","Q2-2019"],
    [1157,1157,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",3,"*N/A","","","","","","Q4-2019"],
    [1158,1158,"SHIP CONSTRUCTION TURNKEY","Kildare","School Walk, Allenwood",4,"*N/A","","","","","","Q4-2019"],
    [1159,1159,"SHIP CONSTRUCTION TURNKEY","Kildare","Stoneleigh, Naas",6,"*N/A","","","","","","Q4-2019"],
    [1160,1160,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",1,"*N/A","","","","","","Q1-2020"],
    [1161,1161,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",1,"*N/A","","","","","","Q3-2020"],
    [1162,1162,"SHIP CONSTRUCTION TURNKEY","Kildare","Barrack Close, Ballymore Eustace",2,"*N/A","","","","","","Q2-2020"],
    [1163,1163,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",6,"*N/A","","","","","","Q2-2020"],
    [1164,1164,"SHIP CONSTRUCTION TURNKEY","Kildare","Brookes Mill Prosperous",1,"*N/A","","","","","","Q4-2019"],
    [1165,1165,"SHIP CONSTRUCTION TURNKEY","Kildare","Greenfield House, Maynooth",1,"*N/A","","","","","","Q4-2019"],
    [1166,1166,"SHIP CONSTRUCTION TURNKEY","Kildare","Crockaun Way, Brownstown Manor, The Curragh",10,"*N/A","","","","","","Q4-2020"],
    [1167,1167,"SHIP CONSTRUCTION TURNKEY","Kildare","Railway House, Dublin Road, Naas ",3,"*N/A","","","","","","Q3-2020"],
    [1168,1168,"SHIP CONSTRUCTION TURNKEY","Kildare","Loughminane Green, Kildare Town ",2,"*N/A","","","","","","Q4-2020"],
    [1169,1169,"SHIP CONSTRUCTION TURNKEY","Kildare","Crockaun Way, Brownstown Manor, The Curragh",26,"*N/A","","","","","","Q4-2020"],
    [1170,1170,"SHIP CONSTRUCTION TURNKEY","Kildare","Crockaun Way, Brownstown Manor, The Curragh",9,"*N/A","","","","","","Q4-2020"],
    [1171,1171,"SHIP CONSTRUCTION TURNKEY","Kildare","Barrack Close, Ballymore Eustace",2,"*N/A","","","","","","Q3-2020"],
    [1172,1172,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",9,"*N/A","","","","","","Q3-2020"],
    [1173,1173,"SHIP CONSTRUCTION TURNKEY","Kildare","Temple Mills, Rathangan",2,"*N/A","","","","","","Q4-2020"],
    [1174,1174,"SHIP CONSTRUCTION TURNKEY","Kildare","Longstone, Craddockstown, Naas",5,"*N/A","","","","","","Q4-2020"],
    [1175,1175,"SHIP CONSTRUCTION TURNKEY","Kildare","Coolaghknock Green, Kildare Town",4,"*N/A","","","","","","Q4-2020"],
    [1176,1176,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",6,"*N/A","","","","","","Q4-2020"],
    [1177,1177,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn",3,"*N/A","","","","","","Q4-2020"],
    [1178,1178,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",2,"*N/A","","","","","","Q4-2020"],
    [1179,1179,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",1,"*N/A","","","","","","Q2-2021"],
    [1180,1180,"SHIP CONSTRUCTION TURNKEY","Kildare","Fitzgerald Close, Greenfield, Maynooth",1,"*N/A","","","","","","Q2-2021"],
    [1181,1181,"SHIP CONSTRUCTION TURNKEY","Kildare","Main Street, Robertstown",2,"*N/A","","","","","","Q4-2020"],
    [1182,1182,"SHIP CONSTRUCTION TURNKEY","Kildare","Coolaghknock Green, Kildare Town",2,"*N/A","","","","","","Q1-2021"],
    [1183,1183,"SHIP CONSTRUCTION TURNKEY","Kildare","Abbotsfield Clane",1,"*N/A","","","","","","Q2-2021"],
    [1184,1184,"SHIP CONSTRUCTION TURNKEY","Kildare","Old Mill Race, Monasterevin",9,"*N/A","","","","","Q4-2019",""],
    [1185,1185,"SHIP CONSTRUCTION TURNKEY","Kildare","Hemmingway Park, Clane",13,"*N/A","","","","","","Q3-2021"],
    [1186,1186,"SHIP CONSTRUCTION TURNKEY","Kildare","Hemmingway Park, Clane",10,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [1187,1187,"SHIP CONSTRUCTION TURNKEY","Kildare","Coolaghknock Green, Kildare Town",2,"*N/A","","","","","","Q2-2021"],
    [1188,1188,"SHIP CONSTRUCTION TURNKEY","Kildare","Newtown, Ardclough Rd, Celbridge",49,"*N/A","","","","","Q2-2021",""],
    [1189,1189,"SHIP CONSTRUCTION TURNKEY","Kildare","Kildare Road, Rathangan",9,"*N/A","","","","","Q1-2021",""],
    [1190,1190,"SHIP CONSTRUCTION TURNKEY","Kildare","Abbotsfield, Clane",2,"*N/A","","","","","","Q3-2021"],
    [1191,1191,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",1,"*N/A","","","","","Q4-2019",""],
    [1192,1192,"SHIP CONSTRUCTION TURNKEY","Kildare","Fitzgerald Close, Greenfield, Maynooth",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1193,1193,"SHIP CONSTRUCTION SINGLE STAGE","Kildare","Patrician Avenue, Naas",3,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1194,1194,"SHIP CONSTRUCTION RAPID","Kildare","Old Greenfield Road, Maynooth",47,"*N/A","Stage 1 approved Q4-2017, outline design and costs being prepared.","","","","",""],
    [1195,1195,"SHIP CONSTRUCTION","Kildare","Athgarvan Village",18,"*N/A","","","","","Q3-2021",""],
    [1196,1196,"SHIP CONSTRUCTION","Kildare","Rathasker Road, Naas",48,"*N/A","Stage 1 approved Q1-2016, outline design and costs being prepared.","","","","",""],
    [1197,1197,"SHIP CONSTRUCTION","Kildare","Dunmurry Rise, Bishopsland, Kildare Town",32,"*N/A","","","","","","Q3-2019"],
    [1198,1198,"SHIP CONSTRUCTION","Kildare","Anne Street, Prosperous",12,"*N/A","","","","","","Q3-2020"],
    [1199,1199,"SHIP CONSTRUCTION","Kildare","Beechgrove, Rathangan",18,"*N/A","","","","","","Q4-2019"],
    [1200,1200,"SHIP CONSTRUCTION","Kildare","Kilcock (Phase 2.1)",6,"*N/A","","","","","","Q4-2017"],
    [1201,1201,"SHIP CONSTRUCTION","Kildare","Athgarvan Road, Newbridge",13,"*N/A","","","","","","Q3-2018"],
    [1202,1202,"SHIP CONSTRUCTION","Kildare","Newtown House, Leixlip",4,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [1203,1203,"SHIP CONSTRUCTION","Kildare","Coill Dubh",10,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1204,1204,"SHIP CONSTRUCTION","Kildare","Ardclough Road, Celbridge",39,"*N/A","Stage 1 approved Q4-2017, outline design and costs being prepared.","","","","",""],
    [1205,1205,"SHIP CONSTRUCTION","Kildare","Kilcock (Phase 2.2)",13,"*N/A","","","","","","Q1-2018"],
    [1206,1206,"SHIP CONSTRUCTION","Kildare","Ambassador Site, Kill",33,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1207,1207,"SHIP CONSTRUCTION","Kildare","Carbury",5,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1208,1208,"SHIP CONSTRUCTION","Kildare","St. Evins Park Monasterevin",16,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1209,1209,"SHIP CONSTRUCTION","Kildare","Castle Park, Athy",4,"*N/A","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [1210,1210,"SHIP CONSTRUCTION","Kildare","Oldtown Mill, Celbridge",57,"*N/A","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [1211,1211,"CAS CONSTRUCTION","Kildare","Craddockstown, Naas",3,"KARE Promoting Inclusion for People with Intellectual Disabilities","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [1212,1212,"CAS CONSTRUCTION","Kildare","El Kantara, Newbridge",2,"KARE Promoting Inclusion for People with Intellectual Disabilities","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1213,1213,"CAS CONSTRUCTION","Kildare","Jigginstown House, Naas",12,"Homeless Care Ltd","","","","","","Q2-2021"],
    [1214,1214,"CAS CONSTRUCTION","Kildare","St. John's Convent, New Street, Rathangan",27,"Sophia Housing Association Ltd","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1215,1215,"CAS CONSTRUCTION","Kildare","Dominican Lands, Athy",30,"Cluid Housing Association","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [1216,1216,"CALF Turnkey","Kildare","1 unit, Loughlion Green, Kildare Town (Phase 1)",1,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2021"],
    [1217,1217,"CALF Turnkey","Kildare","Belin Woods, Newbridge, Co. Kildare (Phase 1)*",30,"Tuath Housing Association","","","","","Q3-2021",""],
    [1218,1218,"CALF Turnkey","Kildare","Belin Woods, Newbridge, Co. Kildare (Phase 2)*",4,"Tuath Housing Association","","","","","Q3-2021",""],
    [1219,1219,"CALF Turnkey","Kildare","Bellingsfield, Naas, Kildare (Phase 1)*",10,"Respond","","","","","","Q4-2018"],
    [1220,1220,"CALF Turnkey","Kildare","Carton Grove, Maynooth, Co. Kildare (Phase 1)*",5,"Clanmil Housing Association Ireland","","","","","","Q4-2018"],
    [1221,1221,"CALF Turnkey","Kildare","Castle Farm, Jigginstown, Naas, Co. Kildare (Phase 1)",8,"Tuath Housing Association","","","","","","Q4-2019"],
    [1222,1222,"CALF Turnkey","Kildare","Castle Farm, Naas, Co. Kildare (Phase 1)*",8,"Tuath Housing Association","","","","","","Q2-2019"],
    [1223,1223,"CALF Construction","Kildare","Castlefen, Castlesize, Sallins, Co. Kildare (Phase 1)",29,"Tuath Housing Association","","","","","Q1-2020",""],
    [1224,1224,"CALF Turnkey","Kildare","Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 1)*",6,"Cill Dara Housing Association","","","","","","Q4-2019"],
    [1225,1225,"CALF Turnkey","Kildare","Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 2)*",11,"Cill Dara Housing Association","","","","","","Q4-2019"],
    [1226,1226,"CALF Turnkey","Kildare","Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 1)*",26,"Tuath Housing Association","","","","","","Q4-2019"],
    [1227,1227,"CALF Turnkey","Kildare","Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 2)*",17,"Tuath Housing Association","","","","","Q2-2018",""],
    [1228,1228,"CALF Turnkey","Kildare","Elsmore, Jigginstown, Nass, Co. Kildare (Phase 1)*",8,"Tuath Housing Association","","","","","","Q4-2018"],
    [1229,1229,"CALF Turnkey","Kildare","Elsmore, Jigginstown, Nass, Co. Kildare (Phase 2)*",3,"Tuath Housing Association","","","","","","Q3-2019"],
    [1230,1230,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 1)",18,"Tuath Housing Association","","","","","","Q1-2019"],
    [1231,1231,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 2)",6,"Tuath Housing Association","","","","","","Q1-2019"],
    [1232,1232,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 3)",6,"Tuath Housing Association","","","","","","Q1-2019"],
    [1233,1233,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 4)",6,"Tuath Housing Association","","","","","","Q2-2019"],
    [1234,1234,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 5)",4,"Tuath Housing Association","","","","","","Q2-2019"],
    [1235,1235,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 6)",5,"Tuath Housing Association","","","","","","Q3-2019"],
    [1236,1236,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 7)*",18,"Tuath Housing Association","","","","","","Q4-2019"],
    [1237,1237,"CALF Construction","Kildare","Flinters Field (Phase 2), Athy, Co. Kildare (Phase 1)",35,"Respond","","","","","Q1-2021",""],
    [1238,1238,"CALF Turnkey","Kildare","Grand Canal Wood, Allenwood, Co. Kildare (Phase 1)*",21,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1239,1239,"CALF Turnkey","Kildare","Grand Canal Wood, Allenwood, Co. Kildare (Phase 2)",19,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1240,1240,"CALF Turnkey","Kildare","Hawthorn Manor, Brockagh, Coill Dubh, Co. Kildare (Phase 1)*",5,"Oaklee Housing","","","","","","Q4-2019"],
    [1241,1241,"CALF Turnkey","Kildare","Kilbelin Abbey, Kildare, Phase 1 (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1242,1242,"CALF Turnkey","Kildare","Kilbelin Abbey, Kildare, Phase 2 (Phase 1)*",4,"Clï¿½id Housing","","","","","Q2-2019",""],
    [1243,1243,"CALF Turnkey","Kildare","Ledwill Park, Kilcock, Co. Kildare (Phase 1)*",31,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1244,1244,"CALF Turnkey","Kildare","Ledwill Park, Kilcock, Co. Kildare (Phase 1)*",27,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1245,1245,"CALF Turnkey","Kildare","Ledwill Park, Kilcock, Co. Kildare (Phase 1)*",3,"Clï¿½id Housing","","","","","Q4-2020",""],
    [1246,1246,"CALF Turnkey","Kildare","Leinster Square, Dublin Street, Kildare Town, Co Kildare (Phase 1)*",4,"Clanmil Housing Association Ireland","","","","","","Q3-2021"],
    [1247,1247,"CALF Turnkey","Kildare","Loughlion, Kildare Town, Kildare (Phase 1)",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1248,1248,"CALF Turnkey","Kildare","Loughlion, Kildare Town, Kildare (Phase 2)*",17,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1249,1249,"CALF Turnkey","Kildare","Loughlion, Kildare Town, Kildare (Phase 3)*",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2021"],
    [1250,1250,"CALF Turnkey","Kildare","Loughlion, Kildare Town, Kildare (Phase 4)",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1251,1251,"CALF Turnkey","Kildare","Loughlion, Kildare Town, Kildare (Phase 5)*",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2021"],
    [1252,1252,"CALF Turnkey","Kildare","Main Street, Prosperous, Clane, Co. Kildare (Phase 1)*",16,"Clanmil Housing Association Ireland","","","","","Q4-2020",""],
    [1253,1253,"CALF Turnkey","Kildare","Mariavilla and Elsmore, Kildare (Phase 1)*",15,"Tuath Housing Association","","","","","","Q4-2019"],
    [1254,1254,"CALF Turnkey","Kildare","Mariavilla, Maynooth, Co. Kildare (Phase 1)*",11,"Tuath Housing Association","","","","","Q3-2019",""],
    [1255,1255,"CALF Turnkey","Kildare","Melitta Road, Co. Kildare (Phase 1)",4,"Clanmil Housing Association Ireland","","","","Q2-2021","",""],
    [1256,1256,"CALF Turnkey","Kildare","Millfield Manor, Newbridge, Co. Kildare (Phase 1)*",19,"Clï¿½id Housing","","","","","","Q3-2018"],
    [1257,1257,"CALF Turnkey","Kildare","Morristown, Newbridge, Co Kildare (Phase 1)",14,"Clï¿½id Housing","","","","","","Q1-2018"],
    [1258,1258,"CALF Turnkey","Kildare","Morristown, Newbridge, Co. Kildare (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q2-2018"],
    [1259,1259,"CALF Turnkey","Kildare","Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 1)*",9,"Tuath Housing Association","","","","","Q4-2019",""],
    [1260,1260,"CALF Turnkey","Kildare","Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 2)*",18,"Tuath Housing Association","","","","","Q4-2019",""],
    [1261,1261,"CALF Turnkey","Kildare","Newtown, Kill, Co. Kildare (Phase 1)*",4,"Tuath Housing Association","","","","Q2-2021","",""],
    [1262,1262,"CALF Turnkey","Kildare","Newtown, Kill, Co. Kildare (Phase 2)*",9,"Tuath Housing Association","","","","Q2-2021","",""],
    [1263,1263,"CALF Turnkey","Kildare","Newtown, Kill, Co. Kildare (Phase 3)",24,"Tuath Housing Association","","","","Q2-2021","",""],
    [1264,1264,"CALF Turnkey","Kildare","Newtown, Kill, Co. Kildare (Phase 4)*",2,"Tuath Housing Association","","","","Q2-2021","",""],
    [1265,1265,"CALF Turnkey","Kildare","Oakpark, Craddockstown, Kildare (Phase 1)",6,"Tuath Housing Association","","","","","","Q4-2020"],
    [1266,1266,"CALF Turnkey","Kildare","Oaktree, Tully Road, Kildare Town (Phase 1)*",10,"Tuath Housing Association","","","","","","Q2-2018"],
    [1267,1267,"CALF Turnkey","Kildare","Oaktree, Tully Road, Kildare Town (Phase 2)*",7,"Tuath Housing Association","","","","","","Q3-2018"],
    [1268,1268,"CALF Turnkey","Kildare","Phase 2, White Oaks, Newbridge, Kildare (Phase 1)",36,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1269,1269,"CALF Turnkey","Kildare","Revised Rye Abbey, Kilcock, Co Kildare (apts)\\n (Phase 1)",33,"Clï¿½id Housing","","","","","","Q2-2017"],
    [1270,1270,"CALF Turnkey","Kildare","Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 1)*",32,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1271,1271,"CALF Turnkey","Kildare","Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 2)*",16,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1272,1272,"CALF Turnkey","Kildare","Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 3)",16,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1273,1273,"CALF Turnkey","Kildare","Robertstown, Naas , Co.Kildare (Phase 1)",5,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2020"],
    [1274,1274,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 1)",13,"Tuath Housing Association","","","","","","Q2-2017"],
    [1275,1275,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 2)",16,"Tuath Housing Association","","","","","","Q4-2017"],
    [1276,1276,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 3)",16,"Tuath Housing Association","","","","","","Q1-2018"],
    [1277,1277,"CALF Turnkey","Kildare","Rye Abbey, Kilcock - revised (houses) (Phase 1)",4,"Clï¿½id Housing","","","","","","Q2-2017"],
    [1278,1278,"CALF Turnkey","Kildare","The Arches, Castlefarm, Naas, Co. Kildare (Phase 1)*",4,"Tuath Housing Association","","","","","","Q4-2020"],
    [1279,1279,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 1)*",5,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1280,1280,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 2)*",3,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1281,1281,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 3)*",16,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1282,1282,"CALF Turnkey","Kildare","The Paddocks, Newbridge, Co Kildare (Phase 1)",18,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1283,1283,"CALF Turnkey","Kildare","The Paddocks, Newbridge, Kildare  (Phase 1)",26,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1284,1284,"CALF Turnkey","Kildare","The Paddocks, Newbridge, Kildare  (Phase 2)",33,"Clï¿½id Housing","","","","","Q2-2020",""],
    [1285,1285,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)",18,"Respond","","","","","","Q4-2019"],
    [1286,1286,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)*",18,"Respond","","","","","","Q2-2021"],
    [1287,1287,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 2)",32,"Respond","","","","","","Q2-2020"],
    [1288,1288,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 3) (Phase 1)",20,"Respond","","","","","Q4-2019",""],
    [1289,1289,"CALF Turnkey","Kildare","Westfield, Leixlip, Co. Kildare (Phase 1)*",20,"Respond","","","","","Q3-2020",""],
    [1290,1290,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 1)*",14,"Clï¿½id Housing","","","","","","Q4-2018"],
    [1291,1291,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 2)",24,"Clï¿½id Housing","","","","","","Q4-2018"],
    [1292,1292,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 3)",20,"Clï¿½id Housing","","","","","","Q1-2019"],
    [1293,1293,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 4)",2,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1294,1294,"CALF Turnkey","Kildare","Whitethorn, Naas, Co. Kildare (Phase 1)*",12,"Tuath Housing Association","","","","","Q2-2020",""],
    [1295,1295,"CALF Turnkey","Kildare","Whitethorn, Naas, Co. Kildare (Phase 2)*",4,"Tuath Housing Association","","","","","Q2-2020",""],
    [1296,1296,"CALF Turnkey","Kildare","Whitethorn, Naas, Co. Kildare (Phase 3)*",4,"Tuath Housing Association","","","","","Q2-2020",""],
    [1297,1297,"CALF Turnkey","Kildare","Willouise, Sallins, Kildare (Phase 1)",31,"Tuath Housing Association","","","","","","Q4-2020"],
    [1298,1298,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Kildare","Craddockstown, Naas (Phase 1)",36,"*N/A","","","","","","Q2-2020"],
    [1299,1299,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Kildare","Craddockstown, Naas (Phase 2)",38,"*N/A","","","","","","Q3-2020"],
    [1300,1300,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Kildare","Butterstream, Clane",77,"*N/A","","","","","Q4-2019",""],
    [1301,1301,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford",11,"*N/A","","","","","","Q2-2017"],
    [1302,1302,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Newpark, Castlecomer Road, Kilkenny",7,"*N/A","","","","","","Q1-2017"],
    [1303,1303,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Abbeygate, Ferrybank",8,"*N/A","","","","","","Q1-2018"],
    [1304,1304,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford",5,"*N/A","","","","","","Q4-2017"],
    [1305,1305,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Abbeygate, Ferrybank",1,"*N/A","","","","","","Q3-2018"],
    [1306,1306,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford (Phase 3)",18,"*N/A","","","","","","Q4-2018"],
    [1307,1307,"SHIP CONSTRUCTION TURNKEY","Kilkenny","New Road, Mooncoin",4,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [1308,1308,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Chapel Street, Mooncoin",2,"*N/A","","","","","Q3-2018",""],
    [1309,1309,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Ogenty, Gowran",12,"*N/A","","","","","","Q4-2018"],
    [1310,1310,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Pennefeather Court, Hebron Road, Kilkenny",8,"*N/A","","","","","Q3-2020",""],
    [1311,1311,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Limegrove, Oakridge, Ferrybank, Co. Kilkenny",4,"*N/A","","","","","","Q2-2020"],
    [1312,1312,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Pennefeather Green, Hebron Road, Kilkenny",52,"*N/A","","","","","Q3-2020",""],
    [1313,1313,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Blackwater Grove, Kilmacow",14,"*N/A","","","","","","Q2-2021"],
    [1314,1314,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Limegrove, Ferrybank, Co. Kilkenny",15,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1315,1315,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Group Home Cloghabrody, Thomastown",4,"*N/A","","","","","","Q3-2020"],
    [1316,1316,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Inchacarron, Mullinavat",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1317,1317,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Shanganny, Jenkinstown",2,"*N/A","","","","","Q4-2020",""],
    [1318,1318,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Ayrfield, Granges Road, Kilkenny",6,"*N/A","","","","","","Q2-2021"],
    [1319,1319,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Old Fire Station, Graiguenamanagh",2,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1320,1320,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Ayrfield, Granges Road, Kilkenny",2,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [1321,1321,"SHIP CONSTRUCTION SINGLE STAGE","Kilkenny","Haggardsgreen, Callan",1,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1322,1322,"SHIP CONSTRUCTION","Kilkenny","Blackstaff House, Callan",4,"*N/A","","","","","","Q4-2019"],
    [1323,1323,"SHIP CONSTRUCTION","Kilkenny","Barna, Freshford",1,"*N/A","","","","","","Q2-2018"],
    [1324,1324,"SHIP CONSTRUCTION","Kilkenny","10 Golf Links Road, Kilkenny",6,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1325,1325,"SHIP CONSTRUCTION","Kilkenny","Main Street, Piltown",17,"*N/A","","","","","","Q4-2020"],
    [1326,1326,"SHIP CONSTRUCTION","Kilkenny","Station Road, Ballyragget",22,"*N/A","","","","","","Q2-2021"],
    [1327,1327,"SHIP CONSTRUCTION","Kilkenny","Bolton, Callan",38,"*N/A","","","","","","Q3-2020"],
    [1328,1328,"SHIP CONSTRUCTION","Kilkenny","Donaguile, Castlecomer",33,"*N/A","","","","","","Q2-2021"],
    [1329,1329,"SHIP CONSTRUCTION","Kilkenny","Rosehill, Kells Road, Kilkenny",6,"*N/A","","","","","","Q1-2017"],
    [1330,1330,"SHIP CONSTRUCTION","Kilkenny","Gaol Road, Kilkenny",10,"*N/A","","","","","","Q3-2016"],
    [1331,1331,"SHIP CONSTRUCTION","Kilkenny","Greensbridge House",5,"*N/A","","","","","","Q4-2018"],
    [1332,1332,"SHIP CONSTRUCTION","Kilkenny","The Broguemaker, Kilkenny",18,"*N/A","","","","","","Q2-2021"],
    [1333,1333,"SHIP CONSTRUCTION","Kilkenny","Ladywell, Thomastown, Co. Kilkenny",25,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1334,1334,"SHIP CONSTRUCTION","Kilkenny","Crokers Hill, Kennyswell Road, Kilkenny",88,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1335,1335,"SHIP CONSTRUCTION","Kilkenny","Canal Road, Johnstown, Co. Kilkenny Project 1",5,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [1336,1336,"SHIP CONSTRUCTION","Kilkenny","Canal Road Johnstown Project 2",2,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [1337,1337,"SHIP CONSTRUCTION","Kilkenny","Canal Road Johnstown Project 3",4,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [1338,1338,"CAS CONSTRUCTION TURNKEY","Kilkenny","Golf Links Road, Kilkenny",15,"Respond","","","","","","Q3-2019"],
    [1339,1339,"CAS CONSTRUCTION","Kilkenny","Kingsriver, Ennisnag",4,"Kingsriver Housing Association Limited","","","","","Q2-2021",""],
    [1340,1340,"CAS CONSTRUCTION","Kilkenny","Garrin Green",6,"SOS Kilkenny Housing Association Ltd","","","","","","Q4-2018"],
    [1341,1341,"CAS CONSTRUCTION","Kilkenny","Hazelbrook, Newrath",2,"Waterford Dove Housing Association","","","","","","Q1-2018"],
    [1342,1342,"CAS CONSTRUCTION","Kilkenny","Good Shepherd Centre - Wing 1952",12,"The Good Shepherd Centre (Kilkenny) Ltd","","","","","","Q4-2018"],
    [1343,1343,"CAS CONSTRUCTION","Kilkenny","Brooke House, Thomastown",5,"Camphill Communities of Ireland","","","","","","Q3-2017"],
    [1344,1344,"CAS CONSTRUCTION","Kilkenny","Friary Walk, Callan",12,"Cluid Housing Association","","","","","","Q3-2016"],
    [1345,1345,"CAS CONSTRUCTION","Kilkenny","Garden Cottage, The Workhouse, Callan",1,"Camphill Communities of Ireland","","","","","","Q4-2017"],
    [1346,1346,"CAS CONSTRUCTION","Kilkenny","Red Barn, Patrick Street, Ballyragget",11,"Good Shepherd Services Ltd","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1347,1347,"CAS CONSTRUCTION","Kilkenny","Smith's Road, Ballyraggett",4,"Oaklee Housing Trust","","","","","","Q4-2018"],
    [1348,1348,"CAS CONSTRUCTION","Kilkenny","8/9 Kilkenny Street, Castlecomer",3,"Good Shepherd Services Ltd","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [1349,1349,"CAS CONSTRUCTION","Kilkenny","19/21 Blackmill Street, Kilkenny",12,"Good Shepherd Services Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1350,1350,"CAS CONSTRUCTION","Kilkenny","Brother Thomas Place, Church Lane, Kilkenny",12,"Good Shepherd Services Ltd","","","","","Q2-2021",""],
    [1351,1351,"CAS CONSTRUCTION","Kilkenny","Bridge Street, Callan",6,"Good Shepherd Services Ltd","","","","","","Q4-2019"],
    [1352,1352,"CAS CONSTRUCTION","Kilkenny","Grennan Villa, Thomastown",5,"Camphill Communities of Ireland","","","","","Q3-2020",""],
    [1353,1353,"CAS CONSTRUCTION","Kilkenny","Fiennes Court, William Street, Kilkenny",7,"Good Shepherd Services Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1354,1354,"CAS CONSTRUCTION","Kilkenny","St. John of god Convent, College Road, Kilkenny",12,"Sophia Housing Association Ltd","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1355,1355,"CAS CONSTRUCTION","Kilkenny","The Round House, Kells, Co. Kilkenny",4,"SOS Kilkenny Housing Association Ltd","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1356,1356,"CAS CONSTRUCTION","Kilkenny","Ladywell Street, Thomastown, Co. Kilkenny",6,"Good Shepherd Services Ltd","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [1357,1357,"CAS CONSTRUCTION","Kilkenny","Dinan lodge,Suttonsrath, Jenkinstown, Co. Kilkenny",4,"Kilkenny Voluntary Housing Association","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [1358,1358,"CAS CONSTRUCTION","Kilkenny","Maudlin Street, Thomastown, Co. Kilkenny",10,"Kilkenny Voluntary Housing Association","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1359,1359,"CAS CONSTRUCTION","Kilkenny","Mill Street, Callan, Co. Kilkenny",12,"Kilkenny Voluntary Housing Association","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1360,1360,"CAS CONSTRUCTION","Kilkenny","Prague House Hall, Freshford, co. Kilkenny",8,"Kilkenny Voluntary Housing Association","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1361,1361,"CALF Turnkey","Kilkenny","Castlehyde, Rosbercon (Phase 1)",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [1362,1362,"CALF Turnkey","Kilkenny","Castlehyde, Rosbercon (Phase 2)",6,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [1363,1363,"CALF Turnkey","Kilkenny","Cois Na Bearu, Graiguenemanagh, Kilkenny (Phase 1)",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2021"],
    [1364,1364,"CALF Turnkey","Kilkenny","Golf Links Road, Kilkenny (Phase 1)*",39,"Respond","","","","","","Q4-2019"],
    [1365,1365,"CALF Turnkey","Kilkenny","Logan Square, Thomastown, Co Kilkenny (Phase 1)*",16,"Oaklee Housing","","","","","","Q2-2017"],
    [1366,1366,"CALF Turnkey","Kilkenny","Love Lane, Castlecomer, Co. Kilkenny (Phase 1)",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2019"],
    [1367,1367,"CALF Turnkey","Kilkenny","Margaretï¿½s Field, Callan Road, Kilkenny City (Phase 1)",40,"Respond","","","","","","Q2-2021"],
    [1368,1368,"CALF Turnkey","Kilkenny","Nuncio Road, Kilkenny (Phase 1)",28,"Respond","","","","","","Q4-2020"],
    [1369,1369,"CALF Turnkey","Kilkenny","Nuncio Road, Kilkenny (Phase 2)*",22,"Respond","","","","","Q4-2018",""],
    [1370,1370,"CALF Turnkey","Kilkenny","Oï¿½Loughlin Court, Kilkenny  (Phase 1)",2,"Respond","","","","","","Q4-2018"],
    [1371,1371,"CALF Turnkey","Kilkenny","Orchard Close, Kilkenny (Phase 1)*",23,"Clï¿½id Housing","","","","","Q4-2020",""],
    [1372,1372,"CALF Construction","Kilkenny","Park Lane, Friary Walk, Callan, Co Kilkenny (Phase 1)*",16,"Clï¿½id Housing","","","","","","Q2-2019"],
    [1373,1373,"CALF Turnkey","Kilkenny","Side Road, Moneenroe, Castlecomer, Co. Kilkenny (Phase 1)",9,"Oaklee Housing","","","","","","Q3-2018"],
    [1374,1374,"CALF Construction","Kilkenny","Walkin St Kilkenny (Phase 1)",27,"Oaklee Housing","","","","","","Q4-2019"],
    [1375,1375,"SHIP CONSTRUCTION TURNKEY","Laois","Priory, Borris in Ossory",6,"*N/A","","","","","","Q4-2020"],
    [1376,1376,"SHIP CONSTRUCTION TURNKEY","Laois","Priory, Borris in Ossory",5,"*N/A","","","","","Q2-2020",""],
    [1377,1377,"SHIP CONSTRUCTION TURNKEY","Laois","Clonaslee",7,"*N/A","","","","","","Q4-2020"],
    [1378,1378,"SHIP CONSTRUCTION TURNKEY","Laois","Bruach Na Habhainn, Killeen, Maganey",4,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1379,1379,"SHIP CONSTRUCTION SINGLE STAGE","Laois","Harpurs Lane, Portlaoise",1,"*N/A","","","","","","Q4-2019"],
    [1380,1380,"SHIP CONSTRUCTION SINGLE STAGE","Laois","Hillview, Portlaoise",2,"*N/A","","","","","","Q4-2020"],
    [1381,1381,"SHIP CONSTRUCTION SINGLE STAGE","Laois","Coolroe, Ballybrittas",1,"*N/A","","","","","Q4-2020",""],
    [1382,1382,"SHIP CONSTRUCTION SINGLE STAGE","Laois","The Orchard, Stradbally",6,"*N/A","","","","","","Q1-2020"],
    [1383,1383,"SHIP CONSTRUCTION","Laois","Moore Street, Rathdowney",6,"*N/A","","","","","Q3-2020",""],
    [1384,1384,"SHIP CONSTRUCTION","Laois","Ballymorris Road, Portarlington",22,"*N/A","","","","","","Q2-2021"],
    [1385,1385,"SHIP CONSTRUCTION","Laois","Gleann na Glaise, Ballyroan",10,"*N/A","","","","","Q4-2020",""],
    [1386,1386,"SHIP CONSTRUCTION","Laois","Pattison Est. Mountmellick",10,"*N/A","","","","","Q4-2020",""],
    [1387,1387,"SHIP CONSTRUCTION","Laois","Shannon Street, Mountrath",6,"*N/A","","","","","","Q2-2021"],
    [1388,1388,"SHIP CONSTRUCTION","Laois","Conniberry Way, Old Knockmay Road, Portlaoise",33,"*N/A","","","","","","Q2-2018"],
    [1389,1389,"SHIP CONSTRUCTION","Laois","Harbour Court, Mountmellick",6,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1390,1390,"SHIP CONSTRUCTION","Laois","Mooreville, Rathdowney",7,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1391,1391,"SHIP CONSTRUCTION","Laois","Sean Doire, Cork Road, Durrow",22,"*N/A","","","","","Q4-2020",""],
    [1392,1392,"SHIP CONSTRUCTION","Laois","St Kieran's Park, Errill",14,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1393,1393,"SHIP CONSTRUCTION","Laois","Clonrooske, Knockmay",11,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1394,1394,"SHIP CONSTRUCTION","Laois","Carraig Glas, Stradbally",26,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [1395,1395,"SHIP CONSTRUCTION","Laois","Stradbally Road, Portlaoise",50,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1396,1396,"SHIP CONSTRUCTION","Laois","Iona,Abbeyleix Rd., Portlaoise",9,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [1397,1397,"CAS CONSTRUCTION","Laois","Presentation Convent & Lands, Portlaoise, ",51,"Sophia Housing Association Ltd","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1398,1398,"CAS CONSTRUCTION","Laois","County Hotel, Portlaoise",10,"Cluid Housing Association","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [1399,1399,"CALF Turnkey","Laois","Ballickmoyler, Graiguecullen, Laois (Phase 1)*",20,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1400,1400,"CALF Turnkey","Laois","Ballymorris Green, Portarlington, Co Laois (Phase 1)",12,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1401,1401,"CALF Turnkey","Laois","Ballymorris Green, Portarlington, Co Laois (Phase 2)",20,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1402,1402,"CALF Turnkey","Laois","Ballymorris Green, Portarlington, Co Laois (Phase 3)",14,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1403,1403,"CALF Turnkey","Laois","Bellingham, Portlaoise\\n (Phase 1)",4,"Clï¿½id Housing","","","","","","Q3-2019"],
    [1404,1404,"CALF Turnkey","Laois","Bellingham, Portlaoise\\n (Phase 2)",6,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1405,1405,"CALF Turnkey","Laois","Bellingham, Portlaoise\\n (Phase 3)",5,"Clï¿½id Housing","","","","","","Q2-2020"],
    [1406,1406,"CALF Turnkey","Laois","Bellingham, Portlaoise\\n (Phase 4)*",9,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1407,1407,"CALF Turnkey","Laois","Bellingham, Portlaoise\\n (Phase 5)*",6,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1408,1408,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 1)*",9,"Tuath Housing Association","","","","","","Q3-2020"],
    [1409,1409,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 2)*",8,"Tuath Housing Association","","","","","","Q3-2020"],
    [1410,1410,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 3)",10,"Tuath Housing Association","","","","","","Q4-2020"],
    [1411,1411,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 4)",9,"Tuath Housing Association","","","","","","Q1-2021"],
    [1412,1412,"CALF Turnkey","Laois","Clonroosk Abbey, Portlaoise, Co. Laois (Phase 1)",14,"Clï¿½id Housing","","","","","Q4-2018",""],
    [1413,1413,"CALF Turnkey","Laois","Clonroosk Abbey, Portlaoise, Co. Laois (Phase 2)*",6,"Clï¿½id Housing","","","","","Q4-2018",""],
    [1414,1414,"CALF Turnkey","Laois","Clonroosk Abbey, Portlaoise, Co. Laois (Phase 3)",12,"Clï¿½id Housing","","","","","Q4-2018",""],
    [1415,1415,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 1)",17,"Tuath Housing Association","","","","","","Q3-2018"],
    [1416,1416,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 2)",9,"Tuath Housing Association","","","","","","Q4-2018"],
    [1417,1417,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 3)",13,"Tuath Housing Association","","","","","","Q4-2018"],
    [1418,1418,"CALF Turnkey","Laois","Doirinn Alainn, Ballylynan, Co. Laois (Phase 1)",2,"North & East Housing Association Ltd","","","","","","Q3-2020"],
    [1419,1419,"CALF Turnkey","Laois","Doirinn Alainn, Ballylynan, Co. Laois (Phase 2)",4,"North & East Housing Association Ltd","","","","","","Q4-2020"],
    [1420,1420,"CALF Turnkey","Laois","Doirinn Alainn, Ballylynan, Co. Laois (Phase 3)*",6,"North & East Housing Association Ltd","","","","","","Q2-2021"],
    [1421,1421,"CALF Turnkey","Laois","Droimnin, Stradbally, Co Laois  (Phase 1)",6,"Clï¿½id Housing","","","","","","Q3-2018"],
    [1422,1422,"CALF Turnkey","Laois","Harpurs Lane, Portlaoise, Co. Laois (Phase 1)*",44,"Respond","","","","","Q2-2021",""],
    [1423,1423,"CALF Turnkey","Laois","Holdbrook, Portlaoise, Co. Laois (Phase 1)",10,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1424,1424,"CALF Turnkey","Laois","Holdbrook, Portlaoise, Co. Laois (Phase 2)",10,"Clï¿½id Housing","","","","","Q3-2018",""],
    [1425,1425,"CALF Construction","Laois","Kirwan Park, Mountmellick, Co Laois  (Phase 1)",2,"Clï¿½id Housing","","","","","","Q2-2018"],
    [1426,1426,"CALF Turnkey","Laois","Knockmay Mews, Old Knockmay Road, Portlaoise, Co. Laois (Phase 1)",3,"Tuath Housing Association","","","","","","Q3-2020"],
    [1427,1427,"CALF Turnkey","Laois","Lake Drive, Kilminchy, Portlaoise, Co. Laois (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1428,1428,"CALF Turnkey","Laois","Main Street, Stradbally, Co. Laois (Phase 1)",16,"North & East Housing Association Ltd","","","","","","Q3-2020"],
    [1429,1429,"CALF Turnkey","Laois","Phase 2 The Glen, Kilnacourt, Portarlington, Co Laois (Phase 1)",18,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1430,1430,"CALF Turnkey","Laois","Phase 3 The Glen, Kilnacourt, Portarlington, Co Laois. (Phase 1)",8,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2021"],
    [1431,1431,"CALF Construction","Laois","POST TENDER - Cluinin  Mountrath, Co. Laois (Phase 1)",11,"Oaklee Housing","","","","","","Q1-2018"],
    [1432,1432,"CALF Turnkey","Laois","Rathillion, Killeshin, Co. Laois (Phase 1)*",4,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1433,1433,"CALF Turnkey","Laois","South Dublin Road, Portlaoise, Co. Laois (Phase 1)",13,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [1434,1434,"CALF Turnkey","Laois","South Dublin Road, Portlaoise, Co. Laois (Phase 2)",14,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [1435,1435,"CALF Turnkey","Laois","South Dublin Road, Portlaoise, Co. Laois (Phase 3)*",9,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [1436,1436,"CALF Turnkey","Laois","Spa Street, Droughill, Portarlington, Co. Laois (Phase 1)*",26,"Oaklee Housing","","","","","Q4-2020",""],
    [1437,1437,"CALF Turnkey","Laois","The Glen, Kilnacourt, Portarlington, Co. Laois (Phase 1)",18,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2020"],
    [1438,1438,"CALF Turnkey","Laois","The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 1)*",15,"Clï¿½id Housing","","","","","Q1-2020",""],
    [1439,1439,"CALF Turnkey","Laois","The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 2)*",40,"Clï¿½id Housing","","","","","Q1-2020",""],
    [1440,1440,"CALF Turnkey","Laois","The Meadows, Mountrath Road, Portlaoise, Co. Laois (Phase 1)*",48,"Clï¿½id Housing","","","","Q3-2021","",""],
    [1441,1441,"CALF Turnkey","Laois","Wilton Lawns, Portarlington, Co. Laois (Phase 1)",2,"Respond","","","","","Q2-2021",""],
    [1442,1442,"SHIP CONSTRUCTION TURNKEY","Leitrim","Roosky",7,"*N/A","","","","","","Q4-2019"],
    [1443,1443,"SHIP CONSTRUCTION TURNKEY","Leitrim","Drumshanbo",9,"*N/A","","","","","","Q3-2019"],
    [1444,1444,"SHIP CONSTRUCTION TURNKEY","Leitrim","Church Lane, Ballinamore",9,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1445,1445,"SHIP CONSTRUCTION TURNKEY","Leitrim","Druminshingore, Newtowngore",2,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [1446,1446,"SHIP CONSTRUCTION TURNKEY","Leitrim","Carraig Breac, Drumshanbo",5,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [1447,1447,"SHIP CONSTRUCTION TURNKEY","Leitrim","Oakgrove, Kinlough",5,"*N/A","","","","","","Q4-2020"],
    [1448,1448,"SHIP CONSTRUCTION TURNKEY","Leitrim","Ard na Drise, Mohill",3,"*N/A","","","","","","Q4-2020"],
    [1449,1449,"SHIP CONSTRUCTION TURNKEY","Leitrim","Ard na Drise, Mohill",2,"*N/A","","","","","","Q1-2021"],
    [1450,1450,"SHIP CONSTRUCTION TURNKEY","Leitrim","Lough Meen Estate, Drumkeerin",2,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1451,1451,"SHIP CONSTRUCTION TURNKEY","Leitrim","Commons Lane, Manorhamilton",4,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [1452,1452,"SHIP CONSTRUCTION TURNKEY","Leitrim","Cluain Oir, Liscara, Carrick on Shannon",2,"*N/A","","","","","","Q2-2021"],
    [1453,1453,"SHIP CONSTRUCTION TURNKEY","Leitrim","Manorhamilton & Carrigallen",2,"*N/A","","","","","","Q3-2021"],
    [1454,1454,"SHIP CONSTRUCTION SINGLE STAGE","Leitrim","St. Patricks Park Site, Carrick on Shannon",2,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1455,1455,"SHIP CONSTRUCTION SINGLE STAGE","Leitrim","Druminshingore Td., Newtowngore",3,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1456,1456,"SHIP CONSTRUCTION SINGLE STAGE","Leitrim","Dromahair Td., Dromahair",4,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [1457,1457,"SHIP CONSTRUCTION","Leitrim","Autumn View, Summerhill, Carrick on Shannon",27,"*N/A","","","","","Q4-2019",""],
    [1458,1458,"SHIP CONSTRUCTION","Leitrim","Taobh Tire, Manorhamilton (Phase 2)",7,"*N/A","","","","","","Q4-2018"],
    [1459,1459,"SHIP CONSTRUCTION","Leitrim","Taobh Tire, Manorhamilton (Phase 3)",5,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1460,1460,"SHIP CONSTRUCTION","Leitrim","Townparks, Carrick on Shannon",12,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1461,1461,"SHIP CONSTRUCTION","Leitrim","Lahard, Ballinamore",10,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1462,1462,"CAS CONSTRUCTION","Leitrim","Ballinamore",2,"Society of Saint Vincent de Paul","","","","","","Q4-2017"],
    [1463,1463,"CALF Turnkey","Leitrim","Cnoc an Luir, Drumshanbo, Co. Leitrim (Phase 1)",10,"Tuath Housing Association","","","","","","Q4-2019"],
    [1464,1464,"SHIP CONSTRUCTION TURNKEY","Limerick","Woodlawn Park, Ballysimon Road, Limerick",9,"*N/A","","","","","","Q4-2019"],
    [1465,1465,"SHIP CONSTRUCTION TURNKEY","Limerick","Woodlawn Park, Ballysimon Road, Limerick",1,"*N/A","","","","","","Q4-2019"],
    [1466,1466,"SHIP CONSTRUCTION TURNKEY","Limerick","Carraig Desmond, Newcastle West",8,"*N/A","","","","","","Q4-2019"],
    [1467,1467,"SHIP CONSTRUCTION TURNKEY","Limerick","Knocklong",2,"*N/A","","","","","","Q4-2020"],
    [1468,1468,"SHIP CONSTRUCTION TURNKEY","Limerick","Carraig Desmond, Newcastle West",2,"*N/A","","","","","","Q4-2019"],
    [1469,1469,"SHIP CONSTRUCTION TURNKEY","Limerick","Redgate Close, Old Cratloe Road, Limerick City",14,"*N/A","","","","","Q1-2020",""],
    [1470,1470,"SHIP CONSTRUCTION TURNKEY","Limerick","The Orchard, Main Street, Pallaskenry",8,"*N/A","","","","","Q1-2020",""],
    [1471,1471,"SHIP CONSTRUCTION TURNKEY","Limerick","Gortboy, Charleville Road, kiImallock",33,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1472,1472,"SHIP CONSTRUCTION TURNKEY","Limerick","The Orchard, Main Street, Pallaskenry",8,"*N/A","","","","","Q1-2020",""],
    [1473,1473,"SHIP CONSTRUCTION TURNKEY","Limerick","Knocklong",5,"*N/A","","","","","Q2-2021",""],
    [1474,1474,"SHIP CONSTRUCTION RAPID","Limerick","Faha View, Patrickswell",16,"*N/A","","","","","","Q4-2019"],
    [1475,1475,"SHIP CONSTRUCTION RAPID","Limerick","Old Christians Site, Rathbane",43,"*N/A","","","","","","Q2-2021"],
    [1476,1476,"SHIP CONSTRUCTION","Limerick","Patrickï¿½s Villas, Castleconnell",4,"*N/A","","","","","","Q4-2020"],
    [1477,1477,"SHIP CONSTRUCTION","Limerick","Ballysimon, Greenhill Road ",14,"*N/A","","","","","Q1-2020",""],
    [1478,1478,"SHIP CONSTRUCTION","Limerick","Gough Place, Rosbrien Road, Limerick",17,"*N/A","","","","","Q4-2020",""],
    [1479,1479,"SHIP CONSTRUCTION","Limerick","Burke Avenue, Limerick City",12,"*N/A","","","","","","Q4-2019"],
    [1480,1480,"SHIP CONSTRUCTION","Limerick","Fannings Corner, Limerick City",3,"*N/A","","","","","","Q4-2019"],
    [1481,1481,"SHIP CONSTRUCTION","Limerick","Wallers Well, Limerick City (Phase 2)",13,"*N/A","","","","","","Q4-2020"],
    [1482,1482,"SHIP CONSTRUCTION","Limerick","Clonmacken, Limerick City",43,"*N/A","","","","","Q3-2019",""],
    [1483,1483,"SHIP CONSTRUCTION","Limerick","Glenview Drive, Hospital",20,"*N/A","","","","","Q3-2020",""],
    [1484,1484,"SHIP CONSTRUCTION","Limerick","Clare Street, Limerick City",7,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [1485,1485,"SHIP CONSTRUCTION","Limerick","Hasset Villas, Thomondgate",3,"*N/A","","","","","","Q4-2018"],
    [1486,1486,"SHIP CONSTRUCTION","Limerick","Kilmurry Court, Garryowen",7,"*N/A","","","","","","Q4-2019"],
    [1487,1487,"SHIP CONSTRUCTION","Limerick","Rathbane Road, Limerick City",2,"*N/A","","","","","","Q1-2019"],
    [1488,1488,"SHIP CONSTRUCTION","Limerick","Sycamore Avenue, Limerick City",5,"*N/A","","","","","","Q3-2019"],
    [1489,1489,"SHIP CONSTRUCTION","Limerick","Lower Carey's Road, Limerick City",11,"*N/A","","","","","","Q1-2021"],
    [1490,1490,"SHIP CONSTRUCTION","Limerick","Kileely Road, Moyross",5,"*N/A","","","","","","Q2-2021"],
    [1491,1491,"SHIP CONSTRUCTION","Limerick","Clare Street, Limerick City",2,"*N/A","","","","","","Q4-2017"],
    [1492,1492,"SHIP CONSTRUCTION","Limerick","Knocklong",12,"*N/A","","","","","Q3-2021",""],
    [1493,1493,"SHIP CONSTRUCTION","Limerick","Colbert Terrace, Abbeyfeale",4,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [1494,1494,"SHIP CONSTRUCTION","Limerick","St. Michael's Court, Watergate Flats, ",9,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [1495,1495,"SHIP CONSTRUCTION","Limerick","Ballygrennan Road, Limerick City",2,"*N/A","","","","","","Q4-2017"],
    [1496,1496,"SHIP CONSTRUCTION","Limerick","Ballysimon, Greenhills Road",3,"*N/A","","","","","Q2-2020",""],
    [1497,1497,"SHIP CONSTRUCTION","Limerick","Clueing Dara, Broadford, Limerick",18,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1498,1498,"SHIP CONSTRUCTION","Limerick","Radharc an Ghleanna, Mountcollins",4,"*N/A","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [1499,1499,"SHIP CONSTRUCTION","Limerick","Oï¿½Connor Park, Ardagh, Co. Limerick",8,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [1500,1500,"SHIP CONSTRUCTION","Limerick","Church Glen, Ballylanders, Co. Limerick",9,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [1501,1501,"SHIP CONSTRUCTION","Limerick","Radharc Cillin, Kilfinane, Co. Limerick",10,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [1502,1502,"REGENERATION","Limerick","Lord Edward Street, P2: Main Contract",79,"*N/A","","","","","","Q4-2017"],
    [1503,1503,"REGENERATION","Limerick","Lord Edward Street, P2: Main Contract",2,"*N/A","","","","","","Q1-2017"],
    [1504,1504,"REGENERATION","Limerick","Sheep / Athlunkards Street",8,"Tï¿½ath Housing Association Ltd","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [1505,1505,"REGENERATION","Limerick","Churchfield",19,"*N/A","","","","","","Q1-2018"],
    [1506,1506,"REGENERATION","Limerick","Churchfield",38,"Cluid Housing Association","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [1507,1507,"REGENERATION","Limerick","Cosgrave Park",30,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [1508,1508,"REGENERATION","Limerick","Orchard Site",26,"Oaklee Housing Trust","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [1509,1509,"REGENERATION","Limerick","176 & 177 Cliona Park",2,"*N/A","","","","","","Q2-2016"],
    [1510,1510,"REGENERATION","Limerick","Cliona Park (Phase 2)",10,"*N/A","","","","","","Q2-2017"],
    [1511,1511,"REGENERATION","Limerick","8-10 Gaol Lane",3,"*N/A","","","","","","Q4-2016"],
    [1512,1512,"REGENERATION","Limerick","1 3 Weston Gardens",3,"*N/A","","","","","","Q2-2016"],
    [1513,1513,"REGENERATION","Limerick","2016 Moyross Rebuild",6,"*N/A","","","","","","Q4-2016"],
    [1514,1514,"REGENERATION","Limerick","2016 Southhill Rebuild",8,"*N/A","","","","","","Q4-2016"],
    [1515,1515,"REGENERATION","Limerick","2016 St. Mary's Park Rebuild",9,"*N/A","","","","","","Q4-2016"],
    [1516,1516,"REGENERATION","Limerick","Ballinacurra Weston Vacant Refurbs, Lot 1 & 2**",14,"*N/A","","","","","","Q4-2016"],
    [1517,1517,"REGENERATION","Limerick","St. Mary's Park Infills",15,"*N/A","","","","","","Q4-2018"],
    [1518,1518,"REGENERATION","Limerick","Cliona Park (Phase 3)",18,"Tï¿½ath Housing Association Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1519,1519,"REGENERATION","Limerick","45A-46A Cliona Park",2,"*N/A","","","","","","Q3-2021"],
    [1520,1520,"REGENERATION","Limerick","Dalgaish Park",27,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [1521,1521,"REGENERATION","Limerick","2017 St Mary's Park Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1522,1522,"REGENERATION","Limerick","2017 Ballinacurra Weston Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1523,1523,"REGENERATION","Limerick","2017 Southill Rebuilds",13,"*N/A","","","","","","Q4-2017"],
    [1524,1524,"REGENERATION","Limerick","2017 Moyross Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1525,1525,"REGENERATION","Limerick","Churchfield",23,"*N/A","","","","","","Q2-2018"],
    [1526,1526,"REGENERATION","Limerick","St. Mary's Park Infills",4,"*N/A","","","","","","Q1-2019"],
    [1527,1527,"REGENERATION","Limerick","Infill developments at Carew Park and Moyross",38,"Peter McVerry Trust Ltd","","","","","Q1-2021",""],
    [1528,1528,"REGENERATION","Limerick","2019 Rebuilds (Southill, Moyross, St Mary's Park and Ballinacurra Weston)",8,"*N/A","","","","","","Q4-2019"],
    [1529,1529,"CAS CONSTRUCTION TURNKEY","Limerick","Carebright Community, Ardykeohane, Bruff",6,"Carebright Ltd","","","","","","Q1-2019"],
    [1530,1530,"CAS CONSTRUCTION TURNKEY","Limerick","Barrack Mews, Brennan's Row, Cathedral Place",2,"Arlington Novas Ireland Ltd","","","","","","Q4-2019"],
    [1531,1531,"CAS CONSTRUCTION TURNKEY","Limerick","Barrack Mews, Brennan's Row, Cathedral place",3,"Arlington Novas Ireland Ltd","","","","","","Q1-2020"],
    [1532,1532,"CAS CONSTRUCTION TURNKEY","Limerick","Barrack Mews, Brennan's Row, Cathedral place",1,"Arlington Novas Ireland Ltd","","","","","","Q2-2020"],
    [1533,1533,"CAS CONSTRUCTION","Limerick","Towerfield Crescent, Croom",16,"Croom Voluntary Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1534,1534,"CAS CONSTRUCTION","Limerick","Cappamore",10,"Cappamore Housing Association Ltd","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1535,1535,"CAS CONSTRUCTION","Limerick","Speakers Corner, Limerick City",4,"Simon Community : Midwest Simon","","","","","","Q3-2018"],
    [1536,1536,"CAS CONSTRUCTION","Limerick","Cuan Mhuire, Bruree",6,"Cuan Mhuire Teoranta","","","","","","Q3-2018"],
    [1537,1537,"CAS CONSTRUCTION","Limerick","Mirth, Thomondgate",18,"Associated Charities Trust Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1538,1538,"CAS CONSTRUCTION","Limerick","Cois na Feile, Abbeyfeale ",12,"Cluid Housing Association","","","","","","Q4-2016"],
    [1539,1539,"CAS CONSTRUCTION","Limerick","2/3 Mallow Street",12,"Peter McVerry Trust Ltd","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [1540,1540,"CAS CONSTRUCTION","Limerick","St. Pauls Convent, Kilfinane",9,"Sophia Housing Association Ltd","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [1541,1541,"CAS CONSTRUCTION","Limerick","McGarry House, 7 Alphonsus Street",8,"Arlington Novas Ireland Ltd","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [1542,1542,"CAS CONSTRUCTION","Limerick","47 & 48 Main Street, Croom, Limerick",4,"Croom Voluntary Housing Association Ltd","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1543,1543,"CAS CONSTRUCTION","Limerick","58 Henry Street",5,"Simon Community : Midwest Simon","","","","","Q1-2021",""],
    [1544,1544,"CAS CONSTRUCTION","Limerick","28/29 Lower Gerald Griffin Street, Limerick",4,"Peter McVerry Trust Ltd","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1545,1545,"CAS CONSTRUCTION","Limerick","42 St Joseph's Street, Limerick",3,"Peter McVerry Trust Ltd","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1546,1546,"CALF Turnkey","Limerick","19 and 20 Castleview Shopping Centre Castleconnell  Limerick (Phase 1)",2,"Focus Housing Association CLG","","","","","Q4-2019",""],
    [1547,1547,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 1)",2,"Respond","","","","","","Q4-2018"],
    [1548,1548,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 2)",2,"Respond","","","","","","Q4-2018"],
    [1549,1549,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 3)",2,"Respond","","","","","","Q4-2018"],
    [1550,1550,"CALF Turnkey","Limerick","Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 1)",46,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [1551,1551,"CALF Turnkey","Limerick","Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 2)*",25,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1552,1552,"CALF Turnkey","Limerick","Bloodmill Road, Singland, Limerick (Phase 1)*",52,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1553,1553,"CALF Turnkey","Limerick","Bloodmill Road, Singland, Limerick (Phase 2)",28,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1554,1554,"CALF Turnkey","Limerick","Bloodmill Road, Singland, Limerick (Phase 3)*",23,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1555,1555,"CALF Turnkey","Limerick","Bloodmill Road, Singland, Limerick (Phase 4)*",34,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1556,1556,"CALF Turnkey","Limerick","Clonmacken, Condell Road, Limerick (Phase 1)*",35,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1557,1557,"CALF Turnkey","Limerick","Clonmacken, Condell Road, Limerick (Phase 2)",12,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1558,1558,"CALF Turnkey","Limerick","Clonmacken, Condell Road, Limerick (Phase 3)*",21,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1559,1559,"CALF Turnkey","Limerick","Clonmacken, Condell Road, Limerick (Phase 4)*",20,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1560,1560,"CALF Turnkey","Limerick","Clonmacken, Condell Road, Limerick (Phase 5)*",22,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1561,1561,"CALF Turnkey","Limerick","Cluain Ard, Fedamore, Co Limerick  (Phase 1)",2,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2018"],
    [1562,1562,"CALF Turnkey","Limerick","Cluain Ard, Fedamore, Co Limerick  (Phase 2)",2,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2018"],
    [1563,1563,"CALF Turnkey","Limerick","Cois Carraig, Clarina Village, Clarina, Co. Limerick (Phase 1)",18,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1564,1564,"CALF Turnkey","Limerick","Dromsally Woods, Cappamore, Co. Limerick (Phase 1)",5,"Focus Housing Association CLG","","","","","Q3-2020",""],
    [1565,1565,"CALF Turnkey","Limerick","Glendale Lawn, Bloodmill Road, Limerick (Phase 1)",4,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1566,1566,"CALF Construction","Limerick","Hyde Road, Limerick City (Phase 1)",20,"Clï¿½id Housing","","","","","","Q1-2018"],
    [1567,1567,"CALF Turnkey","Limerick","Laurelville, Mill Road, Corbally, Limerick (Phase 1)",4,"Clï¿½id Housing","","","","","Q3-2018",""],
    [1568,1568,"CALF Turnkey","Limerick","Laurelville, Mill Road, Corbally, Limerick (Phase 2)*",9,"Clï¿½id Housing","","","","","Q3-2018",""],
    [1569,1569,"CALF Turnkey","Limerick","Mungret Gate, Baunacloka, Mungret, Limerick (Phase 1)",8,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1570,1570,"CALF Turnkey","Limerick","Mungret Gate, Baunacloka, Mungret, Limerick (Phase 2)*",23,"Clï¿½id Housing","","","","","Q3-2018",""],
    [1571,1571,"CALF Turnkey","Limerick","Newtown, Castletroy, Limerick (Phase 1)*",31,"Clï¿½id Housing","","","","Q2-2021","",""],
    [1572,1572,"CALF Turnkey","Limerick","Revised - Ard Aulin, Mungret, Co Limerick (Phase 1)",7,"Clï¿½id Housing","","","","","","Q2-2017"],
    [1573,1573,"CALF Turnkey","Limerick","Toormore, Main Street, Bruree, Co. Limerick (Phase 1)",16,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1574,1574,"CALF Construction","Limerick","Turragh Crescent, Cappamore, Limerick (Phase 1)",15,"Clï¿½id Housing","","","","Q3-2021","",""],
    [1575,1575,"CALF Turnkey","Limerick","Woodfield Manor, Cloonyscrehane, Newcastle West (Phase 1)*",19,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1576,1576,"CALF Turnkey","Limerick","Woodfield Manor, Cloonyscrehane, Newcastle West (Phase 2)",11,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1577,1577,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",14,"*N/A","","","","","","Q4-2017"],
    [1578,1578,"SHIP CONSTRUCTION TURNKEY","Longford","Knock, Lanesborough",4,"*N/A","","","","","","Q3-2018"],
    [1579,1579,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",2,"*N/A","","","","","","Q1-2018"],
    [1580,1580,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck",7,"*N/A","","","","","","Q4-2018"],
    [1581,1581,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck",4,"*N/A","","","","","","Q3-2019"],
    [1582,1582,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck",6,"*N/A","","","","","","Q4-2019"],
    [1583,1583,"SHIP CONSTRUCTION TURNKEY","Longford","Rock View, Cloondara",5,"*N/A","","","","","","Q4-2018"],
    [1584,1584,"SHIP CONSTRUCTION TURNKEY","Longford","Greville Court, Granard",14,"*N/A","","","","","","Q4-2019"],
    [1585,1585,"SHIP CONSTRUCTION TURNKEY","Longford","Knock, Lanesborough",29,"*N/A","","","","","","Q4-2018"],
    [1586,1586,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",2,"*N/A","","","","","","Q4-2019"],
    [1587,1587,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",4,"*N/A","","","","","","Q3-2019"],
    [1588,1588,"SHIP CONSTRUCTION TURNKEY","Longford","Church Street, Edgeworthstown",5,"*N/A","","","","","","Q3-2020"],
    [1589,1589,"SHIP CONSTRUCTION TURNKEY","Longford","Smithfield, Legan",18,"*N/A","","","","","","Q3-2020"],
    [1590,1590,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",4,"*N/A","","","","","","Q4-2019"],
    [1591,1591,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",4,"*N/A","","","","","","Q2-2019"],
    [1592,1592,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",6,"*N/A","","","","","","Q4-2019"],
    [1593,1593,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",4,"*N/A","","","","","","Q2-2019"],
    [1594,1594,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",4,"*N/A","","","","","","Q3-2019"],
    [1595,1595,"SHIP CONSTRUCTION TURNKEY","Longford"," Abhainn Glas, Edgeworthstown",4,"*N/A","","","","","","Q4-2019"],
    [1596,1596,"SHIP CONSTRUCTION TURNKEY","Longford","Caislean Breac, Newtownforbes",2,"*N/A","","","","","","Q4-2019"],
    [1597,1597,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",4,"*N/A","","","","","","Q1-2020"],
    [1598,1598,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",4,"*N/A","","","","","","Q4-2019"],
    [1599,1599,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",2,"*N/A","","","","","","Q4-2019"],
    [1600,1600,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",6,"*N/A","","","","","","Q4-2020"],
    [1601,1601,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",7,"*N/A","","","","","","Q4-2019"],
    [1602,1602,"SHIP CONSTRUCTION TURNKEY","Longford","Slï¿½ Corglass, Legga",4,"*N/A","","","","","","Q1-2021"],
    [1603,1603,"SHIP CONSTRUCTION TURNKEY","Longford","Radharc Na Muileann, Knock, Lanesborough",2,"*N/A","","","","","","Q4-2019"],
    [1604,1604,"SHIP CONSTRUCTION TURNKEY","Longford","Pearse Drive, Longford Town",1,"*N/A","","","","","","Q4-2019"],
    [1605,1605,"SHIP CONSTRUCTION TURNKEY","Longford","Cartrons, Kenagh",5,"*N/A","","","","","","Q4-2020"],
    [1606,1606,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",4,"*N/A","","","","","","Q3-2020"],
    [1607,1607,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",8,"*N/A","","","","","","Q1-2021"],
    [1608,1608,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",1,"*N/A","","","","","","Q4-2020"],
    [1609,1609,"SHIP CONSTRUCTION TURNKEY","Longford","Campbell's Drive, Campbell's Lane, Longford",6,"*N/A","","","","","","Q3-2021"],
    [1610,1610,"SHIP CONSTRUCTION TURNKEY","Longford","O'Hara Site, Connaught Rd.,Longford",14,"*N/A","","","","","Q1-2021",""],
    [1611,1611,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",2,"*N/A","","","","","","Q4-2020"],
    [1612,1612,"SHIP CONSTRUCTION TURNKEY","Longford","Alder Field, Farnagh Hill (Phase 2)",11,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [1613,1613,"SHIP CONSTRUCTION TURNKEY","Longford","Slï¿½ Corglass, Legga",4,"*N/A","","","","","","Q2-2021"],
    [1614,1614,"SHIP CONSTRUCTION TURNKEY","Longford","Campbell's Drive, Campbell's Lane, Longford",4,"*N/A","","","","","","Q2-2021"],
    [1615,1615,"SHIP CONSTRUCTION TURNKEY","Longford","Slï¿½ Corglass, Legga ",1,"*N/A","","","","","","Q3-2021"],
    [1616,1616,"SHIP CONSTRUCTION TURNKEY","Longford","Campbell's Lane, Longford",5,"*N/A","","","","","","Q2-2021"],
    [1617,1617,"SHIP CONSTRUCTION TURNKEY","Longford","St. Patricks Ct., Ballinamuck",8,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1618,1618,"SHIP CONSTRUCTION TURNKEY","Longford","Alder Field, Farnagh Hill",12,"N/A","","","","","","Q3-2021"],
    [1619,1619,"SHIP CONSTRUCTION TURNKEY","Longford","Campbell's Drive, Campbell's Lane, Longford",6,"N/A","","","","","Q2-2021",""],
    [1620,1620,"SHIP CONSTRUCTION","Longford","Rathcline Road, Lanesborough",4,"*N/A","","","","","","Q3-2019"],
    [1621,1621,"SHIP CONSTRUCTION","Longford","Edgeworthstown Road, Ballymahon",4,"*N/A","","","","","","Q1-2018"],
    [1622,1622,"SHIP CONSTRUCTION","Longford","Daroge, Ballymahon",1,"*N/A","","","","","","Q4-2019"],
    [1623,1623,"SHIP CONSTRUCTION","Longford","'Rose Cottage', Ballinalee",6,"*N/A","","","","","Q3-2020",""],
    [1624,1624,"SHIP CONSTRUCTION","Longford","St.Rita's, Park Road, Longford",14,"*N/A","","Stage 2 approved Q1-2020, full design/tender being prepared.","","","",""],
    [1625,1625,"SHIP CONSTRUCTION","Longford","Fairgreen View, Longford Town",1,"*N/A","","","","","","Q2-2021"],
    [1626,1626,"SHIP CONSTRUCTION","Longford","Cranleymore, Abbeylara",3,"*N/A","","","Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.","","",""],
    [1627,1627,"SHIP CONSTRUCTION","Longford","Cloonahard, Edgeworthstown",1,"*N/A","","","","","","Q2-2021"],
    [1628,1628,"SHIP CONSTRUCTION","Longford","Woodlands Path, Keenagh",4,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1629,1629,"SHIP CONSTRUCTION","Longford","Clough Dillons, Keenagh",4,"N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1630,1630,"CALF Turnkey","Longford","Cartrun Breac, Lisbrack Rd, Longford (Phase 1)",7,"Clï¿½id Housing","","","","","","Q1-2017"],
    [1631,1631,"CALF Construction","Longford","Colmcille Terrace, Granard, Co. Longford. (Phase 1)",21,"Tuath Housing Association","","","","Q2-2018","",""],
    [1632,1632,"SHIP CONSTRUCTION TURNKEY","Louth","Brabazon Hall, Termonfeckin, Drogheda",5,"*N/A","","","","","","Q4-2019"],
    [1633,1633,"SHIP CONSTRUCTION TURNKEY","Louth","ï¿½Gort Buiï¿½, Ballymakenny Road, Drogheda",13,"*N/A","","","","","","Q4-2020"],
    [1634,1634,"SHIP CONSTRUCTION TURNKEY","Louth","Green Gates Manor, Haynestown, Dundalk",44,"*N/A","","","","","","Q2-2020"],
    [1635,1635,"SHIP CONSTRUCTION TURNKEY","Louth","Wadman Park, Haynestown, Dundalk",16,"*N/A","","","","","","Q3-2020"],
    [1636,1636,"SHIP CONSTRUCTION TURNKEY","Louth","ï¿½Gort Buiï¿½, Ballymakenny Road, Drogheda",9,"*N/A","","","","","","Q4-2020"],
    [1637,1637,"SHIP CONSTRUCTION TURNKEY","Louth","ï¿½Gort Buiï¿½, Ballymakenny Road, Drogheda",10,"*N/A","","","","","","Q1-2021"],
    [1638,1638,"SHIP CONSTRUCTION TURNKEY","Louth","ï¿½Gort Buiï¿½, Ballymakenny Road, Drogheda",9,"*N/A","","","","","","Q2-2021"],
    [1639,1639,"SHIP CONSTRUCTION TURNKEY","Louth","ï¿½Gort Buiï¿½, Ballymakenny Road, Drogheda",8,"*N/A","","","","","","Q2-2021"],
    [1640,1640,"SHIP CONSTRUCTION TURNKEY","Louth","Wadman Park, Haynestown, Dundalk",17,"*N/A","","","","","","Q4-2020"],
    [1641,1641,"SHIP CONSTRUCTION TURNKEY","Louth","Bridgegate Close, Bridgegate, Ardee",1,"*N/A","","","","","","Q4-2020"],
    [1642,1642,"SHIP CONSTRUCTION TURNKEY","Louth","Termon River, Termonfeckin",2,"*N/A","","","","","","Q4-2020"],
    [1643,1643,"SHIP CONSTRUCTION TURNKEY","Louth","Glyde View, Tallanstown",2,"*N/A","","","","","","Q2-2021"],
    [1644,1644,"SHIP CONSTRUCTION TURNKEY","Louth","Wadman Park, Haynestown, Dundalk",29,"*N/A","","","","","","Q4-2020"],
    [1645,1645,"SHIP CONSTRUCTION TURNKEY","Louth","Termon River, Termonfeckin",1,"*N/A","","","","","Q1-2018",""],
    [1646,1646,"SHIP CONSTRUCTION SINGLE STAGE","Louth","55/57 Bothar Brugha, Drogheda",3,"*N/A","","","","","","Q4-2017"],
    [1647,1647,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",4,"*N/A","","","","","","Q1-2018"],
    [1648,1648,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",7,"*N/A","","","","","","Q4-2016"],
    [1649,1649,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",5,"*N/A","","","","","","Q2-2017"],
    [1650,1650,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",3,"*N/A","","","","","","Q3-2017"],
    [1651,1651,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",7,"*N/A","","","","","","Q4-2017"],
    [1652,1652,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",1,"*N/A","","","","","","Q3-2018"],
    [1653,1653,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",1,"*N/A","","","","","","Q3-2018"],
    [1654,1654,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",2,"*N/A","","","","","","Q4-2019"],
    [1655,1655,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",2,"*N/A","","","","","","Q2-2017"],
    [1656,1656,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",1,"*N/A","","","","","","Q3-2017"],
    [1657,1657,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",4,"*N/A","","","","","","Q4-2017"],
    [1658,1658,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",2,"*N/A","","","","","","Q1-2019"],
    [1659,1659,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 4",1,"*N/A","","","","","","Q3-2018"],
    [1660,1660,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 1",1,"*N/A","","","","","","Q1-2020"],
    [1661,1661,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 4",5,"*N/A","","","","","","Q1-2019"],
    [1662,1662,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",1,"*N/A","","","","","","Q2-2018"],
    [1663,1663,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",4,"*N/A","","","","","","Q3-2018"],
    [1664,1664,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",1,"*N/A","","","","","","Q1-2019"],
    [1665,1665,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",1,"*N/A","","","","","","Q4-2018"],
    [1666,1666,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 4",4,"*N/A","","","","","","Q4-2018"],
    [1667,1667,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",5,"*N/A","","","","","","Q4-2018"],
    [1668,1668,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 4",1,"*N/A","","","","","","Q4-2018"],
    [1669,1669,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 3",2,"*N/A","","","","","","Q2-2019"],
    [1670,1670,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",2,"*N/A","","","","","","Q2-2019"],
    [1671,1671,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q1-2019"],
    [1672,1672,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",3,"*N/A","","","","","","Q4-2019"],
    [1673,1673,"SHIP CONSTRUCTION SINGLE STAGE","Louth","Moneymore, Drogheda",1,"*N/A","","","","","Q2-2020",""],
    [1674,1674,"SHIP CONSTRUCTION SINGLE STAGE","Louth","Gort Uaine, Clogherhead",1,"*N/A","","","","","Q3-2020",""],
    [1675,1675,"SHIP CONSTRUCTION SINGLE STAGE","Louth","School Lane, Dunleer",1,"*N/A","","","","","Q3-2020",""],
    [1676,1676,"SHIP CONSTRUCTION SINGLE STAGE","Louth","Doire Beag, Collon",6,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1677,1677,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 2",1,"*N/A","","","","","","Q3-2019"],
    [1678,1678,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 6",1,"*N/A","","","","","","Q3-2019"],
    [1679,1679,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",4,"*N/A","","","","","","Q3-2019"],
    [1680,1680,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 6",2,"*N/A","","","","","","Q4-2019"],
    [1681,1681,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q1-2020"],
    [1682,1682,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q2-2020"],
    [1683,1683,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q2-2020"],
    [1684,1684,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q2-2020"],
    [1685,1685,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 5 - Dundalk",1,"*N/A","","","","","","Q4-2020"],
    [1686,1686,"SHIP CONSTRUCTION SINGLE STAGE","Louth","CPO Bundle 6",1,"*N/A","","","","","","Q3-2020"],
    [1687,1687,"SHIP CONSTRUCTION","Louth","Woodlands, Dunleer",4,"*N/A","","","","","","Q4-2016"],
    [1688,1688,"SHIP CONSTRUCTION","Louth","Boice Court (Phase 2), Drogheda",72,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [1689,1689,"SHIP CONSTRUCTION","Louth","Father Finn Park (Phase 2)",17,"*N/A","","","","","","Q2-2021"],
    [1690,1690,"SHIP CONSTRUCTION","Louth","Mount Avenue, Dundalk",93,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [1691,1691,"SHIP CONSTRUCTION","Louth","Muirhevnamor, Dundalk (Phase 1)",11,"*N/A","","","","","Q1-2021",""],
    [1692,1692,"REGENERATION","Louth","Cox's Demesne Phase 2a",14,"*N/A","","","","","","Q4-2016"],
    [1693,1693,"REGENERATION","Louth","Cox's Demesne Phase 2b",22,"*N/A","","","","","Q1-2020",""],
    [1694,1694,"CAS CONSTRUCTION TURNKEY","Louth","Liscorrie, Bog Road, Drogheda",12,"Tï¿½ath Housing Association Ltd","","","","","","Q2-2021"],
    [1695,1695,"CAS CONSTRUCTION","Louth","5 Slieveroe Crescent, Dundalk",1,"Cluid Housing Association","","","","","Q1-2021",""],
    [1696,1696,"CAS CONSTRUCTION","Louth","Barrack Street, Dundalk",21,"Simon Community : Dundalk Simon","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1697,1697,"CAS CONSTRUCTION","Louth","McArdle Green (Moneymore), Drogheda",1,"North ? East Housing Association Ltd","","","","","","Q4-2018"],
    [1698,1698,"CAS CONSTRUCTION","Louth","Tierney Street, Ardee",7,"Oaklee Housing Trust","","","Stage 3 approved Q1-2018, the scheme is now approved to proceed to tender.","","",""],
    [1699,1699,"CAS CONSTRUCTION","Louth","Tredagh View, Drogheda",1,"Respond","","","","","","Q1-2017"],
    [1700,1700,"CAS CONSTRUCTION","Louth","Coulter Park, Dundalk",7,"Tï¿½ath Housing Association Ltd","","","","","Q3-2021",""],
    [1701,1701,"CAS CONSTRUCTION","Louth","Four Winds, Mullacapple, Collon",1,"St. John of God Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1702,1702,"CAS CONSTRUCTION","Louth","St. John's Home, Peter's Hill, Drogheda",4,"North ? East Housing Association Ltd","","","Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.","","",""],
    [1703,1703,"CAS CONSTRUCTION","Louth","Riverwell Close, Dundalk",1,"Respond","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1704,1704,"CAS CONSTRUCTION","Louth","Highfield, Newry Road, Dundalk (Domestic Violence Refuge)",12,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1705,1705,"CAS CONSTRUCTION","Louth","10-16 The Alleys, St. Peter's Place, Drogheda",14,"Peter McVerry Trust Ltd","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [1706,1706,"CALF Turnkey","Louth","2 units An Rian, Termonfeckin Rd., Drogheda, Co. Louth (Phase 1)",2,"North & East Housing Association Ltd","","","","","","Q2-2019"],
    [1707,1707,"CALF Turnkey","Louth","Aston Village, Drogheda (Phase 1)*",8,"Respond","","","","","","Q3-2018"],
    [1708,1708,"CALF Construction","Louth","Bishops Court, Dundalk, Co Louth  (Phase 1)",2,"Tuath Housing Association","","","","","","Q3-2020"],
    [1709,1709,"CALF Turnkey","Louth","Carlinn Drive, Mullaharlin Road, Dundalk, Co. Louth (Phase 1)",6,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1710,1710,"CALF Turnkey","Louth","Castle Court, Castlebellingham, Louth (Phase 1)",4,"Clï¿½id Housing","","","","","","Q1-2017"],
    [1711,1711,"CALF Turnkey","Louth","Castle Court, Castlebellingham, Louth (Phase 2)",10,"Clï¿½id Housing","","","","","","Q1-2017"],
    [1712,1712,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 1)",9,"Tuath Housing Association","","","","","","Q1-2018"],
    [1713,1713,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 2)*",20,"Tuath Housing Association","","","","","","Q1-2018"],
    [1714,1714,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 3)",8,"Tuath Housing Association","","","","","","Q3-2018"],
    [1715,1715,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 4)",15,"Tuath Housing Association","","","","","","Q3-2018"],
    [1716,1716,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 5)",6,"Tuath Housing Association","","","","","","Q4-2018"],
    [1717,1717,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 6)*",22,"Tuath Housing Association","","","","","","Q4-2018"],
    [1718,1718,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 7)",22,"Tuath Housing Association","","","","","","Q2-2019"],
    [1719,1719,"CALF Turnkey","Louth","Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 1)*",16,"Tuath Housing Association","","","","","","Q1-2021"],
    [1720,1720,"CALF Turnkey","Louth","Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 2)",10,"Tuath Housing Association","","","","","","Q2-2021"],
    [1721,1721,"CALF Turnkey","Louth","Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 3)",16,"Tuath Housing Association","","","","","Q1-2020",""],
    [1722,1722,"CALF Turnkey","Louth","Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 4)",11,"Tuath Housing Association","","","","","Q1-2020",""],
    [1723,1723,"CALF Turnkey","Louth","Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 5)",12,"Tuath Housing Association","","","","","Q1-2020",""],
    [1724,1724,"CALF Turnkey","Louth","Clonmore Close, Ardee, Co. Louth (Phase 1)",12,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1725,1725,"CALF Turnkey","Louth","Clonmore Close, Ardee, Co. Louth (Phase 2)*",15,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1726,1726,"CALF Turnkey","Louth","Clonmore Close, Ardee, Co. Louth (Phase 3)",15,"Clï¿½id Housing","","","","","Q3-2019",""],
    [1727,1727,"CALF Turnkey","Louth","Clonmore Close, Ardee, Co. Louth (Phase 4)",13,"Clï¿½id Housing","","","","","Q3-2019",""],
    [1728,1728,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 1)*",13,"Tuath Housing Association","","","","","","Q4-2018"],
    [1729,1729,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 2)",8,"Tuath Housing Association","","","","","","Q1-2019"],
    [1730,1730,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 3)",7,"Tuath Housing Association","","","","","","Q2-2019"],
    [1731,1731,"CALF Turnkey","Louth","Coulter Place Armagh Road (Phase 1)",10,"Clï¿½id Housing","","","","","","Q1-2017"],
    [1732,1732,"CALF Turnkey","Louth","Coulter Place Armagh Road (Phase 2)",12,"Clï¿½id Housing","","","","","","Q3-2017"],
    [1733,1733,"CALF Turnkey","Louth","Donore Road, Drogheda, Co. Louth (Phase 1)",66,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1734,1734,"CALF Turnkey","Louth","Dowdallshill, Dundalk, Co. Louth (Phase 1)*",13,"North & East Housing Association Ltd","","","","","","Q3-2020"],
    [1735,1735,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth (Phase 1)*",65,"Respond","","","","","Q4-2020",""],
    [1736,1736,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth(Glenview) (Phase 1)*",14,"Respond","","","","","","Q1-2019"],
    [1737,1737,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth(Glenview) (Phase 2)*",14,"Respond","","","","","","Q4-2019"],
    [1738,1738,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth(Glenview) (Phase 3)",3,"Respond","","","","","Q3-2017",""],
    [1739,1739,"CALF Turnkey","Louth","Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 1)*",87,"Clï¿½id Housing","","","","","Q4-2020",""],
    [1740,1740,"CALF Turnkey","Louth","Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 2)",43,"Clï¿½id Housing","","","","","Q4-2020",""],
    [1741,1741,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 1)*",11,"Tuath Housing Association","","","","","","Q2-2019"],
    [1742,1742,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 2)*",14,"Tuath Housing Association","","","","","","Q2-2019"],
    [1743,1743,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 3)*",15,"Tuath Housing Association","","","","","","Q2-2019"],
    [1744,1744,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 4)*",47,"Tuath Housing Association","","","","","","Q3-2019"],
    [1745,1745,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 5)*",24,"Tuath Housing Association","","","","","","Q4-2019"],
    [1746,1746,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 6)*",1,"Tuath Housing Association","","","","","","Q4-2020"],
    [1747,1747,"CALF Construction","Louth","Fire Station Site, Scarlett St, Drogheda (Phase 1)",15,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1748,1748,"CALF Turnkey","Louth","Haliday Mills, Quay Street, Dundalk, Co. Louth (Phase 1)*",85,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [1749,1749,"CALF Turnkey","Louth","Harbour Grove, Dundalk, Co. Louth (Phase 1)",8,"North & East Housing Association Ltd","","","","","","Q2-2020"],
    [1750,1750,"CALF Turnkey","Louth","Harbour View, Coulter Place, Dundalk (Phase 1)",24,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1751,1751,"CALF Turnkey","Louth","Knock Shee Close, Blackrock, Co. Louth (Phase 1)",1,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1752,1752,"CALF Turnkey","Louth","Knock Shee, Old Golf Links Road, Blackrock, Co Louth  (Phase 1)",3,"Clï¿½id Housing","","","","","","Q4-2017"],
    [1753,1753,"CALF Turnkey","Louth","Knockshee Close, Blackrock, Co. Louth (Phase 1)",3,"Clï¿½id Housing","","","","","","Q2-2020"],
    [1754,1754,"CALF Turnkey","Louth","Liscorrie, Bog Lane, Drogheda (Phase 1)",41,"Tuath Housing Association","","","","","","Q4-2017"],
    [1755,1755,"CALF Turnkey","Louth","Lismullen Grove, Dundalk, Co. Louth (Phase 1)*",15,"Tuath Housing Association","","","","","","Q4-2020"],
    [1756,1756,"CALF Turnkey","Louth","Lismullen Grove, Dundalk, Co. Louth (Phase 2)",8,"Tuath Housing Association","","","","","","Q1-2021"],
    [1757,1757,"CALF Turnkey","Louth","Mount Hamilton, Dundalk, Co. Louth (Phase 1)",20,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1758,1758,"CALF Turnkey","Louth","Newfoundwell Road, Drogheda, Co Louth (Phase 1)*",55,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1759,1759,"CALF Turnkey","Louth","Newfoundwell Road, Drogheda, Co Louth (Phase 2)",39,"Clï¿½id Housing","","","","","Q3-2020",""],
    [1760,1760,"CALF Turnkey","Louth","Newtown, Marsh Road, Drogheda, Co. Louth (Phase 1)*",17,"Respond","","","","","Q4-2020",""],
    [1761,1761,"CALF Turnkey","Louth","Newtown, Marsh Road, Drogheda, Co. Louth (Phase 2)*",23,"Respond","","","","","Q4-2020",""],
    [1762,1762,"CALF Turnkey","Louth","Newtown, Marsh Road, Drogheda, Co. Louth (Phase 3)*",46,"Respond","","","","","Q4-2020",""],
    [1763,1763,"CALF Turnkey","Louth","Newtown, Marsh Road, Drogheda, Co. Louth (Phase 4)*",47,"Respond","","","","","Q4-2020",""],
    [1764,1764,"CALF Turnkey","Louth","Oriel Heights, Collon, Co. Louth (Phase 1)*",13,"North & East Housing Association Ltd","","","","Q3-2021","",""],
    [1765,1765,"CALF Construction","Louth","Post Tender - Clos na Manach, Carlingford, Co Louth (Phase 1)",10,"Tuath Housing Association","","","","","","Q2-2018"],
    [1766,1766,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 1)",20,"Clanmil Housing Association Ireland","","","","","Q1-2019",""],
    [1767,1767,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 2)*",25,"Clanmil Housing Association Ireland","","","","","Q1-2019",""],
    [1768,1768,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 1)",11,"Tuath Housing Association","","","","","","Q4-2019"],
    [1769,1769,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 2)*",16,"Tuath Housing Association","","","","","Q1-2019",""],
    [1770,1770,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 3)*",19,"Tuath Housing Association","","","","","Q1-2019",""],
    [1771,1771,"CALF Turnkey","Louth","Rath na Gloine, Commons Road, Louth (Phase 1)",3,"Clï¿½id Housing","","","","","","Q3-2016"],
    [1772,1772,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 1)",3,"North & East Housing Association Ltd","","","","","","Q4-2018"],
    [1773,1773,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 2)",6,"North & East Housing Association Ltd","","","","","","Q2-2019"],
    [1774,1774,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 3)",3,"North & East Housing Association Ltd","","","","","","Q3-2019"],
    [1775,1775,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 4)",14,"North & East Housing Association Ltd","","","","","","Q3-2019"],
    [1776,1776,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 5)",12,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1777,1777,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 6)",16,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1778,1778,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 1)",4,"Tuath Housing Association","","","","","","Q2-2018"],
    [1779,1779,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 2)",6,"Tuath Housing Association","","","","","","Q3-2018"],
    [1780,1780,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 3)",4,"Tuath Housing Association","","","","","","Q3-2018"],
    [1781,1781,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 4)",15,"Tuath Housing Association","","","","","","Q4-2018"],
    [1782,1782,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 5)",6,"Tuath Housing Association","","","","","","Q2-2019"],
    [1783,1783,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 6)",4,"Tuath Housing Association","","","","","","Q4-2019"],
    [1784,1784,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 7)",12,"Tuath Housing Association","","","","","","Q3-2020"],
    [1785,1785,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 1)",12,"Clï¿½id Housing","","","","","","Q4-2017"],
    [1786,1786,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 2)",15,"Clï¿½id Housing","","","","","","Q3-2019"],
    [1787,1787,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 3)",16,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1788,1788,"CALF Turnkey","Louth","Scotch Hall, Drogheda, Co Louth  (Phase 1)",21,"Respond","","","","Q3-2021","",""],
    [1789,1789,"CALF Construction","Louth","Slieve Row Crescent, Dundalk (Phase 1)",1,"Clï¿½id Housing","","","","","","Q2-2016"],
    [1790,1790,"CALF Turnkey","Louth","Termon River, Baltray Road, Termonfeckin, Co. Louth (Phase 1)",1,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1791,1791,"CALF Turnkey","Louth","Termon River, Baltray Road, Termonfeckin, Drogheda, Co.Louth (Phase 1)*",1,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1792,1792,"CALF Turnkey","Louth","Tullybrook, Drogheda, Co. Louth  (Phase 1)*",85,"Clï¿½id Housing","","","","","Q1-2021",""],
    [1793,1793,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Louth","Ravel Ardee Road, Dunleer",80,"*N/A","","","","","","Q2-2020"],
    [1794,1794,"SHIP CONSTRUCTION TURNKEY","Mayo","Carrabeg, Newport Road, Castlebar",2,"*N/A","","","","","","Q4-2018"],
    [1795,1795,"SHIP CONSTRUCTION TURNKEY","Mayo","Cois Abhainn, Bonniconlon",2,"*N/A","","","","","","Q2-2019"],
    [1796,1796,"SHIP CONSTRUCTION TURNKEY","Mayo","Chapel Street, Louisburgh",3,"*N/A","","","","","","Q4-2019"],
    [1797,1797,"SHIP CONSTRUCTION TURNKEY","Mayo","Bunree, Ballina",3,"*N/A","","","","","Q4-2019",""],
    [1798,1798,"SHIP CONSTRUCTION TURNKEY","Mayo","Heathervale, Castlebar - Phase 2",9,"*N/A","","","","","","Q4-2020"],
    [1799,1799,"SHIP CONSTRUCTION TURNKEY","Mayo","Friars Court, Ballina",2,"*N/A","","","","","","Q4-2019"],
    [1800,1800,"SHIP CONSTRUCTION TURNKEY","Mayo","Riverside Drive, Ballina",3,"*N/A","","","","","","Q4-2019"],
    [1801,1801,"SHIP CONSTRUCTION TURNKEY","Mayo","Davitt Terrace, Castlebar",4,"*N/A","","","","","","Q4-2019"],
    [1802,1802,"SHIP CONSTRUCTION TURNKEY","Mayo","Chapel St., Louisburgh",2,"*N/A","","","","","","Q4-2020"],
    [1803,1803,"SHIP CONSTRUCTION TURNKEY","Mayo","Ard Rua, Claremorris",7,"*N/A","","","","","","Q4-2019"],
    [1804,1804,"SHIP CONSTRUCTION TURNKEY","Mayo","Silver Springs, Claremorris",20,"*N/A","","","","","Q3-2020",""],
    [1805,1805,"SHIP CONSTRUCTION TURNKEY","Mayo","Barley Hill, Bohola",3,"*N/A","","","","","","Q4-2020"],
    [1806,1806,"SHIP CONSTRUCTION TURNKEY","Mayo","Main St., Charlestown",2,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1807,1807,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","Pound Road, Castlebar",6,"*N/A","","","","","","Q4-2019"],
    [1808,1808,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","The Boreen, Crossmolina",3,"*N/A","","","","","Q1-2020",""],
    [1809,1809,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","Deel Court, Crossmolina",3,"*N/A","","","","","Q1-2020",""],
    [1810,1810,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","Kilmaine",6,"*N/A","","","","","","Q4-2019"],
    [1811,1811,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","Knockroe, Moygownagh",3,"*N/A","","","","","Q1-2020",""],
    [1812,1812,"SHIP CONSTRUCTION SINGLE STAGE","Mayo","Low Park, Charlestown",3,"*N/A","","","","","Q3-2020",""],
    [1813,1813,"SHIP CONSTRUCTION","Mayo","Knocknageeha, Newport",1,"*N/A","","","","","","Q2-2019"],
    [1814,1814,"SHIP CONSTRUCTION","Mayo","ï¿½it Aoibhinn, Kilkelly Road, Knock (Phase 3)",4,"*N/A","","","","","","Q3-2018"],
    [1815,1815,"SHIP CONSTRUCTION","Mayo","Kilmeena (Phase 2)",4,"*N/A","","","","","","Q3-2018"],
    [1816,1816,"SHIP CONSTRUCTION","Mayo","Knockmore, Ballina",8,"*N/A","","","","","","Q1-2019"],
    [1817,1817,"SHIP CONSTRUCTION","Mayo","Radharc an tSaillin, Binghamstown, Belmullet (Phase 2)",4,"*N/A","","","","","","Q2-2019"],
    [1818,1818,"SHIP CONSTRUCTION","Mayo","Sliabh Rua, Foxford (Phase 3)",10,"*N/A","","","","","","Q4-2019"],
    [1819,1819,"SHIP CONSTRUCTION","Mayo","Woodlands, Balla (Phase 3)",4,"*N/A","","","","","","Q4-2019"],
    [1820,1820,"SHIP CONSTRUCTION","Mayo","Slinaunroe, Clogher (SRD)",1,"*N/A","","","","","","Q2-2017"],
    [1821,1821,"SHIP CONSTRUCTION","Mayo","Abbeyquarter, Ballyhaunis",18,"*N/A","","","","","","Q4-2020"],
    [1822,1822,"SHIP CONSTRUCTION","Mayo","Tonragee West, Achill (Phase 2)",5,"*N/A","","","","","","Q4-2019"],
    [1823,1823,"SHIP CONSTRUCTION","Mayo","Sli na Roba, Friarsquarter, Ballinrobe",16,"*N/A","","","","","","Q4-2020"],
    [1824,1824,"SHIP CONSTRUCTION","Mayo","Marian Crescent, Ballina",4,"*N/A","","","","","","Q2-2018"],
    [1825,1825,"SHIP CONSTRUCTION","Mayo","Tubberhill, Westport (Phase 3)",21,"*N/A","","","","","","Q1-2018"],
    [1826,1826,"SHIP CONSTRUCTION","Mayo","Parke, Castlebar",8,"*N/A","","","","","","Q4-2019"],
    [1827,1827,"SHIP CONSTRUCTION","Mayo","Killavally",10,"*N/A","","","","","","Q4-2019"],
    [1828,1828,"SHIP CONSTRUCTION","Mayo","Lios na Circa, Saleen, Castlebar - Phase 2",22,"*N/A","","","Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.","","",""],
    [1829,1829,"SHIP CONSTRUCTION","Mayo","Kilkelly Road, Swinford",27,"*N/A","","","","","","Q4-2020"],
    [1830,1830,"SHIP CONSTRUCTION","Mayo","Barhauve, Rossport (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [1831,1831,"SHIP CONSTRUCTION","Mayo","Glaggaun, Ballycroy (SRD)",1,"*N/A","","","","","","Q4-2017"],
    [1832,1832,"SHIP CONSTRUCTION","Mayo","Glengad, Pollatomish (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [1833,1833,"SHIP CONSTRUCTION","Mayo","Gorthbrack, Inver (SRD)",1,"*N/A","","","","","","Q1-2018"],
    [1834,1834,"SHIP CONSTRUCTION","Mayo","Cross",15,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [1835,1835,"SHIP CONSTRUCTION","Mayo","Bonniconlon",5,"*N/A","","","","","Q2-2020",""],
    [1836,1836,"SHIP CONSTRUCTION","Mayo","Cloonkeadagh Road, Kiltimagh",21,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [1837,1837,"SHIP CONSTRUCTION","Mayo","Rehins Fort, Ballina",20,"*N/A","","","","","Q3-2021",""],
    [1838,1838,"SHIP CONSTRUCTION","Mayo","Murrevagh, Mulranney",14,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [1839,1839,"SHIP CONSTRUCTION","Mayo","50 Units @ Golf Course Rd., Westport",50,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [1840,1840,"SHIP CONSTRUCTION","Mayo","Ballyglass, Carnacon, Claremorris",6,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1841,1841,"SHIP CONSTRUCTION","Mayo","Lios na Circe, Saleen, Castlebar - Phase 3",14,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1842,1842,"SHIP CONSTRUCTION","Mayo","7 St. Patrick's Terrace, Westport",1,"*N/A","","","","","","Q3-2017"],
    [1843,1843,"SHIP CONSTRUCTION","Mayo","Atlantic Drive ,Belmullet",4,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1844,1844,"SHIP CONSTRUCTION","Mayo","Liskilleen, Ballinrobe,",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1845,1845,"SHIP CONSTRUCTION","Mayo","Walsh St., Ballina",8,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [1846,1846,"SHIP CONSTRUCTION","Mayo","Main Street, Ballyvary",10,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1847,1847,"SHIP CONSTRUCTION","Mayo","Rehins Fort, Foxford Rd., Ballina",30,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [1848,1848,"SHIP CONSTRUCTION","Mayo","AchilL Sound",20,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1849,1849,"CAS CONSTRUCTION","Mayo","Admiral Browne Road, Foxford (Phase 2)",4,"Society of Saint Vincent de Paul","","","","","","Q1-2018"],
    [1850,1850,"CAS CONSTRUCTION","Mayo","Killosheehan, Ballinrobe",6,"Society of Saint Vincent de Paul","","","","","","Q4-2018"],
    [1851,1851,"CAS CONSTRUCTION","Mayo","Admiral Browne Road, Foxford",8,"Society of Saint Vincent de Paul","","","","","","Q3-2016"],
    [1852,1852,"CAS CONSTRUCTION","Mayo","Logmore, Belmullet",7,"Irish Wheelchair Association Ltd","","","","","","Q2-2017"],
    [1853,1853,"CAS CONSTRUCTION","Mayo","Ellison House, Ellison St., Castlebar",8,"Peter McVerry Trust Ltd","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1854,1854,"CALF Turnkey","Mayo","Chestnut Grove, Castlebar, Co. Mayo (Phase 1)",4,"Tuath Housing Association","","","","","Q3-2020",""],
    [1855,1855,"CALF Turnkey","Mayo","Chestnut Grove, Castlebar, Co. Mayo (Phase 2)",4,"Tuath Housing Association","","","","","Q3-2020",""],
    [1856,1856,"CALF Turnkey","Mayo","Glenlara, Westport, Co Mayo  (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [1857,1857,"CALF Turnkey","Mayo","Humbert Way, Castlebar, Co. Mayo (Phase 1)",20,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2020",""],
    [1858,1858,"CALF Turnkey","Mayo","Monamore, Lodge Road, Westport, Co. Mayo (Phase 1)*",2,"Tuath Housing Association","","","","","","Q4-2019"],
    [1859,1859,"CALF Turnkey","Mayo","The Sycamores, Ballina (Phase 1)",11,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1860,1860,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin, Johnstown, Navan",19,"*N/A","","","","","","Q4-2018"],
    [1861,1861,"SHIP CONSTRUCTION TURNKEY","Meath","Cluain Adain, Clonmagadden, Navan",16,"*N/A","","","","","","Q4-2018"],
    [1862,1862,"SHIP CONSTRUCTION TURNKEY","Meath","Dun Eimear, Bettystown",8,"*N/A","","","","","","Q3-2019"],
    [1863,1863,"SHIP CONSTRUCTION TURNKEY","Meath","Bracken Hill, Kilmessan",3,"*N/A","","","","","","Q4-2019"],
    [1864,1864,"SHIP CONSTRUCTION TURNKEY","Meath","Cluain Adain, Clonmagadden, Navan",4,"*N/A","","","","","","Q3-2019"],
    [1865,1865,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin Walk, Johnstown, Navan",5,"*N/A","","","","","","Q4-2018"],
    [1866,1866,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin Walk, Johnstown, Navan",4,"*N/A","","","","","","Q3-2019"],
    [1867,1867,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin, Johnstown, Navan ",8,"*N/A","","","","","","Q2-2019"],
    [1868,1868,"SHIP CONSTRUCTION TURNKEY","Meath","Cois na Mara, Bettystown",2,"*N/A","","","","","","Q3-2019"],
    [1869,1869,"SHIP CONSTRUCTION TURNKEY","Meath","Dun Eimear, Bettystown",14,"*N/A","","","","","","Q4-2019"],
    [1870,1870,"SHIP CONSTRUCTION TURNKEY","Meath","Cherry Hill Court, Kells",2,"*N/A","","","","","","Q4-2019"],
    [1871,1871,"SHIP CONSTRUCTION TURNKEY","Meath","Broadmeadow Vale, Rathoath",2,"*N/A","","","","","","Q4-2019"],
    [1872,1872,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin, Johnstown, Navan",11,"*N/A","","","","","","Q4-2020"],
    [1873,1873,"SHIP CONSTRUCTION TURNKEY","Meath","Cluain Adain, Clonmagadden, Navan",15,"*N/A","","","","","","Q4-2020"],
    [1874,1874,"SHIP CONSTRUCTION TURNKEY","Meath","The Brambles, Longford rd., Duleek",16,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1875,1875,"SHIP CONSTRUCTION TURNKEY","Meath","26 Willow Green, Dunshaughlin",1,"*N/A","","","","","","Q3-2020"],
    [1876,1876,"SHIP CONSTRUCTION TURNKEY","Meath","Seoid na Tra, Bettytown",2,"*N/A","","","","","","Q3-2020"],
    [1877,1877,"SHIP CONSTRUCTION TURNKEY","Meath","Dun Eimear, Bettystown",1,"*N/A","","","","","","Q4-2020"],
    [1878,1878,"SHIP CONSTRUCTION TURNKEY","Meath","Connaught Street, Athboy",7,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1879,1879,"SHIP CONSTRUCTION SINGLE STAGE","Meath","Proudstown Road, Navan",4,"*N/A","","","","","","Q4-2018"],
    [1880,1880,"SHIP CONSTRUCTION SINGLE STAGE","Meath","The Belfry, Trim",3,"*N/A","","","","","","Q4-2019"],
    [1881,1881,"SHIP CONSTRUCTION SINGLE STAGE","Meath","Broville, Corballis, Laytown",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1882,1882,"SHIP CONSTRUCTION SINGLE STAGE","Meath","11 Glenidan Court, Enfield",1,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [1883,1883,"SHIP CONSTRUCTION RAPID","Meath","Kilmainhamwood",4,"*N/A","","","","","","Q4-2019"],
    [1884,1884,"SHIP CONSTRUCTION RAPID","Meath","Cortown",10,"*N/A","","","","","","Q4-2019"],
    [1885,1885,"SHIP CONSTRUCTION RAPID","Meath","Oldcastle",16,"*N/A","","","","","","Q4-2019"],
    [1886,1886,"SHIP CONSTRUCTION","Meath","Bettystown (Phase 2)",15,"*N/A","","","","","","Q4-2020"],
    [1887,1887,"SHIP CONSTRUCTION","Meath","St. Oliver's Park, Ratoath",17,"*N/A","","","","","","Q4-2019"],
    [1888,1888,"SHIP CONSTRUCTION","Meath","Riverside (Townparks), Kells",40,"*N/A","","","","","","Q4-2020"],
    [1889,1889,"SHIP CONSTRUCTION","Meath","Cherry Court, Summerhill",19,"*N/A","","","","","","Q1-2019"],
    [1890,1890,"SHIP CONSTRUCTION","Meath","Connaught Grove, Athboy",32,"*N/A","","","","","","Q2-2018"],
    [1891,1891,"SHIP CONSTRUCTION","Meath","Carlanstown",13,"*N/A","","","","","","Q4-2020"],
    [1892,1892,"SHIP CONSTRUCTION","Meath","Donore",21,"*N/A","","","","","Q4-2020",""],
    [1893,1893,"SHIP CONSTRUCTION","Meath","Dunshaughlin",26,"*N/A","","","","","Q1-2020",""],
    [1894,1894,"SHIP CONSTRUCTION","Meath","Bettystown (Phase 1)",16,"*N/A","","","","","","Q3-2017"],
    [1895,1895,"SHIP CONSTRUCTION","Meath","Farganstown, Navan",84,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [1896,1896,"SHIP CONSTRUCTION","Meath","Blackhill Crescent, Donacarney",2,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1897,1897,"SHIP CONSTRUCTION","Meath","Archdeaconary Glebe, Kells",20,"*N/A","","Stage 2 approved Q1-2020, full design/tender being prepared.","","","",""],
    [1898,1898,"SHIP CONSTRUCTION","Meath","Nangle Court, Navan",15,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1899,1899,"SHIP CONSTRUCTION","Meath","Castle Street, Ashbourne - Dept of Education Site",74,"*N/A","","Stage 2 approved Q1-2020, full design/tender being prepared.","","","",""],
    [1900,1900,"SHIP CONSTRUCTION","Meath","Church View, Rathmolyon",22,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [1901,1901,"SHIP CONSTRUCTION","Meath","Church Street, Kells, Co. Meath",3,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1902,1902,"SHIP CONSTRUCTION","Meath","Haggard Street, Trim, Co. Meath",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1903,1903,"SHIP CONSTRUCTION","Meath","Pitcher Lane, Kells, Co. Meath",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1904,1904,"SHIP CONSTRUCTION","Meath","Swan Lane, Balreask",6,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1905,1905,"SHIP CONSTRUCTION","Meath","Carrick St., Kells",43,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1906,1906,"SHIP CONSTRUCTION","Meath","Lagore, Dunshaughlin",34,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [1907,1907,"SHIP CONSTRUCTION","Meath","Convent Lands, Kildalkey, Athboy",20,"*N/A","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1908,1908,"SHIP CONSTRUCTION","Meath","Ratholdren Court, Navan",26,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [1909,1909,"CAS CONSTRUCTION TURNKEY","Meath","Bridge Street, Ashbourne, Co Meath  ",20,"Peter McVerry Trust Ltd","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [1910,1910,"CAS CONSTRUCTION TURNKEY","Meath","Gainsfield, Commons Road, Navan Co. Meath",6,"Tï¿½ath Housing Association Ltd","","","","","","Q2-2021"],
    [1911,1911,"CAS CONSTRUCTION","Meath","Blackcastle, Slane Road, Navan",17,"Tï¿½ath Housing Association Ltd","","","","","","Q4-2018"],
    [1912,1912,"CAS CONSTRUCTION","Meath","Women's Refuge, Tailteann Drive, Windtown, Navan",8,"Meath Womenï¿½s Housing Association CLG","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [1913,1913,"CAS CONSTRUCTION","Meath","Park Avenue, Oldcastle",5,"Society of Saint Vincent de Paul","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [1914,1914,"CALF Turnkey","Meath","18 units Churchfields, Ashbourne, Co. Meath (Phase 1)",18,"Tuath Housing Association","","","","","","Q4-2018"],
    [1915,1915,"CALF Turnkey","Meath","5 units Dunville, Athlumney, Navan, Co. Meath (Phase 1)",5,"Tuath Housing Association","","","","","","Q1-2019"],
    [1916,1916,"CALF Turnkey","Meath","6 Units Seabury Lawns, Mornington, Co Meath (Phase 1)",6,"Clï¿½id Housing","","","","","","Q1-2018"],
    [1917,1917,"CALF Turnkey","Meath","Applewood Court, Beaufort Place, Navan, Co. Meath (Phase 1)",6,"Tuath Housing Association","","","","","Q3-2020",""],
    [1918,1918,"CALF Turnkey","Meath","Applewood Court, Beaufort Place, Navan, Co. Meath (Phase 2)*",15,"Tuath Housing Association","","","","","Q3-2020",""],
    [1919,1919,"CALF Turnkey","Meath","Ardmore Rise, Bettystown, Co Meath  (Phase 1)",1,"North & East Housing Association Ltd","","","","","","Q4-2018"],
    [1920,1920,"CALF Turnkey","Meath","Ashewood, Ashbourne, Co Meath (Phase 1)",11,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1921,1921,"CALF Turnkey","Meath","Athboy Road, Navan, Co. Meath (Phase 1)*",63,"Respond","","","","","Q1-2020",""],
    [1922,1922,"CALF Turnkey","Meath","Blackcastle, Slane Road, Navan, Co. Meath (Phase 1)",9,"Tuath Housing Association","","","","","","Q4-2018"],
    [1923,1923,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 1)*",1,"Tuath Housing Association","","","","","","Q2-2019"],
    [1924,1924,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 2)*",1,"Tuath Housing Association","","","","","","Q2-2019"],
    [1925,1925,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 3)*",10,"Tuath Housing Association","","","","","","Q4-2019"],
    [1926,1926,"CALF Turnkey","Meath","Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 1)*",24,"Tuath Housing Association","","","","","Q1-2021",""],
    [1927,1927,"CALF Turnkey","Meath","Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 2)*",4,"Tuath Housing Association","","","","","Q1-2021",""],
    [1928,1928,"CALF Turnkey","Meath","Ceamach Close, Donacarney, Co Meath  (Phase 1)",7,"Clï¿½id Housing","","","","","","Q2-2018"],
    [1929,1929,"CALF Turnkey","Meath","Ceamach Close, Donacarney, Co Meath  (Phase 2)*",9,"Clï¿½id Housing","","","","","","Q3-2018"],
    [1930,1930,"CALF Turnkey","Meath","Cherryvalley, Rathmoylan, Co Meath (Phase 1)",9,"Clï¿½id Housing","","","","","","Q4-2017"],
    [1931,1931,"CALF Turnkey","Meath","Churchfields, Ashbourne, Co Meath (Phase 1)*",8,"Tuath Housing Association","","","","","","Q2-2017"],
    [1932,1932,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 1)*",10,"Tuath Housing Association","","","","","","Q4-2018"],
    [1933,1933,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 2)*",3,"Tuath Housing Association","","","","","","Q2-2019"],
    [1934,1934,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 3)*",12,"Tuath Housing Association","","","","","","Q4-2019"],
    [1935,1935,"CALF Turnkey","Meath","Commons Road, Navan, Co Meath  (Phase 1)",12,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1936,1936,"CALF Turnkey","Meath","Commons, Duleek, Co. Meath (Phase 1)*",22,"North & East Housing Association Ltd","","","","","Q1-2021",""],
    [1937,1937,"CALF Turnkey","Meath","Dun Eimear, Bettystown, Co. Meath (Phase 1)*",12,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1938,1938,"CALF Turnkey","Meath","Dun Eimear, Bettystown, Co. Meath (Phase 2)*",11,"Clï¿½id Housing","","","","","","Q4-2019"],
    [1939,1939,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 1)",10,"Tuath Housing Association","","","","","","Q1-2018"],
    [1940,1940,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 2)*",8,"Tuath Housing Association","","","","","","Q1-2018"],
    [1941,1941,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 3)*",10,"Tuath Housing Association","","","","","","Q2-2018"],
    [1942,1942,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 4)*",6,"Tuath Housing Association","","","","","","Q2-2018"],
    [1943,1943,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 5)*",18,"Tuath Housing Association","","","","","","Q2-2018"],
    [1944,1944,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 6)",12,"Tuath Housing Association","","","","","","Q3-2018"],
    [1945,1945,"CALF Turnkey","Meath","Eastham Square, Bettystown, Meath (Phase 1)*",5,"Clï¿½id Housing","","","","","","Q1-2019"],
    [1946,1946,"CALF Turnkey","Meath","Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)*",1,"Tuath Housing Association","","","","","","Q3-2018"],
    [1947,1947,"CALF Turnkey","Meath","Frederick Manor, Ashbourne, Co. Meath (Phase 1)*",11,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1948,1948,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 1)",20,"Tuath Housing Association","","","","","","Q4-2019"],
    [1949,1949,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 2)",18,"Tuath Housing Association","","","","","","Q4-2020"],
    [1950,1950,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 3)",7,"Tuath Housing Association","","","","","","Q1-2021"],
    [1951,1951,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 4)",9,"Tuath Housing Association","","","","","","Q2-2021"],
    [1952,1952,"CALF Turnkey","Meath","Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 1)",19,"Tuath Housing Association","","","","","Q4-2020",""],
    [1953,1953,"CALF Turnkey","Meath","Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 2)",15,"Tuath Housing Association","","","","","Q4-2020",""],
    [1954,1954,"CALF Turnkey","Meath","Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 3)",15,"Tuath Housing Association","","","","","Q4-2020",""],
    [1955,1955,"CALF Turnkey","Meath","Grangehall, Dunshaughlin (Phase 1)",7,"Tuath Housing Association","","","","","","Q2-2018"],
    [1956,1956,"CALF Turnkey","Meath","Kellets Grove, Dunshauglin, Co Meath  (Phase 1)*",6,"Tuath Housing Association","","","","","","Q1-2018"],
    [1957,1957,"CALF Turnkey","Meath","Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 1)",5,"Tuath Housing Association","","","","","","Q3-2021"],
    [1958,1958,"CALF Turnkey","Meath","Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 2)",5,"Tuath Housing Association","","","","","","Q3-2021"],
    [1959,1959,"CALF Turnkey","Meath","Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 3)",6,"Tuath Housing Association","","","","","Q3-2020",""],
    [1960,1960,"CALF Turnkey","Meath","Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 1)*",11,"Tuath Housing Association","","","","","Q3-2021",""],
    [1961,1961,"CALF Turnkey","Meath","Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 2)*",11,"Tuath Housing Association","","","","","Q3-2021",""],
    [1962,1962,"CALF Turnkey","Meath","Maudelins Brook, Duleek, Co.Meath (Phase 1)*",20,"Respond","","","","","","Q4-2019"],
    [1963,1963,"CALF Turnkey","Meath","Maydenhayes, Donacarney, Co. Meath (Phase 1)*",12,"Clï¿½id Housing","","","","","","Q3-2021"],
    [1964,1964,"CALF Turnkey","Meath","Mill Lane, Flower Hill, Navan, Co Meath (Phase 1)",20,"Oaklee Housing","","","","","","Q4-2016"],
    [1965,1965,"CALF Turnkey","Meath","Millrace Court, Emmet Street, Trim, Co Meath  (Phase 1)",11,"North & East Housing Association Ltd","","","","","","Q2-2018"],
    [1966,1966,"CALF Turnkey","Meath","Millteog, Athboy Road, Trim, Co. Meath (Phase 1)*",16,"Oaklee Housing","","","","","","Q4-2019"],
    [1967,1967,"CALF Turnkey","Meath","Millteog, Athboy Road, Trim, Co. Meath (Phase 2)*",9,"Oaklee Housing","","","","","","Q2-2020"],
    [1968,1968,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 1)",11,"Clï¿½id Housing","","","","","","Q1-2017"],
    [1969,1969,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 2)",36,"Clï¿½id Housing","","","","","","Q4-2017"],
    [1970,1970,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 3)",20,"Clï¿½id Housing","","","","","","Q4-2017"],
    [1971,1971,"CALF Turnkey","Meath","Moydervey Manor, Longwood, Trim, Co. Meath (Phase 1)*",13,"Tuath Housing Association","","","","","","Q4-2020"],
    [1972,1972,"CALF Turnkey","Meath","Narrow Ways, Bettystown, Co. Meath (Phase 1)",6,"Tuath Housing Association","","","","","Q2-2021",""],
    [1973,1973,"CALF Turnkey","Meath","Narrow Ways, Bettystown, Co. Meath (Phase 2)",6,"Tuath Housing Association","","","","","Q2-2021",""],
    [1974,1974,"CALF Turnkey","Meath","Oldbridge Manor, Drogheda, Co. Meath (Phase 1)*",29,"Tuath Housing Association","","","","","","Q4-2020"],
    [1975,1975,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)",3,"Tuath Housing Association","","","","","","Q4-2018"],
    [1976,1976,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 10)",5,"Tuath Housing Association","","","","","","Q4-2020"],
    [1977,1977,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 2)",6,"Tuath Housing Association","","","","","","Q2-2019"],
    [1978,1978,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 3)",2,"Tuath Housing Association","","","","","","Q3-2019"],
    [1979,1979,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 4)",5,"Tuath Housing Association","","","","","","Q3-2019"],
    [1980,1980,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 5)",4,"Tuath Housing Association","","","","","","Q4-2019"],
    [1981,1981,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 6)",6,"Tuath Housing Association","","","","","","Q1-2020"],
    [1982,1982,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 7)",3,"Tuath Housing Association","","","","","","Q1-2020"],
    [1983,1983,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 8)",4,"Tuath Housing Association","","","","","","Q3-2020"],
    [1984,1984,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 9)",6,"Tuath Housing Association","","","","","","Q3-2020"],
    [1985,1985,"CALF Turnkey","Meath","Royal Oaks, Enfield, Co Meath (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q2-2017"],
    [1986,1986,"CALF Turnkey","Meath","Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q4-2020"],
    [1987,1987,"CALF Turnkey","Meath","Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 2)*",14,"Clï¿½id Housing","","","","","","Q2-2021"],
    [1988,1988,"CALF Turnkey","Meath","Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 3)",16,"Clï¿½id Housing","","","","","Q4-2019",""],
    [1989,1989,"CALF Turnkey","Meath","Ruxton Oaks, Navan, Co. Meath (Phase 1)*",8,"Clï¿½id Housing","","","","","Q1-2021",""],
    [1990,1990,"CALF Turnkey","Meath","Ruxton Oaks, Navan, Co. Meath (Phase 2)*",12,"Clï¿½id Housing","","","","","Q1-2021",""],
    [1991,1991,"CALF Turnkey","Meath","Seabury Lawns, Mornington, Co. Meath (Phase 1)",25,"Clï¿½id Housing","","","","","","Q3-2017"],
    [1992,1992,"CALF Turnkey","Meath","St Marys Dunboyne, Co. Meath (Phase 1)",16,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2021"],
    [1993,1993,"CALF Turnkey","Meath","Station Road, Dunboyne, Co. Meath (Phase 1)",24,"Respond","","","","","","Q4-2018"],
    [1994,1994,"CALF Turnkey","Meath","The Bungalows, Dunshauglin, Co. Meath (Phase 1)*",8,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2020"],
    [1995,1995,"CALF Turnkey","Meath","The Maudelins (Phase 2), Main Street, Duleek, Co. Meath (Phase 1)*",30,"Respond","","","","","","Q4-2020"],
    [1996,1996,"CALF Turnkey","Meath","The Maudlins, Trim, Co. Meath (Phase 1)",9,"Clï¿½id Housing","","","","","","Q1-2021"],
    [1997,1997,"CALF Turnkey","Meath","The Way, Broadmeadow Vale, Ratoath, Co. Meath (Phase 1)",2,"Tuath Housing Association","","","","","","Q4-2019"],
    [1998,1998,"CALF Turnkey","Meath","The Willows, Dunshaughlin, Co. Meath (Phase 1)*",96,"Clï¿½id Housing","","","","","Q2-2021",""],
    [1999,1999,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 1)",8,"Clï¿½id Housing","","","","","","Q2-2016"],
    [2000,2000,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 2)",7,"Clï¿½id Housing","","","","","","Q3-2016"],
    [2001,2001,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 3)",8,"Clï¿½id Housing","","","","","","Q4-2016"],
    [2002,2002,"CALF Turnkey","Meath","Whitefield Hall, Bettystown, Co. Meath (Phase 1)",14,"Tuath Housing Association","","","","","","Q2-2020"],
    [2003,2003,"CALF Turnkey","Meath","Whitefield Hall, Bettystown, Co. Meath (Phase 2)",13,"Tuath Housing Association","","","","","","Q3-2020"],
    [2004,2004,"CALF Turnkey","Meath","Whitefield Hall, Bettystown, Co. Meath (Phase 3)",2,"Tuath Housing Association","","","","","","Q3-2021"],
    [2005,2005,"SHIP CONSTRUCTION TURNKEY","Monaghan","Drumbear Wood, Monaghan Town",12,"*N/A","","","","","","Q4-2017"],
    [2006,2006,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town",6,"*N/A","","","","","","Q4-2017"],
    [2007,2007,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town (Phase 2)",8,"*N/A","","","","","","Q2-2017"],
    [2008,2008,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town (Phase 1)",8,"*N/A","","","","","","Q2-2017"],
    [2009,2009,"SHIP CONSTRUCTION TURNKEY","Monaghan","Killycard, Bree, Castleblaney",4,"*N/A","","","","","","Q2-2019"],
    [2010,2010,"SHIP CONSTRUCTION TURNKEY","Monaghan","The Meadows, Smithborough",5,"*N/A","","","","","","Q4-2017"],
    [2011,2011,"SHIP CONSTRUCTION TURNKEY","Monaghan","Maple Grove, Smithborough",11,"*N/A","","","","","","Q4-2018"],
    [2012,2012,"SHIP CONSTRUCTION TURNKEY","Monaghan","Plï¿½s an Bhrï¿½, Rosevale, Bree, Castleblayney",26,"*N/A","","","","","","Q4-2020"],
    [2013,2013,"SHIP CONSTRUCTION TURNKEY","Monaghan","Ard na Radhairc, Carrickmacross, Co. Monaghan",41,"*N/A","","","","","Q3-2019",""],
    [2014,2014,"SHIP CONSTRUCTION TURNKEY","Monaghan","Coill an Ri, Carrickmacross",6,"*N/A","","","","","","Q4-2020"],
    [2015,2015,"SHIP CONSTRUCTION TURNKEY","Monaghan","The Meadows, Smithborough",5,"*N/A","","","","","","Q3-2019"],
    [2016,2016,"SHIP CONSTRUCTION TURNKEY","Monaghan","Drummond Radhairc, Carrickmacross",1,"*N/A","","","","","","Q3-2019"],
    [2017,2017,"SHIP CONSTRUCTION TURNKEY","Monaghan","Cnoc na Greine, Tydavnet",6,"*N/A","","","","","","Q4-2020"],
    [2018,2018,"SHIP CONSTRUCTION TURNKEY","Monaghan","Coill Darach, Bree, Castleblayney",30,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [2019,2019,"SHIP CONSTRUCTION TURNKEY","Monaghan","Coill an Ri, Carrickmacross",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [2020,2020,"SHIP CONSTRUCTION TURNKEY","Monaghan","Coill an Ri, Carrickmacross",30,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2021,2021,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockcarrick, Annyalla",30,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2022,2022,"SHIP CONSTRUCTION SINGLE STAGE","Monaghan","Folly Court, Ballybay",6,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2023,2023,"SHIP CONSTRUCTION","Monaghan","Bree, Castleblayney",8,"*N/A","","","","","","Q2-2019"],
    [2024,2024,"SHIP CONSTRUCTION","Monaghan","Latlorcan, Monaghan Town",43,"*N/A","","","","","","Q4-2019"],
    [2025,2025,"SHIP CONSTRUCTION","Monaghan","Fermanagh St., Clones",3,"*N/A","","","","","","Q4-2020"],
    [2026,2026,"SHIP CONSTRUCTION","Monaghan","Fermanagh St., Clones",3,"*N/A","","","","","","Q4-2020"],
    [2027,2027,"SHIP CONSTRUCTION","Monaghan","Fermanagh St., Clones",3,"*N/A","","","","","Q3-2019",""],
    [2028,2028,"SHIP CONSTRUCTION","Monaghan","Fermanagh St., Clones",6,"*N/A","","","","","Q3-2019",""],
    [2029,2029,"SHIP CONSTRUCTION","Monaghan","2a & 3 Analore St., Clones",2,"*N/A","","","","","Q3-2019",""],
    [2030,2030,"SHIP CONSTRUCTION","Monaghan","Abbey Gatehouse, Analore St., Clones",4,"*N/A","","","","","Q3-2019",""],
    [2031,2031,"SHIP CONSTRUCTION","Monaghan","Lui Na Greine, Scotstown",6,"*N/A","","","","","Q2-2020",""],
    [2032,2032,"SHIP CONSTRUCTION","Monaghan","Latlorcan, Monaghan",16,"*N/A","","","","","","Q4-2018"],
    [2033,2033,"SHIP CONSTRUCTION","Monaghan","12 Church St., Ballybay",2,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2034,2034,"SHIP CONSTRUCTION","Monaghan","Fermanagh St., Clones",3,"*N/A","","","","","Q1-2020",""],
    [2035,2035,"SHIP CONSTRUCTION","Monaghan","Church Hill, Clones",2,"*N/A","","","","","Q2-2021",""],
    [2036,2036,"SHIP CONSTRUCTION","Monaghan","13 McCurtain Street, Clones",1,"*N/A","","","","","Q1-2021",""],
    [2037,2037,"SHIP CONSTRUCTION","Monaghan","Lui na Greine, Scotstown",26,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [2038,2038,"SHIP CONSTRUCTION","Monaghan","Ballybay Courtyard, Ballybay",7,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2039,2039,"CAS CONSTRUCTION","Monaghan","Drumillard, Castleblayney (Phase 2)",2,"Castleblayney Care Housing Association Ltd","","","","","Q1-2021",""],
    [2040,2040,"CAS CONSTRUCTION","Monaghan","Liseggerton, Clones",19,"Oaklee Housing Trust","","","","","","Q2-2021"],
    [2041,2041,"CAS CONSTRUCTION","Monaghan","Convent Lands, Carrickmacross",7,"Respond","","","","","","Q2-2017"],
    [2042,2042,"CAS CONSTRUCTION","Monaghan","Birch Court Apts., 34 Main Street, Ballybay",4,"North ? East Housing Association Ltd","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2043,2043,"CALF Turnkey","Monaghan","Bree, Castleblayney \\n (Phase 1)",11,"Tuath Housing Association","","","","","","Q4-2020"],
    [2044,2044,"CALF Turnkey","Monaghan","Bree, Castleblayney \\n (Phase 2)",6,"Tuath Housing Association","","","","","","Q2-2021"],
    [2045,2045,"CALF Turnkey","Monaghan","Bree, Castleblayney \\n (Phase 3)",8,"Tuath Housing Association","","","","","","Q3-2021"],
    [2046,2046,"CALF Turnkey","Monaghan","Bree, Castleblayney \\n (Phase 4)",13,"Tuath Housing Association","","","","","Q2-2019",""],
    [2047,2047,"CALF Turnkey","Monaghan","Kingscourt Road, Carrickmacross, Co Monaghan  (Phase 1)",50,"Respond","","","","","","Q4-2019"],
    [2048,2048,"CALF Turnkey","Monaghan","Lakeview Apartments, Drummond Radhairc, Carrickmacross, Co Monaghan (Phase 1)*",12,"North & East Housing Association Ltd","","","","","Q3-2019",""],
    [2049,2049,"CALF Turnkey","Monaghan","Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 1)*",20,"Tuath Housing Association","","","","Q2-2021","",""],
    [2050,2050,"CALF Turnkey","Monaghan","Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 2)*",21,"Tuath Housing Association","","","","Q2-2021","",""],
    [2051,2051,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 1)",7,"Tuath Housing Association","","","","","","Q2-2021"],
    [2052,2052,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 2)",6,"Tuath Housing Association","","","","","Q3-2019",""],
    [2053,2053,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 3)",6,"Tuath Housing Association","","","","","Q3-2019",""],
    [2054,2054,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 4)",14,"Tuath Housing Association","","","","","Q3-2019",""],
    [2055,2055,"CALF Construction","Monaghan","Post Tender - Liseggerton Road, Clones (Phase 1)",6,"Oaklee Housing","","","","","","Q4-2018"],
    [2056,2056,"CALF Turnkey","Monaghan","Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 1)",8,"Tuath Housing Association","","","","","Q3-2020",""],
    [2057,2057,"CALF Turnkey","Monaghan","Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 2)*",8,"Tuath Housing Association","","","","","Q3-2020",""],
    [2058,2058,"CALF Turnkey","Monaghan","The Meadows, Emy, Emyvale, Co. Monaghan (Phase 1)*",7,"Tuath Housing Association","","","","","Q2-2021",""],
    [2059,2059,"CALF Turnkey","Monaghan","The Meadows, Emy, Emyvale, Co. Monaghan (Phase 2)",7,"Tuath Housing Association","","","","","Q2-2021",""],
    [2060,2060,"SHIP CONSTRUCTION TURNKEY","Offaly","MacRegol Pairc, Birr",2,"*N/A","","","","","","Q3-2020"],
    [2061,2061,"SHIP CONSTRUCTION TURNKEY","Offaly","Mill Race, Ferbane",5,"*N/A","","","","","","Q4-2017"],
    [2062,2062,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Spideoga, Cloghan",6,"*N/A","","","","","","Q2-2019"],
    [2063,2063,"SHIP CONSTRUCTION TURNKEY","Offaly","Frankford, Kilcormac",12,"*N/A","","","","","","Q4-2018"],
    [2064,2064,"SHIP CONSTRUCTION TURNKEY","Offaly","MacRegol Pairc, Birr",4,"*N/A","","","","","","Q4-2019"],
    [2065,2065,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Greine, Cloneygowan",4,"*N/A","","","","","","Q4-2019"],
    [2066,2066,"SHIP CONSTRUCTION TURNKEY","Offaly","Main Street, Daingean",8,"*N/A","","","","","Q4-2020",""],
    [2067,2067,"SHIP CONSTRUCTION TURNKEY","Offaly","McCauley Drive, Birr",34,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2068,2068,"SHIP CONSTRUCTION TURNKEY","Offaly","Riverside, Tullamore",5,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2069,2069,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Greine, Clonygowan",2,"*N/A","","","","","","Q2-2021"],
    [2070,2070,"SHIP CONSTRUCTION TURNKEY","Offaly","Coolgarry, Walsh Island ",4,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2071,2071,"SHIP CONSTRUCTION TURNKEY","Offaly","Mucklagh, Tullamore",8,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2072,2072,"SHIP CONSTRUCTION TURNKEY","Offaly","MacRegol Pairc, Birr",2,"*N/A","","","","","","Q1-2021"],
    [2073,2073,"SHIP CONSTRUCTION TURNKEY","Offaly","Bog Road, Portarlington",28,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2074,2074,"SHIP CONSTRUCTION TURNKEY","Offaly","MacRegol Pairc, Birr",4,"*N/A","","","","","","Q2-2021"],
    [2075,2075,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Greine, Clonygowan",1,"*N/A","","","","Stage 4 approved Q4-2020, the scheme is fully approved.","",""],
    [2076,2076,"SHIP CONSTRUCTION SINGLE STAGE","Offaly","78 & 110 Church Hill, Tullamore",2,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2077,2077,"SHIP CONSTRUCTION","Offaly","Chancery Lane, Tullamore",14,"*N/A","","","","","","Q3-2020"],
    [2078,2078,"SHIP CONSTRUCTION","Offaly","Circular Road, Daingean",9,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [2079,2079,"SHIP CONSTRUCTION","Offaly","Kylebeg, Banagher (Phase 2)",18,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2080,2080,"SHIP CONSTRUCTION","Offaly","Blundell Wood, Edenderry",33,"*N/A","","","","","","Q4-2019"],
    [2081,2081,"SHIP CONSTRUCTION","Offaly","Beechgrove, Belmont",7,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [2082,2082,"SHIP CONSTRUCTION","Offaly","Raheen ,Clara",38,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2083,2083,"SHIP CONSTRUCTION","Offaly","Elderberry Drive, Moneygall",4,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [2084,2084,"SHIP CONSTRUCTION","Offaly","Sr. Senan Avenue, Edenderry",4,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2085,2085,"SHIP CONSTRUCTION","Offaly","Dargan Drive, Chancery Lane, Tullamore (Phase 2)",20,"*N/A","Stage 1 approved Q1-2020, outline design and costs being prepared.","","","","",""],
    [2086,2086,"SHIP CONSTRUCTION","Offaly","1 Newbridge St., Birr",1,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2087,2087,"SHIP CONSTRUCTION","Offaly","Sycamore Drive, Ballycumber",8,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2088,2088,"SHIP CONSTRUCTION","Offaly","Circular Road, Daingean Phase 2",9,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2089,2089,"CAS CONSTRUCTION","Offaly","Mountbolus",4,"Mid Offaly Housing Association Ltd","","","","","","Q4-2019"],
    [2090,2090,"CAS CONSTRUCTION","Offaly","Killane Court, Edenderry",2,"Tï¿½ath Housing Association Ltd","","","","","","Q2-2021"],
    [2091,2091,"CAS CONSTRUCTION","Offaly","Scurragh, Birr (AKA Camcor Green)",6,"Cluid Housing Association","","","","","","Q4-2019"],
    [2092,2092,"CAS CONSTRUCTION","Offaly","Clonminch, Tullamore",19,"Oaklee Housing Trust","","","","","Q1-2021",""],
    [2093,2093,"CAS CONSTRUCTION","Offaly","Presentation Convent, Portarlington",39,"Sophia Housing Association Ltd","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2094,2094,"CAS CONSTRUCTION","Offaly","Clonamore Hotel, Tullamore",17,"Sophia Housing Association Ltd","Stage 1 approved Q2-2020, outline design and costs being prepared.","","","","",""],
    [2095,2095,"CALF Turnkey","Offaly","3 units, An Corran, Crinkle, Birr, Co. Offaly (Phase 1)",3,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2021"],
    [2096,2096,"CALF Construction","Offaly","Kearneyï¿½s Field, Tullamore, Co. Offaly (Phase 1)",41,"Oaklee Housing","","","","","Q2-2021",""],
    [2097,2097,"CALF Construction","Offaly","Killane Drive, Edenderry, Co Offaly (Phase 1)",25,"Tuath Housing Association","","","","","","Q2-2021"],
    [2098,2098,"CALF Turnkey","Offaly","Rahan Road, Tullamore, Co. Offaly (Phase 1)*",26,"Clï¿½id Housing","","","","","Q4-2020",""],
    [2099,2099,"CALF Turnkey","Offaly","The Hawthorns, Arden Road, Tullamore, Co. Offaly (Phase 1)",16,"Clï¿½id Housing","","","","","Q1-2020",""],
    [2100,2100,"SHIP CONSTRUCTION TURNKEY","Roscommon","Monksland, Athlone",10,"*N/A","","","","","","Q3-2018"],
    [2101,2101,"SHIP CONSTRUCTION TURNKEY","Roscommon","Station Road, Termon, Boyle",10,"*N/A","","","","","","Q1-2019"],
    [2102,2102,"SHIP CONSTRUCTION TURNKEY","Roscommon","Lisroyne Court, Strokestown",10,"*N/A","","","","","","Q4-2019"],
    [2103,2103,"SHIP CONSTRUCTION TURNKEY","Roscommon","Warren Grove, Boyle",4,"*N/A","","","","","","Q4-2018"],
    [2104,2104,"SHIP CONSTRUCTION TURNKEY","Roscommon","Monksfield, Monksland",2,"*N/A","","","","","","Q4-2020"],
    [2105,2105,"SHIP CONSTRUCTION","Roscommon","Cloonfad",3,"*N/A","","","","","","Q2-2021"],
    [2106,2106,"SHIP CONSTRUCTION","Roscommon","Greenfields, Blackstick Road, Roscommon Town",6,"*N/A","","","","","","Q3-2017"],
    [2107,2107,"SHIP CONSTRUCTION","Roscommon","River Oaks, Ballaghaderreen",10,"*N/A","","","","","","Q4-2017"],
    [2108,2108,"SHIP CONSTRUCTION","Roscommon","Silveroe Meadows, Boyle",12,"*N/A","","","","","","Q4-2020"],
    [2109,2109,"SHIP CONSTRUCTION","Roscommon","Cluain Fraoigh, Cloonbeirne",7,"*N/A","","","","","","Q1-2021"],
    [2110,2110,"SHIP CONSTRUCTION","Roscommon","Old Tuam Road,  Monksland, Athlone",2,"*N/A","","","","","","Q4-2020"],
    [2111,2111,"SHIP CONSTRUCTION","Roscommon","Meadowbrook, Ballyclare Td., Ballyleague",16,"*N/A","","","","","Q3-2020",""],
    [2112,2112,"SHIP CONSTRUCTION","Roscommon","Lisroyne Td., Strokestown",10,"*N/A","","","","","Q4-2020",""],
    [2113,2113,"SHIP CONSTRUCTION","Roscommon","Windmill Road, Elphin Road",10,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2114,2114,"SHIP CONSTRUCTION","Roscommon","Lakeview Heights, Bellspark Td., Boyle",6,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2115,2115,"SHIP CONSTRUCTION","Roscommon","Lisnamult, Ardnanagh Td., Roscommon Town",8,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [2116,2116,"CALF Turnkey","Roscommon","Castle View Apartments, Block B, Roscommon Town (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [2117,2117,"CALF Turnkey","Roscommon","Monksland, Athlone, Co. Roscommon (Phase 1)*",35,"Tuath Housing Association","","","","","Q4-2019",""],
    [2118,2118,"CALF Turnkey","Roscommon","Revised - Monksfield Park, Bealnamulla, Athlone (Phase 1)",13,"Clï¿½id Housing","","","","","","Q3-2018"],
    [2119,2119,"CALF Turnkey","Roscommon","River Oaks, Kilcolman, Ballaghaderreen, Co. Roscommon (Phase 1)",12,"Respond","","","","","","Q1-2018"],
    [2120,2120,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Roscommon","The Walk, Roscommon Town",53,"*N/A","","","","","","Q2-2021"],
    [2121,2121,"SHIP CONSTRUCTION TURNKEY","Sligo","Fairgreen Square, Ballisodare",2,"*N/A","","","","","","Q4-2019"],
    [2122,2122,"SHIP CONSTRUCTION TURNKEY","Sligo","Ursuline Convent",14,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2123,2123,"SHIP CONSTRUCTION TURNKEY","Sligo","Ursuline Convent",16,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2124,2124,"SHIP CONSTRUCTION TURNKEY","Sligo","Ursuline Convent",30,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2125,2125,"SHIP CONSTRUCTION TURNKEY","Sligo","Ursuline Convent",13,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2126,2126,"SHIP CONSTRUCTION SINGLE STAGE","Sligo","St. Joseph's Terrace, Sligo",1,"*N/A","","","","","","Q4-2019"],
    [2127,2127,"SHIP CONSTRUCTION","Sligo","Collooney",18,"*N/A","","","","","","Q4-2019"],
    [2128,2128,"SHIP CONSTRUCTION","Sligo","Knappagh Road, Sligo",28,"*N/A","","","","","","Q4-2020"],
    [2129,2129,"SHIP CONSTRUCTION","Sligo","Caltragh, Culleens",1,"*N/A","","","","","","Q4-2018"],
    [2130,2130,"SHIP CONSTRUCTION","Sligo","Fr. Flanagan Terrace",14,"*N/A","","","","","","Q3-2018"],
    [2131,2131,"SHIP CONSTRUCTION","Sligo","Daghloonagh, Keash - SRD",1,"*N/A","","","","","","Q4-2016"],
    [2132,2132,"SHIP CONSTRUCTION","Sligo","Rosses Point",14,"*N/A","","","","","","Q4-2019"],
    [2133,2133,"SHIP CONSTRUCTION","Sligo","Fr. Flanagan Terrace",8,"*N/A","","","","","","Q4-2017"],
    [2134,2134,"SHIP CONSTRUCTION","Sligo","Connolly Park, Tubbercurry (Phase 1)",10,"*N/A","","","","","Q3-2020",""],
    [2135,2135,"SHIP CONSTRUCTION","Sligo","Dromore West",10,"*N/A","","","","","Q4-2019",""],
    [2136,2136,"SHIP CONSTRUCTION","Sligo","Robbers' Lane, Maugheraboy, Sligo",62,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2137,2137,"SHIP CONSTRUCTION","Sligo","House at Ballinode",1,"*N/A","","","","","","Q4-2018"],
    [2138,2138,"SHIP CONSTRUCTION","Sligo","SRD at Crowagh, Dromore West",1,"*N/A","","","","","Q4-2020",""],
    [2139,2139,"SHIP CONSTRUCTION","Sligo","Gormley Park, Bunnanadden",6,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [2140,2140,"SHIP CONSTRUCTION","Sligo","Connolly Park, Tubbercurry (Phase 2) & The Green Rd,",19,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2141,2141,"CAS CONSTRUCTION","Sligo","Cuan Iosa, Ballymote",8,"Society of Saint Vincent de Paul","","","","","","Q3-2020"],
    [2142,2142,"CAS CONSTRUCTION","Sligo","Killeshin, First Sea Road, Sligo",5,"Newgrove Housing Association Ltd","","","","","Q4-2020",""],
    [2143,2143,"SHIP CONSTRUCTION TURNKEY","South Dublin","Ardsolus, Kingswood, Dublin 24",2,"*N/A","","","","","","Q4-2018"],
    [2144,2144,"SHIP CONSTRUCTION TURNKEY","South Dublin","White Pines, Stocking Avenue, Rathfarnham, Dublin 16",26,"*N/A","","","","","","Q4-2018"],
    [2145,2145,"SHIP CONSTRUCTION TURNKEY","South Dublin","Shackleton Park / Gandon Park, Adamstown",22,"*N/A","","","","","","Q4-2019"],
    [2146,2146,"SHIP CONSTRUCTION TURNKEY","South Dublin","Gandon Park, Adamstown, Lucan",12,"*N/A","","","","","","Q4-2019"],
    [2147,2147,"SHIP CONSTRUCTION SINGLE STAGE","South Dublin","37 Greenfort Gardens, Clondalkin",2,"*N/A","","","","","Q4-2020",""],
    [2148,2148,"SHIP CONSTRUCTION RAPID","South Dublin","Killininny Road, Firhouse (Old Mill, Old Bawn)",24,"*N/A","","","","","","Q4-2018"],
    [2149,2149,"SHIP CONSTRUCTION RAPID","South Dublin","St Cuthbert's, Clondalkin (Phase 1)",63,"*N/A","","","","","","Q3-2019"],
    [2150,2150,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght",47,"*N/A","","","","","","Q2-2018"],
    [2151,2151,"SHIP CONSTRUCTION RAPID","South Dublin","St. Marks Avenue, Clondalkin",41,"*N/A","","","","","Q3-2020",""],
    [2152,2152,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght",22,"*N/A","","","","","","Q3-2018"],
    [2153,2153,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght",21,"*N/A","","","","","","Q4-2018"],
    [2154,2154,"SHIP CONSTRUCTION RAPID","South Dublin","Riversdale, Clondalkin, Dublin 22",22,"*N/A","","","","","Q4-2020",""],
    [2155,2155,"SHIP CONSTRUCTION RAPID","South Dublin","Riverside Cottages, Templeogue",10,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2156,2156,"SHIP CONSTRUCTION RAPID","South Dublin","Riversdale, Clondalkin, Dublin 22",21,"*N/A","","","","","Q4-2020",""],
    [2157,2157,"SHIP CONSTRUCTION","South Dublin","Killinarden, Tallaght",17,"*N/A","","","","","","Q4-2018"],
    [2158,2158,"SHIP CONSTRUCTION","South Dublin","Letts Field, Neilstown, Clondalkin",37,"*N/A","","","","","","Q4-2018"],
    [2159,2159,"SHIP CONSTRUCTION","South Dublin","Owendoher, Ballyboden,  Rathfarnham",40,"*N/A","","","","","","Q1-2019"],
    [2160,2160,"SHIP CONSTRUCTION","South Dublin","Dromcarra, Tallaght",14,"*N/A","","","","","","Q4-2018"],
    [2161,2161,"SHIP CONSTRUCTION","South Dublin","Fortunestown (MacUilliam)",28,"*N/A","","","","","","Q4-2018"],
    [2162,2162,"SHIP CONSTRUCTION","South Dublin","Mayfield Estate, Clondalkin",17,"*N/A","","","","","","Q2-2018"],
    [2163,2163,"SHIP CONSTRUCTION","South Dublin","St Marks Green, Clondalkin",11,"*N/A","","","","","","Q3-2018"],
    [2164,2164,"SHIP CONSTRUCTION","South Dublin","Balgaddy F, Griffeen Avenue, Lucan Co. Dublin",69,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [2165,2165,"SHIP CONSTRUCTION","South Dublin","St Finians",2,"*N/A","","","","","","Q3-2016"],
    [2166,2166,"SHIP CONSTRUCTION","South Dublin","Suncroft, Tallaght",10,"*N/A","","","","","","Q4-2016"],
    [2167,2167,"SHIP CONSTRUCTION","South Dublin","Belgard Road",3,"*N/A","","","","","","Q1-2016"],
    [2168,2168,"SHIP CONSTRUCTION","South Dublin","St. Catherineï¿½s, Knockmore Avenue, Killinarden, Tallaght",12,"*N/A","","","","","Q4-2020",""],
    [2169,2169,"SHIP CONSTRUCTION","South Dublin","Homeville, Knocklyon, Dublin 16",16,"*N/A","","","","","Q4-2020",""],
    [2170,2170,"SHIP CONSTRUCTION","South Dublin","Killinarden, Tallaght",9,"*N/A","","","","","","Q1-2019"],
    [2171,2171,"SHIP CONSTRUCTION","South Dublin","Nangor Road, Clondalkin, Dublin 22",93,"*N/A","","","Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.","","",""],
    [2172,2172,"SHIP CONSTRUCTION","South Dublin","Grand Canal, Lindisfarne, Clondalkin,",19,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2173,2173,"CAS CONSTRUCTION","South Dublin","Collinstown Grove, Clondalkin",4,"Tï¿½ath Housing Association Ltd","","","","","","Q1-2020"],
    [2174,2174,"CAS CONSTRUCTION","South Dublin","Old Nangor Road, Clondalkin",10,"Simon Community : Dublin Simon","","","","","Q4-2019",""],
    [2175,2175,"CALF Turnkey","South Dublin","2 properties Tullyhall, Lucan, County Dublin (Phase 1)*",2,"Tuath Housing Association","","","","","","Q2-2019"],
    [2176,2176,"CALF Turnkey","South Dublin","6 units Elder Heath, Kiltipper Road, Tallaght, Dublin 24 (Phase 1)*",6,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2177,2177,"CALF Turnkey","South Dublin","Ardsolus, Old Naas Road, Dublin 22 (Phase 1)",10,"Respond","","","","","","Q3-2019"],
    [2178,2178,"CALF Turnkey","South Dublin","Aylmer Heath, Newcastle, Co. Dublin 22 (Phase 1)",32,"Respond","","","","","","Q4-2020"],
    [2179,2179,"CALF Turnkey","South Dublin","Ballynakelly, Newcastle, Co. Dublin (Phase 1)",6,"Tuath Housing Association","","","","","","Q4-2018"],
    [2180,2180,"CALF Turnkey","South Dublin","Ballynakelly, Newcastle, Co. Dublin (Phase 2)",4,"Tuath Housing Association","","","","","","Q1-2019"],
    [2181,2181,"CALF Turnkey","South Dublin","Balrothery, Castletymon Road, Dublin Road (Phase 1)*",13,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2182,2182,"CALF Turnkey","South Dublin","Broadfield Grove, Rathcoole, Co. Dublin (Phase 1)*",14,"Oaklee Housing","","","","","","Q3-2017"],
    [2183,2183,"CALF Turnkey","South Dublin","Burgage Gardens, Newcastle, Co. Dublin (Phase 1)*",4,"Respond","","","","","","Q2-2020"],
    [2184,2184,"CALF Turnkey","South Dublin","Burgage, Newcastle, Co. Dublin 22 (Phase 1)",10,"Respond","","","","","","Q4-2019"],
    [2185,2185,"CALF Turnkey","South Dublin","Burgage, Newcastle, Co. Dublin 22 (Phase 2)",26,"Respond","","","","","","Q2-2020"],
    [2186,2186,"CALF Turnkey","South Dublin","Citywest Quarter, Citywest, Dublin 24 (Phase 1)*",32,"Tuath Housing Association","","","","","","Q2-2021"],
    [2187,2187,"CALF Turnkey","South Dublin","Cloverhill Lodge, Cloverhill Rd, Clondalkin, D22 (Phase 1)*",40,"Oaklee Housing","","","","","Q2-2021",""],
    [2188,2188,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 1)",45,"Tuath Housing Association","","","","","","Q4-2020"],
    [2189,2189,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 2)",15,"Tuath Housing Association","","","","","","Q4-2020"],
    [2190,2190,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 3)*",23,"Tuath Housing Association","","","","","","Q4-2020"],
    [2191,2191,"CALF Turnkey","South Dublin","Cuil Duin Green, Cuil Duin, Citywest, Dublin 24 (Phase 1)*",24,"Fold Housing Association Ireland Ltd","","","","","","Q4-2020"],
    [2192,2192,"CALF Turnkey","South Dublin","De Selby Heights, Tallaght, Dublin 24 (Phase 1)",9,"Tuath Housing Association","","","","","","Q4-2019"],
    [2193,2193,"CALF Turnkey","South Dublin","Dodderbrook (Apartments), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*",6,"Clï¿½id Housing","","","","","","Q1-2018"],
    [2194,2194,"CALF Turnkey","South Dublin","Dodderbrook (Houses), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*",8,"Clï¿½id Housing","","","","","","Q1-2018"],
    [2195,2195,"CALF Turnkey","South Dublin","Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2196,2196,"CALF Turnkey","South Dublin","Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 2)*",9,"Clï¿½id Housing","","","","","","Q1-2021"],
    [2197,2197,"CALF Turnkey","South Dublin","Dodderbrook, Oldcourt Road, Ballycllen, Dublin 24 (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q3-2018"],
    [2198,2198,"CALF Turnkey","South Dublin","Edenbrook, Citywest, Dublin 24 (Phase 1)",17,"Tuath Housing Association","","","","","","Q4-2019"],
    [2199,2199,"CALF Turnkey","South Dublin","Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 1)*",18,"Clï¿½id Housing","","","","","","Q1-2018"],
    [2200,2200,"CALF Turnkey","South Dublin","Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 2)*",10,"Clï¿½id Housing","","","","","","Q2-2018"],
    [2201,2201,"CALF Construction","South Dublin","Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 1)",40,"Clï¿½id Housing","","","","","Q3-2020",""],
    [2202,2202,"CALF Turnkey","South Dublin","Finians Way, Newcastle South, Newcastle, Co. Dublin (Phase 1)*",2,"Clanmil Housing Association Ireland","","","","","Q1-2020",""],
    [2203,2203,"CALF Turnkey","South Dublin","Finnstown, Lucan, Co. Dublin (Phase 1)",32,"Respond","","","","","","Q3-2021"],
    [2204,2204,"CALF Turnkey","South Dublin","Finnstown, Lucan, Co. Dublin (Phase 2)",38,"Respond","","","","","","Q3-2021"],
    [2205,2205,"CALF Turnkey","South Dublin","Finnstown, Lucan, Co. Dublin (Phase 3)*",24,"Respond","","","","","Q4-2018",""],
    [2206,2206,"CALF Turnkey","South Dublin","Graydon, Newcastle, Co. Dublin (Phase 1)*",8,"Tuath Housing Association","","","","","Q1-2020",""],
    [2207,2207,"CALF Turnkey","South Dublin","Green Lane, Rathcoole, Co. Dublin (Phase 1)*",12,"Tuath Housing Association","","","","","","Q4-2020"],
    [2208,2208,"CALF Turnkey","South Dublin","Green Lane, Rathcoole, Co. Dublin (Phase 2)*",9,"Tuath Housing Association","","","","","","Q4-2020"],
    [2209,2209,"CALF Turnkey","South Dublin","Hallwell, Tubber Lane, Adamstown, Co Dublin (Phase 1)*",45,"The Iveagh Trust","","","","","Q2-2018",""],
    [2210,2210,"CALF Turnkey","South Dublin","Kingswood, Old Ballymount Road, Tallaght, Dublin 24 (Phase 1)*",24,"Respond","","","","","Q4-2018",""],
    [2211,2211,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Apartments (Phase 1)*",13,"Clï¿½id Housing","","","","","","Q2-2018"],
    [2212,2212,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Apartments (Phase 2)",12,"Clï¿½id Housing","","","","","","Q4-2018"],
    [2213,2213,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Houses (Phase 1)",25,"Clï¿½id Housing","","","","","","Q1-2017"],
    [2214,2214,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Houses (Phase 2)",15,"Clï¿½id Housing","","","","","","Q3-2017"],
    [2215,2215,"CALF Turnkey","South Dublin","Millford Manor, Cloverhill Road, Clondalkin, Dublin 22 (Phase 1)*",2,"Clï¿½id Housing","","","","","","Q4-2018"],
    [2216,2216,"CALF Turnkey","South Dublin","Mountain Gate, Kiltipper Rd., Dublin 24 (Phase 1)*",22,"Co - Operative Housing Ireland Society Limited","","","","Q3-2021","",""],
    [2217,2217,"CALF Turnkey","South Dublin","Moyglas, Lucan, Co Dublin (Phase 1)",13,"Respond","","","","","","Q1-2016"],
    [2218,2218,"CALF Turnkey","South Dublin","Moyglas, Lucan, Co Dublin (Phase 2)*",1,"Respond","","","","","","Q2-2017"],
    [2219,2219,"CALF Turnkey","South Dublin","New Bancroft, Tallaght, Dublin 24 (Phase 1)*",16,"Clï¿½id Housing","","","","","","Q3-2017"],
    [2220,2220,"CALF Construction","South Dublin","Old Lucan Road, Palmerstown, Dublin 20 (Phase 1)",4,"Tuath Housing Association","","","","Q3-2021","",""],
    [2221,2221,"CALF Turnkey","South Dublin","Palmerstown Avenue, Dublin 20 (Phase 1)",7,"Respond","","","","","","Q4-2020"],
    [2222,2222,"CALF Turnkey","South Dublin","Palmerstown Way, Clondalkin, Dublin 22 (Phase 1)*",6,"Tuath Housing Association","","","","","","Q3-2018"],
    [2223,2223,"CALF Turnkey","South Dublin","Phase 2, Aylmer Drive, Aylmer Heath, Newcastle, Co. Dublin (Phase 1)*",17,"Respond","","","","","","Q2-2021"],
    [2224,2224,"CALF Turnkey","South Dublin","Raheen House, Old Nangor Road, Clondalkin, Dublin 22 (Phase 1)",9,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [2225,2225,"CALF Turnkey","South Dublin","Rathmill Meadows and Green, Rathcoole, Co. Dublin (Phase 1)*",11,"Oaklee Housing","","","","","","Q4-2019"],
    [2226,2226,"CALF Turnkey","South Dublin","Sallypark, Clondalkin, Dublin 22 (Phase 1)*",85,"Clï¿½id Housing","","","","","Q4-2020",""],
    [2227,2227,"CALF Turnkey","South Dublin","San Guida, New Road, Clondalkin, Dublin 22 (Phase 1)*",21,"Clï¿½id Housing","","","","","Q3-2021",""],
    [2228,2228,"CALF Turnkey","South Dublin","Scholarstown Road, Rathfarnham, Dublin 16 (Phase 1)*",7,"Circle Voluntary Housing Association Ltd","","","","","Q2-2019",""],
    [2229,2229,"CALF Turnkey","South Dublin","Scholarstown Road, Rathfarnham, Dublin 16 (Phase 2)*",7,"Circle Voluntary Housing Association Ltd","","","","","Q2-2019",""],
    [2230,2230,"CALF Turnkey","South Dublin","Scholarstown Wood (Apartments), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*",6,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [2231,2231,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2017"],
    [2232,2232,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 2)*",4,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [2233,2233,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 3)*",1,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [2234,2234,"CALF Turnkey","South Dublin","Shackleton Park, Lucan, Co. Dublin (Phase 1)*",8,"Clï¿½id Housing","","","","","","Q2-2019"],
    [2235,2235,"CALF Turnkey","South Dublin","Somerton, Lucan, Co. Dublin (Phase 1)*",32,"Respond","","","","","","Q4-2019"],
    [2236,2236,"CALF Construction","South Dublin","St. Catherineï¿½s, Knockmore Avenue, Killinarden, Tallaght, Dublin 24 (Phase 1)",2,"Sophia Housing Association Ltd","","","","","Q2-2021",""],
    [2237,2237,"CALF Turnkey","South Dublin","St. Johns, Firhouse, Dublin 24 (Phase 1)*",10,"Respond","","","","","","Q4-2019"],
    [2238,2238,"CALF Turnkey","South Dublin","Station Road, Clondalkin, Co. Dublin (Phase 1)",5,"Respond","","","","","","Q3-2017"],
    [2239,2239,"CALF Turnkey","South Dublin","Stone Masons Court, Fortunestown Lane, Citywest Dublin (Phase 1)*",12,"Clï¿½id Housing","","","","","","Q2-2019"],
    [2240,2240,"CALF Turnkey","South Dublin","Temple Court, Temple Woods, Greenhills Road, Dublin 12 (Phase 1)*",6,"Tuath Housing Association","","","","","","Q4-2018"],
    [2241,2241,"CALF Turnkey","South Dublin","The Mews, Citywest Village, Citywest, Dublin 24 (Phase 1)*",22,"Fold Housing Association Ireland Ltd","","","","","","Q4-2020"],
    [2242,2242,"CALF Turnkey","South Dublin","The Rise, Citywest Village, Citywest, Dublin 24 (Phase 1)*",13,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [2243,2243,"CALF Construction","South Dublin","The Weir, Whitestown Way, Tallaght, Dublin 24 (Phase 1)",81,"Clï¿½id Housing","","","","","Q2-2021",""],
    [2244,2244,"CALF Turnkey","South Dublin","Tullyhall, Lucan, Co Dublin (Phase 1)*",2,"Tuath Housing Association","","","","","","Q3-2017"],
    [2245,2245,"CALF Turnkey","South Dublin","Tullyhall, Lucan, Co Dublin (Phase 2)*",2,"Tuath Housing Association","","","","","","Q4-2018"],
    [2246,2246,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 1)",28,"Clï¿½id Housing","","","","","","Q4-2018"],
    [2247,2247,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 2)",28,"Clï¿½id Housing","","","","","","Q2-2019"],
    [2248,2248,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 3)",28,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2249,2249,"CALF Turnkey","South Dublin","Wilkins Court, Limekiln Lane, Dublin 12 (Phase 1)*",6,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [2250,2250,"CALF Turnkey","South Dublin","Wilkins View, Greenhills, Dublin 12 (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [2251,2251,"CALF Turnkey","South Dublin","Willowview, Ballyboden Road, Rathfarnham, Dublin 14 (Phase 1)*",12,"Clï¿½id Housing","","","","","","Q2-2021"],
    [2252,2252,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","South Dublin","Corkage Grange (part of Kilcarbery)",109,"*N/A","","","","","","Q4-2020"],
    [2253,2253,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard",6,"*N/A","","","","","","Q2-2019"],
    [2254,2254,"SHIP CONSTRUCTION TURNKEY","Tipperary","Strylea, Fethard",3,"*N/A","","","","","","Q4-2020"],
    [2255,2255,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ardan, Borrisokane",9,"*N/A","","","","","","Q4-2018"],
    [2256,2256,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles",4,"*N/A","","","","","","Q4-2018"],
    [2257,2257,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ardan, Borrisokane",4,"*N/A","","","","","","Q2-2019"],
    [2258,2258,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles",5,"*N/A","","","","","","Q4-2019"],
    [2259,2259,"SHIP CONSTRUCTION TURNKEY","Tipperary","Prior Park, Clonmel",12,"*N/A","","","","","Q3-2020",""],
    [2260,2260,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ma Charoin, Manna South, Templemore",13,"*N/A","","","","","Q1-2021",""],
    [2261,2261,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard",5,"*N/A","","","","","","Q3-2019"],
    [2262,2262,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard",6,"*N/A","","","","","","Q4-2019"],
    [2263,2263,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glencree, Newport",3,"*N/A","","","","","","Q4-2019"],
    [2264,2264,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard",4,"*N/A","","","","","","Q4-2019"],
    [2265,2265,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles",5,"*N/A","","","","","","Q4-2019"],
    [2266,2266,"SHIP CONSTRUCTION TURNKEY","Tipperary","Prior Park, Clonmel",29,"*N/A","","","","","Q3-2020",""],
    [2267,2267,"SHIP CONSTRUCTION TURNKEY","Tipperary","Rosanna Close, Tipperary Town",18,"*N/A","","","","","","Q4-2020"],
    [2268,2268,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glenconnor Road, Clonmel",10,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2269,2269,"SHIP CONSTRUCTION TURNKEY","Tipperary","Rosanna Close, Tipperary Town",1,"*N/A","","","","","Q3-2020",""],
    [2270,2270,"SHIP CONSTRUCTION TURNKEY","Tipperary","Hazel Close, Carrick on Suir",14,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2271,2271,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glenconnor",2,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2272,2272,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cois Abhainn, Mullinahone",3,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2273,2273,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glentara, Roscrea",2,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [2274,2274,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glenconnor Road, Clonmel",11,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2275,2275,"SHIP CONSTRUCTION SINGLE STAGE","Tipperary","Mulkear View, Newport, Tipperary",3,"*N/A","","","","","","Q4-2018"],
    [2276,2276,"SHIP CONSTRUCTION SINGLE STAGE","Tipperary","Grange Road, Ballina",4,"*N/A","","","","","","Q4-2020"],
    [2277,2277,"SHIP CONSTRUCTION RENEWAL","Tipperary","Boherclough Street, Cashel",9,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2278,2278,"SHIP CONSTRUCTION","Tipperary","Ard na Greine, Clonmel",2,"*N/A","","","","","Q4-2020",""],
    [2279,2279,"SHIP CONSTRUCTION","Tipperary","Knockanrawley",14,"*N/A","","","","","","Q1-2021"],
    [2280,2280,"SHIP CONSTRUCTION","Tipperary","Mill Road, Thurles",14,"*N/A","","","","","Q2-2020",""],
    [2281,2281,"SHIP CONSTRUCTION","Tipperary","Mulkear View, Newport",6,"*N/A","","","","","Q4-2020",""],
    [2282,2282,"SHIP CONSTRUCTION","Tipperary","Treacy Park, Carrick on Suir",1,"*N/A","","","","","","Q3-2018"],
    [2283,2283,"SHIP CONSTRUCTION","Tipperary","Templetouhy",10,"*N/A","","","","","Q4-2019",""],
    [2284,2284,"SHIP CONSTRUCTION","Tipperary","Abbey Street, Cahir",10,"*N/A","","","","","Q3-2020",""],
    [2285,2285,"SHIP CONSTRUCTION","Tipperary","Borrisokane",16,"*N/A","","","","","Q3-2020",""],
    [2286,2286,"SHIP CONSTRUCTION","Tipperary","Portroe, Nenagh",14,"*N/A","","","","","Q4-2020",""],
    [2287,2287,"SHIP CONSTRUCTION","Tipperary","Cloughjordan",2,"*N/A","","","","","","Q2-2021"],
    [2288,2288,"SHIP CONSTRUCTION","Tipperary","Glenconnor Road, Clonmel",26,"*N/A","","","","","","Q3-2020"],
    [2289,2289,"SHIP CONSTRUCTION","Tipperary","Gortataggart, Thurles",2,"*N/A","","","","","","Q4-2018"],
    [2290,2290,"SHIP CONSTRUCTION","Tipperary","Kilcooly Way, Gortnahoe",5,"*N/A","","","","","","Q3-2020"],
    [2291,2291,"SHIP CONSTRUCTION","Tipperary","Lacey Avenue, Templemore",3,"*N/A","","","","","","Q3-2016"],
    [2292,2292,"SHIP CONSTRUCTION","Tipperary","Mitchel St., Thurles",1,"*N/A","","","","","Q4-2019",""],
    [2293,2293,"SHIP CONSTRUCTION","Tipperary","Borrisoleigh",1,"*N/A","","","","","","Q4-2016"],
    [2294,2294,"SHIP CONSTRUCTION","Tipperary","Lower Ballingarry",1,"*N/A","","","","","","Q2-2016"],
    [2295,2295,"SHIP CONSTRUCTION","Tipperary","Poulamaleen, Faugheen",1,"*N/A","","","","","","Q2-2016"],
    [2296,2296,"SHIP CONSTRUCTION","Tipperary","Cormack Drive, Nenagh",8,"*N/A","","","","","Q3-2020",""],
    [2297,2297,"SHIP CONSTRUCTION","Tipperary","Lacey Avenue, Templemore",1,"*N/A","","","","","","Q3-2017"],
    [2298,2298,"SHIP CONSTRUCTION","Tipperary","Borrisoleigh",1,"*N/A","","","","","","Q4-2018"],
    [2299,2299,"SHIP CONSTRUCTION","Tipperary","Bansha",14,"*N/A","","","","","Q3-2021",""],
    [2300,2300,"SHIP CONSTRUCTION","Tipperary","Ned Hayes Drive, Twomileborris, Thurles",22,"*N/A","","","","","Q3-2021",""],
    [2301,2301,"SHIP CONSTRUCTION","Tipperary","Donohill",8,"*N/A","","","","","Q3-2021",""],
    [2302,2302,"SHIP CONSTRUCTION","Tipperary","Mullinahone",10,"*N/A","","","","","Q1-2021",""],
    [2303,2303,"SHIP CONSTRUCTION","Tipperary","Ballyclerihan",14,"*N/A","","","","","Q3-2021",""],
    [2304,2304,"SHIP CONSTRUCTION","Tipperary","Ard Alainn, Moyne",9,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2305,2305,"SHIP CONSTRUCTION","Tipperary","Ardcroney",4,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2306,2306,"SHIP CONSTRUCTION","Tipperary","Comeragh Drive, Clonmel",2,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2307,2307,"SHIP CONSTRUCTION","Tipperary","Church Street, Templemore",2,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2308,2308,"SHIP CONSTRUCTION","Tipperary","Woodview Close, Nenagh",10,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [2309,2309,"SHIP CONSTRUCTION","Tipperary","Grove Street. Roscrea",7,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2310,2310,"SHIP CONSTRUCTION","Tipperary","William Street, Clonmel",4,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2311,2311,"SHIP CONSTRUCTION","Tipperary","Glencarrick, Roscrea",26,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2312,2312,"SHIP CONSTRUCTION","Tipperary","Knockanrawley",14,"*N/A","","","","","","Q2-2021"],
    [2313,2313,"SHIP CONSTRUCTION","Tipperary","Cormack Drive, Nenagh",4,"*N/A","","","","","Q3-2020",""],
    [2314,2314,"SHIP CONSTRUCTION","Tipperary","Mill Road, Thurles",14,"*N/A","","","","","Q2-2020",""],
    [2315,2315,"SHIP CONSTRUCTION","Tipperary","Mulkear View, Newport",5,"*N/A","","","","","Q4-2020",""],
    [2316,2316,"SHIP CONSTRUCTION","Tipperary","Mountain View, Cahir",43,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2317,2317,"SHIP CONSTRUCTION","Tipperary","Glencarrick, Roscrea",20,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2318,2318,"CAS CONSTRUCTION TURNKEY","Tipperary","Monastery Close, Templemore Road, Thurles",15,"Thurles Lions Trust Housing Assoc.","","","","","","Q2-2019"],
    [2319,2319,"CAS CONSTRUCTION TURNKEY","Tipperary","Drummin Village, Nenagh",8,"Nenagh Voluntary Housing Association","","","","","","Q4-2020"],
    [2320,2320,"CAS CONSTRUCTION TURNKEY","Tipperary","Kichham Street, Carrick en Suir",12,"Tï¿½ath Housing Association Ltd","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2321,2321,"CAS CONSTRUCTION","Tipperary","Glenconnor Road, Clonmel",9,"Cluid Housing Association","","","","","Q2-2021",""],
    [2322,2322,"CAS CONSTRUCTION","Tipperary","Stanwix House, Kickham Street, Thurles",19,"Thurles Lions Trust Housing Assoc.","","","","","Q2-2021",""],
    [2323,2323,"CAS CONSTRUCTION","Tipperary","Main Street, Templemore",14,"Templemore Voluntary Housing Association","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [2324,2324,"CAS CONSTRUCTION","Tipperary","Deerpark Road, Ashwell's Lot",2,"SPADE ï¿½ St. Patrickï¿½s Dwellings for the Elderly","","","","","Q2-2021",""],
    [2325,2325,"CALF Turnkey","Tipperary","An Duiche, Tipperary Town, Co. Tipperary (Phase 1)",41,"Respond","","","","","","Q4-2019"],
    [2326,2326,"CALF Turnkey","Tipperary","An Duiche, Tipperary Town, Co. Tipperary (Phase 2)",2,"Respond","","","","","","Q4-2019"],
    [2327,2327,"CALF Turnkey","Tipperary","Ashbury, Roscrea, Co Tipperary (Phase 1)",12,"Clï¿½id Housing","","","","","","Q2-2017"],
    [2328,2328,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co Tipperary  (Phase 1)",9,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [2329,2329,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [2330,2330,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 2)",7,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [2331,2331,"CALF Turnkey","Tipperary","Mill Street, Carrick on Suir, Co. Tipperary (Phase 1)",22,"Tuath Housing Association","","","","","","Q3-2020"],
    [2332,2332,"CALF Turnkey","Tipperary","The Avenue, Drummin Village, Nenagh, Co. Tipperary (Phase 1)",13,"Focus Housing Association CLG","","","","","","Q4-2020"],
    [2333,2333,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan",8,"*N/A","","","","","","Q3-2018"],
    [2334,2334,"SHIP CONSTRUCTION TURNKEY","Waterford","Gibbethill, Gracedieu",5,"*N/A","","","","","","Q3-2018"],
    [2335,2335,"SHIP CONSTRUCTION TURNKEY","Waterford","Carrickphierish, Gracedieu, Waterford",31,"*N/A","","","","","","Q4-2018"],
    [2336,2336,"SHIP CONSTRUCTION TURNKEY","Waterford","Shandon, Dungarvan",5,"*N/A","","","","","","Q3-2018"],
    [2337,2337,"SHIP CONSTRUCTION TURNKEY","Waterford","Airport Road, Waterford City",33,"*N/A","","","","","","Q4-2018"],
    [2338,2338,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan",10,"*N/A","","","","","","Q4-2018"],
    [2339,2339,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan",21,"*N/A","","","","","","Q4-2018"],
    [2340,2340,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford",20,"*N/A","","","","","","Q3-2019"],
    [2341,2341,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford",14,"*N/A","","","","","","Q4-2019"],
    [2342,2342,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford",6,"*N/A","","","","","","Q2-2020"],
    [2343,2343,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford",15,"*N/A","","","","","","Q3-2020"],
    [2344,2344,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",6,"*N/A","","","","","","Q3-2019"],
    [2345,2345,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",8,"*N/A","","","","","","Q4-2019"],
    [2346,2346,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",6,"*N/A","","","","","","Q4-2019"],
    [2347,2347,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount Suir, Gracedieu, Carrickphierish",18,"*N/A","","","","","","Q4-2019"],
    [2348,2348,"SHIP CONSTRUCTION TURNKEY","Waterford","Brideview Close, Tallow",2,"*N/A","","","","","","Q3-2020"],
    [2349,2349,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount William, Williamstown, Waterford City",19,"*N/A","","","","","","Q4-2020"],
    [2350,2350,"SHIP CONSTRUCTION TURNKEY","Waterford","7A and 8A Barnes Lane, The Glen, Waterford",2,"*N/A","","","","","","Q4-2019"],
    [2351,2351,"SHIP CONSTRUCTION TURNKEY","Waterford","Sherlock Walk, Gracedieu, Waterford",2,"*N/A","","","","","","Q2-2020"],
    [2352,2352,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount William, Williamstown, Waterford City",13,"*N/A","","","","","","Q1-2021"],
    [2353,2353,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount William, Williamstown, Waterford City",10,"*N/A","","","","","","Q2-2021"],
    [2354,2354,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount William, Williamstown, Waterford City",23,"*N/A","","","","","","Q2-2021"],
    [2355,2355,"SHIP CONSTRUCTION TURNKEY","Waterford","The Courtyard, Morrissons Road, Waterford City",8,"*N/A","","","","","","Q2-2021"],
    [2356,2356,"SHIP CONSTRUCTION TURNKEY","Waterford","Bounds Court, Airport Road, Waterford",15,"N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2357,2357,"SHIP CONSTRUCTION TURNKEY","Waterford","Brideview Close, Tallow; Main Street, Aglish; Bye Lane, Kilmacthomas, Co. Waterford",9,"N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2358,2358,"SHIP CONSTRUCTION SINGLE STAGE","Waterford","Apt 1 and Apt 2 Rivercourt, Grattan Quay, Waterford City",2,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [2359,2359,"SHIP CONSTRUCTION RAPID","Waterford","Ballygunner, Waterford City",49,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [2360,2360,"SHIP CONSTRUCTION RAPID","Waterford","Ballynaneashagh, Waterford City",22,"*N/A","","Stage 2 approved Q2-2020, full design/tender being prepared.","","","",""],
    [2361,2361,"SHIP CONSTRUCTION","Waterford","An Garran, Crobally Upper, Tramore",50,"*N/A","","","Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.","","",""],
    [2362,2362,"SHIP CONSTRUCTION","Waterford","Alms Houses, Tallow",4,"*N/A","","","","","","Q4-2018"],
    [2363,2363,"SHIP CONSTRUCTION","Waterford","Ardmore Park/Priory Lawn (Saviours Green), Ballybeg",5,"*N/A","","","","","","Q3-2020"],
    [2364,2364,"SHIP CONSTRUCTION","Waterford","Ballinroad, Dungarvan",21,"*N/A","","","","","","Q2-2020"],
    [2365,2365,"SHIP CONSTRUCTION","Waterford","Barrack Street, Cappoquin",4,"*N/A","","","","","","Q4-2017"],
    [2366,2366,"SHIP CONSTRUCTION","Waterford","Coolfin Woods, Portlaw",12,"*N/A","","","","","","Q2-2019"],
    [2367,2367,"SHIP CONSTRUCTION","Waterford","Larchville, Waterford City",5,"*N/A","","","","","","Q2-2021"],
    [2368,2368,"SHIP CONSTRUCTION","Waterford","Patrick Street, Tramore",2,"*N/A","","","","","","Q3-2018"],
    [2369,2369,"SHIP CONSTRUCTION","Waterford","Doyles Street, Waterford City",4,"*N/A","","","","","Q2-2020",""],
    [2370,2370,"SHIP CONSTRUCTION","Waterford","Old Cinema Site, Dungarvan",15,"*N/A","","","","","","Q4-2016"],
    [2371,2371,"SHIP CONSTRUCTION","Waterford","The Glen, Bridge St, Waterford",17,"*N/A","","","","","Q3-2021",""],
    [2372,2372,"SHIP CONSTRUCTION","Waterford","Clarendon Court, Penrose Lane, Waterford",24,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [2373,2373,"SHIP CONSTRUCTION","Waterford","Summerland Square, Waterford",12,"*N/A","","","Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.","","",""],
    [2374,2374,"SHIP CONSTRUCTION","Waterford","Bath St, Waterford City",4,"*N/A","","","","","","Q4-2019"],
    [2375,2375,"SHIP CONSTRUCTION","Waterford","Graigueshoneen, Kilmacthomas",16,"*N/A","","","","","Q4-2020",""],
    [2376,2376,"SHIP CONSTRUCTION","Waterford","Mount Esker, Ballytruckle Road, Waterford City",14,"*N/A","","","Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.","","",""],
    [2377,2377,"SHIP CONSTRUCTION","Waterford","Newgate Street, Waterford City",36,"*N/A","Stage 1 approved Q3-2020, outline design and costs being prepared.","","","","",""],
    [2378,2378,"SHIP CONSTRUCTION","Waterford","Fountain Street, Ferrybank, Waterford",14,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [2379,2379,"SHIP CONSTRUCTION","Waterford","Meeting House Lane, Waterford City",6,"N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [2380,2380,"CAS CONSTRUCTION","Waterford","Convent Hill, Tramore",10,"Society of Saint Vincent de Paul","","","","","","Q1-2017"],
    [2381,2381,"CAS CONSTRUCTION","Waterford","Powersfield, Hennessys Road, Waterford",3,"Focus Ireland","","Stage 2 approved Q2-2016, full design/tender being prepared.","","","",""],
    [2382,2382,"CAS CONSTRUCTION","Waterford","Wadding Manor, Ferrybank",10,"Respond","","","","","","Q2-2021"],
    [2383,2383,"CAS CONSTRUCTION","Waterford","Ballycarnane, Tramore",18,"Oaklee Housing Trust","Stage 1 approved Q4-2016, outline design and costs being prepared.","","","","",""],
    [2384,2384,"CAS CONSTRUCTION","Waterford","The Paddocks, Williamstown Rd. Waterford ",9,"Anvers Housing Association Ltd","","","","","","Q4-2020"],
    [2385,2385,"CALF Turnkey","Waterford","Kilbarry, Waterford (Phase 1)",69,"Respond","","","","","","Q3-2020"],
    [2386,2386,"CALF Turnkey","Waterford","Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 1)",26,"Circle Voluntary Housing Association Ltd","","","","","Q3-2019",""],
    [2387,2387,"CALF Turnkey","Waterford","Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 2)",31,"Circle Voluntary Housing Association Ltd","","","","","Q3-2019",""],
    [2388,2388,"CALF Construction","Waterford","St Johns College, Waterford (Phase 1)",36,"Respond","","","","","","Q1-2016"],
    [2389,2389,"CALF Turnkey","Waterford","The Walk, Fairfield Park, Kilcohan, Waterford (Phase 1)",40,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [2390,2390,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Waterford","Slievekeale, Waterford City (Phase 1)",24,"*N/A","","","","","","Q2-2021"],
    [2391,2391,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Waterford","Slievekeale, Waterford City (Phase 2)",34,"*N/A","","","","","","Q3-2021"],
    [2392,2392,"SHIP DIALOG","Westmeath","Lissywollen, Athlone",55,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2393,2393,"SHIP DIALOG","Westmeath","Lissywollen, Athlone",55,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2394,2394,"SHIP DIALOG","Westmeath","Lissywollen, Athlone",38,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2395,2395,"SHIP DIALOG","Westmeath","Lissywollen, Athlone",22,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2396,2396,"SHIP CONSTRUCTION TURNKEY","Westmeath","Belvedere Hills, Mullingar",21,"*N/A","","","","","","Q4-2017"],
    [2397,2397,"SHIP CONSTRUCTION TURNKEY","Westmeath","Cloon Lara, Mullingar",12,"*N/A","","","","","","Q2-2019"],
    [2398,2398,"SHIP CONSTRUCTION TURNKEY","Westmeath","Abbeybrook, Kilbeggan",7,"*N/A","","","","","","Q1-2019"],
    [2399,2399,"SHIP CONSTRUCTION TURNKEY","Westmeath","Coill Rua, Mullingar",6,"*N/A","","","","","","Q4-2019"],
    [2400,2400,"SHIP CONSTRUCTION TURNKEY","Westmeath","Rathgarve Green, Castlepollard",3,"*N/A","","","","","","Q1-2020"],
    [2401,2401,"SHIP CONSTRUCTION TURNKEY","Westmeath","Austin Friars Street, Mullingar",4,"*N/A","","","","","Q3-2020",""],
    [2402,2402,"SHIP CONSTRUCTION TURNKEY","Westmeath","Rathgarve Green, Castlepollard",5,"*N/A","","","","","","Q4-2020"],
    [2403,2403,"SHIP CONSTRUCTION TURNKEY","Westmeath","Oakcrest, Ballinderry, Mullingar",8,"*N/A","","","","","Q2-2021",""],
    [2404,2404,"SHIP CONSTRUCTION TURNKEY","Westmeath","St. Marys Place, Athlone",9,"*N/A","","","","","Q2-2021",""],
    [2405,2405,"SHIP CONSTRUCTION TURNKEY","Westmeath","Rathgarve Green, Castlepollard",1,"*N/A","","","","","","Q2-2021"],
    [2406,2406,"SHIP CONSTRUCTION TURNKEY","Westmeath","Bellaugh, Athlone",17,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2407,2407,"SHIP CONSTRUCTION TURNKEY","Westmeath","The Cedars, Lakepoint, Mullingar",7,"*N/A","","","","","Q2-2021",""],
    [2408,2408,"SHIP CONSTRUCTION TURNKEY","Westmeath","The Cedars, Lakepoint, Mullingar",10,"*N/A","","","","","Q2-2021",""],
    [2409,2409,"SHIP CONSTRUCTION TURNKEY","Westmeath","The Cedars, Lakepoint, Mullingar",11,"*N/A","","","","","Q2-2021",""],
    [2410,2410,"SHIP CONSTRUCTION RAPID","Westmeath","O'Growney Green, Mullingar",22,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [2411,2411,"SHIP CONSTRUCTION RAPID","Westmeath","Dalton Park, Mullingar",17,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [2412,2412,"SHIP CONSTRUCTION RAPID","Westmeath","Water Street, Castlepollard",8,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2413,2413,"SHIP CONSTRUCTION RAPID","Westmeath","Ennell Court, Mullingar (Phase 1)",15,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [2414,2414,"SHIP CONSTRUCTION","Westmeath","Bun Daire, Kinnegad (Phase 3)",8,"*N/A","","","","","","Q2-2021"],
    [2415,2415,"SHIP CONSTRUCTION","Westmeath","St. Laurence's Terrace, Mullingar",9,"*N/A","","","","","","Q4-2018"],
    [2416,2416,"SHIP CONSTRUCTION","Westmeath","Ennell Court, Mullingar",1,"*N/A","","","","","","Q1-2018"],
    [2417,2417,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone",21,"*N/A","","","","","","Q2-2020"],
    [2418,2418,"SHIP CONSTRUCTION","Westmeath","Ennell Court (Phase 2)",3,"*N/A","","","","","","Q2-2016"],
    [2419,2419,"SHIP CONSTRUCTION","Westmeath","Grange Crescent, Mullingar",2,"*N/A","","","","","","Q1-2016"],
    [2420,2420,"SHIP CONSTRUCTION","Westmeath","Ennell Court, Mullingar",31,"*N/A","","","","","Q2-2021",""],
    [2421,2421,"SHIP CONSTRUCTION","Westmeath","Cloghanboy, Athlone",10,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2422,2422,"SHIP CONSTRUCTION","Westmeath","Bishopsgate, Mullingar",2,"*N/A","","","","","","Q2-2021"],
    [2423,2423,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone (Phase 2)",24,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [2424,2424,"SHIP CONSTRUCTION","Westmeath","Canal Avenue, Mullingar",32,"*N/A","","Stage 2 approved Q4-2020, full design/tender being prepared.","","","",""],
    [2425,2425,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone",12,"*N/A","","","","","","Q3-2020"],
    [2426,2426,"SHIP CONSTRUCTION","Westmeath","Bun Daire, Kinnegad (Phase 3)",4,"*N/A","","","","","","Q3-2021"],
    [2427,2427,"SHIP CONSTRUCTION","Westmeath","Bishopsgate, Mullingar",2,"*N/A","","","","","Q4-2019",""],
    [2428,2428,"CAS CONSTRUCTION TURNKEY","Westmeath","Elm Row, Royal Canal, Mullingar",10,"Tï¿½ath Housing Association Ltd","","","","","","Q1-2021"],
    [2429,2429,"CAS CONSTRUCTION TURNKEY","Westmeath","Elm Row, Royal Canal, Mullingar",17,"Tï¿½ath Housing Association Ltd","","","","","Q4-2019",""],
    [2430,2430,"CAS CONSTRUCTION TURNKEY","Westmeath","Elm Row, Royal Canal, Mullingar",9,"Tï¿½ath Housing Association Ltd","","","","","Q4-2019",""],
    [2431,2431,"CAS CONSTRUCTION","Westmeath","Farran, Mullingar",4,"Tï¿½ath Housing Association Ltd","","","","","","Q3-2021"],
    [2432,2432,"CALF Turnkey","Westmeath","Ashe Road, Mullingar, Co. Westmeath (Phase 1)*",18,"Clï¿½id Housing","","","","Q2-2021","",""],
    [2433,2433,"CALF Turnkey","Westmeath","Athlone Road, Moate, Co. Westmeath (Phase 1)*",14,"Oaklee Housing","","","","","","Q2-2021"],
    [2434,2434,"CALF Turnkey","Westmeath","Bower Hill, Lower Road, Athlone, Co. Westmeath (Phase 1)*",15,"Clï¿½id Housing","","","","Q3-2021","",""],
    [2435,2435,"CALF Turnkey","Westmeath","Charlestown, Mullingar (Phase 1)*",37,"Respond","","","","Q2-2021","",""],
    [2436,2436,"CALF Turnkey","Westmeath","Charlestown, Mullingar (Phase 2)*",62,"Respond","","","","Q2-2021","",""],
    [2437,2437,"CALF Turnkey","Westmeath","Cluain Mullen, Castlepollard, Co. Westmeath (Phase 1)",8,"Tuath Housing Association","","","","","","Q4-2020"],
    [2438,2438,"CALF Turnkey","Westmeath","Cluain Mullen, Castlepollard, Westmeath (Phase 1)",2,"Tuath Housing Association","","","","","","Q2-2017"],
    [2439,2439,"CALF Turnkey","Westmeath","Coill Rua, Mullingar, Co. Westmeath (Phase 1)*",13,"Clï¿½id Housing","","","","","","Q4-2020"],
    [2440,2440,"CALF Turnkey","Westmeath","Coill Rua, Mullingar, Co. Westmeath (Phase 2)*",23,"Clï¿½id Housing","","","","","","Q1-2021"],
    [2441,2441,"CALF Turnkey","Westmeath","Coill Rua, Mullingar, Co. Westmeath (Phase 3)",8,"Clï¿½id Housing","","","","","","Q2-2021"],
    [2442,2442,"CALF Construction","Westmeath","Farran, Mullingar, Co. Westmeath (Phase 1)",10,"Tuath Housing Association","","","","","","Q3-2021"],
    [2443,2443,"CALF Turnkey","Westmeath","Garran Geal, Kinnegad, Westmeath (Phase 1)*",24,"Tuath Housing Association","","","","","Q4-2020",""],
    [2444,2444,"CALF Turnkey","Westmeath","Ghairdin Beag, Main Street, Rathwire, Killucan, Co. Westmeath (Phase 1)",6,"Tuath Housing Association","","","","","","Q4-2020"],
    [2445,2445,"CALF Turnkey","Westmeath","Rahanine, Rochfortbridge, Co Westmeath (Phase 1)*",12,"Tuath Housing Association","","","","","","Q2-2021"],
    [2446,2446,"CALF Turnkey","Westmeath","Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 1)",4,"Tuath Housing Association","","","","","","Q1-2021"],
    [2447,2447,"CALF Turnkey","Westmeath","Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 2)",4,"Tuath Housing Association","","","","","Q3-2019",""],
    [2448,2448,"CALF Turnkey","Westmeath","Springfield Cottages, Mullingar, Co. Westmeath (Phase 1)*",13,"Clï¿½id Housing","","","","Q2-2021","",""],
    [2449,2449,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 1)",8,"Tuath Housing Association","","","","","","Q4-2019"],
    [2450,2450,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 2)*",14,"Tuath Housing Association","","","","","","Q2-2020"],
    [2451,2451,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 3)",10,"Tuath Housing Association","","","","","","Q2-2020"],
    [2452,2452,"SHIP CONSTRUCTION TURNKEY","Wexford","Madeira Oaks, Wexford",8,"*N/A","","","","","","Q3-2017"],
    [2453,2453,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",8,"*N/A","","","","","","Q1-2018"],
    [2454,2454,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",11,"*N/A","","","","","","Q4-2018"],
    [2455,2455,"SHIP CONSTRUCTION TURNKEY","Wexford","Rath an Duin, Castlebridge",3,"*N/A","","","","","","Q3-2018"],
    [2456,2456,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",2,"*N/A","","","","","","Q2-2019"],
    [2457,2457,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",10,"*N/A","","","","","","Q1-2019"],
    [2458,2458,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",10,"*N/A","","","","","","Q4-2018"],
    [2459,2459,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey",5,"*N/A","","","","","","Q4-2018"],
    [2460,2460,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey",2,"*N/A","","","","","","Q1-2019"],
    [2461,2461,"SHIP CONSTRUCTION TURNKEY","Wexford","Whitewater Estuary, Ballyhack",3,"*N/A","","","","","","Q3-2020"],
    [2462,2462,"SHIP CONSTRUCTION TURNKEY","Wexford","Riverchapel Lane, Gorey",4,"*N/A","","","","","","Q4-2019"],
    [2463,2463,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",4,"*N/A","","","","","","Q2-2019"],
    [2464,2464,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey",3,"*N/A","","","","","","Q4-2019"],
    [2465,2465,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",10,"*N/A","","","","","","Q3-2019"],
    [2466,2466,"SHIP CONSTRUCTION TURNKEY","Wexford","St. Martin's Road, Rosslare Harbour",4,"*N/A","","","","","","Q4-2019"],
    [2467,2467,"SHIP CONSTRUCTION TURNKEY","Wexford","Clonattin Upper, Gorey",8,"*N/A","","","","","","Q4-2020"],
    [2468,2468,"SHIP CONSTRUCTION TURNKEY","Wexford","Airhill, Belvedere Rd, Wexford",7,"*N/A","","","","","","Q3-2021"],
    [2469,2469,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",2,"*N/A","","","","","","Q4-2019"],
    [2470,2470,"SHIP CONSTRUCTION TURNKEY","Wexford","Michael Street, New Ross ",3,"*N/A","","","","","","Q2-2021"],
    [2471,2471,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",14,"*N/A","","","","","","Q4-2020"],
    [2472,2472,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",1,"*N/A","","","","","","Q3-2019"],
    [2473,2473,"SHIP CONSTRUCTION TURNKEY","Wexford","Ballynaglough, Blackwater",4,"*N/A","","","","","Q4-2019",""],
    [2474,2474,"SHIP CONSTRUCTION TURNKEY","Wexford","No.'s 64 & 74 Chapelwood, Kilmuckridge",2,"*N/A","","","","","","Q1-2020"],
    [2475,2475,"SHIP CONSTRUCTION TURNKEY","Wexford","5 The Break Ayelsbridge, Riverchapel",1,"*N/A","","","","","","Q1-2020"],
    [2476,2476,"SHIP CONSTRUCTION TURNKEY","Wexford","Tobar Muire, Creagh Gorey",10,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [2477,2477,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",1,"*N/A","","","","","","Q1-2020"],
    [2478,2478,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Gorey - Phase 2",4,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2479,2479,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock Hill, Wexford",5,"*N/A","","","","","","Q2-2021"],
    [2480,2480,"SHIP CONSTRUCTION TURNKEY","Wexford","Cluain Beag, Clonard, Wexford",5,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2481,2481,"SHIP CONSTRUCTION TURNKEY","Wexford","Cluain Beag, Clonard, Wexford",6,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2482,2482,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",2,"*N/A","","","","","","Q2-2021"],
    [2483,2483,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard an Bhile, Healysland, New Ross, Co. Wexford",22,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2484,2484,"SHIP CONSTRUCTION TURNKEY","Wexford","Tobar Muire, Creagh Gorey",29,"*N/A","","","","Stage 4 approved Q2-2020, the scheme is fully approved.","",""],
    [2485,2485,"SHIP CONSTRUCTION TURNKEY","Wexford","Ballynaglough, Blackwater",12,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [2486,2486,"SHIP CONSTRUCTION TURNKEY","Wexford","Roxborough Manor",3,"*N/A","","","","","Q2-2021",""],
    [2487,2487,"SHIP CONSTRUCTION TURNKEY","Wexford","Roxborough Manor",3,"*N/A","","","","","Q2-2021",""],
    [2488,2488,"SHIP CONSTRUCTION TURNKEY","Wexford","Roxborough Manor",4,"*N/A","","","","","Q2-2021",""],
    [2489,2489,"SHIP CONSTRUCTION TURNKEY","Wexford","Roxborough Manor",3,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2490,2490,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",2,"*N/A","","","","","","Q2-2021"],
    [2491,2491,"SHIP CONSTRUCTION TURNKEY","Wexford","Clonard Little, Wexford ",9,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2492,2492,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard an Bhile, Healysland, New Ross, Co. Wexford",21,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2493,2493,"SHIP CONSTRUCTION TURNKEY","Wexford","Cluain Beag, Clonard, Wexford",9,"*N/A","","","","Stage 4 approved Q3-2020, the scheme is fully approved.","",""],
    [2494,2494,"SHIP CONSTRUCTION","Wexford","SN Castlemoyle, New Ross",1,"*N/A","","","","","","Q4-2019"],
    [2495,2495,"SHIP CONSTRUCTION","Wexford","Cloghulatagh, Taghmon",18,"*N/A","","","","","","Q4-2020"],
    [2496,2496,"SHIP CONSTRUCTION","Wexford","Coolcotts, Clonard",7,"*N/A","","","","","","Q4-2019"],
    [2497,2497,"SHIP CONSTRUCTION","Wexford","Creagh, Gorey",10,"*N/A","","","","","","Q1-2019"],
    [2498,2498,"SHIP CONSTRUCTION","Wexford","Danescastle",10,"*N/A","","","","","","Q1-2019"],
    [2499,2499,"SHIP CONSTRUCTION","Wexford","Slippery Green, Wexford",10,"*N/A","","","","","","Q3-2019"],
    [2500,2500,"SHIP CONSTRUCTION","Wexford","Whiterock Hill, Wexford",22,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2501,2501,"SHIP CONSTRUCTION","Wexford","Cois Mara",2,"*N/A","","","","","","Q3-2018"],
    [2502,2502,"SHIP CONSTRUCTION","Wexford","Killeens, Wexford",40,"*N/A","","","","","Q2-2020",""],
    [2503,2503,"SHIP CONSTRUCTION","Wexford","Oilgate, Enniscorthy",2,"*N/A","","","","","","Q2-2018"],
    [2504,2504,"SHIP CONSTRUCTION","Wexford","Cherryorchard, Enniscorthy",8,"*N/A","","","","","","Q3-2018"],
    [2505,2505,"SHIP CONSTRUCTION","Wexford","Ross Road, Enniscorthy",1,"*N/A","","","","","Q3-2018",""],
    [2506,2506,"SHIP CONSTRUCTION","Wexford","Baile Eoghain, Gorey",5,"*N/A","","","","","","Q4-2018"],
    [2507,2507,"SHIP CONSTRUCTION","Wexford","Baile an Trï¿½, Riverchapel (Courtown Ardamine)",10,"*N/A","","","","","","Q2-2016"],
    [2508,2508,"SHIP CONSTRUCTION","Wexford","Shanna Court, Coolcotts",8,"*N/A","","","","","","Q1-2016"],
    [2509,2509,"SHIP CONSTRUCTION","Wexford","Francis Street, Wexford",1,"*N/A","","","","","","Q1-2017"],
    [2510,2510,"SHIP CONSTRUCTION","Wexford","Commodore Barry",1,"*N/A","","","","","","Q2-2016"],
    [2511,2511,"SHIP CONSTRUCTION","Wexford","Glentire, The Ballagh, Enniscorthy",6,"*N/A","","","","","Q2-2019",""],
    [2512,2512,"SHIP CONSTRUCTION","Wexford","Rosetown, Rosslare, Co Wexford, Phase 1",23,"*N/A","","","","","Q2-2019",""],
    [2513,2513,"SHIP CONSTRUCTION","Wexford","Carley's Bridge, Enniscorthy",17,"*N/A","","","","","Q2-2019",""],
    [2514,2514,"SHIP CONSTRUCTION","Wexford","Creagh, Gorey",12,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [2515,2515,"SHIP CONSTRUCTION","Wexford","Baile Eoghain, Gorey",4,"*N/A","","","","","","Q4-2018"],
    [2516,2516,"SHIP CONSTRUCTION","Wexford","Wexford Street, Gorey",30,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [2517,2517,"SHIP CONSTRUCTION","Wexford","Bullawn, Irishtown, New Ross",3,"*N/A","","","","","Q3-2021",""],
    [2518,2518,"SHIP CONSTRUCTION","Wexford","Ballyhine, Barntown",7,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2519,2519,"SHIP CONSTRUCTION","Wexford","Whiterock Hill, Wexford",22,"*N/A","","","Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.","","",""],
    [2520,2520,"SHIP CONSTRUCTION","Wexford","Doire Moling estate at Monamolin, Gorey, Co. Wexford",5,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [2521,2521,"CAS CONSTRUCTION TURNKEY","Wexford","Clonattin, Gorey",6,"Tï¿½ath Housing Association Ltd","","","","","","Q2-2021"],
    [2522,2522,"CAS CONSTRUCTION","Wexford","Barrystown",16,"Grantstown Voluntary Housing Association Ltd","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [2523,2523,"CAS CONSTRUCTION","Wexford","Rathangan",7,"Rathangan Senior Citizens Housing Association Ltd","","","","","","Q3-2017"],
    [2524,2524,"CAS CONSTRUCTION","Wexford","Wexford Women's Refuge, Maudlintown",12,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [2525,2525,"CALF Turnkey","Wexford","24 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)",8,"Tuath Housing Association","","","","","","Q3-2020"],
    [2526,2526,"CALF Turnkey","Wexford","24 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 2)",16,"Tuath Housing Association","","","","","","Q4-2020"],
    [2527,2527,"CALF Turnkey","Wexford","67 units, Coolcotts, Wexford (Phase 1)*",67,"Clï¿½id Housing","","","","","Q3-2020",""],
    [2528,2528,"CALF Turnkey","Wexford","9 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)",9,"Tuath Housing Association","","","","","","Q2-2021"],
    [2529,2529,"CALF Turnkey","Wexford"," Ard Uisce, Wexford Town (Phase 1)",5,"Tuath Housing Association","","","","","","Q4-2017"],
    [2530,2530,"CALF Turnkey","Wexford"," Ard Uisce, Whiterock, Wexford  (Phase 1)",1,"Tuath Housing Association","","","","","","Q1-2018"],
    [2531,2531,"CALF Turnkey","Wexford","Ard Uisce, Whiterock, Wexford (Phase 1)",6,"Tuath Housing Association","","","","","","Q1-2018"],
    [2532,2532,"CALF Turnkey","Wexford","Ard Uisce, Whiterock, Wexford (Phase 1)*",6,"Tuath Housing Association","","","","","","Q1-2017"],
    [2533,2533,"CALF Turnkey","Wexford","Ballyboggan, Castlebridge, Co Wexford (Phase 1)",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [2534,2534,"CALF Turnkey","Wexford","Clonard, Wexford (Phase 1)*",10,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [2535,2535,"CALF Turnkey","Wexford","Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 1)",34,"Oaklee Housing","","","","","","Q4-2018"],
    [2536,2536,"CALF Turnkey","Wexford","Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 2)",6,"Oaklee Housing","","","","","","Q2-2019"],
    [2537,2537,"CALF Turnkey","Wexford","Forgelands, Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)*",18,"Tuath Housing Association","","","","","","Q3-2021"],
    [2538,2538,"CALF Turnkey","Wexford","Fort Road, Ramsfort Park, Gorey, Co. Wexford (Phase 1)*",11,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2020"],
    [2539,2539,"CALF Turnkey","Wexford","Gleann an Ghairdin, Gorey (Phase 1)",9,"Tuath Housing Association","","","","","","Q4-2019"],
    [2540,2540,"CALF Turnkey","Wexford","Gleann an Ghairdin, Gorey (Phase 2)",9,"Tuath Housing Association","","","","","","Q1-2020"],
    [2541,2541,"CALF Turnkey","Wexford","Greenville, Enniscorthy, Co. Wexford (Phase 1)*",6,"Oaklee Housing","","","","","","Q2-2019"],
    [2542,2542,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 1)",7,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2016"],
    [2543,2543,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 2)",11,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2016"],
    [2544,2544,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 3)",11,"Co - Operative Housing Ireland Society Limited","","","","","","Q1-2017"],
    [2545,2545,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 4)",9,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2017"],
    [2546,2546,"CALF Turnkey","Wexford","Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 1)",14,"Tuath Housing Association","","","","","","Q4-2020"],
    [2547,2547,"CALF Turnkey","Wexford","Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 2)",14,"Tuath Housing Association","","","","","","Q4-2020"],
    [2548,2548,"CALF Turnkey","Wexford","Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 3)",16,"Tuath Housing Association","","","","","","Q1-2021"],
    [2549,2549,"CALF Turnkey","Wexford","Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 4)*",27,"Tuath Housing Association","","","","","","Q2-2021"],
    [2550,2550,"CALF Turnkey","Wexford","Meadowfields Enniscorthy, Co. Wexford (Phase 1)",12,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2016"],
    [2551,2551,"CALF Turnkey","Wexford","Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 1)*",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q2-2019"],
    [2552,2552,"CALF Turnkey","Wexford","Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 2)*",14,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [2553,2553,"CALF Turnkey","Wexford","Mill Heights, Castlebridge, Wexford (Phase 1)",12,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [2554,2554,"CALF Turnkey","Wexford","Mill Heights, Castlebridge, Wexford (Phase 2)*",13,"Co - Operative Housing Ireland Society Limited","","","","","Q2-2021",""],
    [2555,2555,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)",11,"Tuath Housing Association","","","","","","Q4-2020"],
    [2556,2556,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 2)*",14,"Tuath Housing Association","","","","","","Q4-2020"],
    [2557,2557,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 3)*",8,"Tuath Housing Association","","","","","","Q1-2021"],
    [2558,2558,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 4)*",8,"Tuath Housing Association","","","","","","Q2-2021"],
    [2559,2559,"CALF Turnkey","Wexford","Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 1)*",15,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [2560,2560,"CALF Turnkey","Wexford","Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 2)",19,"Co - Operative Housing Ireland Society Limited","","","","","Q1-2020",""],
    [2561,2561,"CALF Turnkey","Wexford","Pï¿½irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 1)*",16,"Clï¿½id Housing","","","","","","Q3-2021"],
    [2562,2562,"CALF Turnkey","Wexford","Pï¿½irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 2)",14,"Clï¿½id Housing","","","","","","Q3-2021"],
    [2563,2563,"CALF Turnkey","Wexford","Pï¿½irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 3)*",22,"Clï¿½id Housing","","","","","Q3-2019",""],
    [2564,2564,"CALF Turnkey","Wexford","Ramstown, Gorey, Wexford (Phase 1)",24,"Tuath Housing Association","","","","","Q2-2021",""],
    [2565,2565,"CALF Turnkey","Wexford","Ramstown, Gorey, Wexford (Phase 2)",20,"Tuath Housing Association","","","","","Q2-2021",""],
    [2566,2566,"CALF Turnkey","Wexford","Ramstown, Gorey, Wexford (Phase 3)*",24,"Tuath Housing Association","","","","","Q2-2021",""],
    [2567,2567,"CALF Turnkey","Wexford","Tobar Mhuire, Creagh, Gorey, Wexford (Phase 1)*",17,"Clï¿½id Housing","","","","Q2-2021","",""],
    [2568,2568,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",2,"*N/A","","","","","","Q2-2018"],
    [2569,2569,"SHIP CONSTRUCTION TURNKEY","Wicklow","No. 7 Mill Court, Tinahely ",1,"*N/A","","","","","","Q4-2018"],
    [2570,2570,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",10,"*N/A","","","","","","Q2-2019"],
    [2571,2571,"SHIP CONSTRUCTION TURNKEY","Wicklow","Fernhill, Arklow",1,"*N/A","","","","","","Q3-2018"],
    [2572,2572,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",1,"*N/A","","","","","","Q1-2019"],
    [2573,2573,"SHIP CONSTRUCTION TURNKEY","Wicklow","Woodview Cottages, Rathnew",2,"*N/A","","","","","","Q4-2019"],
    [2574,2574,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",10,"*N/A","","","","","","Q3-2019"],
    [2575,2575,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",1,"*N/A","","","","","","Q2-2019"],
    [2576,2576,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",15,"*N/A","","","","","","Q3-2019"],
    [2577,2577,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",4,"*N/A","","","","","","Q4-2019"],
    [2578,2578,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",2,"*N/A","","","","","","Q4-2019"],
    [2579,2579,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",14,"*N/A","","","","","","Q4-2019"],
    [2580,2580,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",6,"*N/A","","","","","","Q2-2020"],
    [2581,2581,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",9,"*N/A","","","","","","Q4-2019"],
    [2582,2582,"SHIP CONSTRUCTION TURNKEY","Wicklow","Kirvin Hill, Broomhall, Rathnew",2,"*N/A","","","","","","Q2-2019"],
    [2583,2583,"SHIP CONSTRUCTION TURNKEY","Wicklow","Weaver Square, Baltinglass, Co. Wicklow",2,"*N/A","","","","Stage 4 approved Q1-2020, the scheme is fully approved.","",""],
    [2584,2584,"SHIP CONSTRUCTION TURNKEY","Wicklow","Carraig Beag, WicklowTown",5,"*N/A","","","","","","Q3-2020"],
    [2585,2585,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bramble Hill, Lugduff, Tinahely",2,"*N/A","","","","","","Q4-2020"],
    [2586,2586,"SHIP CONSTRUCTION TURNKEY","Wicklow","The Birches, Ballinaclash",2,"*N/A","","","","","","Q2-2021"],
    [2587,2587,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods Phase 2",2,"*N/A","","","","","","Q2-2020"],
    [2588,2588,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods Phase 2",1,"*N/A","","","","","","Q4-2020"],
    [2589,2589,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bramble Hill, Lugduff, Tinahely",2,"*N/A","","","","","","Q1-2021"],
    [2590,2590,"SHIP CONSTRUCTION TURNKEY","Wicklow","Vartry Heights, Roundwood, Co. Wicklow",3,"*N/A","","","","Stage 4 approved Q1-2021, the scheme is fully approved.","",""],
    [2591,2591,"SHIP CONSTRUCTION TURNKEY","Wicklow","Avonmore View, Rathdrum",13,"*N/A","","","","Stage 4 approved Q2-2021, the scheme is fully approved.","",""],
    [2592,2592,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bramble Hill, Lugduff, Tinahely",1,"*N/A","","","","","","Q2-2021"],
    [2593,2593,"SHIP CONSTRUCTION SINGLE STAGE","Wicklow","Church Lane, Newcastle",1,"*N/A","","","","Stage 4 approved Q3-2021, the scheme is fully approved.","",""],
    [2594,2594,"SHIP CONSTRUCTION RAPID","Wicklow","Sli na Slainte, Whitehall, Baltinglass",7,"*N/A","","","","","","Q4-2019"],
    [2595,2595,"SHIP CONSTRUCTION RAPID","Wicklow","Merrymeeting View, Rathnew",46,"*N/A","","","","","","Q2-2021"],
    [2596,2596,"SHIP CONSTRUCTION RAPID","Wicklow","Coolattin Oaks, Carnew (Phase 4)",22,"*N/A","","","","","","Q4-2020"],
    [2597,2597,"SHIP CONSTRUCTION RAPID","Wicklow","Shillelagh Phase 4",20,"*N/A","","Stage 2 approved Q2-2021, full design/tender being prepared.","","","",""],
    [2598,2598,"SHIP CONSTRUCTION RAPID","Wicklow","Ashtown Lane, Wicklow Town",40,"*N/A","","","","","Q3-2020",""],
    [2599,2599,"SHIP CONSTRUCTION RAPID","Wicklow","Ard na Greine, West Ward, Bray",31,"*N/A","","","","","Q2-2020",""],
    [2600,2600,"SHIP CONSTRUCTION RAPID","Wicklow","Avondale Heights, Rathdrum",20,"*N/A","","","","","Q3-2021",""],
    [2601,2601,"SHIP CONSTRUCTION RAPID","Wicklow","Sheehan Court, Back Street, Arklow",7,"*N/A","","","","","Q2-2021",""],
    [2602,2602,"SHIP CONSTRUCTION RAPID","Wicklow","Mountainview, Moneycarroll, Newtownmountkennedy, Co. Wicklow",22,"*N/A","","","","","Q3-2020",""],
    [2603,2603,"SHIP CONSTRUCTION RAPID","Wicklow","Sli na Slainte, Whitehall, Baltinglass",27,"*N/A","","","","","","Q1-2020"],
    [2604,2604,"SHIP CONSTRUCTION RAPID","Wicklow","Three Trouts, Greystones",40,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [2605,2605,"SHIP CONSTRUCTION RAPID","Wicklow","Greenhills Road, Wicklow Town",36,"*N/A","","","","","Q2-2021",""],
    [2606,2606,"SHIP CONSTRUCTION RAPID","Wicklow","Cedar Court, Schools Road, Bray",14,"*N/A","","Stage 2 approved Q3-2020, full design/tender being prepared.","","","",""],
    [2607,2607,"SHIP CONSTRUCTION RAPID","Wicklow","Coolattin Oaks, Carnew (Phase 4)",8,"*N/A","","","","","","Q1-2021"],
    [2608,2608,"SHIP CONSTRUCTION RAPID","Wicklow","Rathnew, Merrymeeting, Co. Wicklow (Phase 2)",21,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2609,2609,"SHIP CONSTRUCTION RAPID","Wicklow","Tinahely & Lugduff, Co Wicklow",20,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [2610,2610,"SHIP CONSTRUCTION RAPID","Wicklow","Carrigoona, Bray",20,"*N/A","Stage 1 approved Q3-2021, outline design and costs being prepared.","","","","",""],
    [2611,2611,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow (Phase 3)",21,"*N/A","","","","","Q4-2019",""],
    [2612,2612,"SHIP CONSTRUCTION","Wicklow","10A & 10 B Castle Villas, Greystones",2,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2613,2613,"SHIP CONSTRUCTION","Wicklow","Druids Brook, Kilcoole",2,"*N/A","","","","","","Q3-2019"],
    [2614,2614,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow",17,"*N/A","","","","","","Q3-2019"],
    [2615,2615,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow (Phase 2)",26,"*N/A","","","","","Q4-2019",""],
    [2616,2616,"SHIP CONSTRUCTION","Wicklow","FCA Hall, Wicklow Town",8,"*N/A","","","","","","Q4-2020"],
    [2617,2617,"SHIP CONSTRUCTION","Wicklow","Kilmantain Place, Bray",4,"*N/A","","","","","","Q4-2020"],
    [2618,2618,"SHIP CONSTRUCTION","Wicklow","O'Byrne Road, Bray",1,"*N/A","","","","","","Q4-2018"],
    [2619,2619,"SHIP CONSTRUCTION","Wicklow","St Mary's Rd., Arklow (Old Library Site)",7,"*N/A","","","","","","Q4-2018"],
    [2620,2620,"SHIP CONSTRUCTION","Wicklow","Jameson Heights,  Kilmacanogue",20,"*N/A","","","","","","Q4-2020"],
    [2621,2621,"SHIP CONSTRUCTION","Wicklow","Avondale Heights, Rathdrum",20,"*N/A","","","","","","Q4-2018"],
    [2622,2622,"SHIP CONSTRUCTION","Wicklow","Kilbride Lane, Bray (Murphy's Lands)",23,"*N/A","","","","","","Q4-2020"],
    [2623,2623,"SHIP CONSTRUCTION","Wicklow","16A Oak Drive, Blessington",1,"*N/A","","","","","","Q3-2019"],
    [2624,2624,"SHIP CONSTRUCTION","Wicklow","Carrig Eden, 1 Marine Road, Greystones (Phases 1 and 2)",35,"*N/A","","","","","","Q4-2020"],
    [2625,2625,"SHIP CONSTRUCTION","Wicklow","Farrankelly, Greystones (Phase 2)",24,"*N/A","","","","","","Q2-2020"],
    [2626,2626,"SHIP CONSTRUCTION","Wicklow","Blackhills, Glenealy, Co. Wicklow",2,"*N/A","","","Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.","","",""],
    [2627,2627,"SHIP CONSTRUCTION","Wicklow","Age Friendly Apartments at Main St, Kilcoole, Greystones",4,"*N/A","","Stage 2 approved Q3-2021, full design/tender being prepared.","","","",""],
    [2628,2628,"SHIP CONSTRUCTION","Wicklow","Mill Road, Greystones",2,"*N/A","","Stage 2 approved Q1-2021, full design/tender being prepared.","","","",""],
    [2629,2629,"SHIP CONSTRUCTION","Wicklow","Carraig Eden, Greysones (Phase 3)",14,"*N/A","Stage 1 approved Q4-2020, outline design and costs being prepared.","","","","",""],
    [2630,2630,"SHIP CONSTRUCTION","Wicklow","Kilbride Lane, Bray (Murphy's Lands)",19,"*N/A","","","","","","Q2-2021"],
    [2631,2631,"SHIP CONSTRUCTION","Wicklow","Knockroe, Delgany, Co. Wicklow",2,"*N/A","Stage 1 approved Q1-2021, outline design and costs being prepared.","","","","",""],
    [2632,2632,"SHIP CONSTRUCTION","Wicklow","Ard Rua, Barndarraig, Arklow, Co. Wicklow",12,"*N/A","Stage 1 approved Q2-2021, outline design and costs being prepared.","","","","",""],
    [2633,2633,"CAS CONSTRUCTION TURNKEY","Wicklow","Rathcoran Square, Baltinglass",8,"Peter McVerry Trust Ltd","","","","","","Q2-2021"],
    [2634,2634,"CAS CONSTRUCTION TURNKEY","Wicklow","Apt 1 & 2 Carrigbrae House, The Friary, Church Road, Bray",2,"Ark Housing Association Limited","","","","","","Q4-2020"],
    [2635,2635,"CAS CONSTRUCTION SINGLE STAGE","Wicklow","Hollybrook Park, Bray, Co. Wicklow",4,"St. John of God Housing Association Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [2636,2636,"CALF Turnkey","Wicklow","Abbey St, Wicklow  (Phase 1)",6,"Tuath Housing Association","","","","","","Q4-2018"],
    [2637,2637,"CALF Turnkey","Wicklow","Avondale Grange, Ballygannon, Rathdrum, Co. Wicklow (Phase 1)*",36,"Respond","","","","","Q2-2021",""],
    [2638,2638,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 1)*",9,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2639,2639,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 2)*",8,"Clï¿½id Housing","","","","","","Q3-2020"],
    [2640,2640,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 3)*",4,"Clï¿½id Housing","","","","","","Q4-2020"],
    [2641,2641,"CALF Turnkey","Wicklow","Ballycrone Manor, Kilcoole, Co. Wicklow (Phase 1)*",18,"Respond","","","","","Q4-2020",""],
    [2642,2642,"CALF Turnkey","Wicklow","Fairgreen Manor, Dunlavin, Co. Wicklow (Phase 1)*",40,"Circle Voluntary Housing Association Ltd","","","","","","Q3-2021"],
    [2643,2643,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co Wicklow  (Phase 1)*",5,"Tuath Housing Association","","","","","","Q2-2018"],
    [2644,2644,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 1)*",8,"Tuath Housing Association","","","","","","Q4-2018"],
    [2645,2645,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 2)*",7,"Tuath Housing Association","","","","","","Q2-2019"],
    [2646,2646,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 3)*",4,"Tuath Housing Association","","","","","","Q4-2019"],
    [2647,2647,"CALF Turnkey","Wicklow","Glenheron, Greystones, County Wicklow (Phase 1)",2,"Tuath Housing Association","","","","","","Q4-2020"],
    [2648,2648,"CALF Turnkey","Wicklow","Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 1)*",15,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2018"],
    [2649,2649,"CALF Turnkey","Wicklow","Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 2)",73,"Co - Operative Housing Ireland Society Limited","","","","","","Q3-2019"],
    [2650,2650,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow (Phase 1)",11,"Tuath Housing Association","","","","","Q2-2021",""],
    [2651,2651,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow (Phase 2)",12,"Tuath Housing Association","","","","","Q2-2021",""],
    [2652,2652,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow (Phase 3)",13,"Tuath Housing Association","","","","","Q2-2021",""],
    [2653,2653,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow (Phase 4)",17,"Tuath Housing Association","","","","","Q2-2021",""],
    [2654,2654,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow (Phase 5)*",35,"Tuath Housing Association","","","","","Q2-2021",""],
    [2655,2655,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)",11,"Tuath Housing Association","","","","","","Q3-2020"],
    [2656,2656,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)",15,"Tuath Housing Association","","","","","Q4-2020",""],
    [2657,2657,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)",14,"Tuath Housing Association","","","","","","Q3-2020"],
    [2658,2658,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)",13,"Tuath Housing Association","","","","","Q4-2020",""],
    [2659,2659,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 3)",13,"Tuath Housing Association","","","","","","Q4-2020"],
    [2660,2660,"CALF Turnkey","Wicklow","Lower Main Street, Arklow, Co. Wicklow (Phase 1)",4,"Clanmil Housing Association Ireland","","","","","Q2-2021",""],
    [2661,2661,"CALF Turnkey","Wicklow","Meadow Gate, Marlton Road, Wicklow Town (Phase 1)*",4,"Tuath Housing Association","","","","","","Q4-2020"],
    [2662,2662,"CALF Turnkey","Wicklow","Phase 2, Hazelbrook, Rathnew, Co. Wicklow (Phase 1)",56,"Co - Operative Housing Ireland Society Limited","","","","","","Q4-2019"],
    [2663,2663,"CALF Turnkey","Wicklow","Rathcoran House, Baltinglass, Co. Wicklow (Phase 1)*",16,"Respond","","","","","","Q4-2020"],
    [2664,2664,"CALF Turnkey","Wicklow","Rathcoran House, Baltinglass, Co. Wicklow (Phase 2)*",24,"Respond","","","","","","Q2-2021"],
    [2665,2665,"CALF Turnkey","Wicklow","Rathcoran House, Baltinglass, Co. Wicklow (Phase 3)",16,"Respond","","","","","","Q3-2021"],
    [2666,2666,"CALF Turnkey","Wicklow","Sessile Oaks, Ballyguile, Wicklow, Co. Wicklow (Phase 1)*",14,"Tuath Housing Association","","","","","Q1-2017",""],
    [2667,2667,"CALF Turnkey","Wicklow","Sessile Oaks, Ballyguile, Wicklow, Co. Wicklow (Phase 2)",10,"Tuath Housing Association","","","","","Q1-2017",""],
    [2668,2668,"CALF Turnkey","Wicklow","Sessile Oaks, Ballyguile, Wicklow, Co. Wicklow (Phase 3)",4,"Tuath Housing Association","","","","","Q1-2017",""],
    [2669,2669,"CALF Turnkey","Wicklow","Ternlee, Coldross Lane, Kilcoole, Co. Wicklow (Phase 1)*",4,"Clï¿½id Housing","","","","","","Q2-2019"],
    [2670,2670,"CALF Turnkey","Wicklow","Ternlee, Coldross Lane, Kilcoole, Co. Wicklow (Phase 2)*",2,"Clï¿½id Housing","","","","","","Q4-2019"],
    [2671,2671,"CALF Turnkey","Wicklow","The Meadows, Ballynerrin, Wicklow Town (Phase 1)*",7,"Tuath Housing Association","","","","","","Q4-2018"],
    [2672,2672,"CALF Turnkey","Wicklow","The Old Rectory, Blessington, Co. Wicklow (Phase 1)*",45,"Co - Operative Housing Ireland Society Limited","","","","","Q3-2020",""],
    [2673,2673,"CALF Turnkey","Wicklow","Viewmount, Rathdrum, County Wicklow (Phase 1)",4,"Tuath Housing Association","","","","","","Q2-2020"],
    [2674,2674,"CALF Turnkey","Wicklow","Woodpark, Rathdrum, Co. Wicklow (Phase 1)*",4,"Tuath Housing Association","","","","","","Q3-2019"],
    [2675,2675,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Wicklow","Convent Lands (Phase 1)",23,"*N/A","","","","","","Q2-2020"],
    [2676,2676,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Wicklow","Convent Lands (Phase 2)",28,"*N/A","","","","","","Q3-2020"]
]}