﻿_id	No.	Funding Programme	LA	Scheme/Project Name	No. of Units	Approved Housing Body	Stage 1 Capital Appraisal	Stage 2 Pre Planning	Stage 3 Pre Tender design	Stage 4 Tender Report or Final Turnkey/CALF approval	On Site	Practical Completion
1	1	CALF CONSTRUCTION TURNKEY	Carlow	Sleaty Street, Graigcullen, Carlow	26	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
2	2	CALF CONSTRUCTION TURNKEY	Carlow	Barrett Street, Bagnalstown	10	Tintean Housing Association	""	""	""	""	Q2-2017	""
3	3	CAS CONSTRUCTION	Carlow	Mill Race Court, Carlow Town	14	Cluid Housing Association	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
4	4	CAS CONSTRUCTION	Carlow	Royal Oak Road, Bagenalstown	6	Respond!	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
5	5	CAS CONSTRUCTION	Carlow	Ballincarrig, Wexford Road	6	Tintean Housing Association Ltd	""	""	""	""	""	Q4-2016
6	6	SHIP CONSTRUCTION	Carlow	Bagenalstown	42	N/A	""	""	""	""	Q4-2017	""
7	7	SHIP CONSTRUCTION	Carlow	Moneybeg, Bagenalstown	24	N/A	""	""	""	""	""	Q3-2017
8	8	SHIP CONSTRUCTION	Carlow	Dublin Road, Tullow	21	N/A	""	""	""	""	Q4-2017	""
9	9	SHIP CONSTRUCTION	Carlow	Ard na Greine, Tullow	16	N/A	""	""	""	""	Q4-2017	""
10	10	SHIP CONSTRUCTION	Carlow	Rathvilly	10	N/A	""	""	""	""	""	Q2-2017
11	11	SHIP CONSTRUCTION	Carlow	The Laurels, Carlow Town	5	N/A	""	""	""	""	Q3-2017	""
12	12	SHIP CONSTRUCTION	Carlow	Maryborough St., Carlow	5	N/A	""	""	""	""	Q1-2016	""
13	13	SHIP CONSTRUCTION	Carlow	Hacketstown	4	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
14	14	SHIP CONSTRUCTION	Carlow	Mount Leinster Park, Carlow	4	N/A	""	""	""	""	""	Q4-2017
15	15	SHIP CONSTRUCTION	Carlow	Myshall	4	N/A	""	""	""	""	Q2-2017	""
16	16	SHIP CONSTRUCTION	Carlow	Pound Lane, Borris	4	N/A	""	""	""	""	""	Q3-2017
17	17	SHIP CONSTRUCTION	Carlow	Bilboa	2	N/A	""	""	""	""	Q4-2017	""
18	18	SHIP CONSTRUCTION	Carlow	Tullow (SRD)	1	N/A	""	""	""	""	""	Q3-2017
19	19	SHIP CONSTRUCTION	Carlow	Rathvilly (SRD)	1	N/A	""	""	""	""	Q4-2017	""
20	20	SHIP CONSTRUCTION TURNKEY	Carlow	Tullow Road, Carlow	63	N/A	""	""	""	""	Q4-2017	""
21	21	CALF CONSTRUCTION TURNKEY	Cavan	Cluain Dara, Kingscourt	16	Cluid Housing Association	""	""	""	""	""	Q4-2016
22	22	CALF CONSTRUCTION TURNKEY	Cavan	Drumalee Manor, Drumalee Phase 2	7	Tath Housing Association	""	""	""	""	Q1-2017	""
23	23	CALF CONSTRUCTION TURNKEY	Cavan	Drumalee Manor, Drumalee Phase 1	4	Tath Housing Association	""	""	""	""	Q1-2017	""
24	24	SHIP CONSTRUCTION	Cavan	Rosehill, Mullagh (Phase 6)	8	N/A	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
25	25	SHIP CONSTRUCTION	Cavan	Woodlands, Ballyhaise	8	N/A	""	""	""	""	Q4-2017	""
26	26	SHIP CONSTRUCTION	Cavan	Butlersbridge (Phase 2)	4	N/A	""	""	""	""	Q2-2017	""
27	27	SHIP CONSTRUCTION	Cavan	Butlersbridge (Phase 1)	2	N/A	""	""	""	""	""	Q2-2017
28	28	SHIP CONSTRUCTION	Cavan	Clones Road, Butlersbridge	2	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
29	29	CALF CONSTRUCTION	Clare	Bruachlan, Westbury	22	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF funding Q2-2016	""	""
30	30	CALF CONSTRUCTION TURNKEY	Clare	Lios Anama, Sixmilebridge	28	Co operative Ireland	""	""	""	""	""	Q4-2017
31	31	CAS CONSTRUCTION	Clare	Cahercalla, Ennis (Phase 2)	10	Cuan an Chlair Ltd	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
32	32	CAS CONSTRUCTION	Clare	Laurel Lodge, Clare Road, Ennis	3	Society of Saint Vincent de Paul	""	""	""	""	""	Q4-2016
33	33	SHIP CONSTRUCTION	Clare	Ashline, Kilrush Road, Ennis	40	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
34	34	SHIP CONSTRUCTION	Clare	Tullyglass, Shannon	21	N/A	""	Stage 2 approved in Q2-2016, full design/tender being prepared.	""	""	""	""
35	35	SHIP CONSTRUCTION	Clare	Seaview Park, Quilty	18	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
36	36	SHIP CONSTRUCTION	Clare	Feakle	11	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
37	37	SHIP CONSTRUCTION	Clare	Glor Srutha, Knockbrack Lower, Clonlara	9	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
38	38	SHIP CONSTRUCTION	Clare	Roslevan, Ennis	8	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
39	39	SHIP CONSTRUCTION TURNKEY	Clare	Haggard View, Clarecastle	4	Anvers Housing Association Ltd	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
40	40	SHIP CONSTRUCTION TURNKEY	Clare	River View, School Road, Corofin	2	N/A	""	""	""	""	Q4-2017	""
41	41	CALF CONSTRUCTION	Cork City	Mile Stream, Shanakiel, Cork City 	50	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
42	42	CALF CONSTRUCTION	Cork City	124 Lr. Glanmire Road & 2 Breamer, Cork	6	Galtan Ltd	""	""	""	""	Q1-2017	""
43	43	CALF CONSTRUCTION TURNKEY	Cork City	the Meadows, Knopckacullen Ease, Gurranabraher, Cork	52	Tath Housing Association	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
44	44	CALF CONSTRUCTION TURNKEY	Cork City	Millfield Cottages, Blackpool	18	Respond!	""	""	""	""	Q1-2017	""
45	45	CALF CONSTRUCTION TURNKEY	Cork City	Leitrim Street, Cork City	18	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q3-2016	""	""
46	46	CALF CONSTRUCTION TURNKEY	Cork City	Popes Road, Blackpool	7	Cluid Housing Association	""	""	""	""	Q1-2017	""
47	47	CAS CONSTRUCTION	Cork City	Edel House, Grattan Street	33	Good Shepherd Services Ltd	""	Stage 2 approved in Q1-2016, full design/tender being prepared.	""	""	""	""
48	48	CAS CONSTRUCTION	Cork City	Thomas Davis Street (Phase 1)	28	Respond!	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
49	49	CAS CONSTRUCTION	Cork City	Saint Vincent's Convent, Vincent's Ave/St. Mary's Street	25	Respond!	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
50	50	CAS CONSTRUCTION	Cork City	27-29 Dublin Street, Blackpool	10	Respond!	""	""	""	""	Q4-2016	""
51	51	CAS CONSTRUCTION	Cork City	St. Joachim & Anne's, Anglesea Street	8	Simon Community : Cork Simon	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
52	52	CAS CONSTRUCTION	Cork City	Ceanncora Lawn, Ballinlough	1	Cork Mental Health Voluntary Housing Association Ltd	""	""	""	""	Q2-2017	""
53	53	REGENERATION	Cork City	Phase 2 A Knocknaheeny	47	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
54	54	REGENERATION	Cork City	Phase 1 C Knocknaheeny	41	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
55	55	REGENERATION	Cork City	Phase 2 B Knocknaheeny	36	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
56	56	REGENERATION	Cork City	Phase 1 B Knocknaheeny	29	N/A	""	""	""	""	""	Q4-2017
57	57	SHIP CONSTRUCTION	Cork City	Deanrock, Togher	65	N/A	""	""	""	""	Q4-2016	""
58	58	SHIP CONSTRUCTION	Cork City	Boyces Street	51	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
59	59	SHIP CONSTRUCTION	Cork City	Gerald Griffin Street	41	N/A	""	""	""	""	Q3-2017	""
60	60	SHIP CONSTRUCTION	Cork City	Shandon Street/John Philpott Curran Street	9	N/A	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
61	61	SHIP CONSTRUCTION	Cork City	St. Johns Well	6	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
62	62	SHIP CONSTRUCTION	Cork City	Churchfield Place East	3	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
63	63	SHIP CONSTRUCTION	Cork City	Cappanoole	2	N/A	""	""	""	""	""	Q4-2016
64	64	SHIP CONSTRUCTION	Cork City	The Meadows, Knocknacullen	1	N/A	""	""	""	""	""	Q3-2016
65	65	SHIP CONSTRUCTION TURNKEY	Cork City	Whites Street	43	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
66	66	SHIP CONSTRUCTION TURNKEY	Cork City	Church Road	43	N/A	""	""	""	""	Q2-2017	""
67	67	SHIP CONSTRUCTION TURNKEY	Cork City	Barack Street	32	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
68	68	SHIP CONSTRUCTION TURNKEY	Cork City	Arus Mhuire	30	N/A	""	""	""	""	Q4-2017	""
69	69	SHIP CONSTRUCTION TURNKEY	Cork City	Sheridan Park, Tramore Road	28	N/A	""	""	""	""	""	Q4-2016
70	70	SHIP CONSTRUCTION TURNKEY	Cork City	Woods Street	16	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
71	71	SHIP CONSTRUCTION TURNKEY	Cork City	High Street	9	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
72	72	SHIP CONSTRUCTION TURNKEY	Cork City	Faranree	5	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
73	73	SHIP CONSTRUCTION TURNKEY	Cork City	Ard Aoibhinn, Banduff, Mayfield	5	N/A	""	""	""	""	Q3-2017	""
74	74	SHIP CONSTRUCTION TURNKEY	Cork City	1-4 Marble Lane	4	N/A	""	""	""	""	""	Q4-2017
75	75	SHIP CONSTRUCTION TURNKEY	Cork City	Tramore Road	4	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
76	76	SHIP CONSTRUCTION TURNKEY	Cork City	Corcorans Quay	3	N/A	""	""	""	Stage 4 approved in Q1-2017, the scheme is now fully approved.	""	""
77	77	CALF CONSTRUCTION	Cork County	Cappagh, Ballynacubby, Kinsale, Co. Cork	40	Cluid Housing Association	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
78	78	CALF CONSTRUCTION	Cork County	Firgrove Harrisons Lane Charleville	6	Co operative Ireland	""	""	""	""	""	Q4-2017
79	79	CALF CONSTRUCTION 	Cork County	Church View, Enniskeane	12	Cluid Housing Association	""	""	""	""	Q1-2017	""
80	80	CALF CONSTRUCTION TURNKEY	Cork County	Tanners Field, Bandon, Co Cork 	11	Tath Housing Association Ltd	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
81	81	CALF CONSTRUCTION TURNKEY	Cork County	College Manor, Cobh	10	Tath Housing Association	""	""	""	""	""	Q4-2016
82	82	CALF CONSTRUCTION TURNKEY	Cork County	Ticknock, Cobh	8	Respond!	""	""	""	""	Q1-2017	""
83	83	CALF CONSTRUCTION TURNKEY	Cork County	Beach Road, Passage West	3	Cluid Housing Association	""	""	""	""	""	Q4-2017
84	84	CAS CONSTRUCTION	Cork County	Fellowship House, Togher	31	Tabor Lodge Addiction ? Housing Services Ltd	""	""	""	""	Q1-2017	""
85	85	CAS CONSTRUCTION	Cork County	Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay	16	Cluid Housing Association	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
86	86	CAS CONSTRUCTION	Cork County	Townlands, Rosscarbery	9	Rosscarbery Housing Association Ltd	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
87	87	CAS CONSTRUCTION	Cork County	Avenue House, Bandon	9	Bandon Geriatric ? Community Council	""	""	""	""	Q3-2016	""
88	88	CAS CONSTRUCTION	Cork County	Church View, Love Lane, Charleville	6	Charleville Care Project Ltd	""	Stage 2 approved in Q3-2015, full design/tender being prepared.	""	""	""	""
89	89	CAS CONSTRUCTION	Cork County	St. Francis Court, Youghal	4	Respond!	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
90	90	CAS CONSTRUCTION	Cork County	Cuan Barra, Kilmore, Ballingeary	3	Coiste Tithe Uibh Laoire Teoranta	""	""	""	""	Q4-2017	""
91	91	SHIP CONSTRUCTION	Cork County	Poulavone, Ballincollig	57	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
92	92	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	56	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
93	93	SHIP CONSTRUCTION	Cork County	Kilnagleary, Carrigaline	49	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
94	94	SHIP CONSTRUCTION	Cork County	Station Road, Blarney	18	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
95	95	SHIP CONSTRUCTION	Cork County	Bluepool, Kanturk	16	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
96	96	SHIP CONSTRUCTION	Cork County	Ard Na Greine, Cortmacsherry	15	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
97	97	SHIP CONSTRUCTION	Cork County	Kilnagleary, Carrigaline (Phase 4)	15	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
98	98	SHIP CONSTRUCTION	Cork County	Oliver Plunkett Hill, Fermoy	10	N/A	""	""	""	""	""	Q2-2017
99	99	SHIP CONSTRUCTION	Cork County	Tower View, Cloyne, East Cork	9	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
100	100	SHIP CONSTRUCTION	Cork County	Fairfield, Macroom	7	N/A	""	""	""	""	Q4-2017	""
101	101	SHIP CONSTRUCTION	Cork County	Model Village, Dripsey	6	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
102	102	SHIP CONSTRUCTION	Cork County	Townsend Street, Skibbereen	6	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
103	103	SHIP CONSTRUCTION	Cork County	Droum, Castletownbere	2	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
104	104	SHIP CONSTRUCTION	Cork County	Castle Treasure Grove	1	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
105	105	SHIP CONSTRUCTION	Cork County	Newtown, Bantry	1	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
106	106	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	52	N/A	""	""	""	""	Q4-2017	""
107	107	SHIP CONSTRUCTION TURNKEY	Cork County	College Wood, Cobh	31	N/A	""	""	""	""	""	Q4-2017
108	108	SHIP CONSTRUCTION TURNKEY	Cork County	Bantry	30	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
109	109	SHIP CONSTRUCTION TURNKEY	Cork County	CulAird, Carraigtwohill	29	N/A	""	""	""	""	""	Q4-2017
110	110	SHIP CONSTRUCTION TURNKEY	Cork County	Church Road, Carrigtwohill	25	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
111	111	SHIP CONSTRUCTION TURNKEY	Cork County	Kanturk	25	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
112	112	SHIP CONSTRUCTION TURNKEY	Cork County	St. Mary?s Road, Dunmanway	20	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
113	113	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas (Phase 2)	16	N/A	""	""	""	""	""	Q1-2017
114	114	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas (Phase 3)	12	N/A	""	""	""	""	""	Q4-2017
115	115	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas (Phase 1)	12	N/A	""	""	""	""	""	Q1-2017
116	116	SHIP CONSTRUCTION TURNKEY	Cork County	Inis Alainn & Castleoaks, Bandon	11	N/A	""	""	""	""	""	Q4-2017
117	117	SHIP CONSTRUCTION TURNKEY	Cork County	Downeen Cross, Rosscarbery	7	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
118	118	SHIP CONSTRUCTION TURNKEY	Cork County	Claragh Road, Millstreet	6	N/A	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
119	119	SHIP CONSTRUCTION TURNKEY	Cork County	Beacon Point	6	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
120	120	SHIP CONSTRUCTION TURNKEY	Cork County	Corrin View	6	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
121	121	SHIP CONSTRUCTION TURNKEY	Cork County	Gleann Tuairigh, Youghal	2	N/A	""	""	""	""	Q4-2017	""
122	122	SHIP CONSTRUCTION TURNKEY	Cork County	Clondulane, Fermoy	2	N/A	""	""	""	""	""	Q4-2017
123	123	CALF CONSTRUCTION	DLR	Clays Farm, Ballyogan Road (Phase 1)* 	44	The Iveagh Trust	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
124	124	CALF CONSTRUCTION	DLR	Abbeyview House, Monkstown	8	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q1-2015	""	""
125	125	CALF CONSTRUCTION 	DLR	Respond & Tuath Project Dublin 18 area.	56	Respond!	""	""	""	Scheme approved for CALF funding Q1-2017	""	""
126	126	CALF CONSTRUCTION TURNKEY	DLR	Respond & Tuath Project Dublin 18 area.	49	Tath Housing Association	""	""	""	Scheme approved for CALF funding Q1-2017	""	""
127	127	CALF CONSTRUCTION TURNKEY	DLR	Hyde Road, Belmont, Stepaside	8	Respond!	""	""	""	""	Q3-2016	""
128	128	CALF CONSTRUCTION TURNKEY	DLR	Bishops Gate, Kilternan, Dublin 18	6	Cluid Housing Association	""	""	""	""	Q3-2017	""
129	129	CALF CONSTRUCTION TURNKEY	DLR	The Avenue, Glenside, Carrickmines Green, Dublin 18 *	5	Fold Ireland Housing Association	""	""	""	""	Q3-2017	""
130	130	CALF CONSTRUCTION TURNKEY	DLR	Woodbank, Dublin Rd, Shankill *	4	Cluid Housing Association	""	""	""	""	""	Q3-2017
131	131	CALF CONSTRUCTION TURNKEY	DLR	Stillorgan Gate, Kilmacud Road Upper, Co. Dublin *	4	Cluid Housing Association	""	""	""	""	""	Q4-2017
132	132	CAS CONSTRUCTION	DLR	30 Obelisk Walk, Blackrock	4	St. John of God Housing Association Ltd	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
133	133	SHIP CONSTRUCTION	DLR	Fitzgerald Park	50	N/A	""	""	""	""	Q4-2016	""
134	134	SHIP CONSTRUCTION	DLR	Rosemount Court	44	N/A	""	""	""	""	Q4-2016	""
135	135	SHIP CONSTRUCTION	DLR	Rochestown House (Phase 2)	34	N/A	""	""	""	""	""	Q1-2016
136	136	SHIP CONSTRUCTION	DLR	Broadford Rise	21	N/A	""	""	""	""	Q3-2017	""
137	137	SHIP CONSTRUCTION	DLR	Cromlech Close	15	N/A	""	""	""	""	""	Q3-2016
138	138	SHIP CONSTRUCTION	DLR	Rochestown House (Phase 3)	14	N/A	""	""	""	""	Q3-2016	""
139	139	SHIP CONSTRUCTION	DLR	The Brambles Park Close Sallynoggin	10	N/A	""	""	""	""	Q1-2017	""
140	140	SHIP CONSTRUCTION	DLR	66 George's Street, Dun Laoghaire	4	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
141	141	SHIP CONSTRUCTION	DLR	132 Pottery Road, Dun Laoghaire	4	N/A	""	""	""	""	Q4-2017	""
142	142	SHIP CONSTRUCTION	DLR	49 The Mews Sallynoggin Park	4	N/A	""	""	""	""	""	Q4-2017
143	143	SHIP CONSTRUCTION	DLR	St Michael's Terrace	4	N/A	""	""	""	""	""	Q3-2017
144	144	SHIP CONSTRUCTION	DLR	Clontibret House	4	N/A	""	""	""	""	""	Q4-2016
145	145	SHIP CONSTRUCTION	DLR	33,35, & 37 Temple Road	3	N/A	""	""	""	""	Q3-2017	""
146	146	SHIP CONSTRUCTION	DLR	Assistant Harbour Master House	2	N/A	""	""	""	""	""	Q3-2017
147	147	SHIP CONSTRUCTION	DLR	41 Ballyogan Ave., Ballyogan, Co. Dublin	2	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
148	148	SHIP CONSTRUCTION	DLR	Shanganagh Park Lodge	1	N/A	""	""	""	""	""	Q2-2016
149	149	SHIP CONSTRUCTION RAPID	DLR	Glenamuck/Stillorgan (Rockville Drive)	14	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
150	150	SHIP CONSTRUCTION RAPID	DLR	George's Place	12	N/A	""	""	""	""	Q3-2017	""
151	151	SHIP CONSTRUCTION TURNKEY	DLR	Hazelbrook, Nutgrove, Churchtown	28	N/A	""	""	""	""	""	Q4-2017
152	152	CALF CONSTRUCTION	Donegal	Ballaghderg, Letterkenny, Co Donegal 	33	Respond!	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
153	153	CALF CONSTRUCTION TURNKEY	Donegal	Ernedale Heights, Ballyshannon	11	Cluid Housing Association	""	""	""	""	Q3-2017	""
154	154	CALF CONSTRUCTION TURNKEY	Donegal	Forge Road, Donegal	4	Cluid Housing Association	""	""	""	""	""	Q3-2016
155	155	CAS CONSTRUCTION	Donegal	Willowbrook, Glencar, Letterkenny	40	Apex Housing Association	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
156	156	CAS CONSTRUCTION	Donegal	Meenmore, Dungloe	15	County Donegal Parents and Friends Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
157	157	CAS CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	10	Oaklee Housing Trust	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
158	158	CAS CONSTRUCTION	Donegal	Glenrowan House, Drumkeen, Stranorlar	6	Apex Housing Association	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
159	159	CAS CONSTRUCTION	Donegal	Dunshenny House, Derry Road, Carndonagh	5	Apex Housing Association	""	""	""	""	Q2-2017	""
160	160	SHIP CONSTRUCTION	Donegal	Long Lane, Letterkenny	29	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
161	161	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	N/A	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
162	162	SHIP CONSTRUCTION	Donegal	Buncrana - Rockytown (Phase 1)	21	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
163	163	SHIP CONSTRUCTION	Donegal	Carrigart (Phase 1)	17	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
164	164	SHIP CONSTRUCTION	Donegal	Dunfanaghy	13	N/A	""	Stage 2 approved in Q2-2016, full design/tender being prepared.	""	""	""	""
165	165	SHIP CONSTRUCTION	Donegal	Meadow Hill, Raphoe	11	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
166	166	SHIP CONSTRUCTION	Donegal	Emerald Drive, Killybegs (Phase 6)	9	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
167	167	SHIP CONSTRUCTION	Donegal	Radharc na Tra Breige, Malin (Phase 3)	8	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
168	168	SHIP CONSTRUCTION	Donegal	Manorcunningham (Phase 2)	8	N/A	""	""	""	""	Q3-2017	""
169	169	SHIP CONSTRUCTION	Donegal	Ardara (Phase 3)	8	N/A	""	""	""	""	""	Q2-2017
170	170	SHIP CONSTRUCTION	Donegal	Newtoncunningham	7	N/A	""	""	""	""	Q1-2017	""
171	171	SHIP CONSTRUCTION	Donegal	Cois Abhainn, St Johnston (Phase 2)	6	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
172	172	SHIP CONSTRUCTION	Donegal	Carndonagh - Abbots Wood (Phase 2)	4	N/A	""	""	""	""	Q3-2017	""
173	173	SHIP CONSTRUCTION	Donegal	Manorcunningham (Phase 1)	2	N/A	""	""	""	""	""	Q2-2017
174	174	SHIP CONSTRUCTION	Donegal	Ard Connell, Ardara (SRD)	1	N/A	""	""	""	""	""	Q1-2017
175	175	SHIP CONSTRUCTION TURNKEY	Donegal	Gleann Na Greine, Mullindrait, Stranorlar	21	N/A	""	""	""	""	Q2-2017	""
176	176	CALF CONSTRUCTION	Dublin City	St Mary?s Mansions, Dublin 1	80	Cluid Housing Association	""	""	""	""	Q4-2017	""
177	177	CALF CONSTRUCTION	Dublin City	Orchard Lawns, Ballyfermot	72	Co-operative Housing Ireland	""	""	""	""	Q4-2016	""
178	178	CALF CONSTRUCTION	Dublin City	Annamore Court, Ballyfermot	70	The Iveagh Trust	""	""	""	""	""	Q2-2017
179	179	CALF CONSTRUCTION	Dublin City	Tonlegee Road, Dublin 5 	47	Fold Housing Association Ireland Ltd	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
180	180	CALF CONSTRUCTION	Dublin City	Dolphin Park, Rialto, Dublin 8	43	Fold Ireland Housing Association	""	""	""	Scheme approved for Revised CALF funding Q3-2017	""	""
181	181	CALF CONSTRUCTION	Dublin City	Richmond Road, Dublin 9	39	Co-operative Housing Ireland	""	""	""	""	Q2-2017	""
182	182	CALF CONSTRUCTION	Dublin City	Raleigh Court, Crumlin	33	Tath Housing Association	""	""	""	""	Q2-2017	""
183	183	CALF CONSTRUCTION	Dublin City	Broome Lodge, Dunmanus Court, Cabra	33	Cluid Housing Association	""	""	""	""	""	Q4-2017
184	184	CALF CONSTRUCTION	Dublin City	5 6 Johns Lane West, Dublin 8	31	Focus Ireland	""	""	""	""	Q2-2017	""
185	185	CALF CONSTRUCTION	Dublin City	84 North King Street, Dublin 7 	30	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
186	186	CALF CONSTRUCTION	Dublin City	Poplar Row, Dublin 3	29	Oaklee Housing Trust	""	""	""	Scheme approved for revised CALF approval Q2-2017	""	""
187	187	CALF CONSTRUCTION	Dublin City	Harolds Cross, Dublin 6	28	Focus Ireland	""	""	""	""	""	Q4-2016
188	188	CALF CONSTRUCTION	Dublin City	Ballygall Road East - Phase 2	11	Fold Ireland Housing Association	""	""	""	""	""	Q1-2016
189	189	CALF CONSTRUCTION	Dublin City	Wad River Close, Ballymun, Dublin 9	9	Cluid Housing Association	""	""	""	Scheme re approved for approval Q3-2017	""	""
190	190	CALF CONSTRUCTION	Dublin City	Dominic Place, Dublin	9	The Aids Fund	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
191	191	CALF CONSTRUCTION TURNKEY	Dublin City	St Agnes Convent, Armagh Road, Crumlin, Dublin 12	97	Fold Ireland Housing Association	""	""	""	""	Q1-2017	""
192	192	CALF CONSTRUCTION TURNKEY	Dublin City	Clongriffin, Dublin 13	84	The Iveagh Trust	""	""	""	""	Q3-2017	""
193	193	CALF CONSTRUCTION TURNKEY	Dublin City	Long Mile Road, Dublin 12	61	Respond!	""	""	""	""	Q2-2017	""
194	194	CALF CONSTRUCTION TURNKEY	Dublin City	Thornwood, Beaumont - Phase 1	46	Tath Housing Association	""	""	""	""	""	Q3-2016
195	195	CALF CONSTRUCTION TURNKEY	Dublin City	Stormanstown Hall, Ballymun Road, (revised)	42	Oaklee Housing Trust	""	""	""	""	Q4-2016	""
196	196	CALF CONSTRUCTION TURNKEY	Dublin City	Thornwood, Beaumont - Final Phase	22	Tath Housing Association	""	""	""	""	""	Q1-2017
197	197	CALF CONSTRUCTION TURNKEY	Dublin City	An Riasc, Farnham Drive, Finglas - Phase 2	21	Tath Housing Association	""	""	""	""	""	Q1-2017
198	198	CALF CONSTRUCTION TURNKEY	Dublin City	Chanel College, Coolock Village, Malahide Road, Dublin 5	16	Respond!	""	""	""	""	""	Q4-2017
199	199	CALF CONSTRUCTION TURNKEY	Dublin City	An Riasc, Farnham Drive, Finglas - Phase 1	14	Tath Housing Association	""	""	""	""	""	Q4-2016
200	200	CALF CONSTRUCTION TURNKEY	Dublin City	An Riasc, Farnham Drive, Finglas - Phase 3	10	Tath Housing Association	""	""	""	""	""	Q2-2017
201	201	CALF CONSTRUCTION TURNKEY	Dublin City	175 176 North Strand Road, 5 Lamps, Dublin 1	10	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
202	202	CALF CONSTRUCTION TURNKEY	Dublin City	Milrose House, Bluebell Avenue, Dublin 12	8	Cluid Housing Association	""	""	""	""	""	Q4-2017
203	203	CALF CONSTRUCTION TURNKEY	Dublin City	Merville Court, Merville Avenue, Fairview	5	Co operative Ireland	""	""	""	""	""	Q1-2017
204	204	CALF CONSTRUCTION TURNKEY	Dublin City	Camac Place, Bluebell, Dublin 12	5	Oaklee Housing Trust	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
205	205	CALF CONSTRUCTION TURNKEY	Dublin City	An Riasc, Farnham Drive, Finglas - Final Phase	3	Tath Housing Association	""	""	""	""	""	Q3-2017
206	206	CALF CONSTRUCTION TURNKEY	Dublin City	11 13 Crumlin Village, Dublin 12 Phase 1	3	Cluid Housing Association	""	""	""	""	""	Q2-2017
207	207	CALF CONSTRUCTION TURNKEY	Dublin City	11 13 Crumlin Village, Dublin 12 Phase 2	2	Cluid Housing Association	""	""	""	""	""	Q3-2017
208	208	CALF CONSTRUCTION TURNKEY	Dublin City	An Riasc, Farnham Drive, Finglas - Final Phase	1	Tath Housing Association	""	""	""	""	Q4-2015	""
209	209	CAS CONSTRUCTION	Dublin City	Ellis Court, Dublin	23	Tath Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
210	210	CAS CONSTRUCTION	Dublin City	Beech Hill	19	Royal Hospital Donnybrook Voluntary Housing Association Ltd	""	""	""	""	Q4-2017	""
211	211	CAS CONSTRUCTION	Dublin City	180-187 Townsend Street	18	Peter McVerry Trust Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
212	212	CAS CONSTRUCTION	Dublin City	55B Arbour Hill, Dublin 7	18	Simon Community : Dublin Simon	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
213	213	CAS CONSTRUCTION	Dublin City	Rafter's Lane, Dublin 12	11	Walkinston Housing Association Ltd (WALK)	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
214	214	CAS CONSTRUCTION	Dublin City	Old Kilmainham Road, Dublin 8	11	Arlington Novas Ireland Ltd	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
215	215	CAS CONSTRUCTION	Dublin City	St Agatha's Court, North William Street, Dublin 1	11	Peter McVerry Trust Ltd	""	""	""	""	""	Q2-2017
216	216	CAS CONSTRUCTION	Dublin City	Broome Lodge, Dunmanus, Dublin 7	10	Cluid Housing Association	""	""	""	""	""	Q4-2017
217	217	CAS CONSTRUCTION	Dublin City	38/39 Bolton Street, Dublin 1	8	Arlington Novas Ireland Ltd	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
218	218	CAS CONSTRUCTION	Dublin City	"""Martanna House"" High Park, Grace Park Road,Dublin 9"	8	Respond!	""	""	""	""	Q4-2017	""
219	219	CAS CONSTRUCTION	Dublin City	26 New Street South, Dublin 8	8	Peter McVerry Trust Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
220	220	REGENERATION	Dublin City	Dolphin House, Dublin 8 (Phase 1)	100	N/A	""	""	""	""	Q4-2016	""
221	221	REGENERATION	Dublin City	Charlemont	79	N/A	""	""	""	""	""	Q4-2017
222	222	REGENERATION	Dublin City	Dominick Street	72	N/A	Stage 1 approved in Q2-2016, outline design and costs are now being prepared.	""	""	""	""	""
223	223	REGENERATION	Dublin City	O'Devaney Gardens	56	N/A	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
224	224	REGENERATION	Dublin City	St. Teresa's Gardens	50	N/A	Stage 1 approved in Q3-2013, outline design and costs are now being prepared.	""	""	""	""	""
225	225	REGENERATION	Dublin City	Buttercup, Darndale	19	N/A	""	""	""	""	""	Q4-2017
226	226	REGENERATION	Dublin City	Buttercup, Darndale	16	N/A	""	""	""	""	Q2-2017	""
227	227	REGENERATION	Dublin City	Sackville Avenue Cottages	12	N/A	Stage 1 approved in Q2-2016, outline design and costs are now being prepared.	""	""	""	""	""
228	228	REGENERATION	Dublin City	Maxwell Road	9	N/A	""	""	""	""	""	Q2-2016
229	229	SHIP CONSTRUCTION	Dublin City	Bunratty Road Phase 1c, Dublin 17	62	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
230	230	SHIP CONSTRUCTION	Dublin City	Cornamona, Ballyfermot, Dublin 12	60	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
231	231	SHIP CONSTRUCTION	Dublin City	St. Finbar's Court, Kilkieran Road, Dublin 7	46	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
232	232	SHIP CONSTRUCTION	Dublin City	Infirmary Road, Dublin 7	30	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
233	233	SHIP CONSTRUCTION	Dublin City	North King Street, Dublin 7	30	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
234	234	SHIP CONSTRUCTION	Dublin City	Priory Hall (2)	26	N/A	""	""	""	""	Q2-2017	""
235	235	SHIP CONSTRUCTION	Dublin City	Hampton Wood	25	N/A	""	""	""	""	""	Q4-2016
236	236	SHIP CONSTRUCTION	Dublin City	Belcamp B, Dublin 17	12	N/A	""	Stage 2 approved in Q3-2015, full design/tender being prepared.	""	""	""	""
237	237	SHIP CONSTRUCTION	Dublin City	Priory Hall (1)	9	N/A	""	""	""	""	""	Q1-2017
238	238	SHIP CONSTRUCTION	Dublin City	Ballybough Road, Dublin 1	7	N/A	""	""	""	""	Q1-2017	""
239	239	SHIP CONSTRUCTION RAPID	Dublin City	Cherry Orchard, Ballyfermot - Rathvilly & Woodbank Drive Finglas	70	N/A	""	""	""	""	Q4-2017	""
240	240	SHIP CONSTRUCTION RAPID	Dublin City	St Helena's Drive, Finglas	39	N/A	""	""	""	""	""	Q3-2017
241	241	SHIP CONSTRUCTION RAPID	Dublin City	Belcamp H, Dublin 17	38	N/A	""	""	""	""	""	Q4-2017
242	242	SHIP CONSTRUCTION RAPID	Dublin City	Mourne Road, Drimnagh	29	N/A	""	""	""	""	""	Q4-2017
243	243	SHIP CONSTRUCTION RAPID	Dublin City	Cherry Orchard, Ballyfermot	24	N/A	""	""	""	""	""	Q4-2017
244	244	SHIP CONSTRUCTION RAPID	Dublin City	Poppintree, Ballymun	22	N/A	""	""	""	""	""	Q2-2016
245	245	SHIP CONSTRUCTION RAPID	Dublin City	Belcamp C, Dublin 17	16	N/A	""	Stage 2 approved in Q3-2015, full design/tender being prepared.	""	""	""	""
246	246	SHIP CONSTRUCTION TURNKEY	Dublin City	Prospecthill	58	N/A	""	""	""	""	""	Q4-2017
247	247	CALF CONSTRUCTION TURNKEY	Fingal	The Hermitage, Balgriffin, Co. Dublin *	54	Cluid Housing Association	""	""	""	""	""	Q4-2017
248	248	CALF CONSTRUCTION TURNKEY	Fingal	Dun Emer, Lusk	54	Tath Housing Association	""	""	""	""	Q4-2017	""
249	249	CALF CONSTRUCTION TURNKEY	Fingal	The Gallery, Donabate	43	Oaklee Housing Trust	""	""	""	""	Q2-2017	""
250	250	CALF CONSTRUCTION TURNKEY	Fingal	Weavers Walk, Clonsilla Road, Dublin 15	33	Co-operative Housing Ireland	""	""	""	""	Q3-2017	""
251	251	CALF CONSTRUCTION TURNKEY	Fingal	Millers Glen, Oldtown, Swords	28	The Iveagh Trust	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
252	252	CALF CONSTRUCTION TURNKEY	Fingal	Castlegrange, Clonsilla - Phase 2	21	Tath Housing Association	""	""	""	""	""	Q1-2017
253	253	CALF CONSTRUCTION TURNKEY	Fingal	Castlegrange, Clonsilla - Phase 1	19	Tath Housing Association	""	""	""	""	""	Q4-2016
254	254	CALF CONSTRUCTION TURNKEY	Fingal	St Werburghs Court, Drynam Rd, Swords*	18	Tath Housing Association	""	""	""	""	""	Q4-2017
255	255	CALF CONSTRUCTION TURNKEY	Fingal	St Marnock's Bay, Portmarnock *	10	Cluid Housing Association	""	""	""	""	""	Q4-2017
256	256	CALF CONSTRUCTION TURNKEY	Fingal	Castlegrange, Clonsilla - Phase 3	8	Tath Housing Association	""	""	""	""	""	Q2-2017
257	257	CAS CONSTRUCTION	Fingal	Killhedge Lane Dun Emer	48	Tath Housing Association Ltd	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
258	258	CAS CONSTRUCTION	Fingal	Church Road/Ladyswell Road, Mulhuddart	22	Cluid Housing Association	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
259	259	CAS CONSTRUCTION	Fingal	Darcystown, Ringfort, Balrothery	9	North ? East Housing Association Ltd	""	""	""	""	""	Q3-2017
260	260	CAS CONSTRUCTION	Fingal	Estuary Road, Malahide	8	Society of Saint Vincent de Paul	""	""	""	""	Q2-2017	""
261	261	CAS CONSTRUCTION	Fingal	Ravenswood	6	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
262	262	CAS CONSTRUCTION	Fingal	22 College Street, Baldoyle	4	Cluid Housing Association	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
263	263	SHIP CONSTRUCTION	Fingal	Racecourse Common, Lusk (Phase 2.1)	49	N/A	""	""	""	""	Q4-2016	""
264	264	SHIP CONSTRUCTION	Fingal	Cappaghfinn (Phase 2)	32	N/A	""	""	Stage 3 approved in Q4-2016 On HOLD.	""	""	""
265	265	SHIP CONSTRUCTION	Fingal	Racecourse Common, Lusk (Phase 2.2)	25	N/A	""	""	""	""	""	Q4-2017
266	266	SHIP CONSTRUCTION	Fingal	Castlelands Part View (Phase 3)	24	N/A	""	""	""	""	Q1-2017	""
267	267	SHIP CONSTRUCTION	Fingal	Rathbeale Road, Swords	24	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
268	268	SHIP CONSTRUCTION	Fingal	Church Road, Mulhuddart, Dublin 15	22	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
269	269	SHIP CONSTRUCTION	Fingal	Rowlestown	20	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
270	270	SHIP CONSTRUCTION	Fingal	Cappaghfinn (Phase 1)	14	N/A	""	""	""	""	""	Q2-2016
271	271	SHIP CONSTRUCTION	Fingal	St. Cronan's Green, Swords	14	N/A	""	""	""	""	""	Q2-2016
272	272	SHIP CONSTRUCTION	Fingal	The Grange, Ballyboughal (Part 2)	6	N/A	""	""	""	""	Q4-2016	""
273	273	SHIP CONSTRUCTION	Fingal	Rivermeade, St. Margarets	2	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
274	274	SHIP CONSTRUCTION	Fingal	The Grange, Ballyboughal (Part 1)	2	N/A	""	""	""	""	""	Q3-2017
275	275	SHIP CONSTRUCTION	Fingal	St. Conan's Cottages, Swords	1	N/A	""	""	""	""	""	Q2-2016
276	276	SHIP CONSTRUCTION RAPID	Fingal	Avondale, Mulhuddart, Dublin 15	44	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
277	277	SHIP CONSTRUCTION RAPID	Fingal	Hansfield, Ongar, Dublin 15	36	N/A	""	""	""	""	""	Q3-2017
278	278	SHIP CONSTRUCTION RAPID	Fingal	Pinewood, Balbriggan	25	N/A	""	""	""	""	Q3-2017	""
279	279	SHIP CONSTRUCTION RAPID	Fingal	Wellview, Mulhuddart	20	N/A	""	""	""	""	""	Q4-2017
280	280	SHIP CONSTRUCTION TURNKEY	Fingal	Blackmills Grove, Blakestown Road, Mulhuddard	10	N/A	""	""	""	""	""	Q2-2017
281	281	SHIP CONSTRUCTION TURNKEY	Fingal	Balgriffin Grove, Malahide Road, Balgriffin	6	N/A	""	""	""	""	""	Q1-2017
282	282	CALF CONSTRUCTION 	Fingal 	Ladyswell Road & Church Road, Mulhuddart, Dublin 15 	43	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q4-2017	""	""
283	283	CALF CONSTRUCTION TURNKEY	Fingal 	Castlefield, Clonsilla, Dublin 11 	62	Tath Housing Association	""	""	""	""	Q1-2017	""
284	284	CALF CONSTRUCTION TURNKEY	Galway City	Castlegar Road, Galway	81	Respond!	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
285	285	CALF CONSTRUCTION TURNKEY	Galway City	Maigh Rua, Doughiska, Galway	23	Co operative Ireland	""	""	""	""	""	Q4-2017
286	286	CALF CONSTRUCTION TURNKEY	Galway City	Murrough, Renmore, Galway	20	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
287	287	CALF CONSTRUCTION TURNKEY	Galway City	Boireann Beag, Ros Cam, Galway	16	Cluid Housing Association	""	""	""	""	""	Q4-2016
288	288	CALF CONSTRUCTION TURNKEY	Galway City	Reilean, Roscam, Block 5 Galway *	12	Tath Housing Association	""	""	""	""	""	Q2-2017
289	289	CALF CONSTRUCTION TURNKEY	Galway City	Reilean, Roscam, Block 4 Galway *	12	Tath Housing Association	""	""	""	""	""	Q2-2017
290	290	CALF CONSTRUCTION TURNKEY	Galway City	Maoilin, Ballymoneen Road, Galway - Phase 2 *	4	Tath Housing Association	""	""	""	""	""	Q4-2017
291	291	CALF CONSTRUCTION TURNKEY	Galway City	Maoilin, Ballymoneen Road, Galway - Phase 1 *	2	Tath Housing Association	""	""	""	""	""	Q1-2017
292	292	CALF CONSTRUCTION TURNKEY	Galway City	Cnoc na R, clybaun Road, Galway *	2	Cluid Housing Association	""	""	""	""	""	Q3-2017
293	293	CAS CONSTRUCTION	Galway City	47 Forster Street	9	Cope Galway	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
294	294	CAS CONSTRUCTION	Galway City	Cul Garrai, Rahoon	6	Peter Triest Housing Association Ltd	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
295	295	CAS CONSTRUCTION	Galway City	97/98 Rockfield	4	Carraig Dubh Housing Association	""	""	""	""	Q2-2017	""
296	296	SHIP CONSTRUCTION	Galway City	Ballymoneen Road (Phase 2)	78	N/A	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
297	297	SHIP CONSTRUCTION	Galway City	Ballymoneen Road (Phase 1)	14	N/A	""	""	""	""	Q2-2017	""
298	298	SHIP CONSTRUCTION	Galway City	Ballinfoile Park, Headford Road (Infill Units)	10	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
299	299	SHIP CONSTRUCTION	Galway City	Corrib Park (Infill Units)	8	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
300	300	SHIP CONSTRUCTION	Galway City	Carn Ard, Circular Road (Infill Units)	6	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
301	301	SHIP CONSTRUCTION	Galway City	Castlepark, Ballybane (Infill Units)	4	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
302	302	CALF CONSTRUCTION	Galway County	Spiddal Cottages, Co Galway - Phase 1	23	Cluid Housing Association	""	""	""	""	""	Q3-2017
303	303	CALF CONSTRUCTION	Galway County	Spiddal Cottages, Co Galway - Phase 2	8	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q1-2016	""	""
304	304	CALF CONSTRUCTION TURNKEY	Galway County	Cnoc na Si, Portumna	13	Co-operative Housing Ireland	""	""	""	""	Q4-2016	""
305	305	CALF CONSTRUCTION TURNKEY	Galway County	Vicars Choral, Tuam, Co Galway 	13	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
306	306	CAS CONSTRUCTION	Galway County	Dunlo Hill, Ballinasloe	17	Cluid Housing Association	""	""	Stage 3 approved in Q1-2016, the scheme is now being tendered.	""	""	""
307	307	CAS CONSTRUCTION	Galway County	Claregalway	14	Claregalway and District Day Care Centre	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
308	308	CAS CONSTRUCTION	Galway County	Eanach Mheain, Carraroe	13	Tearmann Eanna Teoranta	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
309	309	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 1)	13	Cluid Housing Association	""	""	""	""	""	Q2-2016
310	310	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 2)	11	Cluid Housing Association	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
311	311	CAS CONSTRUCTION	Galway County	Rossaveal Cottages, Ros a Mhl, South Connemara	8	Tearmann Eanna Teoranta	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
312	312	CAS CONSTRUCTION	Galway County	Mountbellew	5	Mountbellew Voluntary Homes Association	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
313	313	CAS CONSTRUCTION	Galway County	Springfield, Parkmore	4	Peter Triest Housing Association Ltd	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
314	314	SHIP CONSTRUCTION	Galway County	Gilmartin Road, Tuam	61	N/A	""	""	""	""	Q4-2017	""
315	315	SHIP CONSTRUCTION	Galway County	Weir Road, Tuam	30	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
316	316	SHIP CONSTRUCTION	Galway County	Garbally Drive, Ballinasloe	10	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
317	317	SHIP CONSTRUCTION	Galway County	Gort Mhailor, Athenry (Phase 2)	10	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
318	318	SHIP CONSTRUCTION	Galway County	Roundstone	10	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
319	319	SHIP CONSTRUCTION	Galway County	Sruchain an Chlair, Oughterard, Co. Galway	10	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
320	320	SHIP CONSTRUCTION	Galway County	Culleen, Carraroe, Connemara	6	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
321	321	SHIP CONSTRUCTION	Galway County	Esker Fields, Ballinasloe	2	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
322	322	SHIP CONSTRUCTION	Galway County	Ardrahan (SRD)	1	N/A	""	""	""	""	""	Q4-2017
323	323	SHIP CONSTRUCTION	Galway County	Callowfinish, Carna (SRD)	1	N/A	""	""	""	""	Q2-2017	""
324	324	SHIP CONSTRUCTION	Galway County	Waterdale, Claregalway (SRD)	1	N/A	""	""	""	Stage 4 approved in Q2-2017, the scheme is now fully approved.	""	""
325	325	SHIP CONSTRUCTION	Galway County	Corndulla (SRD)	1	N/A	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
326	326	SHIP CONSTRUCTION	Galway County	Cill Ciarn (SRD)	1	N/A	""	""	""	""	Q3-2017	""
327	327	SHIP CONSTRUCTION	Galway County	Kinvara (SRD)	1	N/A	""	""	""	""	Q2-2017	""
328	328	SHIP CONSTRUCTION TURNKEY	Galway County	Athenry	14	N/A	""	""	""	""	""	Q4-2017
329	329	SHIP CONSTRUCTION TURNKEY	Galway County	Portumna	10	N/A	""	""	""	""	""	Q4-2017
330	330	SHIP CONSTRUCTION TURNKEY	Galway County	Kinvara	6	N/A	""	""	""	""	""	Q4-2017
331	331	CALF CONSTRUCTION TURNKEY	Kerry	Cathair Lakes Farrantoreen Road, Killorglin	6	Cluid Housing Association	""	""	""	""	""	Q2-2016
332	332	CAS CONSTRUCTION	Kerry	Mitchels-Boherbee	16	Cluid Housing Association	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
333	333	CAS CONSTRUCTION	Kerry	Hawley Park Apartemnts, St Martins Park, Mitchels Rd, Tralee	15	Kingdom Voluntary Housing Association	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
334	334	CAS CONSTRUCTION	Kerry	Armagh House, Killarney	6	Cluid Housing Association	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
335	335	CAS CONSTRUCTION	Kerry	The Parsonage, Caherciveen	5	Caherciveen Social Services (Housing) Ltd	""	""	""	""	Q4-2017	""
336	336	CAS CONSTRUCTION	Kerry	22 College Road, Castleisland	4	Kerry Emigrant Support Housing Association Ltd	""	""	""	""	Q4-2017	""
337	337	REGENERATION	Kerry	Croilar Na Mistaelach, Tralee	11	N/A	""	""	""	""	Q2-2017	""
338	338	REGENERATION	Kerry	St Martin's Park, Tralerr	4	N/A	""	""	""	""	Q2-2017	""
339	339	REGENERATION	Kerry	Clonmore Road, Tralee	3	N/A	""	""	""	""	""	Q4-2016
340	340	REGENERATION	Kerry	Urban Terrace, Tralee	2	N/A	""	""	""	""	""	Q4-2016
341	341	REGENERATION	Kerry	Bungalow at Dingle Road, Tralee	1	N/A	""	""	""	""	Q1-2017	""
342	342	SHIP CONSTRUCTION	Kerry	Lohercannon, Tralee	56	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
343	343	SHIP CONSTRUCTION	Kerry	Balloonagh, Tralee	28	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
344	344	SHIP CONSTRUCTION	Kerry	Ardbhearna, Kenmare	22	N/A	""	""	""	""	Q4-2017	""
345	345	SHIP CONSTRUCTION	Kerry	Killeen, Tralee	21	N/A	""	""	""	""	Q4-2017	""
346	346	SHIP CONSTRUCTION	Kerry	Rathmore/Barraduff	20	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
347	347	SHIP CONSTRUCTION	Kerry	The Park, Killarney	20	N/A	""	""	""	""	Q1-2017	""
348	348	SHIP CONSTRUCTION	Kerry	Marconi Avenue, Ballybunion	20	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
349	349	SHIP CONSTRUCTION	Kerry	Ardmoneel, Killorglin	14	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
350	350	SHIP CONSTRUCTION	Kerry	Milltown	8	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
351	351	SHIP CONSTRUCTION	Kerry	Courthouse Lawn, Listowel	7	N/A	""	Stage 2 approved in Q2-2016, full design/tender being prepared.	""	""	""	""
352	352	SHIP CONSTRUCTION	Kerry	Pinewood Estate, Killarney	5	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
353	353	SHIP CONSTRUCTION	Kerry	Bill Kinnerk Road	4	N/A	""	""	""	""	Q2-2017	""
354	354	SHIP CONSTRUCTION	Kerry	Lixnaw	4	N/A	""	""	""	""	""	Q4-2017
355	355	SHIP CONSTRUCTION	Kerry	Dreenagh, Ballyheigue (SRD)	1	N/A	""	""	""	""	""	Q1-2017
356	356	SHIP CONSTRUCTION	Kerry	Callinafercy, Milltown	1	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
357	357	SHIP CONSTRUCTION	Kerry	Cahernaboshina, Ventry	1	N/A	""	""	""	""	Q4-2017	""
358	358	SHIP CONSTRUCTION	Kerry	Pinewood Estate, Killarney	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
359	359	SHIP CONSTRUCTION	Kerry	Drom West, Glenbeigh	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
360	360	SHIP CONSTRUCTION	Kerry	Meanus, Killorglin	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
361	361	SHIP CONSTRUCTION	Kerry	Tullig Beg, Killorglin	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
362	362	SHIP CONSTRUCTION	Kerry	Owngarry, killorglin	1	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
363	363	SHIP CONSTRUCTION	Kerry	BallinaKilly Lower, Glenbeigh	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
364	364	SHIP CONSTRUCTION	Kerry	Ashgrove, Listowel	1	N/A	""	""	""	""	""	Q3-2017
365	365	SHIP CONSTRUCTION	Kerry	SRD @ Cullenagh Upr, Beaufort	1	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
366	366	SHIP CONSTRUCTION TURNKEY	Kerry	Cahirdown Wood, Listowel	22	N/A	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
367	367	SHIP CONSTRUCTION TURNKEY	Kerry	Ard Na Si, Lispole	10	N/A	""	""	""	""	Q2-2017	""
368	368	SHIP CONSTRUCTION TURNKEY	Kerry	1-9 Meadow Park	9	N/A	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
369	369	SHIP CONSTRUCTION TURNKEY	Kerry	1-4 Steeple Meadow View 	4	N/A	""	""	""	""	""	Q4-2017
370	370	CALF CONSTRUCTION	Kildare	Rye Abbey, Kilcock, (Apts)	33	Cluid Housing Association	""	""	""	""	""	Q4-2017
371	371	CALF CONSTRUCTION	Kildare	Morristown, Newbridge, Co Kildare	14	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
372	372	CALF CONSTRUCTION	Kildare	Rye Abbey, Kilcock, (houses)	4	Cluid Housing Association	""	""	""	""	""	Q4-2017
373	373	CALF CONSTRUCTION TURNKEY	Kildare	Gallows Hill, Athy	24	Respond!	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
374	374	CALF CONSTRUCTION TURNKEY	Kildare	Roseberry Hill, Newbridge - Phase 3	16	Tath Housing Association	""	""	""	""	Q3-2016	""
375	375	CALF CONSTRUCTION TURNKEY	Kildare	Roseberry Hill, Newbridge - Phase 2	16	Tath Housing Association	""	""	""	""	""	Q4-2017
376	376	CALF CONSTRUCTION TURNKEY	Kildare	Roseberry Hill, Newbridge - Phase 1	13	Tath Housing Association	""	""	""	""	""	Q2-2017
377	377	CALF CONSTRUCTION TURNKEY	Kildare	The Pike, Shenagun, Castledermot	6	Respond!	""	""	""	Scheme approved for CALF funding Q1-2017	""	""
378	378	CALF CONSTRUCTION TURNKEY	Kildare	Moorefield Road, Newbridge	2	Co-operative Housing Ireland	""	""	""	""	Q2-2017	""
379	379	CAS CONSTRUCTION	Kildare	Jigginstown House, Naas	14	Homeless Care Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
380	380	CAS CONSTRUCTION	Kildare	Main St., Kilcullen	4	Camphill Communities of Ireland	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
381	381	CAS CONSTRUCTION	Kildare	Mansfield Grove, Athy	4	KARE Promoting Inclusion for People with Intellectual Disabilities	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
382	382	CAS CONSTRUCTION	Kildare	Craddockstown, Naas	3	KARE Promoting Inclusion for People with Intellectual Disabilities	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
383	383	CAS CONSTRUCTION	Kildare	El Kantara, Newbridge	2	KARE Promoting Inclusion for People with Intellectual Disabilities	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
384	384	SHIP CONSTRUCTION	Kildare	Rathasker, Naas	48	N/A	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
385	385	SHIP CONSTRUCTION	Kildare	Ardclough Road, Celbridge	36	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
386	386	SHIP CONSTRUCTION	Kildare	Dunmurry Rise, Bishopsland	32	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
387	387	SHIP CONSTRUCTION	Kildare	Athgarvan Village	30	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
388	388	SHIP CONSTRUCTION	Kildare	Dominican Church Site, Athy	30	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
389	389	SHIP CONSTRUCTION	Kildare	Beechgrove, Rathangan	18	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
390	390	SHIP CONSTRUCTION	Kildare	Kilcock (Phase 2.2)	13	N/A	""	""	""	""	Q4-2017	""
391	391	SHIP CONSTRUCTION	Kildare	Athgarvan Road, Newbridge	13	N/A	""	""	""	""	Q3-2017	""
392	392	SHIP CONSTRUCTION	Kildare	Anne Street, Prosperous	12	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
393	393	SHIP CONSTRUCTION	Kildare	Coill Dubh, Co. Kildare	9	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
394	394	SHIP CONSTRUCTION	Kildare	Kilcock (Phase 2.1)	6	N/A	""	""	""	""	""	Q4-2017
395	395	SHIP CONSTRUCTION	Kildare	Hillview Terrace, Narraghmore	4	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
396	396	SHIP CONSTRUCTION	Kildare	Newtown, Leixlip	4	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
397	397	SHIP CONSTRUCTION RAPID	Kildare	Old Greenfield Road, Maynooth	50	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
398	398	SHIP CONSTRUCTION TURNKEY	Kildare	Bodkin Place, Kilmeague	16	N/A	""	""	""	""	""	Q4-2017
399	399	SHIP CONSTRUCTION TURNKEY	Kildare	Monasterevin (2)	7	N/A	""	""	""	""	Q4-2017	""
400	400	SHIP CONSTRUCTION TURNKEY	Kildare	Monasterevin (1)	6	N/A	""	""	""	""	""	Q4-2017
401	401	CALF CONSTRUCTION	Kilkenny	Golf Links Road, Kilkenny *	39	Respond!	""	""	""	Scheme approved for CALF funding Q4-2015 (revised approval received in Q3-2017) 	""	""
402	402	CALF CONSTRUCTION	Kilkenny	Walkin St Kilkenny	27	Oaklee Housing Trust	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
403	403	CALF CONSTRUCTION	Kilkenny	Friary Walk, Callan	16	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
404	404	CALF CONSTRUCTION TURNKEY	Kilkenny	Logan Square, Thomastown, Co. Kilkenny*	16	Oaklee	""	""	""	""	""	Q4-2017
405	405	CALF CONSTRUCTION TURNKEY	Kilkenny	Moneenview side Rd, Moneenroe	9	Oaklee Housing Trust	""	""	""	""	Q1-2017	""
406	406	CALF CONSTRUCTION TURNKEY	Kilkenny	Chapel St. and New Road, Mooncoin, Co. Kilkenny	6	Respond!	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
407	407	CAS CONSTRUCTION	Kilkenny	Golf Links Road, Kilkenny	15	Respond!	Stage 1 approved in Q2-2016, outline design and costs are now being prepared.	""	""	""	""	""
408	408	CAS CONSTRUCTION	Kilkenny	Nimble Spaces Project at Callan	15	Camphill Communities of Ireland	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
409	409	CAS CONSTRUCTION	Kilkenny	Good Shepherd Centre - Wing 1952	12	The Good Shepherd Centre (Kilkenny) Ltd	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
410	410	CAS CONSTRUCTION	Kilkenny	Friary Walk, Callan	12	Cluid Housing Association	""	""	""	""	""	Q3-2016
411	411	CAS CONSTRUCTION	Kilkenny	Garrin Green	6	SOS Kilkenny Housing Association Ltd	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
412	412	CAS CONSTRUCTION	Kilkenny	Bishops Garden, Church Lane, Kiklkenny	6	Good Shepherd Services Ltd	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
413	413	CAS CONSTRUCTION	Kilkenny	"""Brooke House"", Thomastown"	5	Camphill Communities of Ireland	""	""	""	""	""	Q3-2017
414	414	CAS CONSTRUCTION	Kilkenny	Ballytobin, Callan	4	Camphill Communities of Ireland	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
415	415	CAS CONSTRUCTION	Kilkenny	Kyle, Callan, Co. Kilkenny	4	Camphill Communities of Ireland	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
416	416	CAS CONSTRUCTION	Kilkenny	Kingsriver, Ennisnag	2	Kingsriver Housing Association Limited	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
417	417	CAS CONSTRUCTION	Kilkenny	Hazelbrook, Newrath	2	Waterford Dove Housing Association	""	""	""	""	Q3-2017	""
418	418	CAS CONSTRUCTION	Kilkenny	Camphill ~Communities Garden Cottage, The Workhouse, Callan	1	Camphill Communities of Ireland	""	""	""	""	""	Q4-2017
419	419	SHIP CONSTRUCTION	Kilkenny	Crokers Hill, Pennyswell Road, Kilkenny	80	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
420	420	SHIP CONSTRUCTION	Kilkenny	Bolton, Callan	38	N/A	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
421	421	SHIP CONSTRUCTION	Kilkenny	Abbeyquarter Vicar Street, Kilkenny	30	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
422	422	SHIP CONSTRUCTION	Kilkenny	The Butts, Kilkenny	22	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
423	423	SHIP CONSTRUCTION	Kilkenny	Main Street, Piltown	18	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
424	424	SHIP CONSTRUCTION	Kilkenny	Donaguile, Castlecomer	18	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
425	425	SHIP CONSTRUCTION	Kilkenny	The Broguemaker, Kilkenny	15	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
426	426	SHIP CONSTRUCTION	Kilkenny	Station Road, Ballyragget	14	N/A	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
427	427	SHIP CONSTRUCTION	Kilkenny	Gaol Rooad, Kilkenny	10	N/A	""	""	""	""	""	Q3-2016
428	428	SHIP CONSTRUCTION	Kilkenny	10 Golf Links Road, Kilkenny	7	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
429	429	SHIP CONSTRUCTION	Kilkenny	Rosehill, Kells Road, Kilkenny	6	N/A	""	""	""	""	""	Q1-2017
430	430	SHIP CONSTRUCTION	Kilkenny	Greensbridge House	5	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
431	431	SHIP CONSTRUCTION	Kilkenny	Blackstaff House, Callan	4	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
432	432	SHIP CONSTRUCTION	Kilkenny	Robertshill, Kilkenny	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
433	433	SHIP CONSTRUCTION	Kilkenny	Rural Cottage Barna, Freshford	1	N/A	""	""	""	""	Q4-2017	""
434	434	SHIP CONSTRUCTION TURNKEY	Kilkenny	Togher Way, Urlingford	11	N/A	""	""	""	""	""	Q3-2017
435	435	SHIP CONSTRUCTION TURNKEY	Kilkenny	Abbeygate, Ferrybank	11	N/A	""	""	""	""	Q2-2017	""
436	436	SHIP CONSTRUCTION TURNKEY	Kilkenny	Newpark, Castlecomer Road, Kilkenny	7	N/A	""	""	""	""	""	Q1-2017
437	437	SHIP CONSTRUCTION TURNKEY	Kilkenny	Togher Way, Urlingford	5	N/A	""	""	""	""	""	Q4-2017
438	438	CALF CONSTRUCTION	Laois	Cluin Inn Mountrath	11	Oaklee Housing Trust	""	""	""	""	Q3-2017	""
439	439	CALF CONSTRUCTION	Laois	55/56 Kirwan Park, Mountmellick	2	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
440	440	CALF CONSTRUCTION TURNKEY	Laois	Wilton Lawns, Portarlington	2	Tath Housing Association	""	""	""	Scheme approved for CALF funding Q4-2016	""	""
441	441	CAS CONSTRUCTION	Laois	Abbeyleix Road, Portlaoise	16	Respond!	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
442	442	CAS CONSTRUCTION	Laois	St. Fintan's Hospital, Dublin Road, Portlaoise	8	Oaklee Housing Trust	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
443	443	SHIP CONSTRUCTION	Laois	Conniberry Way, Old Knockmay Road, Portlaoise	33	N/A	""	""	""	""	Q4-2016	""
444	444	SHIP CONSTRUCTION	Laois	Ballymorris Road, Portarlington	20	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
445	445	SHIP CONSTRUCTION	Laois	Gleann na Glaise, Ballyroan	10	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
446	446	SHIP CONSTRUCTION	Laois	Pattison Est. Mountmellick	10	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
447	447	SHIP CONSTRUCTION	Laois	Shannon Street, Mountrath	8	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
448	448	SHIP CONSTRUCTION	Laois	Main Street, Rathdowney	5	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
449	449	CALF CONSTRUCTION TURNKEY	Laois 	31 36 Droimnin, Stradbally	6	Cluid Housing Association	""	""	""	""	Q4-2017	""
450	450	CAS CONSTRUCTION	Leitrim	Ballinamore	2	Society of Saint Vincent de Paul	""	""	""	""	""	Q4-2017
451	451	SHIP CONSTRUCTION	Leitrim	Summerhill, Carrick on Shannon	28	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
452	452	SHIP CONSTRUCTION	Leitrim	Attirory, Carrick-on-Shannon	24	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
453	453	SHIP CONSTRUCTION	Leitrim	Taobh Tire, Manorhamilton (Phase 2)	7	N/A	""	""	""	""	Q2-2017	""
454	454	CALF CONSTRUCTION	Limerick	1 20 Park View Row, Hyde Road, Limerick	20	Cluid Housing Association	""	""	""	""	Q3-2016	""
455	455	CALF CONSTRUCTION TURNKEY	Limerick	Cosgrave Park, Moyross, Limerick City (Regen)q2	21	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
456	456	CALF CONSTRUCTION TURNKEY	Limerick	Old Dublin Road, Rhebogue, LimerickX	16	Cluid Housing Association	""	""	""	""	Q3-2017	""
457	457	CALF CONSTRUCTION TURNKEY	Limerick	Woodlawn Park, Ballysimon Road, Limerick	11	Respond!	""	""	""	""	Q4-2017	""
458	458	CALF CONSTRUCTION TURNKEY	Limerick	Ard Aulin, Mungret Phase 1	7	Cluid Housing Association	""	""	""	""	""	Q2-2017
459	459	CALF CONSTRUCTION TURNKEY	Limerick	Cluain Ard, Fedamore	4	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
460	460	CALF CONSTRUCTION TURNKEY	Limerick	Ard Aulin, Mungret Phase 2	1	Cluid Housing Association	""	""	""	""	Q4-2016	""
461	461	CAS CONSTRUCTION	Limerick	Drominbeg, Rhebogue	21	Co-operative Housing Ireland (Formerly NABCo)	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
462	462	CAS CONSTRUCTION	Limerick	Cappamore	12	Cappamore Housing Association Ltd	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
463	463	CAS CONSTRUCTION	Limerick	Mirth, Thomondgate	12	Associated Charities Trust Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
464	464	CAS CONSTRUCTION	Limerick	Cois na Feile, Abbeyfeale 	12	Cluid Housing Association	""	""	""	""	""	Q4-2016
465	465	CAS CONSTRUCTION	Limerick	Towerfield Crescent, Croom	10	Croom Voluntary Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
466	466	CAS CONSTRUCTION	Limerick	Cuan Mhuire, Bruree	6	Cuan Mhuire Teoranta	""	""	""	""	Q3-2017	""
467	467	CAS CONSTRUCTION	Limerick	Speakers Corner, Limerick City	4	Simon Community : Midwest Simon	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
468	468	REGENERATION	Limerick	Lord Edward Street, P2: Main Contract	79	N/A	""	""	""	""	""	Q4-2017
469	469	REGENERATION	Limerick	Churchfield (Phase 1)	42	N/A	""	""	""	""	Q3-2016	""
470	470	REGENERATION	Limerick	Churchfield (Phase 2)	38	Circle Voluntary Housing Association Ltd	""	Stage 2 approved in Q4-2014, full design/tender being prepared.	""	""	""	""
471	471	REGENERATION	Limerick	Carew Park	37	N/A	Stage 1 approved in Q1-2015, outline design and costs are now being prepared.	""	""	""	""	""
472	472	REGENERATION	Limerick	Cosgrave Park	30	Co-operative Housing Ireland (Formerly NABCo)	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
473	473	REGENERATION	Limerick	Palm Court	27	Respond!	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
474	474	REGENERATION	Limerick	Orchard Site	26	Oaklee Housing Trust	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
475	475	REGENERATION	Limerick	Dalgaish Park	24	Cluid Housing Association	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
476	476	REGENERATION	Limerick	St. Mary's Park Infills	19	Tath Housing Association Ltd	""	""	""	""	Q4-2017	""
477	477	REGENERATION	Limerick	Cliona Park (Phase 3)	18	Tath Housing Association Ltd	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
478	478	REGENERATION	Limerick	BCW Vacant Refurbs, Lot 1 & 2**	14	N/A	""	""	""	""	""	Q4-2016
479	479	REGENERATION	Limerick	Markievicz Drive	13	N/A	Stage 1 approved in Q1-2015, outline design and costs are now being prepared.	""	""	""	""	""
480	480	REGENERATION	Limerick	2017 Southill Rebuilds	13	N/A	""	""	""	""	""	Q4-2017
481	481	REGENERATION	Limerick	Cliona Park (Phase 2)	10	N/A	""	""	""	""	""	Q2-2017
482	482	REGENERATION	Limerick	2016 St. Mary's Park Rebuild	9	N/A	""	""	""	""	""	Q4-2016
483	483	REGENERATION	Limerick	Sheep / Athlunkards Street	8	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
484	484	REGENERATION	Limerick	2016 Southhill Rebuild	8	N/A	""	""	""	""	""	Q4-2016
485	485	REGENERATION	Limerick	2016 Moyross Rebuild	6	N/A	""	""	""	""	""	Q4-2016
486	486	REGENERATION	Limerick	8-10 Gaol Lane	3	N/A	""	""	""	""	""	Q4-2016
487	487	REGENERATION	Limerick	1 3 Weston Gardens	3	N/A	""	""	""	""	""	Q2-2016
488	488	REGENERATION	Limerick	Lord Edward Street, P2: Main Contract	2	N/A	""	""	""	""	""	Q1-2017
489	489	REGENERATION	Limerick	176 & 177 Cliona Park	2	N/A	""	""	""	""	""	Q2-2016
490	490	REGENERATION	Limerick	45-46 Cliona Park	2	N/A	""	""	Stage 3 approved in Q1-2017, the scheme is now being tendered.	""	""	""
491	491	REGENERATION	Limerick	Gaol Lane	1	N/A	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
492	492	REGENERATION	Limerick	2017 St Mary's Park Rebuild	1	N/A	""	""	""	""	""	Q4-2017
493	493	REGENERATION	Limerick	2017 Ballinacurra Weston Rebuild	1	N/A	""	""	""	""	""	Q4-2017
494	494	REGENERATION	Limerick	2017 Moyross Rebuild	1	N/A	""	""	""	""	""	Q4-2017
495	495	SHIP CONSTRUCTION	Limerick	Clonmacken, Limerick City	38	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
496	496	SHIP CONSTRUCTION	Limerick	Vance's Lands, Limerick City	37	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
497	497	SHIP CONSTRUCTION	Limerick	Deerpark, Adare	30	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
498	498	SHIP CONSTRUCTION	Limerick	Childers Road, Limerick City	24	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
499	499	SHIP CONSTRUCTION	Limerick	Glenview Drive, Hospital	20	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
500	500	SHIP CONSTRUCTION	Limerick	Lisheen Park, Patrickswell	16	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
501	501	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhill Road 	14	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
502	502	SHIP CONSTRUCTION	Limerick	1-12 Burke Avenue, Limerick City	12	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
503	503	SHIP CONSTRUCTION	Limerick	Wallers Well, Limerick City (Phase 2)	11	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
504	504	SHIP CONSTRUCTION	Limerick	Sexton Street North & Kileely Court	10	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
505	505	SHIP CONSTRUCTION	Limerick	Gough Place, Rosbrien Road, Limerick	7	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
506	506	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	7	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
507	507	SHIP CONSTRUCTION	Limerick	Kilmurry Court, Garryowen	6	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
508	508	SHIP CONSTRUCTION	Limerick	Patrick?s Villas, Castleconnell	5	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
509	509	SHIP CONSTRUCTION	Limerick	Sycamore Avenue, Limerick City	5	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
510	510	SHIP CONSTRUCTION	Limerick	Kileely Road, Moyross	5	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
511	511	SHIP CONSTRUCTION	Limerick	Site Adj. to Athlunkard Boat Club, Limerick City	4	N/A	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
512	512	SHIP CONSTRUCTION	Limerick	Chas Flats, Limerick City	3	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
513	513	SHIP CONSTRUCTION	Limerick	Joseph Street, Limerick City	3	N/A	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
514	514	SHIP CONSTRUCTION	Limerick	Hassett Villas, Thomondgate	3	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
515	515	SHIP CONSTRUCTION	Limerick	Ballygrennan Road, Moyross	3	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
516	516	SHIP CONSTRUCTION	Limerick	Rathbane Road, Limerick City	2	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
517	517	SHIP CONSTRUCTION	Limerick	Ballygreannan Road, Limerick City	2	N/A	""	""	""	""	""	Q4-2017
518	518	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	2	N/A	""	""	""	""	""	Q4-2017
519	519	SHIP CONSTRUCTION RAPID	Limerick	Old Christians Site, Rathbane	34	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
520	520	SHIP CONSTRUCTION RAPID	Limerick	Lower Carey's Road, Limerick City	11	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
521	521	SHIP CONSTRUCTION RAPID	Limerick	Upper Carey's Road	11	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
522	522	SHIP CONSTRUCTION RAPID	Limerick	Mountpelier	10	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
523	523	SHIP CONSTRUCTION RAPID	Limerick	Knocklong	10	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
524	524	SHIP CONSTRUCTION RAPID	Limerick	Ballyhahill	4	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
525	525	CALF CONSTRUCTION TURNKEY	Longford	Cartrun Breac, Lisbrack Rd, Longford	7	Cluid Housing Association	""	""	""	""	""	Q1-2017
526	526	SHIP CONSTRUCTION	Longford	Church View, Lanesborough	13	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
527	527	SHIP CONSTRUCTION	Longford	Rathcline Road, Lanesborough	4	N/A	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
528	528	SHIP CONSTRUCTION	Longford	Edgeworthstown Road, Ballymahon	4	N/A	""	""	""	""	Q2-2017	""
529	529	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	14	N/A	""	""	""	""	""	Q4-2017
530	530	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	2	N/A	""	""	""	""	Q4-2017	""
531	531	CALF CONSTRUCTION	Louth	Scarlett Street, Drogheda	15	North  East Housing Association Ltd	""	""	""	Scheme approved for CALF funding Q3-2016	""	""
532	532	CALF CONSTRUCTION	Louth	Clos na Manach, Carlingford	10	Tath Housing Association	""	""	""	""	Q2-2017	""
533	533	CALF CONSTRUCTION	Louth	Rath na Gloinne	3	Cluid Housing Association	""	""	""	""	""	Q3-2016
534	534	CALF CONSTRUCTION	Louth	Bishops Court, Dundalk	2	Tath Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
535	535	CALF CONSTRUCTION	Louth	2 Slieve Row Crescent, Dundalk	1	Cluid Housing Association	""	""	""	""	""	Q2-2016
536	536	CALF CONSTRUCTION TURNKEY	Louth	Castleguard, Ardee	102	Tath Housing Association	""	""	""	""	Q2-2017	""
537	537	CALF CONSTRUCTION TURNKEY	Louth	Rathmullen Road, Drogheda	54	North  East Housing Association Ltd	""	""	""	""	Q4-2017	""
538	538	CALF CONSTRUCTION TURNKEY	Louth	Rathmullen Road, Drogheda	51	Tath Housing Association	""	""	""	""	Q4-2017	""
539	539	CALF CONSTRUCTION TURNKEY	Louth	Avourwen Meadows, Drogheda	50	Oaklee Housing Trust	""	""	""	Scheme approved for CALF funding Q1-2017	""	""
540	540	CALF CONSTRUCTION TURNKEY	Louth	Liscorrie, Bog Lane, Drogheda Phase 1	41	Tath Housing Association	""	""	""	""	""	Q4-2017
541	541	CALF CONSTRUCTION TURNKEY	Louth	Mount Hamilton, Dundalk Phase 2	16	Cluid Housing Association	""	""	""	""	Q4-2016	""
542	542	CALF CONSTRUCTION TURNKEY	Louth	Mount Hamilton, Dundalk Phase 3	15	Cluid Housing Association	""	""	""	""	Q4-2016	""
543	543	CALF CONSTRUCTION TURNKEY	Louth	Mount Hamilton, Dundalk Phase 1	12	Cluid Housing Association	""	""	""	""	""	Q4-2017
544	544	CALF CONSTRUCTION TURNKEY	Louth	Coulter Place Armagh Road Dundalk Phase 2	12	Cluid Housing Association	""	""	""	""	""	Q3-2017
545	545	CALF CONSTRUCTION TURNKEY	Louth	Coulter Place Armagh Road Dundalk Phase 1	10	Cluid Housing Association	""	""	""	""	""	Q1-2017
546	546	CALF CONSTRUCTION TURNKEY	Louth	Castle Court, Castlebellingham - Phase 2	10	Cluid Housing Association	""	""	""	""	""	Q1-2017
547	547	CALF CONSTRUCTION TURNKEY	Louth	Aston Village	8	Respond!	""	""	""	Scheme approved for CALF funding Q4-2016	""	""
548	548	CALF CONSTRUCTION TURNKEY	Louth	Liscorrie, Bog Lane, Drogheda Phase 2	6	Tath Housing Association	""	""	""	""	Q4-2016	""
549	549	CALF CONSTRUCTION TURNKEY	Louth	Castle Court, Castlebellingham - Phase 1	4	Cluid Housing Association	""	""	""	""	""	Q1-2017
550	550	CALF CONSTRUCTION TURNKEY	Louth	Knock Shee, Old Golf Links road, Blackrock, Co. Louth	3	Cluid Housing Association	""	""	""	""	""	Q4-2017
551	551	CAS CONSTRUCTION	Louth	Clontygora, Dundalk	11	Cluid Housing Association	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
552	552	CAS CONSTRUCTION	Louth	Barrack Street, Dundalk	8	Simon Community : Dundalk Simon	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
553	553	CAS CONSTRUCTION	Louth	Saltown, Dundalk	7	North  East Housing Association Ltd	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
554	554	CAS CONSTRUCTION	Louth	Tierney Street, Ardee	7	Oaklee Housing Trust	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
555	555	CAS CONSTRUCTION	Louth	Coulter Park	6	Tath Housing Association Ltd	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
556	556	CAS CONSTRUCTION	Louth	36 Strand, Clogherhead	4	St. John of God Housing Association Ltd	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
557	557	CAS CONSTRUCTION	Louth	5 Slieveroe Cresent, Dundalk	1	Cluid Housing Association	""	""	""	""	Q4-2017	""
558	558	CAS CONSTRUCTION	Louth	Castletowncooley, Riverstown, Dundalk	1	Tath Housing Association Ltd	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
559	559	CAS CONSTRUCTION	Louth	McArdle Green (Moneymore), Drogheda	1	North  East Housing Association Ltd	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
560	560	CAS CONSTRUCTION	Louth	Tredagh View, Drogheda	1	Respond!	""	""	""	""	""	Q1-2017
561	561	REGENERATION	Louth	Cox's Demesne Phase 2b	22	N/A	Stage 1 approved in Q3-2013, outline design and costs are now being prepared.	""	""	""	""	""
562	562	REGENERATION	Louth	Cox's Demesne Phase 2a	14	N/A	""	""	""	""	""	Q4-2016
563	563	SHIP CONSTRUCTION	Louth	Mount Avenue, Dundalk	75	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
564	564	SHIP CONSTRUCTION	Louth	Boice Court (Phase 2 - 4)	69	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
565	565	SHIP CONSTRUCTION	Louth	Father Finn Park (Phase 2)	17	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
566	566	SHIP CONSTRUCTION	Louth	Drogheda B&R project	12	N/A	""	""	""	""	Q3-2017	""
567	567	SHIP CONSTRUCTION	Louth	Dundalk B&R project (4)	6	N/A	""	""	""	""	""	Q4-2017
568	568	SHIP CONSTRUCTION	Louth	Dundalk B&R project (1)	7	N/A	""	""	""	""	""	Q4-2016
569	569	SHIP CONSTRUCTION	Louth	Dundalk B&R project (2)	7	N/A	""	""	""	""	""	Q2-2017
570	570	SHIP CONSTRUCTION	Louth	Dundalk B&R project (3)	9	N/A	""	""	""	""	""	Q3-2017
571	571	SHIP CONSTRUCTION	Louth	Woodlands, Dunleer	4	N/A	""	""	""	""	""	Q3-2016
572	572	SHIP CONSTRUCTION	Louth	55/57 Bothar Brugha, Drogheda	3	N/A	""	""	""	""	""	Q4-2017
573	573	CALF CONSTRUCTION TURNKEY	Mayo	Ballina area	11	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q4-2016	""	""
574	574	CALF CONSTRUCTION TURNKEY	Mayo	Glenlara, Westport, Co Mayo 	10	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
575	575	CAS CONSTRUCTION	Mayo	Admiral Browne Road, Foxford (Phase 1)	8	Society of Saint Vincent de Paul	""	""	""	""	""	Q3-2016
576	576	CAS CONSTRUCTION	Mayo	Logmore, Belmullet	7	Irish Wheelchair Association Ltd	""	""	""	""	""	Q2-2017
577	577	CAS CONSTRUCTION	Mayo	Glenamoy	6	Glenamoy Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
578	578	CAS CONSTRUCTION	Mayo	Killosheehan, Ballinrobe	6	Society of Saint Vincent de Paul	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
579	579	CAS CONSTRUCTION	Mayo	Admiral Browne Road, Foxford (Phase 2)	4	Society of Saint Vincent de Paul	""	""	Stage 3 approved in Q3-2016, the scheme is now being tendered.	""	""	""
580	580	SHIP CONSTRUCTION	Mayo	Kilkelly Road, Swinford	26	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
581	581	SHIP CONSTRUCTION	Mayo	Lios na Circa, Saleen, Castlebar	22	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
582	582	SHIP CONSTRUCTION	Mayo	Tubberhill, Westport (Phase 3)	21	N/A	""	""	""	""	Q3-2016	""
583	583	SHIP CONSTRUCTION	Mayo	Abbeyquarter, Ballyhaunis	18	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
584	584	SHIP CONSTRUCTION	Mayo	Sli na Roba, Friarsquarter, Ballinrobe	16	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
585	585	SHIP CONSTRUCTION	Mayo	Bothar Dubh, Claremorris	12	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
586	586	SHIP CONSTRUCTION	Mayo	Sliabh Rua, Foxford - Phase 3	10	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
587	587	SHIP CONSTRUCTION	Mayo	Knockmore, Ballina	8	N/A	""	""	""	""	Q4-2017	""
588	588	SHIP CONSTRUCTION	Mayo	Parke, Castlebar	8	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
589	589	SHIP CONSTRUCTION	Mayo	Killavally	8	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
590	590	SHIP CONSTRUCTION	Mayo	Kilkelly Road, Knock (Phase 3)	4	N/A	""	""	""	""	Q3-2017	""
591	591	SHIP CONSTRUCTION	Mayo	Kilmeena (Phase 2)	4	N/A	""	""	""	""	Q3-2017	""
592	592	SHIP CONSTRUCTION	Mayo	Radharc an tSaillin, Binghamstown, Belmullet (Phase 2)	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
593	593	SHIP CONSTRUCTION	Mayo	Woodlands, Balla (Phase 3)	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
594	594	SHIP CONSTRUCTION	Mayo	Tonragee West, Achill (Phase 2)	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
595	595	SHIP CONSTRUCTION	Mayo	Marian Crescent, Ballina	4	N/A	""	""	""	""	Q2-2017	""
596	596	SHIP CONSTRUCTION	Mayo	Market Street, Swinford	2	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
597	597	SHIP CONSTRUCTION	Mayo	Knocknageeha, Newport	1	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
598	598	SHIP CONSTRUCTION	Mayo	St. Patrick's Tce., Westport	1	N/A	""	""	""	""	""	Q2-2017
599	599	SHIP CONSTRUCTION	Mayo	Barhauve, Rossport (SRD)	1	N/A	""	""	""	""	Q4-2016	""
600	600	SHIP CONSTRUCTION	Mayo	Glaggaun, Ballycroy (SRD)	1	N/A	""	""	""	""	""	Q4-2017
601	601	SHIP CONSTRUCTION	Mayo	Glengad, Pollatomish (SRD)	1	N/A	""	""	""	""	Q4-2016	""
602	602	SHIP CONSTRUCTION	Mayo	Gorthbrack, Inver (SRD)	1	N/A	""	""	""	""	Q4-2016	""
603	603	SHIP CONSTRUCTION TURNKEY	Mayo	Slinaunroe, Clogher (SRD)	1	N/A	""	""	""	""	""	Q2-2017
604	604	CALF CONSTRUCTION	Meath	Millrace Court, Emmet Street, Trim, Co Meath 	11	North  East Housing Association Ltd	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
605	605	CALF CONSTRUCTION	Meath	Cherryvalley, Raghmoylan, Co. Meath	9	Cluid Housing Association	""	""	""	""	""	Q4-2017
606	606	CALF CONSTRUCTION	Meath	Kellets Grove, Dunshauglin, Co Meath 	6	Tath Housing Association Ltd	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
607	607	CALF CONSTRUCTION TURNKEY	Meath	Dunville, Athlumney, Co. Meath	64	Tath Housing Association	""	""	""	""	Q3-2017	""
608	608	CALF CONSTRUCTION TURNKEY	Meath	Fitzherbert Wood, Slane Rd., Navan, Co. Meath	44	Tath Housing Association	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
609	609	CALF CONSTRUCTION TURNKEY	Meath	Dun Eimear, Bettytown	30	Tath Housing Association	""	""	""	""	Q3-2017	""
610	610	CALF CONSTRUCTION TURNKEY	Meath	Seabury Lawns, Mornington	25	Cluid Housing Association	""	""	""	""	""	Q3-2017
611	611	CALF CONSTRUCTION TURNKEY	Meath	Tubberclaire, Navan	23	Cluid Housing Association	""	""	""	""	""	Q2-2016
612	612	CALF CONSTRUCTION TURNKEY	Meath	Mill Lane, Flower Hill, Navan	20	Oaklee Housing Trust	""	""	""	""	""	Q1-2016
613	613	CALF CONSTRUCTION TURNKEY	Meath	Ashbourne area - Phase 4	20	Cluid Housing Association	""	""	""	""	""	Q4-2017
614	614	CALF CONSTRUCTION TURNKEY	Meath	Ashbourne area - Phase 3	18	Cluid Housing Association	""	""	""	""	""	Q4-2017
615	615	CALF CONSTRUCTION TURNKEY	Meath	Ashbourne area - Phase 2	18	Cluid Housing Association	""	""	""	""	""	Q4-2017
616	616	CALF CONSTRUCTION TURNKEY	Meath	Ashbourne area - Phase 1	11	Cluid Housing Association	""	""	""	""	""	Q1-2017
617	617	CALF CONSTRUCTION TURNKEY	Meath	Blackcastle, Slane Road, Navan	9	Tath Housing Association	""	""	""	""	Q3-2017	""
618	618	CALF CONSTRUCTION TURNKEY	Meath	Churchfields, Ashbourne *	8	Tath Housing Association	""	""	""	""	""	Q2-2017
619	619	CALF CONSTRUCTION TURNKEY	Meath	Grangehall, Dunshaughlin	7	Tath Housing Association	""	""	""	""	Q1-2017	""
620	620	CALF CONSTRUCTION TURNKEY	Meath	Seabury Lawns, Mornington	6	Cluid Housing Association	""	""	""	""	Q1-2017	""
621	621	CALF CONSTRUCTION TURNKEY	Meath	Royal Oaks, Enfield *	4	Cluid Housing Association	""	""	""	""	""	Q2-2017
622	622	CALF CONSTRUCTION TURNKEY	Meath	27 Ardmore Rise, Bettystown	1	North East Housing Association Ltd	""	""	""	""	Q1-2017	""
623	623	CAS CONSTRUCTION	Meath	Blackcastle, Slane Road, Navan	17	Tath Housing Association	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
624	624	SHIP CONSTRUCTION	Meath	Riverside, Kells	40	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
625	625	SHIP CONSTRUCTION	Meath	Connaught Grove, Athboy	32	N/A	""	""	""	""	Q3-2017	""
626	626	SHIP CONSTRUCTION	Meath	Dunshaughlin	25	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
627	627	SHIP CONSTRUCTION	Meath	Donore	20	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
628	628	SHIP CONSTRUCTION	Meath	Cherry Court, Summerhill	19	N/A	""	""	""	""	Q4-2017	""
629	629	SHIP CONSTRUCTION	Meath	Nobber	19	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
630	630	SHIP CONSTRUCTION	Meath	Ratoath	17	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
631	631	SHIP CONSTRUCTION	Meath	Bettystown (Phase 1)	16	N/A	""	""	""	""	""	Q3-2017
632	632	SHIP CONSTRUCTION	Meath	Bettystown (Phase 2)	12	N/A	Stage 1 approved in Q4-2016, outline design and costs are now being prepared.	""	""	""	""	""
633	633	SHIP CONSTRUCTION	Meath	Carlanstown	10	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
634	634	SHIP CONSTRUCTION	Meath	Proudstown Road, Navan	4	N/A	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
635	635	SHIP CONSTRUCTION RAPID	Meath	Oldcastle	15	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
636	636	SHIP CONSTRUCTION RAPID	Meath	Cortown	10	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
637	637	SHIP CONSTRUCTION RAPID	Meath	Kilmainhamwood	4	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
638	638	CALF CONSTRUCTION	Monaghan	Liseggerton Road, Clones	6	Oaklee Housing Trust	""	""	""	""	Q2-2017	""
639	639	CALF CONSTRUCTION TURNKEY	Monaghan	Kingscourt Road, Carrickmacross, Co. Monaghan	50	Respond!	""	""	""	""	Q3-2017	""
640	640	CALF CONSTRUCTION TURNKEY	Monaghan	Magheross, Carrickmacross *	33	Tath Housing Association	""	""	""	""	Q2-2017	""
641	641	CAS CONSTRUCTION	Monaghan	Liseggerton, Clones	16	Oaklee Housing Trust	Stage 1 approved in Q3-2016, outline design and costs are now being prepared.	""	""	""	""	""
642	642	CAS CONSTRUCTION	Monaghan	Convent Lands, Carrickmacross	7	Respond!	""	""	""	""	""	Q2-2017
643	643	CAS CONSTRUCTION	Monaghan	Drumillard, Castleblayney (Phase 2)	2	Castleblayney Care Housing Association Ltd	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
644	644	SHIP CONSTRUCTION	Monaghan	Latlorcan, Monaghan Town	43	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
645	645	SHIP CONSTRUCTION	Monaghan	Bree, Castleblayney	8	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
646	646	SHIP CONSTRUCTION TURNKEY	Monaghan	Drumbear Wood, Monaghan Town	12	N/A	""	""	""	""	""	Q4-2017
647	647	SHIP CONSTRUCTION TURNKEY	Monaghan	Maple Grove, Smithborough	12	N/A	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
648	648	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan Town (Phase 2)	8	N/A	""	""	""	""	""	Q2-2017
649	649	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan  Town (Phase 1)	8	N/A	""	""	""	""	""	Q2-2017
650	650	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan Town (Phase 3)	6	N/A	""	""	""	""	""	Q4-2017
651	651	SHIP CONSTRUCTION TURNKEY	Monaghan	The Meadows, Smithborough	5	N/A	""	""	""	""	""	Q4-2017
652	652	SHIP CONSTRUCTION TURNKEY	Monaghan	Killycard, Bree, Castleblaney	4	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
653	653	CALF CONSTRUCTION	Offaly	Kearney's Field, Tullamore	53	Oaklee Housing Trust	""	""	""	Scheme approved for CALF funding Q1-2017	""	""
654	654	CALF CONSTRUCTION	Offaly	Killane Drive, Edenderry	25	Tath Housing Association	""	""	""	Scheme approved for CALF funding Q2-2017	""	""
655	655	CAS CONSTRUCTION	Offaly	Clonminch, Tullamore	20	Oaklee Housing Trust	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
656	656	CAS CONSTRUCTION	Offaly	Scurragh, Birr	6	Cluid Housing Association	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
657	657	CAS CONSTRUCTION	Offaly	Mountbolus	4	Mid Offaly Housing Association Ltd	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
658	658	CAS CONSTRUCTION	Offaly	Killane Drive, Edenderry	2	Tath Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
659	659	SHIP CONSTRUCTION	Offaly	Blundell Wood, Edenderry	33	N/A	""	""	""	""	Q4-2017	""
660	660	SHIP CONSTRUCTION	Offaly	Chancery Lane, Tullamore	18	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
661	661	SHIP CONSTRUCTION	Offaly	Kylebeg, Banagher (Phase 2)	18	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
662	662	SHIP CONSTRUCTION	Offaly	Circular Road, Daingean	7	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
663	663	SHIP CONSTRUCTION TURNKEY	Offaly	McGregol, Birr	12	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
664	664	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Spideoga, Cloghan	6	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
665	665	SHIP CONSTRUCTION TURNKEY	Offaly	Mill Race, Ferbane	5	N/A	""	""	""	""	""	Q4-2017
666	666	CALF CONSTRUCTION TURNKEY	Roscommon	Monksfield, Bealnamulla, Athlone	40	Cluid Housing Association	""	""	""	""	Q3-2017	""
667	667	CALF CONSTRUCTION TURNKEY	Roscommon	Monksfield Park, Tuam Road, Athlone	13	Cluid Housing Association	""	""	""	""	Q1-2016	""
668	668	CALF CONSTRUCTION TURNKEY	Roscommon	River Oaks, Kilcolman, Ballaghaderreen	12	Respond!	""	""	""	""	Q3-2017	""
669	669	SHIP CONSTRUCTION	Roscommon	River Oaks, Ballaghaderreen	10	N/A	""	""	""	""	""	Q4-2017
670	670	SHIP CONSTRUCTION	Roscommon	Greenfields, Blackstick Road, Roscommon Town	6	N/A	""	""	""	""	""	Q3-2017
671	671	SHIP CONSTRUCTION	Roscommon	Cloonfad	2	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
672	672	SHIP CONSTRUCTION TURNKEY	Roscommon	Monksland, Athlone	10	N/A	""	""	""	""	Q1-2017	""
673	673	SHIP CONSTRUCTION TURNKEY	Roscommon	Station Road, Termon, Boyle	10	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
674	674	CAS CONSTRUCTION	Sligo	Cuan Iosa, Ballymote	8	Society of Saint Vincent de Paul	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
675	675	SHIP CONSTRUCTION	Sligo	Knappagh Road	28	N/A	""	Stage 2 approved in Q3-2016, full design/tender being prepared.	""	""	""	""
676	676	SHIP CONSTRUCTION	Sligo	Carrowbunnaun, Strandhill	20	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
677	677	SHIP CONSTRUCTION	Sligo	Colloney	15	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
678	678	SHIP CONSTRUCTION	Sligo	Fr. Flanagan Terrace (2)	14	N/A	""	""	""	""	Q1-2017	""
679	679	SHIP CONSTRUCTION	Sligo	Rosses Point	14	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
680	680	SHIP CONSTRUCTION	Sligo	Fr. Flanagan Terrace (1)	8	N/A	""	""	""	""	""	Q4-2017
681	681	SHIP CONSTRUCTION	Sligo	Caltragh, Culleens	1	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
682	682	SHIP CONSTRUCTION	Sligo	Daghloonagh, Keash - SRD	1	N/A	""	""	""	""	""	Q4-2016
683	683	CALF CONSTRUCTION	South Dublin	Westpark, Garters Lane, Saggert, Co Dublin 	84	Cluid Housing Association	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
684	684	CALF CONSTRUCTION	South Dublin	Scholarstown Wood (Apts)	6	Circle Voluntary Housing Association	""	""	""	""	Q3-2017	""
685	685	CALF CONSTRUCTION	South Dublin	Station Road, Clondalkin	5	Respond!	""	""	""	""	""	Q3-2017
686	686	CALF CONSTRUCTION	South Dublin	Scholarstown Wood (Houses) * Phase 1	3	Circle Voluntary Housing Association	""	""	""	""	""	Q4-2017
687	687	CALF CONSTRUCTION	South Dublin	Tullyhall, Lucan - Phase 1 *	2	Tath Housing Association	""	""	""	""	""	Q3-2017
688	688	CALF CONSTRUCTION	South Dublin	Tullyhall, Lucan - Final Phase*	2	Tath Housing Association	""	""	""	""	Q2-2017	""
689	689	CALF CONSTRUCTION	South Dublin	1 Hollyville Terrace, Palmerstown, Dublin	2	Cluid Housing Association	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
690	690	CALF CONSTRUCTION TURNKEY	South Dublin	Elder Heath, Kiltipper Road, Tallaght, Dublin 24 	28	Cluid Housing Association	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
691	691	CALF CONSTRUCTION TURNKEY	South Dublin	Milford Manor, Clondalkin - Phase 1	25	Cluid Housing Association	""	""	""	""	""	Q1-2017
692	692	CALF CONSTRUCTION TURNKEY	South Dublin	Milford Manor, Clondalkin	25	Cluid Housing Association	""	""	""	""	Q1-2017	""
693	693	CALF CONSTRUCTION TURNKEY	South Dublin	New Bancroft, Tallaght, Dublin 24*	16	Cluid Housing Association	""	""	""	""	""	Q4-2017
694	694	CALF CONSTRUCTION TURNKEY	South Dublin	Milford Manor, Clondalkin - Final Phase 	15	Cluid Housing Association	""	""	""	""	""	Q3-2017
695	695	CALF CONSTRUCTION TURNKEY	South Dublin	Dodderbrook, Oldcourt Road, Ballycullen, Dublin 24 	14	Cluid Housing Association	""	""	""	""	Q1-2017	""
696	696	CALF CONSTRUCTION TURNKEY	South Dublin	Broadfield Grove, Rathcoole-phase 1 *	10	Oaklee Housing Trust	""	""	""	""	""	Q3-2017
697	697	CALF CONSTRUCTION TURNKEY	South Dublin	Old Nangor Road, Clondalkin, Dublin 22	7	Clanmil Housing Association	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
698	698	CALF CONSTRUCTION TURNKEY	South Dublin	Scholarstown Wood (Houses) *Phase 2 	5	Circle Voluntary Housing Association	""	""	""	""	Q3-2017	""
699	699	CALF CONSTRUCTION TURNKEY	South Dublin	Broadfield Grove, Rathcoole - final phase *	4	Oaklee Housing Trust	""	""	""	""	""	Q3-2017
700	700	CALF CONSTRUCTION TURNKEY	South Dublin	Moyglas Glade, Lucan, Co Dublin*	1	Respond!	""	""	""	""	""	Q2-2017
701	701	CAS CONSTRUCTION	South Dublin	Old Nangor Road, Clondalkin	10	Simon Community : Dublin Simon	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
702	702	CAS CONSTRUCTION	South Dublin	Collinstown Grove, Clondalkin	4	Tath Housing Association Ltd	""	""	""	Stage 4 approved in Q3-2017, the scheme is now fully approved.	""	""
703	703	SHIP CONSTRUCTION	South Dublin	Balgaddy F	50	N/A	Stage 1 approved in Q1-2015, outline design and costs are now being prepared.	""	""	""	""	""
704	704	SHIP CONSTRUCTION	South Dublin	Ballyboden,  Rathfarnham	40	N/A	""	""	""	""	Q3-2017	""
705	705	SHIP CONSTRUCTION	South Dublin	St. Marks Avenue, Clondalkin	39	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
706	706	SHIP CONSTRUCTION	South Dublin	Letts Field, Neilstown, Clondalkin	37	N/A	""	""	""	""	Q3-2017	""
707	707	SHIP CONSTRUCTION	South Dublin	Killinarden, Tallaght	28	N/A	""	""	""	""	Q3-2017	""
708	708	SHIP CONSTRUCTION	South Dublin	Fortunestown (MacUilliam)	28	N/A	""	""	""	""	Q2-2017	""
709	709	SHIP CONSTRUCTION	South Dublin	Mayfield Estate, Clondalkin	18	N/A	""	""	""	""	Q1-2017	""
710	710	SHIP CONSTRUCTION	South Dublin	Dromcarra, Tallaght	14	N/A	""	""	""	""	Q2-2017	""
711	711	SHIP CONSTRUCTION	South Dublin	St Marks Green, Clondalkin	11	N/A	""	""	""	""	Q2-2017	""
712	712	SHIP CONSTRUCTION	South Dublin	Suncroft, Tallaght	10	N/A	""	""	""	""	""	Q4-2016
713	713	SHIP CONSTRUCTION	South Dublin	Belgard Road, Tallaght	3	N/A	""	""	""	""	""	Q1-2016
714	714	SHIP CONSTRUCTION	South Dublin	St Finians	2	N/A	""	""	""	""	""	Q3-2016
715	715	SHIP CONSTRUCTION RAPID	South Dublin	St Aidan's,  Brookfield, Tallaght	85	N/A	""	""	""	""	Q3-2017	""
716	716	SHIP CONSTRUCTION RAPID	South Dublin	St Cuthbert's, Clondalkin	59	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
717	717	SHIP CONSTRUCTION RAPID	South Dublin	Killininny Road, Firhouse (Old Mill, Old Bawn)	24	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
718	718	CALF CONSTRUCTION	Tipperary	Ashbury, Roscrea	12	Cluid Housing Association	""	""	""	""	""	Q2-2017
719	719	CALF CONSTRUCTION TURNKEY	Tipperary	Ashgrove, Monadreen, Thurles, Co Tipperary 	19	Co-operative Housing Ireland	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
720	720	CAS CONSTRUCTION	Tipperary	Stanwix House, Kickham Street, Thurles	19	Thurles Lions Trust Housing Assoc.	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
721	721	CAS CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	9	Cluid Housing Association	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
722	722	CAS CONSTRUCTION	Tipperary	Fethard	4	Belmont Park Housing Association Ltd	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
723	723	CAS CONSTRUCTION	Tipperary	Ballinagrana, Carrick on Suir	3	Camphill Communities of Ireland	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
724	724	CAS CONSTRUCTION	Tipperary	The Strand, Carrick on Suir	3	Camphill Communities of Ireland	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
725	725	CAS CONSTRUCTION	Tipperary	Castle Street, Carrick on Suir	1	Camphill Communities of Ireland	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
726	726	SHIP CONSTRUCTION	Tipperary	Knockanrawley	28	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
727	727	SHIP CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	26	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
728	728	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	25	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
729	729	SHIP CONSTRUCTION	Tipperary	Cormack Drive, Nenagh	19	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
730	730	SHIP CONSTRUCTION	Tipperary	Portroe, Nenagh	18	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
731	731	SHIP CONSTRUCTION	Tipperary	Borrisokane	17	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
732	732	SHIP CONSTRUCTION	Tipperary	Borrisoleigh	12	N/A	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
733	733	SHIP CONSTRUCTION	Tipperary	Abbey Street, Cahir	11	N/A	Stage 1 approved in Q2-2017, outline design and costs are now being prepared.	""	""	""	""	""
734	734	SHIP CONSTRUCTION	Tipperary	Killeanaule Road, Fethard	10	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
735	735	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	10	N/A	Stage 1 approved in Q2-2015, outline design and costs are now being prepared.	""	""	""	""	""
736	736	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	9	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
737	737	SHIP CONSTRUCTION	Tipperary	Templetouhy	6	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
738	738	SHIP CONSTRUCTION	Tipperary	Kilcooly Way, Gortnahoe	5	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
739	739	SHIP CONSTRUCTION	Tipperary	Lacey Avenue, Templemore	3	N/A	""	""	""	""	""	Q4-2016
740	740	SHIP CONSTRUCTION	Tipperary	Ard na Greine, Clonmel	2	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
741	741	SHIP CONSTRUCTION	Tipperary	Cloughjordan	2	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
742	742	SHIP CONSTRUCTION	Tipperary	Gortataggart, Thurles	2	N/A	""	""	Stage 3 approved in Q4-2015, the scheme is now being tendered.	""	""	""
743	743	SHIP CONSTRUCTION	Tipperary	Borrisoleigh	2	N/A	""	""	""	""	""	Q4-2016
744	744	SHIP CONSTRUCTION	Tipperary	Treacy Park, Carrick on Suir	1	N/A	""	""	Stage 3 approved in Q1-2017, the scheme is now being tendered.	""	""	""
745	745	SHIP CONSTRUCTION	Tipperary	Mitchels St., Thurles	1	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
746	746	SHIP CONSTRUCTION	Tipperary	Lower Ballingarry	1	N/A	""	""	""	""	""	Q2-2016
747	747	SHIP CONSTRUCTION	Tipperary	Poulamaleen, Faugheen	1	N/A	""	""	""	""	""	Q2-2016
748	748	SHIP CONSTRUCTION	Tipperary	Lacey Avenue, Templemore	1	N/A	""	""	""	""	""	Q3-2017
749	749	CALF CONSTRUCTION	Waterford	St Johns College, Waterford	36	Respond!	""	""	""	""	""	Q1-2016
750	750	CALF CONSTRUCTION TURNKEY	Waterford	Estuary Heights, Shandon Road, Dungarvan	20	Co-operative Housing Ireland	""	""	""	""	Q1-2017	""
751	751	CAS CONSTRUCTION	Waterford	Ballycarnane, Tramore	18	Tramore Voluntary Housing Association	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
752	752	CAS CONSTRUCTION	Waterford	Convent Hill, Tramore	10	Society of Saint Vincent de Paul	""	""	""	""	""	Q1-2017
753	753	CAS CONSTRUCTION	Waterford	Wadding Manor, Ferrybank	10	Respond!	""	""	""	""	Q4-2017	""
754	754	CAS CONSTRUCTION	Waterford	Gleann Ealach, Dunhill	8	Gleann Ealach Housing Association	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
755	755	CAS CONSTRUCTION	Waterford	The Paddocks, Williamstown Rd. Waterford	6	Anvers Housing Association Ltd	""	""	""	""	Q4-2017	""
756	756	CAS CONSTRUCTION	Waterford	Powersfield, Hennessys Road, Waterford	3	Focus Ireland	""	""	""	""	Q4-2017	""
757	757	SHIP CONSTRUCTION	Waterford	An Garran, Tramore	32	N/A	""	""	""	""	Q4-2017	""
758	758	SHIP CONSTRUCTION	Waterford	Avondale, Kilcohan	21	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
759	759	SHIP CONSTRUCTION	Waterford	Ballinroad, Dungarvan	20	N/A	""	""	""	""	Q4-2017	""
760	760	SHIP CONSTRUCTION	Waterford	Old Cinema Site, Dungarvan	15	N/A	""	""	""	""	""	Q4-2016
761	761	SHIP CONSTRUCTION	Waterford	Coolfin Woods, Portlaw	12	N/A	""	""	""	""	Q4-2017	""
762	762	SHIP CONSTRUCTION	Waterford	Ardmore Park/Priory Lawn, Waterford City	8	N/A	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
763	763	SHIP CONSTRUCTION	Waterford	Larchville, Waterford City	5	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
764	764	SHIP CONSTRUCTION	Waterford	Alms Houses, Tallow	4	N/A	""	""	""	""	Q4-2017	""
765	765	SHIP CONSTRUCTION	Waterford	Barrack Street, Cappoquin	4	N/A	""	""	""	""	""	Q4-2017
766	766	SHIP CONSTRUCTION	Waterford	Doyle Street, Waterford City	4	N/A	""	""	""	""	Q4-2017	""
767	767	SHIP CONSTRUCTION	Waterford	Patrick Street, Tramore	2	N/A	""	""	""	""	Q3-2017	""
768	768	SHIP CONSTRUCTION TURNKEY	Waterford	Kilrush, Dungarvan	39	N/A	""	""	""	""	Q3-2017	""
769	769	SHIP CONSTRUCTION TURNKEY	Waterford	Airport Road, Waterford City	33	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
770	770	SHIP CONSTRUCTION TURNKEY	Waterford	Carrickphierish, Gracedieu, Waterford	31	N/A	""	""	""	""	Q4-2017	""
771	771	SHIP CONSTRUCTION TURNKEY	Waterford	Gibbethill, Gracedieu	5	N/A	""	""	""	""	Q3-2017	""
772	772	SHIP CONSTRUCTION TURNKEY	Waterford	Shandon, Dungarvan	5	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
773	773	CALF CONSTRUCTION TURNKEY	Westmeath	Glenatore, Coosan, Athlone, Co Westmeath	26	Tath Housing Association Ltd	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
774	774	CALF CONSTRUCTION TURNKEY	Westmeath	Rahanine, Rochfortbridge, Co Westmeath*	12	Tath Housing Association Ltd	""	""	""	Scheme approved for CALF funding Q4-2017 	""	""
775	775	CALF CONSTRUCTION TURNKEY	Westmeath	Cluain Mullen, Castlepollard	2	Tath Housing Association	""	""	""	""	""	Q2-2017
776	776	CAS CONSTRUCTION	Westmeath	Springfield, Mullingar	12	Tath Housing Association Ltd	Stage 1 approved in Q1-2014, outline design and costs are now being prepared.	""	""	""	""	""
777	777	CAS CONSTRUCTION	Westmeath	Canal Avenue, Mullingar	9	Tath Housing Association Ltd	Stage 1 approved in Q3-2015, outline design and costs are now being prepared.	""	""	""	""	""
778	778	CAS CONSTRUCTION	Westmeath	Farran, Mullingar	3	Tath Housing Association Ltd	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
779	779	SHIP CONSTRUCTION	Westmeath	Clonbrusk, Athlone (Arcadia) - Site No. 2	33	N/A	""	""	""	Stage 4 approved in Q4-2017, the scheme is now fully approved.	""	""
780	780	SHIP CONSTRUCTION	Westmeath	Ennell Court (Phase 3)	33	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
781	781	SHIP CONSTRUCTION	Westmeath	Cloghanboy, Athlone	10	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
782	782	SHIP CONSTRUCTION	Westmeath	St. Laurence's Terrace, Mullingar	9	N/A	""	""	""	""	Q2-2017	""
783	783	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
784	784	SHIP CONSTRUCTION	Westmeath	Ennell Court (Phase 2)	3	N/A	""	""	""	""	""	Q2-2016
785	785	SHIP CONSTRUCTION	Westmeath	Grange Crescent, Mullingar	2	N/A	""	""	""	""	""	Q1-2016
786	786	SHIP CONSTRUCTION	Westmeath	16 Ennell Court	1	N/A	""	""	""	""	Q2-2017	""
787	787	SHIP CONSTRUCTION TURNKEY	Westmeath	Mullingar	21	N/A	""	""	""	""	""	Q4-2017
788	788	CALF CONSTRUCTION	Wexford	Meadowfields 	12	Co operative Ireland	""	""	""	""	""	Q3-2016
789	789	CALF CONSTRUCTION TURNKEY	Wexford	Enniscorthy	40	Oaklee Housing Trust	""	""	""	""	Q3-2017	""
790	790	CALF CONSTRUCTION TURNKEY	Wexford	Wexford	28	Oaklee Housing Trust	""	""	""	Scheme approved for CALF funding Q4-2016	""	""
791	791	CALF CONSTRUCTION TURNKEY	Wexford	 Hunters Green, Gorey - Phase 1	18	Co operative Ireland	""	""	""	""	""	Q2-2016
792	792	CALF CONSTRUCTION TURNKEY	Wexford	Hunters Green, Gorey - Phase 2	11	Co operative Ireland	""	""	""	""	""	Q1-2017
793	793	CALF CONSTRUCTION TURNKEY	Wexford	Ballyboggan, Castlebridge	10	Co-operative Housing Ireland	""	""	""	""	Q4-2017	""
794	794	CALF CONSTRUCTION TURNKEY	Wexford	Hunters Green, Gorey - Phase 3	9	Co operative Ireland	""	""	""	""	""	Q4-2017
795	795	CALF CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford*	6	Tath Housing Association	""	""	""	""	""	Q1-2017
796	796	CALF CONSTRUCTION TURNKEY	Wexford	233-253 Ard uisce, Whiterock, Wexford 	6	Tath Housing Association	""	""	""	""	Q4-2016	""
797	797	CALF CONSTRUCTION TURNKEY	Wexford	Unit No's 238, 239, 240, 241, 245 Ard Uisce, Whiterock	5	Tath Housing Association	""	""	""	""	""	Q4-2017
798	798	CAS CONSTRUCTION	Wexford	Barrystown	16	Grantstown Voluntary Housing Association Ltd	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
799	799	CAS CONSTRUCTION	Wexford	Westlands, Wexford	7	Respond!	""	""	""	""	Q4-2017	""
800	800	CAS CONSTRUCTION	Wexford	Rathangan	7	Rathangan Senior Citizens Housing Association Ltd	""	""	""	""	""	Q3-2017
801	801	SHIP CONSTRUCTION	Wexford	Whiterock Hill, Wexford	36	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
802	802	SHIP CONSTRUCTION	Wexford	Clonard, Wexford	26	N/A	Stage 1 approved in Q1-2016, outline design and costs are now being prepared.	""	""	""	""	""
803	803	SHIP CONSTRUCTION	Wexford	Cloghultagh, Taghmon	18	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
804	804	SHIP CONSTRUCTION	Wexford	Carricklawn, Coolcots, Wexford	14	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
805	805	SHIP CONSTRUCTION	Wexford	Killeens, Wexford	14	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
806	806	SHIP CONSTRUCTION	Wexford	Danescastle	12	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
807	807	SHIP CONSTRUCTION	Wexford	Ballywish, Castlebridge	11	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
808	808	SHIP CONSTRUCTION	Wexford	Creagh, Gorey	10	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
809	809	SHIP CONSTRUCTION	Wexford	Slippery Green, Wexford	10	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
810	810	SHIP CONSTRUCTION	Wexford	Baile an Tr, Riverchapel (Courtown Ardamine)	10	N/A	""	""	""	""	""	Q2-2016
811	811	SHIP CONSTRUCTION	Wexford	Baile Eoghain, Gorey	9	N/A	""	""	""	""	Q4-2017	""
812	812	SHIP CONSTRUCTION	Wexford	Cherryorchard, Enniscorthy	8	N/A	""	""	""	""	Q3-2017	""
813	813	SHIP CONSTRUCTION	Wexford	Shanna Court, Coolcotts	8	N/A	""	""	""	""	""	Q1-2016
814	814	SHIP CONSTRUCTION	Wexford	Belvedere Road, Wexford	7	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
815	815	SHIP CONSTRUCTION	Wexford	Coolcotts, Clonard	7	N/A	""	""	Stage 3 approved in Q4-2017, the scheme is now being tendered.	""	""	""
816	816	SHIP CONSTRUCTION	Wexford	Maudlintown, Wexford	5	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
817	817	SHIP CONSTRUCTION	Wexford	Glentire, The Ballagh, Enniscorthy	5	N/A	Stage 1 approved in Q4-2017, outline design and costs are now being prepared.	""	""	""	""	""
818	818	SHIP CONSTRUCTION	Wexford	King Street, Wexford	3	N/A	Stage 1 approved in Q3-2017, outline design and costs are now being prepared.	""	""	""	""	""
819	819	SHIP CONSTRUCTION	Wexford	Cois Mara	2	N/A	""	""	""	""	Q4-2017	""
820	820	SHIP CONSTRUCTION	Wexford	Oylegate	2	N/A	""	""	""	""	Q1-2017	""
821	821	SHIP CONSTRUCTION	Wexford	SN Castlemoyle, New Ross	1	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
822	822	SHIP CONSTRUCTION	Wexford	Ross Road, Enniscorthy	1	N/A	""	""	Stage 3 approved in Q3-2016, the scheme is now being tendered.	""	""	""
823	823	SHIP CONSTRUCTION	Wexford	Francis Street, Wexford	1	N/A	""	""	""	""	""	Q1-2017
824	824	SHIP CONSTRUCTION	Wexford	Commodore Barry	1	N/A	""	""	""	""	""	Q2-2016
825	825	SHIP CONSTRUCTION TURNKEY	Wexford	Madeira Oaks, Wexford	8	N/A	""	""	""	""	""	Q3-2017
826	826	CALF CONSTRUCTION	Wicklow	St Ernan's View, Merrymeeting, Rathnew	45	Cluid Housing Association	""	""	""	Scheme approved for CALF funding Q1-2017 	""	""
827	827	CALF CONSTRUCTION TURNKEY	Wicklow	Bollarney North, Wicklow Town, Wicklow	32	Tath Housing Association	""	""	""	Scheme approved for CALF Funding Q3-2017	""	""
828	828	CALF CONSTRUCTION TURNKEY	Wicklow	The Meadows, Ballynerrin, Wicklow Town	7	Tath Housing Association Ltd	""	""	""	Scheme approved for CALF Funding Q4-2017	""	""
829	829	CALF CONSTRUCTION TURNKEY	Wicklow	Abbey St, Wicklow	6	Tath Housing Association	""	""	""	""	Q2-2017	""
830	830	CAS CONSTRUCTION	Wicklow	Lathaleer, Baltinglass	5	KARE Promoting Inclusion for People with Intellectual Disabilities	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
831	831	SHIP CONSTRUCTION	Wicklow	Kilbride Lane, Bray (Murphy's Lands)	42	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
832	832	SHIP CONSTRUCTION	Wicklow	Carrig Eden,1 Marine Road, Greystones	30	N/A	Stage 1 approved in Q1-2017, outline design and costs are now being prepared.	""	""	""	""	""
833	833	SHIP CONSTRUCTION	Wicklow	Emoclew Road, Arklow (Phase 2)	26	N/A	""	Stage 2 approved in Q2-2017, full design/tender being prepared.	""	""	""	""
834	834	SHIP CONSTRUCTION	Wicklow	Farrankelly, Greystones (Phase 2)	24	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
835	835	SHIP CONSTRUCTION	Wicklow	Emoclew (Phase 3)	21	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
836	836	SHIP CONSTRUCTION	Wicklow	Sugarloaf View, Kilmacanogue	20	N/A	""	Stage 2 approved in Q1-2017, full design/tender being prepared.	""	""	""	""
837	837	SHIP CONSTRUCTION	Wicklow	Avondale Heights, Rathdrum (Phase 2)	20	N/A	""	""	""	""	Q3-2017	""
838	838	SHIP CONSTRUCTION	Wicklow	Emoclew Road, Arklow (Phase 1)	17	N/A	""	""	""	""	Q4-2017	""
839	839	SHIP CONSTRUCTION	Wicklow	FCA Hall, Wicklow Town	8	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
840	840	SHIP CONSTRUCTION	Wicklow	Old Library, Arklow	7	N/A	""	""	Stage 3 approved in Q2-2017, the scheme is now being tendered.	""	""	""
841	841	SHIP CONSTRUCTION	Wicklow	Kilmantain Place, Bray	4	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""
842	842	SHIP CONSTRUCTION	Wicklow	Ard Na Mara, Kilcoole	2	N/A	""	""	Stage 3 approved in Q3-2017, the scheme is now being tendered.	""	""	""
843	843	SHIP CONSTRUCTION	Wicklow	Druids Brook, Kilcoole	2	N/A	""	Stage 2 approved in Q4-2016, full design/tender being prepared.	""	""	""	""
844	844	SHIP CONSTRUCTION	Wicklow	10A Castle Villas, Greystones	1	N/A	""	Stage 2 approved in Q3-2017, full design/tender being prepared.	""	""	""	""
845	845	SHIP CONSTRUCTION	Wicklow	O'Byrne Road, Bray	1	N/A	""	""	""	""	Q4-2017	""
846	846	SHIP CONSTRUCTION	Wicklow	16A Oak Drive, Blessington	1	N/A	""	Stage 2 approved in Q4-2017, full design/tender being prepared.	""	""	""	""