﻿_id	No.	Funding Programme	LA	Scheme/Project Name	No. of Units	Approved Housing Body	Stage 1 Capital Appraisal	Stage 2 Pre Planning	Stage 3 Pre Tender design	Stage 4 Tender Report or Final Turnkey/CALF approval	On Site	Completed
1	1	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	16	*N/A	""	""	""	""	""	Q4-2021
2	2	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	13	*N/A	""	""	""	""	""	Q2-2021
3	3	SHIP CONSTRUCTION TURNKEY	Carlow	Granville Court, Granby Row,Carlow	4	*N/A	""	""	""	""	""	Q4-2021
4	4	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Ardattin	6	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
5	5	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Brownbog, Hackettstown	1	*N/A	""	""	""	""	Q1-2020	""
6	6	SHIP CONSTRUCTION SINGLE STAGE	Carlow	St. Mary?s Court, Carlow	4	*N/A	""	""	""	""	Q1-2022	""
7	7	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Drumphea, Garryhill, Bagenalstown	1	*N/A	""	""	""	""	Q3-2022	""
8	8	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Constable Hill, Hackettstown	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
9	9	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Old Leighlin Road, Carlow	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
10	10	SHIP CONSTRUCTION SINGLE STAGE	Carlow	5 & 6 Staplestown Road, Carlow	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
11	11	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Bahana, Glynn	5	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
12	12	SHIP CONSTRUCTION RENEWAL	Carlow	Barrack Street, Carlow	7	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
13	13	SHIP CONSTRUCTION RENEWAL	Carlow	Bog Lane, Borris	1	*N/A	""	""	""	""	""	Q2-2022
14	14	SHIP CONSTRUCTION RENEWAL	Carlow	2a Chapel Street, Graiguecullen, Carlow	1	*N/A	""	""	""	""	Q2-2022	""
15	15	SHIP CONSTRUCTION RENEWAL	Carlow	24 Church Street, Graiguecullen, Carlow 	1	*N/A	""	""	""	""	Q2-2022	""
16	16	SHIP CONSTRUCTION RENEWAL	Carlow	Breens Shop Units, Main Street, Borris	2	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
17	17	SHIP CONSTRUCTION	Carlow	Pound Lane, Borris	9	*N/A	""	""	""	""	""	Q2-2021
18	18	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	6	*N/A	""	""	""	""	Q3-2021	""
19	19	SHIP CONSTRUCTION	Carlow	41-42 Dublin Street & Cox's Lane, Carlow 	12	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
20	20	SHIP CONSTRUCTION	Carlow	Fr. Flood Park, Rathvilly	10	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
21	21	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	6	*N/A	""	""	""	""	Q3-2021	""
22	22	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	10	*N/A	""	""	""	""	Q3-2021	""
23	23	CAS CONSTRUCTION	Carlow	Gleann na Bearu, Royal Oak Road, Bagenalstown	6	Respond	""	""	""	""	Q4-2020	""
24	24	CAS CONSTRUCTION	Carlow	Homefield, Blackbog Road, Carlow	3	Carlow Voluntary Housing Association	""	""	""	""	""	Q2-2021
25	25	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 1)	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
26	26	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 2)	35	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
27	27	CALF Turnkey	Carlow	Ballyknockan Manor, Leighlinbridge, Co. Carlow (Phase 1)	24	Co - Operative Housing Ireland Society Limited	""	""	""	Q3-2022	""	""
28	28	CALF Turnkey	Carlow	Ballyknockan Manor, Leighlinbridge, Co. Carlow (Phase 2)*	13	Co - Operative Housing Ireland Society Limited	""	""	""	Q3-2022	""	""
29	29	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 1)*	17	Tuath Housing Association	""	""	""	""	""	Q3-2021
30	30	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 2)*	15	Tuath Housing Association	""	""	""	""	""	Q4-2021
31	31	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 3)*	21	Tuath Housing Association	""	""	""	""	""	Q1-2022
32	32	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 4)	10	Tuath Housing Association	""	""	""	""	""	Q2-2022
33	33	CALF Turnkey	Carlow	Granite Court, Ballyknockan, Fenagh, Co Carlow (Phase 1)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
34	34	CALF Turnkey	Carlow	Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
35	35	CALF Turnkey	Carlow	Rivercourt,  Carlow  (Phase 2)*	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2022
36	36	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
37	37	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 2)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
38	38	CALF Turnkey	Carlow	The Millrace, Burrin, Co. Carlow (Phase 1)*	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
39	39	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	4	*N/A	""	""	""	""	""	Q4-2021
40	40	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	4	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
41	41	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	8	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
42	42	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
43	43	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
44	44	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	7	*N/A	""	""	""	""	""	Q2-2022
45	45	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	11	*N/A	""	""	""	""	Q2-2021	""
46	46	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	10	*N/A	""	""	""	""	Q2-2021	""
47	47	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	11	*N/A	""	""	""	""	Q2-2021	""
48	48	SHIP CONSTRUCTION TURNKEY	Cavan	Clankee Court, Lisdrumskea, Shercock	2	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
49	49	SHIP CONSTRUCTION TURNKEY	Cavan	Abhainn Dubh, Rosehill, Mullagh	4	*N/A	""	""	""	""	""	Q4-2021
50	50	SHIP CONSTRUCTION TURNKEY	Cavan	Kilnavara Heights, Cavan Town	2	*N/A	""	""	""	""	Q1-2022	""
51	51	SHIP CONSTRUCTION	Cavan	Corstruce, Ballinagh	4	*N/A	""	""	""	""	""	Q2-2021
52	52	SHIP CONSTRUCTION	Cavan	Main Street, Mullagh	19	*N/A	""	""	""	""	Q4-2020	""
53	53	SHIP CONSTRUCTION	Cavan	Elm Grove, Main St, Cavan Town	13	*N/A	""	""	""	""	Q1-2022	""
54	54	SHIP CONSTRUCTION	Cavan	Cavan Road, Ballinagh	15	*N/A	""	""	""	""	Q2-2021	""
55	55	SHIP CONSTRUCTION	Cavan	Main St., Butlersbridge	6	*N/A	""	""	""	""	""	Q3-2022
56	56	SHIP CONSTRUCTION	Cavan	Cluain Dara, Kingscourt	3	*N/A	""	""	""	""	""	Q4-2021
57	57	SHIP CONSTRUCTION	Cavan	Fairymount Close, Kingscourt, Co. Cavan	3	*N/A	""	""	""	""	Q1-2022	""
58	58	SHIP CONSTRUCTION	Cavan	St. Bridgets Terrace, Cavan Town (Infill)	20	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
59	59	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	12	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
60	60	SHIP CONSTRUCTION	Cavan	Duckin Stool, Main Street, Belturbet	3	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
61	61	SHIP CONSTRUCTION	Cavan	The Widow's Row, Widow's House Lane, Belturbet	9	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
62	62	SHIP CONSTRUCTION	Cavan	Derrylurgan, Ballyjamesduff	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
63	63	SHIP CONSTRUCTION	Cavan	8 Units @ Ashgrove, Derrylurgan, Ballyjamesduff	8	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
64	64	SHIP CONSTRUCTION	Cavan	Dunaree, Kingscourt Town Centre	3	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
65	65	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	18	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
66	66	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	15	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
67	67	SHIP CONSTRUCTION	Cavan	Main St Lower, Kilnaleck, Co Cavan	2	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
68	68	SHIP CONSTRUCTION	Cavan	157 Barrack Road, Kilnaleck	4	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
69	69	SHIP CONSTRUCTION	Cavan	Main St., Kilnaleck	7	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
70	70	CAS CONSTRUCTION TURNKEY	Cavan	Loreto Lodge, Loreto Wood, Cavan Town	7	North ? East Housing Association Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
71	71	CAS CONSTRUCTION RENEWAL	Cavan	16 River St., Cavan	1	Society of Saint Vincent de Paul	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
72	72	CAS CONSTRUCTION	Cavan	St. Killian's Housing Association Ltd., Mullagh, Co. Cavan	4	St. Killian's Housing Association, Mullagh, Co. Cavan	""	""	""	""	Q1-2021	""
73	73	CAS CONSTRUCTION	Cavan	29 Bridge Street Cavan	6	Society of Saint Vincent de Paul	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
74	74	CALF Turnkey	Cavan	16 Units, Fairgreen Park, Mullagh, Co. Cavan (Phase 1)	16	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2021
75	75	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 1)	12	Tuath Housing Association	""	""	""	""	""	Q2-2022
76	76	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 2)	5	Tuath Housing Association	""	""	""	""	Q2-2021	""
77	77	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 3)	8	Tuath Housing Association	""	""	""	""	Q2-2021	""
78	78	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 1)	5	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
79	79	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 3)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
80	80	CALF Turnkey	Cavan	The Gallops, Cavan Town, Co. Cavan (Phase 2)	22	Clid Housing	""	""	""	""	""	Q2-2022
81	81	SHIP CONSTRUCTION TURNKEY	Clare	Shantraud Woods, Killaloe	4	*N/A	""	""	""	""	""	Q1-2022
82	82	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	20	N/A	""	""	""	""	Q2-2021	""
83	83	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	12	N/A	""	""	""	""	""	Q2-2022
84	84	SHIP CONSTRUCTION TURNKEY	Clare	Main St., Mountshannon	4	*N/A	""	""	""	""	""	Q3-2022
85	85	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	23	*N/A	""	""	""	""	Q1-2021	""
86	86	SHIP CONSTRUCTION TURNKEY	Clare	13 TK Units @ Clarehill, Clarecastle, Co Clare	13	N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
87	87	SHIP CONSTRUCTION SINGLE STAGE	Clare	Madden's Terrace, Clarecastle	2	*N/A	""	""	""	""	Q2-2021	""
88	88	SHIP CONSTRUCTION SINGLE STAGE	Clare	Dun na Mara, Doonbeg	2	*N/A	""	""	""	""	""	Q2-2021
89	89	SHIP CONSTRUCTION SINGLE STAGE	Clare	St Senan?s Terrace, Kilrush -No5-No 6	2	*N/A	""	""	""	""	""	Q3-2021
90	90	SHIP CONSTRUCTION RENEWAL	Clare	Nagles Terrace, Kilrush	3	N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
91	91	SHIP CONSTRUCTION	Clare	Ashline, Kilrush Road, Ennis	40	*N/A	""	""	""	""	""	Q2-2022
92	92	SHIP CONSTRUCTION	Clare	Ballard Rd,Miltown Malbay	27	*N/A	""	""	""	""	Q3-2020	""
93	93	SHIP CONSTRUCTION	Clare	Doonaun, Tulla	25	*N/A	""	""	""	""	""	Q2-2022
94	94	SHIP CONSTRUCTION	Clare	Boheraroan, Newmarket-on-Fergus	18	*N/A	""	""	""	""	""	Q1-2022
95	95	SHIP CONSTRUCTION	Clare	Ballyminogue,Feakle Rd., Scariff	18	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
96	96	SHIP CONSTRUCTION	Clare	Kilkee Road, Doonbeg	8	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
97	97	SHIP CONSTRUCTION	Clare	Tulla Road, Roslevan, Ennis (Fannings site)	8	*N/A	""	""	""	""	Q4-2021	""
98	98	SHIP CONSTRUCTION	Clare	Drumcliffe Road, Ennis	26	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
99	99	SHIP CONSTRUCTION	Clare	Deerpark, Ennistymon	30	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.	""	""	""	""	""
100	100	SHIP CONSTRUCTION	Clare	Ballyliddan West, Sixmilebridge	15	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
101	101	SHIP CONSTRUCTION	Clare	Gort Road Ennis	20	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
102	102	CAS CONSTRUCTION TURNKEY	Clare	Market Sq., Ennis	14	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
103	103	CAS CONSTRUCTION	Clare	Teach Rua, Edenvale Ennis	4	Newgrove Housing Association Ltd	""	""	""	""	""	Q2-2021
104	104	CALF Turnkey	Clare	Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 2)*	2	Clid Housing	""	""	""	""	""	Q1-2022
105	105	CALF Turnkey	Clare	Cluain Na Laoi, Kilkishen, Co. Clare (Phase 1)*	6	Circle Voluntary Housing Association Ltd	""	""	""	Q3-2022	""	""
106	106	CALF Turnkey	Clare	Cluain Na Laoi, Kilkishen, Co. Clare (Phase 2)	10	Circle Voluntary Housing Association Ltd	""	""	""	Q3-2022	""	""
107	107	CALF Turnkey	Clare	Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 2)*	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
108	108	CALF Turnkey	Clare	Hogan?s Place, Limerick Road, Ennis, Co. Clare (formerly Abbey View) (Phase 1)	9	Clid Housing	""	""	""	""	Q4-2021	""
109	109	CALF Turnkey	Clare	Hogan?s Place, Limerick Road, Ennis, Co. Clare (formerly Abbey View) (Phase 2)*	15	Clid Housing	""	""	""	""	Q4-2021	""
110	110	CALF Turnkey	Clare	Limerick Rd, Ennis, Co. Clare (Phase 1)*	18	Inis Housing Association	""	""	""	""	Q1-2022	""
111	111	CALF Turnkey	Clare	Radharc an Chnoic, Tulla, Co. Clare (Phase 1)*	2	Clid Housing	""	""	""	""	Q3-2021	""
112	112	CALF Construction	Clare	Revised - Bruachlan, Westbury, Co Clare (Phase 1)	22	Co - Operative Housing Ireland Society Limited	""	""	""	Q2-2021	""	""
113	113	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 1)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
114	114	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 2)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2022
115	115	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 3)*	24	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
116	116	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 4)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2022
117	117	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 1)	20	*N/A	""	""	""	""	""	Q2-2021
118	118	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 2)	31	*N/A	""	""	""	""	""	Q3-2021
119	119	SHIP DIALOG	Cork City	Barrack Street	32	*N/A	""	""	""	""	Q1-2019	""
120	120	SHIP DIALOG	Cork City	Woods Street	16	*N/A	""	""	""	""	Q1-2019	""
121	121	SHIP DIALOG	Cork City	Corkeran's Quay	3	*N/A	""	""	""	""	Q2-2018	""
122	122	SHIP DIALOG	Cork City	Skehard Road, Blackrock, Cork	16	*N/A	""	""	""	""	""	Q2-2022
123	123	SHIP DIALOG	Cork City	Coach Street, Cork	13	*N/A	""	""	""	""	Q3-2021	""
124	124	SHIP DIALOG	Cork City	Shanakiel Road, Cork	20	*N/A	""	""	""	""	""	Q3-2022
125	125	SHIP DIALOG	Cork City	Spring Lane, Blackpool, Cork	8	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
126	126	SHIP DIALOG	Cork City	Glen Ryan Road, Cork	9	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
127	127	SHIP DIALOG	Cork City	Pouladuff Road, Cork 	11	*N/A	""	""	""	""	""	Q2-2022
128	128	SHIP DIALOG	Cork City	Watercourse Road, Blackpool, Cork	37	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
129	129	SHIP DIALOG	Cork City	Denroche's Cross, Glasheen Road, Cork	43	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
130	130	SHIP DIALOG	Cork City	Wolsey Court, Blackpool, Cork	49	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
131	131	SHIP DIALOG	Cork City	Sunview, South Douglas Road, Douglas, Cork	25	*N/A	""	""	""	""	""	Q3-2022
132	132	SHIP DIALOG	Cork City	Former Bolands Mill, Old Mallow Road	54	*N/A	""	""	""	""	Q4-2021	""
133	133	SHIP DIALOG	Cork City	KILLEENS, CO CORK	44	*N/A	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
134	134	SHIP DIALOG	Cork City	Church Road, Black Rock, Cork	30	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
135	135	SHIP DIALOG	Cork City	East Cliff Road, Glanmire, Farranferris	81	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
136	136	SHIP DIALOG	Cork City	Kinsale road Cork City	47	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
137	137	SHIP DIALOG	Cork City	Ballincrokig, Ballyvolane	72	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
138	138	SHIP DIALOG	Cork City	Greenvalley, Douglas, Cork City	27	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
139	139	SHIP DIALOG	Cork City	Farranferris Cork City	26	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
140	140	SHIP DIALOG	Cork City	Grange Scairt Cross	59	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
141	141	SHIP DIALOG	Cork City	21-22 Dominick Street, Shandon, Cork City	9	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
142	142	SHIP DIALOG	Cork City	Hawkes Road, Bishopstown Road, Bishopstown, Cork City	29	*N/A	""	""	""	""	Q4-2021	""
143	143	SHIP DIALOG	Cork City	Lower John Street	3	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
144	144	SHIP CONSTRUCTION RENEWAL	Cork City	38 Gould Street	1	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
145	145	SHIP CONSTRUCTION RENEWAL	Cork City	1 Evenus Ville, Albert Road, Cork City	1	*N/A	""	""	""	""	Q3-2022	""
146	146	SHIP CONSTRUCTION RENEWAL	Cork City	Ard na Ri, Pouladuff Road, Cork City	1	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
147	147	SHIP CONSTRUCTION RENEWAL	Cork City	Mount Eden Road, Cork City	1	*N/A	""	""	""	""	Q3-2022	""
148	148	SHIP CONSTRUCTION RENEWAL	Cork City	21 St Anthony's Road	1	*N/A	""	""	""	""	Q3-2022	""
149	149	SHIP CONSTRUCTION RENEWAL	Cork City	26 Watercourse Road 	1	*N/A	""	""	""	""	Q3-2022	""
150	150	SHIP CONSTRUCTION RENEWAL	Cork City	22 Summerstown Grove	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
151	151	SHIP CONSTRUCTION RENEWAL	Cork City	2A Fairhill	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
152	152	SHIP CONSTRUCTION RENEWAL	Cork City	99 Ballinderry Park	1	*N/A	""	""	""	""	Q3-2022	""
153	153	SHIP CONSTRUCTION DESIGN BUILD	Cork City	Clover Hill Court, Bessboro Road, Mahon, Cork	88	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
154	154	SHIP CONSTRUCTION	Cork City	Poulavone, Ballincollig	64	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
155	155	SHIP CONSTRUCTION	Cork City	Boyces Street	14	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
156	156	SHIP CONSTRUCTION	Cork City	Madonna House, Ballincollig	6	*N/A	""	Stage 2 approved Q4-2019, full design/tender being prepared.	""	""	""	""
157	157	SHIP CONSTRUCTION	Cork City	Bramble Cottages	4	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
158	158	SHIP CONSTRUCTION	Cork City	Errigal Heights, The Glen, Cork City	28	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
159	159	SHIP CONSTRUCTION	Cork City	Glenamoy Lawn, Mayfield, Cork	3	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
160	160	SHIP CONSTRUCTION	Cork City	Hollywood Estate Infill Housing, Blarney Road, Cork	7	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
161	161	SHIP CONSTRUCTION	Cork City	Westside, Model Farm Road, Cork	43	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
162	162	SHIP CONSTRUCTION	Cork City	16A Kerry Road (former Sl Gartan), Mayfield, Cork 	1	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
163	163	SHIP CONSTRUCTION	Cork City	Boyces street	37	*N/A	""	Stage 2 approved Q1-2018, full design/tender being prepared.	""	""	""	""
164	164	SHIP CONSTRUCTION	Cork City	15 Loughview terrace, The Lough, Glasheen Cork City	1	*N/A	""	""	""	""	Q3-2022	""
165	165	SHIP CONSTRUCTION	Cork City	Ballyhooley Road, Cork City	26	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
166	166	SHIP CONSTRUCTION	Cork City	85A Gate Lodge Blackrock	1	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
167	167	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 1C	41	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
168	168	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 2B	38	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
169	169	REGENERATION	Cork City	Foyle Avenue Infill Housing Development, Knocknaheeny, Cork	2	*N/A	""	""	""	""	Q3-2022	""
170	170	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 3B	62	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
171	171	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 4A	43	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
172	172	CAS CONSTRUCTION SINGLE STAGE	Cork City	Eastville, Albert Road, Cork	1	Galtan Ltd	""	""	""	""	""	Q1-2022
173	173	CAS CONSTRUCTION SINGLE STAGE	Cork City	14 Glanmire Road Cork	2	Galtan Ltd	""	""	""	""	""	Q1-2022
174	174	CAS CONSTRUCTION	Cork City	Ard na Ri, Closes Green, Farranree, Cork	20	Farranree Sheltered Housing Association	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
175	175	CAS CONSTRUCTION	Cork City	Apts 2 & 3 Cois Coille, Tivoli, Cork	2	Galtan Ltd	""	""	""	""	""	Q4-2021
176	176	CAS CONSTRUCTION	Cork City	Aras Lean, Murphy?s Farm, Bishopstown, Co. Cork	15	Citizens Housing Association	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
177	177	CAS CONSTRUCTION	Cork City	Gardiners Hill, St Lukes, Cork 	3	Focus Ireland	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
178	178	CAS CONSTRUCTION	Cork City	88 Sundays Well	2	Galtan Ltd	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
179	179	CALF Turnkey	Cork City	12,14,15 Model Quarters, Tower, Blarney, Co Cork  (Phase 1)	3	Circle Voluntary Housing Association Ltd	""	""	""	""	Q2-2019	""
180	180	CALF Turnkey	Cork City	20 and 21 Kyle Street  (Phase 1)	6	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
181	181	CALF Turnkey	Cork City	40-42 Grand Parade, Cork City (Phase 1)	16	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
182	182	CALF Turnkey	Cork City	 Aylesbury, Ballintemple, Cork City (Phase 1)*	16	Respond	""	""	""	""	Q2-2022	""
183	183	CALF Turnkey	Cork City	Baker Street, Ballincollig, Co Cork (Phase 1)*	14	Clid Housing	""	""	""	Q2-2022	""	""
184	184	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 1)*	3	Tuath Housing Association	""	""	""	""	""	Q2-2022
185	185	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 2)*	3	Tuath Housing Association	""	""	""	""	""	Q2-2022
186	186	CALF Turnkey	Cork City	Block 10 Jacobs Island, Mahon, Cork (Phase 1)	69	Respond	""	""	""	Q3-2022	""	""
187	187	CALF Turnkey	Cork City	Boherboy Road, Silversprings Hill, Cork City  (Phase 1)*	15	Respond	""	""	""	""	Q1-2022	""
188	188	CALF Turnkey	Cork City	Brocklesby Street, Blackpool, Cork City (Phase 1)*	42	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
189	189	CALF Turnkey	Cork City	Daltons Avenue, Cornmarket Street, Cork City (Phase 1)*	14	Tuath Housing Association	""	""	""	Q3-2022	""	""
190	190	CALF Turnkey	Cork City	Evergreen Road, Turners Cross, Cork  (Phase 1)*	28	Respond	""	""	""	""	Q1-2021	""
191	191	CALF Turnkey	Cork City	Fairfield Meadows, Upper Fair Hill, Cork (Phase 1)*	18	Focus Housing Association CLG	""	""	""	Q3-2021	""	""
192	192	CALF Turnkey	Cork City	"Glanmire Village, Glanmire, Cork
 (Phase 1)"	3	Focus Housing Association CLG	""	""	""	""	""	Q2-2022
193	193	CALF Construction	Cork City	Green Lane, Blackpool, Cork City (Phase 1)	112	Clid Housing	""	""	""	""	Q4-2021	""
194	194	CALF Turnkey	Cork City	Haig Gardens, Boreenamanna Road and Wallace Avenue, Ballintemple (Phase 1)*	27	Respond	""	""	""	""	Q2-2021	""
195	195	CALF Turnkey	Cork City	Hereford Place, Ballymacthomas Street, Cork City (Phase 1)*	19	Respond	""	""	""	""	Q1-2020	""
196	196	CALF Turnkey	Cork City	Lancaster Gate, Western Road, Cork (Phase 1)	15	Clid Housing	""	""	""	""	Q3-2021	""
197	197	CALF Turnkey	Cork City	Link Road, Ballincollig, Cork (Phase 1)*	40	Respond	""	""	""	""	Q3-2021	""
198	198	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 1)	22	Tuath Housing Association	""	""	""	""	Q3-2021	""
199	199	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 2)	20	Tuath Housing Association	""	""	""	""	Q3-2021	""
200	200	CALF Turnkey	Cork City	Millfield Cottages, Blackpool, Cork City (Phase 1)*	18	Respond	""	""	""	""	Q3-2022	""
201	201	CALF Turnkey	Cork City	Newtown Heights, Boherboy Road, Lotamore, Cork   (Phase 1)	8	Clid Housing	""	""	""	""	Q2-2021	""
202	202	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 2)	31	Respond	""	""	""	""	""	Q4-2021
203	203	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 3)	20	Respond	""	""	""	""	""	Q3-2022
204	204	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 4)*	11	Respond	""	""	""	""	Q1-2020	""
205	205	CALF Turnkey	Cork City	Riverside Farm, Model Farm Road, Bishopstown, Cork (Phase 1)*	48	Respond	""	""	""	Q3-2022	""	""
206	206	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 1)*	22	Respond	""	""	""	""	""	Q2-2022
207	207	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 2)*	19	Respond	""	""	""	""	Q4-2020	""
208	208	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 3)	24	Respond	""	""	""	""	Q4-2020	""
209	209	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork City (Phase 1)	4	Respond	""	""	""	Q2-2022	""	""
210	210	CALF Turnkey	Cork City	Springville House, Bulls Lane, Blackrock Road, Cork (Phase 1)	35	Tuath Housing Association	""	""	""	""	Q4-2020	""
211	211	CALF Construction	Cork City	St Dominics, Middle Glanmire Road, Montenotte, Cork (Phase 1)	27	Tuath Housing Association	""	""	""	""	Q1-2021	""
212	212	CALF Turnkey	Cork City	Strawberry Hill, Blarney Street, Cork (Phase 1)*	16	Respond	""	""	""	Q3-2022	""	""
213	213	CALF Turnkey	Cork City	Summerville Place, Sunday?s Well, Cork (Phase 1)	10	Respond	""	""	""	""	Q1-2021	""
214	214	CALF Turnkey	Cork City	The Oaks, Frankfield, Douglas, Cork City (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2021
215	215	SHIP CONSTRUCTION TURNKEY	Cork County	Claragh Road, Millstreet	5	*N/A	""	""	""	""	""	Q2-2021
216	216	SHIP CONSTRUCTION TURNKEY	Cork County	Seafield, Bantry, 	3	*N/A	""	""	""	""	Q3-2018	""
217	217	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	6	*N/A	""	""	""	""	Q4-2017	""
218	218	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	3	*N/A	""	""	""	""	""	Q4-2021
219	219	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	5	*N/A	""	""	""	""	""	Q2-2022
220	220	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	11	*N/A	""	""	""	""	""	Q1-2021
221	221	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	17	*N/A	""	""	""	""	""	Q2-2021
222	222	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	5	*N/A	""	""	""	""	""	Q3-2022
223	223	SHIP CONSTRUCTION TURNKEY	Cork County	Millview Road, Kanturk	4	*N/A	""	""	""	""	""	Q1-2021
224	224	SHIP CONSTRUCTION TURNKEY	Cork County	Ard an Bhaile, Creggane, Buttevant	6	*N/A	""	""	""	""	Q1-2020	""
225	225	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A	""	""	""	""	""	Q2-2021
226	226	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	12	*N/A	""	""	""	""	""	Q2-2022
227	227	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	16	*N/A	""	""	""	""	Q4-2017	""
228	228	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	10	*N/A	""	""	""	""	Q1-2020	""
229	229	SHIP CONSTRUCTION TURNKEY	Cork County	An Goritin Rua, Millstreet Road, Macroom	14	*N/A	""	""	""	""	""	Q2-2021
230	230	SHIP CONSTRUCTION TURNKEY	Cork County	Lyraneag, Rockchapel,	2	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
231	231	SHIP CONSTRUCTION TURNKEY	Cork County	Eyeries, Castletownbere	6	*N/A	""	""	""	""	Q4-2020	""
232	232	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A	""	""	""	""	""	Q1-2021
233	233	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	18	*N/A	""	""	""	""	""	Q2-2021
234	234	SHIP CONSTRUCTION TURNKEY	Cork County	Drakes Point, Knocknagore, Crosshaven	5	*N/A	""	""	""	""	""	Q3-2021
235	235	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	6	*N/A	""	""	""	""	Q1-2020	""
236	236	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	6	*N/A	""	""	""	""	Q1-2020	""
237	237	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale	19	*N/A	""	""	""	""	""	Q4-2021
238	238	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	4	*N/A	""	""	""	""	""	Q1-2021
239	239	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale (Phase 2)	17	*N/A	""	""	""	""	""	Q3-2022
240	240	SHIP CONSTRUCTION TURNKEY	Cork County	Ard Cashel, Watergrasshill	6	*N/A	""	""	""	""	""	Q1-2022
241	241	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A	""	""	""	""	""	Q2-2021
242	242	SHIP CONSTRUCTION TURNKEY	Cork County	Courtbrack, Tower	1	*N/A	""	""	""	""	""	Q4-2021
243	243	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	10	*N/A	""	""	""	""	Q1-2019	""
244	244	SHIP CONSTRUCTION TURNKEY	Cork County	Lisgoold, An Tui 	2	*N/A	""	""	""	""	""	Q2-2022
245	245	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	26	*N/A	""	""	""	""	Q4-2017	""
246	246	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	4	*N/A	""	""	""	""	""	Q4-2021
247	247	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	7	*N/A	""	""	""	""	""	Q2-2021
248	248	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	3	*N/A	""	""	""	""	""	Q1-2022
249	249	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	5	*N/A	""	""	""	""	""	Q2-2022
250	250	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	4	*N/A	""	""	""	""	""	Q3-2022
251	251	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	12	*N/A	""	""	""	""	""	Q3-2022
252	252	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	5	*N/A	""	""	""	""	Q1-2021	""
253	253	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A	""	""	""	""	""	Q4-2021
254	254	SHIP CONSTRUCTION TURNKEY	Cork County	The Meadows, Dunmanway	4	N/A	""	""	""	""	""	Q3-2022
255	255	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	7	N/A	""	""	""	""	""	Q1-2022
256	256	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	12	*N/A	""	""	""	""	Q1-2020	""
257	257	SHIP CONSTRUCTION TURNKEY	Cork County	Dromdiah Park, Killeagh Gardens, Killeagh	10	*N/A	""	""	""	""	Q2-2021	""
258	258	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	7	*N/A	""	""	""	""	""	Q2-2022
259	259	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	7	*N/A	""	""	""	""	""	Q2-2022
260	260	SHIP CONSTRUCTION TURNKEY	Cork County	The Meadows, Dunmanway (Phase 2)	8	*N/A	""	""	""	""	""	Q3-2022
261	261	SHIP CONSTRUCTION TURNKEY	Cork County	Reanrour East, Bantry 	5	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
262	262	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	11	N/A	""	""	""	""	Q3-2021	""
263	263	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	4	N/A	""	""	""	""	Q1-2022	""
264	264	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	14	N/A	""	""	""	""	Q3-2021	""
265	265	SHIP CONSTRUCTION SINGLE STAGE	Cork County	2A Glenview, Lyre, Banteer	1	*N/A	""	""	""	""	Q2-2022	""
266	266	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Cuirt Na Slini, Cloyne, East Cork 	2	*N/A	""	""	""	""	Q3-2021	""
267	267	SHIP CONSTRUCTION SINGLE STAGE	Cork County	81 Belmont Place, Cobh,	1	*N/A	""	""	""	""	Q2-2022	""
268	268	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Main St. Dunmanway	1	*N/A	""	""	""	""	""	Q4-2021
269	269	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Croke Place, Garranmacgarrett, Kilbrin, kanturk	2	*N/A	""	""	""	""	Q3-2020	""
270	270	SHIP CONSTRUCTION SINGLE STAGE	Cork County	High St., Sleaveen Hill, Macroom	1	*N/A	""	""	""	""	""	Q2-2022
271	271	SHIP CONSTRUCTION SINGLE STAGE	Cork County	49 Masseytown, Macroom	1	*N/A	""	""	""	""	""	Q2-2022
272	272	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Aisling Gheal, Hospital Hill, Kanturk	1	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
273	273	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Carrig Rossa Phase 2, Rossmore	2	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
274	274	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Fana Na gCann, Co. Cork	2	*N/A	""	""	""	""	Q1-2022	""
275	275	SHIP CONSTRUCTION SINGLE STAGE	Cork County	3 Knockbrogan Park, Bandon	1	*N/A	""	""	""	""	""	Q4-2021
276	276	SHIP CONSTRUCTION SINGLE STAGE	Cork County	87 Belmont, Cobh	1	*N/A	""	""	""	""	""	Q3-2022
277	277	SHIP CONSTRUCTION	Cork County	Ard Na Greine, Cortmacsherry	17	*N/A	""	""	""	""	Q3-2019	""
278	278	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	51	*N/A	""	""	""	""	""	Q4-2021
279	279	SHIP CONSTRUCTION	Cork County	Newtown House , Bantry	1	*N/A	""	""	""	""	""	Q4-2021
280	280	SHIP CONSTRUCTION	Cork County	Kilnagleary, Carrigaline (Phase 4)	15	*N/A	""	""	""	""	Q4-2019	""
281	281	SHIP CONSTRUCTION	Cork County	Townsend Street, Skibbereen	6	*N/A	""	""	""	""	""	Q2-2022
282	282	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	5	*N/A	""	""	""	""	""	Q3-2022
283	283	SHIP CONSTRUCTION	Cork County	Richmond Court, Bandon	6	*N/A	""	""	""	""	Q2-2022	""
284	284	SHIP CONSTRUCTION	Cork County	Brigown Road, Mitchelstown	8	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
285	285	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	8	*N/A	""	""	Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.	""	""	""
286	286	SHIP CONSTRUCTION	Cork County	Pound Lane, Kilworth 	7	*N/A	""	""	""	""	Q1-2022	""
287	287	SHIP CONSTRUCTION	Cork County	Broomfield West, Avoncore, Midelton	4	*N/A	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
288	288	SHIP CONSTRUCTION	Cork County	Knocknagown, Rylane	1	*N/A	""	""	""	""	""	Q3-2021
289	289	SHIP CONSTRUCTION	Cork County	Uplands (Phase 2), College Road,  Fermoy	11	*N/A	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
290	290	SHIP CONSTRUCTION	Cork County	Lissoran, Ballinspittle	4	*N/A	""	""	""	""	""	Q4-2021
291	291	SHIP CONSTRUCTION	Cork County	Convent Road, Doneraile	17	*N/A	""	""	""	""	Q4-2021	""
292	292	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	13	*N/A	""	""	""	""	""	Q3-2022
293	293	SHIP CONSTRUCTION	Cork County	Mill Road, Kanturk, Co. Cork	13	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
294	294	SHIP CONSTRUCTION	Cork County	Chapel Lane, Ballydehob, Co. Cork	12	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
295	295	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	16	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
296	296	SHIP CONSTRUCTION	Cork County	Pls an Iarnrid (Railway Place), Old Barrack Road, Bantry, Co. Cork	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
297	297	SHIP CONSTRUCTION	Cork County	Coastguard Cottages, Lower Roads, Crosshaven, Co. Cork	33	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
298	298	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	6	N/A	""	""	""	""	""	Q2-2022
299	299	SHIP CONSTRUCTION	Cork County	Avoncore, Midleton (Rae Avoncore)	6	N/A	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
300	300	SHIP CONSTRUCTION	Cork County	Porter?s Lane, Youghal, Co. 	6	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
301	301	CAS CONSTRUCTION TURNKEY	Cork County	Ardmanagh, Schull	12	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
302	302	CAS CONSTRUCTION TURNKEY	Cork County	1-10 Vickerys Inn, New Street Bantry	10	Peter McVerry Trust Ltd	""	""	""	""	Q4-2019	""
303	303	CAS CONSTRUCTION TURNKEY	Cork County	Main Street, Charleville, Co. Cork	10	Peter McVerry Trust Ltd	""	""	""	""	Q1-2022	""
304	304	CAS CONSTRUCTION TURNKEY	Cork County	Mullavale, Castletownroche	8	Respond	""	""	""	""	Q4-2021	""
305	305	CAS CONSTRUCTION TURNKEY	Cork County	Church Place, Oliver Plunkett Hill, Fermoy, Co Cork	7	Focus Ireland	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
306	306	CAS CONSTRUCTION	Cork County	Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay	18	Cluid Housing Association	""	""	""	""	Q1-2022	""
307	307	CAS CONSTRUCTION	Cork County	Masseytown, Macroom	19	Tath Housing Association Ltd	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
308	308	CAS CONSTRUCTION	Cork County	Baile Bhuire, Macroom	3	Comhlacht Tithe Soisialta Agus ? Forbairt An Tsulain Teoranta	""	""	""	""	""	Q3-2022
309	309	CAS CONSTRUCTION	Cork County	Charleville, Church View, Love Lane, Charleville	9	Charleville Care Project Ltd	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
310	310	CAS CONSTRUCTION	Cork County	St. Michaels, 36 Main Street, Bandon, Co. Cork	6	Bandon Geriatric ? Community Council	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
311	311	CAS CONSTRUCTION	Cork County	Distillery Lane, Distillery Walk, Midleton	6	Midleton Lions Clubs Housing Association Limited	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
312	312	CAS CONSTRUCTION	Cork County	Mardyke, Skibbereen	8	The Skibbereen Geriatric Society Limited	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
313	313	CAS CONSTRUCTION	Cork County	Daniel O?Brien Terrace, Buttevant	9	Tath Housing Association Ltd	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
314	314	CAS CONSTRUCTION	Cork County	Lisheen Field, Kilbarry Road, Dunmanway, Co. Cork	16	Cluid Housing Association	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
315	315	CAS CONSTRUCTION	Cork County	8 Harbour Row, Cobh	5	?glaigh Nisinta na hireann (O.N.E.)	""	""	""	""	""	Q3-2022
316	316	CALF Turnkey	Cork County	Barnahely, Ringaskiddy, Cork (Phase 1)	2	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2021	""
317	317	CALF Turnkey	Cork County	Cascade Apartments, Castlelake, Carrigtwohill, Cork (Phase 1)	95	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2021	""
318	318	CALF Turnkey	Cork County	Castle Heights, Kilmoney, Carrigaline, Co Cork (Phase 1)	8	Clid Housing	""	""	""	""	Q2-2021	""
319	319	CALF Turnkey	Cork County	Castle Heights, Kilmoney, Carrigaline, Co Cork (Phase 2)	4	Clid Housing	""	""	""	""	Q2-2021	""
320	320	CALF Turnkey	Cork County	Cedar Court, Rathgoggin North, Charleville, Cork (Phase 1)	11	Tuath Housing Association	""	""	""	""	Q2-2022	""
321	321	CALF Turnkey	Cork County	Cedar Court, Rathgoggin North, Charleville, Cork (Phase 2)*	23	Tuath Housing Association	""	""	""	""	Q2-2022	""
322	322	CALF Turnkey	Cork County	Church Hill, Carrigaline, Co Cork (Phase 1)*	37	Respond	""	""	""	""	Q3-2021	""
323	323	CALF Turnkey	Cork County	Cooline, Cobh, Co Cork (Phase 1)	17	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
324	324	CALF Turnkey	Cork County	Cooline, Cobh, Co Cork (Phase 2)	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
325	325	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 1)	14	Clid Housing	""	""	""	""	""	Q3-2022
326	326	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 2)	13	Clid Housing	""	""	""	""	Q4-2020	""
327	327	CALF Turnkey	Cork County	Hazel View, Hazel Brooke, Spa Glen, Mallow, Co Cork (Phase 1)	12	Clid Housing	""	""	""	""	Q4-2021	""
328	328	CALF Turnkey	Cork County	Lough Beg, Loughbeg, Ringaskiddy, Cork (Phase 1)*	15	Respond	""	""	""	Q2-2022	""	""
329	329	CALF Turnkey	Cork County	No. 6 Shortcastle St, Mallow, Co Cork  (Phase 1)	8	Focus Housing Association CLG	""	""	""	Q3-2022	""	""
330	330	CALF Turnkey	Cork County	Shambles Lane, Thomas Davis Street, Mallow, Co Cork (Phase 1)	6	Focus Housing Association CLG	""	""	""	""	Q1-2022	""
331	331	CALF Turnkey	Cork County	Westview, Coolroe, Ballincollig, Co. Cork (Phase 2)	20	Respond	""	""	""	""	""	Q1-2021
332	332	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 1)	20	*N/A	""	""	""	""	""	Q2-2021
333	333	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 2)	32	*N/A	""	""	""	""	""	Q4-2021
334	334	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 1)	35	*N/A	""	""	""	""	""	Q2-2021
335	335	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 2)	15	*N/A	""	""	""	""	""	Q4-2021
336	336	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 1)	37	*N/A	""	""	""	""	""	Q2-2021
337	337	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 2)	13	*N/A	""	""	""	""	""	Q3-2021
338	338	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	22	*N/A	""	""	""	""	""	Q1-2021
339	339	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	16	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
340	340	SHIP CONSTRUCTION TURNKEY	DLR	George's Street Upper, Dun Laoghaire, Co. Dublin	5	*N/A	""	""	""	""	""	Q1-2021
341	341	SHIP CONSTRUCTION TURNKEY	DLR	HazelBrook Square, Nutgrove, Churchtown	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
342	342	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	17	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
343	343	SHIP CONSTRUCTION TURNKEY	DLR	Dun Gaoithe, Sandyford, Dublin 18	2	N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
344	344	SHIP CONSTRUCTION DESIGN BUILD	DLR	Ballyogan Square, Ballyogan	67	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
345	345	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	35	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
346	346	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	104	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
347	347	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	61	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
348	348	SHIP CONSTRUCTION	DLR	Park House, 66 George's Street, Dun Laoghaire	4	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
349	349	SHIP CONSTRUCTION	DLR	Broadford Rise	21	*N/A	""	""	""	""	""	Q4-2021
350	350	SHIP CONSTRUCTION	DLR	Ballyogan Avenue, Ballyogan	2	*N/A	""	""	""	""	""	Q2-2021
351	351	SHIP CONSTRUCTION	DLR	St. Laurence?s Park, Stillorgan, Co. Dublin	88	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
352	352	SHIP CONSTRUCTION	DLR	Moyola Court, Churchtown Lower, Dublin 14	4	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
353	353	SHIP CONSTRUCTION	DLR	Site at Roebuck Road, Clonskeagh, Dublin 14	4	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
354	354	SHIP CONSTRUCTION	DLR	37A Rollins Villas, Sallynoggin, Co. Dublin 	1	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
355	355	SHIP CONSTRUCTION	DLR	Old Coastguard Cottages, Coal Harbour, Harbour Road	4	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
356	356	SHIP CONSTRUCTION	DLR	Cross Avenue, Dn Laoghaire, Co. Dublin	4	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
357	357	SHIP CONSTRUCTION	DLR	Infill Site Adjacent to 4 Rockville Drive, Glenamuck, Co. Dublin	1	N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
358	358	SHIP CONSTRUCTION	DLR	Blackglen Road, Sandyford, Dublin 18	98	N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
359	359	CAS CONSTRUCTION SINGLE STAGE	DLR	58-59 Patrick Street, Dn Laoghaire, Co. Dublin	8	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
360	360	CAS CONSTRUCTION	DLR	30 Obelisk Walk, Blackrock	4	St. John of God Housing Association Ltd	""	""	""	""	""	Q4-2021
361	361	CALF Turnkey	DLR	Ardilea Crescent, Ardilea, Clonskeagh, Dublin 14, Co. Dublin (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2021
362	362	CALF Turnkey	DLR	Ballybetagh Road, Kilternan, Co Dublin (Phase 1)*	22	Clanmil Housing Association Ireland	""	""	""	""	Q3-2021	""
363	363	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 1)*	80	Clid Housing	""	""	""	""	Q4-2019	""
364	364	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 2)*	61	Clid Housing	""	""	""	""	Q4-2019	""
365	365	CALF Turnkey	DLR	Egremont, Church Road, Killiney, Co. Dublin (Phase 1)*	4	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2019	""
366	366	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 1)	9	Respond	""	""	""	""	""	Q4-2021
367	367	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 2)	22	Respond	""	""	""	""	""	Q1-2022
368	368	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 3)	22	Respond	""	""	""	""	""	Q1-2022
369	369	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 1)	18	Tuath Housing Association	""	""	""	""	""	Q4-2021
370	370	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 2)	16	Tuath Housing Association	""	""	""	""	""	Q1-2022
371	371	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 3)	18	Tuath Housing Association	""	""	""	""	""	Q1-2022
372	372	CALF Turnkey	DLR	Johnstown Place,Johnstown Road, Cabinteely, Dublin 18 (Formerly Johnstown Court) (Phase 1)*	51	Clid Housing	""	""	""	""	""	Q2-2021
373	373	CALF Turnkey	DLR	Kiln View, Clay Farm Way, Leopardstown, Co Dublin (Phase 1)*	55	The Iveagh Trust	""	""	""	""	Q4-2020	""
374	374	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 1)*	14	Tuath Housing Association	""	""	""	""	""	Q1-2021
375	375	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 2)*	18	Tuath Housing Association	""	""	""	""	""	Q2-2021
376	376	CALF Turnkey	DLR	Oakton Court, Ballybrack, Co. Dublin (Phase 1)	5	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2021	""
377	377	CALF Turnkey	DLR	Phase 2, Elmwood, Johnstown Road, Cabinteely, Dun Laoghaire, Co. Dublin (Phase 1)*	58	Clid Housing	""	""	""	""	""	Q1-2022
378	378	CALF Turnkey	DLR	The Glen, Glenamuck Road, Carrickmines, Dublin 18 (Phase 1)*	48	Respond	""	""	""	""	Q1-2021	""
379	379	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)	30	Respond	""	""	""	""	Q3-2020	""
380	380	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)*	2	Respond	""	""	""	""	Q3-2020	""
381	381	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 2)	29	Respond	""	""	""	""	Q3-2020	""
382	382	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 2)*	4	Respond	""	""	""	""	Q3-2020	""
383	383	SHIP DIALOG	Donegal	Drumrooske West	36	*N/A	""	""	""	Stage 4 approved Q3-2019, the scheme is fully approved.	""	""
384	384	SHIP DIALOG	Donegal	Brookfield, Donegal Town	8	*N/A	""	""	""	""	""	Q1-2022
385	385	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
386	386	SHIP DIALOG	Donegal	Donegal Road, Ballybofey	14	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
387	387	SHIP DIALOG	Donegal	Admiran, Stranorlar	52	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
388	388	SHIP DIALOG	Donegal	Rockview, Carrickboy, Ballyshannon	5	*N/A	""	""	""	""	Q1-2021	""
389	389	SHIP DIALOG	Donegal	Glencrow, Moville	35	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
390	390	SHIP DIALOG	Donegal	Ballyraine, Letterkenny	25	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
391	391	SHIP DIALOG	Donegal	Brookfield, Donegal Town	12	*N/A	""	""	""	""	Q4-2020	""
392	392	SHIP DIALOG	Donegal	Brookfield, Donegal Town	14	*N/A	""	""	""	""	Q4-2020	""
393	393	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
394	394	SHIP DIALOG	Donegal	Cnoc Ard, Carnamuggagh, Letterkenny	6	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
395	395	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Loughanure Annagry	1	*N/A	""	""	""	""	""	Q3-2022
396	396	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Meenderrynasloe, Annagry	1	*N/A	""	""	""	""	""	Q3-2022
397	397	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Knockamany Malin	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
398	398	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Largymore, Kilcar	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
399	399	SHIP CONSTRUCTION SINGLE STAGE	Donegal	The Meadows, Buncrana	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
400	400	SHIP CONSTRUCTION	Donegal	Meadow Hill, Raphoe	11	*N/A	""	""	""	""	Q3-2020	""
401	401	SHIP CONSTRUCTION	Donegal	Long Lane, Letterkenny	29	*N/A	""	""	""	""	""	Q2-2021
402	402	SHIP CONSTRUCTION	Donegal	Rockytown, Buncrana (Phase 1)	21	*N/A	""	""	""	""	""	Q2-2022
403	403	SHIP CONSTRUCTION	Donegal	Pound Street, Dunfanaghy	4	*N/A	""	""	""	""	""	Q3-2022
404	404	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A	""	""	""	""	""	Q2-2021
405	405	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
406	406	SHIP CONSTRUCTION	Donegal	Trusk Road, Ballybofey	19	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
407	407	SHIP CONSTRUCTION	Donegal	Crana Crescent, Buncrana	16	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
408	408	SHIP CONSTRUCTION	Donegal	Drumacrin, Bundoran	42	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
409	409	SHIP CONSTRUCTION	Donegal	Gallow's Lane, Lifford	29	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
410	410	SHIP CONSTRUCTION	Donegal	Chapel Road, Dungloe	45	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
411	411	SHIP CONSTRUCTION	Donegal	Kilmacrennan, Letterkenny	34	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
412	412	SHIP CONSTRUCTION	Donegal	Rockytown, Buncrana (Phase 2)	58	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
413	413	CAS CONSTRUCTION	Donegal	Glenrowan House, Drumkeen, Stranorlar	5	Apex Housing Association	""	""	""	""	Q4-2020	""
414	414	CAS CONSTRUCTION	Donegal	Cois Locha, Meenmore, Dungloe	15	County Donegal Parents and Friends Housing Association Ltd	""	""	""	""	Q3-2020	""
415	415	CAS CONSTRUCTION	Donegal	Raphoe Road, Castlefinn	34	Habinteg Housing Association (Ireland) Ltd	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
416	416	CALF Turnkey	Donegal	Ard na Grine, Glencar Scotch, Letterkenny, Co. Donegal  (Phase 1)*	18	Clid Housing	""	""	""	""	Q2-2021	""
417	417	CALF Turnkey	Donegal	Ballaghderg, Letterkenny, Co Donegal  (Phase 1)*	33	Respond	""	""	""	""	""	Q1-2021
418	418	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	113	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
419	419	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	87	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
420	420	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	75	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
421	421	SHIP CONSTRUCTION TURNKEY	Dublin City	88-89 Drimnagh Road Dublin 12	24	*N/A	""	""	""	""	Q1-2022	""
422	422	SHIP CONSTRUCTION TURNKEY	Dublin City	St. Pancras, Harolds Cross, Dublin 6	4	*N/A	""	""	""	""	""	Q2-2021
423	423	SHIP CONSTRUCTION TURNKEY	Dublin City	Core 4, Block 4 Charlemont Square, Dublin 2	15	*N/A	""	""	""	""	""	Q2-2022
424	424	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Belcamp B, Dublin 17	12	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
425	425	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Bunratty Road	78	*N/A	""	""	""	""	Q4-2019	""
426	426	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Bonham Street Dublin  8 	57	*N/A	""	""	""	""	Q4-2019	""
427	427	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Cork Street/Chamber Street Dublin 8	55	*N/A	""	""	""	""	Q1-2020	""
428	428	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Springvale Chapelizod Dublin 8	71	*N/A	""	""	""	""	Q1-2020	""
429	429	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Cromcastle & Woodville, Coolock, Dublin 5	156	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.	""	""	""	""	""
430	430	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Crumlin Road - Rafters Lane, Dublin 12	47	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
431	431	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	St. Andrews Court, Dublin 2	37	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
432	432	SHIP CONSTRUCTION	Dublin City	Cornamona, Ballyfermot, Dublin 12	61	*N/A	""	""	""	""	Q2-2019	""
433	433	SHIP CONSTRUCTION	Dublin City	Infirmary Road, Dublin 7	38	*N/A	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
434	434	SHIP CONSTRUCTION	Dublin City	North King Street, - Sean Foster Place, Dublin 7	30	*N/A	""	""	""	""	Q2-2019	""
435	435	SHIP CONSTRUCTION	Dublin City	St. Finbar's Court, Kilkieran Road, Dublin 7	46	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
436	436	SHIP CONSTRUCTION	Dublin City	Dominick Street (East side)	72	*N/A	""	""	""	""	Q1-2018	""
437	437	SHIP CONSTRUCTION	Dublin City	O'Devaney Gardens - Phase 1A	56	*N/A	""	""	""	""	Q3-2018	""
438	438	SHIP CONSTRUCTION	Dublin City	Glin Court, Coolock, Dublin 17	32	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
439	439	SHIP CONSTRUCTION	Dublin City	Kildonan Road	75	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
440	440	SHIP CONSTRUCTION	Dublin City	Lands at Emmet Road	117	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
441	441	SHIP CONSTRUCTION	Dublin City	Sarsfield Lands, Sarsfield Road, Ballyfermot, Dublin 10	176	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
442	442	SHIP CONSTRUCTION	Dublin City	St. Anne's Court, All Saints Drive, Raheny, Dublin 5	102	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
443	443	REGENERATION	Dublin City	Dolphin House Phase 1b, Dolphins Barn, Rialto, Dublin 8	35	*N/A	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
444	444	REGENERATION	Dublin City	Dorset Street, Dublin 7	163	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
445	445	REGENERATION	Dublin City	Matt Talbot Court, Matt Talbot Street, Dublin 1	92	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
446	446	REGENERATION	Dublin City	Constitution Hill Dublin 7	124	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
447	447	REGENERATION	Dublin City	Pearse House, Sandwith Street Lower, Dublin 2 (Blocks L,M,N &P)	75	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
448	448	REGENERATION	Dublin City	Bluebell Phase 1A, Bluebell Road, Dublin 12	140	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
449	449	REGENERATION	Dublin City	Liberties Cluster Phase 1, School Street, The Liberties, Dublin 8	115	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
450	450	REGENERATION	Dublin City	Oliver Bond House, Oliver Bond Street, Dublin 8	48	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
451	451	REGENERATION	Dublin City	Glovers Court, York Street, Dublin 2	49	N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
452	452	CAS CONSTRUCTION TURNKEY	Dublin City	Block 70, The Plaza, Parkwest, Dublin 12 	43	Tath Housing Association Ltd	""	""	""	""	""	Q2-2022
453	453	CAS CONSTRUCTION TURNKEY	Dublin City	9-40 Walker Grove, Parkside, Dublin 13	32	Tath Housing Association Ltd	""	""	""	""	""	Q3-2022
454	454	CAS CONSTRUCTION SINGLE STAGE	Dublin City	61 & 63 Rathoath Avenue, Finglas, Dublin 11	6	Arlington Novas Ireland Ltd	""	""	""	""	Q4-2020	""
455	455	CAS CONSTRUCTION SINGLE STAGE	Dublin City	88 Lower Drumcondra Road, Dublin 9 	6	Peter McVerry Trust Ltd	""	""	""	""	Q4-2021	""
456	456	CAS CONSTRUCTION RENEWAL	Dublin City	8 North Frederick Street, Dublin 1	12	Peter McVerry Trust Ltd	""	""	""	""	""	Q4-2021
457	457	CAS CONSTRUCTION RENEWAL	Dublin City	190 -192 Moore Haven, Drumcondra Road Upper, Dublin 9.	8	DePaul Housing	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
458	458	CAS CONSTRUCTION	Dublin City	Ellis Court, Dublin	22	Tath Housing Association Ltd	""	""	""	""	Q3-2019	""
459	459	CAS CONSTRUCTION	Dublin City	180-187 Townsend Street, Dublin 2	20	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
460	460	CAS CONSTRUCTION	Dublin City	26 New Street South, Dublin 8	8	Peter McVerry Trust Ltd	""	""	""	""	""	Q1-2021
461	461	CAS CONSTRUCTION	Dublin City	55B Arbour Hill, Dublin 7	14	Simon Community : Dublin Simon	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
462	462	CAS CONSTRUCTION	Dublin City	St. Michael's Estate, Inchicore, Dublin 8 - Housing Pilot Project 	52	Circle Voluntary Housing Association Ltd	""	""	""	""	Q3-2022	""
463	463	CAS CONSTRUCTION	Dublin City	Shaw Street, Dublin 2	12	Peter McVerry Trust Ltd	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
464	464	CAS CONSTRUCTION	Dublin City	13A Casement Drive, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
465	465	CAS CONSTRUCTION	Dublin City	Sarsfield Road, Ballyfermot, Dublin 10	6	Respond	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
466	466	CAS CONSTRUCTION	Dublin City	25-26 Ushers Island Ushers Quay Dublin 8	0	Simon Community : Dublin Simon	""	""	""	""	Q4-2021	""
467	467	CAS CONSTRUCTION	Dublin City	Barnamore Grove, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
468	468	CAS CONSTRUCTION	Dublin City	5-7 Halston Street, Dublin 7	12	Peter McVerry Trust Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
469	469	CAS CONSTRUCTION	Dublin City	307a Casement Road, Finglas, Co. Dublin 	1	Arlington Novas Ireland Ltd	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
470	470	CAS CONSTRUCTION	Dublin City	29-30 Fishamble Street, Dublin 8	10	Peter McVerry Trust Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
471	471	CAS CONSTRUCTION	Dublin City	26-28 Upper Sherrard Street, Dublin 1	12	Peter McVerry Trust Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
472	472	CALF Turnkey	Dublin City	15 Richmond Avenue, Dublin 3 (Phase 1)	35	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
473	473	CALF Turnkey	Dublin City	25-27 Bow Lane West, Dublin 8 (Phase 1)	27	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
474	474	CALF Turnkey	Dublin City	Aughrim Street, Stoneybatter, Dublin 7 (Phase 1)	4	Clanmil Housing Association Ireland	""	""	""	""	""	Q2-2021
475	475	CALF Construction	Dublin City	Bethany House, Gilford Road, Sandymount, Dublin 4 (Phase 1)	62	Clid Housing	""	""	""	""	Q4-2021	""
476	476	CALF Turnkey	Dublin City	Blackbanks Vie5w, 754 Howth Road, Raheny, Dublin  (Phase 1)*	40	Clid Housing	""	""	""	""	""	Q1-2021
477	477	CALF Turnkey	Dublin City	Bluebell Avenue, Bluebell, Dublin 12 (Phase 1)*	52	Respond	""	""	""	""	""	Q2-2022
478	478	CALF Turnkey	Dublin City	Camac Park, Bluebell, Dublin 12 (Phase 1)	3	Tuath Housing Association	""	""	""	""	""	Q4-2021
479	479	CALF Turnkey	Dublin City	Chanel Manor Apartments, Coolock, Dublin 5. (Phase 1)*	65	Respond	""	""	""	""	Q2-2019	""
480	480	CALF Turnkey	Dublin City	Chanel Manor, Coolock, Dublin 5 (Phase 1)*	22	Respond	""	""	""	""	Q4-2020	""
481	481	CALF Turnkey	Dublin City	Charlemont Gate, Griffith Avenue, Dublin 9 (Phase 1)*	35	Clid Housing	""	""	""	""	""	Q2-2022
482	482	CALF Turnkey	Dublin City	Clonshaugh Road, Clonshaugh, Dublin 17 (Phase 1)	9	North and East Housing Association CLG	""	""	""	""	Q4-2021	""
483	483	CALF Turnkey	Dublin City	Connaught Street, Phibsborough, Dublin 7 (Phase 1)	20	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
484	484	CALF Turnkey	Dublin City	Donnybrook Gardens, Lands of Greenfield Park, Donnybrook, Dublin 4 (Phase 1)*	4	RHD Housing	""	""	""	""	""	Q2-2021
485	485	CALF Turnkey	Dublin City	Elanora Court, Long Mile Road, Walkinstown, Dublin 12 (Phase 1)*	153	Respond	""	""	""	""	Q3-2020	""
486	486	CALF Turnkey	Dublin City	Hillside Manor, Lucan Road, Chapelizod, Dublin 20 (Phase 1)*	30	Clid Housing	""	""	""	""	Q4-2020	""
487	487	CALF Turnkey	Dublin City	Longboat Quay, Sir John Rogerson Quay, Dublin 2 (Phase 1)*	15	Tuath Housing Association	""	""	""	""	Q3-2020	""
488	488	CALF Turnkey	Dublin City	Newtown Cottages Malahide Road Coolock Dublin 17 (Phase 1)	3	Clanmil Housing Association Ireland	""	""	""	""	Q3-2020	""
489	489	CALF Construction	Dublin City	North Great Charles Street, Dublin 1 (Phase 1)	52	Clid Housing	""	""	""	Q4-2021	""	""
490	490	CALF Construction	Dublin City	North King Street, Dublin 7  (Phase 1)	30	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2019	""
491	491	CALF Turnkey	Dublin City	Park West Campus, Kileen Road, Dublin 12 (Phase 1)	43	Tuath Housing Association	""	""	""	""	""	Q2-2022
492	492	CALF Construction	Dublin City	"Railway Street, Dublin 1
 (Phase 1)"	47	Circle Voluntary Housing Association Ltd	""	""	""	""	Q3-2022	""
493	493	CALF Turnkey	Dublin City	Ravensdale Court, Kimmage, Dublin 12. (Phase 1)	12	Tuath Housing Association	""	""	""	""	""	Q2-2022
494	494	CALF Turnkey	Dublin City	St Canice?s Hall, Ballygall Road West, Finglas, Dublin 11 (Phase 1)*	32	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
495	495	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Dublin City	Ayrfield, Malahide Road	150	*N/A	""	""	""	""	""	Q2-2021
496	496	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Ready Mix Site, East Wall, Dublin 3	68	*N/A	""	Q4-2021	""	""	""	""
497	497	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Shangan Road, Ballymun, Dublin 9*	93	*N/A	""	Q4-2021	""	""	""	""
498	498	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Collins Avenue, Whitehall, Dublin 9	83	*N/A	""	Q4-2021	""	""	""	""
499	499	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Collins Avenue, Bring Centre, Dublin 9	99	N/A	Q2-2022	""	""	""	""	""
500	500	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Marrowbone Lane/Forbes Lane (Depot)	78	N/A	Q2-2022	""	""	""	""	""
501	501	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Basin View Flats	100	N/A	Q2-2022	""	""	""	""	""
502	502	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Site 5 Ballymun - Main Street to the south of Santry Cross	56	N/A	Q2-2022	""	""	""	""	""
503	503	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Sites 15, 16 and 17 Ballymun ? Balcurris	20	N/A	Q2-2022	""	""	""	""	""
504	504	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Site 18 Ballymun - Balcurris	50	N/A	Q2-2022	""	""	""	""	""
505	505	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Croke Villas	75	N/A	Q2-2022	""	""	""	""	""
506	506	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Church of the Annunciation, Finglas	100	N/A	Q2-2022	""	""	""	""	""
507	507	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Stanley Street (Depot)	110	N/A	Q2-2022	""	""	""	""	""
508	508	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Wellmount Road, Cardiffsbridge Road, Finglas	100	N/A	Q2-2022	""	""	""	""	""
509	509	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dublin City	Barry Road, Finglas, Dublin 11	70	N/A	Q2-2022	""	""	""	""	""
510	510	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dublin City	Cherry Orchard Avenue, Ballyfermot, Dublin 10	100	N/A	Q2-2022	""	""	""	""	""
511	511	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dun Laoghaire	Ballay, Dublin 16	58	N/A	Q2-2022	""	""	""	""	""
512	512	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dun Laoghaire	Lambs Cross, Sandyford, Dublin 18.	25	N/A	Q2-2022	""	""	""	""	""
513	513	SHIP DIALOG	Fingal	Killhedge Lane, Dun Emer, Lusk	7	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
514	514	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
515	515	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
516	516	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
517	517	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
518	518	SHIP CONSTRUCTION SINGLE STAGE	Fingal	Bowden Court (Outlands), Rathbeale Road, Swords	11	*N/A	""	""	""	""	Q1-2022	""
519	519	SHIP CONSTRUCTION	Fingal	Wellview	20	*N/A	""	""	""	""	Q3-2020	""
520	520	SHIP CONSTRUCTION	Fingal	Cappaghfinn, Cappagh Road Finglas - Phase 3	69	*N/A	""	""	""	""	Q1-2021	""
521	521	SHIP CONSTRUCTION	Fingal	Church Fields, Phase 2B, Mulhuddart, Dublin 15. - part 1	49	*N/A	""	""	""	""	Q4-2021	""
522	522	SHIP CONSTRUCTION	Fingal	Ballough PLace (Leonards Garage), Lusk	10	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
523	523	SHIP CONSTRUCTION	Fingal	Katie Hunt's Cottage, Church Road, Lusk	5	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
524	524	SHIP CONSTRUCTION	Fingal	North Street, Swords	8	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
525	525	SHIP CONSTRUCTION	Fingal	St Ita's, Portrane Avenue, Protrane, Co. Dublin	12	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
526	526	SHIP CONSTRUCTION	Fingal	Church Fields, Phase 2B, Mulhuddart, Dublin 15  - part 2	18	*N/A	""	""	""	""	Q4-2021	""
527	527	CAS CONSTRUCTION RENEWAL	Fingal	44 Alderwood, Hollystown Dublin 15	5	Marillac Housing Association	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
528	528	CAS CONSTRUCTION RENEWAL	Fingal	Abbeyglen, 47 Dublin Road, Swords	5	Praxis Housing Association	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
529	529	CAS CONSTRUCTION	Fingal	Killhedge Lane Dun Emer	31	Tath Housing Association Ltd	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
530	530	CAS CONSTRUCTION	Fingal	22 College Street, Baldoyle	4	Cluid Housing Association	""	""	""	""	""	Q4-2021
531	531	CAS CONSTRUCTION	Fingal	63 Hollystown Park, Holystown, Dublin 15	5	Daughters Of Charity Of St Vincent De Paul	""	""	""	""	""	Q4-2021
532	532	CAS CONSTRUCTION	Fingal	Kenure Park, Rush, Co. Dublin	4	Prosper Fingal Housing Assocaition Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
533	533	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 1)*	17	Tuath Housing Association	""	""	""	""	""	Q2-2021
534	534	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 2)	21	Tuath Housing Association	""	""	""	""	""	Q4-2021
535	535	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 1)*	36	Tuath Housing Association	""	""	""	""	Q3-2020	""
536	536	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 2)*	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
537	537	CALF Turnkey	Fingal	Blackwood Square, Northwood Avenue, Santry Dublin 9 (Phase 1)*	33	Tuath Housing Association	""	""	""	""	Q4-2020	""
538	538	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 1)*	29	Respond	""	""	""	""	""	Q2-2021
539	539	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 2)*	30	Respond	""	""	""	""	""	Q4-2021
540	540	CALF Turnkey	Fingal	Castleland Park, Castleland, Balbriggan, Co. Dublin. (Phase 1)	23	Tuath Housing Association	""	""	""	""	Q3-2021	""
541	541	CALF Turnkey	Fingal	Chapel Hill, Chapel Lane, Garristown, Co. Dublin (Phase 1)*	2	Clanmil Housing Association Ireland	""	""	""	""	Q2-2021	""
542	542	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 1)*	90	Respond	""	""	""	""	""	Q4-2021
543	543	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 2)*	48	Respond	""	""	""	""	""	Q4-2021
544	544	CALF Turnkey	Fingal	Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 2)*	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
545	545	CALF Turnkey	Fingal	Dun Si, St Marnocks Bay, Portmarnock, Co Dublin  (Phase 1)*	18	Clid Housing	""	""	""	""	Q4-2020	""
546	546	CALF Construction	Fingal	Ladyswell Road & Church Road, Mulhuddart, Dublin 15  (Phase 1)	65	Clid Housing	""	""	""	""	""	Q4-2021
547	547	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 1)*	14	Clid Housing	""	""	""	""	""	Q4-2021
548	548	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 2)*	4	Clid Housing	""	""	""	""	""	Q3-2022
549	549	CALF Construction	Fingal	Old Coolock Lane, Santry, Dublin 9 (Phase 1)	28	Circle Voluntary Housing Association Ltd	""	""	""	Q1-2019	""	""
550	550	CALF Turnkey	Fingal	Old Corduff Road, Blanchardstown, Dublin 15 (Phase 2)*	10	Respond	""	""	""	""	""	Q2-2021
551	551	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 1)	30	Respond	""	""	""	Q3-2021	""	""
552	552	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 2)	30	Respond	""	""	""	Q3-2021	""	""
553	553	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 3)	39	Respond	""	""	""	Q3-2021	""	""
554	554	CALF Turnkey	Fingal	Ravens Mill, Church Road, Rowlestown, Co. Dublin (Phase 1)*	27	Tuath Housing Association	""	""	""	""	Q2-2021	""
555	555	CALF Turnkey	Fingal	Ravens Mill, Church Road, Rowlestown, Co. Dublin (Phase 2)	11	Tuath Housing Association	""	""	""	""	Q2-2021	""
556	556	CALF Turnkey	Fingal	Riverwood Square, Porterstown, Dublin 15 (Phase 1)*	24	Clid Housing	""	""	""	""	""	Q3-2021
557	557	CALF Turnkey	Fingal	Semple Woods, Donabate, Co. Dublin (Phase 2)*	3	Tuath Housing Association	""	""	""	""	Q4-2019	""
558	558	CALF Turnkey	Fingal	St Josephs, Clonsilla, Dublin 15 (Phase 1)*	28	Clid Housing	""	""	""	""	""	Q4-2021
559	559	CALF Turnkey	Fingal	Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 2)*	8	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2021
560	560	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*	7	Clid Housing	""	""	""	""	""	Q4-2021
561	561	SHIP CONSTRUCTION TURNKEY	Galway City	Garra Caol, (Coast Road Site) Dublin Road	26	*N/A	""	""	""	""	Q1-2020	""
562	562	SHIP CONSTRUCTION TURNKEY	Galway City	Garra Caol, (Coast Road Site) Dublin Road	22	*N/A	""	""	""	""	Q1-2020	""
563	563	SHIP CONSTRUCTION RENEWAL	Galway City	Merchants Road Lower, Galway City	12	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
564	564	SHIP CONSTRUCTION	Galway City	An Cliathn, Old Monivea Road, Ballybaan Mr	15	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
565	565	SHIP CONSTRUCTION	Galway City	Garra Beag, Monivea Road, Ballybaan More	58	*N/A	""	""	""	""	Q1-2020	""
566	566	SHIP CONSTRUCTION	Galway City	Keeraun, Ballymoneen Road	63	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
567	567	SHIP CONSTRUCTION	Galway City	211 Tirellan Heights, Headford Road	1	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
568	568	SHIP CONSTRUCTION	Galway City	Merlin Park Lands, Galway City	18	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
569	569	SHIP CONSTRUCTION	Galway City	1 Munster Avenue, Galway city	4	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
570	570	SHIP CONSTRUCTION	Galway City	Clybaun Road, Knocknacarra	28	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
571	571	CAS CONSTRUCTION	Galway City	Cul Garrai, Rahoon	6	Peter Triest Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
572	572	CAS CONSTRUCTION	Galway City	Doughiska, Galway City	7	Respond	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
573	573	CAS CONSTRUCTION	Galway City	111 Upper Newcastle Road, Galway City	10	Simon Community : North West Simon	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
574	574	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 1)*	28	Respond	""	""	""	""	Q2-2021	""
575	575	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 2)	24	Respond	""	""	""	""	Q2-2021	""
576	576	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 3)*	49	Respond	""	""	""	""	Q2-2021	""
577	577	CALF Turnkey	Galway City	Briar Hill, Old Monivea Road, Ballybrit, Galway (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
578	578	CALF Turnkey	Galway City	Centrepoint, Liosbaun, Galway (Phase 1)	32	Tuath Housing Association	""	""	""	Q2-2021	""	""
579	579	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City  (Phase 2)	10	Clid Housing	""	""	""	""	""	Q2-2021
580	580	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City, Co. Galway (Phase 1)*	17	Clid Housing	""	""	""	""	""	Q4-2021
581	581	CALF Turnkey	Galway City	Cuirt Bhoirne, Roscam, Co Galway (Phase 1)*	12	Clid Housing	""	""	""	""	Q3-2020	""
582	582	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 1)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2021
583	583	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 2)*	3	Tuath Housing Association	""	""	""	""	""	Q3-2022
584	584	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 3)*	3	Tuath Housing Association	""	""	""	""	Q4-2019	""
585	585	CALF Turnkey	Galway City	Gaelcarrig, Letteragh, Galway City (Phase 1)*	83	Respond	""	""	""	""	Q3-2020	""
586	586	CALF Turnkey	Galway City	Garrai Sheain, Roscam, Galway (Phase 1)	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
587	587	CALF Turnkey	Galway City	Gleann Na Mona, Knocknacarra, Galway (Phase 1)*	16	Clid Housing	""	""	""	""	Q1-2021	""
588	588	CALF Turnkey	Galway City	Leana Mor, Cappagh Road, Galway (Phase 1)*	14	Respond	""	""	""	""	Q2-2021	""
589	589	CALF Turnkey	Galway City	Leana Mor, Cappagh Road, Galway (Phase 2)*	28	Respond	""	""	""	""	Q2-2021	""
590	590	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 1)*	10	Clid Housing	""	""	""	""	""	Q3-2021
591	591	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 2)	13	Clid Housing	""	""	""	""	""	Q4-2021
592	592	CALF Turnkey	Galway City	Phase 3 and 4 Cnocan Glas, Letteragh Road, Rahoon, Galway City (Phase 1)*	16	Clid Housing	""	""	""	""	Q1-2022	""
593	593	CALF Turnkey	Galway City	Phase 3 and 4 Cnocan Glas, Letteragh Road, Rahoon, Galway City (Phase 2)*	25	Clid Housing	""	""	""	""	Q1-2022	""
594	594	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 1)	56	*N/A	""	""	""	""	""	Q2-2021
595	595	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 2)	18	*N/A	""	""	""	""	""	Q3-2021
596	596	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	9	*N/A	""	""	""	""	""	Q1-2021
597	597	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	10	*N/A	""	""	""	""	""	Q1-2021
598	598	SHIP CONSTRUCTION TURNKEY	Galway County	Garra Mhic Aodha, Tubber Road, Gort	9	*N/A	""	""	""	""	""	Q4-2021
599	599	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	9	*N/A	""	""	""	""	""	Q4-2021
600	600	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corrn Eiscir Riada)	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
601	601	SHIP CONSTRUCTION TURNKEY	Galway County	Garra Mhic Aodha, Tubber Road, Gort	18	*N/A	""	""	""	""	""	Q4-2021
602	602	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	14	*N/A	""	""	""	""	""	Q3-2022
603	603	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corrn Eiscir Riada)	15	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
604	604	SHIP CONSTRUCTION TURNKEY	Galway County	Garra Glas, Ballydavid South, Athenry	7	N/A	""	""	""	""	Q2-2021	""
605	605	SHIP CONSTRUCTION TURNKEY	Galway County	Gort an Choirce, Tubber Road, Gort	5	*N/A	""	""	""	""	""	Q2-2022
606	606	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	13	*N/A	""	""	""	""	Q4-2021	""
607	607	SHIP CONSTRUCTION TURNKEY	Galway County	Circular Road & Dublin Road, Tuam	8	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
608	608	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	15	*N/A	""	""	""	""	Q4-2021	""
609	609	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	16	*N/A	""	""	""	""	Q4-2021	""
610	610	SHIP CONSTRUCTION TURNKEY	Galway County	Kilgarve, Ballinasloe	33	*N/A	""	""	""	""	Q3-2022	""
611	611	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corrn Eiscir Riada)	15	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
612	612	SHIP CONSTRUCTION TURNKEY	Galway County	Circular Road & Dublin Road Tuam	2	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
613	613	SHIP CONSTRUCTION SINGLE STAGE	Galway County	Claremount, Oughterard	4	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
614	614	SHIP CONSTRUCTION SINGLE STAGE	Galway County	Corralough, Williamstown (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
615	615	SHIP CONSTRUCTION RENEWAL	Galway County	Dunlo Hill, Ballinasloe	15	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
616	616	SHIP CONSTRUCTION	Galway County	Weir Road, Tuam	30	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
617	617	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	18	*N/A	""	""	""	""	Q4-2020	""
618	618	SHIP CONSTRUCTION	Galway County	Bridge Court, Ahascragh, Ballinasloe	18	*N/A	""	""	""	""	Q2-2022	""
619	619	SHIP CONSTRUCTION	Galway County	Caislen Raithln, Ardrahan	10	*N/A	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
620	620	SHIP CONSTRUCTION	Galway County	Barrack Street, Loughrea	5	*N/A	""	""	""	""	""	Q3-2021
621	621	SHIP CONSTRUCTION	Galway County	Garra Ghuaire, Cartron, Kinvara	10	*N/A	""	""	""	""	Q3-2021	""
622	622	SHIP CONSTRUCTION	Galway County	Fana Bhu, Tuam	16	*N/A	""	""	""	""	""	Q4-2021
623	623	SHIP CONSTRUCTION	Galway County	Cnoc na Carraige, Roundstone	6	*N/A	""	""	""	""	""	Q1-2021
624	624	SHIP CONSTRUCTION	Galway County	Ballyglass, Ardrahan (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
625	625	SHIP CONSTRUCTION	Galway County	Woodpark, Portumna (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
626	626	SHIP CONSTRUCTION	Galway County	Carrowmore West, Clontuskert, Ballinasloe (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
627	627	SHIP CONSTRUCTION	Galway County	Woodfield, Dunmore (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
628	628	SHIP CONSTRUCTION	Galway County	Knockaloura West, Brownsgrove, Tuam (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
629	629	SHIP CONSTRUCTION	Galway County	Creggaturlough, Craughwell (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
630	630	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	8	*N/A	""	""	""	""	Q4-2020	""
631	631	SHIP CONSTRUCTION	Galway County	Fana Bhu, Tuam	16	*N/A	""	""	""	""	Q4-2020	""
632	632	SHIP CONSTRUCTION	Galway County	Fana Bhu, Tuam	16	*N/A	""	""	""	""	Q4-2020	""
633	633	SHIP CONSTRUCTION	Galway County	Ballymoe	8	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
634	634	SHIP CONSTRUCTION	Galway County	Droim na Gaoithe, Baile Chlir (Claregalway)	45	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
635	635	SHIP CONSTRUCTION	Galway County	Cosmona, Loughrea	40	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
636	636	SHIP CONSTRUCTION	Galway County	Barkhill, Woodford	2	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
637	637	SHIP CONSTRUCTION	Galway County	St. Joseph's, Ballinasloe	8	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
638	638	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 2)	11	Cluid Housing Association	""	""	""	""	""	Q1-2022
639	639	CAS CONSTRUCTION	Galway County	Rossaveal Cottages, Ros a Mhl, South Connemara	8	Tearmann Eanna Teoranta	Stage 1 approved Q4-2016, outline design and costs being prepared.	""	""	""	""	""
640	640	CAS CONSTRUCTION	Galway County	Eanach Mheain, Carraroe	13	Tearmann Eanna Teoranta	""	Stage 2 approved Q4-2018, full design/tender being prepared.	""	""	""	""
641	641	CAS CONSTRUCTION	Galway County	Mountbellew	5	Tath Housing Association Ltd	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
642	642	CAS CONSTRUCTION	Galway County	Springfield, Parkmore, Ballinasloe	4	Peter Triest Housing Association Ltd	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
643	643	CAS CONSTRUCTION	Galway County	Shannon Road, Portumna	4	Carraig Dubh Housing Association	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
644	644	CALF Turnkey	Galway County	Cuil na Canalach, Ballinasloe, Co Galway (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
645	645	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 1)	24	Clid Housing	""	""	""	""	Q1-2022	""
646	646	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 2)	14	Clid Housing	""	""	""	""	Q1-2022	""
647	647	CALF Turnkey	Galway County	Gort na Fuinse, Headford, Co. Galway (Phase 1)*	11	Clid Housing	""	""	""	""	Q2-2021	""
648	648	CALF Turnkey	Galway County	Gort na Fuinse, Headford, Co. Galway (Phase 2)	14	Clid Housing	""	""	""	""	Q2-2021	""
649	649	CALF Turnkey	Galway County	Oranhill, Oranmore, Co. Galway (Phase 1)*	22	Clid Housing	""	""	""	Q1-2021	""	""
650	650	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 2)	12	Clid Housing	""	""	""	""	""	Q1-2021
651	651	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 3)*	16	Clid Housing	""	""	""	""	""	Q2-2021
652	652	SHIP CONSTRUCTION TURNKEY	Kerry	Cnoc an Cairn, Chapel Lane, Dingle	2	*N/A	""	""	""	""	""	Q1-2022
653	653	SHIP CONSTRUCTION TURNKEY	Kerry	The Green, Ballinageragh, Lixnaw, Co Kerry	13	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
654	654	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Glannagilliagh, Caragh Lake, Killorglin (SRD)	1	*N/A	""	""	""	""	""	Q2-2022
655	655	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Carrigcannon, Lyreacrumpane (SRD)	1	*N/A	""	""	""	Stage 4 approved Q3-2019, the scheme is fully approved.	""	""
656	656	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Rahinnane, Ventry (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
657	657	SHIP CONSTRUCTION DESIGN BUILD	Kerry	Rathmore/Barraduff	20	*N/A	""	""	""	""	""	Q2-2021
658	658	SHIP CONSTRUCTION	Kerry	Glenach, Ballybunion	20	*N/A	""	""	""	""	""	Q1-2021
659	659	SHIP CONSTRUCTION	Kerry	Lohercannon, Tralee	61	*N/A	""	""	""	""	Q3-2020	""
660	660	SHIP CONSTRUCTION	Kerry	Cullenagh Upper, Beaufort	1	*N/A	""	""	""	""	""	Q1-2021
661	661	SHIP CONSTRUCTION	Kerry	Farranwilliam, Ardfert	22	*N/A	""	""	""	""	""	Q3-2021
662	662	SHIP CONSTRUCTION	Kerry	Ballyrickard, Tralee	21	*N/A	""	""	""	""	""	Q3-2022
663	663	SHIP CONSTRUCTION	Kerry	Croogorts, Tralee (Cruaghoirt)	30	*N/A	""	""	""	""	""	Q3-2022
664	664	SHIP CONSTRUCTION	Kerry	Rock Rd., Killarney	10	*N/A	""	""	""	""	""	Q2-2022
665	665	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 4)	14	*N/A	""	""	""	""	""	Q1-2021
666	666	SHIP CONSTRUCTION	Kerry	Baile an Gharra, Lixnaw (Phase 2)	10	*N/A	""	""	""	""	""	Q2-2021
667	667	SHIP CONSTRUCTION	Kerry	Woodview Place, Tarbert	22	*N/A	""	""	""	""	Q2-2021	""
668	668	SHIP CONSTRUCTION	Kerry	Marconi South, Ballybunion (Glr na Toinne)	14	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
669	669	SHIP CONSTRUCTION	Kerry	Rahoonane, Tralee (New Site)	8	*N/A	""	""	""	""	""	Q3-2022
670	670	SHIP CONSTRUCTION	Kerry	Rusheen, Ballylongford (Carraig an Phoill)	7	*N/A	""	""	""	""	Q4-2021	""
671	671	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 5) (Ard Bhearna)	14	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
672	672	SHIP CONSTRUCTION	Kerry	Matt Talbot Road, Tralee	27	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
673	673	SHIP CONSTRUCTION	Kerry	Locke's Shop, Mitchel's Rd, Tralee	8	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
674	674	SHIP CONSTRUCTION	Kerry	Marian Terrace, Ballyheigue	9	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
675	675	SHIP CONSTRUCTION	Kerry	Bridge Rd, Abbeydorney	1	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
676	676	SHIP CONSTRUCTION	Kerry	Hawley Park Apartments, Tralee	16	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
677	677	SHIP CONSTRUCTION	Kerry	Garryruth, Tralee, Co Kerry	19	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
678	678	SHIP CONSTRUCTION	Kerry	Lohercannon Phase 2, Tralee	94	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
679	679	SHIP CONSTRUCTION	Kerry	SRD at Emlaghmore, Caherciveen, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
680	680	SHIP CONSTRUCTION	Kerry	SRD at Garfinny, Dingle, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
681	681	SHIP CONSTRUCTION	Kerry	SRD at Gortadrislig, Lixnaw, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
682	682	SHIP CONSTRUCTION	Kerry	SRD at Kells, Caherciveen, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
683	683	SHIP CONSTRUCTION	Kerry	Banshagh, Killorglin, Co. Kerry	80	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
684	684	SHIP CONSTRUCTION	Kerry	Ballybeg, Dingle, Co Kerry	37	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
685	685	REGENERATION	Kerry	23 Mitchel's Road, Tralee	1	N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
686	686	CAS CONSTRUCTION TURNKEY	Kerry	Firies Hall, Firies	18	Peter McVerry Trust Ltd	""	""	""	""	Q3-2022	""
687	687	CAS CONSTRUCTION RENEWAL	Kerry	Ardmoneel, Killorglin, Co. Kerry	4	St. John of God Housing Association Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
688	688	CAS CONSTRUCTION	Kerry	Armagh House, Killarney	6	Cluid Housing Association	""	""	""	""	""	Q1-2021
689	689	CAS CONSTRUCTION	Kerry	Chamfers Place (Mitchels road, Tralee)	18	Cluid Housing Association	""	""	""	""	Q2-2021	""
690	690	CAS CONSTRUCTION	Kerry	Mary O'Donoghue Avenue, Cahirciveen, Co Kerry.	7	Caherciveen Social Services (Housing) Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
691	691	CALF Turnkey	Kerry	Apts 52-66 Fels Point, Dan Spring Road, Tralee, Co Kerry (Phase 1)	15	Focus Housing Association CLG	""	""	""	""	Q2-2022	""
692	692	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 1)	28	Clid Housing	""	""	""	""	""	Q3-2022
693	693	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 2)*	26	Clid Housing	""	""	""	""	Q4-2020	""
694	694	CALF Turnkey	Kerry	Barraduff Phase 6, Killarney, Co Kerry  (Phase 1)*	25	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
695	695	CALF Turnkey	Kerry	Barraduff, Killarney, Co Kerry (Phase 1)*	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
696	696	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 4)*	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
697	697	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 1)*	12	Clid Housing	""	""	""	""	""	Q3-2022
698	698	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 2)	26	Clid Housing	""	""	""	""	Q3-2020	""
699	699	CALF Turnkey	Kerry	Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 1)	39	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
700	700	CALF Turnkey	Kerry	Dun Alainn, Listowel, Co. Kerry (Phase 1)*	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
701	701	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 4)	1	Respond	""	""	""	""	""	Q2-2021
702	702	CALF Turnkey	Kerry	Hunters Lodge, Hunters Wood, Ballyseedy, Tralee, Co. Kerry (Phase 1)	10	Clid Housing	""	""	""	""	Q3-2021	""
703	703	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 1)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
704	704	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 2)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
705	705	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 3)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
706	706	CALF Turnkey	Kerry	Lios Ard, Lisloose, Tralee, Co. Kerry (Phase 1)	28	Clid Housing	""	""	""	""	""	Q3-2021
707	707	CALF Turnkey	Kerry	Moanmore, Pound Road, Castleisland, Co. Kerry (Phase 1)*	14	Clid Housing	""	""	""	""	""	Q4-2021
708	708	CALF Turnkey	Kerry	Orglan Heights, Ardmoneel, Killorglin (Phase 1)*	30	Clid Housing	""	""	""	Q3-2021	""	""
709	709	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q2-2021
710	710	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A	""	""	""	""	""	Q2-2021
711	711	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A	""	""	""	""	""	Q1-2021
712	712	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield, Clane	1	*N/A	""	""	""	""	""	Q2-2021
713	713	SHIP CONSTRUCTION TURNKEY	Kildare	Old Mill Race, Monasterevin	9	*N/A	""	""	""	""	Q4-2019	""
714	714	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	13	*N/A	""	""	""	""	""	Q3-2021
715	715	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	10	*N/A	""	""	""	""	Q1-2021	""
716	716	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A	""	""	""	""	""	Q2-2021
717	717	SHIP CONSTRUCTION TURNKEY	Kildare	Newtown, Ardclough Rd, Celbridge	26	*N/A	""	""	""	""	""	Q3-2022
718	718	SHIP CONSTRUCTION TURNKEY	Kildare	Kildare Road, Rathangan	9	*N/A	""	""	""	""	Q1-2021	""
719	719	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield, Clane	2	*N/A	""	""	""	""	""	Q3-2021
720	720	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q4-2021
721	721	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A	""	""	""	""	""	Q4-2021
722	722	SHIP CONSTRUCTION TURNKEY	Kildare	Williams Grove, Ardclough	2	*N/A	""	""	""	""	""	Q4-2021
723	723	SHIP CONSTRUCTION TURNKEY	Kildare	Millstream Court, Kilcullen	1	*N/A	""	""	""	""	""	Q4-2021
724	724	SHIP CONSTRUCTION TURNKEY	Kildare	Newtown, Ardclough Rd, Celbridge	23	*N/A	""	""	""	""	Q2-2021	""
725	725	SHIP CONSTRUCTION SINGLE STAGE	Kildare	Patrician Avenue, Naas	2	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
726	726	SHIP CONSTRUCTION RENEWAL	Kildare	25 St. Corbans Place, Naas 	1	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
727	727	SHIP CONSTRUCTION DESIGN BUILD	Kildare	Old Greenfield Road, Maynooth	65	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
728	728	SHIP CONSTRUCTION	Kildare	Athgarvan Village	18	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
729	729	SHIP CONSTRUCTION	Kildare	Newtown House, Leixlip	4	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
730	730	SHIP CONSTRUCTION	Kildare	Coill Dubh	10	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
731	731	SHIP CONSTRUCTION	Kildare	Ardclough Road, Celbridge	39	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
732	732	SHIP CONSTRUCTION	Kildare	Ambassador Site, Kill	33	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
733	733	SHIP CONSTRUCTION	Kildare	Carbury	5	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
734	734	SHIP CONSTRUCTION	Kildare	St. Evins Park Monasterevin	16	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
735	735	SHIP CONSTRUCTION	Kildare	Castle Park, Athy	5	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
736	736	SHIP CONSTRUCTION	Kildare	Old Caragh Road, Nass	58	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
737	737	CAS CONSTRUCTION	Kildare	Craddockstown, Naas	3	KARE Promoting Inclusion for People with Intellectual Disabilities	""	Stage 2 approved Q2-2018, full design/tender being prepared.	""	""	""	""
738	738	CAS CONSTRUCTION	Kildare	El Kantara, Newbridge	2	KARE Promoting Inclusion for People with Intellectual Disabilities	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
739	739	CAS CONSTRUCTION	Kildare	Jigginstown House, Naas	12	Homeless Care Ltd	""	""	""	""	""	Q2-2021
740	740	CAS CONSTRUCTION	Kildare	St. John's Convent, New Street, Rathangan	27	Sophia Housing Association Ltd	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
741	741	CAS CONSTRUCTION	Kildare	Dominican Lands, Athy	34	Cluid Housing Association	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
742	742	CALF Turnkey	Kildare	1 unit, Loughlion Green, Kildare Town (Phase 1)	1	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
743	743	CALF Turnkey	Kildare	15 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	15	Clid Housing	""	""	""	""	""	Q4-2021
744	744	CALF Turnkey	Kildare	2 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	2	Clid Housing	""	""	""	""	""	Q4-2021
745	745	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 1)*	13	Tuath Housing Association	""	""	""	""	Q3-2021	""
746	746	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 2)*	21	Tuath Housing Association	""	""	""	""	Q3-2021	""
747	747	CALF Construction	Kildare	Castlefen, Castlesize, Sallins, Co. Kildare (Phase 1)	29	Tuath Housing Association	""	""	""	""	""	Q3-2022
748	748	CALF Turnkey	Kildare	Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 2)*	17	Tuath Housing Association	""	""	""	""	""	Q4-2021
749	749	CALF Construction	Kildare	Flinters Field (Phase 2), Athy, Co. Kildare (Phase 1)	23	Respond	""	""	""	""	Q1-2021	""
750	750	CALF Construction	Kildare	Flinters Field (Phase 2), Athy, Co. Kildare (Phase 2)	12	Respond	""	""	""	""	Q1-2021	""
751	751	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 1)*	21	Clid Housing	""	""	""	""	""	Q1-2021
752	752	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 2)	19	Clid Housing	""	""	""	""	""	Q2-2021
753	753	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 1 (Phase 1)*	4	Clid Housing	""	""	""	""	""	Q1-2021
754	754	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 2 (Phase 1)*	4	Clid Housing	""	""	""	""	Q2-2019	""
755	755	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	27	Clid Housing	""	""	""	""	""	Q3-2021
756	756	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	3	Clid Housing	""	""	""	""	""	Q4-2021
757	757	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	20	Clid Housing	""	""	""	""	Q4-2020	""
758	758	CALF Turnkey	Kildare	Leinster Square, Dublin Street, Kildare Town, Co Kildare (Phase 1)*	4	Clanmil Housing Association Ireland	""	""	""	""	""	Q3-2021
759	759	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 3)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
760	760	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 4)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
761	761	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 5)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
762	762	CALF Turnkey	Kildare	Main Street, Prosperous, Clane, Co. Kildare (Phase 1)*	16	Clanmil Housing Association Ireland	""	""	""	""	Q4-2020	""
763	763	CALF Turnkey	Kildare	Mariavilla, Maynooth, Co. Kildare (Phase 1)*	11	Tuath Housing Association	""	""	""	""	""	Q4-2021
764	764	CALF Turnkey	Kildare	Melitta Road, Co. Kildare (Phase 1)	4	Clanmil Housing Association Ireland	""	""	""	Q2-2022	""	""
765	765	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 1)*	15	Tuath Housing Association	""	""	""	""	Q4-2019	""
766	766	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 2)*	12	Tuath Housing Association	""	""	""	""	Q4-2019	""
767	767	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 1)*	13	Tuath Housing Association	""	""	""	""	Q4-2020	""
768	768	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 2)*	2	Tuath Housing Association	""	""	""	""	Q4-2020	""
769	769	CALF Turnkey	Kildare	Oak Park, Naas, Co. Kildare (Phase 1)	26	Tuath Housing Association	""	""	""	""	Q4-2020	""
770	770	CALF Turnkey	Kildare	Old Dublin Road, Celbridge, Co. Kildare (Phase 1)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2020	""
771	771	CALF Turnkey	Kildare	Riverside Green, Riverside Manor,Kilcullen, Co. Kildare (Phase 1)	30	Clid Housing	""	""	""	""	Q2-2021	""
772	772	CALF Turnkey	Kildare	Riverside Green, Riverside Manor,Kilcullen, Co. Kildare (Phase 2)	24	Clid Housing	""	""	""	""	Q2-2021	""
773	773	CALF Turnkey	Kildare	Riverside Green, Riverside Manor,Kilcullen, Co. Kildare (Phase 3)*	10	Clid Housing	""	""	""	""	Q2-2021	""
774	774	CALF Turnkey	Kildare	The Court (Block A) Westfield, Green Lane, Leixlip, Co. Kildare (Phase 1)*	20	Respond	""	""	""	""	Q1-2021	""
775	775	CALF Turnkey	Kildare	The Paddocks, Morristown, Newbridge, Kildare (Phase 3)*	16	Clid Housing	""	""	""	""	""	Q2-2021
776	776	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 1)	26	Clid Housing	""	""	""	""	""	Q3-2021
777	777	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 2)	33	Clid Housing	""	""	""	""	""	Q4-2021
778	778	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)*	18	Respond	""	""	""	""	""	Q2-2021
779	779	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 3) (Phase 1)	20	Respond	""	""	""	""	Q4-2019	""
780	780	CALF Turnkey	Kildare	Walkers Gate, Kildare Town, Co. Kildare (Phase 1)*	10	Tuath Housing Association	""	""	""	""	Q3-2021	""
781	781	CALF Turnkey	Kildare	Walkers Gate, Kildare Town, Co. Kildare (Phase 2)*	30	Tuath Housing Association	""	""	""	""	Q3-2021	""
782	782	CALF Turnkey	Kildare	Westfield, Leixlip, Co. Kildare (Phase 1)*	20	Respond	""	""	""	""	""	Q4-2021
783	783	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2021
784	784	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 2)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2021
785	785	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 3)*	4	Tuath Housing Association	""	""	""	""	""	Q3-2022
786	786	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Kildare	Butterstream, Clane	77	*N/A	""	""	""	""	""	Q4-2021
787	787	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Kildare	Ardrew, Athy, Co. Kildare	73	*N/A	""	Q4-2021	""	""	""	""
788	788	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Kildare	Oldtown Mill, Celbridge	57	N/A	Q2-2022	""	""	""	""	""
789	789	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Kildare	Collaghknock Glebe, Kildare Town	85	N/A	Q2-2022	""	""	""	""	""
790	790	SHIP CONSTRUCTION TURNKEY	Kilkenny	New Road, Mooncoin	4	*N/A	""	""	""	""	Q3-2018	""
791	791	SHIP CONSTRUCTION TURNKEY	Kilkenny	Chapel Street, Mooncoin	2	*N/A	""	""	""	""	Q3-2018	""
792	792	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Court, Hebron Road, Kilkenny	8	*N/A	""	""	""	""	""	Q1-2022
793	793	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Green, Hebron Road, Kilkenny	26	*N/A	""	""	""	""	""	Q1-2022
794	794	SHIP CONSTRUCTION TURNKEY	Kilkenny	Blackwater Grove, Kilmacow	14	*N/A	""	""	""	""	""	Q2-2021
795	795	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank	5	*N/A	""	""	""	""	""	Q4-2021
796	796	SHIP CONSTRUCTION TURNKEY	Kilkenny	Piltown, Kilkenny	4	*N/A	""	""	""	""	Q2-2021	""
797	797	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank	10	*N/A	""	""	""	""	""	Q1-2022
798	798	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Green, Hebron Road, Kilkenny	26	*N/A	""	""	""	""	""	Q2-2022
799	799	SHIP CONSTRUCTION TURNKEY	Kilkenny	Abbeygate, Ferrybank	21	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
800	800	SHIP CONSTRUCTION TURNKEY	Kilkenny	Berkely Drive, Mount Sion Road, Ferrybank	5	*N/A	""	""	""	""	Q1-2022	""
801	801	SHIP CONSTRUCTION TURNKEY	Kilkenny	Old Creamery Site, Kilmacow	8	*N/A	""	""	""	""	Q2-2022	""
802	802	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Inchacarron, Mullinavat	2	*N/A	""	""	""	""	Q1-2022	""
803	803	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Shanganny, Jenkinstown	2	*N/A	""	""	""	""	""	Q2-2022
804	804	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	6	*N/A	""	""	""	""	""	Q2-2021
805	805	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Old Fire Station, Graiguenamanagh	2	*N/A	""	""	""	""	Q1-2022	""
806	806	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	2	*N/A	""	""	""	""	""	Q1-2022
807	807	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Haggardsgreen, Callan	1	*N/A	""	""	""	""	Q2-2022	""
808	808	SHIP CONSTRUCTION RENEWAL	Kilkenny	18 Wolfe Tone Street, Kilkenny	1	*N/A	""	""	""	""	Q3-2022	""
809	809	SHIP CONSTRUCTION	Kilkenny	10 Golf Links Road, Kilkenny	6	*N/A	""	""	""	""	Q1-2022	""
810	810	SHIP CONSTRUCTION	Kilkenny	Station Road, Ballyragget	22	*N/A	""	""	""	""	""	Q2-2021
811	811	SHIP CONSTRUCTION	Kilkenny	Donaguile, Castlecomer	33	*N/A	""	""	""	""	""	Q2-2021
812	812	SHIP CONSTRUCTION	Kilkenny	The Broguemaker, Kilkenny	18	*N/A	""	""	""	""	""	Q2-2021
813	813	SHIP CONSTRUCTION	Kilkenny	Ladywell, Thomastown	25	*N/A	""	""	""	""	Q4-2021	""
814	814	SHIP CONSTRUCTION	Kilkenny	Crokers Hill, Kennyswell Road, Kilkenny	88	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
815	815	SHIP CONSTRUCTION	Kilkenny	Canal Road, Johnstown - Project 1	5	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
816	816	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstow - Project 2	2	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
817	817	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstown - Project 3	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
818	818	SHIP CONSTRUCTION	Kilkenny	Ladywell, Newtown, Thomastown	33	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
819	819	SHIP CONSTRUCTION	Kilkenny	Weather Station, Granges Road, Kilkenny	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
820	820	CAS CONSTRUCTION TURNKEY	Kilkenny	Tinnypark, Callan Road, Kilkenny	6	SOS Kilkenny Housing Association Ltd	""	""	""	""	""	Q3-2022
821	821	CAS CONSTRUCTION TURNKEY	Kilkenny	70-71 Upper Patrick Street, Kilkenny	4	Clanmill Housing Association Ireland	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
822	822	CAS CONSTRUCTION SINGLE STAGE	Kilkenny	Miltown Lodge Phase 2, Johnswell Road, Kilkenny	1	SOS Kilkenny Housing Association Ltd	""	""	""	""	""	Q2-2022
823	823	CAS CONSTRUCTION RENEWAL	Kilkenny	The Round House, Kells	4	SOS Kilkenny Housing Association Ltd	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
824	824	CAS CONSTRUCTION	Kilkenny	Kingsriver, Ennisnag	2	Kingsriver Housing Association Limited	""	""	""	""	""	Q2-2022
825	825	CAS CONSTRUCTION	Kilkenny	19/21 Blackmill Street, Kilkenny	12	Good Shepherd Services Ltd	""	""	""	""	Q4-2021	""
826	826	CAS CONSTRUCTION	Kilkenny	Brother Thomas Place, Church Lane, Kilkenny	12	Good Shepherd Services Ltd	""	""	""	""	""	Q3-2022
827	827	CAS CONSTRUCTION	Kilkenny	Grennan Villa, Thomastown	5	Camphill Communities of Ireland	""	""	""	""	""	Q3-2022
828	828	CAS CONSTRUCTION	Kilkenny	Prague House Hall, Freshford	4	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
829	829	CALF Turnkey	Kilkenny	Breagagh Valley, Kilkenny (Phase 1)*	27	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2021	""
830	830	CALF Turnkey	Kilkenny	Cois Na Bearu, Graiguenemanagh, Kilkenny (Phase 1)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
831	831	CALF Turnkey	Kilkenny	Margaret?s Field, Callan Road, Kilkenny City (Phase 1)	40	Respond	""	""	""	""	""	Q2-2021
832	832	CALF Turnkey	Kilkenny	Nuncio Road, Kilkenny (Phase 2)*	22	Respond	""	""	""	""	Q4-2018	""
833	833	CALF Turnkey	Kilkenny	Orchard Close, Kilkenny (Phase 1)*	23	Clid Housing	""	""	""	""	""	Q3-2022
834	834	SHIP CONSTRUCTION TURNKEY	Laois	Priory, Borris in Ossory	5	*N/A	""	""	""	""	""	Q3-2022
835	835	SHIP CONSTRUCTION TURNKEY	Laois	Church Avenue, Stradbally	20	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
836	836	SHIP CONSTRUCTION TURNKEY	Laois	Bruach Na Habhainn, Killeen, Maganey	3	*N/A	""	""	""	""	""	Q1-2022
837	837	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	2	N/A	""	""	""	""	""	Q1-2022
838	838	SHIP CONSTRUCTION TURNKEY	Laois	Market Square, Portarlington	18	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
839	839	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
840	840	SHIP CONSTRUCTION TURNKEY	Laois	Church Avenue, Stradbally	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
841	841	SHIP CONSTRUCTION TURNKEY	Laois	Bruach Na Habhainn, Killeen, Maganey	1	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
842	842	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
843	843	SHIP CONSTRUCTION SINGLE STAGE	Laois	Coolroe, Ballybrittas	1	*N/A	""	""	""	""	""	Q2-2022
844	844	SHIP CONSTRUCTION SINGLE STAGE	Laois	Ballyadams	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
845	845	SHIP CONSTRUCTION RENEWAL	Laois	Oldcourt Ballylynan	1	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
846	846	SHIP CONSTRUCTION	Laois	Moore Street, Rathdowney	6	*N/A	""	""	""	""	Q3-2020	""
847	847	SHIP CONSTRUCTION	Laois	Ballymorris Road, Portarlington	22	*N/A	""	""	""	""	""	Q2-2021
848	848	SHIP CONSTRUCTION	Laois	Gleann na Glaise, Ballyroan	10	*N/A	""	""	""	""	""	Q3-2022
849	849	SHIP CONSTRUCTION	Laois	Pattison Est. Mountmellick	10	*N/A	""	""	""	""	Q4-2020	""
850	850	SHIP CONSTRUCTION	Laois	Shannon Street, Mountrath	6	*N/A	""	""	""	""	""	Q2-2021
851	851	SHIP CONSTRUCTION	Laois	Harbour Court, Mountmellick	6	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
852	852	SHIP CONSTRUCTION	Laois	Mooreville, Rathdowney	7	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
853	853	SHIP CONSTRUCTION	Laois	Sean Doire, Cork Road, Durrow	22	*N/A	""	""	""	""	Q4-2020	""
854	854	SHIP CONSTRUCTION	Laois	St Kieran's Park, Errill	14	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
855	855	SHIP CONSTRUCTION	Laois	Clonrooske, Knockmay	12	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
856	856	SHIP CONSTRUCTION	Laois	Carraig Glas, Stradbally	26	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
857	857	SHIP CONSTRUCTION	Laois	Iona,Abbeyleix Rd., Portlaoise	9	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
858	858	SHIP CONSTRUCTION	Laois	Doonane	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
859	859	SHIP CONSTRUCTION	Laois	Durrow	18	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
860	860	SHIP CONSTRUCTION	Laois	15 Units at Bracklone Street, Portarlington	15	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
861	861	CAS CONSTRUCTION	Laois	Presentation Convent & Lands, Portlaoise, 	52	Sophia Housing Association Ltd	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
862	862	CAS CONSTRUCTION	Laois	County Hotel, Portlaoise	10	Cluid Housing Association	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
863	863	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 1)	34	Clid Housing	""	""	""	""	Q2-2021	""
864	864	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 2)	12	Clid Housing	""	""	""	""	Q2-2021	""
865	865	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 4)*"	9	Clid Housing	""	""	""	""	""	Q1-2021
866	866	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 5)*"	6	Clid Housing	""	""	""	""	""	Q3-2021
867	867	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 4)	9	Tuath Housing Association	""	""	""	""	""	Q1-2021
868	868	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 1)*	14	Clid Housing	""	""	""	""	Q4-2018	""
869	869	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 2)	12	Clid Housing	""	""	""	""	Q4-2018	""
870	870	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 3)	6	Clid Housing	""	""	""	""	Q4-2018	""
871	871	CALF Turnkey	Laois	Doirin Alainn, Ballylinan, Co. Laois (Phase 1)	9	North and East Housing Association CLG	""	""	""	""	Q1-2022	""
872	872	CALF Turnkey	Laois	Doirinn Alainn, Ballylynan, Co. Laois (Phase 3)*	6	North and East Housing Association CLG	""	""	""	""	""	Q2-2021
873	873	CALF Turnkey	Laois	Droughill Lawn, Portarlington, Co. Laois (Phase 1)*	26	Oaklee Housing	""	""	""	""	""	Q2-2022
874	874	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 1)	13	Clid Housing	""	""	""	""	Q3-2021	""
875	875	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 2)	24	Clid Housing	""	""	""	""	Q3-2021	""
876	876	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 3)	30	Clid Housing	""	""	""	""	Q3-2021	""
877	877	CALF Turnkey	Laois	Harpurs Lane, Portlaoise, Co. Laois (Phase 1)*	44	Respond	""	""	""	""	Q2-2021	""
878	878	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 1)	10	Clid Housing	""	""	""	""	""	Q3-2021
879	879	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 2)	10	Clid Housing	""	""	""	""	Q3-2018	""
880	880	CALF Turnkey	Laois	Lake Drive, Kilminchy, Portlaoise, Co. Laois (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
881	881	CALF Turnkey	Laois	Phase 2 The Glen, Kilnacourt, Portarlington, Co Laois (Phase 1)	18	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
882	882	CALF Turnkey	Laois	Phase 3 The Glen, Kilnacourt, Portarlington, Co Laois. (Phase 1)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
883	883	CALF Construction	Laois	Radharc Darach, Ballyfin Road, Portlaoise, Co. Laois (Phase 1)	54	Clid Housing	""	""	""	Q2-2022	""	""
884	884	CALF Turnkey	Laois	Rathillion, Killeshin, Co. Laois (Phase 1)*	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
885	885	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 1)	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
886	886	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 2)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
887	887	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 3)*	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
888	888	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 1)*	15	Clid Housing	""	""	""	""	""	Q3-2022
889	889	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 2)*	40	Clid Housing	""	""	""	""	Q1-2020	""
890	890	CALF Turnkey	Laois	The Meadows, Mountrath Road, Portlaoise, Co. Laois (Phase 1)*	48	Clid Housing	""	""	""	""	Q1-2022	""
891	891	CALF Turnkey	Laois	The Springs, Kilminchy, Portlaoise, Co Laois (Phase 1)*	43	Clid Housing	""	""	""	""	Q2-2021	""
892	892	SHIP CONSTRUCTION TURNKEY	Leitrim	Church Lane, Ballinamore	9	*N/A	""	""	""	""	""	Q4-2021
893	893	SHIP CONSTRUCTION TURNKEY	Leitrim	Druminshingore, Newtowngore	2	*N/A	""	""	""	""	""	Q4-2021
894	894	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	5	*N/A	""	""	""	""	Q2-2022	""
895	895	SHIP CONSTRUCTION TURNKEY	Leitrim	Ard na Drise, Mohill	2	*N/A	""	""	""	""	""	Q1-2021
896	896	SHIP CONSTRUCTION TURNKEY	Leitrim	Lough Meen Estate, Drumkeerin	2	*N/A	""	""	""	""	""	Q4-2021
897	897	SHIP CONSTRUCTION TURNKEY	Leitrim	Commons Lane, Manorhamilton	4	*N/A	""	""	""	""	Q2-2022	""
898	898	SHIP CONSTRUCTION TURNKEY	Leitrim	Cluain Oir, Liscara, Carrick on Shannon	2	*N/A	""	""	""	""	""	Q2-2021
899	899	SHIP CONSTRUCTION TURNKEY	Leitrim	Manorhamilton & Carrigallen	2	*N/A	""	""	""	""	""	Q3-2021
900	900	SHIP CONSTRUCTION TURNKEY	Leitrim	Druminshingore Td., Newtowngore	3	*N/A	""	""	""	""	""	Q2-2022
901	901	SHIP CONSTRUCTION TURNKEY	Leitrim	Lisnagot, Carrick on Shannon	3	*N/A	""	""	""	""	Q2-2022	""
902	902	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	8	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
903	903	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	4	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
904	904	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Breffni Cres., 53 St. Patricks Park Site, Carrick on Shannon	2	*N/A	""	""	""	""	Q1-2022	""
905	905	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Dromahair Td., Dromahair	4	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
906	906	SHIP CONSTRUCTION RENEWAL	Leitrim	Sean McDermott St., Manorhamilton	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
907	907	SHIP CONSTRUCTION	Leitrim	Autumn View, Summerhill, Carrick on Shannon	27	*N/A	""	""	""	""	""	Q4-2021
908	908	SHIP CONSTRUCTION	Leitrim	Taobh Tire, Manorhamilton (Phase 3)	5	*N/A	""	""	""	""	Q1-2022	""
909	909	SHIP CONSTRUCTION	Leitrim	Pairceanna an Bhaile, Townparks, Carrick on Shannon	7	*N/A	""	""	""	""	Q1-2022	""
910	910	SHIP CONSTRUCTION	Leitrim	Lahard, Ballinamore	10	*N/A	""	""	""	""	Q2-2022	""
911	911	SHIP CONSTRUCTION	Leitrim	Kilboderry Td., Carrick on Shannon	18	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
912	912	SHIP CONSTRUCTION	Leitrim	Pairceanna an Bhaile, Townparks, Carrick on Shannon	5	*N/A	""	""	""	""	Q1-2022	""
913	913	SHIP CONSTRUCTION TURNKEY	Limerick	Redgate Close, Old Cratloe Road, Limerick City	14	*N/A	""	""	""	""	""	Q3-2022
914	914	SHIP CONSTRUCTION TURNKEY	Limerick	Gortboy, Charleville Road, KiImallock	24	*N/A	""	""	""	""	""	Q1-2022
915	915	SHIP CONSTRUCTION TURNKEY	Limerick	Knocklong	5	*N/A	""	""	""	""	Q2-2021	""
916	916	SHIP CONSTRUCTION TURNKEY	Limerick	Gortboy, Charleville Road, KiImallock	9	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
917	917	SHIP CONSTRUCTION TURNKEY	Limerick	Broad Street, Limerick	13	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
918	918	SHIP CONSTRUCTION TURNKEY	Limerick	Laurelville, Mill Rd, Corbally	2	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
919	919	SHIP CONSTRUCTION TURNKEY	Limerick	Woodfield Manor, Cloonyscrehane, Newcastlewest, Co Limerick	19	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
920	920	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 2 Derelict Sites, Limerick	3	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
921	921	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 2 Derelict Sites, Limerick	4	N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
922	922	SHIP CONSTRUCTION DESIGN BUILD	Limerick	Old Christians Site, Rathbane	43	*N/A	""	""	""	""	""	Q2-2021
923	923	SHIP CONSTRUCTION DESIGN BUILD	Limerick	Barnakyle, Patrickswell (Site 2)	24	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
924	924	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhill Road 	14	*N/A	""	""	""	""	""	Q1-2022
925	925	SHIP CONSTRUCTION	Limerick	Gough Place, Rosbrien Road, Limerick	17	*N/A	""	""	""	""	Q4-2020	""
926	926	SHIP CONSTRUCTION	Limerick	Clonmacken, Limerick City	43	*N/A	""	""	""	""	Q3-2019	""
927	927	SHIP CONSTRUCTION	Limerick	Deerpark, Adare	13	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
928	928	SHIP CONSTRUCTION	Limerick	Glenview Drive, Hospital	20	*N/A	""	""	""	""	Q3-2020	""
929	929	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	7	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
930	930	SHIP CONSTRUCTION	Limerick	Lower Carey's Road, Limerick City	11	*N/A	""	""	""	""	""	Q1-2021
931	931	SHIP CONSTRUCTION	Limerick	Kileely Road, Moyross	5	*N/A	""	""	""	""	""	Q2-2021
932	932	SHIP CONSTRUCTION	Limerick	Station Close, Knocklong	12	*N/A	""	""	""	""	Q3-2021	""
933	933	SHIP CONSTRUCTION	Limerick	Colbert Terrace, Abbeyfeale	4	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
934	934	SHIP CONSTRUCTION	Limerick	St. Michael's Court, Watergate Flats, 	9	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
935	935	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhills Road	3	*N/A	""	""	""	""	""	Q1-2022
936	936	SHIP CONSTRUCTION	Limerick	Clueing Dara, Broadford	11	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
937	937	SHIP CONSTRUCTION	Limerick	Sycamore Crescent, Newcastle West, Co Limerick	21	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
938	938	SHIP CONSTRUCTION	Limerick	Radharc an Ghleanna, Mountcollins	4	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
939	939	SHIP CONSTRUCTION	Limerick	O?Connor Park, Ardagh, Co. Limerick	10	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
940	940	SHIP CONSTRUCTION	Limerick	Church Glen, Ballylanders, Co. Limerick	9	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
941	941	SHIP CONSTRUCTION	Limerick	Radharc Cillin, Kilfinane, Co. Limerick	10	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
942	942	SHIP CONSTRUCTION	Limerick	Ballycummin Road, Raheen, Co. Limerick	19	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
943	943	SHIP CONSTRUCTION	Limerick	Brugh na Deise, Bruff, Co Limerick	17	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
944	944	SHIP CONSTRUCTION	Limerick	Quinns Cross, Skehacreggaun, Mungret, Limerik.	28	Cluid Housing Association	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
945	945	SHIP CONSTRUCTION	Limerick	(Formerly Whelan's Pub), 52 New Road, Thomandgate, Limerick	6	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
946	946	SHIP CONSTRUCTION	Limerick	Deerpark, Adare	18	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
947	947	SHIP CONSTRUCTION	Limerick	Sycamore Crescent, Newcastle West, Co Limerick	10	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
948	948	SHIP CONSTRUCTION	Limerick	Mulchaire Drive, Annacotty, Co Limerick.	6	N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
949	949	SHIP CONSTRUCTION	Limerick	Clueing Dara, Broadford	8	N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
950	950	REGENERATION	Limerick	Sheep / Athlunkards Street	8	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
951	951	REGENERATION	Limerick	Churchfield	37	Cluid Housing Association	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
952	952	REGENERATION	Limerick	Cosgrave Park	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
953	953	REGENERATION	Limerick	Orchard Site	27	Oaklee Housing Trust	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
954	954	REGENERATION	Limerick	Cliona Park Phase 3	18	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
955	955	REGENERATION	Limerick	45A-46A Cliona Park	2	*N/A	""	""	""	""	""	Q3-2021
956	956	REGENERATION	Limerick	Dalgaish Park	27	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
957	957	REGENERATION	Limerick	Cliona Park Phase 4	20	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
958	958	CAS CONSTRUCTION	Limerick	Towerfield Crescent, Croom	16	Croom Voluntary Housing Association Ltd	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
959	959	CAS CONSTRUCTION	Limerick	Cappamore (Creamery Site)	10	Cappamore Housing Association Ltd	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
960	960	CAS CONSTRUCTION	Limerick	Mirth, Thomondgate	18	Associated Charities Trust Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
961	961	CAS CONSTRUCTION	Limerick	2/3 Mallow Street	12	Peter McVerry Trust Ltd	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
962	962	CAS CONSTRUCTION	Limerick	St. Pauls Convent, Kilfinane	9	Sophia Housing Association Ltd	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
963	963	CAS CONSTRUCTION	Limerick	McGarry House, 7 Alphonsus Street	8	Arlington Novas Ireland Ltd	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
964	964	CAS CONSTRUCTION	Limerick	47 & 48 Main Street, Croom, Limerick	5	Croom Voluntary Housing Association Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
965	965	CAS CONSTRUCTION	Limerick	58 Henry Street, Limerick	5	Simon Community : Midwest Simon	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
966	966	CAS CONSTRUCTION	Limerick	Ballygrennan Close, Moyross (7 units)	7	Respond	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
967	967	CAS CONSTRUCTION	Limerick	Infills Carew Park, Southhill and Moyross	14	Peter McVerry Trust Ltd	""	""	""	""	Q1-2021	""
968	968	CAS CONSTRUCTION	Limerick	28/29 Lower Gerald Griffin Street, Limerick	4	Peter McVerry Trust Ltd	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
969	969	CAS CONSTRUCTION	Limerick	42 St Joseph's Street, Limerick	3	Peter McVerry Trust Ltd	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
970	970	CAS CONSTRUCTION	Limerick	Nunan's Corner, Tullaha, Broadford, Co Limerick	7	Broadford Voluntary Housing and Community Childcare CLG	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
971	971	CAS CONSTRUCTION	Limerick	Infills Carew Park, Southhill and Moyross	24	Peter McVerry Trust Ltd	""	""	""	""	Q1-2021	""
972	972	CAS CONSTRUCTION	Limerick	Athea, Galeside	4	Athea Voluntary Housing CLG	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
973	973	CAS CONSTRUCTION	Limerick	Cloverfield, Glin, Co Limerick	10	Glin Homes for the Elderly Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
974	974	CAS CONSTRUCTION	Limerick	Gortmore, Feenagh, Co Limerick	8	Corran ? Deel Voluntary Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
975	975	CALF Turnkey	Limerick	19 and 20 Castleview Shopping Centre Castleconnell  Limerick (Phase 1)	2	Focus Housing Association CLG	""	""	""	""	""	Q4-2021
976	976	CALF Construction	Limerick	4 Focus Units in County Limerick (Phase 1)	4	Focus Housing Association CLG	""	""	""	Q3-2022	""	""
977	977	CALF Turnkey	Limerick	Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 2)*	25	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
978	978	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 1)*	52	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
979	979	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 2)	32	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
980	980	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 3)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
981	981	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 4)*	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
982	982	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 5)	24	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
983	983	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 1)*	35	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
984	984	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 2)	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
985	985	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 3)*	29	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
986	986	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 4)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
987	987	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 5)*	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
988	988	CALF Turnkey	Limerick	Dromsally Woods, Cappamore, Co. Limerick (Phase 1)	5	Focus Housing Association CLG	""	""	""	""	Q3-2020	""
989	989	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 1)	8	Clid Housing	""	""	""	""	""	Q2-2021
990	990	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 2)*	23	Clid Housing	""	""	""	""	""	Q2-2022
991	991	CALF Turnkey	Limerick	Newtown, Castletroy, Limerick (Phase 1)*	31	Clid Housing	""	""	""	""	Q3-2022	""
992	992	CALF Turnkey	Limerick	Old Dublin Road, Rhebogue, Limerick (Phase 1)*	16	Focus Housing Association CLG	""	""	""	""	""	Q2-2022
993	993	CALF Turnkey	Limerick	Phase 2 Newtown Meadows, Castletroy, Limerick (Phase 1)*	32	Clid Housing	""	""	""	Q4-2021	""	""
994	994	CALF Turnkey	Limerick	Toormore, Main Street, Bruree, Co. Limerick (Phase 1)	16	Clid Housing	""	""	""	""	""	Q2-2021
995	995	CALF Construction	Limerick	Turragh Crescent, Cappamore, Limerick (Phase 1)	15	Clid Housing	""	""	""	Q3-2021	""	""
996	996	CALF Turnkey	Limerick	Woodfield Manor, Cloonyscrehane, Newcastle West, Co Limerick (Phase 1)*	11	Clid Housing	""	""	""	""	Q3-2020	""
997	997	SHIP CONSTRUCTION TURNKEY	Longford	Sl Corglass, Legga	4	*N/A	""	""	""	""	""	Q1-2021
998	998	SHIP CONSTRUCTION TURNKEY	Longford	Richmond St., Longford Town	23	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
999	999	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	8	*N/A	""	""	""	""	""	Q1-2021
1000	1000	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	6	*N/A	""	""	""	""	""	Q3-2021
1001	1001	SHIP CONSTRUCTION TURNKEY	Longford	O'Hara Site, Connaught Rd.,Longford	14	*N/A	""	""	""	""	Q1-2021	""
1002	1002	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	4	*N/A	""	""	""	""	""	Q4-2021
1003	1003	SHIP CONSTRUCTION TURNKEY	Longford	Sl Corglass, Legga	4	*N/A	""	""	""	""	""	Q2-2021
1004	1004	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	4	*N/A	""	""	""	""	""	Q2-2021
1005	1005	SHIP CONSTRUCTION TURNKEY	Longford	Sl Corglass, Legga	1	*N/A	""	""	""	""	""	Q3-2021
1006	1006	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	5	*N/A	""	""	""	""	""	Q2-2021
1007	1007	SHIP CONSTRUCTION TURNKEY	Longford	St. Patricks Ct., Ballinamuck	8	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1008	1008	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	12	N/A	""	""	""	""	""	Q3-2021
1009	1009	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	6	N/A	""	""	""	""	""	Q4-2021
1010	1010	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	4	N/A	""	""	""	""	""	Q4-2021
1011	1011	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	3	N/A	""	""	""	""	""	Q4-2021
1012	1012	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	1	N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1013	1013	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane, Longford Town	2	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1014	1014	SHIP CONSTRUCTION TURNKEY	Longford	Caislean Breac, Newtownforbes	2	*N/A	""	""	""	""	""	Q3-2022
1015	1015	SHIP CONSTRUCTION TURNKEY	Longford	Forthill, Aughnacliffe	13	N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1016	1016	SHIP CONSTRUCTION TURNKEY	Longford	Farrells , Ballinalee	4	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1017	1017	SHIP CONSTRUCTION TURNKEY	Longford	Woodlawn Path, Keenagh	5	N/A	""	""	""	""	Q3-2022	""
1018	1018	SHIP CONSTRUCTION	Longford	'Rose Cottage', Ballinalee	6	*N/A	""	""	""	""	""	Q4-2021
1019	1019	SHIP CONSTRUCTION	Longford	St.Rita's, Park Road, Longford	11	*N/A	""	Stage 2 approved Q1-2020, full design/tender being prepared.	""	""	""	""
1020	1020	SHIP CONSTRUCTION	Longford	Fairgreen View, Longford Town	1	*N/A	""	""	""	""	""	Q2-2021
1021	1021	SHIP CONSTRUCTION	Longford	Cranleymore, Abbeylara	3	*N/A	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
1022	1022	SHIP CONSTRUCTION	Longford	Cloonahard, Edgeworthstown	1	*N/A	""	""	""	""	""	Q2-2021
1023	1023	SHIP CONSTRUCTION	Longford	Woodlands Path, Keenagh	4	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1024	1024	SHIP CONSTRUCTION	Longford	Clough Dillons, Keenagh	4	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1025	1025	SHIP CONSTRUCTION	Longford	Radharc Na Muileann, Lanesborough	10	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1026	1026	SHIP CONSTRUCTION	Longford	24B Congress Terrace, Longford	1	N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
1027	1027	SHIP CONSTRUCTION	Longford	Cnoc Na Grine, Granard	6	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1028	1028	SHIP CONSTRUCTION	Longford	Radharc Na Muileann, Lanesborough	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1029	1029	CAS CONSTRUCTION	Longford	Comcille Terrace, Granard 	11	Tath Housing Association Ltd	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1030	1030	CALF Construction	Longford	Colmcille Terrace, Granard, Co Longford (Phase 1)	8	Tuath Housing Association	""	""	""	Q3-2022	""	""
1031	1031	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	10	*N/A	""	""	""	""	""	Q1-2021
1032	1032	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	9	*N/A	""	""	""	""	""	Q2-2021
1033	1033	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	8	*N/A	""	""	""	""	""	Q2-2021
1034	1034	SHIP CONSTRUCTION TURNKEY	Louth	Glyde View, Tallanstown	2	*N/A	""	""	""	""	""	Q2-2021
1035	1035	SHIP CONSTRUCTION TURNKEY	Louth	Termon River, Termonfeckin	1	*N/A	""	""	""	""	""	Q4-2021
1036	1036	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	8	*N/A	""	""	""	""	Q1-2022	""
1037	1037	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A	""	""	""	""	Q1-2022	""
1038	1038	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A	""	""	""	""	Q1-2022	""
1039	1039	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	17	*N/A	""	""	""	""	Q1-2022	""
1040	1040	SHIP CONSTRUCTION TURNKEY	Louth	Tullybrook Place, Slane Road, Drogheda	3	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1041	1041	SHIP CONSTRUCTION TURNKEY	Louth	Cuirt Na Gcloch, Stoneylane, Ardee	14	*N/A	""	""	""	""	Q3-2022	""
1042	1042	SHIP CONSTRUCTION SINGLE STAGE	Louth	Moneymore, Drogheda	1	*N/A	""	""	""	""	Q2-2020	""
1043	1043	SHIP CONSTRUCTION SINGLE STAGE	Louth	Gort Uaine, Clogherhead	1	*N/A	""	""	""	""	Q3-2020	""
1044	1044	SHIP CONSTRUCTION SINGLE STAGE	Louth	School Lane, Dunleer	1	*N/A	""	""	""	""	Q3-2020	""
1045	1045	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q1-2021
1046	1046	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6	1	*N/A	""	""	""	""	""	Q1-2021
1047	1047	SHIP CONSTRUCTION	Louth	Boice Court (Phase 2), Drogheda	72	*N/A	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
1048	1048	SHIP CONSTRUCTION	Louth	Father Finn Park (Phase 2)	17	*N/A	""	""	""	""	""	Q2-2021
1049	1049	SHIP CONSTRUCTION	Louth	Mount Avenue, Dundalk	93	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1050	1050	SHIP CONSTRUCTION	Louth	Muirhevnamor, Dundalk (Phase 1)	11	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1051	1051	SHIP CONSTRUCTION	Louth	Rathmullen Park, Drogheda	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1052	1052	REGENERATION	Louth	Cox's Demesne Phase 2b	22	*N/A	""	""	""	""	""	Q3-2022
1053	1053	CAS CONSTRUCTION TURNKEY	Louth	Liscorrie, Bog Road, Drogheda	12	Tath Housing Association Ltd	""	""	""	""	""	Q2-2021
1054	1054	CAS CONSTRUCTION RENEWAL	Louth	Kincora House	8	Peter McVerry Trust Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1055	1055	CAS CONSTRUCTION	Louth	5 Slieveroe Crescent, Dundalk	1	Cluid Housing Association	""	""	""	""	""	Q4-2021
1056	1056	CAS CONSTRUCTION	Louth	Barrack Street, Dundalk	30	Simon Community : Dundalk Simon	Stage 1 approved Q3-2018, outline design and costs being prepared.	""	""	""	""	""
1057	1057	CAS CONSTRUCTION	Louth	Coulter Park, Dundalk	7	Tath Housing Association Ltd	""	""	""	""	Q3-2021	""
1058	1058	CAS CONSTRUCTION	Louth	Four Winds, Mullacapple, Collon	4	St. John of God Housing Association Ltd	""	""	""	""	""	Q3-2022
1059	1059	CAS CONSTRUCTION	Louth	St. John's Home, Peter's Hill, Drogheda	4	North ? East Housing Association Ltd	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
1060	1060	CAS CONSTRUCTION	Louth	Riverwell Close, Dundalk	1	Respond	Stage 1 approved Q1-2019, outline design and costs being prepared.	""	""	""	""	""
1061	1061	CAS CONSTRUCTION	Louth	Highfield, Newry Road, Dundalk	12	Women's Aid (Dundalk) CLG	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1062	1062	CAS CONSTRUCTION	Louth	10-16 The Alleys, St. Peter's Place, Drogheda	14	Peter McVerry Trust Ltd	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
1063	1063	CALF Turnkey	Louth	Bellewsbridge Road, Dundalk, Co. Louth (Phase 1)	5	Circle Voluntary Housing Association Ltd	""	""	""	""	Q2-2022	""
1064	1064	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 1)*	16	Tuath Housing Association	""	""	""	""	""	Q1-2021
1065	1065	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 2)	10	Tuath Housing Association	""	""	""	""	""	Q2-2021
1066	1066	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 3)	16	Tuath Housing Association	""	""	""	""	""	Q4-2021
1067	1067	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 4)	11	Tuath Housing Association	""	""	""	""	""	Q4-2021
1068	1068	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 5)	12	Tuath Housing Association	""	""	""	""	Q1-2020	""
1069	1069	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 1)	12	Clid Housing	""	""	""	""	""	Q1-2021
1070	1070	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 2)*	15	Clid Housing	""	""	""	""	""	Q3-2021
1071	1071	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 3)	15	Clid Housing	""	""	""	""	""	Q4-2021
1072	1072	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 4)	13	Clid Housing	""	""	""	""	""	Q4-2021
1073	1073	CALF Turnkey	Louth	Connolly Field, Dundalk, Co. Louth (Phase 1)*	30	Fold Housing Association Ireland Ltd	""	""	""	Q2-2022	""	""
1074	1074	CALF Turnkey	Louth	Connolly Field, Dundalk, Co. Louth (Phase 2)	40	Fold Housing Association Ireland Ltd	""	""	""	Q2-2022	""	""
1075	1075	CALF Turnkey	Louth	Donore Road, Drogheda, Co. Louth (Phase 1)	66	Clid Housing	""	""	""	""	Q2-2021	""
1076	1076	CALF Turnkey	Louth	Drybridge, Drogheda, Co. Louth (Phase 1)	16	North and East Housing Association CLG	""	""	""	""	Q1-2022	""
1077	1077	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth (Phase 1)*	49	Respond	""	""	""	""	Q4-2020	""
1078	1078	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth (Phase 2)	16	Respond	""	""	""	""	Q4-2020	""
1079	1079	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 1)*	47	Clid Housing	""	""	""	""	Q4-2020	""
1080	1080	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 2)	24	Clid Housing	""	""	""	""	Q4-2020	""
1081	1081	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 3)	59	Clid Housing	""	""	""	""	Q4-2020	""
1082	1082	CALF Turnkey	Louth	Fairways Gardens, Dundalk Co Louth (Phase 1)	8	Clid Housing	""	""	""	""	""	Q4-2021
1083	1083	CALF Turnkey	Louth	Halliday Mills, Quay Street, Dundalk, Co. Louth (Phase 1)*	85	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1084	1084	CALF Turnkey	Louth	Harbour View, Coulter Place, Dundalk (Phase 1)	24	Clid Housing	""	""	""	""	""	Q3-2021
1085	1085	CALF Turnkey	Louth	Lismullen Grove, Dundalk, Co. Louth (Phase 2)	8	Tuath Housing Association	""	""	""	""	""	Q1-2021
1086	1086	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 1)*	55	Clid Housing	""	""	""	""	""	Q1-2022
1087	1087	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 2)	39	Clid Housing	""	""	""	""	Q3-2020	""
1088	1088	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 1)*	17	Respond	""	""	""	""	Q4-2020	""
1089	1089	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 2)*	23	Respond	""	""	""	""	Q4-2020	""
1090	1090	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 3)*	46	Respond	""	""	""	""	Q4-2020	""
1091	1091	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 4)*	47	Respond	""	""	""	""	Q4-2020	""
1092	1092	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 1)	6	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1093	1093	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 2)	9	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1094	1094	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 3)	8	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1095	1095	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 4)*	10	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1096	1096	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 5)*	6	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1097	1097	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 6)*	6	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1098	1098	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 2)"	10	Tuath Housing Association	""	""	""	""	""	Q2-2022
1099	1099	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 3)*"	13	Tuath Housing Association	""	""	""	""	Q1-2019	""
1100	1100	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 4)"	12	Tuath Housing Association	""	""	""	""	Q1-2019	""
1101	1101	CALF Turnkey	Louth	Tierney Street, Ardee, Co. Louth (Phase 1)	11	Circle Voluntary Housing Association Ltd	""	""	""	""	Q3-2021	""
1102	1102	CALF Turnkey	Louth	Tullybrook, Drogheda, Co. Louth  (Phase 1)*	85	Clid Housing	""	""	""	""	Q1-2021	""
1103	1103	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Louth	Ballymakenny East	80	N/A	Q2-2022	""	""	""	""	""
1104	1104	SHIP CONSTRUCTION TURNKEY	Mayo	Bunree, Ballina	3	*N/A	""	""	""	""	Q4-2019	""
1105	1105	SHIP CONSTRUCTION TURNKEY	Mayo	Silver Springs, Claremorris	20	*N/A	""	""	""	""	Q3-2020	""
1106	1106	SHIP CONSTRUCTION TURNKEY	Mayo	Main St., Charlestown	2	*N/A	""	""	""	""	""	Q4-2021
1107	1107	SHIP CONSTRUCTION TURNKEY	Mayo	Aidan St., Kiltimagh	2	N/A	""	""	""	""	Q1-2022	""
1108	1108	SHIP CONSTRUCTION SINGLE STAGE	Mayo	The Boreen, Crossmolina	3	*N/A	""	""	""	""	""	Q4-2021
1109	1109	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Deel Court, Crossmolina	3	*N/A	""	""	""	""	""	Q4-2021
1110	1110	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Knockroe, Moygownagh	3	*N/A	""	""	""	""	""	Q4-2021
1111	1111	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Low Park, Charlestown	3	*N/A	""	""	""	""	""	Q4-2021
1112	1112	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Church Manor, Ballina	3	N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1113	1113	SHIP CONSTRUCTION RENEWAL	Mayo	Main St., Hollymount	1	N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1114	1114	SHIP CONSTRUCTION DESIGN BUILD	Mayo	Murrevagh, Mulranney	16	*N/A	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
1115	1115	SHIP CONSTRUCTION	Mayo	Lios na Circa, Saleen, Castlebar - Phase 2	22	*N/A	""	""	""	""	Q1-2022	""
1116	1116	SHIP CONSTRUCTION	Mayo	Cross	8	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1117	1117	SHIP CONSTRUCTION	Mayo	Bonniconlon	5	*N/A	""	""	""	""	""	Q4-2021
1118	1118	SHIP CONSTRUCTION	Mayo	Cloonkeadagh Road, Kiltimagh	21	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1119	1119	SHIP CONSTRUCTION	Mayo	Rehins Fort, Ballina	20	*N/A	""	""	""	""	Q3-2021	""
1120	1120	SHIP CONSTRUCTION	Mayo	50 Units @ Golf Course Rd., Westport	50	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1121	1121	SHIP CONSTRUCTION	Mayo	Ballyglass, Carnacon, Claremorris	5	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
1122	1122	SHIP CONSTRUCTION	Mayo	Lios na Circe, Saleen, Castlebar - Phase 3	14	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1123	1123	SHIP CONSTRUCTION	Mayo	Atlantic Drive ,Belmullet	4	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
1124	1124	SHIP CONSTRUCTION	Mayo	Liskilleen, Ballinrobe,	1	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1125	1125	SHIP CONSTRUCTION	Mayo	Main Street, Ballyvary	12	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
1126	1126	SHIP CONSTRUCTION	Mayo	Rehins Fort, Ballina	30	*N/A	""	""	""	""	Q3-2021	""
1127	1127	SHIP CONSTRUCTION	Mayo	AchilL Sound	20	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1128	1128	CAS CONSTRUCTION TURNKEY	Mayo	Black Oak Rise, Newport	22	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1129	1129	CAS CONSTRUCTION TURNKEY	Mayo	Apt 1-8 Tone Street, Ballina	8	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1130	1130	CAS CONSTRUCTION RENEWAL	Mayo	20 NewLine , Castlebar	2	Mayo Mental Health Association	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1131	1131	CAS CONSTRUCTION	Mayo	Kilbride, Swinford	4	Sophia Housing Association Ltd	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1132	1132	CAS CONSTRUCTION	Mayo	Mount St Mary's Convent, Westport	17	Tath Housing Association Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1133	1133	CAS CONSTRUCTION	Mayo	Ellison House, Ellison St., Castlebar	8	Peter McVerry Trust Ltd	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1134	1134	CAS CONSTRUCTION	Mayo	Chapel Road,  Ballinrobe 	8	Sophia Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1135	1135	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 1)	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
1136	1136	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 2)	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
1137	1137	CALF Turnkey	Mayo	Humbert Way, Castlebar, Co. Mayo (Phase 1)	20	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1138	1138	CALF Turnkey	Mayo	The Sycamores, Ballina (Phase 1)	11	Clid Housing	""	""	""	""	""	Q2-2021
1139	1139	SHIP CONSTRUCTION TURNKEY	Meath	The Brambles, Longford Rd., Duleek	13	*N/A	""	""	""	""	""	Q3-2022
1140	1140	SHIP CONSTRUCTION TURNKEY	Meath	Connaught Street, Athboy	5	*N/A	""	""	""	""	Q4-2020	""
1141	1141	SHIP CONSTRUCTION TURNKEY	Meath	Town Parks, Oldcastle Road, Kells, Co. Meath	12	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1142	1142	SHIP CONSTRUCTION TURNKEY	Meath	Connaught Street, Athboy	2	*N/A	""	""	""	""	""	Q2-2022
1143	1143	SHIP CONSTRUCTION TURNKEY	Meath	23-24 Dunville Avenue, Navan	2	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1144	1144	SHIP CONSTRUCTION TURNKEY	Meath	Bakery Lane, Navan	4	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1145	1145	SHIP CONSTRUCTION TURNKEY	Meath	The Brambles, Longford Rd., Duleek	3	*N/A	""	""	""	""	Q1-2021	""
1146	1146	SHIP CONSTRUCTION RENEWAL	Meath	Carrick St., Kells	49	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1147	1147	SHIP CONSTRUCTION RENEWAL	Meath	Broville, Corballis, Laytown	1	*N/A	""	""	""	""	Q2-2021	""
1148	1148	SHIP CONSTRUCTION RENEWAL	Meath	11 Glenidan Court, Enfield	1	*N/A	""	""	""	""	""	Q1-2022
1149	1149	SHIP CONSTRUCTION RENEWAL	Meath	25 Carrick Street, Kells	1	*N/A	""	""	""	""	""	Q3-2022
1150	1150	SHIP CONSTRUCTION	Meath	Staleen Park, Donore	21	*N/A	""	""	""	""	Q2-2021	""
1151	1151	SHIP CONSTRUCTION	Meath	Dunshaughlin	26	*N/A	""	""	""	""	""	Q4-2021
1152	1152	SHIP CONSTRUCTION	Meath	Farganstown, Navan	84	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
1153	1153	SHIP CONSTRUCTION	Meath	Blackhill Crescent, Donacarney	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1154	1154	SHIP CONSTRUCTION	Meath	Archdeaconary Glebe, Kells	22	*N/A	""	Stage 2 approved Q1-2020, full design/tender being prepared.	""	""	""	""
1155	1155	SHIP CONSTRUCTION	Meath	Nangle Court, Navan	15	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1156	1156	SHIP CONSTRUCTION	Meath	Castle Street, Ashbourne - Dept of Education Site	74	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1157	1157	SHIP CONSTRUCTION	Meath	Church View, Rathmolyon	22	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1158	1158	SHIP CONSTRUCTION	Meath	Haggard Street, Trim, Co. Meath	4	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
1159	1159	SHIP CONSTRUCTION	Meath	Pitcher Lane, Kells, Co. Meath	5	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1160	1160	SHIP CONSTRUCTION	Meath	Swan Lane, Balreask	6	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1161	1161	SHIP CONSTRUCTION	Meath	Lagore, Dunshaughlin	42	*N/A	""	""	""	""	Q3-2020	""
1162	1162	SHIP CONSTRUCTION	Meath	Convent Lands, Kildalkey, Athboy	28	*N/A	""	Stage 2 approved Q1-2022, full design/tender being prepared.	""	""	""	""
1163	1163	SHIP CONSTRUCTION	Meath	Ratholdren Court, Navan	27	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1164	1164	SHIP CONSTRUCTION	Meath	Brews Hill, Navan	12	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1165	1165	SHIP CONSTRUCTION	Meath	Newtown, Drumconrath	1	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1166	1166	SHIP CONSTRUCTION	Meath	New Lane, Abbey Lands, Navan, Co. Meath	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1167	1167	CAS CONSTRUCTION TURNKEY	Meath	Gainsfield, (Gort Fionnbarra) Commons Road, Navan Co. Meath	6	Tath Housing Association Ltd	""	""	""	""	""	Q2-2021
1168	1168	CAS CONSTRUCTION TURNKEY	Meath	6-7 Knightsbrook Close, Iffernock, Trim	2	Tath Housing Association Ltd	""	""	""	""	""	Q4-2021
1169	1169	CAS CONSTRUCTION TURNKEY	Meath	4-5 Oak Hall, Carlanstown, Co Meath	2	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1170	1170	CAS CONSTRUCTION	Meath	Women's Refuge, Tailteann Drive, Windtown, Navan	8	Meath Women?s Housing Association CLG	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1171	1171	CAS CONSTRUCTION	Meath	St. Lomans Street, Trim	4	Society of Saint Vincent de Paul	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1172	1172	CAS CONSTRUCTION	Meath	Park Avenue, Church Street, Oldcastle	5	Society of Saint Vincent de Paul	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1173	1173	CALF Turnkey	Meath	Applewood Court, Beaufort Place, Navan, Co. Meath (Phase 1)*	21	Tuath Housing Association	""	""	""	""	Q3-2020	""
1174	1174	CALF Turnkey	Meath	Ashewood, Ashbourne, Co Meath (Phase 1)	11	Clid Housing	""	""	""	""	""	Q4-2021
1175	1175	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 1)*	34	Respond	""	""	""	""	Q1-2020	""
1176	1176	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 2)	18	Respond	""	""	""	""	Q1-2020	""
1177	1177	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 3)*	11	Respond	""	""	""	""	Q1-2020	""
1178	1178	CALF Turnkey	Meath	Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 1)*	24	Tuath Housing Association	""	""	""	""	Q1-2021	""
1179	1179	CALF Turnkey	Meath	Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 2)*	4	Tuath Housing Association	""	""	""	""	Q1-2021	""
1180	1180	CALF Turnkey	Meath	Colliers Place, Abbey Road, Commons, Duleek, Co. Meath (Phase 1)*	17	North and East Housing Association CLG	""	""	""	""	""	Q2-2022
1181	1181	CALF Turnkey	Meath	Colliers Place, Abbey Road, Commons, Duleek, Co. Meath (Phase 2)	5	North and East Housing Association CLG	""	""	""	""	Q1-2021	""
1182	1182	CALF Turnkey	Meath	Frederick Manor, Ashbourne, Co. Meath (Phase 1)*	11	Clid Housing	""	""	""	""	""	Q1-2021
1183	1183	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 3)	7	Tuath Housing Association	""	""	""	""	""	Q1-2021
1184	1184	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 4)	9	Tuath Housing Association	""	""	""	""	""	Q2-2021
1185	1185	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 1)	19	Tuath Housing Association	""	""	""	""	""	Q4-2021
1186	1186	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 2)	16	Tuath Housing Association	""	""	""	""	""	Q2-2022
1187	1187	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 3)	14	Tuath Housing Association	""	""	""	""	""	Q3-2022
1188	1188	CALF Turnkey	Meath	Gort Fionnbarra, Commons Road, Navan, Co. Meath (Phase 1)	2	Tuath Housing Association	""	""	""	""	""	Q3-2022
1189	1189	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q3-2021
1190	1190	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 2)	5	Tuath Housing Association	""	""	""	""	""	Q3-2021
1191	1191	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 3)	6	Tuath Housing Association	""	""	""	""	""	Q4-2021
1192	1192	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q3-2022
1193	1193	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 2)*	7	Tuath Housing Association	""	""	""	""	""	Q3-2022
1194	1194	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 3)*	7	Tuath Housing Association	""	""	""	""	""	Q3-2022
1195	1195	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 1)	8	Tuath Housing Association	""	""	""	""	Q1-2022	""
1196	1196	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 2)	20	Tuath Housing Association	""	""	""	""	Q1-2022	""
1197	1197	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 3)	11	Tuath Housing Association	""	""	""	""	Q1-2022	""
1198	1198	CALF Turnkey	Meath	Maydenhayes, Donacarney, Co. Meath (Phase 1)*	12	Clid Housing	""	""	""	""	""	Q3-2021
1199	1199	CALF Turnkey	Meath	Narrow Ways, Bettystown, Co. Meath (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q1-2022
1200	1200	CALF Turnkey	Meath	Narrow Ways, Bettystown, Co. Meath (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q1-2022
1201	1201	CALF Turnkey	Meath	Oak Hall, Ardee Road, Carlanstown, Co. Meath (Phase 1)	8	Tuath Housing Association	""	""	""	""	Q1-2022	""
1202	1202	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 2)*	14	Clid Housing	""	""	""	""	""	Q2-2021
1203	1203	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 3)	16	Clid Housing	""	""	""	""	""	Q2-2022
1204	1204	CALF Turnkey	Meath	Ruxton Oaks, Navan, Co. Meath (Phase 1)*	20	Clid Housing	""	""	""	""	""	Q4-2021
1205	1205	CALF Turnkey	Meath	St Marys Dunboyne, Co. Meath (Phase 1)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1206	1206	CALF Turnkey	Meath	The Maudlins, Trim, Co. Meath (Phase 1)	9	Clid Housing	""	""	""	""	""	Q1-2021
1207	1207	CALF Turnkey	Meath	The Willows, Dunshaughlin, Co. Meath (Phase 1)*	96	Clid Housing	""	""	""	""	Q2-2021	""
1208	1208	CALF Turnkey	Meath	Tubberclaire Meadows, Navan, Co. Meath (Phase 1)*	8	Clid Housing	""	""	""	""	Q1-2022	""
1209	1209	CALF Turnkey	Meath	Whitefield Hall, Bettystown, Co. Meath (Phase 3)	2	Tuath Housing Association	""	""	""	""	""	Q3-2021
1210	1210	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc, Carrickmacross	6	*N/A	""	""	""	""	""	Q4-2021
1211	1211	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill Darach, Bree, Castleblayney	16	*N/A	""	""	""	""	Q1-2022	""
1212	1212	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill an Ri, Carrickmacross	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1213	1213	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockcarrick, Annyalla	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1214	1214	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc, Carrickmacross	28	*N/A	""	""	""	""	""	Q3-2022
1215	1215	SHIP CONSTRUCTION TURNKEY	Monaghan	Ballinode	22	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1216	1216	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc Carrickmacross	7	*N/A	""	""	""	""	Q3-2019	""
1217	1217	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill Darach, Castleblayney	14	*N/A	""	""	""	""	Q1-2022	""
1218	1218	SHIP CONSTRUCTION SINGLE STAGE	Monaghan	Folly Court, Ballybay	6	*N/A	""	""	""	""	""	Q4-2021
1219	1219	SHIP CONSTRUCTION RENEWAL	Monaghan	82 & 83 Fermanagh St., Clones	3	*N/A	""	""	""	""	""	Q3-2022
1220	1220	SHIP CONSTRUCTION RENEWAL	Monaghan	An Bonnan Bui & Flower Shop, Fermanagh St., Clones	6	*N/A	""	""	""	""	""	Q2-2022
1221	1221	SHIP CONSTRUCTION RENEWAL	Monaghan	2a & 3 Analore St., Clones	2	*N/A	""	""	""	""	Q3-2019	""
1222	1222	SHIP CONSTRUCTION RENEWAL	Monaghan	Abbey Gatehouse, Analore St., Clones	4	*N/A	""	""	""	""	Q3-2019	""
1223	1223	SHIP CONSTRUCTION RENEWAL	Monaghan	63 Fermanagh St., Clones	3	*N/A	""	""	""	""	""	Q2-2022
1224	1224	SHIP CONSTRUCTION	Monaghan	Lui Na Greine, Scotstown	6	*N/A	""	""	""	""	""	Q4-2021
1225	1225	SHIP CONSTRUCTION	Monaghan	12 Church St., Ballybay	2	*N/A	""	""	""	""	Q4-2021	""
1226	1226	SHIP CONSTRUCTION	Monaghan	Church Hill, Clones	2	*N/A	""	""	""	""	Q2-2021	""
1227	1227	SHIP CONSTRUCTION	Monaghan	13 McCurtain Street, Clones	1	*N/A	""	""	""	""	Q1-2021	""
1228	1228	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	12	*N/A	""	""	""	""	""	Q2-2022
1229	1229	SHIP CONSTRUCTION	Monaghan	An Cls, Cornamucklaglass, Ballybay 	7	*N/A	""	""	""	""	Q2-2022	""
1230	1230	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	1	*N/A	""	""	""	""	""	Q2-2022
1231	1231	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	5	*N/A	""	""	""	""	""	Q3-2022
1232	1232	SHIP CONSTRUCTION	Monaghan	Lecklevera, Monaghan	1	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1233	1233	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	8	*N/A	""	""	""	""	Q2-2020	""
1234	1234	CAS CONSTRUCTION	Monaghan	Drumillard, Castleblayney (Phase 2)	2	Castleblayney Care Housing Association Ltd	""	""	""	""	Q1-2021	""
1235	1235	CAS CONSTRUCTION	Monaghan	Liseggerton, Clones	19	Oaklee Housing Trust	""	""	""	""	""	Q2-2021
1236	1236	CAS CONSTRUCTION	Monaghan	Birch Court Apts., 34 Main Street, Ballybay	4	North ? East Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1237	1237	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 2)"	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
1238	1238	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 3)"	8	Tuath Housing Association	""	""	""	""	""	Q3-2021
1239	1239	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 4)"	8	Tuath Housing Association	""	""	""	""	""	Q2-2022
1240	1240	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 5)"	3	Tuath Housing Association	""	""	""	""	""	Q2-2022
1241	1241	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 6)"	2	Tuath Housing Association	""	""	""	""	Q2-2019	""
1242	1242	CALF Turnkey	Monaghan	Drumbear Wood, Monaghan, Co. Monaghan  (Phase 1)*	17	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2022	""
1243	1243	CALF Turnkey	Monaghan	Lakeview Apartments, Drummond Radhairc, Carrickmacross, Co Monaghan (Phase 1)*	12	North and East Housing Association CLG	""	""	""	""	""	Q2-2022
1244	1244	CALF Turnkey	Monaghan	Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 1)*	41	Tuath Housing Association	""	""	""	Q2-2021	""	""
1245	1245	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 1)	7	Tuath Housing Association	""	""	""	""	""	Q2-2021
1246	1246	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 2)	6	Tuath Housing Association	""	""	""	""	Q3-2019	""
1247	1247	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 3)	6	Tuath Housing Association	""	""	""	""	Q3-2019	""
1248	1248	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 4)	14	Tuath Housing Association	""	""	""	""	Q3-2019	""
1249	1249	CALF Turnkey	Monaghan	Part 2, Radharc An Bhri, Bree, Castleblayney, Co. Monaghan (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q2-2022
1250	1250	CALF Turnkey	Monaghan	Part 2, Radharc An Bhri, Bree, Castleblayney, Co. Monaghan (Phase 2)	8	Tuath Housing Association	""	""	""	""	Q4-2021	""
1251	1251	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 1)	8	Tuath Housing Association	""	""	""	""	Q3-2020	""
1252	1252	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 2)*	8	Tuath Housing Association	""	""	""	""	Q3-2020	""
1253	1253	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 1)*	8	Tuath Housing Association	""	""	""	""	Q2-2021	""
1254	1254	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 2)	6	Tuath Housing Association	""	""	""	""	Q2-2021	""
1255	1255	SHIP CONSTRUCTION TURNKEY	Offaly	Main Street, Daingean	8	*N/A	""	""	""	""	""	Q4-2021
1256	1256	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	5	*N/A	""	""	""	""	""	Q4-2021
1257	1257	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Greine, Clonygowan	2	*N/A	""	""	""	""	""	Q2-2021
1258	1258	SHIP CONSTRUCTION TURNKEY	Offaly	Coolgarry, Walsh Island 	4	*N/A	""	""	""	""	Q3-2021	""
1259	1259	SHIP CONSTRUCTION TURNKEY	Offaly	Castle View, Mucklagh, Tullamore	8	*N/A	""	""	""	""	""	Q2-2022
1260	1260	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	2	*N/A	""	""	""	""	""	Q1-2021
1261	1261	SHIP CONSTRUCTION TURNKEY	Offaly	Bog Road, Portarlington	28	*N/A	""	""	""	""	Q2-2021	""
1262	1262	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	4	*N/A	""	""	""	""	""	Q2-2021
1263	1263	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	6	*N/A	""	""	""	""	""	Q2-2022
1264	1264	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	5	*N/A	""	""	""	""	""	Q1-2022
1265	1265	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	8	*N/A	""	""	""	""	""	Q3-2022
1266	1266	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	11	N/A	""	""	""	""	Q2-2021	""
1267	1267	SHIP CONSTRUCTION RENEWAL	Offaly	1 Newbridge St., Birr	1	*N/A	""	""	""	""	""	Q3-2022
1268	1268	SHIP CONSTRUCTION RENEWAL	Offaly	Church Hill, Tullamore	2	*N/A	""	""	""	""	""	Q3-2022
1269	1269	SHIP CONSTRUCTION	Offaly	Beechwood Drive, Circular Road, Daingean	9	*N/A	""	""	Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.	""	""	""
1270	1270	SHIP CONSTRUCTION	Offaly	Kylebeg, Banagher (Phase 2)	18	*N/A	""	""	""	""	Q3-2021	""
1271	1271	SHIP CONSTRUCTION	Offaly	Beechgrove, Belmont	7	*N/A	""	""	""	""	Q4-2021	""
1272	1272	SHIP CONSTRUCTION	Offaly	Raheen ,Clara	38	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1273	1273	SHIP CONSTRUCTION	Offaly	Elderberry Drive, Moneygall	4	*N/A	""	""	""	""	Q1-2022	""
1274	1274	SHIP CONSTRUCTION	Offaly	Sr. Senan Avenue, Edenderry	4	*N/A	""	""	""	""	Q2-2022	""
1275	1275	SHIP CONSTRUCTION	Offaly	Dargan Drive, Chancery Lane, Tullamore (Phase 2)	20	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1276	1276	SHIP CONSTRUCTION	Offaly	Sycamore Drive, Ballycumber	9	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1277	1277	SHIP CONSTRUCTION	Offaly	Circular Road, Daingean Phase 2	9	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1278	1278	CAS CONSTRUCTION	Offaly	Killane Court, Edenderry	2	Tath Housing Association Ltd	""	""	""	""	""	Q2-2021
1279	1279	CAS CONSTRUCTION	Offaly	Clonminch, Tullamore	19	Oaklee Housing Trust	""	""	""	""	Q1-2021	""
1280	1280	CAS CONSTRUCTION	Offaly	Presentation Lands, Portarlington	39	Sophia Housing Association Ltd	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1281	1281	CAS CONSTRUCTION	Offaly	Clonamore Hotel, Tullamore	17	Sophia Housing Association Ltd	""	""	""	""	Q3-2022	""
1282	1282	CALF Turnkey	Offaly	3 units, An Corran, Crinkle, Birr, Co. Offaly (Phase 1)	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
1283	1283	CALF Construction	Offaly	Kearney?s Field, Tullamore, Co. Offaly (Phase 1)	41	Oaklee Housing	""	""	""	""	Q2-2021	""
1284	1284	CALF Construction	Offaly	Killane Drive, Edenderry, Co Offaly (Phase 1)	25	Tuath Housing Association	""	""	""	""	""	Q2-2021
1285	1285	CALF Turnkey	Offaly	Rahan Road, Tullamore, Co. Offaly (aka Jackson?s Hill) (Phase 1)*	26	Clid Housing	""	""	""	""	""	Q2-2022
1286	1286	CALF Turnkey	Offaly	The Hawthorns, Arden Road, Tullamore, Co. Offaly (Phase 1)	16	Clid Housing	""	""	""	""	""	Q2-2022
1287	1287	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1288	1288	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	11	N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1289	1289	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	5	N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1290	1290	SHIP CONSTRUCTION SINGLE STAGE	Roscommon	The Meadows, Castlerea 	2	*N/A	""	""	""	""	Q2-2022	""
1291	1291	SHIP CONSTRUCTION RENEWAL	Roscommon	Ardnanagh ,Roscommon Town	1	*N/A	""	""	""	""	Q1-2022	""
1292	1292	SHIP CONSTRUCTION RENEWAL	Roscommon	Elphin Courthouse, Elphin	3	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1293	1293	SHIP CONSTRUCTION RENEWAL	Roscommon	Pound St., Ballaghaderreen	1	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1294	1294	SHIP CONSTRUCTION	Roscommon	Cloonfad	3	*N/A	""	""	""	""	""	Q2-2021
1295	1295	SHIP CONSTRUCTION	Roscommon	Cluain Fraoigh, Cloonbeirne	7	*N/A	""	""	""	""	""	Q1-2021
1296	1296	SHIP CONSTRUCTION	Roscommon	Sli an Choiste, Monksland	20	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1297	1297	SHIP CONSTRUCTION	Roscommon	Meadowbrook, Ballyclare Td., Ballyleague	16	*N/A	""	""	""	""	""	Q4-2021
1298	1298	SHIP CONSTRUCTION	Roscommon	Lisroyne Td., Strokestown	10	*N/A	""	""	""	""	""	Q4-2021
1299	1299	SHIP CONSTRUCTION	Roscommon	Windmill Road, Elphin Road	10	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1300	1300	SHIP CONSTRUCTION	Roscommon	Lakeview Heights, Bellspark Td., Boyle	6	*N/A	""	""	""	""	Q2-2022	""
1301	1301	SHIP CONSTRUCTION	Roscommon	Lisnamult, Ardnanagh Td., Roscommon Town	13	*N/A	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
1302	1302	SHIP CONSTRUCTION	Roscommon	Station Rd., Cortober, Carrickk on Shannon	4	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1303	1303	SHIP CONSTRUCTION	Roscommon	Curlew View, Boyle	14	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1304	1304	CAS CONSTRUCTION RENEWAL	Roscommon	2 Tithe na gCarad, Willliamstown Road, Castlerea	4	Sophia Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1305	1305	CALF Turnkey	Roscommon	Monksland, Athlone, Co. Roscommon (Cloongowna). (Phase 1)*	35	Tuath Housing Association	""	""	""	""	Q4-2019	""
1306	1306	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Roscommon	The Walk, Roscommon Town	53	*N/A	""	""	""	""	""	Q2-2021
1307	1307	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	12	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1308	1308	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	15	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1309	1309	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	26	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1310	1310	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	13	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1311	1311	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 1)	10	*N/A	""	""	""	""	""	Q4-2021
1312	1312	SHIP CONSTRUCTION	Sligo	Dromore West 	10	*N/A	""	""	""	""	""	Q4-2021
1313	1313	SHIP CONSTRUCTION	Sligo	Robbers' Lane, Maugheraboy, Sligo	62	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1314	1314	SHIP CONSTRUCTION	Sligo	SRD at Crowagh, Dromore West	1	*N/A	""	""	""	""	""	Q4-2021
1315	1315	SHIP CONSTRUCTION	Sligo	Gormley Park, Bunnanadden	6	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1316	1316	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 2) & The Green Rd,	19	*N/A	""	""	""	""	Q2-2022	""
1317	1317	SHIP CONSTRUCTION	Sligo	Geldof Drive & Centre Park, Cranmore, Sligo	30	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
1318	1318	CAS CONSTRUCTION TURNKEY	Sligo	Avena, Ballisodare, Co Sligo	6	Tath Housing Association Ltd	""	""	""	""	""	Q1-2022
1319	1319	CAS CONSTRUCTION	Sligo	Killeshin, First Sea Road, Sligo	5	Newgrove Housing Association Ltd	""	""	""	""	Q4-2020	""
1320	1320	CAS CONSTRUCTION	Sligo	Summerhill, Tubbercurry, Co Sligo	6	Sophia Housing Association Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1321	1321	CAS CONSTRUCTION	Sligo	Adelaide Street,  Sligo	38	Tath Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1322	1322	CALF Turnkey	Sligo	The Fairways, Tubbercurry, Co. Sligo (Phase 1)	8	Co - Operative Housing Ireland Society Limited	""	""	""	Q3-2022	""	""
1323	1323	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Sligo	Rathellen, Finisklin, Co. Sligo	63	*N/A	""	Q4-2021	""	""	""	""
1324	1324	SHIP DIALOG	South Dublin	Kilcarbery JV Social	16	*N/A	""	""	""	""	""	Q3-2022
1325	1325	SHIP DIALOG	South Dublin	Kilcarbery JV Social	20	*N/A	""	""	""	""	""	Q3-2022
1326	1326	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1327	1327	SHIP DIALOG	South Dublin	Kilcarbery JV Social	6	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1328	1328	SHIP DIALOG	South Dublin	Clonburris 1	93	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1329	1329	SHIP DIALOG	South Dublin	Clonburris 2	56	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1330	1330	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1331	1331	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1332	1332	SHIP DIALOG	South Dublin	Kilcarbery JV Social	22	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1333	1333	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1334	1334	SHIP DIALOG	South Dublin	Kilcarbery JV Social	26	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1335	1335	SHIP DIALOG	South Dublin	Kilcarbery JV Social	5	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1336	1336	SHIP DIALOG	South Dublin	Kilcarbery JV Social	3	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1337	1337	SHIP DIALOG	South Dublin	Kilcarbery JV Social	27	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1338	1338	SHIP DIALOG	South Dublin	Kilcarbery JV Social	28	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1339	1339	SHIP DIALOG	South Dublin	Kilcarbery JV Social	17	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1340	1340	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1341	1341	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1342	1342	SHIP DIALOG	South Dublin	Kilcarbery JV Social	9	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1343	1343	SHIP DIALOG	South Dublin	Kilcarbery JV Social	7	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1344	1344	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1345	1345	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1346	1346	SHIP DIALOG	South Dublin	Kilcarbery JV Social	21	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1347	1347	SHIP DIALOG	South Dublin	Kilcarbery JV Social	4	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1348	1348	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1349	1349	SHIP DIALOG	South Dublin	Kilcarbery JV Social	5	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1350	1350	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	37 Greenfort Gardens, Clondalkin	2	*N/A	""	""	""	""	""	Q4-2021
1351	1351	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	Brady's Court, Old Bawn, Tallaght	12	*N/A	""	""	""	""	Q3-2022	""
1352	1352	SHIP CONSTRUCTION RENEWAL	South Dublin	Cloragh Mills, Edmonstown Road, Rathfarnham, Dublin 16	8	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1353	1353	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	St. Marks Avenue, Clondalkin	38	*N/A	""	""	""	""	Q3-2020	""
1354	1354	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Balgaddy F, Griffeen Avenue, Lucan Co. Dublin	69	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1355	1355	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riversdale, Clondalkin, Dublin 22	25	*N/A	""	""	""	""	Q4-2020	""
1356	1356	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riverside Cottages, Templeogue	10	*N/A	""	""	""	""	Q3-2022	""
1357	1357	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riversdale, Clondalkin, Dublin 22	18	*N/A	""	""	""	""	Q4-2020	""
1358	1358	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Grand Canal, Lindisfarne, Clondalkin,	19	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1359	1359	SHIP CONSTRUCTION	South Dublin	St. Catherine?s, Knockmore Avenue, Killinarden, Tallaght	12	*N/A	""	""	""	""	Q4-2020	""
1360	1360	SHIP CONSTRUCTION	South Dublin	Homeville, Knocklyon, Dublin 16	16	*N/A	""	""	""	""	Q4-2020	""
1361	1361	SHIP CONSTRUCTION	South Dublin	Nangor Road, Clondalkin, Dublin 22	93	*N/A	""	""	""	""	Q2-2022	""
1362	1362	CAS CONSTRUCTION TURNKEY	South Dublin	Oakridge, Ballynakelly,Edge, Newcastle, Co. Dublin	3	Tath Housing Association Ltd	""	""	""	""	""	Q2-2022
1363	1363	CAS CONSTRUCTION TURNKEY	South Dublin	3 Cornerpark Rise	1	Arlington Novas Ireland Ltd	""	""	""	""	""	Q4-2021
1364	1364	CAS CONSTRUCTION	South Dublin	Old Nangor Road, Clondalkin	10	Simon Community : Dublin Simon	""	Stage 2 approved Q4-2016, full design/tender being prepared.	""	""	""	""
1365	1365	CALF Turnkey	South Dublin	Ballynakelly Rise, Newcastle Boulevard and Graydon Park, Newcastle, County Dublin (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q2-2022
1366	1366	CALF Turnkey	South Dublin	Ballynakelly Rise, Newcastle Boulevard and Graydon Park, Newcastle, County Dublin (Phase 2)*	8	Tuath Housing Association	""	""	""	""	""	Q3-2022
1367	1367	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 1)*	10	Tuath Housing Association	""	""	""	""	Q4-2021	""
1368	1368	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 2)*	9	Tuath Housing Association	""	""	""	""	Q4-2021	""
1369	1369	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 3)*	27	Tuath Housing Association	""	""	""	""	Q4-2021	""
1370	1370	CALF Turnkey	South Dublin	Citywest Quarter, Citywest, Dublin 24 (Phase 1)*	32	Tuath Housing Association	""	""	""	""	""	Q2-2021
1371	1371	CALF Turnkey	South Dublin	Citywest Village House, Citywest Village, D24 (Phase 1)*	36	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q1-2022
1372	1372	CALF Turnkey	South Dublin	Cloverhill Lodge, Cloverhill Rd, Clondalkin, D22 (Phase 1)*	40	Oaklee Housing	""	""	""	""	Q2-2021	""
1373	1373	CALF Turnkey	South Dublin	Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 2)*	9	Clid Housing	""	""	""	""	""	Q1-2021
1374	1374	CALF Construction	South Dublin	Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 1)	17	Clid Housing	""	""	""	""	Q3-2020	""
1375	1375	CALF Construction	South Dublin	Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 2)	23	Clid Housing	""	""	""	""	Q3-2020	""
1376	1376	CALF Turnkey	South Dublin	Finians Way, Newcastle South, Newcastle, Co. Dublin (Phase 1)*	2	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2021
1377	1377	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 1)	32	Respond	""	""	""	""	""	Q3-2021
1378	1378	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 2)	38	Respond	""	""	""	""	""	Q3-2021
1379	1379	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 3)*	24	Respond	""	""	""	""	""	Q4-2021
1380	1380	CALF Turnkey	South Dublin	Graydon, Newcastle, Co. Dublin (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q4-2021
1381	1381	CALF Turnkey	South Dublin	Hallwell, Tubber Lane, Adamstown, Co Dublin (Phase 1)*	45	The Iveagh Trust	""	""	""	""	""	Q4-2021
1382	1382	CALF Turnkey	South Dublin	Kingswood, Old Ballymount Road, Tallaght, Dublin 24 (Phase 1)*	24	Respond	""	""	""	""	""	Q4-2021
1383	1383	CALF Construction	South Dublin	Old Lucan Road, Palmerstown, Dublin 20 (Phase 1)	4	Tuath Housing Association	""	""	""	Q3-2021	""	""
1384	1384	CALF Turnkey	South Dublin	Phase 2, Aylmer Drive, Aylmer Heath, Newcastle, Co. Dublin (Phase 1)*	17	Respond	""	""	""	""	""	Q2-2021
1385	1385	CALF Turnkey	South Dublin	"Sallymills
(Formerly Sallypark),
 Clondalkin, Dublin 22 (Phase 1)*"	85	Clid Housing	""	""	""	""	Q4-2020	""
1386	1386	CALF Turnkey	South Dublin	San Guida, New Road, Clondalkin, Dublin 22 (Phase 1)*	21	Clid Housing	""	""	""	""	Q3-2021	""
1387	1387	CALF Turnkey	South Dublin	"Scholarstown Road, Rathfarnham, Dublin 16


 (Phase 1)*"	14	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q1-2022
1388	1388	CALF Turnkey	South Dublin	Somerton Gate, Adamstown, Lucan, Co. Dublin (Phase 1)*	36	Clid Housing	""	""	""	""	Q2-2021	""
1389	1389	CALF Construction	South Dublin	St. Catherine?s, Knockmore Avenue, Killinarden, Tallaght, Dublin 24 (Phase 1)	2	Sophia Housing Association Ltd	""	""	""	""	""	Q2-2022
1390	1390	CALF Construction	South Dublin	The Weir, Whitestown Way, Tallaght, Dublin 24 (Phase 1)	81	Clid Housing	""	""	""	""	Q2-2021	""
1391	1391	CALF Turnkey	South Dublin	Willowview, Ballyboden Road, Rathfarnham, Dublin 14 (Phase 1)*	12	Clid Housing	""	""	""	""	""	Q2-2021
1392	1392	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	South Dublin	Clonburris	120	N/A	Q2-2022	""	""	""	""	""
1393	1393	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	18	*N/A	""	""	""	""	Q3-2020	""
1394	1394	SHIP CONSTRUCTION TURNKEY	Tipperary	Ma Charoin, Manna South, Templemore	13	*N/A	""	""	""	""	Q1-2021	""
1395	1395	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	23	*N/A	""	""	""	""	Q3-2020	""
1396	1396	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	10	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1397	1397	SHIP CONSTRUCTION TURNKEY	Tipperary	Rosanna Close, Tipperary Town	1	*N/A	""	""	""	""	Q3-2020	""
1398	1398	SHIP CONSTRUCTION TURNKEY	Tipperary	Hazel Close, Carrick on Suir	14	*N/A	""	""	""	""	""	Q4-2021
1399	1399	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1400	1400	SHIP CONSTRUCTION TURNKEY	Tipperary	Cois Abhainn, Mullinahone	3	*N/A	""	""	""	""	""	Q4-2021
1401	1401	SHIP CONSTRUCTION TURNKEY	Tipperary	Glentara, Roscrea	2	*N/A	""	""	""	""	""	Q4-2021
1402	1402	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	11	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1403	1403	SHIP CONSTRUCTION TURNKEY	Tipperary	Carrick Beg, Carrick on Suir	22	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1404	1404	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel 	2	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1405	1405	SHIP CONSTRUCTION TURNKEY	Tipperary	Clogheen Road, Ardfinnan	13	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1406	1406	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenoir, Cullen	7	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1407	1407	SHIP CONSTRUCTION TURNKEY	Tipperary	Ard na Sidhe, Clonmel	9	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1408	1408	SHIP CONSTRUCTION TURNKEY	Tipperary	Springfort Meadows, Nenagh	17	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1409	1409	SHIP CONSTRUCTION TURNKEY	Tipperary	Kilsheelan, Clonmel	2	*N/A	""	""	""	""	""	Q3-2022
1410	1410	SHIP CONSTRUCTION TURNKEY	Tipperary	Drangan	3	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1411	1411	SHIP CONSTRUCTION TURNKEY	Tipperary	Stradavoher Road, Thurles	29	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1412	1412	SHIP CONSTRUCTION TURNKEY	Tipperary	Kilsheelan, Clonmel	1	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1413	1413	SHIP CONSTRUCTION RENEWAL	Tipperary	Ard na Greine, Clonmel	2	*N/A	""	""	""	""	Q4-2020	""
1414	1414	SHIP CONSTRUCTION RENEWAL	Tipperary	Boherclough Street, Cashel	9	*N/A	""	""	""	""	Q3-2022	""
1415	1415	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A	""	""	""	""	""	Q1-2021
1416	1416	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A	""	""	""	""	""	Q4-2021
1417	1417	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	10	*N/A	""	""	""	""	""	Q4-2021
1418	1418	SHIP CONSTRUCTION	Tipperary	Templetouhy	10	*N/A	""	""	""	""	""	Q4-2021
1419	1419	SHIP CONSTRUCTION	Tipperary	Abbey Street, Cahir	10	*N/A	""	""	""	""	Q3-2020	""
1420	1420	SHIP CONSTRUCTION	Tipperary	Borrisokane	14	*N/A	""	""	""	""	""	Q4-2021
1421	1421	SHIP CONSTRUCTION	Tipperary	Portroe, Nenagh	14	*N/A	""	""	""	""	Q4-2021	""
1422	1422	SHIP CONSTRUCTION	Tipperary	Cloughjordan	2	*N/A	""	""	""	""	""	Q2-2021
1423	1423	SHIP CONSTRUCTION	Tipperary	Mitchel St., Thurles	1	*N/A	""	""	""	""	""	Q4-2021
1424	1424	SHIP CONSTRUCTION	Tipperary	Cormack Drive, Nenagh	12	*N/A	""	""	""	""	""	Q3-2022
1425	1425	SHIP CONSTRUCTION	Tipperary	Bansha	14	*N/A	""	""	""	""	Q3-2021	""
1426	1426	SHIP CONSTRUCTION	Tipperary	Ned Hayes Drive, Twomileborris, Thurles	22	*N/A	""	""	""	""	Q3-2021	""
1427	1427	SHIP CONSTRUCTION	Tipperary	Donohill	8	*N/A	""	""	""	""	Q3-2021	""
1428	1428	SHIP CONSTRUCTION	Tipperary	Mullinahone	10	*N/A	""	""	""	""	Q1-2021	""
1429	1429	SHIP CONSTRUCTION	Tipperary	Ballyclerihan	14	*N/A	""	""	""	""	Q3-2021	""
1430	1430	SHIP CONSTRUCTION	Tipperary	Ard Alainn, Moyne	9	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1431	1431	SHIP CONSTRUCTION	Tipperary	Ardcroney	4	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1432	1432	SHIP CONSTRUCTION	Tipperary	Comeragh Drive, Clonmel	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1433	1433	SHIP CONSTRUCTION	Tipperary	Church Street, Templemore	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1434	1434	SHIP CONSTRUCTION	Tipperary	Woodview Close, Castle Crescent,  Nenagh	10	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1435	1435	SHIP CONSTRUCTION	Tipperary	Grove Street. Roscrea	6	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1436	1436	SHIP CONSTRUCTION	Tipperary	William Street, Clonmel	4	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1437	1437	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	26	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1438	1438	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A	""	""	""	""	""	Q2-2021
1439	1439	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A	""	""	""	""	""	Q2-2022
1440	1440	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	1	*N/A	""	""	""	""	""	Q1-2022
1441	1441	SHIP CONSTRUCTION	Tipperary	Mountain View, Cahir	23	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1442	1442	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	20	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1443	1443	SHIP CONSTRUCTION	Tipperary	William Street, Nenagh	7	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
1444	1444	SHIP CONSTRUCTION	Tipperary	Borrisokane	1	*N/A	""	""	""	""	""	Q1-2022
1445	1445	SHIP CONSTRUCTION	Tipperary	Ashbury, Roscrea	10	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1446	1446	SHIP CONSTRUCTION	Tipperary	Fr. Mathew Street, Tipperary Town	4	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1447	1447	CAS CONSTRUCTION TURNKEY	Tipperary	Kichham Street, Carrick en Suir	12	Tath Housing Association Ltd	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1448	1448	CAS CONSTRUCTION RENEWAL	Tipperary	7 Stradavoher Court, Thurles	2	Arlington Novas Ireland Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1449	1449	CAS CONSTRUCTION RENEWAL	Tipperary	1 and 1A Limerick Road	2	Thurles Lions Trust Housing Assoc.	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1450	1450	CAS CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	9	Cluid Housing Association	""	""	""	""	Q2-2021	""
1451	1451	CAS CONSTRUCTION	Tipperary	Stanwix House, Kickham Street, Thurles	19	Thurles Lions Trust Housing Assoc.	""	""	""	""	Q2-2021	""
1452	1452	CAS CONSTRUCTION	Tipperary	Main Street, Templemore	24	Templemore Voluntary Housing Association	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
1453	1453	CAS CONSTRUCTION	Tipperary	Deerpark Road, Ashwell's Lot	2	SPADE ? St. Patrick?s Dwellings for the Elderly	""	""	""	""	""	Q2-2022
1454	1454	CAS CONSTRUCTION	Tipperary	Gort an Oir, Fethard	7	Belmont Park Housing Association Ltd	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1455	1455	CALF Turnkey	Tipperary	Abbey Court Lodges, Old Dublin Road, Nenagh, Co Tipperary (Phase 1)	12	Focus Housing Association CLG	""	""	""	""	""	Q1-2022
1456	1456	CALF Turnkey	Tipperary	Abbey Court Lodges, Old Dublin Road, Nenagh, Co Tipperary (Phase 2)	4	Focus Housing Association CLG	""	""	""	""	""	Q2-2022
1457	1457	CALF Turnkey	Tipperary	Ballygraigue Court, Ballygraigue Road, Nenagh (Phase 1)	5	Clid Housing	""	""	""	""	""	Q2-2022
1458	1458	CALF Turnkey	Tipperary	Wallers Lot, East Cashel, Co. Tipperary (Phase 1)*	40	Tuath Housing Association	""	""	""	""	Q1-2022	""
1459	1459	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	13	*N/A	""	""	""	""	""	Q1-2021
1460	1460	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	10	*N/A	""	""	""	""	""	Q2-2021
1461	1461	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	23	*N/A	""	""	""	""	""	Q2-2021
1462	1462	SHIP CONSTRUCTION TURNKEY	Waterford	The Courtyard, Morrissons Road, Waterford City	8	*N/A	""	""	""	""	""	Q2-2021
1463	1463	SHIP CONSTRUCTION TURNKEY	Waterford	Bounds Court, Airport Road, Waterford	15	N/A	""	""	""	""	""	Q1-2022
1464	1464	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main St., Aglish; Bye Lane, Kilmacthomas	6	N/A	""	""	""	""	""	Q4-2021
1465	1465	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main St., Aglish; Bye Lane, Kilmacthomas	3	*N/A	""	""	""	""	""	Q3-2022
1466	1466	SHIP CONSTRUCTION TURNKEY	Waterford	Radharc na Siuire, Knockboy	3	*N/A	""	""	""	""	""	Q1-2022
1467	1467	SHIP CONSTRUCTION TURNKEY	Waterford	Radharc na Siuire, Knockboy	4	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1468	1468	SHIP CONSTRUCTION RENEWAL	Waterford	Clarendon Court, Penrose Lane, Waterford	24	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
1469	1469	SHIP CONSTRUCTION RENEWAL	Waterford	Apt 1 and Apt 2 Rivercourt, Grattan Quay, Waterford City	2	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1470	1470	SHIP CONSTRUCTION RENEWAL	Waterford	Meeting House Lane, Waterford City	6	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1471	1471	SHIP CONSTRUCTION RENEWAL	Waterford	29 The Glen, Waterford City	4	*N/A	""	""	""	""	Q2-2022	""
1472	1472	SHIP CONSTRUCTION RENEWAL	Waterford	22 and 23 Thomas Hill, Waterford	3	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1473	1473	SHIP CONSTRUCTION RENEWAL	Waterford	Apts 1-6, The Old Convent, Kilmacthomas	6	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1474	1474	SHIP CONSTRUCTION RENEWAL	Waterford	70 and 71 O'Connell Street, Waterford	5	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1475	1475	SHIP CONSTRUCTION DESIGN BUILD	Waterford	Ballygunner, Waterford City	49	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1476	1476	SHIP CONSTRUCTION DESIGN BUILD	Waterford	Ballynaneashagh, Waterford City	22	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1477	1477	SHIP CONSTRUCTION	Waterford	An Garrn, Crobally Upper, Tramore	50	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1478	1478	SHIP CONSTRUCTION	Waterford	Larchville, Waterford City	5	*N/A	""	""	""	""	""	Q2-2021
1479	1479	SHIP CONSTRUCTION	Waterford	Doyles Street, Waterford City	4	*N/A	""	""	""	""	""	Q4-2021
1480	1480	SHIP CONSTRUCTION	Waterford	The Glen, Bridge St, Waterford	17	*N/A	""	Stage 2 approved Q3-2018, full design/tender being prepared.	""	""	""	""
1481	1481	SHIP CONSTRUCTION	Waterford	Summerland Square, Waterford	12	*N/A	""	""	Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.	""	""	""
1482	1482	SHIP CONSTRUCTION	Waterford	Graigueshoneen, Kilmacthomas	16	*N/A	""	""	""	""	""	Q1-2022
1483	1483	SHIP CONSTRUCTION	Waterford	Mount Esker, Ballytruckle Road, Waterford City	14	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1484	1484	SHIP CONSTRUCTION	Waterford	Newgate Street, Waterford City	36	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
1485	1485	SHIP CONSTRUCTION	Waterford	Fountain Street, Ferrybank, Waterford	14	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
1486	1486	SHIP CONSTRUCTION	Waterford	50-53 Ballytruckle Road, Waterford	11	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1487	1487	SHIP CONSTRUCTION	Waterford	Rossmore, Kilmacthomas	6	*N/A	""	Stage 2 approved Q3-2022, full design/tender being prepared.	""	""	""	""
1488	1488	CAS CONSTRUCTION RENEWAL	Waterford	Wadding Manor, Ferrybank	10	Respond	""	""	""	""	""	Q2-2021
1489	1489	CAS CONSTRUCTION	Waterford	Ballycarnane, Tramore	18	Oaklee Housing Trust	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1490	1490	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 1)	26	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2021
1491	1491	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 2)	31	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2022
1492	1492	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 1)	6	Oaklee Housing	""	""	""	""	Q1-2022	""
1493	1493	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 2)*	7	Oaklee Housing	""	""	""	""	Q1-2022	""
1494	1494	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 3)	2	Oaklee Housing	""	""	""	""	Q1-2022	""
1495	1495	CALF Turnkey	Waterford	Sl na Coille, Tramore, Co Waterford (Phase 1)*	27	Clid Housing	""	""	""	""	""	Q3-2022
1496	1496	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 1)	24	*N/A	""	""	""	""	""	Q2-2021
1497	1497	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 2)	34	*N/A	""	""	""	""	""	Q3-2021
1498	1498	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1499	1499	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1500	1500	SHIP DIALOG	Westmeath	Lissywollen, Athlone	38	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1501	1501	SHIP DIALOG	Westmeath	Lissywollen, Athlone	22	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1502	1502	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friars Street, Mullingar	4	*N/A	""	""	""	""	Q3-2020	""
1503	1503	SHIP CONSTRUCTION TURNKEY	Westmeath	Oakcrest, Ballinderry, Mullingar	5	*N/A	""	""	""	""	Q4-2019	""
1504	1504	SHIP CONSTRUCTION TURNKEY	Westmeath	St. Marys Place, Athlone	9	*N/A	""	""	""	""	Q2-2021	""
1505	1505	SHIP CONSTRUCTION TURNKEY	Westmeath	Rathgarve Green, Castlepollard	1	*N/A	""	""	""	""	""	Q2-2021
1506	1506	SHIP CONSTRUCTION TURNKEY	Westmeath	Bellaugh, Athlone	17	*N/A	""	""	""	""	Q2-2021	""
1507	1507	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	7	*N/A	""	""	""	""	""	Q2-2022
1508	1508	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	9	*N/A	""	""	""	""	Q2-2021	""
1509	1509	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	12	*N/A	""	""	""	""	Q2-2021	""
1510	1510	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friar Street, Mullingar	2	*N/A	""	""	""	""	Q1-2022	""
1511	1511	SHIP CONSTRUCTION TURNKEY	Westmeath	Athboy Rd, Delvin	6	*N/A	""	""	""	""	Q1-2022	""
1512	1512	SHIP CONSTRUCTION TURNKEY	Westmeath	Kileenboylegan, Moate	6	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1513	1513	SHIP CONSTRUCTION TURNKEY	Westmeath	Mount Carmel Drive, Moate	9	N/A	""	""	""	""	Q2-2022	""
1514	1514	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friar Street, Mullingar	4	*N/A	""	""	""	Stage 4 approved Q1-2022, the scheme is fully approved.	""	""
1515	1515	SHIP CONSTRUCTION TURNKEY	Westmeath	Oakcrest, Ballinderry, Mullingar	3	*N/A	""	""	""	""	Q4-2019	""
1516	1516	SHIP CONSTRUCTION TURNKEY	Westmeath	Arcadia, Clonbrusk	2	*N/A	""	""	""	""	Q2-2021	""
1517	1517	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	O'Growney Green, Mullingar	22	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1518	1518	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Dalton Park, Mullingar	17	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1519	1519	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Water Street, Castlepollard	8	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1520	1520	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Ennell Court, Mullingar (Phase 1)	15	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1521	1521	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	8	*N/A	""	""	""	""	""	Q2-2021
1522	1522	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	19	*N/A	""	""	""	""	Q2-2021	""
1523	1523	SHIP CONSTRUCTION	Westmeath	Quinlan Park, Athlone	10	*N/A	""	""	""	""	Q4-2021	""
1524	1524	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A	""	""	""	""	""	Q2-2021
1525	1525	SHIP CONSTRUCTION	Westmeath	Arcadia, Athlone (Phase 2)	24	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
1526	1526	SHIP CONSTRUCTION	Westmeath	Canal Avenue, Mullingar	32	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
1527	1527	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	4	*N/A	""	""	""	""	""	Q3-2021
1528	1528	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A	""	""	""	""	""	Q4-2021
1529	1529	SHIP CONSTRUCTION	Westmeath	Cornamaddy, Athlone	50	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1530	1530	SHIP CONSTRUCTION	Westmeath	Water Street, Castlepollard 	1	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1531	1531	SHIP CONSTRUCTION	Westmeath	Belvedere Orphanage, Tyrellspass	6	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1532	1532	SHIP CONSTRUCTION	Westmeath	Cornamaddy, Athlone	58	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1533	1533	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	12	*N/A	""	""	""	""	Q2-2021	""
1534	1534	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	10	Tath Housing Association Ltd	""	""	""	""	""	Q1-2021
1535	1535	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	17	Tath Housing Association Ltd	""	""	""	""	""	Q3-2022
1536	1536	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	9	Tath Housing Association Ltd	""	""	""	""	""	Q3-2022
1537	1537	CAS CONSTRUCTION RENEWAL	Westmeath	The Hermitage Building, Retreat Road, Athlone	55	Tath Housing Association Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1538	1538	CAS CONSTRUCTION	Westmeath	Farran, Mullingar	4	Tath Housing Association Ltd	""	""	""	""	""	Q3-2021
1539	1539	CALF Turnkey	Westmeath	Ashe Road, Mullingar, Co. Westmeath (Phase 1)*	18	Clid Housing	""	""	""	""	Q2-2021	""
1540	1540	CALF Turnkey	Westmeath	Athlone Road, Moate, Co. Westmeath (Phase 1)*	14	Oaklee Housing	""	""	""	""	""	Q2-2021
1541	1541	CALF Turnkey	Westmeath	Bower Hill, Lower Road, Athlone, Co. Westmeath (Phase 1)*	15	Clid Housing	""	""	""	Q3-2021	""	""
1542	1542	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 1)*	37	Respond	""	""	""	""	Q4-2021	""
1543	1543	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 2)*	62	Respond	""	""	""	""	Q4-2021	""
1544	1544	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 2)*	23	Clid Housing	""	""	""	""	""	Q1-2021
1545	1545	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 3)	8	Clid Housing	""	""	""	""	""	Q2-2021
1546	1546	CALF Construction	Westmeath	Farran, Mullingar, Co. Westmeath (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q3-2021
1547	1547	CALF Turnkey	Westmeath	Garran Gael, Kinnegad, Westmeath (Phase 1)*	24	Tuath Housing Association	""	""	""	""	Q4-2020	""
1548	1548	CALF Turnkey	Westmeath	Rahanine, Rochfortbridge, Co Westmeath (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q2-2021
1549	1549	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q1-2021
1550	1550	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 2)	4	Tuath Housing Association	""	""	""	""	""	Q2-2022
1551	1551	SHIP CONSTRUCTION TURNKEY	Wexford	Airhill, Belvedere Rd, Wexford	7	*N/A	""	""	""	""	""	Q3-2021
1552	1552	SHIP CONSTRUCTION TURNKEY	Wexford	Michael Street, New Ross 	3	*N/A	""	""	""	""	""	Q2-2021
1553	1553	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	4	*N/A	""	""	""	""	""	Q2-2022
1554	1554	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	10	*N/A	""	""	""	""	""	Q3-2022
1555	1555	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Gorey - Phase 2	4	*N/A	""	""	""	""	""	Q4-2021
1556	1556	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	5	*N/A	""	""	""	""	""	Q2-2021
1557	1557	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	5	*N/A	""	""	""	""	""	Q4-2021
1558	1558	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	6	*N/A	""	""	""	""	""	Q4-2021
1559	1559	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A	""	""	""	""	""	Q2-2021
1560	1560	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross, Co. Wexford	20	*N/A	""	""	""	""	Q4-2021	""
1561	1561	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	29	*N/A	""	""	""	""	Q4-2020	""
1562	1562	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	12	*N/A	""	""	""	""	Q4-2020	""
1563	1563	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A	""	""	""	""	""	Q2-2022
1564	1564	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	4	*N/A	""	""	""	""	""	Q2-2022
1565	1565	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A	""	""	""	""	""	Q2-2022
1566	1566	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A	""	""	""	""	Q3-2021	""
1567	1567	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A	""	""	""	""	""	Q2-2021
1568	1568	SHIP CONSTRUCTION TURNKEY	Wexford	Clonard Little, Wexford 	9	*N/A	""	""	""	""	Q2-2022	""
1569	1569	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross, Co. Wexford	23	*N/A	""	""	""	""	Q4-2021	""
1570	1570	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	7	*N/A	""	""	""	""	""	Q1-2022
1571	1571	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	4	*N/A	""	""	""	""	""	Q2-2022
1572	1572	SHIP CONSTRUCTION TURNKEY	Wexford	Castlelands, Ferns, Co. Wexford	20	*N/A	""	""	""	""	Q4-2020	""
1573	1573	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	2	*N/A	""	""	""	""	""	Q2-2022
1574	1574	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	4	*N/A	""	""	""	""	Q1-2021	""
1575	1575	SHIP CONSTRUCTION	Wexford	Whiterock Hill Phase 1, Wexford	22	*N/A	""	""	""	""	Q1-2021	""
1576	1576	SHIP CONSTRUCTION	Wexford	Killeens, Wexford	40	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
1577	1577	SHIP CONSTRUCTION	Wexford	Ross Road, Enniscorthy	1	*N/A	""	""	""	""	""	Q4-2021
1578	1578	SHIP CONSTRUCTION	Wexford	Glentire, The Ballagh, Enniscorthy	7	*N/A	""	""	""	""	""	Q3-2022
1579	1579	SHIP CONSTRUCTION	Wexford	Rosetown Phase 1, Rosslare	23	*N/A	""	""	""	""	Q2-2021	""
1580	1580	SHIP CONSTRUCTION	Wexford	Carley's Bridge, Enniscorthy	17	*N/A	""	""	""	""	""	Q1-2022
1581	1581	SHIP CONSTRUCTION	Wexford	Creagh, Gorey	22	*N/A	Stage 1 approved Q2-2018, outline design and costs being prepared.	""	""	""	""	""
1582	1582	SHIP CONSTRUCTION	Wexford	Rosbercon, New Ross	38	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.	""	""	""	""	""
1583	1583	SHIP CONSTRUCTION	Wexford	Wexford Street, Gorey	30	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1584	1584	SHIP CONSTRUCTION	Wexford	Ballyhine, Barntown, Co. Wexford	7	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1585	1585	SHIP CONSTRUCTION	Wexford	Whiterock Hill Phase 2, Wexford	22	*N/A	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
1586	1586	SHIP CONSTRUCTION	Wexford	Rosetown Phase 2, Rosslare	12	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1587	1587	SHIP CONSTRUCTION	Wexford	Doire Moling, Monamolin, Gorey, Co. Wexford	5	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1588	1588	SHIP CONSTRUCTION	Wexford	20 Francis Street, Wexford	2	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1589	1589	SHIP CONSTRUCTION	Wexford	Ballygillane Big, Rosslare Harbour, Co. Wexford	5	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1590	1590	SHIP CONSTRUCTION	Wexford	Grogan?s Road, Wexford Town 	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1591	1591	CAS CONSTRUCTION TURNKEY	Wexford	Clonattin, Gorey	6	Tath Housing Association Ltd	""	""	""	""	""	Q2-2021
1592	1592	CAS CONSTRUCTION TURNKEY	Wexford	2&3 The Quay, New Ross, Co. Wexford	6	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1593	1593	CAS CONSTRUCTION RENEWAL	Wexford	Ard na Naoimh, Gorey Hill	4	St. Aidan's Day Care Centre CLG	Stage 1 approved Q1-2022, outline design and costs being prepared.	""	""	""	""	""
1594	1594	CAS CONSTRUCTION	Wexford	Wexford Women's Refuge, Maudlintown	13	Wexford Womens? Refuge CLG	""	""	Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.	""	""	""
1595	1595	CALF Turnkey	Wexford	67 units, Coolcotts, Wexford (Barr An Aird, Coolcotts) (Phase 1)*	67	Clid Housing	""	""	""	""	Q3-2020	""
1596	1596	CALF Turnkey	Wexford	9 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q2-2021
1597	1597	CALF Turnkey	Wexford	Cuil na Dara, Coolcotts, Wexford  (Phase 1)*	25	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
1598	1598	CALF Turnkey	Wexford	Forgelands, Enniscorthy Co. Wexford. (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q3-2022
1599	1599	CALF Turnkey	Wexford	Forgelands, Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)*	18	Tuath Housing Association	""	""	""	""	""	Q3-2021
1600	1600	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey, Co Wexford (Phase 1)	8	Tuath Housing Association	""	""	""	""	Q3-2021	""
1601	1601	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey, Co Wexford (Phase 2)	16	Tuath Housing Association	""	""	""	""	Q3-2021	""
1602	1602	CALF Construction	Wexford	Hewitsland, New Ross, County Wexford (Phase 1)	48	Clid Housing	""	""	""	Q2-2022	""	""
1603	1603	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 3)	16	Tuath Housing Association	""	""	""	""	""	Q1-2021
1604	1604	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 4)*	27	Tuath Housing Association	""	""	""	""	""	Q2-2021
1605	1605	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 1)	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1606	1606	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 2)*	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2022
1607	1607	CALF Turnkey	Wexford	Moongate, Townspark, Co Wexford (Phase 1)*	17	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
1608	1608	CALF Turnkey	Wexford	Moongate, Townspark, Co Wexford (Phase 2)*	21	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
1609	1609	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 3)*	8	Tuath Housing Association	""	""	""	""	""	Q1-2021
1610	1610	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 4)*	8	Tuath Housing Association	""	""	""	""	""	Q2-2021
1611	1611	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 1)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1612	1612	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 2)	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1613	1613	CALF Turnkey	Wexford	Pirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 1)*	16	Clid Housing	""	""	""	""	""	Q3-2021
1614	1614	CALF Turnkey	Wexford	Pirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 2)*	14	Clid Housing	""	""	""	""	""	Q3-2021
1615	1615	CALF Turnkey	Wexford	Pirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 3)	22	Clid Housing	""	""	""	""	""	Q4-2021
1616	1616	CALF Turnkey	Wexford	"Pairc na Greine, Coolcotts, Wexford phase 2 (Sub phase 2).
 (Phase 1)"	24	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2022	""
1617	1617	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 1)	24	Tuath Housing Association	""	""	""	""	Q2-2021	""
1618	1618	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 2)	20	Tuath Housing Association	""	""	""	""	Q2-2021	""
1619	1619	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 3)*	24	Tuath Housing Association	""	""	""	""	Q2-2021	""
1620	1620	CALF Turnkey	Wexford	Tobar Mhuire, Creagh, Gorey, Wexford (Phase 1)*	17	Clid Housing	""	""	""	""	Q4-2021	""
1621	1621	SHIP CONSTRUCTION TURNKEY	Wicklow	Weaver Square, Baltinglass, Co. Wicklow	2	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
1622	1622	SHIP CONSTRUCTION TURNKEY	Wicklow	The Birches, Ballinaclash	2	*N/A	""	""	""	""	""	Q2-2021
1623	1623	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	2	*N/A	""	""	""	""	""	Q1-2021
1624	1624	SHIP CONSTRUCTION TURNKEY	Wicklow	Vartry Heights, Roundwood, Co. Wicklow	3	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1625	1625	SHIP CONSTRUCTION TURNKEY	Wicklow	Avonmore View, Rathdrum	13	*N/A	""	""	""	""	Q4-2021	""
1626	1626	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	1	*N/A	""	""	""	""	""	Q2-2021
1627	1627	SHIP CONSTRUCTION TURNKEY	Wicklow	95 Waverley Drive, Broomhall, Rathnew	1	*N/A	""	""	""	""	""	Q1-2022
1628	1628	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	3	*N/A	""	""	""	""	""	Q2-2022
1629	1629	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	3	N/A	""	""	""	""	""	Q1-2022
1630	1630	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	1	*N/A	""	""	""	""	""	Q2-2022
1631	1631	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	2	*N/A	""	""	""	""	""	Q2-2022
1632	1632	SHIP CONSTRUCTION SINGLE STAGE	Wicklow	Ballynerrin Upper, Wicklow Town	10	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1633	1633	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Merrymeeting View, Rathnew	46	*N/A	""	""	""	""	""	Q2-2021
1634	1634	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Shillelagh Phase 4	20	*N/A	""	""	""	Stage 4 approved Q2-2022, the scheme is fully approved.	""	""
1635	1635	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Ashtown Lane, Wicklow Town	40	*N/A	""	""	""	""	""	Q2-2022
1636	1636	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Ard na Greine, West Ward, Bray	31	*N/A	""	""	""	""	""	Q1-2022
1637	1637	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Avondale Heights, Rathdrum	20	*N/A	""	""	""	""	Q3-2021	""
1638	1638	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Sheehan Court, Back Street, Arklow	7	*N/A	""	""	""	""	""	Q3-2022
1639	1639	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Mountainview, Moneycarroll, Newtownmountkennedy	22	*N/A	""	""	""	""	""	Q2-2022
1640	1640	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Three Trouts, Greystones	41	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1641	1641	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Greenhill Road, Wicklow Town	36	*N/A	""	""	""	""	Q2-2021	""
1642	1642	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Cedar Court, Schools Road, Bray	14	*N/A	""	""	""	""	Q1-2022	""
1643	1643	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Coolattin Oaks, Carnew (Phase 4)	8	*N/A	""	""	""	""	""	Q1-2021
1644	1644	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Rathnew, Merrymeeting, Co. Wicklow (Phase 2)	21	*N/A	""	""	Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.	""	""	""
1645	1645	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Tinahely, Lugduff, Co Wicklow	20	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1646	1646	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Carrigoona, Bray	15	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
1647	1647	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Lott Lane, Kilcoole	80	*N/A	""	Stage 2 approved Q2-2022, full design/tender being prepared.	""	""	""	""
1648	1648	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow (Phase 3)	10	*N/A	""	""	""	""	""	Q1-2022
1649	1649	SHIP CONSTRUCTION	Wicklow	10A & 10 B Castle Villas, Greystones	2	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1650	1650	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow (Phase 2)	37	*N/A	""	""	""	""	""	Q4-2021
1651	1651	SHIP CONSTRUCTION	Wicklow	Blackhills, Glenealy, Co. Wicklow	2	*N/A	""	""	""	""	Q4-2021	""
1652	1652	SHIP CONSTRUCTION	Wicklow	Age Friendly Apartments at Main St, Kilcoole, Greystones	4	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1653	1653	SHIP CONSTRUCTION	Wicklow	Mill Road, Killincarrig, Greystones	2	*N/A	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1654	1654	SHIP CONSTRUCTION	Wicklow	Carraig Eden, Greysones (Phase 3)	14	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1655	1655	SHIP CONSTRUCTION	Wicklow	Kilbride Lane, Bray (Murphy's Lands)	19	*N/A	""	""	""	""	""	Q2-2021
1656	1656	SHIP CONSTRUCTION	Wicklow	Knockroe, Delgany, Co. Wicklow	2	*N/A	""	""	Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.	""	""	""
1657	1657	SHIP CONSTRUCTION	Wicklow	10A Mill Road, Greystones	2	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1658	1658	SHIP CONSTRUCTION	Wicklow	Mountain View, Blessington, Co.Wicklow	10	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.	""	""	""	""	""
1659	1659	CAS CONSTRUCTION TURNKEY	Wicklow	Rathcoran Square, Baltinglass	8	Peter McVerry Trust Ltd	""	""	""	""	""	Q2-2021
1660	1660	CAS CONSTRUCTION TURNKEY	Wicklow	Aldborough Manor, Hawkins Wood, Greystones, Co. Wicklow	90	Tath Housing Association Ltd	""	""	""	""	Q4-2020	""
1661	1661	CAS CONSTRUCTION SINGLE STAGE	Wicklow	Hollybrook Park, Bray, Co. Wicklow	4	St. John of God Housing Association Ltd	""	""	""	Stage 4 approved Q3-2019, the scheme is fully approved.	""	""
1662	1662	CAS CONSTRUCTION RENEWAL	Wicklow	4 Wyndham Park, Bray, Co. Wicklow	2	DePaul Housing	""	""	""	Stage 4 approved Q3-2022, the scheme is fully approved.	""	""
1663	1663	CALF Turnkey	Wicklow	Adelaide Apartments, St Laurence?s Terrace, Bray, Co. Wicklow (Phase 1)*	18	Respond	""	""	""	""	Q2-2021	""
1664	1664	CALF Turnkey	Wicklow	Aldborough Hall, Hawkins Wood, Greystones, Co. Wicklow (Phase 1)	84	Tuath Housing Association	""	""	""	""	Q2-2021	""
1665	1665	CALF Turnkey	Wicklow	Avondale Grange, Ballygannon, Rathdrum, Co. Wicklow (Phase 1)*	36	Respond	""	""	""	""	Q2-2021	""
1666	1666	CALF Turnkey	Wicklow	Fairgreen Manor, Dunlavin, Co. Wicklow (Phase 1)*	40	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q3-2021
1667	1667	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 1)*	14	Tuath Housing Association	""	""	""	""	Q2-2021	""
1668	1668	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 2)*	30	Tuath Housing Association	""	""	""	""	Q2-2021	""
1669	1669	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 3)*	16	Tuath Housing Association	""	""	""	""	Q2-2021	""
1670	1670	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q2-2022
1671	1671	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 2)	12	Tuath Housing Association	""	""	""	""	""	Q3-2022
1672	1672	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 3)	17	Tuath Housing Association	""	""	""	""	Q2-2021	""
1673	1673	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 4)	18	Tuath Housing Association	""	""	""	""	Q2-2021	""
1674	1674	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 5)	13	Tuath Housing Association	""	""	""	""	Q2-2021	""
1675	1675	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 6)*	17	Tuath Housing Association	""	""	""	""	Q2-2021	""
1676	1676	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)	15	Tuath Housing Association	""	""	""	""	""	Q4-2021
1677	1677	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)	10	Tuath Housing Association	""	""	""	""	""	Q1-2022
1678	1678	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 3)	3	Tuath Housing Association	""	""	""	""	Q4-2020	""
1679	1679	CALF Turnkey	Wicklow	Main Street, Blessington, Co. Wicklow (Phase 1)*	22	Circle Voluntary Housing Association Ltd	""	""	""	Q2-2022	""	""
1680	1680	CALF Turnkey	Wicklow	Main Street, Blessington, Co. Wicklow (Phase 2)*	36	Circle Voluntary Housing Association Ltd	""	""	""	Q2-2022	""	""
1681	1681	CALF Turnkey	Wicklow	Oak Springs, Rathdrum, County Wicklow  (Phase 1)*	5	Tuath Housing Association	""	""	""	""	""	Q3-2022
1682	1682	CALF Turnkey	Wicklow	Phase 2, Southern Cross, Bray, Co. Wicklow (Phase 1)	80	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2020	""
1683	1683	CALF Turnkey	Wicklow	Phase 3, Southern Cross, Bray, Co. Wicklow (Phase 1)*	80	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2020	""
1684	1684	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 2)*	24	Respond	""	""	""	""	""	Q2-2021
1685	1685	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 3)	16	Respond	""	""	""	""	""	Q3-2021
1686	1686	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 1)*"	30	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2022
1687	1687	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 2)*"	18	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2022
1688	1688	CALF Turnkey	Wicklow	The Old Rectory, Blessington, Co. Wicklow (Phase 1)*	45	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
1689	1689	CALF Turnkey	Wicklow	Vartry Wood, Ashford, Co. Wicklow (Phase 1)*	16	Clid Housing	""	""	""	""	Q2-2021	""
1690	1690	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Wicklow	Burgage More, Blessington, Co. Wicklow	106	*N/A	""	Q4-2021	""	""	""	""
1691	1691	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Wicklow	Burnaby, Greystones	80	N/A	Q2-2022	""	""	""	""	""
1692	1692	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Wicklow	Rehillls, Bray	120	N/A	Q2-2022 	""	""	""	""	""