  "fields": [{"id":"_id","type":"int"},{"id":"No_","type":"numeric"},{"id":"Funding Programme","type":"text"},{"id":"LA","type":"text"},{"id":"Scheme/Project Name","type":"text"},{"id":"No_ of Units","type":"numeric"},{"id":"Approved Housing Body","type":"text"},{"id":"Stage 1 Capital Appraisal","type":"text"},{"id":"Stage 2 Pre Planning","type":"text"},{"id":"Stage 3 Pre Tender design","type":"text"},{"id":"Stage 4 Tender Report of Final Turnkey/CALF approval","type":"text"},{"id":"On site","type":"text"},{"id":"Completed","type":"text"}],
  "records": [
    [1,1,"CALF Turnkey","Carlow","7 units, Rivercourt, Carlow (Phase 1)",3,"Co-operative Housing Ireland","","","","","","Q3-2019"],
    [2,2,"CALF Turnkey","Carlow","7 units, Rivercourt, Carlow (Phase 2)",4,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [3,3,"CALF Turnkey","Carlow","Ballickmoyler, Graigcullen, Carlow (Phase 1)",27,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [4,4,"CALF Turnkey","Carlow","Ballickmoyler, Graigcullen, Carlow (Phase 2)",30,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [5,5,"CALF Turnkey","Carlow","Barrett Street, Bagnalstown, Co. Carlow (Phase 1)",10,"Tintean Housing Association Ltd","","","","","","Q1-2018"],
    [6,6,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 1)",15,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [7,7,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 2)",12,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [8,8,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 3)",10,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [9,9,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 4)",6,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [10,10,"CALF Turnkey","Carlow","Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 5)",16,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [11,11,"CALF Turnkey","Carlow","Browneshill Wood, Browneshill Road, Chapelstown, Carlow (Phase 1)",14,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [12,12,"CALF Turnkey","Carlow","Greenhills, Leighlin Road, Graiguecullen, Carlow (Phase 1)",8,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [13,13,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 1)*",8,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [14,14,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 2)",8,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [15,15,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 3)",12,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [16,16,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 4)",9,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [17,17,"CALF Turnkey","Carlow","Rivercourt,  Carlow  (Phase 5)",10,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [18,18,"CALF Turnkey","Carlow","Sli na Ri, Bagnalstown, Co. Carlow (Phase 1)*",19,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [19,19,"CALF Turnkey","Carlow","The Millrace, Burrin, Co. Carlow (Phase 1)*",22,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [20,20,"CALF Turnkey","Carlow","Sleaty Street, Graigcullen, Carlow  (Phase 1)",26,"Cluid Housing","","","","","","Q1-2019"],
    [21,21,"CAS CONSTRUCTION","Carlow","Gleann na Bearu, Royal Oak Road, Bagenalstown",6,"Respond","","","Stage 3 approved Q4-2017, the scheme is now approved to proceed to tender.","","",""],
    [22,22,"CAS CONSTRUCTION","Carlow","Ballincarrig, Wexford Road",6,"Tintean Housing Association Ltd","","","","","","Q4-2016"],
    [23,23,"CAS CONSTRUCTION TURNKEY","Carlow","Pollerton Big, Carlow",6,"Tintean Housing Association Ltd","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [24,24,"SHIP CONSTRUCTION","Carlow","The Laurels, Carlow Town",5,"*N/A","","","","","","Q2-2018"],
    [25,25,"SHIP CONSTRUCTION","Carlow","Ard na Greine, Tullow",16,"*N/A","","","","","","Q4-2018"],
    [26,26,"SHIP CONSTRUCTION","Carlow","Bagenalstown",20,"*N/A","","","","","Q2-2019",""],
    [27,27,"SHIP CONSTRUCTION","Carlow","Bilboa",2,"*N/A","","","","","","Q3-2018"],
    [28,28,"SHIP CONSTRUCTION","Carlow","Slate Row, Hacketstown",4,"*N/A","","","","","","Q4-2018"],
    [29,29,"SHIP CONSTRUCTION","Carlow","Mount Leinster Park, Carlow",4,"*N/A","","","","","","Q4-2017"],
    [30,30,"SHIP CONSTRUCTION","Carlow","Myshall",4,"*N/A","","","","","","Q1-2018"],
    [31,31,"SHIP CONSTRUCTION","Carlow","Pound Lane, Borris",4,"*N/A","","","","","","Q3-2017"],
    [32,32,"SHIP CONSTRUCTION","Carlow","Rathvilly",10,"*N/A","","","","","","Q2-2017"],
    [33,33,"SHIP CONSTRUCTION","Carlow","Moneybeg, Bagenalstown",24,"*N/A","","","","","","Q3-2017"],
    [34,34,"SHIP CONSTRUCTION","Carlow","Paulville, Tullow (SRD)",1,"*N/A","","","","","","Q3-2017"],
    [35,35,"SHIP CONSTRUCTION","Carlow","Maryborough St., Carlow",5,"*N/A","","","","","","Q1-2018"],
    [36,36,"SHIP CONSTRUCTION","Carlow","Drumin, St. Mullins (SRD)",1,"*N/A","","","","","","Q1-2019"],
    [37,37,"SHIP CONSTRUCTION","Carlow","Pound Lane, Borris, Co. carlow",9,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [38,38,"SHIP CONSTRUCTION","Carlow","Courtview, Tullow, Co. Carlow",20,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [39,39,"SHIP CONSTRUCTION","Carlow","Dublin Road, Tullow",21,"*N/A","","","","","","Q3-2019"],
    [40,40,"SHIP CONSTRUCTION","Carlow","Father Flood Avenue, Rathvilly",8,"*N/A","","","","","","Q4-2019"],
    [41,41,"SHIP CONSTRUCTION","Carlow","St. Mary's Court & Dereen Heights",6,"*N/A","","","","","Q3-2019",""],
    [42,42,"SHIP CONSTRUCTION","Carlow","Crowsgrove, Kildavin",1,"*N/A","","","","","Q2-2019",""],
    [43,43,"SHIP CONSTRUCTION","Carlow","Shillelagh Road, Tullow, Co. Carlow",6,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [44,44,"SHIP CONSTRUCTION","Carlow","Ardattin",6,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [45,45,"SHIP CONSTRUCTION","Carlow","Brownbog, Hackettstown",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [46,46,"SHIP CONSTRUCTION","Carlow","Spahill, Borris, Co. Carlow",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [47,47,"SHIP CONSTRUCTION","Carlow","St. Oliver's Crescent, Myshall",4,"*N/A","","","","","","Q4-2019"],
    [48,48,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",6,"*N/A","","","","","","Q3-2019"],
    [49,49,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",6,"*N/A","","","","","","Q3-2019"],
    [50,50,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",8,"*N/A","","","","","Q4-2017",""],
    [51,51,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",12,"*N/A","","","","","Q4-2017",""],
    [52,52,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",12,"*N/A","","","","","Q4-2017",""],
    [53,53,"SHIP CONSTRUCTION TURNKEY","Carlow","Carrigbrook, Tullow Road, Carlow",19,"*N/A","","","","","Q4-2017",""],
    [54,54,"CALF Turnkey","Cavan","16 Units, Fairgreen Park, Mullagh, Co. Cavan (Phase 1)",16,"Clanmil Housing Association Ireland","","","","Q4-2019","",""],
    [55,55,"CALF Turnkey","Cavan","25 units, Drumalee Manor, Drumalee, Co. Cavan (Phase 1)",12,"T�ath Housing Association Ltd","","","","Q3-2019","",""],
    [56,56,"CALF Turnkey","Cavan","25 units, Drumalee Manor, Drumalee, Co. Cavan (Phase 2)",13,"T�ath Housing Association Ltd","","","","Q3-2019","",""],
    [57,57,"CALF Turnkey","Cavan","Cluain Dara, Kingscourt, Co Cavan (Phase 1)",16,"Cluid Housing","","","","","","Q4-2016"],
    [58,58,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 1)",4,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [59,59,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 2)",5,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [60,60,"CALF Turnkey","Cavan","Drumalee Manor, Drumalee, Cavan (Phase 3)",2,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [61,61,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 3)",11,"Co-operative Housing Ireland","","","","","Q1-2019",""],
    [62,62,"CALF Turnkey","Cavan","The Gallops, Cavan Town, Co. Cavan (Phase 1)*",34,"Cluid Housing","","","","","Q4-2019",""],
    [63,63,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 1)",2,"Co-operative Housing Ireland","","","","","","Q3-2019"],
    [64,64,"CALF Turnkey","Cavan","Rampart View, Virginia, Co. Cavan (Phase 2)",6,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [65,65,"CAS CONSTRUCTION TURNKEY","Cavan","Castlemanor Village, Cavan Town",29,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [66,66,"SHIP CONSTRUCTION","Cavan","Butlersbridge",4,"*N/A","","","","","","Q1-2018"],
    [67,67,"SHIP CONSTRUCTION","Cavan","Woodlands, Ballyhaise",8,"*N/A","","","","","","Q4-2018"],
    [68,68,"SHIP CONSTRUCTION","Cavan","Butlersbridge (Phase 1)",2,"*N/A","","","","","","Q2-2017"],
    [69,69,"SHIP CONSTRUCTION","Cavan","Clones Road, Butlersbridge",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [70,70,"SHIP CONSTRUCTION","Cavan","Corstruce, Ballinagh",4,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [71,71,"SHIP CONSTRUCTION","Cavan","Main Street, Mullagh",19,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [72,72,"SHIP CONSTRUCTION","Cavan","Elm Grove, Main St, Cavan Town",13,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [73,73,"SHIP CONSTRUCTION","Cavan","Cavan Road, Ballinagh",15,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [74,74,"SHIP CONSTRUCTION","Cavan","Main St., Butlersbridge",6,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [75,75,"SHIP CONSTRUCTION","Cavan","Cluain Dara, Kingscourt",3,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [76,76,"SHIP CONSTRUCTION","Cavan","Magheranure, Cootehill, Co. Cavan",22,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [77,77,"SHIP CONSTRUCTION","Cavan","Fairymount Close, Kingscourt, Co. Cavan",3,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [78,78,"SHIP CONSTRUCTION","Cavan","St. Bridgets Terrace, Cavan Town (Infill)",12,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [79,79,"SHIP CONSTRUCTION","Cavan","Rosehill, Mullagh (Phase 6)",8,"*N/A","","","","","","Q1-2019"],
    [80,80,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff",3,"*N/A","","","","","","Q4-2019"],
    [81,81,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduff (Phase 2)",4,"*N/A","","","","","Q2-2019",""],
    [82,82,"SHIP CONSTRUCTION TURNKEY","Cavan","Ashgrove, Derrylurgan, Ballyjamesduffy (Phase 3)",7,"*N/A","","","","","Q2-2019",""],
    [83,83,"CALF Construction","Clare","Revised - Bruachlan, Westbury, Co Clare (Phase 1)",22,"Co-operative Housing Ireland","","","","Q1-2017","",""],
    [84,84,"CALF Turnkey","Clare","Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 1)",12,"Cluid Housing","","","","","","Q2-2018"],
    [85,85,"CALF Turnkey","Clare","Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 2)",18,"Cluid Housing","","","","","","Q4-2018"],
    [86,86,"CALF Turnkey","Clare","Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 1)*",2,"Cluid Housing","","","","","Q2-2019",""],
    [87,87,"CALF Turnkey","Clare","Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 2)*",2,"Cluid Housing","","","","","Q2-2019",""],
    [88,88,"CALF Turnkey","Clare","Cluain Fia, Crusheen, Co. Clare (Phase 1)*",2,"Cluid Housing","","","","","Q1-2019",""],
    [89,89,"CALF Turnkey","Clare","Cluain Fia, Crusheen, Co. Clare (Phase 2)*",2,"Cluid Housing","","","","","Q1-2019",""],
    [90,90,"CALF Turnkey","Clare","Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 1)",3,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [91,91,"CALF Turnkey","Clare","Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 1)*",31,"Co-operative Housing Ireland","","","","Q2-2019","",""],
    [92,92,"CALF Turnkey","Clare","Lios Anama, Sixmilebridge, Clare (Phase 1)",28,"Co-operative Housing Ireland","","","","","","Q4-2017"],
    [93,93,"CALF Turnkey","Clare","Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 2)",2,"Co-operative Housing Ireland","","","","","","Q2-2019"],
    [94,94,"CALF Turnkey","Clare","Sycamore Drive, Ennis, Co. Clare (Phase 2)*",2,"Cluid Housing","","","","","Q3-2018",""],
    [95,95,"CALF Turnkey","Clare","Sycamore Drive, Ennis, Co. Clare (Phase 1)*",3,"Cluid Housing","","","","","","Q4-2019"],
    [96,96,"CALF Turnkey","Clare","Tullyvarraga, Shannon, Co. Clare (Phase 1)*",31,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [97,97,"CALF Turnkey","Clare","Tullyvarraga, Shannon, Co. Clare (Phase 2)",16,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [98,98,"CAS CONSTRUCTION","Clare","9 Elmwood, Ballycannon Heights, Meelick",4,"Thomond Housing Association Ltd","","","","","","Q1-2019"],
    [99,99,"CAS CONSTRUCTION","Clare","Cahercalla, Ennis (Phase 2)",15,"Cuan an Chlair Ltd","","","","","Q3-2019",""],
    [100,100,"CAS CONSTRUCTION","Clare","Laurel Lodge, Clare Road, Ennis",3,"Society of Saint Vincent de Paul","","","","","","Q4-2016"],
    [101,101,"CAS CONSTRUCTION","Clare","Monaskeha Heights",4,"Newgrove Housing Association Ltd","","","","","","Q3-2019"],
    [102,102,"CAS CONSTRUCTION","Clare","Roo East",4,"Thomond Housing Association Ltd","","","","","","Q4-2018"],
    [103,103,"CAS CONSTRUCTION","Clare","Teach Rua, Edenvale Ennis",4,"Newgrove Housing Association Ltd","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [104,104,"CAS CONSTRUCTION TURNKEY","Clare","Haggard View, Clarecastle (Phase 2)",2,"Anvers Housing Association Ltd","","","","","","Q2-2018"],
    [105,105,"CAS CONSTRUCTION TURNKEY","Clare","Haggard View, Clarecastle (Phase 1)",2,"Anvers Housing Association Ltd","","","","","","Q1-2018"],
    [106,106,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Clare","Shannon East",51,"*N/A","","","","","Q4-2019",""],
    [107,107,"SHIP CONSTRUCTION","Clare","Feakle",13,"*N/A","","","","","","Q4-2019"],
    [108,108,"SHIP CONSTRUCTION","Clare","Glor Srutha, Knockbrack Lower, Clonlara",9,"*N/A","","","","","","Q4-2019"],
    [109,109,"SHIP CONSTRUCTION","Clare","St Senan's Terrace, Kilrush",3,"*N/A","","","","","","Q4-2019"],
    [110,110,"SHIP CONSTRUCTION","Clare","Roslevan, Ennis",8,"*N/A","","","","","Q2-2019",""],
    [111,111,"SHIP CONSTRUCTION","Clare","Seaview Park, Quilty",18,"*N/A","","","","","Q2-2019",""],
    [112,112,"SHIP CONSTRUCTION","Clare","Ashline, Kilrush Road, Ennis",40,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [113,113,"SHIP CONSTRUCTION","Clare","Miltown Malbay",27,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [114,114,"SHIP CONSTRUCTION","Clare","Doonaun, Tulla",25,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [115,115,"SHIP CONSTRUCTION","Clare","Boheraroan, Newmarket-on-Fergus",18,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [116,116,"SHIP CONSTRUCTION","Clare","Scariff",18,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [117,117,"SHIP CONSTRUCTION","Clare","Kilkee Road, Doonbeg",8,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [118,118,"SHIP CONSTRUCTION","Clare","Tulla Road, Roslevan",8,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [119,119,"SHIP CONSTRUCTION","Clare","Cappagh Lodge, Sixmilebridge",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [120,120,"SHIP CONSTRUCTION","Clare","St. Michaels Place, Kilmihil",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [121,121,"SHIP CONSTRUCTION","Clare","Madden's Terrace, Clarecastle",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [122,122,"SHIP CONSTRUCTION TURNKEY","Clare","River View, School Road, Corofin",2,"*N/A","","","","","","Q4-2018"],
    [123,123,"CALF Construction","Cork City","Green Lane, Blackpool, Cork City (Phase 1)",112,"Cluid Housing","","","","Q2-2019","",""],
    [124,124,"CALF Construction","Cork City","Lr. Glanmire Road & 2 Braemer, Cork (Phase 1)",3,"Galtan Ltd","","","","","","Q1-2018"],
    [125,125,"CALF Construction","Cork City","Lr. Glanmire Road & 2 Braemer, Cork (Phase 2)",3,"Galtan Ltd","","","","","","Q4-2018"],
    [126,126,"CALF Construction","Cork City","Lower Glanmire Road, Cork City (Phase 1)",8,"Galtan Ltd","","","","","","Q4-2019"],
    [127,127,"CALF Turnkey","Cork City","5 units, Shandon Street, Cork (Phase 1)",5,"Circle Voluntary Housing Association Ltd","","","","","","Q3-2019"],
    [128,128,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 2)*",7,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [129,129,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 3)",8,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [130,130,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 4)*",13,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [131,131,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 5)*",11,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [132,132,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 6)",10,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [133,133,"CALF Turnkey","Cork City","Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 1)",4,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [134,134,"CALF Turnkey","Cork City","Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 2)",2,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [135,135,"CALF Turnkey","Cork City","Croppy Boy, Fairhill, Cork (Phase 1)",7,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [136,136,"CALF Turnkey","Cork City","Croppy Boy, Fairhill, Cork (Phase 2)*",14,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [137,137,"CALF Turnkey","Cork City","Hereford Place, Ballymacthomas Street, Cork City (Phase 1)*",19,"Respond","","","","Q4-2019","",""],
    [138,138,"CALF Turnkey","Cork City","Leeside Apartments, Bachelors Quay, Cork City (Phase 1)",72,"Cluid Housing","","","","","","Q4-2018"],
    [139,139,"CALF Turnkey","Cork City","Lios Cara, Rathpeacon, Killeens, Cork (Phase 1)",12,"Cluid Housing","","","","Q4-2019","",""],
    [140,140,"CALF Turnkey","Cork City","Millerd Street, Cork (Phase 1)",25,"Respond","","","","","Q1-2019",""],
    [141,141,"CALF Turnkey","Cork City","North Abbey Street, Cork City  (Phase 1)",6,"Respond","","","","","","Q4-2018"],
    [142,142,"CALF Turnkey","Cork City","Redforge Road, Blackpool, Cork City (Phase 1)*",80,"Respond","","","","Q4-2019","",""],
    [143,143,"CALF Turnkey","Cork City","Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 1)",31,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [144,144,"CALF Turnkey","Cork City","Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 1)*",37,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [145,145,"CALF Turnkey","Cork City","Convent Gardens, Blackrock Villas, Blackrock, Co. Cork (Phase 1)",1,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [146,146,"CALF Turnkey","Cork City","Leeside Apartments, Bachelors Quay, Cork City (Phase 2)",6,"Cluid Housing","","","","","","Q3-2019"],
    [147,147,"CALF Turnkey","Cork City","Maryborough Ridge & Blackrock  Villas\\n (Phase 1)*",57,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [148,148,"CALF Turnkey","Cork City","Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 2)",21,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [149,149,"CALF Turnkey","Cork City","The Meadows (Phase 2) Gurranabraher, Cork City  (Phase 1)",17,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [150,150,"CAS CONSTRUCTION","Cork City","Edel House, Grattan Street",37,"Good Shepherd Services Ltd","","","","","Q2-2019",""],
    [151,151,"CAS CONSTRUCTION","Cork City","Saint Vincent's Convent, Vincent's Ave/St. Mary's Street",20,"Respond","Stage 1 approved Q2-2015, outline design and costs being prepared.","","","","",""],
    [152,152,"CAS CONSTRUCTION","Cork City","Thomas Davis Street (Phase 1)",28,"Respond","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [153,153,"CAS CONSTRUCTION","Cork City","Ceanncora Lawn, Ballinlough",1,"Cork Mental Health Voluntary Housing Association Ltd","","","","","","Q3-2018"],
    [154,154,"CAS CONSTRUCTION","Cork City","St. Joachim & Anne's, Anglesea Street",8,"Simon Community : Cork Simon","","","","","Q3-2019",""],
    [155,155,"CAS CONSTRUCTION","Cork City","27-29 Dublin Street, Blackpool",10,"Respond","","","","","","Q3-2018"],
    [156,156,"REGENERATION","Cork City","Phase 1 B Knocknaheeny",29,"*N/A","","","","","","Q4-2017"],
    [157,157,"REGENERATION","Cork City","Phase 1 C Knocknaheeny",41,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [158,158,"REGENERATION","Cork City","Phase 2 B Knocknaheeny",38,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [159,159,"REGENERATION","Cork City","Phase 2 C Knocknaheeny",24,"*N/A","","","","","Q4-2019",""],
    [160,160,"REGENERATION","Cork City","Foyle Avenue Infill Housing Development, Foyle Avenue, Knocknaheeny, Cork",2,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [161,161,"REGENERATION","Cork City","Ardmore Avenue, Knocknaheeny, Cork",1,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [162,162,"REGENERATION","Cork City","Phase 3 B Knocknaheeny",62,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [163,163,"REGENERATION","Cork City","Phase 2 A Knocknaheeny",47,"*N/A","","","","","","Q4-2019"],
    [164,164,"SHIP CONSTRUCTION","Cork City","Poulavone, Ballincollig",57,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [165,165,"SHIP CONSTRUCTION","Cork City","The Meadows, Knocknacullen",1,"*N/A","","","","","","Q3-2016"],
    [166,166,"SHIP CONSTRUCTION","Cork City","Boyces Street",51,"*N/A","","","Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.","","",""],
    [167,167,"SHIP CONSTRUCTION","Cork City","Shandon Street/John Philpott Curran Street",9,"*N/A","","","","","Q4-2019",""],
    [168,168,"SHIP CONSTRUCTION","Cork City","Churchfield Place East",3,"*N/A","","","","","","Q4-2018"],
    [169,169,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher (Phase 1)",8,"*N/A","","","","","","Q4-2018"],
    [170,170,"SHIP CONSTRUCTION","Cork City","Gerald Griffin Street",42,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [171,171,"SHIP CONSTRUCTION","Cork City","Cappanoole",2,"*N/A","","","","","","Q4-2016"],
    [172,172,"SHIP CONSTRUCTION","Cork City","Madonna House, Ballincollig (Phase 2)",6,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [173,173,"SHIP CONSTRUCTION","Cork City","Bramble Cottages",5,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [174,174,"SHIP CONSTRUCTION","Cork City","Errigal Heights, The Glen, Cork City",20,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [175,175,"SHIP CONSTRUCTION","Cork City","Glenamoy Lawn, Mayfield, Cork",2,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [176,176,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher (Phase 2)",7,"*N/A","","","","","","Q1-2019"],
    [177,177,"SHIP CONSTRUCTION","Cork City","Hollywood Estate Infill Housing, Blarney Road, Cork",7,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [178,178,"SHIP CONSTRUCTION","Cork City","Deanrock, Togher (Phase 3)",50,"*N/A","","","","","","Q3-2019"],
    [179,179,"SHIP CONSTRUCTION","Cork City","Clover Hill Court, Bessboro Road, Mahon, Cork",51,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [180,180,"SHIP CONSTRUCTION","Cork City","Westside, Model Farm Road, Cork",32,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [181,181,"SHIP CONSTRUCTION","Cork City","Gerald Griffin Apartments - Block 7, North Monastery Road / St. Vincent's Road, Cork",6,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [182,182,"SHIP CONSTRUCTION","Cork City","Sli Gartan, Mayfield, Cork ",1,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [183,183,"SHIP CONSTRUCTION","Cork City","St. Johns Well",6,"*N/A","","","","","","Q4-2019"],
    [184,184,"SHIP CONSTRUCTION TURNKEY","Cork City","134A Eagle Valley, Sarsfield Road",1,"*N/A","","","","","","Q4-2019"],
    [185,185,"SHIP CONSTRUCTION TURNKEY","Cork City","3-10 Herbert Lawn, Belmont, Rochestown, Cork",8,"*N/A","","","","","","Q4-2019"],
    [186,186,"SHIP CONSTRUCTION TURNKEY","Cork City","Ard na Ri, Banduff Road, Cork",10,"*N/A","","","","","","Q4-2019"],
    [187,187,"SHIP CONSTRUCTION TURNKEY","Cork City","Ard na Ri, Banduff Road, Cork (Phase 2)",10,"*N/A","","","","","","Q4-2019"],
    [188,188,"SHIP CONSTRUCTION TURNKEY","Cork City","Aspen Drive, Maryborough Hill, Cork ",29,"*N/A","","","","","","Q4-2019"],
    [189,189,"SHIP CONSTRUCTION TURNKEY","Cork City","Ballinlough Road / Knockrea Lawn, Ballinlough, Cork",6,"*N/A","","","","","","Q2-2019"],
    [190,190,"SHIP CONSTRUCTION TURNKEY","Cork City","Blarney Street",25,"*N/A","","","","","","Q4-2019"],
    [191,191,"SHIP CONSTRUCTION TURNKEY","Cork City","Arus Mhuire",30,"*N/A","","","","","","Q4-2018"],
    [192,192,"SHIP CONSTRUCTION TURNKEY","Cork City","Barrack Street",32,"*N/A","","","","Stage 4 approved Q1-2018, the scheme is fully approved.","",""],
    [193,193,"SHIP CONSTRUCTION TURNKEY","Cork City","Elton Wood & Herbert Lawn, Rochestown, Cork ",8,"*N/A","","","","","","Q4-2019"],
    [194,194,"SHIP CONSTRUCTION TURNKEY","Cork City","FaranFerris",5,"*N/A","","","","","","Q4-2019"],
    [195,195,"SHIP CONSTRUCTION TURNKEY","Cork City","Tramore Road",4,"*N/A","","","","","","Q4-2018"],
    [196,196,"SHIP CONSTRUCTION TURNKEY","Cork City","Gearney's Boreen, Commons Road, Cork",3,"*N/A","","","","","","Q4-2019"],
    [197,197,"SHIP CONSTRUCTION TURNKEY","Cork City","Woods Street",16,"*N/A","","","","Stage 4 approved Q1-2018, the scheme is fully approved.","",""],
    [198,198,"SHIP CONSTRUCTION TURNKEY","Cork City","Church Road, Blackrock",43,"*N/A","","","","","","Q3-2018"],
    [199,199,"SHIP CONSTRUCTION TURNKEY","Cork City","1-5, Ard Aoibhinn, Banduff, Mayfield",5,"*N/A","","","","","","Q3-2018"],
    [200,200,"SHIP CONSTRUCTION TURNKEY","Cork City","Corcorans Quay",3,"*N/A","","","","","Q2-2018",""],
    [201,201,"SHIP CONSTRUCTION TURNKEY","Cork City","High Street",9,"*N/A","","","","","","Q4-2019"],
    [202,202,"SHIP CONSTRUCTION TURNKEY","Cork City","Ballinure Road, Cork City",5,"*N/A","","","","Stage 4 approved Q3-2018, the scheme is fully approved.","",""],
    [203,203,"SHIP CONSTRUCTION TURNKEY","Cork City","Moss Lane, Riverway, Cork",5,"*N/A","","","","Stage 4 approved Q3-2018, the scheme is fully approved.","",""],
    [204,204,"SHIP CONSTRUCTION TURNKEY","Cork City","7-11 Gerald Griffin Street, Cork",13,"*N/A","","","","","Q2-2019",""],
    [205,205,"SHIP CONSTRUCTION TURNKEY","Cork City","29/30 Lower John Street, Cork",17,"*N/A","","","","","Q1-2019",""],
    [206,206,"SHIP CONSTRUCTION TURNKEY","Cork City","Skehard Road, Blackrock, Cork",16,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [207,207,"SHIP CONSTRUCTION TURNKEY","Cork City","Coach Street, Cork",13,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [208,208,"SHIP CONSTRUCTION TURNKEY","Cork City","Shanakiel Road, Cork",20,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [209,209,"SHIP CONSTRUCTION TURNKEY","Cork City","Spring Lane, Blackpool, Cork",8,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [210,210,"SHIP CONSTRUCTION TURNKEY","Cork City","Glen Ryan Road, Cork",9,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [211,211,"SHIP CONSTRUCTION TURNKEY","Cork City","1-4 Marble Lane",4,"*N/A","","","","","","Q4-2017"],
    [212,212,"SHIP CONSTRUCTION TURNKEY","Cork City","Sheridan Park, Tramore Road",28,"*N/A","","","","","","Q4-2016"],
    [213,213,"SHIP CONSTRUCTION TURNKEY","Cork City","37-39 Dublin Street, Blackpool, Cork",5,"*N/A","","","","","","Q2-2018"],
    [214,214,"SHIP CONSTRUCTION TURNKEY","Cork City","6-10, Ard Aoibhinn, Banduff, Mayfield",5,"*N/A","","","","","","Q4-2018"],
    [215,215,"SHIP CONSTRUCTION TURNKEY","Cork City","2 Deanrock Cottages, Togher",4,"*N/A","","","","","","Q4-2018"],
    [216,216,"SHIP CONSTRUCTION TURNKEY","Cork City","258 & 259 Blarney Street, Cork",2,"*N/A","","","","","","Q1-2018"],
    [217,217,"SHIP CONSTRUCTION TURNKEY","Cork City","1 & 2 The Groves, Skehard Road, Cork",2,"*N/A","","","","","","Q2-2018"],
    [218,218,"SHIP CONSTRUCTION TURNKEY","Cork City","3B & 9B South Terrace Court, South Terrace, Cork",2,"*N/A","","","","","","Q4-2018"],
    [219,219,"SHIP CONSTRUCTION TURNKEY","Cork City","Sites 3 & 8, Knockfree Cottages, Knockfree Avenue, Glengarriff Road, Fairhill, Cork",2,"*N/A","","","","","","Q4-2019"],
    [220,220,"SHIP CONSTRUCTION TURNKEY","Cork City","Whites Street",43,"*N/A","","","","","","Q4-2019"],
    [221,221,"CALF Construction","Cork County","Duntahane, Fermoy, Co. Cork (Phase 1)",46,"Respond","","","","","Q4-2018",""],
    [222,222,"CALF Construction","Cork County","Firgrove Harrisons lane (Phase 1)",6,"Co-operative Housing Ireland","","","","","","Q4-2017"],
    [223,223,"CALF Construction","Cork County","Post Tender - Radharc An tSaile, Cappagh, Ballynacubby, Kinsale, Co Cork (Phase 1)",40,"Cluid Housing","","","","","Q4-2018",""],
    [224,224,"CALF Turnkey","Cork County","3 units, Mullavale, Castletownroche, Co. Cork (Phase 1)",3,"Respond","","","","","","Q2-2019"],
    [225,225,"CALF Turnkey","Cork County","Beach Road, Passage West, Co. Cork (Phase 1)",3,"Cluid Housing","","","","","","Q4-2017"],
    [226,226,"CALF Turnkey","Cork County","Brookhill, Carrigaline, Co. Cork (Phase 1)*",31,"Co-operative Housing Ireland","","","","","Q4-2018",""],
    [227,227,"CALF Turnkey","Cork County","Brookhill, Carrigaline, Co. Cork (Phase 2)",8,"Co-operative Housing Ireland","","","","","Q4-2018",""],
    [228,228,"CALF Turnkey","Cork County","Codrum, Macroom, Co. Cork (Phase 1)",5,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [229,229,"CALF Turnkey","Cork County","College Manor, Cobh (Phase 1)",10,"T�ath Housing Association Ltd","","","","","","Q4-2016"],
    [230,230,"CALF Turnkey","Cork County","Coolroe, Ballincollig, Co. Cork (Phase 1)*",44,"Respond","","","","","Q3-2019",""],
    [231,231,"CALF Turnkey","Cork County","Market Green, Knockgriffin, Midleton, Co. Cork (Phase 2)*",22,"Respond","","","","","Q4-2018",""],
    [232,232,"CALF Turnkey","Cork County","Mullavale, Castletownroche, Co. Cork (Phase 1)",6,"Respond","","","","","","Q4-2018"],
    [233,233,"CALF Turnkey","Cork County","Ticknock, Cobh, Cork (Phase 1)",8,"Respond","","","","","","Q4-2018"],
    [234,234,"CALF Turnkey","Cork County","Brookhill (5 Units), Carrigaline, Cork (Phase 1)",5,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [235,235,"CALF Turnkey","Cork County","Weston, Carrigaline, Co. Cork (Phase 1)",7,"Respond","","","","","","Q2-2018"],
    [236,236,"CALF Turnkey","Cork County","Market Green, Knockgriffin, Midleton, Co. Cork (Phase 1)",20,"Respond","","","","","","Q4-2019"],
    [237,237,"CALF Turnkey","Cork County","Tanners Field, Bandon, Co Cork  (Phase 1)",11,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [238,238,"CALF Turnkey","Cork County","Togher Cross, Lehenaghmore, Co. Cork (Phase 1)",9,"Cluid Housing","","","","","","Q4-2019"],
    [239,239,"CAS CONSTRUCTION","Cork County","Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay",16,"Cluid Housing Association","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [240,240,"CAS CONSTRUCTION","Cork County","Cuan Barra, Kilmore, Ballingeary",3,"Coiste Tithe Uibh Laoire Teoranta","","","","","","Q3-2018"],
    [241,241,"CAS CONSTRUCTION","Cork County","Avenue House, Bandon",9,"Bandon Geriatric ? Community Council","","","","","","Q1-2018"],
    [242,242,"CAS CONSTRUCTION","Cork County","Caim Hill, Townlands, Rosscarbery",9,"Rosscarbery Housing Association Ltd","","","","","","Q1-2019"],
    [243,243,"CAS CONSTRUCTION","Cork County","Fellowship House, Togher",31,"Tabor Lodge Addiction ? Housing Services Ltd","","","","","","Q2-2018"],
    [244,244,"CAS CONSTRUCTION","Cork County","Care Home Facility, Masseytown, Macroom",1,"T�ath Housing Association Ltd","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [245,245,"CAS CONSTRUCTION","Cork County","Baile Bhuire, Macroom",3,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [246,246,"CAS CONSTRUCTION","Cork County","Charleville, Church View, Love Lane, Charleville",8,"Charleville Care Project Ltd","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [247,247,"CAS CONSTRUCTION","Cork County","St. Michaels, 36 Main Street, Bandon, Co. Cork",6,"Bandon Geriatric ? Community Council","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [248,248,"CAS CONSTRUCTION","Cork County","Church View, Love Lane, Charleville",4,"Charleville Care Project Ltd","","","","","","Q4-2019"],
    [249,249,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","The Miles, Clonakilty",52,"*N/A","","","","","Q4-2019",""],
    [250,250,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Poundhill, Skibbereen",50,"*N/A","","","","","Q4-2019",""],
    [251,251,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Cork County","Oakwood, Macroom",50,"*N/A","","","","","Q4-2019",""],
    [252,252,"SHIP CONSTRUCTION","Cork County","Abbeywood, Midleton",70,"*N/A","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [253,253,"SHIP CONSTRUCTION","Cork County","Ard Na Greine, Cortmacsherry",17,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [254,254,"SHIP CONSTRUCTION","Cork County","Station Road, Blarney",18,"*N/A","","","","","Q3-2019",""],
    [255,255,"SHIP CONSTRUCTION","Cork County","Bluepool, Kanturk",12,"*N/A","","","","","Q4-2019",""],
    [256,256,"SHIP CONSTRUCTION","Cork County","Beechgrove, Clonakilty",57,"*N/A","","","","","Q3-2019",""],
    [257,257,"SHIP CONSTRUCTION","Cork County","Newtown House , Bantry",1,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [258,258,"SHIP CONSTRUCTION","Cork County","Fairfield, Masseytown, Macroom",7,"*N/A","","","","","","Q4-2018"],
    [259,259,"SHIP CONSTRUCTION","Cork County","12 & 14 Droum, Castletownbere",2,"*N/A","","","","","","Q4-2018"],
    [260,260,"SHIP CONSTRUCTION","Cork County","Kilnagleary, Carrigaline (Phase 4)",15,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [261,261,"SHIP CONSTRUCTION","Cork County","Oliver Plunkett Hill, Fermoy",10,"*N/A","","","","","","Q2-2017"],
    [262,262,"SHIP CONSTRUCTION","Cork County","Townsend Street, Skibbereen",6,"*N/A","","","","","Q3-2019",""],
    [263,263,"SHIP CONSTRUCTION","Cork County","Forest View, Mallow",10,"*N/A","","","","","Q4-2019",""],
    [264,264,"SHIP CONSTRUCTION","Cork County","11/10 Harbour Hill, Cobh",1,"*N/A","","","","","","Q2-2018"],
    [265,265,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline",10,"*N/A","","","","","","Q4-2018"],
    [266,266,"SHIP CONSTRUCTION","Cork County","Kearney's field Dunmanway",5,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [267,267,"SHIP CONSTRUCTION","Cork County","Richmond Court, Bandon",6,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [268,268,"SHIP CONSTRUCTION","Cork County","Brigown Road, Mitchelstown",8,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [269,269,"SHIP CONSTRUCTION","Cork County","Sleaveen Sleaveen East, Macroom",8,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [270,270,"SHIP CONSTRUCTION","Cork County","Kilnagleary, Carrigaline Phase 1B",5,"*N/A","","","","","","Q4-2018"],
    [271,271,"SHIP CONSTRUCTION","Cork County","Pound Lane, Kilworth ",6,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [272,272,"SHIP CONSTRUCTION","Cork County","24 Glenview Terrace Lyre Co Cork",1,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [273,273,"SHIP CONSTRUCTION","Cork County","Broomfield West, Avoncore, Midelton",10,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [274,274,"SHIP CONSTRUCTION","Cork County","Uplands (Phase 2), College Road,  Fermoy",11,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [275,275,"SHIP CONSTRUCTION","Cork County","Lissoran, Ballinspittle",4,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [276,276,"SHIP CONSTRUCTION","Cork County","Tower View/C�irt na Sil�n�, Cloyne, East Cork - Phase 2",2,"*N/A","","","","Stage 4 approved Q2-2018, the scheme is fully approved.","",""],
    [277,277,"SHIP CONSTRUCTION","Cork County","Convent Road, Doneraile",17,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [278,278,"SHIP CONSTRUCTION","Cork County","Kearney's field Dunmanway",13,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [279,279,"SHIP CONSTRUCTION","Cork County","Downeen Cross, Rosscarbery",7,"*N/A","","","","","","Q4-2019"],
    [280,280,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline (Phase 1A & 1B (ii))",16,"*N/A","","","","","","Q1-2019"],
    [281,281,"SHIP CONSTRUCTION","Cork County","Kilnagleary Carrigaline (Phase 1C)",18,"*N/A","","","","","","Q1-2019"],
    [282,282,"SHIP CONSTRUCTION","Cork County","Tower View/C�irt na Sil�n�, Cloyne, East Cork Phase 1",7,"*N/A","","","","","","Q3-2019"],
    [283,283,"SHIP CONSTRUCTION","Cork County","Tudor Grove, Ballincollig",16,"*N/A","","","","","","Q4-2019"],
    [284,284,"SHIP CONSTRUCTION","Cork County","Castletreasure Grove, Douglas",2,"*N/A","","","","","","Q4-2019"],
    [285,285,"SHIP CONSTRUCTION","Cork County","Model Village, Dripsey",6,"*N/A","","","","","Q2-2019",""],
    [286,286,"SHIP CONSTRUCTION","Cork County","Seaview Cottages, Derrymihan, Castletownbere",3,"*N/A","","","","","Q3-2019",""],
    [287,287,"SHIP CONSTRUCTION","Cork County","Knocknagown, Rylane",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [288,288,"SHIP CONSTRUCTION","Cork County","Thomas Kent Street, Cobh",1,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [289,289,"SHIP CONSTRUCTION","Cork County","Curraleigh, Inniscarra",1,"*N/A","","","","","","Q3-2019"],
    [290,290,"SHIP CONSTRUCTION TURNKEY","Cork County","An Tui, Lisgoold, Leamlara",3,"*N/A","","","","","","Q4-2019"],
    [291,291,"SHIP CONSTRUCTION TURNKEY","Cork County","Baltimore, West Cork",12,"*N/A","","","","","","Q4-2019"],
    [292,292,"SHIP CONSTRUCTION TURNKEY","Cork County","Beacon Point, Baltimore",6,"*N/A","","","","","","Q2-2019"],
    [293,293,"SHIP CONSTRUCTION TURNKEY","Cork County","Bruhenny, Churchtown",6,"*N/A","","","","","","Q4-2019"],
    [294,294,"SHIP CONSTRUCTION TURNKEY","Cork County","Chapel Court, Skibbereen",2,"*N/A","","","","","","Q4-2019"],
    [295,295,"SHIP CONSTRUCTION TURNKEY","Cork County","Chapel Court, Skibbereen",3,"*N/A","","","","","","Q4-2019"],
    [296,296,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas",9,"*N/A","","","","","","Q2-2019"],
    [297,297,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas Phase 2",14,"*N/A","","","","","","Q4-2019"],
    [298,298,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Ard, Cobh",6,"*N/A","","","","","","Q3-2019"],
    [299,299,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Ard, Freemount",4,"*N/A","","","","","","Q4-2019"],
    [300,300,"SHIP CONSTRUCTION TURNKEY","Cork County","Church Road/Station Road, Carrigtwohill",18,"*N/A","","","","","","Q2-2018"],
    [301,301,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis Alainn & Castleoaks, Bandon",11,"*N/A","","","","","","Q4-2017"],
    [302,302,"SHIP CONSTRUCTION TURNKEY","Cork County","Gleann Tuairigh, Youghal",3,"*N/A","","","","","","Q4-2018"],
    [303,303,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",2,"*N/A","","","","","","Q3-2019"],
    [304,304,"SHIP CONSTRUCTION TURNKEY","Cork County","Clondulane, Fermoy",2,"*N/A","","","","","","Q4-2017"],
    [305,305,"SHIP CONSTRUCTION TURNKEY","Cork County","College Wood, Cobh",31,"*N/A","","","","","","Q4-2017"],
    [306,306,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas (Phase 3)",12,"*N/A","","","","","","Q4-2017"],
    [307,307,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",7,"*N/A","","","","","","Q4-2019"],
    [308,308,"SHIP CONSTRUCTION TURNKEY","Cork County","CulAird Carraigtwohill",29,"*N/A","","","","","","Q4-2017"],
    [309,309,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas",12,"*N/A","","","","","","Q1-2017"],
    [310,310,"SHIP CONSTRUCTION TURNKEY","Cork County","Castletreasure, Douglas (Phase 2)",16,"*N/A","","","","","","Q1-2017"],
    [311,311,"SHIP CONSTRUCTION TURNKEY","Cork County","Claragh Road, Millstreet",5,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [312,312,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Mary�s Road, Dunmanway Phase 2",7,"*N/A","","","","","Q3-2018",""],
    [313,313,"SHIP CONSTRUCTION TURNKEY","Cork County","Glanworth, Fermoy",10,"*N/A","","","","Stage 4 approved Q1-2018, the scheme is fully approved.","",""],
    [314,314,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Reidh, Ballyvourney",1,"*N/A","","","","","","Q4-2019"],
    [315,315,"SHIP CONSTRUCTION TURNKEY","Cork County","Corrin View, Fermoy",6,"*N/A","","","","","","Q2-2019"],
    [316,316,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy",4,"*N/A","","","","","","Q4-2019"],
    [317,317,"SHIP CONSTRUCTION TURNKEY","Cork County","No. 43 & No. 50 Chapel Court, Skibbereen ",2,"*N/A","","","","","","Q3-2018"],
    [318,318,"SHIP CONSTRUCTION TURNKEY","Cork County","Cul Na Smear, Bandon",14,"*N/A","","","","","","Q4-2018"],
    [319,319,"SHIP CONSTRUCTION TURNKEY","Cork County","Glen Dara, Ard Cashel, Watergrasshill",6,"*N/A","","","","","","Q4-2018"],
    [320,320,"SHIP CONSTRUCTION TURNKEY","Cork County","Sweetfields, Youghal",15,"*N/A","","","","","Q1-2019",""],
    [321,321,"SHIP CONSTRUCTION TURNKEY","Cork County","Lismire",4,"*N/A","","","","","","Q4-2018"],
    [322,322,"SHIP CONSTRUCTION TURNKEY","Cork County","Rylane, Mount Rivers, Co. Cork.",3,"*N/A","","","","Stage 4 approved Q2-2018, the scheme is fully approved.","",""],
    [323,323,"SHIP CONSTRUCTION TURNKEY","Cork County","Clarendon Brooks, Carrs Hill, Douglas Phase 3",21,"*N/A","","","","","Q1-2019",""],
    [324,324,"SHIP CONSTRUCTION TURNKEY","Cork County","Seafield, Bantry, ",3,"*N/A","","","","","Q3-2018",""],
    [325,325,"SHIP CONSTRUCTION TURNKEY","Cork County","Eyeries, Castletownbere",6,"*N/A","","","","","Q2-2019",""],
    [326,326,"SHIP CONSTRUCTION TURNKEY","Cork County","Parklands, Youghal",13,"*N/A","","","","","","Q4-2018"],
    [327,327,"SHIP CONSTRUCTION TURNKEY","Cork County","Fairgreen, Mallow",10,"*N/A","","","","","","Q4-2019"],
    [328,328,"SHIP CONSTRUCTION TURNKEY","Cork County","No.9 and No.10  Chapel Court, Skibbereen,",2,"*N/A","","","","","","Q4-2018"],
    [329,329,"SHIP CONSTRUCTION TURNKEY","Cork County","Tir Cluain, Midleton",8,"*N/A","","","","","","Q4-2018"],
    [330,330,"SHIP CONSTRUCTION TURNKEY","Cork County","College Mews, Cobh",6,"*N/A","","","","","","Q4-2018"],
    [331,331,"SHIP CONSTRUCTION TURNKEY","Cork County","Rathcormac",4,"*N/A","","","","","","Q4-2018"],
    [332,332,"SHIP CONSTRUCTION TURNKEY","Cork County","Gleann Orga, Ballinhassig",4,"*N/A","","","","","","Q4-2019"],
    [333,333,"SHIP CONSTRUCTION TURNKEY","Cork County","Glenbeg The Beeches, Boherbue",4,"*N/A","","","","","","Q4-2019"],
    [334,334,"SHIP CONSTRUCTION TURNKEY","Cork County","Church Road/Station Road, Carrigtwohill (2)",7,"*N/A","","","","","","Q3-2018"],
    [335,335,"SHIP CONSTRUCTION TURNKEY","Cork County","Percival St, Kanturk",2,"*N/A","","","","","","Q4-2018"],
    [336,336,"SHIP CONSTRUCTION TURNKEY","Cork County","9 & 9a Main Street, Boherbue",2,"*N/A","","","","","","Q4-2018"],
    [337,337,"SHIP CONSTRUCTION TURNKEY","Cork County","Glengarriff",5,"*N/A","","","","","","Q4-2019"],
    [338,338,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis F�il, Curraclough, Bandon",13,"*N/A","","","","","","Q4-2019"],
    [339,339,"SHIP CONSTRUCTION TURNKEY","Cork County","Maple Woods, Midleton",6,"*N/A","","","","","","Q4-2018"],
    [340,340,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy - Phase 3",8,"*N/A","","","","","Q4-2017",""],
    [341,341,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Mary's Road, Dunmanway Phase 3",6,"*N/A","","","","","Q4-2018",""],
    [342,342,"SHIP CONSTRUCTION TURNKEY","Cork County","Sweetfields, Youghal, Phase 2",20,"*N/A","","","","","Q1-2019",""],
    [343,343,"SHIP CONSTRUCTION TURNKEY","Cork County","Copper Point, Schull, Co. Cork",7,"*N/A","","","","","Q2-2019",""],
    [344,344,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore, Bloomfield, Midleton",10,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [345,345,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore,  Broomfield, Midleton - Phase 2",8,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [346,346,"SHIP CONSTRUCTION TURNKEY","Cork County","Mill Road, Avoncore,  Bloomfield, Midleton - Phase 3",22,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [347,347,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow ",52,"*N/A","","","","","Q1-2019",""],
    [348,348,"SHIP CONSTRUCTION TURNKEY","Cork County","Lios Ard BallyHooly",20,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [349,349,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk",11,"*N/A","","","","","","Q4-2019"],
    [350,350,"SHIP CONSTRUCTION TURNKEY","Cork County","Oliver Plunkett Place, Doneraile",2,"*N/A","","","","","","Q4-2019"],
    [351,351,"SHIP CONSTRUCTION TURNKEY","Cork County","Parklands, Youghal - Phase 2",6,"*N/A","","","","","","Q2-2019"],
    [352,352,"SHIP CONSTRUCTION TURNKEY","Cork County","Quartertown, Mallow",5,"*N/A","","","","","","Q4-2019"],
    [353,353,"SHIP CONSTRUCTION TURNKEY","Cork County","Rathcormac Phase 2",4,"*N/A","","","","","","Q2-2019"],
    [354,354,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",8,"*N/A","","","","","","Q4-2019"],
    [355,355,"SHIP CONSTRUCTION TURNKEY","Cork County","Copper Point, Schull, Co. Cork",7,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [356,356,"SHIP CONSTRUCTION TURNKEY","Cork County","Spa Glen,Ballyviniter, Mallow",8,"*N/A","","","","","","Q3-2019"],
    [357,357,"SHIP CONSTRUCTION TURNKEY","Cork County","Millstreet Road, Macroom",12,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [358,358,"SHIP CONSTRUCTION TURNKEY","Cork County","St. Mary�s Road, Dunmanway ",7,"*N/A","","","","","","Q4-2019"],
    [359,359,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road, Carrigtwohill",12,"*N/A","","","","","Q2-2019",""],
    [360,360,"SHIP CONSTRUCTION TURNKEY","Cork County","The Court, Ard Cashel, Watergrasshill",4,"*N/A","","","","","","Q4-2019"],
    [361,361,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk - Phase 3",4,"*N/A","","","","","Q3-2018",""],
    [362,362,"SHIP CONSTRUCTION TURNKEY","Cork County","An Tui, Lisgoold, Leamlara, Co. Cork",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [363,363,"SHIP CONSTRUCTION TURNKEY","Cork County","The Cove, Glandore",4,"*N/A","","","","","","Q4-2019"],
    [364,364,"SHIP CONSTRUCTION TURNKEY","Cork County","Ard Bhaile, Buttevant, Co. Cork",6,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [365,365,"SHIP CONSTRUCTION TURNKEY","Cork County","Cecilstown, Mallow, Co. Cork",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [366,366,"SHIP CONSTRUCTION TURNKEY","Cork County","Ballymacmoy, Killavullen, Co. Cork",13,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [367,367,"SHIP CONSTRUCTION TURNKEY","Cork County","Tir Cluain, Midleton (Phase 2)",14,"*N/A","","","","","","Q3-2019"],
    [368,368,"SHIP CONSTRUCTION TURNKEY","Cork County","Gortnaclohy, Skibbereen, Co. Cork",34,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [369,369,"SHIP CONSTRUCTION TURNKEY","Cork County","Castle Heights, Carrigaline",3,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [370,370,"SHIP CONSTRUCTION TURNKEY","Cork County","Millview Road, Kanturk - Phase 2",10,"*N/A","","","","","Q3-2018",""],
    [371,371,"SHIP CONSTRUCTION TURNKEY","Cork County","Glenbeg, The Beeches, Boherbue",8,"*N/A","","","","","Q1-2019",""],
    [372,372,"SHIP CONSTRUCTION TURNKEY","Cork County","Fairgreen, Mallow ",2,"*N/A","","","","Stage 4 approved Q3-2018, the scheme is fully approved.","",""],
    [373,373,"SHIP CONSTRUCTION TURNKEY","Cork County","Oliver Plunkett Place, Doneraile",4,"*N/A","","","","","Q3-2018",""],
    [374,374,"SHIP CONSTRUCTION TURNKEY","Cork County","Crann Ard, Fermoy - Phase 2",40,"*N/A","","","","","Q4-2017",""],
    [375,375,"SHIP CONSTRUCTION TURNKEY","Cork County","Inis F�il, Curraclough, Bandon",17,"*N/A","","","","","Q4-2018",""],
    [376,376,"SHIP CONSTRUCTION TURNKEY","Cork County","Cluain Cairn, Station Road Carrigtwohill",7,"*N/A","","","","","Q2-2019",""],
    [377,377,"CALF Construction","DLR","Abbeyview House, Monkstown, Dublin (Phase 1)",11,"Cluid Housing","","","","","Q3-2019",""],
    [378,378,"CALF Construction","DLR","Cromlech Fields, Loughlinstown, Ballybrack, Dublin (Phase 1)",34,"Co-operative Housing Ireland","","","","Q1-2019","",""],
    [379,379,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 18 (Phase 1)",53,"Respond","","","","","Q3-2019",""],
    [380,380,"CALF Construction","DLR","Enniskerry Road, Sandyford, Dublin 19, (Phase 1)",52,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [381,381,"CALF Turnkey","DLR","Ardilea Crescent, Clonskeagh, Dublin 14 (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [382,382,"CALF Turnkey","DLR","Belarmine Drive, Belarmine, Stepaside, Dublin 18 (Phase 1)*",6,"Cluid Housing","","","","","","Q4-2019"],
    [383,383,"CALF Turnkey","DLR","Bishops Gate, Enniskerry Rd., Dublin 18 (Phase 1)*",4,"Cluid Housing","","","","","","Q4-2019"],
    [384,384,"CALF Turnkey","DLR","Bishops Gate, Kilternan, Dublin 18  (Phase 1)*",4,"Cluid Housing","","","","","","Q3-2018"],
    [385,385,"CALF Turnkey","DLR","Bishops Gate, Kilternan, Dublin 18  (Phase 2)*",2,"Cluid Housing","","","","","","Q3-2018"],
    [386,386,"CALF Turnkey","DLR","Block C, Abbey Road, Monkstown, (Phase 1)*",3,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [387,387,"CALF Turnkey","DLR","Clay Farm (Block E3), Ballyogan Road, Leopardstown, Dublin 18 (Phase 1)*",24,"The Iveagh Trust","","","","","","Q4-2019"],
    [388,388,"CALF Turnkey","DLR","Clays Farm, Ballyogan Road (Phase 1)  (Phase 1)*",44,"The Iveagh Trust","","","","","","Q2-2019"],
    [389,389,"CALF Turnkey","DLR","Eustace Court, Upper Glenageary Road, Dun Laoghaire, Rathdown, Co. Dublin (Phase 1)",4,"St John of God Housing Association Ltd","","","","","","Q4-2019"],
    [390,390,"CALF Turnkey","DLR","Garrison Mews, The Ramparts, Cabinteely, Co. Dublin (Phase 1)*",5,"Focus Housing Association CLG","","","","Q4-2019","",""],
    [391,391,"CALF Turnkey","DLR","Greenbank House, Upper Glenageary Road, Dun Laoghaire, Co. Dublin (Phase 1)",1,"St John of God Housing Association Ltd","","","","","","Q4-2018"],
    [392,392,"CALF Turnkey","DLR","Hyde Road, Belmont, Stepaside, Co. Dublin (Phase 1)*",8,"Respond","","","","","","Q4-2018"],
    [393,393,"CALF Turnkey","DLR","Johnstown Court, Cabinteely, Dun Laoghaire (Phase 1)",51,"Cluid Housing","","","","","Q2-2019",""],
    [394,394,"CALF Turnkey","DLR","Knockrabo, Mount Anville Road, Goatstown, Dublin 14 (Phase 1)*",6,"Oaklee Housing","","","","","Q3-2016",""],
    [395,395,"CALF Turnkey","DLR","Marine Walk, Marine Road, Dun Laoghaire (Phase 1)*",2,"Oaklee Housing","","","","Q1-2019","",""],
    [396,396,"CALF Turnkey","DLR","Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 1)*",18,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [397,397,"CALF Turnkey","DLR","Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 2)*",14,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [398,398,"CALF Turnkey","DLR","Our Ladys Grove, Goatstown, Dublin 14 (Phase 1)*",2,"Respond","","","","","","Q4-2018"],
    [399,399,"CALF Turnkey","DLR","Rockville Hall, Glenamuck Road, Dunlaoghaire, Dublin 18 (Phase 1)*",12,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [400,400,"CALF Turnkey","DLR","Stillorgan Gate, Kilmacud Road Upper, Co Dublin  (Phase 1)*",4,"Cluid Housing","","","","","","Q4-2017"],
    [401,401,"CALF Turnkey","DLR","Stillorgan Gate, Kilmacud Road Upper, Stillorgan, Co. Dublin (Phase 1)*",2,"Cluid Housing","","","","","","Q4-2018"],
    [402,402,"CALF Turnkey","DLR","The Avenue, Glenside,  Carrickmines Green, Dublin 18 (Phase 1)*",5,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [403,403,"CALF Turnkey","DLR","Whinsfield, Sandyford Road, Dublin 18 (Phase 1)",59,"Respond","","","","Q4-2019","",""],
    [404,404,"CALF Turnkey","DLR","Woodbank, Dublin Rd, Shankill, Co Dublin  (Phase 1)*",4,"Cluid Housing","","","","","","Q3-2017"],
    [405,405,"CAS CONSTRUCTION","DLR","30 Obelisk Walk, Blackrock",4,"St. John of God Housing Association Ltd","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [406,406,"SHIP CONSTRUCTION","DLR","Rockville Drive (Glenamuck Cottages)",13,"*N/A","","Stage 2 approved Q4-2016, full design/tender being prepared.","","","",""],
    [407,407,"SHIP CONSTRUCTION","DLR","132 Pottery Road, Dun Laoghaire",4,"*N/A","","","","","","Q3-2018"],
    [408,408,"SHIP CONSTRUCTION","DLR","Temple Road",3,"*N/A","","","","","","Q2-2018"],
    [409,409,"SHIP CONSTRUCTION","DLR","Assistant Harbour Master House",2,"*N/A","","","","","","Q3-2017"],
    [410,410,"SHIP CONSTRUCTION","DLR","The Brambles Park Close Sallynoggin",10,"*N/A","","","","","","Q2-2018"],
    [411,411,"SHIP CONSTRUCTION","DLR","49 The Mews Sallynoggin Park",4,"*N/A","","","","","","Q4-2017"],
    [412,412,"SHIP CONSTRUCTION","DLR","Shanganagh Park Lodge",1,"*N/A","","","","","","Q2-2016"],
    [413,413,"SHIP CONSTRUCTION","DLR","Rosemount Court",44,"*N/A","","","","","","Q4-2018"],
    [414,414,"SHIP CONSTRUCTION","DLR","Broadford Rise",21,"*N/A","","","","","Q3-2017",""],
    [415,415,"SHIP CONSTRUCTION","DLR","Fitzgerald Park",33,"*N/A","","","","","","Q4-2018"],
    [416,416,"SHIP CONSTRUCTION","DLR","Rochestown House (Phase 3)",14,"*N/A","","","","","","Q3-2018"],
    [417,417,"SHIP CONSTRUCTION","DLR","St Michael's Terrace",4,"*N/A","","","","","","Q3-2017"],
    [418,418,"SHIP CONSTRUCTION","DLR","Clontibret House",4,"*N/A","","","","","","Q4-2016"],
    [419,419,"SHIP CONSTRUCTION","DLR","Cromlech Close",15,"*N/A","","","","","","Q3-2016"],
    [420,420,"SHIP CONSTRUCTION","DLR","Rochestown House (Phase 2)",34,"*N/A","","","","","","Q3-2016"],
    [421,421,"SHIP CONSTRUCTION","DLR","Ballyogan Avenue, Ballyogan",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [422,422,"SHIP CONSTRUCTION","DLR","St. Laurence�s Park, Stillorgan",89,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [423,423,"SHIP CONSTRUCTION","DLR","Fitzgerald Park - Phase 2",17,"*N/A","","","","","","Q1-2019"],
    [424,424,"SHIP CONSTRUCTION","DLR","Ballyogan Court, Ballyogan",67,"*N/A","","Stage 2 approved Q4-2018, full design/tender being prepared.","","","",""],
    [425,425,"SHIP CONSTRUCTION","DLR","Moyola Court, Churchtown Lower, Dublin 14",4,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [426,426,"SHIP CONSTRUCTION TURNKEY","DLR","Hazelbrook, Nutgrove, Churchtown",28,"*N/A","","","","","","Q4-2017"],
    [427,427,"SHIP CONSTRUCTION TURNKEY","DLR","Dunedin Terrace, Monkstown",14,"*N/A","","","","","","Q4-2018"],
    [428,428,"SHIP CONSTRUCTION RAPID","DLR","George's Place",12,"*N/A","","","","","","Q2-2018"],
    [429,429,"CALF Construction","Donegal","Post Tender - Ernedale Ballyshannon (Phase 1)",11,"Cluid Housing","","","","","","Q4-2018"],
    [430,430,"CALF Construction","Donegal","Raphoe Road, Castlefinn, Co. Donegal (Phase 1)",10,"Habinteg Housing Association (Ireland) Ltd","","","","Q2-2018","",""],
    [431,431,"CALF Turnkey","Donegal","Ballaghderg, Letterkenny, Co Donegal  (Phase 1)*",33,"Respond","","","","","Q4-2017",""],
    [432,432,"CALF Turnkey","Donegal","Forge Road, Donegal (Phase 1)",4,"Cluid Housing","","","","","","Q3-2016"],
    [433,433,"CAS CONSTRUCTION","Donegal","Glenrowan House, Drumkeen, Stranorlar",5,"Apex Housing Association","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [434,434,"CAS CONSTRUCTION","Donegal","Cois Locha, Meenmore, Dungloe",15,"County Donegal Parents and Friends Housing Association Ltd","","","Stage 3 approved Q3-2018, the scheme is now approved to proceed to tender.","","",""],
    [435,435,"CAS CONSTRUCTION","Donegal","Railway Park, Drumrooske, Donegal Town",10,"Oaklee Housing Trust","","","","","Q2-2019",""],
    [436,436,"CAS CONSTRUCTION","Donegal","Dunshenny House, Derry Road, Carndonagh",5,"Apex Housing Association","","","","","","Q2-2018"],
    [437,437,"CAS CONSTRUCTION","Donegal","Raphoe Road, Castlefinn",20,"Habinteg Housing Association (Ireland) Ltd","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [438,438,"SHIP CONSTRUCTION","Donegal","Meadow Hill, Raphoe",11,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [439,439,"SHIP CONSTRUCTION","Donegal","Cois Abhainn, St Johnston (Phase 2)",6,"*N/A","","","","","Q1-2019",""],
    [440,440,"SHIP CONSTRUCTION","Donegal","Long Lane, Letterkenny",29,"*N/A","","","","","Q4-2019",""],
    [441,441,"SHIP CONSTRUCTION","Donegal","Rockytown, Buncrana (Phase 1)",21,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [442,442,"SHIP CONSTRUCTION","Donegal","Manorcunningham (Phase 2)",8,"*N/A","","","","","","Q4-2018"],
    [443,443,"SHIP CONSTRUCTION","Donegal","Abbots Wood, Carndonagh (Ph 2)",4,"*N/A","","","","","","Q4-2018"],
    [444,444,"SHIP CONSTRUCTION","Donegal","Ardara (Phase 3)",8,"*N/A","","","","","","Q2-2017"],
    [445,445,"SHIP CONSTRUCTION","Donegal","Newtoncunningham",7,"*N/A","","","","","","Q4-2018"],
    [446,446,"SHIP CONSTRUCTION","Donegal","Railway Park, Drumrooske, Donegal Town",24,"*N/A","","","","","Q2-2019",""],
    [447,447,"SHIP CONSTRUCTION","Donegal","Ard Connell, Ardara (SRD)",1,"*N/A","","","","","","Q1-2017"],
    [448,448,"SHIP CONSTRUCTION","Donegal","Manorcunningham (Phase 1)",2,"*N/A","","","","","","Q2-2017"],
    [449,449,"SHIP CONSTRUCTION","Donegal","Emerald Drive, Killybegs (Phase 6)",9,"*N/A","","","","","","Q4-2019"],
    [450,450,"SHIP CONSTRUCTION","Donegal","Radharc na Tra Breige, Malin (Phase 3)",8,"*N/A","","","","","","Q4-2019"],
    [451,451,"SHIP CONSTRUCTION","Donegal","Figart, Dunfanaghy",8,"*N/A","","","","","","Q4-2019"],
    [452,452,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny (Phase 2)",8,"*N/A","","","","","","Q1-2019"],
    [453,453,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny (Phase 3)",10,"*N/A","","","","","","Q2-2019"],
    [454,454,"SHIP CONSTRUCTION TURNKEY","Donegal","Drumrooske West",36,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [455,455,"SHIP CONSTRUCTION TURNKEY","Donegal","Brookfield",38,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [456,456,"SHIP CONSTRUCTION TURNKEY","Donegal","Convent Road, Carndonagh",57,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [457,457,"SHIP CONSTRUCTION TURNKEY","Donegal","Donegal Road, Ballybofey",14,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [458,458,"SHIP CONSTRUCTION TURNKEY","Donegal","Admiran, Stranorlar",52,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [459,459,"SHIP CONSTRUCTION TURNKEY","Donegal","Gleann Na Greine, Mullindrait, Stranorlar",21,"*N/A","","","","","","Q2-2018"],
    [460,460,"SHIP CONSTRUCTION TURNKEY","Donegal","Crievesmith, Letterkenny",18,"*N/A","","","","","","Q4-2018"],
    [461,461,"SHIP CONSTRUCTION TURNKEY","Donegal","Radharc an Chuain, Ramelton",18,"*N/A","","","","","Q4-2019",""],
    [462,462,"SHIP CONSTRUCTION TURNKEY","Donegal","Carnamuggagh, Letterkenny",30,"*N/A","","","","","Q1-2019",""],
    [463,463,"SHIP CONSTRUCTION TURNKEY","Donegal","Heathhill, Newtowncunningham",9,"*N/A","","","","","Q2-2019",""],
    [464,464,"SHIP CONSTRUCTION TURNKEY","Donegal","Heathhill, Newtowncunningham",10,"*N/A","","","","","","Q4-2019"],
    [465,465,"SHIP CONSTRUCTION TURNKEY","Donegal","St�isi�n an Ch�irt, Falcarragh Phase 1",6,"*N/A","","","","","","Q4-2019"],
    [466,466,"SHIP CONSTRUCTION RAPID","Dublin City","Bunratty Road",78,"*N/A","","","","","Q4-2019",""],
    [467,467,"CALF Construction","Dublin City","3 units, Block A Jamestown Court, Dublin 8 (Phase 1)",3,"ALONE","","","","","Q2-2019",""],
    [468,468,"CALF Construction","Dublin City","Annamore Court, Ballyfermot (Phase 1)",70,"The Iveagh Trust","","","","","","Q2-2017"],
    [469,469,"CALF Construction","Dublin City","Ballygall Road East Phase 2 (Phase 1)",11,"Fold Housing Association Ireland Ltd","","","","","","Q1-2016"],
    [470,470,"CALF Construction","Dublin City","Bethany House, Gilford Road, Sandymount, Dublin 4 (Phase 1)",62,"Cluid Housing","","","","Q2-2018","",""],
    [471,471,"CALF Construction","Dublin City","Block A, Jamestown Court, Dublin 8 (Phase 1)",9,"ALONE","","","","","Q2-2019",""],
    [472,472,"CALF Construction","Dublin City","Broome Lodge,\\nDunmanus Court, Cabra (Phase 1)",33,"Cluid Housing","","","","","","Q4-2017"],
    [473,473,"CALF Construction","Dublin City","Harolds Cross, Dublin 6 (Phase 1)",28,"Focus Housing Association CLG","","","","","","Q4-2016"],
    [474,474,"CALF Construction","Dublin City","North King Street, Dublin 7  (Phase 1)",30,"Co-operative Housing Ireland","","","","","Q4-2019",""],
    [475,475,"CALF Construction","Dublin City","Orchard Lawns, Ballyfermot (Phase 1)",36,"Co-operative Housing Ireland","","","","","","Q3-2018"],
    [476,476,"CALF Construction","Dublin City","Orchard Lawns, Ballyfermot (Phase 2)",36,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [477,477,"CALF Construction","Dublin City","Post Tender Johns Lane West Dublin 8 (Phase 1)",31,"Focus Housing Association CLG","","","","","","Q4-2018"],
    [478,478,"CALF Construction","Dublin City","Revised - Dominic Place, Dublin (Phase 1)",9,"The Paddy McGrath Housing Project","","","","","Q2-2019",""],
    [479,479,"CALF Construction","Dublin City","Richmond Road, Dublin 9 (Phase 1)",40,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [480,480,"CALF Construction","Dublin City","Post Tender - Wad River Close Phase 2, Ballymun, Dublin 9  (Phase 1)",9,"Cluid Housing","","","","","","Q4-2019"],
    [481,481,"CALF Construction","Dublin City","POST TENDER Dolphin Park, Rialto, Dublin 8 (Phase 1)",43,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [482,482,"CALF Construction","Dublin City","POST TENDER, Poplar Row, Ballybough, Dublin 3 (Phase 1)",29,"Oaklee Housing","","","","","","Q4-2019"],
    [483,483,"CALF Construction","Dublin City","Revised - St Mary�s Mansions, Dublin 1 (Phase 1)",80,"Cluid Housing","","","","","","Q4-2019"],
    [484,484,"CALF Construction","Dublin City","Revised Post Tender - Raleigh Square, Crumlin (Phase 1)",33,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [485,485,"CALF Turnkey","Dublin City","Canal Meadows, Bluebell, Dublin 12 (Phase 1)",4,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [486,486,"CALF Turnkey","Dublin City","9 units Dorset Street, Dublin 1 (Phase 1)",9,"Clanmil Housing Association Ireland","","","","","Q2-2019",""],
    [487,487,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 1)",14,"T�ath Housing Association Ltd","","","","","","Q4-2016"],
    [488,488,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 2)",21,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [489,489,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 3)",10,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [490,490,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 4)",3,"T�ath Housing Association Ltd","","","","","","Q3-2017"],
    [491,491,"CALF Turnkey","Dublin City","An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 5)",1,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [492,492,"CALF Turnkey","Dublin City","Aughrim Street, Stoneybatter, Dublin 7 (Phase 1)",4,"Clanmil Housing Association Ireland","","","","","Q3-2019",""],
    [493,493,"CALF Turnkey","Dublin City","Balfe Road, Crumlin, Dublin 12 (Phase 1)*",16,"Respond","","","","","","Q4-2018"],
    [494,494,"CALF Turnkey","Dublin City","Block A Northbank, Castleforbes, Dublin 1  (Phase 1)*",26,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [495,495,"CALF Turnkey","Dublin City","Bluebell Avenue, Bluebell, Dublin 12 (Phase 1)*",52,"Respond","","","","","Q4-2019",""],
    [496,496,"CALF Turnkey","Dublin City","Bluebell Avenue, Dublin 12 (Phase 1)",7,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [497,497,"CALF Turnkey","Dublin City","Bow Lane West, Dublin 8 (Phase 1)",16,"Oaklee Housing","","","","Q2-2019","",""],
    [498,498,"CALF Turnkey","Dublin City","Camac Park, Bluebell, Dublin 12 (Phase 1)",5,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [499,499,"CALF Turnkey","Dublin City","Clongriffin, Dublin 13 (Phase 1)*",84,"The Iveagh Trust","","","","","","Q2-2019"],
    [500,500,"CALF Turnkey","Dublin City","Chanel College, Coolock Village, Malahide Road, Dublin 5  (Phase 1)*",16,"Respond","","","","","","Q4-2017"],
    [501,501,"CALF Turnkey","Dublin City","Chanel Manor Apartments, Coolock, Dublin 5. (Phase 1)*",65,"Respond","","","","","Q2-2019",""],
    [502,502,"CALF Turnkey","Dublin City","Crumlin Village, Dublin 12 (Phase 1)",3,"Cluid Housing","","","","","","Q2-2017"],
    [503,503,"CALF Turnkey","Dublin City","Crumlin Village, Dublin 12 (Phase 2)",2,"Cluid Housing","","","","","","Q3-2017"],
    [504,504,"CALF Turnkey","Dublin City","Lough Conn Road, Ballyfermot, Dublin 10 (Phase 1)",1,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [505,505,"CALF Turnkey","Dublin City","Lough Conn Road, Ballyfermot, Dublin 10 (Phase 2)",4,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [506,506,"CALF Turnkey","Dublin City","Merville Court, Merville Avenue, Fairview (Phase 1)",5,"Co-operative Housing Ireland","","","","","","Q1-2017"],
    [507,507,"CALF Turnkey","Dublin City","Millrose House, Bluebell Avenue, Dublin 12 (Phase 1)",8,"Cluid Housing","","","","","","Q4-2017"],
    [508,508,"CALF Turnkey","Dublin City","Mountjoy Square North, Dublin 1 (Phase 1)",31,"Respond","","","","","","Q4-2019"],
    [509,509,"CALF Turnkey","Dublin City","Old School House Lane, Magenta Crescent, Santry, Dublin 9 (Phase 1)",8,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [510,510,"CALF Turnkey","Dublin City","Park West Campus, Kileen Road, Dublin 12 (Phase 1)",8,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [511,511,"CALF Turnkey","Dublin City","Park West Campus, Kileen Road, Dublin 12 (Phase 2)",9,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [512,512,"CALF Turnkey","Dublin City","Park West Campus, Kileen Road, Dublin 12 (Phase 3)",41,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [513,513,"CALF Turnkey","Dublin City","Park West Campus, Kileen Road, Dublin 12 (Phase 4)",43,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [514,514,"CALF Turnkey","Dublin City","Ravensdale Court, Kimmage, Dublin 12. (Phase 1)",12,"T�ath Housing Association Ltd","","","","Q3-2019","",""],
    [515,515,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)",6,"Fold Housing Association Ireland Ltd","","","","","Q1-2018",""],
    [516,516,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 2)",53,"Fold Housing Association Ireland Ltd","","","","Q4-2019","",""],
    [517,517,"CALF Turnkey","Dublin City","Stormanstown Hall, Ballymun Road, (revised) (Phase 1)",42,"Oaklee Housing","","","","","","Q3-2018"],
    [518,518,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 1)",28,"T�ath Housing Association Ltd","","","","","","Q2-2016"],
    [519,519,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 2)",18,"T�ath Housing Association Ltd","","","","","","Q4-2016"],
    [520,520,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 3)",14,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [521,521,"CALF Turnkey","Dublin City","Thornwood, Beaumont (Phase 4)",8,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [522,522,"CALF Turnkey","Dublin City","Tonlegee Road, Dublin 5  (Phase 1)",47,"Fold Housing Association Ireland Ltd","","","","","","Q4-2018"],
    [523,523,"CALF Turnkey","Dublin City","Tramyard Exchange, 27  Carman's Hall, Meath Street, Dublin 8 (Phase 1)",15,"Cluid Housing","","","","","Q4-2019",""],
    [524,524,"CALF Turnkey","Dublin City","St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)",44,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [525,525,"CALF Turnkey","Dublin City","Sundrive Mews, Kimmage, Dublin 12 (Phase 1)",9,"Cluid Housing","","","","","","Q4-2019"],
    [526,526,"CAS CONSTRUCTION","Dublin City","1 - 2 Rafter's Lane, Dublin 12",11,"Walkinston Housing Association Ltd (WALK)","","","","","","Q4-2019"],
    [527,527,"CAS CONSTRUCTION","Dublin City","Beech Hill",19,"Royal Hospital Donnybrook Voluntary Housing Association Ltd","","","","","","Q4-2018"],
    [528,528,"CAS CONSTRUCTION","Dublin City","Ellis Court, Dublin",22,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [529,529,"CAS CONSTRUCTION","Dublin City","Martanna House, High Park, Grace Park Road,Dublin 9",8,"Respond","","","","","","Q4-2018"],
    [530,530,"CAS CONSTRUCTION","Dublin City","180-187 Townsend Street",18,"Peter McVerry Trust Ltd","","","Stage 3 approved Q4-2018, the scheme is now approved to proceed to tender.","","",""],
    [531,531,"CAS CONSTRUCTION","Dublin City","Old Kilmainham Road, Dublin 8",11,"Arlington Novas Ireland Ltd","Stage 1 approved Q1-2017, outline design and costs being prepared.","","","","",""],
    [532,532,"CAS CONSTRUCTION","Dublin City","26 New Street South, Dublin 8",8,"Peter McVerry Trust Ltd","","","","","Q4-2019",""],
    [533,533,"CAS CONSTRUCTION","Dublin City","Broome Lodge, Dunmanus, Dublin 7",10,"Cluid Housing Association","","","","","","Q4-2017"],
    [534,534,"CAS CONSTRUCTION","Dublin City","St Agatha's Court, North William Street, Dublin 1",11,"Peter McVerry Trust Ltd","","","","","","Q2-2017"],
    [535,535,"CAS CONSTRUCTION","Dublin City","55B Arbour Hill, Dublin 7",14,"Simon Community : Dublin Simon","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [536,536,"CAS CONSTRUCTION","Dublin City","St. Michael's Estate, Inchicore, Dublin 8 - Housing Pilot Project ",52,"Circle Voluntary Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [537,537,"CAS CONSTRUCTION","Dublin City","Shaw Street, Dublin 2",12,"Peter McVerry Trust Ltd","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [538,538,"CAS CONSTRUCTION SINGLE STAGE","Dublin City","13A Casement Drive / 307A Casement Road, Finglas, Dublin 11",4,"Arlington Novas Ireland Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [539,539,"CAS CONSTRUCTION TURNKEY","Dublin City","61 & 63 Rathoath Avenue, Finglas, Dublin 11",6,"Arlington Novas Ireland Ltd","","","","","Q3-2019",""],
    [540,540,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Dublin City","Ayrfield, Malahide Road",150,"*N/A","","","","","Q1-2019",""],
    [541,541,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Dublin City","Scribblestown",70,"*N/A","","","","","Q1-2019",""],
    [542,542,"REGENERATION","Dublin City","St. Teresa's Gardens",54,"*N/A","","","","","Q4-2018",""],
    [543,543,"REGENERATION","Dublin City","Dolphin House, Dublin 8",100,"*N/A","","","","","","Q3-2018"],
    [544,544,"REGENERATION","Dublin City","Sackville Avenue Cottages",11,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [545,545,"REGENERATION","Dublin City","Charlemont",79,"*N/A","","","","","","Q4-2017"],
    [546,546,"REGENERATION","Dublin City","Maxwell Road",9,"*N/A","","","","","","Q2-2016"],
    [547,547,"REGENERATION","Dublin City","Buttercup, Darndale",19,"*N/A","","","","","","Q4-2017"],
    [548,548,"REGENERATION","Dublin City","Buttercup, Darndale",9,"*N/A","","","","","","Q1-2018"],
    [549,549,"REGENERATION","Dublin City","Buttercup, Darndale",7,"*N/A","","","","","","Q2-2018"],
    [550,550,"REGENERATION","Dublin City","St. Bricins Park",11,"*N/A","","","","","","Q4-2018"],
    [551,551,"REGENERATION","Dublin City","Dolphin House, Dublin 8",35,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [552,552,"SHIP CONSTRUCTION","Dublin City","Ballybough Road, Dublin 1 - Phase 2",2,"*N/A","","","","","","Q4-2019"],
    [553,553,"SHIP CONSTRUCTION RAPID","Dublin City","Springvale Chapelizod Dublin 8",71,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [554,554,"SHIP CONSTRUCTION RAPID","Dublin City","Bonham Street Dublin  8",57,"*N/A","","","","","Q4-2019",""],
    [555,555,"SHIP CONSTRUCTION RAPID","Dublin City","Cork Street / Chamber Street Dublin 8",55,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [556,556,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot - Rathvilly & Woodbank Drive Finglas - Cherry Orchard",53,"*N/A","","","","","","Q4-2018"],
    [557,557,"SHIP CONSTRUCTION","Dublin City","Priory Hall Phase 2",24,"*N/A","","","","","","Q4-2019"],
    [558,558,"SHIP CONSTRUCTION","Dublin City","Hampton Wood",25,"*N/A","","","","","","Q4-2016"],
    [559,559,"SHIP CONSTRUCTION","Dublin City","Cornamona, Ballyfermot, Dublin 12",61,"*N/A","","","","","Q2-2019",""],
    [560,560,"SHIP CONSTRUCTION","Dublin City","Infirmary Road, Dublin 7",38,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [561,561,"SHIP CONSTRUCTION","Dublin City","North King Street, - Sean Foster Place, Dublin 7",30,"*N/A","","","","","Q1-2019",""],
    [562,562,"SHIP CONSTRUCTION","Dublin City","Ballybough Road, Dublin 1",5,"*N/A","","","","","","Q4-2018"],
    [563,563,"SHIP CONSTRUCTION","Dublin City","St. Finbar's Court, Kilkieran Road, Dublin 7",46,"*N/A","Stage 1 approved Q4-2017, outline design and costs being prepared.","","","","",""],
    [564,564,"SHIP CONSTRUCTION","Dublin City","Dominick Street (East side)",72,"*N/A","","","","","Q1-2019",""],
    [565,565,"SHIP CONSTRUCTION","Dublin City","O'Devaney Gardens",56,"*N/A","","","","","Q3-2018",""],
    [566,566,"SHIP CONSTRUCTION","Dublin City","Priory Hall",9,"*N/A","","","","","","Q1-2017"],
    [567,567,"SHIP CONSTRUCTION","Dublin City","Glin Court, Coolock, Dublin 17",25,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [568,568,"SHIP CONSTRUCTION TURNKEY","Dublin City","Hampton Wood, Finglas",45,"*N/A","","","","","","Q4-2019"],
    [569,569,"SHIP CONSTRUCTION TURNKEY","Dublin City","Prospect Hill",58,"*N/A","","","","","","Q4-2017"],
    [570,570,"SHIP CONSTRUCTION TURNKEY","Dublin City","Parkside, Balgriffin, Dublin 13",16,"*N/A","","","","","","Q4-2018"],
    [571,571,"SHIP CONSTRUCTION TURNKEY","Dublin City","Hampton Wood, Finglas",47,"*N/A","","","","","","Q4-2018"],
    [572,572,"SHIP CONSTRUCTION RAPID","Dublin City","St Helena's Drive, Finglas",39,"*N/A","","","","","","Q3-2017"],
    [573,573,"SHIP CONSTRUCTION RAPID","Dublin City","Belcamp H, Dublin 17",38,"*N/A","","","","","","Q4-2017"],
    [574,574,"SHIP CONSTRUCTION RAPID","Dublin City","Mourne Road, Drimnagh",29,"*N/A","","","","","","Q4-2017"],
    [575,575,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot",24,"*N/A","","","","","","Q4-2017"],
    [576,576,"SHIP CONSTRUCTION RAPID","Dublin City","Poppintree, Ballymun",22,"*N/A","","","","","","Q2-2016"],
    [577,577,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot - Rathvilly & Woodbank Drive Finglas - Cherry Orchard site Ph 2",19,"*N/A","","","","","","Q4-2019"],
    [578,578,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot - Rathvilly & Woodbank Drive Finglas - Rathvilly Drive site",13,"*N/A","","","","","","Q3-2018"],
    [579,579,"SHIP CONSTRUCTION RAPID","Dublin City","Belcamp B, Dublin 17",12,"*N/A","Stage 1 approved Q3-2015, outline design and costs being prepared.","","","","",""],
    [580,580,"SHIP CONSTRUCTION RAPID","Dublin City","Cherry Orchard, Ballyfermot - Rathvilly & Woodbank Drive Finglas - Woodbank Drive site",3,"*N/A","","","","","","Q3-2018"],
    [581,581,"SHIP CONSTRUCTION RAPID","Fingal","Avondale, Mulhuddart, Dublin 15",42,"*N/A","","","","","","Q4-2019"],
    [582,582,"CALF Construction","Fingal","Ladyswell Road & Church Road, Mulhuddart, Dublin 15  (Phase 1)",65,"Cluid Housing","","","","","Q4-2018",""],
    [583,583,"CALF Construction","Fingal","Old Coolock Lane, Santry, Dublin 9 (Phase 1)",28,"Circle Voluntary Housing Association Ltd","","","","Q1-2019","",""],
    [584,584,"CALF Turnkey","Fingal","4 units, Taylor Hill, Balbriggan, Co. Dublin (Phase 1)",4,"Cluid Housing","","","","","","Q4-2018"],
    [585,585,"CALF Turnkey","Fingal","Allendale Square, Clonsilla, Dublin 15 (Phase 1)*",28,"Respond","","","","","Q1-2019",""],
    [586,586,"CALF Turnkey","Fingal","Barnwell Woods, Hansfield, Dublin 15 (Phase 1)*",12,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [587,587,"CALF Turnkey","Fingal","Barnwell Woods, Hansfield, Dublin 15 (Phase 2)*",12,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [588,588,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 1)",18,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [589,589,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 2)",15,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [590,590,"CALF Turnkey","Fingal","Belcamp Manor, Malahide Road, Balgriffin, Dublin 13 (Phase 3)",16,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [591,591,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 1)",5,"T�ath Housing Association Ltd","","","","","","Q2-2016"],
    [592,592,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 2)",7,"T�ath Housing Association Ltd","","","","","","Q3-2016"],
    [593,593,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 3)",7,"T�ath Housing Association Ltd","","","","","","Q4-2016"],
    [594,594,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 4)",21,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [595,595,"CALF Turnkey","Fingal","Castlegrange Park (2) Clonsilla (Phase 5)",8,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [596,596,"CALF Turnkey","Fingal","Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 1)*",138,"Respond","","","","","Q3-2019",""],
    [597,597,"CALF Turnkey","Fingal","Cois Sruthan, Ballyboughal, Co.Dublin (Phase 1)*",17,"Oaklee Housing","","","","","Q4-2017",""],
    [598,598,"CALF Turnkey","Fingal","An Muileann, Kettles Lane, Swords, Dublin (Phase 1)",24,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [599,599,"CALF Turnkey","Fingal","Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 2)*",6,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [600,600,"CALF Turnkey","Fingal","Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin (Phase 1)*",10,"Cluid Housing","","","","","Q3-2018",""],
    [601,601,"CALF Turnkey","Fingal","Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin (Phase 2)*",5,"Cluid Housing","","","","","Q3-2018",""],
    [602,602,"CALF Turnkey","Fingal","Lanesborough Close, Finglas, Dublin 11 (Phase 1)*",21,"Cluid Housing","","","","","","Q4-2018"],
    [603,603,"CALF Turnkey","Fingal","Martello Place, Balbriggan, Co Dublin  (Phase 1)",18,"Respond","","","","","","Q3-2018"],
    [604,604,"CALF Turnkey","Fingal","Millers Glen, Oldtown, Swords, Co. Dublin (Phase 1)*",10,"The Iveagh Trust","","","","","Q3-2018",""],
    [605,605,"CALF Turnkey","Fingal","Millers Glen, Oldtown, Swords, Co. Dublin (Phase 2)*",18,"The Iveagh Trust","","","","","Q3-2018",""],
    [606,606,"CALF Turnkey","Fingal","Northwood Green, Santry, Dublin 9 (Phase 1)*",6,"Respond","","","","","","Q4-2018"],
    [607,607,"CALF Turnkey","Fingal","Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 2)*",7,"Respond","","","","","Q3-2018",""],
    [608,608,"CALF Turnkey","Fingal","Old Corduff Road, Blanchardstown, Dublin 15 (Phase 1)*",28,"Respond","","","","","Q4-2018",""],
    [609,609,"CALF Turnkey","Fingal","Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 1)",11,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [610,610,"CALF Turnkey","Fingal","Seamus Ennis Terrace, Naul, Co. Dublin (Phase 1)",2,"Respond","","","","","Q4-2017",""],
    [611,611,"CALF Turnkey","Fingal","St Marnock�s Bay, Portmarnock, Co Dublin   (Phase 1)*",10,"Cluid Housing","","","","","","Q4-2017"],
    [612,612,"CALF Turnkey","Fingal","St Werburghs Court Drynam Rd Swords Co Dublin (Phase 1)*",18,"T�ath Housing Association Ltd","","","","","","Q4-2017"],
    [613,613,"CALF Turnkey","Fingal","Knightsgate, Rush, Co. Dublin (Phase 1)*",38,"Cluid Housing","","","","","","Q4-2019"],
    [614,614,"CALF Turnkey","Fingal","Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 2)*",8,"Circle Voluntary Housing Association Ltd","","","","","Q4-2017",""],
    [615,615,"CALF Turnkey","Fingal","Taylor Hill Crescent, Balbriggan, Co. Dublin (Phase 1)",4,"Cluid Housing","","","","","","Q4-2018"],
    [616,616,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*",31,"Cluid Housing","","","","","","Q4-2018"],
    [617,617,"CALF Turnkey","Fingal","Millers Glen, Phase 3, Oldtown, Swords (Phase 1)*",14,"The Iveagh Trust","","","","","","Q4-2019"],
    [618,618,"CALF Turnkey","Fingal","Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 1)",48,"Respond","","","","","","Q4-2019"],
    [619,619,"CALF Turnkey","Fingal","Pappan Grove, Northwood, Santry, Dublin 9 (Phase 1)*",35,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [620,620,"CALF Turnkey","Fingal","The Hermitage, Balgriffin, Co Dublin  (Phase 1)*",54,"Cluid Housing","","","","","","Q4-2017"],
    [621,621,"CALF Turnkey","Fingal","Weavers Wood, Clonsilla Road, Clonsilla, Dublin 15  (Phase 1)*",33,"Co-operative Housing Ireland","","","","","","Q3-2018"],
    [622,622,"CALF Turnkey","Fingal","Phoenix Park Avenue, Castleknock, Dublin 15 (Phase 1)*",31,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [623,623,"CALF Turnkey","Fingal","Weston, Feltrim Road, Swords, North County Dublin (Phase 2)*",10,"Oaklee Housing","","","","","Q1-2019",""],
    [624,624,"CALF Turnkey","Fingal","Semple Woods, Donabate, North County Dublin (Phase 1)*",30,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [625,625,"CALF Turnkey","Fingal","Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [626,626,"CALF Turnkey","Fingal","Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*",24,"Cluid Housing","","","","","","Q4-2019"],
    [627,627,"CALF Turnkey","Fingal","The Forge, Lusk, Co. Dublin (Phase 1)",8,"Oaklee Housing","","","","","","Q4-2019"],
    [628,628,"CALF Turnkey","Fingal","The Galleries (Wrens Hill), Turvey Avenue, Donabate (Phase 1)",43,"Oaklee Housing","","","","","","Q4-2019"],
    [629,629,"CALF Turnkey","Fingal","Weston, Feltrim Road, Swords, North County Dublin (Phase 1)",24,"Oaklee Housing","","","","","","Q4-2019"],
    [630,630,"CAS CONSTRUCTION","Fingal","Killhedge Lane Dun Emer",48,"T�ath Housing Association Ltd","Stage 1 approved Q1-2017, outline design and costs being prepared.","","","","",""],
    [631,631,"CAS CONSTRUCTION","Fingal","Ravenswood, North Road, Finglas",6,"Peter McVerry Trust Ltd","","","","","","Q4-2018"],
    [632,632,"CAS CONSTRUCTION","Fingal","22 College Street, Baldoyle",4,"Cluid Housing Association","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [633,633,"CAS CONSTRUCTION","Fingal","Darcystown, Ringfort, Balrothery",9,"North ? East Housing Association Ltd","","","","","","Q3-2017"],
    [634,634,"CAS CONSTRUCTION","Fingal","Estuary Road, Malahide",8,"Society of Saint Vincent de Paul","","","","","","Q2-2018"],
    [635,635,"SHIP CONSTRUCTION","Fingal","Castlelands, Park View, Balbriggan (Phase 3)",24,"*N/A","","","","","","Q1-2019"],
    [636,636,"SHIP CONSTRUCTION","Fingal","Cappaghfinn (Phase 1)",14,"*N/A","","","","","","Q2-2016"],
    [637,637,"SHIP CONSTRUCTION","Fingal","Redevelopment of Community Centre, Pinewood, Balbriggan",2,"*N/A","","","","","","Q3-2019"],
    [638,638,"SHIP CONSTRUCTION","Fingal","Rivermeade, St. Margarets",2,"*N/A","","","","","","Q2-2019"],
    [639,639,"SHIP CONSTRUCTION","Fingal","Rowlestown (Phase 1)",10,"*N/A","","","","","","Q2-2019"],
    [640,640,"SHIP CONSTRUCTION","Fingal","Rathbeale Road, Swords",24,"*N/A","","","","","Q4-2018",""],
    [641,641,"SHIP CONSTRUCTION RAPID","Fingal","Hansfield, Ongar, Dublin 15",36,"*N/A","","","","","","Q3-2017"],
    [642,642,"SHIP CONSTRUCTION","Fingal","Rowlestown (Phase 2)",4,"*N/A","","","","","","Q3-2019"],
    [643,643,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk",25,"*N/A","","","","","","Q4-2017"],
    [644,644,"SHIP CONSTRUCTION","Fingal","Tucketts Lane, Howth, Co Dublin",8,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [645,645,"SHIP CONSTRUCTION","Fingal","Wellview Infill",20,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [646,646,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk (Phase 2.2) ",15,"*N/A","","","","","","Q1-2018"],
    [647,647,"SHIP CONSTRUCTION","Fingal","Outlands, Rathbeale Road, Swords, Co.Dublin",11,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [648,648,"SHIP CONSTRUCTION","Fingal","Cappagh Lands, Cappagh Road Finglas",69,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [649,649,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk (Phase 2.3)",5,"*N/A","","","","","","Q2-2018"],
    [650,650,"SHIP CONSTRUCTION","Fingal","Churchfields, Phase 2B, Mulhuddart, Dublin 15.",70,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [651,651,"SHIP CONSTRUCTION","Fingal","Leonards Garage, Lusk, Co. Dublin",14,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [652,652,"SHIP CONSTRUCTION","Fingal","Church Road, Lusk",5,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [653,653,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk (Phase 2.4)",4,"*N/A","","","","","","Q3-2018"],
    [654,654,"SHIP CONSTRUCTION","Fingal","Racecourse Commons, Lusk (Phase 2.5)",25,"*N/A","","","","","","Q4-2018"],
    [655,655,"SHIP CONSTRUCTION","Fingal","Rowlestown (Phase 3)",12,"*N/A","","","","","","Q4-2019"],
    [656,656,"SHIP CONSTRUCTION","Fingal","St. Cronan's Cottages, Swords - Infill",1,"*N/A","","","","","","Q2-2016"],
    [657,657,"SHIP CONSTRUCTION","Fingal","St. Cronan's Green, Swords",14,"*N/A","","","","","","Q2-2016"],
    [658,658,"SHIP CONSTRUCTION","Fingal","The Grange, Ballyboughal",2,"*N/A","","","","","","Q3-2017"],
    [659,659,"SHIP CONSTRUCTION","Fingal","The Grange, Ballyboughal (Part 2)",6,"*N/A","","","","","","Q4-2018"],
    [660,660,"SHIP CONSTRUCTION TURNKEY","Fingal","Cnoc Dubh Ballyboughal Co. Dublin",5,"*N/A","","","","","","Q3-2019"],
    [661,661,"SHIP CONSTRUCTION TURNKEY","Fingal","Hollytown Cottages",4,"*N/A","","","","","","Q4-2019"],
    [662,662,"SHIP CONSTRUCTION TURNKEY","Fingal","Rahillion, Donabate",1,"*N/A","","","","","","Q4-2019"],
    [663,663,"SHIP CONSTRUCTION TURNKEY","Fingal","Balgriffin Grove, Malahide Road, Balgriffin",6,"*N/A","","","","","","Q1-2017"],
    [664,664,"SHIP CONSTRUCTION TURNKEY","Fingal","Blackmills Grove, Blakestown Road, Mulhuddard",10,"*N/A","","","","","","Q2-2017"],
    [665,665,"SHIP CONSTRUCTION TURNKEY","Fingal","Boroimhe, Swords",6,"*N/A","","","","","","Q3-2018"],
    [666,666,"SHIP CONSTRUCTION TURNKEY","Fingal","Bremore Pastures Park, Balbriggan",4,"*N/A","","","","","","Q4-2018"],
    [667,667,"SHIP CONSTRUCTION TURNKEY","Fingal","Cnoc Dubh, Ballyboughal",6,"*N/A","","","","","","Q4-2018"],
    [668,668,"SHIP CONSTRUCTION TURNKEY","Fingal","Glaslinn, Donabate",3,"*N/A","","","","","","Q4-2018"],
    [669,669,"SHIP CONSTRUCTION TURNKEY","Fingal","Hansfield (Phase 1), Ongar, Dublin 15",16,"*N/A","","","","","","Q1-2018"],
    [670,670,"SHIP CONSTRUCTION TURNKEY","Fingal","Hansfield (Phase 2), Ongar, Dublin 15",16,"*N/A","","","","","","Q2-2018"],
    [671,671,"SHIP CONSTRUCTION TURNKEY","Fingal","Kenure Gate, Park Road, Rush",4,"*N/A","","","","","","Q4-2018"],
    [672,672,"SHIP CONSTRUCTION TURNKEY","Fingal","Northwood Green, Santry, Dublin 9",37,"*N/A","","","","","","Q4-2018"],
    [673,673,"SHIP CONSTRUCTION TURNKEY","Fingal","Ravenswood, North Road, Finglas (Phase 2)",2,"Peter McVerry Trust Ltd","","","","","","Q4-2018"],
    [674,674,"SHIP CONSTRUCTION RAPID","Fingal","Church Road, Mulhuddart, Dublin 15",22,"*N/A","","","","","","Q4-2019"],
    [675,675,"SHIP CONSTRUCTION RAPID","Fingal","Pinewood, Balbriggan",20,"*N/A","","","","","","Q2-2018"],
    [676,676,"SHIP CONSTRUCTION RAPID","Fingal","Wellview, Mulhuddart",20,"*N/A","","","","","","Q4-2017"],
    [677,677,"CALF Turnkey","Galway City","Boireann Beag, Ros Cam, Galway (Phase 1)",16,"Cluid Housing","","","","","","Q4-2016"],
    [678,678,"CALF Turnkey","Galway City","Belmont, Renmore, Galway City (Phase 1)*",16,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [679,679,"CALF Turnkey","Galway City","Block D, Sraith Fhada, Doughiska, Galway (Phase 1)",14,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [680,680,"CALF Turnkey","Galway City","Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 2)*",8,"Respond","","","","","Q2-2019",""],
    [681,681,"CALF Turnkey","Galway City","Breacan, Letteragh Road, Galway City (Phase 1)*",2,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [682,682,"CALF Turnkey","Galway City","Caireal Mor, Castlegar Road, Galway (Phase 2)",63,"Respond","","","","","Q2-2018",""],
    [683,683,"CALF Turnkey","Galway City","Caireal Mor, Castlegar Road, Galway (Phase 3)",8,"Respond","","","","","Q2-2018",""],
    [684,684,"CALF Turnkey","Galway City","Cnoc na Ri, Clybaun Road, Galway  (Phase 1)*",2,"Cluid Housing","","","","","","Q3-2017"],
    [685,685,"CALF Turnkey","Galway City","Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 1)",7,"Respond","","","","","","Q4-2019"],
    [686,686,"CALF Turnkey","Galway City","Maigh Rua, Doughiska, Galway  (Phase 1)",23,"Co-operative Housing Ireland","","","","","","Q4-2017"],
    [687,687,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Galway (Phase 1)*",2,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [688,688,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Galway (Phase 2)*",4,"T�ath Housing Association Ltd","","","","","","Q4-2017"],
    [689,689,"CALF Turnkey","Galway City","Maoilin, Ballymoneen Road, Knocknacarra, Galway CIty (Phase 1)*",3,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [690,690,"CALF Turnkey","Galway City","Reilean, Roscam, Block 5 Galway (Phase 1)*",12,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [691,691,"CALF Turnkey","Galway City","Reilean, Roscam,Block 4 Galway (Phase 1)*",12,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [692,692,"CALF Turnkey","Galway City","Caireal Mor, Castlegar Road, Galway (Phase 1)",10,"Respond","","","","","","Q4-2019"],
    [693,693,"CALF Turnkey","Galway City","Leana Theas, Cappagh Road, Galway City (Phase 1)*",10,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [694,694,"CALF Turnkey","Galway City","Revised Murrough, Renmore, Galway  (Phase 1)*",20,"Cluid Housing","","","","","","Q1-2019"],
    [695,695,"CAS CONSTRUCTION","Galway City","47 Forster Street",9,"Cope Galway","","","","","","Q4-2019"],
    [696,696,"CAS CONSTRUCTION","Galway City","97/98 Rockfield",4,"Carraig Dubh Housing Association","","","","","","Q1-2018"],
    [697,697,"CAS CONSTRUCTION","Galway City","Cul Garrai, Rahoon",6,"Peter Triest Housing Association Ltd","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [698,698,"CAS CONSTRUCTION","Galway City","Doughiska, Galway City",7,"Respond","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [699,699,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Galway City","Ballyburke",74,"*N/A","","","","","Q4-2019",""],
    [700,700,"SHIP CONSTRUCTION","Galway City","Ballymoneen Road (Phase 2)",78,"*N/A","","","","","Q2-2019",""],
    [701,701,"SHIP CONSTRUCTION","Galway City","Ballymoneen Road (Phase 1)",14,"*N/A","","","","","","Q2-2018"],
    [702,702,"SHIP CONSTRUCTION","Galway City","Monivea Road, Ballybaan More",7,"*N/A","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [703,703,"SHIP CONSTRUCTION","Galway City","Monivea Road, Ballybaan More",58,"*N/A","","","Stage 3 approved Q2-2019, the scheme is now approved to proceed to tender.","","",""],
    [704,704,"SHIP CONSTRUCTION","Galway City","Headford Road, Castlegar",70,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [705,705,"SHIP CONSTRUCTION","Galway City","Tirellan Heights, Headford Road",4,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [706,706,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Gr�ine (Glasshouse Site), Monivea Road - (Phase 2)",16,"*N/A","","","","","","Q4-2019"],
    [707,707,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Gr�ine (Glasshouse Site), Monivea Road - (Phase 3)",7,"*N/A","","","","","","Q4-2019"],
    [708,708,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Gr�ine, (Glasshouse Site) Monivea Road (Phase 1)",6,"*N/A","","","","","","Q3-2019"],
    [709,709,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Gr�ine (Glasshouse Site), Monivea Road - (Phase 4)",17,"*N/A","","","","","Q4-2018",""],
    [710,710,"SHIP CONSTRUCTION TURNKEY","Galway City","Radharc na Gr�ine (Glasshouse Site), Monivea Road - (Phase 5)",4,"*N/A","","","","","Q4-2018",""],
    [711,711,"CALF Construction","Galway County","Spiddal Cottages, Co Galway (Phase 1)",23,"Cluid Housing","","","","","","Q3-2017"],
    [712,712,"CALF Turnkey","Galway County","Cnoc na Si, Portumna, Co Galway (Phase 1)",10,"Co-operative Housing Ireland","","","","","","Q2-2018"],
    [713,713,"CALF Turnkey","Galway County","Dunloe Street, Ballinasloe, Co. Galway (Phase 1)",9,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [714,714,"CALF Turnkey","Galway County","Tir an Choir, Vicars Choral, Tuam, Co. Galway (Phase 1)",12,"Co-operative Housing Ireland","","","","Q3-2019","",""],
    [715,715,"CAS CONSTRUCTION","Galway County","Letterfrack (Phase 2)",11,"Cluid Housing Association","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [716,716,"CAS CONSTRUCTION","Galway County","Rossaveal Cottages, Ros a Mh�l, South Connemara",8,"Tearmann Eanna Teoranta","Stage 1 approved Q4-2016, outline design and costs being prepared.","","","","",""],
    [717,717,"CAS CONSTRUCTION","Galway County","Mountbellew",5,"Mountbellew Voluntary Homes Association","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [718,718,"CAS CONSTRUCTION","Galway County","Springfield, Parkmore (Ballinasloe)",4,"Peter Triest Housing Association Ltd","Stage 1 approved Q2-2017, outline design and costs being prepared.","","","","",""],
    [719,719,"CAS CONSTRUCTION","Galway County","Letterfrack (Phase 1)",13,"Cluid Housing Association","","","","","","Q2-2016"],
    [720,720,"CAS CONSTRUCTION","Galway County","Dunlo Hill, Ballinasloe",18,"Cluid Housing Association","","","","","Q4-2018",""],
    [721,721,"CAS CONSTRUCTION","Galway County","Caheroyn, Athenry",4,"Peter Triest Housing Association Ltd","Stage 1 approved Q3-2017, outline design and costs being prepared.","","","","",""],
    [722,722,"CAS CONSTRUCTION","Galway County","Aggard More, Craughwell",4,"Peter Triest Housing Association Ltd","","","","","","Q4-2019"],
    [723,723,"CAS CONSTRUCTION","Galway County","The Old Post Office, Inverin",4,"Tearmann Eanna Teoranta","","","","","Q4-2019",""],
    [724,724,"CAS CONSTRUCTION","Galway County","Cregboy, Claregalway",14,"Claregalway and District Day Care Centre","","","","","","Q3-2019"],
    [725,725,"CAS CONSTRUCTION TURNKEY","Galway County","Tubber Road, Gort",11,"Inis Housing Association Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [726,726,"SHIP CONSTRUCTION","Galway County","Corndulla (SRD)",1,"*N/A","","","","","","Q1-2019"],
    [727,727,"SHIP CONSTRUCTION","Galway County","Ardrahan (SRD)",1,"*N/A","","","","","","Q4-2017"],
    [728,728,"SHIP CONSTRUCTION","Galway County","Callowfinish, Carna (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [729,729,"SHIP CONSTRUCTION","Galway County","Waterdale, Claregalway (SRD)",1,"*N/A","","","","","","Q4-2018"],
    [730,730,"SHIP CONSTRUCTION","Galway County","Esker Fields, Ballinasloe",2,"*N/A","","","","","","Q4-2019"],
    [731,731,"SHIP CONSTRUCTION","Galway County","Cill Ciar�n (SRD)",1,"*N/A","","","","","","Q3-2018"],
    [732,732,"SHIP CONSTRUCTION","Galway County","Kinvara (SRD)",1,"*N/A","","","","","","Q3-2018"],
    [733,733,"SHIP CONSTRUCTION","Galway County","Cnoc na Carraige, Roundstone",10,"*N/A","","","","","Q3-2019",""],
    [734,734,"SHIP CONSTRUCTION","Galway County","Hospital Road, Clifden",26,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [735,735,"SHIP CONSTRUCTION","Galway County","Bridge Court, Ahascragh, Ballinasloe",17,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [736,736,"SHIP CONSTRUCTION","Galway County","Caisle�n Raithl�n, Ardrahan",12,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [737,737,"SHIP CONSTRUCTION","Galway County","Barrack Street, Loughrea",5,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [738,738,"SHIP CONSTRUCTION","Galway County","Garbally Drive, Ballinasloe",10,"*N/A","","","","","","Q3-2019"],
    [739,739,"SHIP CONSTRUCTION","Galway County","Cartron, Kinvarra",10,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [740,740,"SHIP CONSTRUCTION","Galway County","Gort U� Lochlainn, Moycullen",31,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [741,741,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam",16,"*N/A","","","","","","Q4-2018"],
    [742,742,"SHIP CONSTRUCTION","Galway County","T�r an Bhu�, Tuam",51,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [743,743,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam, Phase 3",19,"*N/A","","","","","","Q4-2019"],
    [744,744,"SHIP CONSTRUCTION","Galway County","Cnoc na Carraige , Roundstone",4,"*N/A","","","","","Q3-2019",""],
    [745,745,"SHIP CONSTRUCTION","Galway County","Gilmartin Road, Tuam. Phase 2",24,"*N/A","","","","","","Q3-2019"],
    [746,746,"SHIP CONSTRUCTION","Galway County","Na Clocha Rua, An Cheathr� Rua",4,"*N/A","","","","","","Q4-2019"],
    [747,747,"SHIP CONSTRUCTION TURNKEY","Galway County","Arvough, Kinvara",4,"*N/A","","","","","","Q4-2019"],
    [748,748,"SHIP CONSTRUCTION TURNKEY","Galway County","Lorro gate, Prospect, Athenry",14,"*N/A","","","","","","Q4-2017"],
    [749,749,"SHIP CONSTRUCTION TURNKEY","Galway County","Arvough, Kinvara",6,"*N/A","","","","","","Q4-2017"],
    [750,750,"SHIP CONSTRUCTION TURNKEY","Galway County","Castlecourt, Abbey Street, Portumna",10,"*N/A","","","","","","Q4-2017"],
    [751,751,"SHIP CONSTRUCTION TURNKEY","Galway County","Ashthorn Avenue, Headford",10,"*N/A","","","","","","Q4-2018"],
    [752,752,"SHIP CONSTRUCTION TURNKEY","Galway County","Cuirt na hAbhann, Claregalway ",8,"*N/A","","","","","","Q4-2018"],
    [753,753,"SHIP CONSTRUCTION TURNKEY","Galway County","An Fuaran Estate, Oranmore",4,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [754,754,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen",8,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [755,755,"SHIP CONSTRUCTION TURNKEY","Galway County","Garra� Mhic Aodha, Tubber Road, Gort",20,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [756,756,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea -  Phase 2",25,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [757,757,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",3,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [758,758,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",6,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [759,759,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",12,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [760,760,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",8,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [761,761,"SHIP CONSTRUCTION TURNKEY","Galway County","Kylebroughlan, Moycullen ",7,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [762,762,"SHIP CONSTRUCTION TURNKEY","Galway County","Garra� Mhic Aodha, Tubber Road, Gort (Phase 2)",11,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [763,763,"SHIP CONSTRUCTION TURNKEY","Galway County","Tullahill, Loughrea",36,"*N/A","","","","","","Q4-2019"],
    [764,764,"CALF Turnkey","Kerry","Barraduff, Killarney, Co. Kerry (Phase 1)*",56,"Co-operative Housing Ireland","","","","Q3-2019","",""],
    [765,765,"CALF Turnkey","Kerry","Cathair Lakes Farrantoreen Road, Killorglin, Co Kerry (Phase 1)",5,"Cluid Housing","","","","","","Q2-2016"],
    [766,766,"CALF Turnkey","Kerry","Commons East, Ardfert, Co. Kerry (Phase 1)*",6,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [767,767,"CALF Turnkey","Kerry","Commons East, Ardfert, Co. Kerry (Phase 2)",6,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [768,768,"CALF Turnkey","Kerry","Commons East, Ardfert, Co. Kerry (Phase 3)",10,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [769,769,"CALF Turnkey","Kerry","Commons East, Ardfert, Co. Kerry (Phase 4)",8,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [770,770,"CALF Turnkey","Kerry","Deerpark Avenue, Tralee, Co. Kerry (Phase 1)",4,"Co-operative Housing Ireland","","","","","Q1-2019",""],
    [771,771,"CALF Turnkey","Kerry","Derreen, Killarney, Co Kerry  (Phase 1)*",61,"Cluid Housing","","","","","Q4-2018",""],
    [772,772,"CALF Turnkey","Kerry","Doon Road, Lisloose, Tralee, Co. Kerry (Phase 1)*",14,"Co-operative Housing Ireland","","","","","Q4-2018",""],
    [773,773,"CALF Turnkey","Kerry","Dromcairn, Tralee, Co. Kerry (Phase 1)",12,"Cluid Housing","","","","","Q1-2019",""],
    [774,774,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 1)",14,"Respond","","","","","","Q4-2018"],
    [775,775,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 3)",6,"Respond","","","","","Q3-2018",""],
    [776,776,"CALF Turnkey","Kerry","Fir na Fiuise, Gortanora, Dingle, Co. Kerry (Phase 1)",5,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [777,777,"CALF Turnkey","Kerry"," Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 2)",2,"Respond","","","","","","Q4-2019"],
    [778,778,"CALF Turnkey","Kerry","The Grove, Dingle, Co. Kerry (Phase 1)*",20,"Cluid Housing","","","","","Q1-2019",""],
    [779,779,"CALF Turnkey","Kerry","Fortfield, Tralee, Co. Kerry (Phase 1)*",15,"Cluid Housing","","","","","","Q4-2019"],
    [780,780,"CALF Turnkey","Kerry","Killeen, Abbeydorney Road, Tralee, Co. Kerry (Phase 1)*",17,"Cluid Housing","","","","","","Q4-2019"],
    [781,781,"CALF Turnkey","Kerry","Oakwood, Coolegrean, Killarney, Co. Kerry (Phase 1)",59,"Cluid Housing","","","","","","Q3-2019"],
    [782,782,"CAS CONSTRUCTION","Kerry","Armagh House, Killarney",6,"Cluid Housing Association","","","","","Q4-2019",""],
    [783,783,"CAS CONSTRUCTION","Kerry","22 College Road, Castleisland",4,"Kerry Emigrant Support Housing Association Ltd","","","","","","Q4-2018"],
    [784,784,"CAS CONSTRUCTION","Kerry","Chamfers Place (Mitchels road, Tralee)",18,"Cluid Housing Association","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [785,785,"CAS CONSTRUCTION","Kerry","The Parsonage, Caherciveen",5,"Caherciveen Social Services (Housing) Ltd","","","","","","Q4-2018"],
    [786,786,"CAS CONSTRUCTION","Kerry","Hawley Park Apartments, St Martins Park, Mitchels Rd, Tralee",15,"Kingdom Voluntary Housing Association","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [787,787,"CAS CONSTRUCTION","Kerry","The Presentation Convent, Rathmore",4,"Social Action Group Rathmore","","","","","Q4-2018",""],
    [788,788,"REGENERATION","Kerry","Croilar Na Mistaelach, Tralee",11,"*N/A","","","","","","Q4-2018"],
    [789,789,"REGENERATION","Kerry","Urban Terrace, Tralee",2,"*N/A","","","","","","Q4-2016"],
    [790,790,"REGENERATION","Kerry","Clonmore Road, Tralee",3,"*N/A","","","","","","Q4-2016"],
    [791,791,"REGENERATION","Kerry","St Martin's Park, Tralee",4,"*N/A","","","","","","Q4-2018"],
    [792,792,"REGENERATION","Kerry","Dingle Road, Tralee",1,"*N/A","","","","","","Q2-2018"],
    [793,793,"SHIP CONSTRUCTION","Kerry","Cois Gallain, Killorglin",14,"*N/A","","","","","","Q4-2019"],
    [794,794,"SHIP CONSTRUCTION","Kerry","Rathmore/Barraduff",20,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [795,795,"SHIP CONSTRUCTION","Kerry","Ardbhearna, Kenmare",22,"*N/A","","","","","","Q4-2018"],
    [796,796,"SHIP CONSTRUCTION","Kerry","Bill Kinnerk Road, Tralee",4,"*N/A","","","","","","Q1-2018"],
    [797,797,"SHIP CONSTRUCTION","Kerry","Courthouse Lawn, Listowel",7,"*N/A","","","","","","Q4-2019"],
    [798,798,"SHIP CONSTRUCTION","Kerry","Cuirt Eaglaise, Milltown",8,"*N/A","","","","","","Q4-2019"],
    [799,799,"SHIP CONSTRUCTION","Kerry","Lixnaw",4,"*N/A","","","","","","Q4-2017"],
    [800,800,"SHIP CONSTRUCTION","Kerry","The Park, Killarney",20,"*N/A","","","","","","Q1-2018"],
    [801,801,"SHIP CONSTRUCTION","Kerry","Dreenagh, Ballyheigue (SRD)",1,"*N/A","","","","","","Q1-2017"],
    [802,802,"SHIP CONSTRUCTION","Kerry","Glenach, Ballybunion",20,"*N/A","","","","","Q4-2019",""],
    [803,803,"SHIP CONSTRUCTION","Kerry","Callinafercy, Milltown",1,"*N/A","","","","","","Q4-2018"],
    [804,804,"SHIP CONSTRUCTION","Kerry","Cahernaboshina, Ventry",1,"*N/A","","","","","","Q4-2018"],
    [805,805,"SHIP CONSTRUCTION","Kerry","An Carrigin, Tralee",28,"*N/A","","","","","Q2-2019",""],
    [806,806,"SHIP CONSTRUCTION","Kerry","Pinewood Estate, Killarney",1,"*N/A","","","","","","Q4-2018"],
    [807,807,"SHIP CONSTRUCTION","Kerry","Drom West, Glenbeigh",1,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [808,808,"SHIP CONSTRUCTION","Kerry","Killeen, Tralee",21,"*N/A","","","","","","Q3-2019"],
    [809,809,"SHIP CONSTRUCTION","Kerry","Meanus, Killorglin",1,"*N/A","","","","","","Q3-2019"],
    [810,810,"SHIP CONSTRUCTION","Kerry","Lohercannon, Tralee",61,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [811,811,"SHIP CONSTRUCTION","Kerry","BallinaKilly Lower, Glenbeigh",1,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [812,812,"SHIP CONSTRUCTION","Kerry","Ashgrove, Listowel",1,"*N/A","","","","","","Q3-2017"],
    [813,813,"SHIP CONSTRUCTION","Kerry","Cullenagh Upper, Beaufort",1,"*N/A","","","Stage 3 approved Q4-2017, the scheme is now approved to proceed to tender.","","",""],
    [814,814,"SHIP CONSTRUCTION","Kerry","Farranwilliam, Ardfert",22,"*N/A","","","","","Q3-2019",""],
    [815,815,"SHIP CONSTRUCTION","Kerry","Ballyrickard, Tralee",21,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [816,816,"SHIP CONSTRUCTION","Kerry","Crogorts, Tralee",30,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [817,817,"SHIP CONSTRUCTION","Kerry","Rock Rd., Killarney",10,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [818,818,"SHIP CONSTRUCTION","Kerry","Gortamullin, Kenmare (Phase4)",14,"*N/A","","","","","Q4-2019",""],
    [819,819,"SHIP CONSTRUCTION","Kerry","Baile an Gharra�, Lixnaw (PHASE 2)",10,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [820,820,"SHIP CONSTRUCTION","Kerry","Woodview Place, Tarbert",22,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [821,821,"SHIP CONSTRUCTION","Kerry","Marconi South, Ballybunion",12,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [822,822,"SHIP CONSTRUCTION","Kerry","Rahoonane - New Site, Tralee",8,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [823,823,"SHIP CONSTRUCTION","Kerry","Rusheen, Ballylongford",6,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [824,824,"SHIP CONSTRUCTION","Kerry","Owngarry, Killorglin",1,"*N/A","","","","","","Q4-2019"],
    [825,825,"SHIP CONSTRUCTION","Kerry","Tullig Beg, Killorglin",1,"*N/A","","","","","","Q3-2019"],
    [826,826,"SHIP CONSTRUCTION","Kerry","Glannagilliagh, Caragh Lake, Killorglin (SRD)",1,"*N/A","","","","","Q4-2019",""],
    [827,827,"SHIP CONSTRUCTION","Kerry","Knockawinna, Brosna, Co Kerry",1,"*N/A","","","","","Q4-2019",""],
    [828,828,"SHIP CONSTRUCTION","Kerry","Carrigcannon, Lyreacrumpane (SRD)",1,"*N/A","","","","","Q4-2019",""],
    [829,829,"SHIP CONSTRUCTION","Kerry","Cleandries, Causeway",1,"*N/A","","","","","Q4-2019",""],
    [830,830,"SHIP CONSTRUCTION","Kerry","Pinewood Estate, Killarney",6,"*N/A","","","","","","Q4-2019"],
    [831,831,"SHIP CONSTRUCTION TURNKEY","Kerry","Ardmoniel Heights, Killorglin - Phase 2",1,"*N/A","","","","","","Q2-2019"],
    [832,832,"SHIP CONSTRUCTION TURNKEY","Kerry","Ballygologue, Road, Listowel",2,"*N/A","","","","","","Q4-2019"],
    [833,833,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole",2,"*N/A","","","","","","Q1-2018"],
    [834,834,"SHIP CONSTRUCTION TURNKEY","Kerry","1-4 Steeple Meadow View, Milltown",4,"*N/A","","","","","","Q4-2017"],
    [835,835,"SHIP CONSTRUCTION TURNKEY","Kerry","Meadow Park, Milltown",9,"*N/A","","","","","","Q2-2018"],
    [836,836,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole, Phase 2",5,"*N/A","","","","","","Q3-2018"],
    [837,837,"SHIP CONSTRUCTION TURNKEY","Kerry","Ardmoniel Heights, Killorglin",3,"*N/A","","","","","","Q4-2018"],
    [838,838,"SHIP CONSTRUCTION TURNKEY","Kerry","47 Woodview, Cahirdown, Listowel",1,"*N/A","","","","","","Q2-2018"],
    [839,839,"SHIP CONSTRUCTION TURNKEY","Kerry","Dromin Upper, Listowel",8,"*N/A","","","","Stage 4 approved Q4-2018, the scheme is fully approved.","",""],
    [840,840,"SHIP CONSTRUCTION TURNKEY","Kerry","Ard Na Si, Lispole, Phase 3",3,"*N/A","","","","","","Q4-2018"],
    [841,841,"SHIP CONSTRUCTION RAPID","Kildare","Old Greenfield Road, Maynooth",47,"*N/A","Stage 1 approved Q4-2017, outline design and costs being prepared.","","","","",""],
    [842,842,"CALF Construction","Kildare","Castlefen, Castlesize, Sallins, Co. Kildare (Phase 1)",29,"T�ath Housing Association Ltd","","","","Q4-2019","",""],
    [843,843,"CALF Construction","Kildare","Flinters Field (Phase 2), Athy, Co. Kildare (Phase 1)",35,"Respond","","","","Q2-2019","",""],
    [844,844,"CALF Turnkey","Kildare","Bellingsfield, Naas, Kildare (Phase 1)*",10,"Respond","","","","","","Q4-2018"],
    [845,845,"CALF Turnkey","Kildare","Carton Grove, Maynooth, Co. Kildare (Phase 1)*",5,"Clanmil Housing Association Ireland","","","","","","Q4-2018"],
    [846,846,"CALF Turnkey","Kildare","Castle Farm, Jigginstown, Naas, Co. Kildare (Phase 1)",8,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [847,847,"CALF Turnkey","Kildare","Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 2)*",2,"T�ath Housing Association Ltd","","","","","Q2-2018",""],
    [848,848,"CALF Turnkey","Kildare","Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 3)*",15,"T�ath Housing Association Ltd","","","","","Q2-2018",""],
    [849,849,"CALF Turnkey","Kildare","Elsmore, Jigginstown, Nass, Co. Kildare (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [850,850,"CALF Turnkey","Kildare","Castle Farm, Naas, Co. Kildare (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [851,851,"CALF Turnkey","Kildare","Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 1)*",6,"Cill Dara Housing Association","","","","","","Q4-2019"],
    [852,852,"CALF Turnkey","Kildare","Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 2)*",11,"Cill Dara Housing Association","","","","","","Q4-2019"],
    [853,853,"CALF Turnkey","Kildare","Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 1)*",26,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [854,854,"CALF Turnkey","Kildare","Elsmore, Jigginstown, Nass, Co. Kildare (Phase 2)*",3,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [855,855,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 1)",18,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [856,856,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 2)",6,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [857,857,"CALF Turnkey","Kildare","Kilbelin Abbey, Newbridge, Co. Kildare (Phase 1)*",4,"Cluid Housing","","","","","Q2-2019",""],
    [858,858,"CALF Turnkey","Kildare","Kilbelin Abbey, Newbridge, Co. Kildare (Phase 2)*",4,"Cluid Housing","","","","","Q2-2019",""],
    [859,859,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 3)",6,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [860,860,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 4)",6,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [861,861,"CALF Turnkey","Kildare","Millfield Manor, Newbridge, Co. Kildare (Phase 1)*",19,"Cluid Housing","","","","","","Q3-2018"],
    [862,862,"CALF Turnkey","Kildare","Morristown, Newbridge, Co Kildare (Phase 1)",14,"Cluid Housing","","","","","","Q1-2018"],
    [863,863,"CALF Turnkey","Kildare","Morristown, Newbridge, Co. Kildare (Phase 1)*",4,"Cluid Housing","","","","","","Q2-2018"],
    [864,864,"CALF Turnkey","Kildare","Oaktree, Tully Road, Kildare Town (Phase 1)*",10,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [865,865,"CALF Turnkey","Kildare","Oaktree, Tully Road, Kildare Town (Phase 2)*",7,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [866,866,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 5)",4,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [867,867,"CALF Turnkey","Kildare","Revised Rye Abbey, Kilcock, Co Kildare (apts)\\n (Phase 1)",33,"Cluid Housing","","","","","","Q2-2017"],
    [868,868,"CALF Turnkey","Kildare","Robertstown, Naas , Co.Kildare (Phase 1)",5,"Co-operative Housing Ireland","","","","","Q2-2018",""],
    [869,869,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 1)",13,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [870,870,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 2)",16,"T�ath Housing Association Ltd","","","","","","Q4-2017"],
    [871,871,"CALF Turnkey","Kildare","Roseberry Hill, Newbridge (Phase 3)",16,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [872,872,"CALF Turnkey","Kildare","Rye Abbey, Kilcock - revised (houses) (Phase 1)",4,"Cluid Housing","","","","","","Q2-2017"],
    [873,873,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 6)",5,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [874,874,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 2)*",7,"Cluid Housing","","","","","Q4-2018",""],
    [875,875,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 3)*",12,"Cluid Housing","","","","","Q4-2018",""],
    [876,876,"CALF Turnkey","Kildare","Fenton Green, Kilcock, Co Kildare  (Phase 7)*",18,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [877,877,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)*",18,"Respond","","","","","Q3-2019",""],
    [878,878,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 2)",32,"Respond","","","","","Q4-2018",""],
    [879,879,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 1)*",14,"Cluid Housing","","","","","","Q4-2018"],
    [880,880,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 2)",24,"Cluid Housing","","","","","","Q4-2018"],
    [881,881,"CALF Turnkey","Kildare","Hawthorn Manor, Brockagh, Coill Dubh, Co. Kildare (Phase 1)*",5,"Oaklee Housing","","","","","","Q4-2019"],
    [882,882,"CALF Turnkey","Kildare","Ledwill Park, Kilcock, Co. Kildare (Phase 1)*",31,"Cluid Housing","","","","","","Q4-2019"],
    [883,883,"CALF Turnkey","Kildare","Mariavilla and Elsmore, Kildare (Phase 1)*",15,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [884,884,"CALF Turnkey","Kildare","Phase 2, White Oaks, Newbridge, Kildare (Phase 1)",36,"Cluid Housing","","","","","","Q4-2019"],
    [885,885,"CALF Turnkey","Kildare","The Paddocks, Morristown, Newbridge, Kildare (Phase 1)*",5,"Cluid Housing","","","","","","Q4-2019"],
    [886,886,"CALF Turnkey","Kildare","The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)",18,"Respond","","","","","","Q4-2019"],
    [887,887,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 3)",20,"Cluid Housing","","","","","","Q1-2019"],
    [888,888,"CALF Turnkey","Kildare","White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 4)",2,"Cluid Housing","","","","","","Q4-2019"],
    [889,889,"CAS CONSTRUCTION","Kildare","Craddockstown, Naas",3,"KARE Promoting Inclusion for People with Intellectual Disabilities","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [890,890,"CAS CONSTRUCTION","Kildare","Main St., Kilcullen",4,"Camphill Communities of Ireland","","Stage 2 approved Q4-2017, full design/tender being prepared.","","","",""],
    [891,891,"CAS CONSTRUCTION","Kildare","El Kantara, Newbridge",2,"KARE Promoting Inclusion for People with Intellectual Disabilities","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [892,892,"CAS CONSTRUCTION","Kildare","Jigginstown House, Naas",12,"Homeless Care Ltd","","","","","Q4-2019",""],
    [893,893,"CAS CONSTRUCTION","Kildare","St. John's Convent, New Street, Rathangan",28,"Sophia Housing Association Ltd","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [894,894,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Kildare","Craddockstown, Naas",74,"*N/A","","","","","Q1-2019",""],
    [895,895,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Kildare","Butterstream, Clane",77,"*N/A","","","","","Q1-2019",""],
    [896,896,"SHIP CONSTRUCTION","Kildare","Beechgrove, Rathangan",18,"*N/A","","","","","","Q4-2019"],
    [897,897,"SHIP CONSTRUCTION","Kildare","Dunmurry Rise, Bishopsland, Kildare Town",32,"*N/A","","","","","","Q3-2019"],
    [898,898,"SHIP CONSTRUCTION","Kildare","Hillview Terrace, Narraghmore",4,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [899,899,"SHIP CONSTRUCTION","Kildare","Athgarvan Village",18,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [900,900,"SHIP CONSTRUCTION","Kildare","Rathasker Road, Naas",48,"*N/A","Stage 1 approved Q1-2016, outline design and costs being prepared.","","","","",""],
    [901,901,"SHIP CONSTRUCTION","Kildare","Anne Street, Prosperous",12,"*N/A","","","","","Q1-2019",""],
    [902,902,"SHIP CONSTRUCTION","Kildare","Kilcock (Phase 2.1)",6,"*N/A","","","","","","Q4-2017"],
    [903,903,"SHIP CONSTRUCTION","Kildare","Athgarvan Road, Newbridge",13,"*N/A","","","","","","Q3-2018"],
    [904,904,"SHIP CONSTRUCTION","Kildare","Newtown, Leixlip",4,"*N/A","Stage 1 approved Q3-2017, outline design and costs being prepared.","","","","",""],
    [905,905,"SHIP CONSTRUCTION","Kildare","Coill Dubh",10,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [906,906,"SHIP CONSTRUCTION","Kildare","Kilcock (Phase 2.2)",13,"*N/A","","","","","","Q1-2018"],
    [907,907,"SHIP CONSTRUCTION","Kildare","Skenagun, Castledermot",2,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [908,908,"SHIP CONSTRUCTION TURNKEY","Kildare","Beech Park Wood, Leixlip",4,"*N/A","","","","","","Q3-2019"],
    [909,909,"SHIP CONSTRUCTION TURNKEY","Kildare","Brookes Mill Prosperous",1,"*N/A","","","","","","Q4-2019"],
    [910,910,"SHIP CONSTRUCTION TURNKEY","Kildare","Cluain Dara, Derrinturn, Kildare",1,"*N/A","","","","","","Q2-2019"],
    [911,911,"SHIP CONSTRUCTION TURNKEY","Kildare","Greenfield, Maynooth",1,"*N/A","","","","","","Q4-2019"],
    [912,912,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",3,"*N/A","","","","","","Q4-2019"],
    [913,913,"SHIP CONSTRUCTION TURNKEY","Kildare","Bodkin Place, Kilmeague",16,"*N/A","","","","","","Q4-2017"],
    [914,914,"SHIP CONSTRUCTION TURNKEY","Kildare","Drogheda Street, Monasterevin",6,"*N/A","","","","","","Q4-2017"],
    [915,915,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town",8,"*N/A","","","","","","Q3-2018"],
    [916,916,"SHIP CONSTRUCTION TURNKEY","Kildare","Moore Abbey Court, Monasterevin",2,"*N/A","","","","","","Q1-2018"],
    [917,917,"SHIP CONSTRUCTION TURNKEY","Kildare","Drogheda Street, Monasterevin (Phase 2)",7,"*N/A","","","","","","Q1-2018"],
    [918,918,"SHIP CONSTRUCTION TURNKEY","Kildare","Moss Brook, Prosperous",2,"*N/A","","","","","","Q1-2018"],
    [919,919,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",2,"*N/A","","","","","","Q4-2018"],
    [920,920,"SHIP CONSTRUCTION TURNKEY","Kildare","Whitethorn Park, Allenwood",2,"*N/A","","","","","","Q3-2018"],
    [921,921,"SHIP CONSTRUCTION TURNKEY","Kildare","The Pike, Castledermot",6,"*N/A","","","","","","Q4-2018"],
    [922,922,"SHIP CONSTRUCTION TURNKEY","Kildare","Grove Lane, Robertstown",3,"*N/A","","","","","Q1-2019",""],
    [923,923,"SHIP CONSTRUCTION TURNKEY","Kildare","Brookes Mill, Prosperous",5,"*N/A","","","","","","Q4-2018"],
    [924,924,"SHIP CONSTRUCTION TURNKEY","Kildare","The Green, Elsmore Naas",5,"*N/A","","","","","","Q4-2018"],
    [925,925,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",19,"*N/A","","","","","Q4-2018",""],
    [926,926,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town",18,"*N/A","","","","","","Q2-2019"],
    [927,927,"SHIP CONSTRUCTION TURNKEY","Kildare","Oaktree, Tully Road, Kildare Town (Phase 2)",20,"*N/A","","","","","","Q3-2019"],
    [928,928,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",10,"*N/A","","","","","","Q1-2019"],
    [929,929,"SHIP CONSTRUCTION TURNKEY","Kildare","Oakwood Park, Derrinturn ",10,"*N/A","","","","","","Q3-2019"],
    [930,930,"SHIP CONSTRUCTION TURNKEY","Kildare","School Walk, Allenwood",4,"*N/A","","","","","","Q4-2019"],
    [931,931,"SHIP CONSTRUCTION TURNKEY","Kildare","Stoneleigh, Naas",6,"*N/A","","","","","","Q4-2019"],
    [932,932,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [933,933,"SHIP CONSTRUCTION TURNKEY","Kildare","The Willows, Allenwood",4,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [934,934,"SHIP CONSTRUCTION TURNKEY","Kildare","Barrack Close, Ballymore Eustace",4,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [935,935,"SHIP CONSTRUCTION TURNKEY","Kildare","Hawthorn Manor, Brockagh, Coill Dubh",21,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [936,936,"CALF Construction","Kilkenny","Park Lane, Friary Walk, Callan, Co Kilkenny (Phase 1)*",16,"Cluid Housing","","","","","","Q2-2019"],
    [937,937,"CALF Construction","Kilkenny","Walkin St Kilkenny (Phase 1)",27,"Oaklee Housing","","","","","","Q4-2019"],
    [938,938,"CALF Turnkey","Kilkenny","Castlehyde, Rosbercon (Phase 1)",4,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [939,939,"CALF Turnkey","Kilkenny","Castlehyde, Rosbercon (Phase 2)",6,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [940,940,"CALF Turnkey","Kilkenny","Logan Square, Thomastown, Co Kilkenny (Phase 1)*",16,"Oaklee Housing","","","","","","Q2-2017"],
    [941,941,"CALF Turnkey","Kilkenny","Margaret�s Field, Callan Road, Kilkenny City (Phase 1)",40,"Respond","","","","","Q1-2019",""],
    [942,942,"CALF Turnkey","Kilkenny","Nuncio Road, Kilkenny (Phase 1)*",50,"Respond","","","","","Q4-2018",""],
    [943,943,"CALF Turnkey","Kilkenny","O�Loughlin Court, Kilkenny  (Phase 1)",2,"Respond","","","","","","Q4-2018"],
    [944,944,"CALF Turnkey","Kilkenny","Side Road, Moneenroe, Castlecomer, Co. Kilkenny (Phase 1)",9,"Oaklee Housing","","","","","","Q3-2018"],
    [945,945,"CALF Turnkey","Kilkenny","Golf Links Road, Kilkenny (Phase 1)*",39,"Respond","","","","","","Q4-2019"],
    [946,946,"CALF Turnkey","Kilkenny","Love Lane, Castlecomer, Co. Kilkenny (Phase 1)",4,"Co-operative Housing Ireland","","","","","","Q3-2019"],
    [947,947,"CAS CONSTRUCTION","Kilkenny","Bridge Street, Callan",6,"Good Shepherd Services Ltd","","","","","","Q4-2019"],
    [948,948,"CAS CONSTRUCTION","Kilkenny","Kingsriver, Ennisnag",4,"Kingsriver Housing Association Limited","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [949,949,"CAS CONSTRUCTION","Kilkenny","Garrin Green",6,"SOS Kilkenny Housing Association Ltd","","","","","","Q4-2018"],
    [950,950,"CAS CONSTRUCTION","Kilkenny","Hazelbrook, Newrath",2,"Waterford Dove Housing Association","","","","","","Q1-2018"],
    [951,951,"CAS CONSTRUCTION","Kilkenny","Good Shepherd Centre - Wing 1952",12,"The Good Shepherd Centre (Kilkenny) Ltd","","","","","","Q4-2018"],
    [952,952,"CAS CONSTRUCTION","Kilkenny","\"Brooke House\", Thomastown",5,"Camphill Communities of Ireland","","","","","","Q3-2017"],
    [953,953,"CAS CONSTRUCTION","Kilkenny","Friary Walk, Callan",12,"Cluid Housing Association","","","","","","Q3-2016"],
    [954,954,"CAS CONSTRUCTION","Kilkenny","Garden Cottage, The Workhouse, Callan",1,"Camphill Communities of Ireland","","","","","","Q4-2017"],
    [955,955,"CAS CONSTRUCTION","Kilkenny","\"Red Barn\" Patrick Street, Ballyragget",12,"Good Shepherd Services Ltd","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [956,956,"CAS CONSTRUCTION","Kilkenny","Smith's Road, Ballyraggett",4,"Oaklee Housing Trust","","","","","","Q4-2018"],
    [957,957,"CAS CONSTRUCTION","Kilkenny","Fennelly's Lane Jerpoint",3,"Camphill Communities of Ireland","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [958,958,"CAS CONSTRUCTION","Kilkenny","8/9 Kilkenny Street, Castlecomer",4,"Good Shepherd Services Ltd","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [959,959,"CAS CONSTRUCTION","Kilkenny","19/21 Blackmill Street, Kilkenny",12,"Good Shepherd Services Ltd","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [960,960,"CAS CONSTRUCTION","Kilkenny","Brother Thomas Place, Church Lane, Kilkenny",12,"Good Shepherd Services Ltd","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [961,961,"CAS CONSTRUCTION","Kilkenny","Grennan Villa, Thomastown",5,"Camphill Communities of Ireland","","","Stage 3 approved Q4-2018, the scheme is now approved to proceed to tender.","","",""],
    [962,962,"CAS CONSTRUCTION","Kilkenny","Fiennes Court, William Street, Kilkenny",7,"Good Shepherd Services Ltd","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [963,963,"CAS CONSTRUCTION","Kilkenny","St. John of god Convent, College Road, Kilkenny",12,"Sophia Housing Association Ltd","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [964,964,"CAS CONSTRUCTION TURNKEY","Kilkenny","Golf Links Road, Kilkenny",15,"Respond","","","","","","Q3-2019"],
    [965,965,"SHIP CONSTRUCTION","Kilkenny","Blackstaff House, Callan",4,"*N/A","","","","","","Q4-2019"],
    [966,966,"SHIP CONSTRUCTION","Kilkenny","Barna, Freshford",1,"*N/A","","","","","","Q2-2018"],
    [967,967,"SHIP CONSTRUCTION","Kilkenny","10 Golf Links Road, Kilkenny",6,"*N/A","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [968,968,"SHIP CONSTRUCTION","Kilkenny","Crokers Hill (Phase 2) Kennyswell Road, Kilkenny",35,"*N/A","Stage 1 approved Q2-2017, outline design and costs being prepared.","","","","",""],
    [969,969,"SHIP CONSTRUCTION","Kilkenny","Main Street, Piltown",17,"*N/A","","","","","Q1-2019",""],
    [970,970,"SHIP CONSTRUCTION","Kilkenny","Station Road, Ballyragget",22,"*N/A","","","","","Q3-2019",""],
    [971,971,"SHIP CONSTRUCTION","Kilkenny","Bolton, Callan",38,"*N/A","","","","","Q2-2018",""],
    [972,972,"SHIP CONSTRUCTION","Kilkenny","Donaguile, Castlecomer",33,"*N/A","","","","","Q1-2019",""],
    [973,973,"SHIP CONSTRUCTION","Kilkenny","Rosehill, Kells Road, Kilkenny",6,"*N/A","","","","","","Q1-2017"],
    [974,974,"SHIP CONSTRUCTION","Kilkenny","Gaol Road, Kilkenny",10,"*N/A","","","","","","Q3-2016"],
    [975,975,"SHIP CONSTRUCTION","Kilkenny","Greensbridge House",5,"*N/A","","","","","","Q4-2018"],
    [976,976,"SHIP CONSTRUCTION","Kilkenny","The Broguemaker, Kilkenny",18,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [977,977,"SHIP CONSTRUCTION","Kilkenny","Ladywell, Thomastown",25,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [978,978,"SHIP CONSTRUCTION","Kilkenny","Crokers Hill, Kennyswell Road, Kilkenny",51,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [979,979,"SHIP CONSTRUCTION","Kilkenny","Group Home Cloghabrody, Thomastown",4,"*N/A","","","","","Q3-2019",""],
    [980,980,"SHIP CONSTRUCTION","Kilkenny","Inchacarron, Mullinavat",2,"*N/A","","","","","Q3-2019",""],
    [981,981,"SHIP CONSTRUCTION","Kilkenny","Shanganny, Jenkinstown",2,"*N/A","","","","","Q4-2019",""],
    [982,982,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford",11,"*N/A","","","","","","Q2-2017"],
    [983,983,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Newpark, Castlecomer Road, Kilkenny",7,"*N/A","","","","","","Q1-2017"],
    [984,984,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Abbeygate, Ferrybank",8,"*N/A","","","","","","Q1-2018"],
    [985,985,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford",5,"*N/A","","","","","","Q4-2017"],
    [986,986,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Abbeygate, Ferrybank (Phase 2)",1,"*N/A","","","","","","Q3-2018"],
    [987,987,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Togher Way, Urlingford (Phase 3)",18,"*N/A","","","","","","Q4-2018"],
    [988,988,"SHIP CONSTRUCTION TURNKEY","Kilkenny","New Road, Mooncoin",4,"*N/A","","","","","Q3-2018",""],
    [989,989,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Chapel Street, Mooncoin",2,"*N/A","","","","","Q3-2018",""],
    [990,990,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Ogenty, Gowran",12,"*N/A","","","","","","Q4-2018"],
    [991,991,"SHIP CONSTRUCTION TURNKEY","Kilkenny","Lower Kilmacow",16,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [992,992,"CALF Construction","Laois","Kirwan Park, Mountmellick, Co Laois  (Phase 1)",2,"Cluid Housing","","","","","","Q2-2018"],
    [993,993,"CALF Construction","Laois","POST TENDER - Cluinin  Mountrath, Co. Laois (Phase 1)",11,"Oaklee Housing","","","","","","Q1-2018"],
    [994,994,"CALF Turnkey","Laois","Ballickmoyler, Graigcullen, Laois (Phase 1)*",20,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [995,995,"CALF Turnkey","Laois","Bellingham, Portlaoise, Co. Laois (Phase 1)",4,"Cluid Housing","","","","","","Q3-2019"],
    [996,996,"CALF Turnkey","Laois","Bellingham, Portlaoise, Co. Laois (Phase 3)",5,"Cluid Housing","","","","","Q1-2017",""],
    [997,997,"CALF Turnkey","Laois","Bellingham, Portlaoise, Co. Laois (Phase 4)*",9,"Cluid Housing","","","","","Q1-2017",""],
    [998,998,"CALF Turnkey","Laois","Bellingham, Portlaoise, Co. Laois (Phase 5)*",6,"Cluid Housing","","","","","Q1-2017",""],
    [999,999,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 1)*",17,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1000,1000,"CALF Turnkey","Laois","Borris Road, Portlaoise, Co. Laois (Phase 2)",19,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1001,1001,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 1)",17,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1002,1002,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 2)",9,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1003,1003,"CALF Turnkey","Laois","Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 3)",13,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1004,1004,"CALF Turnkey","Laois","Doirinn Alainn, Ballylynan, Co. Laois (Phase 1)*",6,"North & East Housing Association Ltd","","","","","Q1-2019",""],
    [1005,1005,"CALF Turnkey","Laois","Doirinn Alainn, Ballylynan, Co. Laois (Phase 2)",6,"North & East Housing Association Ltd","","","","","Q1-2019",""],
    [1006,1006,"CALF Turnkey","Laois","Droimnin, Stradbally, Co Laois  (Phase 1)",6,"Cluid Housing","","","","","","Q3-2018"],
    [1007,1007,"CALF Turnkey","Laois","Main Street, Stradbally, Co. Laois (Phase 1)",16,"North & East Housing Association Ltd","","","","","Q1-2019",""],
    [1008,1008,"CALF Turnkey","Laois","South Dublin Road, Kilminchy, Portlaoise, Co. Laois (Phase 1)",13,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [1009,1009,"CALF Turnkey","Laois","South Dublin Road, Kilminchy, Portlaoise, Co. Laois (Phase 2)",14,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [1010,1010,"CALF Turnkey","Laois","South Dublin Road, Kilminchy, Portlaoise, Co. Laois (Phase 3)*",9,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [1011,1011,"CALF Turnkey","Laois","The Glen, Kilnacourt, Portarlington, Co. Laois (Phase 1)",18,"Co-operative Housing Ireland","","","","Q4-2019","",""],
    [1012,1012,"CALF Turnkey","Laois","Wilton Lawns, Portarlington, Co. Laois (Phase 1)",2,"Respond","","","","Q4-2019","",""],
    [1013,1013,"CALF Turnkey","Laois","Bellingham, Portlaoise, Co. Laois (Phase 2)",6,"Cluid Housing","","","","","","Q4-2019"],
    [1014,1014,"CAS CONSTRUCTION","Laois","Presentation Convent & Lands, Portlaoise, ",47,"Sophia Housing Association Ltd","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1015,1015,"SHIP CONSTRUCTION","Laois","Moore Street, Rathdowney",6,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [1016,1016,"SHIP CONSTRUCTION","Laois","Ballymorris Road, Portarlington",22,"*N/A","","","","","Q3-2019",""],
    [1017,1017,"SHIP CONSTRUCTION","Laois","Gleann na Glaise, Ballyroan",10,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1018,1018,"SHIP CONSTRUCTION","Laois","Pattison Est. Mountmellick",10,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1019,1019,"SHIP CONSTRUCTION","Laois","Shannon Street, Mountrath",6,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1020,1020,"SHIP CONSTRUCTION","Laois","Conniberry Way, Old Knockmay Road, Portlaoise",33,"*N/A","","","","","","Q2-2018"],
    [1021,1021,"SHIP CONSTRUCTION","Laois","Harbour Court, Mountmellick",6,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1022,1022,"SHIP CONSTRUCTION","Laois","Mooreville, Rathdowney",8,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1023,1023,"SHIP CONSTRUCTION","Laois","Sean Doire, Cork Road, Durrow",22,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1024,1024,"SHIP CONSTRUCTION","Laois","St Kieran's Park, Errill",14,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1025,1025,"SHIP CONSTRUCTION","Laois","Clonrooske, Knockmay",11,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1026,1026,"SHIP CONSTRUCTION","Laois","Carraig Glas, Stradbally",26,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1027,1027,"SHIP CONSTRUCTION","Laois","Hillview, Portlaoise",2,"*N/A","","","","","Q4-2019",""],
    [1028,1028,"SHIP CONSTRUCTION","Laois","The Orchard, Stradbally",6,"*N/A","","","","","Q4-2019",""],
    [1029,1029,"SHIP CONSTRUCTION","Laois","Harpurs Lane, Portlaoise",1,"*N/A","","","","","","Q4-2019"],
    [1030,1030,"SHIP CONSTRUCTION TURNKEY","Laois","Priory, Borris in Ossory",6,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1031,1031,"SHIP CONSTRUCTION TURNKEY","Laois","Priory, Borris in Ossory",5,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1032,1032,"CALF Turnkey","Leitrim","Cnoc an Luir, Drumshanbo, Co. Leitrim (Phase 1)",10,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1033,1033,"CAS CONSTRUCTION","Leitrim","Ballinamore",2,"Society of Saint Vincent de Paul","","","","","","Q4-2017"],
    [1034,1034,"SHIP CONSTRUCTION","Leitrim","Autumn View, Summerhill, Carrick on Shannon",27,"*N/A","","","","","Q4-2019",""],
    [1035,1035,"SHIP CONSTRUCTION","Leitrim","Taobh Tire, Manorhamilton (Phase 2)",7,"*N/A","","","","","","Q4-2018"],
    [1036,1036,"SHIP CONSTRUCTION","Leitrim","Taobh Tire, Manorhamilton (Phase 3)",5,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1037,1037,"SHIP CONSTRUCTION","Leitrim","Lahard, Ballinamore",10,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1038,1038,"SHIP CONSTRUCTION TURNKEY","Leitrim","Drumshanbo",9,"*N/A","","","","","","Q3-2019"],
    [1039,1039,"SHIP CONSTRUCTION TURNKEY","Leitrim","Church Lane, Ballinamore",9,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1040,1040,"SHIP CONSTRUCTION TURNKEY","Leitrim","Roosky",7,"*N/A","","","","","","Q4-2019"],
    [1041,1041,"SHIP CONSTRUCTION RAPID","Limerick","Old Christians Site, Rathbane",43,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1042,1042,"CALF Construction","Limerick","Hyde Road, Limerick City (Phase 1)",20,"Cluid Housing","","","","","","Q1-2018"],
    [1043,1043,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 1)",2,"Respond","","","","","","Q4-2018"],
    [1044,1044,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 2)",2,"Respond","","","","","","Q4-2018"],
    [1045,1045,"CALF Turnkey","Limerick","Ballygrennan Close, Moyross, Limerick  (Phase 3)",2,"Respond","","","","","","Q4-2018"],
    [1046,1046,"CALF Turnkey","Limerick","Cluain Ard, Fedamore, Co Limerick  (Phase 1)",2,"Co-operative Housing Ireland","","","","","","Q1-2018"],
    [1047,1047,"CALF Turnkey","Limerick","Cluain Ard, Fedamore, Co Limerick  (Phase 2)",2,"Co-operative Housing Ireland","","","","","","Q3-2018"],
    [1048,1048,"CALF Turnkey","Limerick","Drominbeg, Rhebogue, Limerick (Phase 1)",10,"Co-operative Housing Ireland","","","","Q2-2019","",""],
    [1049,1049,"CALF Turnkey","Limerick","Drominbeg, Rhebogue, Limerick (Phase 2)",10,"Co-operative Housing Ireland","","","","Q2-2019","",""],
    [1050,1050,"CALF Turnkey","Limerick","Revised - Ard Aulin, Mungret, Co Limerick (Phase 1)",7,"Cluid Housing","","","","","","Q2-2017"],
    [1051,1051,"CAS CONSTRUCTION","Limerick","Towerfield Crescent, Croom",16,"Croom Voluntary Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1052,1052,"CAS CONSTRUCTION","Limerick","Cappamore",10,"Cappamore Housing Association Ltd","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [1053,1053,"CAS CONSTRUCTION","Limerick","Speakers Corner, Limerick City",4,"Simon Community : Midwest Simon","","","","","","Q3-2018"],
    [1054,1054,"CAS CONSTRUCTION","Limerick","Cuan Mhuire, Bruree",6,"Cuan Mhuire Teoranta","","","","","","Q3-2018"],
    [1055,1055,"CAS CONSTRUCTION","Limerick","Mirth, Thomondgate",18,"Associated Charities Trust Ltd","Stage 1 approved Q3-2017, outline design and costs being prepared.","","","","",""],
    [1056,1056,"CAS CONSTRUCTION","Limerick","Cois na Feile, Abbeyfeale ",12,"Cluid Housing Association","","","","","","Q4-2016"],
    [1057,1057,"CAS CONSTRUCTION","Limerick","2/3 Mallow Street",6,"Peter McVerry Trust Ltd","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [1058,1058,"CAS CONSTRUCTION","Limerick","St. Pauls Convent, Kilfinane",9,"Sophia Housing Association Ltd","Stage 1 approved Q4-2018, outline design and costs being prepared.","","","","",""],
    [1059,1059,"CAS CONSTRUCTION","Limerick","McGarry House, 7 Alphonsus Street",8,"Arlington Novas Ireland Ltd","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1060,1060,"CAS CONSTRUCTION","Limerick","47 & 48 Main Street, Croom, Limerick",4,"Croom Voluntary Housing Association Ltd","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1061,1061,"CAS CONSTRUCTION TURNKEY","Limerick","Barrack Mews, Brennan's Row, Cathedral Place",2,"Arlington Novas Ireland Ltd","","","","","","Q4-2019"],
    [1062,1062,"CAS CONSTRUCTION TURNKEY","Limerick","Barrack Mews, Brennan's Row, Cathedral place",4,"Arlington Novas Ireland Ltd","","","","","Q3-2019",""],
    [1063,1063,"CAS CONSTRUCTION TURNKEY","Limerick","Carebright Community, Ardykeohane, Bruff",6,"Carebright Ltd","","","","","","Q1-2019"],
    [1064,1064,"REGENERATION","Limerick","Lord Edward Street, P2: Main Contract",79,"*N/A","","","","","","Q4-2017"],
    [1065,1065,"REGENERATION","Limerick","Lord Edward Street, P2: Main Contract",2,"*N/A","","","","","","Q1-2017"],
    [1066,1066,"REGENERATION","Limerick","Gaol Lane",1,"*N/A","","Stage 2 approved Q3-2016, full design/tender being prepared.","","","",""],
    [1067,1067,"REGENERATION","Limerick","Sheep / Athlunkards Street",8,"T�ath Housing Association Ltd","","Stage 2 approved Q2-2014, full design/tender being prepared.","","","",""],
    [1068,1068,"REGENERATION","Limerick","Churchfield",19,"*N/A","","","","","","Q1-2018"],
    [1069,1069,"REGENERATION","Limerick","Churchfield (Phase 2)",38,"Cluid Housing Association","","Stage 2 approved Q4-2014, full design/tender being prepared.","","","",""],
    [1070,1070,"REGENERATION","Limerick","Cosgrave Park",9,"Co-operative Housing Ireland (Formerly NABCo)","","","Stage 3 approved Q1-2018, the scheme is now approved to proceed to tender.","","",""],
    [1071,1071,"REGENERATION","Limerick","Orchard Site",26,"Oaklee Housing Trust","","Stage 2 approved Q3-2017, full design/tender being prepared.","","","",""],
    [1072,1072,"REGENERATION","Limerick","176 & 177 Cliona Park",2,"*N/A","","","","","","Q2-2016"],
    [1073,1073,"REGENERATION","Limerick","Cliona Park (Phase 2)",10,"*N/A","","","","","","Q2-2017"],
    [1074,1074,"REGENERATION","Limerick","8-10 Gaol Lane",3,"*N/A","","","","","","Q4-2016"],
    [1075,1075,"REGENERATION","Limerick","1 3 Weston Gardens",3,"*N/A","","","","","","Q2-2016"],
    [1076,1076,"REGENERATION","Limerick","2016 Moyross Rebuild",6,"*N/A","","","","","","Q4-2016"],
    [1077,1077,"REGENERATION","Limerick","2016 Southhill Rebuild",8,"*N/A","","","","","","Q4-2016"],
    [1078,1078,"REGENERATION","Limerick","2016 St. Mary's Park Rebuild",9,"*N/A","","","","","","Q4-2016"],
    [1079,1079,"REGENERATION","Limerick","BCW Vacant Refurbs, Lot 1 & 2**",14,"*N/A","","","","","","Q4-2016"],
    [1080,1080,"REGENERATION","Limerick","St. Mary's Park Infills",15,"*N/A","","","","","","Q4-2018"],
    [1081,1081,"REGENERATION","Limerick","Cliona Park (Phase 3)",18,"T�ath Housing Association Ltd","","Stage 2 approved Q3-2016, full design/tender being prepared.","","","",""],
    [1082,1082,"REGENERATION","Limerick","45A-46A Cliona Park",2,"*N/A","","","","","Q4-2019",""],
    [1083,1083,"REGENERATION","Limerick","Dalgaish Park",27,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1084,1084,"REGENERATION","Limerick","2017 St Mary's Park Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1085,1085,"REGENERATION","Limerick","2017 Ballinacurra Weston Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1086,1086,"REGENERATION","Limerick","2017 Southill Rebuilds",13,"*N/A","","","","","","Q4-2017"],
    [1087,1087,"REGENERATION","Limerick","2017 Moyross Rebuild",1,"*N/A","","","","","","Q4-2017"],
    [1088,1088,"REGENERATION","Limerick","Churchfield (Phase 1.1)",23,"*N/A","","","","","","Q2-2018"],
    [1089,1089,"REGENERATION","Limerick","St. Mary's Park Infills (Phase 2)",4,"*N/A","","","","","","Q1-2019"],
    [1090,1090,"REGENERATION","Limerick","2019 Rebuilds (Southill, Moyross, St Mary's Park and Ballinacurra Weston)",8,"*N/A","","","","","","Q4-2019"],
    [1091,1091,"SHIP CONSTRUCTION","Limerick","Burke Avenue, Limerick City",12,"*N/A","","","","","","Q4-2019"],
    [1092,1092,"SHIP CONSTRUCTION","Limerick","Barnakyle, Patrickswell (Site 2)",24,"*N/A","","","Stage 3 approved Q3-2018, the scheme is now approved to proceed to tender.","","",""],
    [1093,1093,"SHIP CONSTRUCTION","Limerick","Patrick�s Villas, Castleconnell",4,"*N/A","","","","","Q3-2019",""],
    [1094,1094,"SHIP CONSTRUCTION","Limerick","Ballysimon, Greenhill Road ",14,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1095,1095,"SHIP CONSTRUCTION","Limerick","Gough Place, Rosbrien Road, Limerick",17,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [1096,1096,"SHIP CONSTRUCTION","Limerick","Wallers Well, Limerick City (Phase 2)",13,"*N/A","","","","","Q2-2019",""],
    [1097,1097,"SHIP CONSTRUCTION","Limerick","Clonmacken, Limerick City",43,"*N/A","","","","","Q3-2019",""],
    [1098,1098,"SHIP CONSTRUCTION","Limerick","Deerpark, Adare",30,"*N/A","Stage 1 approved Q2-2015, outline design and costs being prepared.","","","","",""],
    [1099,1099,"SHIP CONSTRUCTION","Limerick","Glenview Drive, Hospital",20,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1100,1100,"SHIP CONSTRUCTION","Limerick","Clare Street, Limerick City",7,"*N/A","","Stage 2 approved Q3-2017, full design/tender being prepared.","","","",""],
    [1101,1101,"SHIP CONSTRUCTION","Limerick","Hasset Villas, Thomondgate",3,"*N/A","","","","","","Q4-2018"],
    [1102,1102,"SHIP CONSTRUCTION","Limerick","Fannings Corner, Limerick City",3,"*N/A","","","","","","Q4-2019"],
    [1103,1103,"SHIP CONSTRUCTION","Limerick","Kilmurry Court, Garryowen",7,"*N/A","","","","","","Q4-2019"],
    [1104,1104,"SHIP CONSTRUCTION","Limerick","Lower Carey's Road, Limerick City",11,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1105,1105,"SHIP CONSTRUCTION","Limerick","Kileely Road, Moyross",5,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1106,1106,"SHIP CONSTRUCTION","Limerick","Clare Street, Limerick City",2,"*N/A","","","","","","Q4-2017"],
    [1107,1107,"SHIP CONSTRUCTION","Limerick","Knocklong",12,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1108,1108,"SHIP CONSTRUCTION","Limerick","Convent Street, King's Island",2,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [1109,1109,"SHIP CONSTRUCTION","Limerick","Colbert Terrace, Abbeyfeale",3,"*N/A","","Stage 2 approved Q4-2018, full design/tender being prepared.","","","",""],
    [1110,1110,"SHIP CONSTRUCTION","Limerick","Ballygrennan Road, Limerick City",2,"*N/A","","","","","","Q4-2017"],
    [1111,1111,"SHIP CONSTRUCTION","Limerick","Rathbane Road, Limerick City",2,"*N/A","","","","","","Q1-2019"],
    [1112,1112,"SHIP CONSTRUCTION","Limerick","Sycamore Avenue, Limerick City",5,"*N/A","","","","","","Q3-2019"],
    [1113,1113,"SHIP CONSTRUCTION TURNKEY","Limerick","Carraig Desmond",2,"*N/A","","","","","","Q4-2019"],
    [1114,1114,"SHIP CONSTRUCTION TURNKEY","Limerick","Carraig Desmond, Newcastle West",8,"*N/A","","","","","","Q4-2019"],
    [1115,1115,"SHIP CONSTRUCTION TURNKEY","Limerick","Knocklong",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1116,1116,"SHIP CONSTRUCTION TURNKEY","Limerick","Woodlawn Park (Phase 2), Ballysimon Road, ",1,"*N/A","","","","","","Q4-2019"],
    [1117,1117,"SHIP CONSTRUCTION TURNKEY","Limerick","Woodlawn Park, Ballysimon Road, Limerick",9,"*N/A","","","","","","Q4-2019"],
    [1118,1118,"SHIP CONSTRUCTION RAPID","Limerick","Faha View, Patrickswell",16,"*N/A","","","","","","Q4-2019"],
    [1119,1119,"CALF Construction","Longford","Colmcille Terrace, Granard, Co. Longford. (Phase 1)",21,"T�ath Housing Association Ltd","","","","Q2-2018","",""],
    [1120,1120,"CALF Turnkey","Longford","Cartrun Breac, Lisbrack Rd, Longford (Phase 1)",7,"Cluid Housing","","","","","","Q1-2017"],
    [1121,1121,"SHIP CONSTRUCTION","Longford","Edgeworthstown Road, Ballymahon",4,"*N/A","","","","","","Q1-2018"],
    [1122,1122,"SHIP CONSTRUCTION","Longford","'Rose Cottage', Ballinalee",6,"*N/A","","","Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.","","",""],
    [1123,1123,"SHIP CONSTRUCTION","Longford","St.Rita's, Park Road, Longford",14,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1124,1124,"SHIP CONSTRUCTION","Longford","Fairgreen View, Longford Town",1,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1125,1125,"SHIP CONSTRUCTION","Longford","Cranleymore, Abbeylara",3,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1126,1126,"SHIP CONSTRUCTION","Longford","Cloonahard",1,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1127,1127,"SHIP CONSTRUCTION","Longford","Daroge, Ballymahon",1,"*N/A","","","","","","Q4-2019"],
    [1128,1128,"SHIP CONSTRUCTION","Longford","Rathcline Road, Lanesborough",4,"*N/A","","","","","","Q3-2019"],
    [1129,1129,"SHIP CONSTRUCTION TURNKEY","Longford"," Abhainn Glas, Edgeworthstown",4,"*N/A","","","","","","Q4-2019"],
    [1130,1130,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",14,"*N/A","","","","","","Q4-2017"],
    [1131,1131,"SHIP CONSTRUCTION TURNKEY","Longford","Knock, Lanesborough",4,"*N/A","","","","","","Q3-2018"],
    [1132,1132,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish (Phase 2)",2,"*N/A","","","","","","Q1-2018"],
    [1133,1133,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck",7,"*N/A","","","","","","Q4-2018"],
    [1134,1134,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck (Phase 2)",4,"*N/A","","","","","","Q3-2019"],
    [1135,1135,"SHIP CONSTRUCTION TURNKEY","Longford","Ballinamuck (Phase 3)",6,"*N/A","","","","","","Q4-2019"],
    [1136,1136,"SHIP CONSTRUCTION TURNKEY","Longford","Rock View, Cloondara",5,"*N/A","","","","","","Q4-2018"],
    [1137,1137,"SHIP CONSTRUCTION TURNKEY","Longford","Caislean Breac, Newtownforbes",2,"*N/A","","","","","","Q4-2019"],
    [1138,1138,"SHIP CONSTRUCTION TURNKEY","Longford","Knock, Lanesborough (Phase 2)",29,"*N/A","","","","","","Q4-2018"],
    [1139,1139,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",4,"*N/A","","","","","","Q3-2019"],
    [1140,1140,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard",7,"*N/A","","","","","","Q4-2019"],
    [1141,1141,"SHIP CONSTRUCTION TURNKEY","Longford","Church Street, Edgeworthstown",5,"*N/A","","","","","Q1-2019",""],
    [1142,1142,"SHIP CONSTRUCTION TURNKEY","Longford","Smithfield, Legan",18,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1143,1143,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard (Phase 2)",4,"*N/A","","","","","","Q2-2019"],
    [1144,1144,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard (Phase 4)",6,"*N/A","","","","","","Q4-2019"],
    [1145,1145,"SHIP CONSTRUCTION TURNKEY","Longford","Carragh, Granard(Phase 3)",4,"*N/A","","","","","","Q4-2019"],
    [1146,1146,"SHIP CONSTRUCTION TURNKEY","Longford","Greville Court, Granard",14,"*N/A","","","","","","Q4-2019"],
    [1147,1147,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",2,"*N/A","","","","","","Q4-2019"],
    [1148,1148,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",4,"*N/A","","","","","","Q4-2019"],
    [1149,1149,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill",4,"*N/A","","","","","Q4-2019",""],
    [1150,1150,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",4,"*N/A","","","","","","Q2-2019"],
    [1151,1151,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish",2,"*N/A","","","","","","Q4-2019"],
    [1152,1152,"SHIP CONSTRUCTION TURNKEY","Longford","Farnagh Hill, Longford Town",12,"*N/A","","","","","Q4-2019",""],
    [1153,1153,"SHIP CONSTRUCTION TURNKEY","Longford","Mill Race Park, Drumlish (Phase 3)",4,"*N/A","","","","","","Q3-2019"],
    [1154,1154,"SHIP CONSTRUCTION TURNKEY","Longford","Pearse Drive, Longford Town",1,"*N/A","","","","","","Q4-2019"],
    [1155,1155,"SHIP CONSTRUCTION TURNKEY","Longford","Radharc Na Muileann, Knock, Lanesborough",2,"*N/A","","","","","","Q4-2019"],
    [1156,1156,"CALF Construction","Louth","Bishops Court, Dundalk, Co Louth  (Phase 1)",2,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1157,1157,"CALF Construction","Louth","Post Tender - Clos na Manach, Carlingford, Co Louth (Phase 1)",10,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1158,1158,"CALF Construction","Louth","Slieve Row Crescent, Dundalk (Phase 1)",1,"Cluid Housing","","","","","","Q2-2016"],
    [1159,1159,"CALF Construction","Louth","Fire Station Site, Scarlett St, Drogheda (Phase 1)",15,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1160,1160,"CALF Turnkey","Louth","2 units An Rian, Termonfeckin Rd., Drogheda, Co. Louth (Phase 1)",2,"North & East Housing Association Ltd","","","","","","Q2-2019"],
    [1161,1161,"CALF Turnkey","Louth","Aston Village, Drogheda (Phase 1)*",8,"Respond","","","","","","Q3-2018"],
    [1162,1162,"CALF Turnkey","Louth","Castle Court, Castlebellingham, Louth (Phase 1)",4,"Cluid Housing","","","","","","Q1-2017"],
    [1163,1163,"CALF Turnkey","Louth","Castle Court, Castlebellingham, Louth (Phase 2)",10,"Cluid Housing","","","","","","Q1-2017"],
    [1164,1164,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 1)",9,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1165,1165,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 2)*",20,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1166,1166,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 3)",8,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1167,1167,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 4)",15,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1168,1168,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 5)",6,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1169,1169,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 6)*",22,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1170,1170,"CALF Turnkey","Louth","Castleguard, Ardee, Co. Louth (Phase 7)",22,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1171,1171,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 1)*",13,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1172,1172,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 2)",8,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [1173,1173,"CALF Turnkey","Louth","Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 3)",7,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1174,1174,"CALF Turnkey","Louth","Coulter Place Armagh Road (Phase 1)",10,"Cluid Housing","","","","","","Q1-2017"],
    [1175,1175,"CALF Turnkey","Louth","Coulter Place Armagh Road (Phase 2)",12,"Cluid Housing","","","","","","Q3-2017"],
    [1176,1176,"CALF Turnkey","Louth","Dowdallshill, Dundalk, Co. Louth (Phase 1)*",13,"North & East Housing Association Ltd","","","","","Q3-2018",""],
    [1177,1177,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth (Phase 3)",3,"Respond","","","","","Q3-2017",""],
    [1178,1178,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 6)*",1,"T�ath Housing Association Ltd","","","","","Q2-2018",""],
    [1179,1179,"CALF Turnkey","Louth","Harbour Grove, Dundalk, Co. Louth (Phase 1)",8,"North & East Housing Association Ltd","","","","","Q3-2018",""],
    [1180,1180,"CALF Turnkey","Louth","Knock Shee, Old Golf Links Road, Blackrock, Co Louth  (Phase 1)",3,"Cluid Housing","","","","","","Q4-2017"],
    [1181,1181,"CALF Turnkey","Louth","Knockshee Close, Blackrock, Co. Louth (Phase 1)",3,"Cluid Housing","","","","","Q3-2019",""],
    [1182,1182,"CALF Turnkey","Louth","Liscorrie, Bog Lane, Drogheda (Phase 1)",41,"T�ath Housing Association Ltd","","","","","","Q4-2017"],
    [1183,1183,"CALF Turnkey","Louth","Lismullen Grove, Dundalk, Co. Louth (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1184,1184,"CALF Turnkey","Louth","Lismullen Grove, Dundalk, Co. Louth (Phase 2)",7,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1185,1185,"CALF Turnkey","Louth","Lismullen Grove, Dundalk, Co. Louth (Phase 3)",8,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1186,1186,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 1)",20,"Clanmil Housing Association Ireland","","","","","Q1-2019",""],
    [1187,1187,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 2)*",25,"Clanmil Housing Association Ireland","","","","","Q1-2019",""],
    [1188,1188,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 2)*",22,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1189,1189,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 3)*",6,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1190,1190,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 4)*",7,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1191,1191,"CALF Turnkey","Louth","Rath na Gloine, Commons Road, Louth (Phase 1)",3,"Cluid Housing","","","","","","Q3-2016"],
    [1192,1192,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 1)",3,"North & East Housing Association Ltd","","","","","","Q4-2018"],
    [1193,1193,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth (Phase 1)*",14,"Respond","","","","","","Q1-2019"],
    [1194,1194,"CALF Turnkey","Louth","Dublin Road, Dundalk, Co. Louth (Phase 2)*",14,"Respond","","","","","","Q4-2019"],
    [1195,1195,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 1)",4,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1196,1196,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 2)",6,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1197,1197,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 3)",4,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1198,1198,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 4)",15,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1199,1199,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 1)*",11,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1200,1200,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 2)*",14,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1201,1201,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 7)",12,"T�ath Housing Association Ltd","","","","","Q4-2017",""],
    [1202,1202,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 1)",12,"Cluid Housing","","","","","","Q4-2017"],
    [1203,1203,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 3)*",15,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1204,1204,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 4)*",47,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [1205,1205,"CALF Turnkey","Louth","Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 5)*",24,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1206,1206,"CALF Turnkey","Louth","Tullybrook, Slane Road, Drogheda, Co. Louth (Phase 1)",4,"Cluid Housing","","","","","Q4-2018",""],
    [1207,1207,"CALF Turnkey","Louth","Mount Hamilton, Dundalk, Co. Louth (Phase 1)",20,"Cluid Housing","","","","","","Q4-2019"],
    [1208,1208,"CALF Turnkey","Louth","Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 1)",11,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1209,1209,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 2)",6,"North & East Housing Association Ltd","","","","","","Q2-2019"],
    [1210,1210,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 3)",3,"North & East Housing Association Ltd","","","","","","Q3-2019"],
    [1211,1211,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 4)",14,"North & East Housing Association Ltd","","","","","","Q3-2019"],
    [1212,1212,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 5)",12,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1213,1213,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Phase 6)",16,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1214,1214,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 5)",6,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1215,1215,"CALF Turnkey","Louth","Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 6)",4,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1216,1216,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 2)",15,"Cluid Housing","","","","","","Q3-2019"],
    [1217,1217,"CALF Turnkey","Louth","Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 3)",16,"Cluid Housing","","","","","","Q4-2019"],
    [1218,1218,"CALF Turnkey","Louth","Termon River, Baltray Road, Termonfeckin, Co. Louth (Phase 1)",1,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1219,1219,"CALF Turnkey","Louth","Termon River, Baltray Road, Termonfeckin, Drogheda, Co.Louth (Phase 1)*",1,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1220,1220,"CAS CONSTRUCTION","Louth","5 Slieveroe Crescent, Dundalk",1,"Cluid Housing Association","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1221,1221,"CAS CONSTRUCTION","Louth","Barrack Street, Dundalk",21,"Simon Community : Dundalk Simon","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1222,1222,"CAS CONSTRUCTION","Louth","McArdle Green (Moneymore), Drogheda",1,"North ? East Housing Association Ltd","","","","","","Q4-2018"],
    [1223,1223,"CAS CONSTRUCTION","Louth","Tierney Street, Ardee",7,"Oaklee Housing Trust","","","Stage 3 approved Q1-2018, the scheme is now approved to proceed to tender.","","",""],
    [1224,1224,"CAS CONSTRUCTION","Louth","Tredagh View, Drogheda",1,"Respond","","","","","","Q1-2017"],
    [1225,1225,"CAS CONSTRUCTION","Louth","Coulter Park, Dundalk",7,"T�ath Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1226,1226,"CAS CONSTRUCTION","Louth","Four Winds, Mullacapple, Collon",1,"St. John of God Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1227,1227,"CAS CONSTRUCTION","Louth","St. John's Home, Peter's Hill, Drogheda",4,"North ? East Housing Association Ltd","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1228,1228,"CAS CONSTRUCTION","Louth","Riverwell Close, Dundalk",1,"Respond","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1229,1229,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Louth","Ravel Ardee Road, Dunleer",80,"*N/A","","","","","Q1-2019",""],
    [1230,1230,"REGENERATION","Louth","Cox's Demesne Phase 2a",14,"*N/A","","","","","","Q4-2016"],
    [1231,1231,"REGENERATION","Louth","Cox's Demesne Phase 2b",22,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1232,1232,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 3",1,"*N/A","","","","","","Q1-2019"],
    [1233,1233,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 5",1,"*N/A","","","","","","Q3-2019"],
    [1234,1234,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 6",2,"*N/A","","","","","","Q4-2019"],
    [1235,1235,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 7",2,"*N/A","","","","","","Q1-2019"],
    [1236,1236,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 8",2,"*N/A","","","","","","Q2-2019"],
    [1237,1237,"SHIP CONSTRUCTION","Louth","CPO Bundle 4 - Phase 3",5,"*N/A","","","","","","Q1-2019"],
    [1238,1238,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 1",1,"*N/A","","","","","","Q1-2019"],
    [1239,1239,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 2",2,"*N/A","","","","","","Q2-2019"],
    [1240,1240,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 3",4,"*N/A","","","","","","Q3-2019"],
    [1241,1241,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 4",3,"*N/A","","","","","","Q4-2019"],
    [1242,1242,"SHIP CONSTRUCTION","Louth","CPO Bundle 6 - Phase 1",1,"*N/A","","","","","","Q3-2019"],
    [1243,1243,"SHIP CONSTRUCTION","Louth","CPO Bundle 6 - Phase 2",2,"*N/A","","","","","","Q4-2019"],
    [1244,1244,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 1",4,"*N/A","","","","","","Q1-2018"],
    [1245,1245,"SHIP CONSTRUCTION","Louth","CPO Bundle 1",7,"*N/A","","","","","","Q4-2016"],
    [1246,1246,"SHIP CONSTRUCTION","Louth","CPO Bundle 1 - Phase 2",5,"*N/A","","","","","","Q2-2017"],
    [1247,1247,"SHIP CONSTRUCTION","Louth","CPO Bundle 1 - Phase 3",3,"*N/A","","","","","","Q3-2017"],
    [1248,1248,"SHIP CONSTRUCTION","Louth","Woodlands, Dunleer",4,"*N/A","","","","","","Q4-2016"],
    [1249,1249,"SHIP CONSTRUCTION","Louth","Boice Court, Drogheda (Phase 2 - 4)",69,"*N/A","","Stage 2 approved Q3-2017, full design/tender being prepared.","","","",""],
    [1250,1250,"SHIP CONSTRUCTION","Louth","Father Finn Park (Phase 2)",17,"*N/A","","","Stage 3 approved Q2-2019, the scheme is now approved to proceed to tender.","","",""],
    [1251,1251,"SHIP CONSTRUCTION","Louth","CPO Bundle 1 - Phase 4",7,"*N/A","","","","","","Q4-2017"],
    [1252,1252,"SHIP CONSTRUCTION","Louth","Mount Avenue, Dundalk",93,"*N/A","Stage 1 approved Q4-2017, outline design and costs being prepared.","","","","",""],
    [1253,1253,"SHIP CONSTRUCTION","Louth","CPO Bundle 1 - Phase 5",1,"*N/A","","","","","","Q3-2018"],
    [1254,1254,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 2",1,"*N/A","","","","","","Q3-2018"],
    [1255,1255,"SHIP CONSTRUCTION","Louth","CPO Bundle 3",2,"*N/A","","","","","","Q2-2017"],
    [1256,1256,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 2",1,"*N/A","","","","","","Q3-2017"],
    [1257,1257,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 3",4,"*N/A","","","","","","Q4-2017"],
    [1258,1258,"SHIP CONSTRUCTION","Louth","CPO Bundle 4",1,"*N/A","","","","","","Q3-2018"],
    [1259,1259,"SHIP CONSTRUCTION","Louth","CPO Bundle 1 - Phase 6",1,"*N/A","","","","Stage 4 approved Q1-2016, the scheme is fully approved.","",""],
    [1260,1260,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 4",1,"*N/A","","","","","","Q2-2018"],
    [1261,1261,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 5",4,"*N/A","","","","","","Q3-2018"],
    [1262,1262,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 4",1,"*N/A","","","","","","Q4-2018"],
    [1263,1263,"SHIP CONSTRUCTION","Louth","CPO Bundle 4 - Phase 2",4,"*N/A","","","","","","Q4-2018"],
    [1264,1264,"SHIP CONSTRUCTION","Louth","CPO Bundle 3 - Phase 6",5,"*N/A","","","","","","Q4-2018"],
    [1265,1265,"SHIP CONSTRUCTION","Louth","CPO Bundle 4 - Phase 4",1,"*N/A","","","","","","Q4-2018"],
    [1266,1266,"SHIP CONSTRUCTION","Louth","Muirhevnamor, Dundalk (Phase 1)",18,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1267,1267,"SHIP CONSTRUCTION","Louth","CPO Bundle 6 - Phase 4",4,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1268,1268,"SHIP CONSTRUCTION","Louth","CPO Bundle 6 - Phase 3",3,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1269,1269,"SHIP CONSTRUCTION","Louth","CPO Bundle 2 - Phase 7",1,"*N/A","","","","","Q3-2017",""],
    [1270,1270,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 5",4,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1271,1271,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 6",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1272,1272,"SHIP CONSTRUCTION","Louth","CPO Bundle 5 - Phase 7",3,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1273,1273,"SHIP CONSTRUCTION","Louth","55/57 Bothar Brugha, Drogheda",3,"*N/A","","","","","","Q4-2017"],
    [1274,1274,"SHIP CONSTRUCTION","Louth","Infill Housing Construction, Gort Uaine, Clogherhead, Co. Louth",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1275,1275,"SHIP CONSTRUCTION","Louth","Infill Housing Construction, School Lane, Dunleer, Co. Louth",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1276,1276,"SHIP CONSTRUCTION TURNKEY","Louth","1-5 Brabazon Hall, Termonfeckin, Drogheda",5,"*N/A","","","","","","Q4-2019"],
    [1277,1277,"SHIP CONSTRUCTION TURNKEY","Louth","Moneymore, Drogheda, Co. Louth",1,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1278,1278,"SHIP CONSTRUCTION TURNKEY","Louth","Rathmullen, Drogheda, Co. Louth",4,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1279,1279,"SHIP CONSTRUCTION TURNKEY","Louth","Castletown Road, Dundalk ",6,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1280,1280,"SHIP CONSTRUCTION TURNKEY","Louth","�Gort Bui�, Ballymakenny Road, Drogheda - Phase 1",12,"*N/A","","","","","Q4-2019",""],
    [1281,1281,"SHIP CONSTRUCTION TURNKEY","Louth","�Gort Bui�, Ballymakenny Road, Drogheda - Phase 2",8,"*N/A","","","","","Q4-2019",""],
    [1282,1282,"SHIP CONSTRUCTION TURNKEY","Louth","�Gort Bui�, Ballymakenny Road, Drogheda - Phase 3",9,"*N/A","","","","","Q4-2019",""],
    [1283,1283,"SHIP CONSTRUCTION TURNKEY","Louth","�Gort Bui�, Ballymakenny Road, Drogheda - Phase 4",9,"*N/A","","","","","Q4-2019",""],
    [1284,1284,"SHIP CONSTRUCTION TURNKEY","Louth","�Gort Bui�, Ballymakenny Road, Drogheda - Phase 5",7,"*N/A","","","","","Q4-2019",""],
    [1285,1285,"CALF Turnkey","Mayo","The Sycamores, Ballina (Phase 1)",11,"Cluid Housing","","","","","Q2-2019",""],
    [1286,1286,"CALF Turnkey","Mayo","Glenlara, Westport, Co Mayo  (Phase 1)",10,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1287,1287,"CALF Turnkey","Mayo","Monamore, Lodge Road, Westport, Co. Mayo (Phase 1)*",2,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1288,1288,"CAS CONSTRUCTION","Mayo","Admiral Browne Road, Foxford (Phase 2)",4,"Society of Saint Vincent de Paul","","","","","","Q1-2018"],
    [1289,1289,"CAS CONSTRUCTION","Mayo","Killosheehan, Ballinrobe",6,"Society of Saint Vincent de Paul","","","","","","Q4-2018"],
    [1290,1290,"CAS CONSTRUCTION","Mayo","Admiral Browne Road, Foxford",8,"Society of Saint Vincent de Paul","","","","","","Q3-2016"],
    [1291,1291,"CAS CONSTRUCTION","Mayo","Logmore, Belmullet",7,"Irish Wheelchair Association Ltd","","","","","","Q2-2017"],
    [1292,1292,"SHIP CONSTRUCTION","Mayo","St. Patrick's Terrace, Westport",1,"*N/A","","","","","","Q3-2017"],
    [1293,1293,"SHIP CONSTRUCTION","Mayo","Kilkelly Road, Knock (Phase 3)",4,"*N/A","","","","","","Q3-2018"],
    [1294,1294,"SHIP CONSTRUCTION","Mayo","Kilmeena (Phase 2)",4,"*N/A","","","","","","Q3-2018"],
    [1295,1295,"SHIP CONSTRUCTION","Mayo","Slinaunroe, Clogher (SRD)",1,"*N/A","","","","","","Q2-2017"],
    [1296,1296,"SHIP CONSTRUCTION","Mayo","Abbeyquarter, Ballyhaunis",18,"*N/A","","","","","Q1-2019",""],
    [1297,1297,"SHIP CONSTRUCTION","Mayo","Killavally",10,"N/A","","","","","","Q4-2019"],
    [1298,1298,"SHIP CONSTRUCTION","Mayo","Sli na Roba, Friarsquarter, Ballinrobe",16,"*N/A","","","","","Q4-2018",""],
    [1299,1299,"SHIP CONSTRUCTION","Mayo","Marian Crescent, Ballina",4,"*N/A","","","","","","Q2-2018"],
    [1300,1300,"SHIP CONSTRUCTION","Mayo","Tubberhill, Westport (Phase 3)",21,"*N/A","","","","","","Q1-2018"],
    [1301,1301,"SHIP CONSTRUCTION","Mayo","Knockmore, Ballina",8,"*N/A","","","","","","Q1-2019"],
    [1302,1302,"SHIP CONSTRUCTION","Mayo","Lios na Circa, Saleen, Castlebar",22,"*N/A","Stage 1 approved Q3-2017, outline design and costs being prepared.","","","","",""],
    [1303,1303,"SHIP CONSTRUCTION","Mayo","Kilkelly Road, Swinford",27,"*N/A","","","","","Q1-2019",""],
    [1304,1304,"SHIP CONSTRUCTION","Mayo","Barhauve, Rossport (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [1305,1305,"SHIP CONSTRUCTION","Mayo","Glaggaun, Ballycroy (SRD)",1,"*N/A","","","","","","Q4-2017"],
    [1306,1306,"SHIP CONSTRUCTION","Mayo","Glengad, Pollatomish (SRD)",1,"*N/A","","","","","","Q2-2018"],
    [1307,1307,"SHIP CONSTRUCTION","Mayo","Gorthbrack, Inver (SRD)",1,"*N/A","","","","","","Q1-2018"],
    [1308,1308,"SHIP CONSTRUCTION","Mayo","Cross",8,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1309,1309,"SHIP CONSTRUCTION","Mayo","Bonniconlon",5,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1310,1310,"SHIP CONSTRUCTION","Mayo","Cloonkeadagh Road, Kiltimagh",23,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1311,1311,"SHIP CONSTRUCTION","Mayo","Rehins Fort, Ballina",50,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1312,1312,"SHIP CONSTRUCTION","Mayo","Knocknageeha, Newport",1,"*N/A","","","","","","Q2-2019"],
    [1313,1313,"SHIP CONSTRUCTION","Mayo","Parke, Castlebar",8,"*N/A","","","","","","Q4-2019"],
    [1314,1314,"SHIP CONSTRUCTION","Mayo","Radharc an tSaillin, Binghamstown, Belmullet (Phase 2)",4,"*N/A","","","","","","Q2-2019"],
    [1315,1315,"SHIP CONSTRUCTION","Mayo","Sliabh Rua, Foxford (Phase 3)",10,"*N/A","","","","","","Q4-2019"],
    [1316,1316,"SHIP CONSTRUCTION","Mayo","Tonragee West, Achill (Phase 2)",5,"N/A","","","","","","Q4-2019"],
    [1317,1317,"SHIP CONSTRUCTION","Mayo","Woodlands, Balla (Phase 3)",4,"*N/A","","","","","","Q4-2019"],
    [1318,1318,"SHIP CONSTRUCTION","Mayo","Kilmaine",6,"*N/A","","","","","","Q4-2019"],
    [1319,1319,"SHIP CONSTRUCTION","Mayo","The Boreen, Crossmolina",3,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [1320,1320,"SHIP CONSTRUCTION","Mayo","Deel Court, Crossmolina",3,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [1321,1321,"SHIP CONSTRUCTION","Mayo","Knockroe, Moygownagh",3,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [1322,1322,"SHIP CONSTRUCTION","Mayo","Pound Road, Castlebar",6,"*N/A","","","","","","Q4-2019"],
    [1323,1323,"SHIP CONSTRUCTION TURNKEY","Mayo","Ard Rua, Claremorris",7,"*N/A","","","","","","Q4-2019"],
    [1324,1324,"SHIP CONSTRUCTION TURNKEY","Mayo","Chapel Street, Louisburgh",3,"*N/A","","","","","","Q4-2019"],
    [1325,1325,"SHIP CONSTRUCTION TURNKEY","Mayo","Cois Abhainn, Bonniconlon",2,"*N/A","","","","","","Q2-2019"],
    [1326,1326,"SHIP CONSTRUCTION TURNKEY","Mayo","Davitt Terrace, Castlebar",4,"*N/A","","","","","","Q4-2019"],
    [1327,1327,"SHIP CONSTRUCTION TURNKEY","Mayo","Friars Court, Ballina",2,"*N/A","","","","","","Q4-2019"],
    [1328,1328,"SHIP CONSTRUCTION TURNKEY","Mayo","Carrabeg, Newport Road, Castlebar",2,"*N/A","","","","","","Q4-2018"],
    [1329,1329,"SHIP CONSTRUCTION TURNKEY","Mayo","Bunree, Ballina",3,"*N/A","","","","","Q4-2019",""],
    [1330,1330,"SHIP CONSTRUCTION TURNKEY","Mayo","Riverside Drive, Ballina",3,"*N/A","","","","","","Q4-2019"],
    [1331,1331,"SHIP CONSTRUCTION TURNKEY","Mayo","Chapel St., Louisburgh",2,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1332,1332,"CALF Turnkey","Meath","18 units Churchfields, Ashbourne, Co. Meath (Phase 1)",18,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1333,1333,"CALF Turnkey","Meath","6 Units Seabury Lawns, Mornington, Co Meath (Phase 1)",6,"Cluid Housing","","","","","","Q1-2018"],
    [1334,1334,"CALF Turnkey","Meath","Ardmore Rise, Bettystown, Co Meath  (Phase 1)",1,"North & East Housing Association Ltd","","","","","","Q4-2018"],
    [1335,1335,"CALF Turnkey","Meath","Athboy Road, Navan, Co. Meath (Phase 1)*",63,"Respond","","","","","Q2-2019",""],
    [1336,1336,"CALF Turnkey","Meath","Blackcastle, Slane Road, Navan, Co. Meath (Phase 1)",9,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1337,1337,"CALF Turnkey","Meath","5 units Dunville, Athlumney, Navan, Co. Meath (Phase 1)",5,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [1338,1338,"CALF Turnkey","Meath","Ceamach Close, Donacarney, Co Meath  (Phase 1)",7,"Cluid Housing","","","","","","Q2-2018"],
    [1339,1339,"CALF Turnkey","Meath","Ceamach Close, Donacarney, Co Meath  (Phase 2)*",9,"Cluid Housing","","","","","","Q3-2018"],
    [1340,1340,"CALF Turnkey","Meath","Cherryvalley, Rathmoylan, Co Meath (Phase 1)",9,"Cluid Housing","","","","","","Q4-2017"],
    [1341,1341,"CALF Turnkey","Meath","Churchfields, Ashbourne, Co Meath (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [1342,1342,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 1)*",10,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1343,1343,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 1)*",1,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1344,1344,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 2)*",1,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1345,1345,"CALF Turnkey","Meath","Broadmeadow Vale, Ratoath, Meath (Phase 3)*",10,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1346,1346,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 1)",10,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1347,1347,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 2)*",8,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1348,1348,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 3)*",10,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1349,1349,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 4)*",6,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1350,1350,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 5)*",18,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1351,1351,"CALF Turnkey","Meath","Dunville, Athlumney, Co Meath  (Phase 6)",12,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1352,1352,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 2)*",3,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1353,1353,"CALF Turnkey","Meath","Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)*",1,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1354,1354,"CALF Turnkey","Meath","Frederick Manor, Ashbourne, Co. Meath (Phase 1)*",11,"Cluid Housing","","","","","Q4-2017",""],
    [1355,1355,"CALF Turnkey","Meath","Churchfields, Ashbourne, Meath (Phase 3)*",12,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1356,1356,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 2)",19,"T�ath Housing Association Ltd","","","","","Q3-2018",""],
    [1357,1357,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 3)",15,"T�ath Housing Association Ltd","","","","","Q3-2018",""],
    [1358,1358,"CALF Turnkey","Meath","Grangehall, Dunshaughlin (Phase 1)",7,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1359,1359,"CALF Turnkey","Meath","Kellets Grove, Dunshauglin, Co Meath  (Phase 1)*",6,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1360,1360,"CALF Turnkey","Meath","Ledwidge Hall Green, Drogheda Road, Slane, Co. Meath (Phase 1)*",6,"Oaklee Housing","","","","","Q1-2017",""],
    [1361,1361,"CALF Turnkey","Meath","Ledwidge Hall Green, Drogheda Road, Slane, Co. Meath (Phase 2)",6,"Oaklee Housing","","","","","Q1-2017",""],
    [1362,1362,"CALF Turnkey","Meath","Ledwidge Hall Green, Drogheda Road, Slane, Co. Meath (Phase 3)*",16,"Oaklee Housing","","","","","Q1-2017",""],
    [1363,1363,"CALF Turnkey","Meath","Mill Lane, Flower Hill, Navan, Co Meath (Phase 1)",20,"Oaklee Housing","","","","","","Q4-2016"],
    [1364,1364,"CALF Turnkey","Meath","Millrace Court, Emmet Street, Trim, Co Meath  (Phase 1)",11,"North & East Housing Association Ltd","","","","","","Q2-2018"],
    [1365,1365,"CALF Turnkey","Meath","Millteog, Athboy Road, Trim, Co. Meath (Phase 2)*",9,"Oaklee Housing","","","","","Q2-2019",""],
    [1366,1366,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 1)",11,"Cluid Housing","","","","","","Q1-2017"],
    [1367,1367,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 2)",36,"Cluid Housing","","","","","","Q4-2017"],
    [1368,1368,"CALF Turnkey","Meath","Milltown, Ashbourne, Co Meath (Phase 3)",20,"Cluid Housing","","","","","","Q4-2017"],
    [1369,1369,"CALF Turnkey","Meath","Moydervey Manor, Longwood, Trim, Co. Meath (Phase 1)*",6,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1370,1370,"CALF Turnkey","Meath","Moydervey Manor, Longwood, Trim, Co. Meath (Phase 2)",7,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1371,1371,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)",3,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1372,1372,"CALF Turnkey","Meath","Commons Road, Navan, Co Meath  (Phase 1)",12,"North & East Housing Association Ltd","","","","","","Q4-2019"],
    [1373,1373,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 6)",20,"T�ath Housing Association Ltd","","","","","Q2-2018",""],
    [1374,1374,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 7)",4,"T�ath Housing Association Ltd","","","","","Q2-2018",""],
    [1375,1375,"CALF Turnkey","Meath","Royal Oaks, Enfield, Co Meath (Phase 1)*",4,"Cluid Housing","","","","","","Q2-2017"],
    [1376,1376,"CALF Turnkey","Meath","Seabury Lawns, Mornington, Co. Meath (Phase 1)",25,"Cluid Housing","","","","","","Q3-2017"],
    [1377,1377,"CALF Turnkey","Meath","Sl�n Duff, Kentstown, Co. Meath (Phase 1)",2,"Cluid Housing","","","","","Q1-2018",""],
    [1378,1378,"CALF Turnkey","Meath","Station Road, Dunboyne, Co. Meath (Phase 1)",24,"Respond","","","","","","Q4-2018"],
    [1379,1379,"CALF Turnkey","Meath","The Bungalows, Dunshauglin, Co. Meath (Phase 1)*",8,"Circle Voluntary Housing Association Ltd","","","","","Q3-2019",""],
    [1380,1380,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 1)",8,"Cluid Housing","","","","","","Q2-2016"],
    [1381,1381,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 2)",7,"Cluid Housing","","","","","","Q3-2016"],
    [1382,1382,"CALF Turnkey","Meath","Tubberclaire, Navan, Co Meath (Phase 3)",8,"Cluid Housing","","","","","","Q4-2016"],
    [1383,1383,"CALF Turnkey","Meath","Whitefield Hall, Bettystown, Co. Meath (Phase 1)",14,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1384,1384,"CALF Turnkey","Meath","Whitefield Hall, Bettystown, Co. Meath (Phase 2)",15,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1385,1385,"CALF Turnkey","Meath","Dun Eimear, Bettystown, Co. Meath (Phase 1)*",12,"Cluid Housing","","","","","","Q4-2019"],
    [1386,1386,"CALF Turnkey","Meath","Dun Eimear, Bettystown, Co. Meath (Phase 2)*",11,"Cluid Housing","","","","","","Q4-2019"],
    [1387,1387,"CALF Turnkey","Meath","Eastham Square, Bettystown, Meath (Phase 1)*",5,"Cluid Housing","","","","","","Q1-2019"],
    [1388,1388,"CALF Turnkey","Meath","Gainsfield, Commons Road, Navan, Co. Meath (Phase 1)",20,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1389,1389,"CALF Turnkey","Meath","Maudelins Brook, Duleek, Co.Meath (Phase 1)*",20,"Respond","","","","","","Q4-2019"],
    [1390,1390,"CALF Turnkey","Meath","Millteog, Athboy Road, Trim, Co. Meath (Phase 1)*",16,"Oaklee Housing","","","","","","Q4-2019"],
    [1391,1391,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 2)",6,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1392,1392,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 3)",2,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [1393,1393,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 4)",5,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [1394,1394,"CALF Turnkey","Meath","Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 5)",4,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1395,1395,"CALF Turnkey","Meath","The Way, Broadmeadow Vale, Ratoath, Co. Meath (Phase 1)",2,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1396,1396,"CAS CONSTRUCTION","Meath","Blackcastle, Slane Road, Navan",17,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1397,1397,"SHIP CONSTRUCTION","Meath","Cherry Court, Summerhill",19,"*N/A","","","","","","Q1-2019"],
    [1398,1398,"SHIP CONSTRUCTION","Meath","Bettystown (Phase 2)",15,"*N/A","","","","","Q1-2019",""],
    [1399,1399,"SHIP CONSTRUCTION","Meath","Riverside, Kells",40,"*N/A","","","","","Q1-2019",""],
    [1400,1400,"SHIP CONSTRUCTION","Meath","Connaught Grove, Athboy",32,"*N/A","","","","","","Q2-2018"],
    [1401,1401,"SHIP CONSTRUCTION","Meath","Nobber",18,"*N/A","","Stage 2 approved Q4-2018, full design/tender being prepared.","","","",""],
    [1402,1402,"SHIP CONSTRUCTION","Meath","Carlanstown",13,"*N/A","","","","","Q2-2019",""],
    [1403,1403,"SHIP CONSTRUCTION","Meath","Donore",21,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1404,1404,"SHIP CONSTRUCTION","Meath","Dunshaughlin",26,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1405,1405,"SHIP CONSTRUCTION","Meath","Bettystown (Phase 1)",16,"*N/A","","","","","","Q3-2017"],
    [1406,1406,"SHIP CONSTRUCTION","Meath","Blackhill Crescent, Donacarney",2,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1407,1407,"SHIP CONSTRUCTION","Meath","Archdeaconary Glebe, Kells",20,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1408,1408,"SHIP CONSTRUCTION","Meath","Nangle Court, Navan",6,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1409,1409,"SHIP CONSTRUCTION","Meath","Castle Street, Ashbourne",76,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1410,1410,"SHIP CONSTRUCTION","Meath","Church View, Rathmolyon",9,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1411,1411,"SHIP CONSTRUCTION","Meath","Church Street, Kells, Co. Meath",3,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1412,1412,"SHIP CONSTRUCTION","Meath","Haggard Street, Trim, Co. Meath",4,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1413,1413,"SHIP CONSTRUCTION","Meath","Pitcher Lane, Kells, Co. Meath",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1414,1414,"SHIP CONSTRUCTION","Meath","Swan Lane, Balreask",6,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1415,1415,"SHIP CONSTRUCTION","Meath","Carrick St., Kells",30,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1416,1416,"SHIP CONSTRUCTION","Meath","Lagore, Dunshaughlin",34,"*N/A","Stage 1 approved Q4-2019, outline design and costs being prepared.","","","","",""],
    [1417,1417,"SHIP CONSTRUCTION","Meath","St. Oliver's, Ratoath",17,"*N/A","","","","","","Q4-2019"],
    [1418,1418,"SHIP CONSTRUCTION","Meath","Proudstown Road, Navan",4,"*N/A","","","","","","Q4-2018"],
    [1419,1419,"SHIP CONSTRUCTION","Meath","The Belfry, Trim",3,"*N/A","","","","","","Q4-2019"],
    [1420,1420,"SHIP CONSTRUCTION TURNKEY","Meath","Bracken Hill, Kilmessan",3,"*N/A","","","","","","Q4-2019"],
    [1421,1421,"SHIP CONSTRUCTION TURNKEY","Meath","Broadmeadow Vale, Rathoath",2,"*N/A","","","","","","Q4-2019"],
    [1422,1422,"SHIP CONSTRUCTION TURNKEY","Meath","Cherry Hill Court, Kells",2,"*N/A","","","","","","Q4-2019"],
    [1423,1423,"SHIP CONSTRUCTION TURNKEY","Meath","Cluain Adain, Clonmagadden, Navan",4,"*N/A","","","","","","Q3-2019"],
    [1424,1424,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin Walk, Johnstown, Navan",4,"*N/A","","","","","","Q3-2019"],
    [1425,1425,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin, Johnstown, Navan ",8,"*N/A","","","","","","Q2-2019"],
    [1426,1426,"SHIP CONSTRUCTION TURNKEY","Meath","Cois na Mara, Bettystown",2,"*N/A","","","","","","Q3-2019"],
    [1427,1427,"SHIP CONSTRUCTION TURNKEY","Meath","Dun Eimear, Bettystown",8,"*N/A","","","","","","Q3-2019"],
    [1428,1428,"SHIP CONSTRUCTION TURNKEY","Meath","Dun Eimear, Bettystown",14,"*N/A","","","","","","Q4-2019"],
    [1429,1429,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin, Johnstown, Navan",19,"*N/A","","","","","","Q4-2018"],
    [1430,1430,"SHIP CONSTRUCTION TURNKEY","Meath","Cluain Adain, Clonmagadden, Navan",16,"*N/A","","","","","","Q4-2018"],
    [1431,1431,"SHIP CONSTRUCTION TURNKEY","Meath","Cois Glaisin Walk, Johnstown, Navan",5,"*N/A","","","","","","Q4-2018"],
    [1432,1432,"SHIP CONSTRUCTION RAPID","Meath","Oldcastle",16,"*N/A","","","","","","Q4-2019"],
    [1433,1433,"SHIP CONSTRUCTION RAPID","Meath","Cortown",10,"*N/A","","","","","","Q4-2019"],
    [1434,1434,"SHIP CONSTRUCTION RAPID","Meath","Kilmainhamwood",4,"*N/A","","","","","","Q4-2019"],
    [1435,1435,"CALF Construction","Monaghan","Post Tender - Liseggerton Road, Clones (Phase 1)",6,"Oaklee Housing","","","","","","Q4-2018"],
    [1436,1436,"CALF Turnkey","Monaghan","Bree, Castleblayney, Co. Monaghan (Phase 1)",13,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1437,1437,"CALF Turnkey","Monaghan","Bree, Castleblayney, Co. Monaghan (Phase 2)",12,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1438,1438,"CALF Turnkey","Monaghan","Bree, Castleblayney, Co. Monaghan (Phase 3)",13,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1439,1439,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 1)",7,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1440,1440,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 2)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1441,1441,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 3)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1442,1442,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 4)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1443,1443,"CALF Turnkey","Monaghan","Magheross, Carrickmacross, Co Monaghan (Phase 5)",14,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1444,1444,"CALF Turnkey","Monaghan","Kingscourt Road, Carrickmacross, Co Monaghan  (Phase 1)",50,"Respond","","","","","","Q4-2019"],
    [1445,1445,"CAS CONSTRUCTION","Monaghan","Drumillard, Castleblayney (Phase 2)",2,"Castleblayney Care Housing Association Ltd","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1446,1446,"CAS CONSTRUCTION","Monaghan","Liseggerton, Clones",16,"Oaklee Housing Trust","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1447,1447,"CAS CONSTRUCTION","Monaghan","Convent Lands, Carrickmacross",7,"Respond","","","","","","Q2-2017"],
    [1448,1448,"CAS CONSTRUCTION","Monaghan","Birch Court Apts., 34 Main Street, Ballybay",4,"North ? East Housing Association Ltd","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1449,1449,"SHIP CONSTRUCTION","Monaghan","Bree, Castleblayney",8,"*N/A","","","","","","Q2-2019"],
    [1450,1450,"SHIP CONSTRUCTION","Monaghan","Davy's & Adjacent Porperty, Fermanagh St., Clones",3,"*N/A","","","","","Q3-2019",""],
    [1451,1451,"SHIP CONSTRUCTION","Monaghan","Boyle Sports Site, Fermanagh St., Clones",3,"*N/A","","","","","Q3-2019",""],
    [1452,1452,"SHIP CONSTRUCTION","Monaghan","82 & 83 Fermanagh St., Clones",3,"*N/A","","","","","Q3-2019",""],
    [1453,1453,"SHIP CONSTRUCTION","Monaghan","An Bonnan Bui & Flower Shop, Fermanagh St., Clones",6,"*N/A","","","","","Q3-2019",""],
    [1454,1454,"SHIP CONSTRUCTION","Monaghan","2a & 3 Analore St., Clones",2,"*N/A","","","","","Q3-2019",""],
    [1455,1455,"SHIP CONSTRUCTION","Monaghan","Abbey Gatehouse, Analore St., Clones",4,"*N/A","","","","","Q3-2019",""],
    [1456,1456,"SHIP CONSTRUCTION","Monaghan","Lui Na Greine, Scotstown",32,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1457,1457,"SHIP CONSTRUCTION","Monaghan","Latlorcan, Monaghan",16,"*N/A","","","","","","Q4-2018"],
    [1458,1458,"SHIP CONSTRUCTION","Monaghan","12 Church St., Ballybay",2,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1459,1459,"SHIP CONSTRUCTION","Monaghan","3 Apts @ 63 Fermanagh St., Clones",3,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1460,1460,"SHIP CONSTRUCTION","Monaghan","2 Units @ 13 Church Hill, Clones",2,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1461,1461,"SHIP CONSTRUCTION","Monaghan","Latlorcan, Monaghan Town",43,"*N/A","","","","","","Q4-2019"],
    [1462,1462,"SHIP CONSTRUCTION TURNKEY","Monaghan","Drummond Radhairc, Carrickmacross",1,"*N/A","","","","","","Q3-2019"],
    [1463,1463,"SHIP CONSTRUCTION TURNKEY","Monaghan","Drumbear Wood, Monaghan Town",12,"*N/A","","","","","","Q4-2017"],
    [1464,1464,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town",6,"*N/A","","","","","","Q4-2017"],
    [1465,1465,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town (Phase 2)",8,"*N/A","","","","","","Q2-2017"],
    [1466,1466,"SHIP CONSTRUCTION TURNKEY","Monaghan","Knockroe Glen, Monaghan Town (Phase 1)",8,"*N/A","","","","","","Q2-2017"],
    [1467,1467,"SHIP CONSTRUCTION TURNKEY","Monaghan","Killycard, Bree, Castleblaney",4,"*N/A","","","","","","Q2-2019"],
    [1468,1468,"SHIP CONSTRUCTION TURNKEY","Monaghan","The Meadows, Smithborough",5,"*N/A","","","","","","Q4-2017"],
    [1469,1469,"SHIP CONSTRUCTION TURNKEY","Monaghan","Maple Grove, Smithborough",11,"*N/A","","","","","","Q4-2018"],
    [1470,1470,"SHIP CONSTRUCTION TURNKEY","Monaghan","Rosevale, Bree, Castleblayney",26,"*N/A","","","","","Q2-2019",""],
    [1471,1471,"SHIP CONSTRUCTION TURNKEY","Monaghan","Corr an Tobair, Carrickmacross, Co. Monaghan",41,"*N/A","","","","","Q3-2019",""],
    [1472,1472,"SHIP CONSTRUCTION TURNKEY","Monaghan","Coill an Ri, Carrickmacross, Co. Monaghan",8,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1473,1473,"SHIP CONSTRUCTION TURNKEY","Monaghan","The Meadows, Smithborough",5,"*N/A","","","","","","Q3-2019"],
    [1474,1474,"CALF Construction","Offaly","Kearney�s Field, Tullamore, Co. Offaly (Phase 1)",41,"Oaklee Housing","","","","Q2-2019","",""],
    [1475,1475,"CALF Construction","Offaly","Killane Drive, Edenderry, Co Offaly (Phase 1)",25,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1476,1476,"CALF Turnkey","Offaly","3 units, An Corran, Crinkle, Birr, Co. Offaly (Phase 1)",3,"Co-operative Housing Ireland","","","","","Q3-2019",""],
    [1477,1477,"CALF Turnkey","Offaly","Riverside, Portarlington, Co. Offaly (Phase 1)",8,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1478,1478,"CALF Turnkey","Offaly","Riverside, Portarlington, Co. Offaly (Phase 2)",8,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1479,1479,"CAS CONSTRUCTION","Offaly","Killane Court, Edenderry",2,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1480,1480,"CAS CONSTRUCTION","Offaly","Clonminch, Tullamore",19,"Oaklee Housing Trust","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [1481,1481,"CAS CONSTRUCTION","Offaly","Presentation Convent, Portarlington",32,"Sophia Housing Association Ltd","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1482,1482,"CAS CONSTRUCTION","Offaly","Mountbolus",4,"Mid Offaly Housing Association Ltd","","","","","","Q4-2019"],
    [1483,1483,"CAS CONSTRUCTION","Offaly","Scurragh, Birr (AKA Camcor Green)",6,"Cluid Housing Association","","","","","","Q4-2019"],
    [1484,1484,"SHIP CONSTRUCTION","Offaly","Blundell Wood, Edenderry",33,"*N/A","","","","","","Q4-2019"],
    [1485,1485,"SHIP CONSTRUCTION","Offaly","Chancery Lane, Tullamore",14,"*N/A","","","","","Q3-2018",""],
    [1486,1486,"SHIP CONSTRUCTION","Offaly","Circular Road, Daingean",7,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1487,1487,"SHIP CONSTRUCTION","Offaly","Kylebeg, Banagher (Phase 2)",18,"*N/A","Stage 1 approved Q3-2017, outline design and costs being prepared.","","","","",""],
    [1488,1488,"SHIP CONSTRUCTION","Offaly","Church Street, Clara",3,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1489,1489,"SHIP CONSTRUCTION","Offaly","Beechgrove, Belmont",7,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1490,1490,"SHIP CONSTRUCTION","Offaly","Raheen ,Clara",38,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1491,1491,"SHIP CONSTRUCTION","Offaly","Elderberry Drive, Moneygall",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1492,1492,"SHIP CONSTRUCTION","Offaly","Sr. Senan Avenue, Edenderry",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1493,1493,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Greine, Cloneygowan",4,"*N/A","","","","","","Q4-2019"],
    [1494,1494,"SHIP CONSTRUCTION TURNKEY","Offaly","McGregol, Birr (Phase 2)",8,"*N/A","","","","Stage 4 approved Q3-2018, the scheme is fully approved.","",""],
    [1495,1495,"SHIP CONSTRUCTION TURNKEY","Offaly","Mill Race, Ferbane",5,"*N/A","","","","","","Q4-2017"],
    [1496,1496,"SHIP CONSTRUCTION TURNKEY","Offaly","Cluain na Spideoga, Cloghan",6,"*N/A","","","","","","Q2-2019"],
    [1497,1497,"SHIP CONSTRUCTION TURNKEY","Offaly","Frankford, Kilcormac",12,"*N/A","","","","","","Q4-2018"],
    [1498,1498,"SHIP CONSTRUCTION TURNKEY","Offaly","McGregol, Birr (Phase 1)",4,"*N/A","","","","","","Q4-2019"],
    [1499,1499,"CALF Turnkey","Roscommon","Castle View Apartments, Block A, Roscommon Town (Phase 1)",10,"Co-operative Housing Ireland","","","","","Q2-2019",""],
    [1500,1500,"CALF Turnkey","Roscommon","Revised - Monksfield Park, Bealnamulla, Athlone (Phase 1)",13,"Cluid Housing","","","","","","Q3-2018"],
    [1501,1501,"CALF Turnkey","Roscommon","River Oaks, Kilcolman, Ballaghaderreen, Co. Roscommon (Phase 1)",12,"Respond","","","","","","Q1-2018"],
    [1502,1502,"CALF Turnkey","Roscommon","Castle View Apartments, Block B, Roscommon Town (Phase 1)",10,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1503,1503,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Roscommon","The Walk, Roscommon Town",53,"*N/A","","","","","Q4-2019",""],
    [1504,1504,"SHIP CONSTRUCTION","Roscommon","Cloonfad",3,"*N/A","","","","","Q4-2019",""],
    [1505,1505,"SHIP CONSTRUCTION","Roscommon","Greenfields, Blackstick Road, Roscommon Town",6,"*N/A","","","","","","Q3-2017"],
    [1506,1506,"SHIP CONSTRUCTION","Roscommon","River Oaks, Ballaghaderreen",10,"*N/A","","","","","","Q4-2017"],
    [1507,1507,"SHIP CONSTRUCTION","Roscommon","Silveroe Meadows, Boyle",12,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1508,1508,"SHIP CONSTRUCTION","Roscommon","Cluain Fraoigh, Cloonbeirne",7,"*N/A","","","","","Q4-2019",""],
    [1509,1509,"SHIP CONSTRUCTION","Roscommon","Old Tuam Road,  Monksland, Athlone",2,"*N/A","","","Stage 3 approved Q2-2019, the scheme is now approved to proceed to tender.","","",""],
    [1510,1510,"SHIP CONSTRUCTION","Roscommon","Meadowbrook, Ballyclare Td., Ballyleague, Co. Roscommon",18,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1511,1511,"SHIP CONSTRUCTION","Roscommon","Lisroyne Td., Strokestown",10,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1512,1512,"SHIP CONSTRUCTION TURNKEY","Roscommon","Monksland, Athlone",10,"*N/A","","","","","","Q3-2018"],
    [1513,1513,"SHIP CONSTRUCTION TURNKEY","Roscommon","Lisroyne Court, Strokestown",10,"*N/A","","","","","","Q4-2019"],
    [1514,1514,"SHIP CONSTRUCTION TURNKEY","Roscommon","Warren Grove, Boyle",4,"*N/A","","","","","","Q4-2018"],
    [1515,1515,"SHIP CONSTRUCTION TURNKEY","Roscommon","Monksfield, Monksland, Co. Roscommon",2,"*N/A","","","","","Q3-2019",""],
    [1516,1516,"SHIP CONSTRUCTION TURNKEY","Roscommon","Station Road, Termon, Boyle",10,"*N/A","","","","","","Q1-2019"],
    [1517,1517,"CAS CONSTRUCTION","Sligo","Cuan Iosa, Ballymote",8,"Society of Saint Vincent de Paul","","","","","Q4-2018",""],
    [1518,1518,"CAS CONSTRUCTION","Sligo","Killeshin, First Sea Road, Sligo",4,"Newgrove Housing Association Ltd","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1519,1519,"SHIP CONSTRUCTION","Sligo","Knappagh Road",28,"*N/A","","","","","Q4-2018",""],
    [1520,1520,"SHIP CONSTRUCTION","Sligo","Caltragh, Culleens",1,"*N/A","","","","","","Q4-2018"],
    [1521,1521,"SHIP CONSTRUCTION","Sligo","Fr. Flanagan Terrace",14,"*N/A","","","","","","Q3-2018"],
    [1522,1522,"SHIP CONSTRUCTION","Sligo","Daghloonagh, Keash - SRD",1,"*N/A","","","","","","Q4-2016"],
    [1523,1523,"SHIP CONSTRUCTION","Sligo","Collooney",18,"*N/A","","","","","","Q4-2019"],
    [1524,1524,"SHIP CONSTRUCTION","Sligo","Fr. Flanagan Terrace",8,"*N/A","","","","","","Q4-2017"],
    [1525,1525,"SHIP CONSTRUCTION","Sligo","Connolly Park, Tubbercurry",10,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1526,1526,"SHIP CONSTRUCTION","Sligo","Dromore West",10,"*N/A","","","","","Q4-2019",""],
    [1527,1527,"SHIP CONSTRUCTION","Sligo","House at Ballinode",1,"*N/A","","","","","","Q4-2018"],
    [1528,1528,"SHIP CONSTRUCTION","Sligo","SRD ar Crowagh, Dromore West",1,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1529,1529,"SHIP CONSTRUCTION","Sligo","Rosses Point",14,"*N/A","","","","","","Q4-2019"],
    [1530,1530,"SHIP CONSTRUCTION","Sligo","St. Joseph's Terrace, Sligo",1,"*N/A","","","","","","Q4-2019"],
    [1531,1531,"SHIP CONSTRUCTION TURNKEY","Sligo","Fairgreen Square, Ballisodare",2,"*N/A","","","","","","Q4-2019"],
    [1532,1532,"SHIP CONSTRUCTION RAPID","South Dublin","St Cuthbert's, Clondalkin (Phase 1)",63,"*N/A","","","","","","Q3-2019"],
    [1533,1533,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght",47,"*N/A","","","","","","Q2-2018"],
    [1534,1534,"SHIP CONSTRUCTION RAPID","South Dublin","Riversdale, Clondalkin, Dublin 22",43,"*N/A","","Stage 2 approved Q4-2018, full design/tender being prepared.","","","",""],
    [1535,1535,"SHIP CONSTRUCTION RAPID","South Dublin","Killininny Road, Firhouse (Old Mill, Old Bawn)",24,"*N/A","","","","","","Q4-2018"],
    [1536,1536,"CALF Construction","South Dublin","Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 1)",40,"Cluid Housing","","","","Q4-2019","",""],
    [1537,1537,"CALF Construction","South Dublin","St. Catherines, Killinarden, Tallaght, Dublin 24 (Phase 1)",2,"Sophia Housing Association Ltd","","","","Q2-2019","",""],
    [1538,1538,"CALF Construction","South Dublin","Whitestown Way, Tallaght, Dublin 24 (Phase 1)",81,"Cluid Housing","","","","Q1-2019","",""],
    [1539,1539,"CALF Turnkey","South Dublin","2 properties Tullyhall, Lucan, County Dublin (Phase 1)*",2,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1540,1540,"CALF Turnkey","South Dublin","6 units Elder Heath, Kiltipper Road, Tallaght, Dublin 24 (Phase 1)*",6,"Cluid Housing","","","","","","Q4-2019"],
    [1541,1541,"CALF Turnkey","South Dublin","Ballynakelly, Newcastle, Co. Dublin (Phase 1)",6,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1542,1542,"CALF Turnkey","South Dublin","Ardsolus, Old Naas Road, Dublin 22 (Phase 1)",10,"Respond","","","","","","Q3-2019"],
    [1543,1543,"CALF Turnkey","South Dublin","Ballynakelly, Newcastle, Co. Dublin (Phase 2)",4,"T�ath Housing Association Ltd","","","","","","Q1-2019"],
    [1544,1544,"CALF Turnkey","South Dublin","Broadfield Grove, Rathcoole, Co. Dublin (Phase 1)*",14,"Oaklee Housing","","","","","","Q3-2017"],
    [1545,1545,"CALF Turnkey","South Dublin","Burgage Gardens, Newcastle, Co. Dublin (Phase 1)*",4,"Respond","","","","","Q3-2019",""],
    [1546,1546,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 1)",16,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1547,1547,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 2)",12,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1548,1548,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 3)",14,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1549,1549,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 4)",15,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1550,1550,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 5)",6,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1551,1551,"CALF Turnkey","South Dublin","Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 6)*",20,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1552,1552,"CALF Turnkey","South Dublin","Cuil Duin Green, Cuil Duin, Citywest, Dublin 24 (Phase 1)*",24,"Fold Housing Association Ireland Ltd","","","","","Q4-2018",""],
    [1553,1553,"CALF Turnkey","South Dublin","Balrothery, Castletymon Road, Dublin Road (Phase 1)*",13,"Cluid Housing","","","","","","Q4-2019"],
    [1554,1554,"CALF Turnkey","South Dublin","Dodderbrook (Apartments), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*",6,"Cluid Housing","","","","","","Q1-2018"],
    [1555,1555,"CALF Turnkey","South Dublin","Dodderbrook (Houses), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*",8,"Cluid Housing","","","","","","Q1-2018"],
    [1556,1556,"CALF Turnkey","South Dublin","De Selby Lawns, Heights, Dublin 24 (Phase 1)",9,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1557,1557,"CALF Turnkey","South Dublin","Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 2)*",9,"Cluid Housing","","","","","Q1-2019",""],
    [1558,1558,"CALF Turnkey","South Dublin","Dodderbrook, Oldcourt Road, Ballycllen, Dublin 24 (Phase 1)*",4,"Cluid Housing","","","","","","Q3-2018"],
    [1559,1559,"CALF Turnkey","South Dublin","Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 1)*",4,"Cluid Housing","","","","","","Q4-2019"],
    [1560,1560,"CALF Turnkey","South Dublin","Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 1)*",18,"Cluid Housing","","","","","","Q1-2018"],
    [1561,1561,"CALF Turnkey","South Dublin","Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 2)*",10,"Cluid Housing","","","","","","Q2-2018"],
    [1562,1562,"CALF Turnkey","South Dublin","Finnstown, Lucan, Co. Dublin (Phase 1)*",94,"Respond","","","","","Q4-2018",""],
    [1563,1563,"CALF Turnkey","South Dublin","Green Lane, Rathcoole, Co. Dublin (Phase 1)*",12,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1564,1564,"CALF Turnkey","South Dublin","Green Lane, Rathcoole, Co. Dublin (Phase 2)*",9,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1565,1565,"CALF Turnkey","South Dublin","Kingswood, Old Ballymount Road, Tallaght, Dublin 24 (Phase 1)*",24,"Respond","","","","","Q4-2018",""],
    [1566,1566,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Apartments (Phase 1)*",13,"Cluid Housing","","","","","","Q2-2018"],
    [1567,1567,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Apartments (Phase 2)",12,"Cluid Housing","","","","","","Q4-2018"],
    [1568,1568,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Houses (Phase 1)",25,"Cluid Housing","","","","","","Q1-2017"],
    [1569,1569,"CALF Turnkey","South Dublin","Millford Manor, Clondalkin - Houses (Phase 2)",15,"Cluid Housing","","","","","","Q3-2017"],
    [1570,1570,"CALF Turnkey","South Dublin","Millford Manor, Cloverhill Road, Clondalkin, Dublin 22 (Phase 1)*",2,"Cluid Housing","","","","","","Q4-2018"],
    [1571,1571,"CALF Turnkey","South Dublin","New Bancroft, Tallaght, Dublin 24 (Phase 1)*",16,"Cluid Housing","","","","","","Q3-2017"],
    [1572,1572,"CALF Turnkey","South Dublin","Palmerstown Avenue, Dublin 20 (Phase 1)",7,"Respond","","","","","Q2-2019",""],
    [1573,1573,"CALF Turnkey","South Dublin","Palmerstown Way, Clondalkin, Dublin 22 (Phase 1)*",6,"T�ath Housing Association Ltd","","","","","","Q3-2018"],
    [1574,1574,"CALF Turnkey","South Dublin","Edenbrook, Citywest, Dublin 24 (Phase 1)",17,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1575,1575,"CALF Turnkey","South Dublin","Scholarstown Wood (Apartments), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*",6,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [1576,1576,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2017"],
    [1577,1577,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 2)*",4,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [1578,1578,"CALF Turnkey","South Dublin","Raheen House, Old Nangor Road, Clondalkin, Dublin 22 (Phase 1)",9,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [1579,1579,"CALF Turnkey","South Dublin","Rathmill Meadows and Green, Rathcoole, Co. Dublin (Phase 1)*",11,"Oaklee Housing","","","","","","Q4-2019"],
    [1580,1580,"CALF Turnkey","South Dublin","South Castle, Newcastle, Co. Dublin (Phase 2)",26,"Respond","","","","","Q3-2019",""],
    [1581,1581,"CALF Turnkey","South Dublin","Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 3)*",1,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [1582,1582,"CALF Turnkey","South Dublin","Station Road, Clondalkin, Co. Dublin (Phase 1)",5,"Respond","","","","","","Q3-2017"],
    [1583,1583,"CALF Turnkey","South Dublin","Temple Court, Temple Woods, Greenhills Road, Dublin 12 (Phase 1)*",6,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1584,1584,"CALF Turnkey","South Dublin","The Mews, Citywest Village, Citywest, Dublin 24 (Phase 1)*",22,"Fold Housing Association Ireland Ltd","","","","","Q3-2019",""],
    [1585,1585,"CALF Turnkey","South Dublin","Shackleton Park, Lucan, Co. Dublin (Phase 1)*",8,"Cluid Housing","","","","","","Q2-2019"],
    [1586,1586,"CALF Turnkey","South Dublin","Tullyhall, Lucan, Co Dublin (Phase 1)*",2,"T�ath Housing Association Ltd","","","","","","Q3-2017"],
    [1587,1587,"CALF Turnkey","South Dublin","Tullyhall, Lucan, Co Dublin (Phase 2)*",2,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1588,1588,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 1)",28,"Cluid Housing","","","","","","Q4-2018"],
    [1589,1589,"CALF Turnkey","South Dublin","Somerton, Lucan, Co. Dublin (Phase 1)*",32,"Respond","","","","","","Q4-2019"],
    [1590,1590,"CALF Turnkey","South Dublin","South Castle, Newcastle, Co. Dublin (Phase 1)",10,"Respond","","","","","","Q4-2019"],
    [1591,1591,"CALF Turnkey","South Dublin","Wilkins View, Greenhills, Dublin 12 (Phase 1)*",3,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2018"],
    [1592,1592,"CALF Turnkey","South Dublin","St. Johns, Firhouse, Dublin 24 (Phase 1)*",10,"Respond","","","","","","Q4-2019"],
    [1593,1593,"CALF Turnkey","South Dublin","Stone Masons Court, Fortunestown Lane, Citywest Dublin (Phase 1)*",12,"Cluid Housing","","","","","","Q2-2019"],
    [1594,1594,"CALF Turnkey","South Dublin","The Rise, Citywest Village, Citywest, Dublin 24 (Phase 1)*",13,"Fold Housing Association Ireland Ltd","","","","","","Q4-2019"],
    [1595,1595,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 2)",28,"Cluid Housing","","","","","","Q2-2019"],
    [1596,1596,"CALF Turnkey","South Dublin","Westpark, Garters Lane, Saggert, Co Dublin  (Phase 3)",28,"Cluid Housing","","","","","","Q4-2019"],
    [1597,1597,"CALF Turnkey","South Dublin","Wilkins Court, Limekiln Lane, Dublin 12 (Phase 1)*",6,"Circle Voluntary Housing Association Ltd","","","","","","Q2-2019"],
    [1598,1598,"CAS CONSTRUCTION","South Dublin","Collinstown Grove, Clondalkin",4,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1599,1599,"CAS CONSTRUCTION","South Dublin","Old Nangor Road, Clondalkin",10,"Simon Community : Dublin Simon","","","","","Q4-2019",""],
    [1600,1600,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","South Dublin","Corkage Grange (part of Kilcarbery)",109,"*N/A","","","","","Q1-2019",""],
    [1601,1601,"SHIP CONSTRUCTION","South Dublin","Killinarden, Tallaght (Phase 2)",9,"*N/A","","","","","","Q1-2019"],
    [1602,1602,"SHIP CONSTRUCTION","South Dublin","Owendoher, Ballyboden,  Rathfarnham",40,"*N/A","","","","","","Q1-2019"],
    [1603,1603,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght (Phase 2)",22,"*N/A","","","","","","Q3-2018"],
    [1604,1604,"SHIP CONSTRUCTION RAPID","South Dublin","St. Aidan's Brookfield, Tallaght (Sheehy Skeffington)",21,"*N/A","","","","","","Q4-2018"],
    [1605,1605,"SHIP CONSTRUCTION","South Dublin","Killinarden, Tallaght",17,"*N/A","","","","","","Q4-2018"],
    [1606,1606,"SHIP CONSTRUCTION","South Dublin","Letts Field, Neilstown, Clondalkin",37,"*N/A","","","","","","Q4-2018"],
    [1607,1607,"SHIP CONSTRUCTION","South Dublin","Dromcarra, Tallaght",14,"*N/A","","","","","","Q4-2018"],
    [1608,1608,"SHIP CONSTRUCTION","South Dublin","Fortunestown (MacUilliam)",28,"*N/A","","","","","","Q4-2018"],
    [1609,1609,"SHIP CONSTRUCTION","South Dublin","Mayfield Estate, Clondalkin",17,"*N/A","","","","","","Q2-2018"],
    [1610,1610,"SHIP CONSTRUCTION","South Dublin","St Marks Green, Clondalkin",11,"*N/A","","","","","","Q3-2018"],
    [1611,1611,"SHIP CONSTRUCTION","South Dublin","St. Marks Avenue, Clondalkin",41,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1612,1612,"SHIP CONSTRUCTION","South Dublin","St Finians",2,"*N/A","","","","","","Q3-2016"],
    [1613,1613,"SHIP CONSTRUCTION","South Dublin","Suncroft, Tallaght",10,"*N/A","","","","","","Q4-2016"],
    [1614,1614,"SHIP CONSTRUCTION","South Dublin","Belgard Road",3,"*N/A","","","","","","Q1-2016"],
    [1615,1615,"SHIP CONSTRUCTION","South Dublin","St. Catherine�s, Knockmore Avenue, Killinarden, Tallaght",12,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1616,1616,"SHIP CONSTRUCTION","South Dublin","Homeville, Knocklyon, Dublin 16",16,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1617,1617,"SHIP CONSTRUCTION","South Dublin","Nangor Road, Clondalkin, Dublin 22",93,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1618,1618,"SHIP CONSTRUCTION TURNKEY","South Dublin","Gandon Park, Adamstown, Lucan",12,"*N/A","","","","","","Q4-2019"],
    [1619,1619,"SHIP CONSTRUCTION TURNKEY","South Dublin","Shackleton Park / Gandon Park, Adamstown",22,"*N/A","","","","","","Q4-2019"],
    [1620,1620,"SHIP CONSTRUCTION TURNKEY","South Dublin","Ardsolus, Kingswood, Dublin 24",2,"*N/A","","","","","","Q4-2018"],
    [1621,1621,"SHIP CONSTRUCTION TURNKEY","South Dublin","White Pines, Stocking Avenue, Rathfarnham, Dublin 16",26,"*N/A","","","","","","Q4-2018"],
    [1622,1622,"SHIP CONSTRUCTION RAPID","South Dublin","Riverside Cottages, Templeogue",11,"*N/A","","Stage 2 approved Q1-2019, full design/tender being prepared.","","","",""],
    [1623,1623,"CALF Turnkey","Tipperary","An Duiche, Tipperary Town, Co. Tipperary (Phase 1)",41,"Respond","","","","","","Q4-2019"],
    [1624,1624,"CALF Turnkey","Tipperary","Ashbury, Roscrea, Co Tipperary (Phase 1)",12,"Cluid Housing","","","","","","Q2-2017"],
    [1625,1625,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co Tipperary  (Phase 1)",9,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [1626,1626,"CALF Turnkey","Tipperary","An Duiche, Tipperary Town, Co. Tipperary (Phase 2)",2,"Respond","","","","","","Q4-2019"],
    [1627,1627,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 2)",7,"Co-operative Housing Ireland","","","","","Q1-2019",""],
    [1628,1628,"CALF Turnkey","Tipperary","Mill Street, Carrick on Suir, Co. Tipperary (Phase 1)",22,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1629,1629,"CALF Turnkey","Tipperary","Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 1)",10,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1630,1630,"CAS CONSTRUCTION","Tipperary","Ballinagrana, Carrick on Suir",3,"Camphill Communities of Ireland","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1631,1631,"CAS CONSTRUCTION","Tipperary","Castle Street, Carrick on Suir",1,"Camphill Communities of Ireland","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1632,1632,"CAS CONSTRUCTION","Tipperary","The Strand, Carrick on Suir",3,"Camphill Communities of Ireland","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1633,1633,"CAS CONSTRUCTION","Tipperary","Glenconnor Road, Clonmel",9,"Cluid Housing Association","","Stage 2 approved Q4-2017, full design/tender being prepared.","","","",""],
    [1634,1634,"CAS CONSTRUCTION","Tipperary","Stanwix House, Kickham Street, Thurles",19,"Thurles Lions Trust Housing Assoc.","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1635,1635,"CAS CONSTRUCTION TURNKEY","Tipperary","Monastery Close, Templemore Road, Thurles",15,"Thurles Lions Trust Housing Assoc.","","","","","","Q2-2019"],
    [1636,1636,"SHIP CONSTRUCTION","Tipperary","Ard na Greine, Clonmel",2,"*N/A","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [1637,1637,"SHIP CONSTRUCTION","Tipperary","Knockanrawley",28,"*N/A","","","","","Q4-2019",""],
    [1638,1638,"SHIP CONSTRUCTION","Tipperary","Mill Road, Thurles",28,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [1639,1639,"SHIP CONSTRUCTION","Tipperary","Mulkear View, Newport",11,"*N/A","","Stage 2 approved Q4-2017, full design/tender being prepared.","","","",""],
    [1640,1640,"SHIP CONSTRUCTION","Tipperary","Treacy Park, Carrick on Suir",1,"*N/A","","","","","","Q3-2018"],
    [1641,1641,"SHIP CONSTRUCTION","Tipperary","Templetouhy",10,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1642,1642,"SHIP CONSTRUCTION","Tipperary","Borrisoleigh",12,"*N/A","Stage 1 approved Q1-2016, outline design and costs being prepared.","","","","",""],
    [1643,1643,"SHIP CONSTRUCTION","Tipperary","Abbey Street, Cahir",10,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [1644,1644,"SHIP CONSTRUCTION","Tipperary","Borrisokane",16,"*N/A","","","Stage 3 approved Q3-2019, the scheme is now approved to proceed to tender.","","",""],
    [1645,1645,"SHIP CONSTRUCTION","Tipperary","Portroe, Nenagh",14,"*N/A","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [1646,1646,"SHIP CONSTRUCTION","Tipperary","Cloughjordan",2,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1647,1647,"SHIP CONSTRUCTION","Tipperary","Glenconnor Road, Clonmel",26,"*N/A","","","","","Q4-2018",""],
    [1648,1648,"SHIP CONSTRUCTION","Tipperary","Gortataggart, Thurles",2,"*N/A","","","","","","Q4-2018"],
    [1649,1649,"SHIP CONSTRUCTION","Tipperary","Kilcooly Way, Gortnahoe",5,"*N/A","","","","","Q1-2019",""],
    [1650,1650,"SHIP CONSTRUCTION","Tipperary","Lacey Avenue, Templemore",3,"*N/A","","","","","","Q3-2016"],
    [1651,1651,"SHIP CONSTRUCTION","Tipperary","Mitchel St., Thurles",1,"*N/A","","","","","Q4-2019",""],
    [1652,1652,"SHIP CONSTRUCTION","Tipperary","Borrisoleigh",1,"*N/A","","","","","","Q4-2016"],
    [1653,1653,"SHIP CONSTRUCTION","Tipperary","Lower Ballingarry",1,"*N/A","","","","","","Q2-2016"],
    [1654,1654,"SHIP CONSTRUCTION","Tipperary","Poulamaleen, Faugheen",1,"*N/A","","","","","","Q2-2016"],
    [1655,1655,"SHIP CONSTRUCTION","Tipperary","Cormack Drive, Nenagh",12,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [1656,1656,"SHIP CONSTRUCTION","Tipperary","Lacey Avenue, Templemore",1,"*N/A","","","","","","Q3-2017"],
    [1657,1657,"SHIP CONSTRUCTION","Tipperary","Borrisoleigh",1,"*N/A","","","","","","Q4-2018"],
    [1658,1658,"SHIP CONSTRUCTION","Tipperary","Bansha",14,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1659,1659,"SHIP CONSTRUCTION","Tipperary","Twomileborris, Thurles",22,"*N/A","","Stage 2 approved Q2-2019, full design/tender being prepared.","","","",""],
    [1660,1660,"SHIP CONSTRUCTION","Tipperary","Donohill, ",4,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1661,1661,"SHIP CONSTRUCTION","Tipperary","Mullinahone",10,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1662,1662,"SHIP CONSTRUCTION","Tipperary","Clerihan",14,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1663,1663,"SHIP CONSTRUCTION","Tipperary","Ard Alainn, Moyne",9,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1664,1664,"SHIP CONSTRUCTION","Tipperary","Ardcroney",4,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1665,1665,"SHIP CONSTRUCTION","Tipperary","Mulkear View, Newport, Tipperary",3,"*N/A","","","","","","Q4-2018"],
    [1666,1666,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles (Phase 2)",5,"*N/A","","","","","","Q4-2019"],
    [1667,1667,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles (Phase 3)",5,"*N/A","","","","","","Q4-2019"],
    [1668,1668,"SHIP CONSTRUCTION TURNKEY","Tipperary","Strylea, Fethard",3,"*N/A","","","","","Q4-2018",""],
    [1669,1669,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ardan, Borrisokane",9,"*N/A","","","","","","Q4-2018"],
    [1670,1670,"SHIP CONSTRUCTION TURNKEY","Tipperary","An Grianan, Killenaule, Thurles",4,"*N/A","","","","","","Q4-2018"],
    [1671,1671,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ardan, Borrisokane (Phase 2)",4,"*N/A","","","","","","Q2-2019"],
    [1672,1672,"SHIP CONSTRUCTION TURNKEY","Tipperary","Prior Park, Clonmel",20,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1673,1673,"SHIP CONSTRUCTION TURNKEY","Tipperary","Ma Charoin, Manna South, Templemore",13,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1674,1674,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard",6,"*N/A","","","","","","Q2-2019"],
    [1675,1675,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard (Phase 2)",5,"*N/A","","","","","","Q3-2019"],
    [1676,1676,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard (Phase 3)",6,"*N/A","","","","","","Q4-2019"],
    [1677,1677,"SHIP CONSTRUCTION TURNKEY","Tipperary","Cloneen Road, Fethard (Phase 4)",4,"*N/A","","","","","","Q4-2019"],
    [1678,1678,"SHIP CONSTRUCTION TURNKEY","Tipperary","Glencree, Newport",3,"*N/A","","","","","","Q4-2019"],
    [1679,1679,"SHIP CONSTRUCTION TURNKEY","Tipperary","Prior Park, Clonmel",21,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1680,1680,"SHIP CONSTRUCTION RAPID","Waterford","Ballygunner, Waterford City",49,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1681,1681,"CALF Construction","Waterford","St Johns College, Waterford (Phase 1)",36,"Respond","","","","","","Q1-2016"],
    [1682,1682,"CALF Turnkey","Waterford","Kilbarry, Waterford (Phase 1)",69,"Respond","","","","","Q4-2018",""],
    [1683,1683,"CALF Turnkey","Waterford","The Walk, Fairfield Park, Kilcohan, Waterford (Phase 1)",40,"Circle Voluntary Housing Association Ltd","","","","","","Q4-2019"],
    [1684,1684,"CAS CONSTRUCTION","Waterford","Convent Hill, Tramore",10,"Society of Saint Vincent de Paul","","","","","","Q1-2017"],
    [1685,1685,"CAS CONSTRUCTION","Waterford","Powersfield, Hennessys Road, Waterford",3,"Focus Ireland","","Stage 2 approved Q2-2016, full design/tender being prepared.","","","",""],
    [1686,1686,"CAS CONSTRUCTION","Waterford","Wadding Manor, Ferrybank",10,"Respond","","","","","Q4-2019",""],
    [1687,1687,"CAS CONSTRUCTION","Waterford","Gleann Ealach, Dunhill",8,"Gleann Ealach Housing Association","","Stage 2 approved Q4-2017, full design/tender being prepared.","","","",""],
    [1688,1688,"CAS CONSTRUCTION","Waterford","The Paddocks, Williamstown Rd. Waterford",9,"Anvers Housing Association Ltd","","","Stage 3 approved Q2-2018, the scheme is now approved to proceed to tender.","","",""],
    [1689,1689,"PUBLIC PRIVATE PARTNERSHIP (Bundle 2)","Waterford","Slievekeale, Waterford City",58,"*N/A","","","","","Q4-2019",""],
    [1690,1690,"SHIP CONSTRUCTION RAPID","Waterford","Ballynaneashagh, Waterford City",20,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [1691,1691,"SHIP CONSTRUCTION","Waterford","An Garran, Crobally Upper, Tramore",50,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [1692,1692,"SHIP CONSTRUCTION","Waterford","Alms Houses, Tallow",4,"*N/A","","","","","","Q4-2018"],
    [1693,1693,"SHIP CONSTRUCTION","Waterford","Ardmore Park/Priory Lawn, Waterford City",5,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1694,1694,"SHIP CONSTRUCTION","Waterford","Ballinroad, Dungarvan",21,"*N/A","","","","","Q2-2019",""],
    [1695,1695,"SHIP CONSTRUCTION","Waterford","Barrack Street, Cappoquin",4,"*N/A","","","","","","Q4-2017"],
    [1696,1696,"SHIP CONSTRUCTION","Waterford","Larchville, Waterford City",5,"*N/A","","","Stage 3 approved Q2-2018, the scheme is now approved to proceed to tender.","","",""],
    [1697,1697,"SHIP CONSTRUCTION","Waterford","Patrick Street, Tramore",2,"*N/A","","","","","","Q3-2018"],
    [1698,1698,"SHIP CONSTRUCTION","Waterford","Doyle Street, Waterford City",3,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1699,1699,"SHIP CONSTRUCTION","Waterford","Old Cinema Site, Dungarvan",15,"*N/A","","","","","","Q4-2016"],
    [1700,1700,"SHIP CONSTRUCTION","Waterford","The Glen, Bridge St, Waterford",17,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1701,1701,"SHIP CONSTRUCTION","Waterford","Clarendon Court, Penrose Lane, Waterford",24,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [1702,1702,"SHIP CONSTRUCTION","Waterford","Summerland Square, Waterford",12,"*N/A","","","Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.","","",""],
    [1703,1703,"SHIP CONSTRUCTION","Waterford","Bath St, Waterford City",4,"*N/A","","","","","","Q4-2019"],
    [1704,1704,"SHIP CONSTRUCTION","Waterford","Graigueshoneen, Kilthomas, Co Waterford",24,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1705,1705,"SHIP CONSTRUCTION","Waterford","Mount Esker, Ballytruckle Road, Waterford City",13,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [1706,1706,"SHIP CONSTRUCTION","Waterford","Coolfin Woods, Portlaw",12,"*N/A","","","","","","Q2-2019"],
    [1707,1707,"SHIP CONSTRUCTION TURNKEY","Waterford","Barnes Lane, Waterford",2,"*N/A","","","","","","Q4-2019"],
    [1708,1708,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan",8,"*N/A","","","","","","Q3-2018"],
    [1709,1709,"SHIP CONSTRUCTION TURNKEY","Waterford","Gibbethill, Gracedieu",5,"*N/A","","","","","","Q3-2018"],
    [1710,1710,"SHIP CONSTRUCTION TURNKEY","Waterford","Carrickphierish, Gracedieu, Waterford",31,"*N/A","","","","","","Q4-2018"],
    [1711,1711,"SHIP CONSTRUCTION TURNKEY","Waterford","Shandon, Dungarvan",5,"*N/A","","","","","","Q3-2018"],
    [1712,1712,"SHIP CONSTRUCTION TURNKEY","Waterford","Airport Road, Waterford City",33,"*N/A","","","","","","Q4-2018"],
    [1713,1713,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan - Phase 2",10,"*N/A","","","","","","Q4-2018"],
    [1714,1714,"SHIP CONSTRUCTION TURNKEY","Waterford","Kilrush, Dungarvan - Phase 3",21,"*N/A","","","","","","Q4-2018"],
    [1715,1715,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",6,"*N/A","","","","","","Q3-2019"],
    [1716,1716,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford - Phase 3",10,"*N/A","","","","","Q4-2018",""],
    [1717,1717,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford - Phase 4",11,"*N/A","","","","Stage 4 approved Q3-2018, the scheme is fully approved.","",""],
    [1718,1718,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",8,"*N/A","","","","","","Q4-2019"],
    [1719,1719,"SHIP CONSTRUCTION TURNKEY","Waterford","Railway Gardens, Lismore",6,"*N/A","","","","","Q3-2019",""],
    [1720,1720,"SHIP CONSTRUCTION TURNKEY","Waterford","Estuary Heights, Shandon, Dungarvan",6,"*N/A","","","","","","Q4-2019"],
    [1721,1721,"SHIP CONSTRUCTION TURNKEY","Waterford","Railway Gardens, Lismore - Phase 2",6,"*N/A","","","","","Q3-2019",""],
    [1722,1722,"SHIP CONSTRUCTION TURNKEY","Waterford","Railway Gardens, Lismore - Phase 2",5,"*N/A","","","","","Q3-2019",""],
    [1723,1723,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford",20,"*N/A","","","","","","Q3-2019"],
    [1724,1724,"SHIP CONSTRUCTION TURNKEY","Waterford","Lacken Road, Waterford - Phase 2",14,"*N/A","","","","","","Q4-2019"],
    [1725,1725,"SHIP CONSTRUCTION TURNKEY","Waterford","Mount Suir, Gracedieu, Carrickphierish",18,"*N/A","","","","","","Q4-2019"],
    [1726,1726,"CALF Construction","Westmeath","Farran, Mullingar, Co. Westmeath (Phase 1)",10,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1727,1727,"CALF Turnkey","Westmeath","Athlone Road, Moate, Co. Westmeath (Phase 1)*",14,"Oaklee Housing","","","","Q4-2019","",""],
    [1728,1728,"CALF Turnkey","Westmeath","Cluain Mullen, Castlepollard, Co. Westmeath (Phase 1)",8,"T�ath Housing Association Ltd","","","","","Q2-2019",""],
    [1729,1729,"CALF Turnkey","Westmeath","Cluain Mullen, Castlepollard, Westmeath (Phase 1)",2,"T�ath Housing Association Ltd","","","","","","Q2-2017"],
    [1730,1730,"CALF Turnkey","Westmeath","Rahanine, Rochfortbridge, Co Westmeath (Phase 1)",12,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1731,1731,"CALF Turnkey","Westmeath","Rathwire, Killucan, Co. Westmeath (Phase 1)",4,"T�ath Housing Association Ltd","","","","Q4-2019","",""],
    [1732,1732,"CALF Turnkey","Westmeath","Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 1)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1733,1733,"CALF Turnkey","Westmeath","Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 2)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1734,1734,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 2)*",10,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1735,1735,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 3)*",14,"T�ath Housing Association Ltd","","","","","Q1-2019",""],
    [1736,1736,"CALF Turnkey","Westmeath","The Orchard, Athlone, Co. Westmeath (Phase 1)",8,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1737,1737,"CAS CONSTRUCTION","Westmeath","Farran, Mullingar",4,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1738,1738,"CAS CONSTRUCTION TURNKEY","Westmeath","Ardmore Road, Mullingar",14,"T�ath Housing Association Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1739,1739,"CAS CONSTRUCTION TURNKEY","Westmeath","Ardmore Road, Mullingar",22,"T�ath Housing Association Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1740,1740,"SHIP CONSTRUCTION RAPID","Westmeath","Ennell Court, Mullingar (Phase 1)",15,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1741,1741,"SHIP CONSTRUCTION","Westmeath","Bun Daire, Kinnegad (Phase 3)",12,"*N/A","","","","","Q3-2019",""],
    [1742,1742,"SHIP CONSTRUCTION","Westmeath","St. Laurence's Terrace, Mullingar",9,"*N/A","","","","","","Q4-2018"],
    [1743,1743,"SHIP CONSTRUCTION","Westmeath","Ennell Court, Mullingar",1,"*N/A","","","","","","Q1-2018"],
    [1744,1744,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone (Phase 1.1)",19,"*N/A","","","","","Q2-2018",""],
    [1745,1745,"SHIP CONSTRUCTION","Westmeath","Ennell Court (Phase 2)",3,"*N/A","","","","","","Q2-2016"],
    [1746,1746,"SHIP CONSTRUCTION","Westmeath","Grange Crescent, Mullingar",2,"*N/A","","","","","","Q1-2016"],
    [1747,1747,"SHIP CONSTRUCTION","Westmeath","Ennell Court, Mullingar (Phase 2)",31,"*N/A","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [1748,1748,"SHIP CONSTRUCTION","Westmeath","Cloghanboy, Athlone",10,"*N/A","","Stage 2 approved Q3-2018, full design/tender being prepared.","","","",""],
    [1749,1749,"SHIP CONSTRUCTION","Westmeath","Bishopsgate, Mullingar",4,"*N/A","","","","","Q3-2019",""],
    [1750,1750,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone (Phase 2)",21,"*N/A","Stage 1 approved Q3-2018, outline design and costs being prepared.","","","","",""],
    [1751,1751,"SHIP CONSTRUCTION","Westmeath","Canal Avenue, Mullingar",23,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1752,1752,"SHIP CONSTRUCTION","Westmeath","Arcadia, Athlone (Phase 1.2)",14,"*N/A","","","","","Q2-2018",""],
    [1753,1753,"SHIP CONSTRUCTION","Westmeath","Railway Terrace, Mullingar",24,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1754,1754,"SHIP CONSTRUCTION","Westmeath","Railway Terrace, Mullingar",16,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1755,1755,"SHIP CONSTRUCTION TURNKEY","Westmeath","Belvedere Hills, Mullingar",21,"*N/A","","","","","","Q4-2017"],
    [1756,1756,"SHIP CONSTRUCTION TURNKEY","Westmeath","Abbeybrook, Kilbeggan",7,"*N/A","","","","","","Q1-2019"],
    [1757,1757,"SHIP CONSTRUCTION TURNKEY","Westmeath","Cloon Lara, Mullingar",12,"*N/A","","","","","","Q2-2019"],
    [1758,1758,"SHIP CONSTRUCTION TURNKEY","Westmeath","Lakepoint, Mullingar",31,"*N/A","","","","","Q4-2019",""],
    [1759,1759,"SHIP CONSTRUCTION TURNKEY","Westmeath","Coill Rua, Mullingar",6,"*N/A","","","","","","Q4-2019"],
    [1760,1760,"SHIP CONSTRUCTION TURNKEY","Westmeath","Rathgarve Green, Castlepollard",5,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1761,1761,"SHIP CONSTRUCTION TURNKEY","Westmeath","Valley Cottages, Mullingar",3,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1762,1762,"SHIP CONSTRUCTION TURNKEY","Westmeath","Austin Friars Street, Mullingar",4,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1763,1763,"SHIP CONSTRUCTION TURNKEY","Westmeath","Rathgarve Green, Castlepollard",5,"*N/A","","","","Stage 4 approved Q4-2019, the scheme is fully approved.","",""],
    [1764,1764,"SHIP CONSTRUCTION RAPID","Westmeath","O'Growney Green, Mullingar",14,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [1765,1765,"SHIP CONSTRUCTION RAPID","Westmeath","Dalton Park, Mullingar",12,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1766,1766,"SHIP CONSTRUCTION RAPID","Westmeath","Water Street, Castlepollard",7,"*N/A","Stage 1 approved Q3-2019, outline design and costs being prepared.","","","","",""],
    [1767,1767,"CALF Turnkey","Wexford","24 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)",24,"T�ath Housing Association Ltd","","","","","Q3-2018",""],
    [1768,1768,"CALF Turnkey","Wexford","9 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)",9,"T�ath Housing Association Ltd","","","","Q3-2019","",""],
    [1769,1769,"CALF Turnkey","Wexford"," Ard Uisce, Wexford Town (Phase 1)",5,"T�ath Housing Association Ltd","","","","","","Q4-2017"],
    [1770,1770,"CALF Turnkey","Wexford"," Ard Uisce, Whiterock, Wexford  (Phase 1)",1,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1771,1771,"CALF Turnkey","Wexford","Ard Uisce, Whiterock, Wexford (Phase 1)",6,"T�ath Housing Association Ltd","","","","","","Q1-2018"],
    [1772,1772,"CALF Turnkey","Wexford","Ard Uisce, Whiterock, Wexford (Phase 1)*",6,"T�ath Housing Association Ltd","","","","","","Q1-2017"],
    [1773,1773,"CALF Turnkey","Wexford","Ballyboggan, Castlebridge, Co Wexford (Phase 1)",10,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [1774,1774,"CALF Turnkey","Wexford","Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 1)",34,"Oaklee Housing","","","","","","Q4-2018"],
    [1775,1775,"CALF Turnkey","Wexford","Fort Road, Ramsfort Park, Gorey, Co. Wexford (Phase 1)*",11,"Co-operative Housing Ireland","","","","","Q3-2018",""],
    [1776,1776,"CALF Turnkey","Wexford","Gleann an Ghairdin, Gorey (Phase 2)",9,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1777,1777,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 1)",7,"Co-operative Housing Ireland","","","","","","Q2-2016"],
    [1778,1778,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 2)",11,"Co-operative Housing Ireland","","","","","","Q3-2016"],
    [1779,1779,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 3)",11,"Co-operative Housing Ireland","","","","","","Q1-2017"],
    [1780,1780,"CALF Turnkey","Wexford","Hunters Green, Gorey (Phase 4)",9,"Co-operative Housing Ireland","","","","","","Q4-2017"],
    [1781,1781,"CALF Turnkey","Wexford","Kerlogue Manor, Drinagh, Wexford (Phase 1)",12,"T�ath Housing Association Ltd","","","","Q2-2019","",""],
    [1782,1782,"CALF Turnkey","Wexford","Kerlogue Manor, Drinagh, Wexford (Phase 2)",9,"T�ath Housing Association Ltd","","","","Q2-2019","",""],
    [1783,1783,"CALF Turnkey","Wexford","Kerlogue Manor, Drinagh, Wexford (Phase 3)",6,"T�ath Housing Association Ltd","","","","Q2-2019","",""],
    [1784,1784,"CALF Turnkey","Wexford","Kerlogue Manor, Drinagh, Wexford (Phase 4)*",22,"T�ath Housing Association Ltd","","","","Q2-2019","",""],
    [1785,1785,"CALF Turnkey","Wexford","Kerlogue Manor, Drinagh, Wexford (Phase 5)",22,"T�ath Housing Association Ltd","","","","Q2-2019","",""],
    [1786,1786,"CALF Turnkey","Wexford","Meadowfields Enniscorthy, Co. Wexford (Phase 1)",12,"Co-operative Housing Ireland","","","","","","Q3-2016"],
    [1787,1787,"CALF Turnkey","Wexford","Clonard, Wexford (Phase 1)*",10,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1788,1788,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)*",19,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1789,1789,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 2)*",22,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1790,1790,"CALF Turnkey","Wexford","Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 3)*",18,"T�ath Housing Association Ltd","","","","","Q4-2019",""],
    [1791,1791,"CALF Turnkey","Wexford","P�irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 1)*",52,"Cluid Housing","","","","Q2-2019","",""],
    [1792,1792,"CALF Turnkey","Wexford","Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 2)",6,"Oaklee Housing","","","","","","Q2-2019"],
    [1793,1793,"CALF Turnkey","Wexford","Gleann an Ghairdin, Gorey (Phase 1)",9,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1794,1794,"CALF Turnkey","Wexford","Greenville, Enniscorthy, Co. Wexford (Phase 1)*",6,"Oaklee Housing","","","","","","Q2-2019"],
    [1795,1795,"CALF Turnkey","Wexford","Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 1)*",14,"Co-operative Housing Ireland","","","","","","Q2-2019"],
    [1796,1796,"CALF Turnkey","Wexford","Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 2)*",14,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1797,1797,"CAS CONSTRUCTION","Wexford","Barrystown",16,"Grantstown Voluntary Housing Association Ltd","","Stage 2 approved Q1-2018, full design/tender being prepared.","","","",""],
    [1798,1798,"CAS CONSTRUCTION","Wexford","Rathangan",7,"Rathangan Senior Citizens Housing Association Ltd","","","","","","Q3-2017"],
    [1799,1799,"CAS CONSTRUCTION","Wexford","Wexford Women's Refuge, Maudlintown, Co Wexford",13,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [1800,1800,"SHIP CONSTRUCTION","Wexford","Coolcotts, Clonard",7,"*N/A","","","","","","Q4-2019"],
    [1801,1801,"SHIP CONSTRUCTION","Wexford","Creagh, Gorey",10,"*N/A","","","","","","Q1-2019"],
    [1802,1802,"SHIP CONSTRUCTION","Wexford","Cloghultagh, Taghmon",18,"*N/A","","","","","Q2-2019",""],
    [1803,1803,"SHIP CONSTRUCTION","Wexford","Danescastle",10,"*N/A","","","","","","Q1-2019"],
    [1804,1804,"SHIP CONSTRUCTION","Wexford","Whiterock Hill, Wexford",20,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [1805,1805,"SHIP CONSTRUCTION","Wexford","Cois Mara",2,"*N/A","","","","","","Q3-2018"],
    [1806,1806,"SHIP CONSTRUCTION","Wexford","Killeens, Wexford",40,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1807,1807,"SHIP CONSTRUCTION","Wexford","Oylegate",2,"*N/A","","","","","","Q2-2018"],
    [1808,1808,"SHIP CONSTRUCTION","Wexford","Cherryorchard, Enniscorthy",8,"*N/A","","","","","","Q3-2018"],
    [1809,1809,"SHIP CONSTRUCTION","Wexford","Ross Road, Enniscorthy",1,"*N/A","","","","","Q3-2018",""],
    [1810,1810,"SHIP CONSTRUCTION","Wexford","Baile Eoghain, Gorey",5,"*N/A","","","","","","Q4-2018"],
    [1811,1811,"SHIP CONSTRUCTION","Wexford","Baile an Tr�, Riverchapel (Courtown Ardamine)",10,"*N/A","","","","","","Q2-2016"],
    [1812,1812,"SHIP CONSTRUCTION","Wexford","Shanna Court, Coolcotts",8,"*N/A","","","","","","Q1-2016"],
    [1813,1813,"SHIP CONSTRUCTION","Wexford","Francis Street, Wexford",1,"*N/A","","","","","","Q1-2017"],
    [1814,1814,"SHIP CONSTRUCTION","Wexford","Commodore Barry",1,"*N/A","","","","","","Q2-2016"],
    [1815,1815,"SHIP CONSTRUCTION","Wexford","Glentire, The Ballagh, Enniscorthy",7,"*N/A","","","","","Q2-2019",""],
    [1816,1816,"SHIP CONSTRUCTION","Wexford","Rosetown, Rosslare, Co Wexford",36,"*N/A","Stage 1 approved Q1-2018, outline design and costs being prepared.","","","","",""],
    [1817,1817,"SHIP CONSTRUCTION","Wexford","Carley's Bridge, Enniscorthy, Co Wexford",17,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1818,1818,"SHIP CONSTRUCTION","Wexford","Creagh (East), Gorey",4,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [1819,1819,"SHIP CONSTRUCTION","Wexford","Rosbercon, New Ross",28,"*N/A","Stage 1 approved Q4-2018, outline design and costs being prepared.","","","","",""],
    [1820,1820,"SHIP CONSTRUCTION","Wexford","Baile Eoghain, Gorey (Phase 2)",4,"*N/A","","","","","","Q4-2018"],
    [1821,1821,"SHIP CONSTRUCTION","Wexford","Wexford Street, Gorey",20,"*N/A","Stage 1 approved Q1-2019, outline design and costs being prepared.","","","","",""],
    [1822,1822,"SHIP CONSTRUCTION","Wexford","Rosemary Heights, Ferns,Co. Wicklow",7,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1823,1823,"SHIP CONSTRUCTION","Wexford","Bullawn, Irishtown, New Ross",2,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1824,1824,"SHIP CONSTRUCTION","Wexford","Ballyhine, Barntown, Co. Wexford",6,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1825,1825,"SHIP CONSTRUCTION","Wexford","Whiterock Hill, Wexford (Phase 2)",24,"*N/A","","Stage 2 approved Q2-2018, full design/tender being prepared.","","","",""],
    [1826,1826,"SHIP CONSTRUCTION","Wexford","Creagh (West), Gorey",8,"*N/A","Stage 1 approved Q2-2018, outline design and costs being prepared.","","","","",""],
    [1827,1827,"SHIP CONSTRUCTION","Wexford","Slippery Green, Wexford",10,"*N/A","","","","","","Q3-2019"],
    [1828,1828,"SHIP CONSTRUCTION","Wexford","SN Castlemoyle, New Ross",1,"*N/A","","","","","","Q4-2019"],
    [1829,1829,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford - Phase 2",10,"*N/A","","","","","","Q1-2019"],
    [1830,1830,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford Phase 4",10,"*N/A","","","","","","Q3-2019"],
    [1831,1831,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford-Phase 3",4,"*N/A","","","","","","Q2-2019"],
    [1832,1832,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey (Phase 2 C)",1,"*N/A","","","","","","Q3-2019"],
    [1833,1833,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey (Phase 2a)",2,"*N/A","","","","","","Q2-2019"],
    [1834,1834,"SHIP CONSTRUCTION TURNKEY","Wexford","Madeira Oaks, Wexford",8,"*N/A","","","","","","Q3-2017"],
    [1835,1835,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey",8,"*N/A","","","","","","Q1-2018"],
    [1836,1836,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",11,"*N/A","","","","","","Q4-2018"],
    [1837,1837,"SHIP CONSTRUCTION TURNKEY","Wexford","Rath an Duin, Castlebridge",3,"*N/A","","","","","","Q3-2018"],
    [1838,1838,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey (Phase 2b)",2,"*N/A","","","","","","Q4-2019"],
    [1839,1839,"SHIP CONSTRUCTION TURNKEY","Wexford","Gleann an Ghairdin, Ballytegan Road, Gorey (Phase 1b)",10,"*N/A","","","","","","Q4-2018"],
    [1840,1840,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey",5,"*N/A","","","","","","Q4-2018"],
    [1841,1841,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey - Phase 2",2,"*N/A","","","","","","Q1-2019"],
    [1842,1842,"SHIP CONSTRUCTION TURNKEY","Wexford","Whitewater Estuary, Ballyhack, Co. Wexford",3,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [1843,1843,"SHIP CONSTRUCTION TURNKEY","Wexford","Glen Aoibhinn, Ardamine, Gorey - Phase 3",3,"*N/A","","","","","","Q4-2019"],
    [1844,1844,"SHIP CONSTRUCTION TURNKEY","Wexford","Airhill, Belvedere Rd, Wexford",3,"*N/A","","","","","Q2-2019",""],
    [1845,1845,"SHIP CONSTRUCTION TURNKEY","Wexford","Riverchapel Lane, Gorey",4,"*N/A","","","","","","Q4-2019"],
    [1846,1846,"SHIP CONSTRUCTION TURNKEY","Wexford","Airhill, Belvedere Rd, Wexford",4,"*N/A","","","","","Q2-2019",""],
    [1847,1847,"SHIP CONSTRUCTION TURNKEY","Wexford","Michael Street, New Ross ",3,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1848,1848,"SHIP CONSTRUCTION TURNKEY","Wexford","Ard Uisce, Whiterock, Wexford",19,"*N/A","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1849,1849,"SHIP CONSTRUCTION TURNKEY","Wexford","St. Martin's Road, Rosslare Harbour",4,"*N/A","","","","","","Q4-2019"],
    [1850,1850,"SHIP CONSTRUCTION RAPID","Wicklow","Merrymeeting View, Rathnew",46,"*N/A","","","","","Q2-2019",""],
    [1851,1851,"SHIP CONSTRUCTION RAPID","Wicklow","Ashtown Lane, Wicklow Town",40,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1852,1852,"SHIP CONSTRUCTION RAPID","Wicklow","Three Trouts, Greystones",40,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1853,1853,"SHIP CONSTRUCTION RAPID","Wicklow","Greenhills Road, Wicklow Town",36,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1854,1854,"SHIP CONSTRUCTION RAPID","Wicklow","Ard na Greine, West Ward, Bray",31,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1855,1855,"SHIP CONSTRUCTION RAPID","Wicklow","Coolattin Oaks (Ph4), Carnew",30,"*N/A","","","","","Q3-2019",""],
    [1856,1856,"SHIP CONSTRUCTION RAPID","Wicklow","Sli na Slainte, Whitehall, Baltinglass",27,"*N/A","","","","Stage 4 approved Q1-2019, the scheme is fully approved.","",""],
    [1857,1857,"SHIP CONSTRUCTION RAPID","Wicklow","Shillelagh Phase 4",22,"*N/A","","","Stage 3 approved Q4-2019, the scheme is now approved to proceed to tender.","","",""],
    [1858,1858,"SHIP CONSTRUCTION RAPID","Wicklow","Mountainview, NTMK",22,"*N/A","Stage 1 approved Q2-2019, outline design and costs being prepared.","","","","",""],
    [1859,1859,"SHIP CONSTRUCTION","Wicklow","Avondale Heights, Rathdrum",20,"*N/A","","","","","","Q4-2018"],
    [1860,1860,"CALF Turnkey","Wicklow","1 - 14 Wentworth Place, Wicklow Town (Phase 1)",14,"T�ath Housing Association Ltd","","","","Q4-2018","",""],
    [1861,1861,"CALF Turnkey","Wicklow","Abbey St, Wicklow  (Phase 1)",6,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1862,1862,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 2)*",8,"Cluid Housing","","","","","Q1-2018",""],
    [1863,1863,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 3)*",4,"Cluid Housing","","","","","Q1-2018",""],
    [1864,1864,"CALF Turnkey","Wicklow","Fairgreen Manor, Dunlavin, Co. Wicklow (Phase 1)*",40,"Circle Voluntary Housing Association Ltd","","","","","Q3-2018",""],
    [1865,1865,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co Wicklow  (Phase 1)*",5,"T�ath Housing Association Ltd","","","","","","Q2-2018"],
    [1866,1866,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 1)*",8,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1867,1867,"CALF Turnkey","Wicklow","Ballinahinch Woods, Ashford, Co. Wicklow (Phase 1)*",9,"Cluid Housing","","","","","","Q4-2019"],
    [1868,1868,"CALF Turnkey","Wicklow","Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 1)*",15,"Co-operative Housing Ireland","","","","","","Q4-2018"],
    [1869,1869,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)",7,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1870,1870,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)",4,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1871,1871,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 3)",6,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1872,1872,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 4)",8,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1873,1873,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 5)",5,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1874,1874,"CALF Turnkey","Wicklow","Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 6)",8,"T�ath Housing Association Ltd","","","","","Q4-2018",""],
    [1875,1875,"CALF Turnkey","Wicklow","The Meadows, Ballynerrin, Wicklow Town (Phase 1)*",7,"T�ath Housing Association Ltd","","","","","","Q4-2018"],
    [1876,1876,"CALF Turnkey","Wicklow","Viewmount, Rathdrum, County Wicklow (Phase 1)",4,"T�ath Housing Association Ltd","","","","","Q3-2019",""],
    [1877,1877,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 2)*",7,"T�ath Housing Association Ltd","","","","","","Q2-2019"],
    [1878,1878,"CALF Turnkey","Wicklow","Glenheron, Greystones, Co. Wicklow (Phase 3)*",4,"T�ath Housing Association Ltd","","","","","","Q4-2019"],
    [1879,1879,"CALF Turnkey","Wicklow","Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 2)",73,"Co-operative Housing Ireland","","","","","","Q3-2019"],
    [1880,1880,"CALF Turnkey","Wicklow","Phase 2, Hazelbrook, Rathnew, Co. Wicklow (Phase 1)",56,"Co-operative Housing Ireland","","","","","","Q4-2019"],
    [1881,1881,"CALF Turnkey","Wicklow","Ternlee, Cooldross Lane, Kilcoole, Co. Wicklow (Phase 1)*",4,"Cluid Housing","","","","","","Q2-2019"],
    [1882,1882,"CALF Turnkey","Wicklow","Ternlee, Cooldross Lane, Kilcoole, Co. Wicklow (Phase 2)*",2,"Cluid Housing","","","","","","Q4-2019"],
    [1883,1883,"CALF Turnkey","Wicklow","Woodpark, Rathdrum, Co. Wicklow (Phase 1)*",4,"T�ath Housing Association Ltd","","","","","","Q3-2019"],
    [1884,1884,"CAS CONSTRUCTION SINGLE STAGE","Wicklow","Hollybrook Park, Bray, Co. Wicklow",4,"St. John of God Housing Association Ltd","","","","Stage 4 approved Q3-2019, the scheme is fully approved.","",""],
    [1885,1885,"PUBLIC PRIVATE PARTNERSHIP (Bundle 1)","Wicklow","Convent Lands",51,"*N/A","","","","","Q1-2019",""],
    [1886,1886,"SHIP CONSTRUCTION","Wicklow","16A Oak Drive, Blessington",1,"*N/A","","","","","","Q3-2019"],
    [1887,1887,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow",17,"*N/A","","","","","","Q3-2019"],
    [1888,1888,"SHIP CONSTRUCTION","Wicklow","Druids Brook, Kilcoole",2,"*N/A","","","","","","Q3-2019"],
    [1889,1889,"SHIP CONSTRUCTION RAPID","Wicklow","Avondale Heights, Rathdrum",20,"*N/A","","Stage 2 approved Q4-2019, full design/tender being prepared.","","","",""],
    [1890,1890,"SHIP CONSTRUCTION RAPID","Wicklow","Sli na Slainte, Whitehall, Baltinglass",7,"*N/A","","","","","","Q4-2019"],
    [1891,1891,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow (Phase 3)",21,"*N/A","","","","","Q4-2019",""],
    [1892,1892,"SHIP CONSTRUCTION","Wicklow","Delaney Park, Emoclew Road, Arklow (Phase 2)",26,"*N/A","","","","","Q4-2019",""],
    [1893,1893,"SHIP CONSTRUCTION","Wicklow","FCA Hall, Wicklow Town",8,"*N/A","","","","","Q3-2018",""],
    [1894,1894,"SHIP CONSTRUCTION","Wicklow","Kilmantain Place, Bray",4,"*N/A","","","","Stage 4 approved Q2-2019, the scheme is fully approved.","",""],
    [1895,1895,"SHIP CONSTRUCTION","Wicklow","O'Byrne Road, Bray",1,"*N/A","","","","","","Q4-2018"],
    [1896,1896,"SHIP CONSTRUCTION","Wicklow","St Mary's Rd., Arklow (Old Library Site)",7,"*N/A","","","","","","Q4-2018"],
    [1897,1897,"SHIP CONSTRUCTION","Wicklow","Jameson Heights,  Kilmacanogue",20,"*N/A","","","","","Q2-2019",""],
    [1898,1898,"SHIP CONSTRUCTION","Wicklow","Kilbride Lane, Bray (Murphy's Lands)",42,"*N/A","","","","","Q1-2019",""],
    [1899,1899,"SHIP CONSTRUCTION","Wicklow","Carrig Eden,1 Marine Road, Greystones",30,"*N/A","","","","","Q4-2019",""],
    [1900,1900,"SHIP CONSTRUCTION","Wicklow","Farrankelly, Greystones (Phase 2)",24,"*N/A","","","","","Q1-2019",""],
    [1901,1901,"SHIP CONSTRUCTION","Wicklow","Sheehan Court, Back Street, Arklow",7,"*N/A","","Stage 2 approved Q3-2019, full design/tender being prepared.","","","",""],
    [1902,1902,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",10,"*N/A","","","","","","Q3-2019"],
    [1903,1903,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",14,"*N/A","","","","","","Q4-2019"],
    [1904,1904,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",10,"*N/A","","","","","","Q2-2019"],
    [1905,1905,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",15,"*N/A","","","","","","Q3-2019"],
    [1906,1906,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",2,"*N/A","","","","","","Q2-2018"],
    [1907,1907,"SHIP CONSTRUCTION TURNKEY","Wicklow","No. 7 Mill Court, Tinahely ",1,"*N/A","","","","","","Q4-2018"],
    [1908,1908,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",4,"*N/A","","","","","","Q4-2019"],
    [1909,1909,"SHIP CONSTRUCTION TURNKEY","Wicklow","Fernhill, Arklow",1,"*N/A","","","","","","Q3-2018"],
    [1910,1910,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",2,"*N/A","","","","","","Q4-2019"],
    [1911,1911,"SHIP CONSTRUCTION TURNKEY","Wicklow","Heatherside, Vale Road, Arklow",9,"*N/A","","","","","","Q4-2019"],
    [1912,1912,"SHIP CONSTRUCTION TURNKEY","Wicklow","Kirvin Hill, Broomhall, Rathnew",2,"*N/A","","","","","","Q2-2019"],
    [1913,1913,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",1,"*N/A","","","","","","Q1-2019"],
    [1914,1914,"SHIP CONSTRUCTION TURNKEY","Wicklow","Mill Court, Tinahely ",1,"*N/A","","","","","","Q2-2019"],
    [1915,1915,"SHIP CONSTRUCTION TURNKEY","Wicklow","Bollarney Woods, Wicklow Town",9,"*N/A","","","","","Q2-2018",""],
    [1916,1916,"SHIP CONSTRUCTION TURNKEY","Wicklow","Woodview Cottages, Rathnew",2,"*N/A","","","","","","Q4-2019"]
]}