﻿_id	No.	Funding Programme	LA	Scheme/Project Name	No. of Units	Approved Housing Body	Stage 1 Capital Appraisal	Stage 2 Pre Planning	Stage 3 Pre Tender design	Stage 4 Tender Report or Final Turnkey/CALF approval	On Site	Completed
1	1	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	6	*N/A	""	""	""	""	""	Q3-2019
2	2	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	6	*N/A	""	""	""	""	""	Q3-2019
3	3	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	12	*N/A	""	""	""	""	""	Q3-2020
4	4	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	10	*N/A	""	""	""	""	""	Q4-2020
5	5	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	16	*N/A	""	""	""	""	""	Q4-2021
6	6	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	13	*N/A	""	""	""	""	""	Q2-2021
7	7	SHIP CONSTRUCTION TURNKEY	Carlow	Granville Court, Granby Row,Carlow	4	*N/A	""	""	""	""	""	Q4-2021
8	8	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Father Flood Avenue, Rathvilly	8	*N/A	""	""	""	""	""	Q4-2019
9	9	SHIP CONSTRUCTION SINGLE STAGE	Carlow	St. Oliver's Crescent, Myshall	4	*N/A	""	""	""	""	""	Q4-2019
10	10	SHIP CONSTRUCTION SINGLE STAGE	Carlow	St. Mary's Court & Dereen Heights, Carlow Town	6	*N/A	""	""	""	""	""	Q4-2020
11	11	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Crowsgrove, Kildavin	1	*N/A	""	""	""	""	""	Q1-2020
12	12	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Ardattin	6	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
13	13	SHIP CONSTRUCTION SINGLE STAGE	Carlow	SRD: Brownbog, Hackettstown	1	*N/A	""	""	""	""	Q1-2020	""
14	14	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Spahill, Borris	1	*N/A	""	""	""	""	""	Q4-2020
15	15	SHIP CONSTRUCTION SINGLE STAGE	Carlow	St. Mary’s Court, Carlow	4	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
16	16	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Drumphea, Garryhill, Bagenalstown	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
17	17	SHIP CONSTRUCTION SINGLE STAGE	Carlow	SRD - Constable Hill, Hackettstown	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
18	18	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Lackabeg, Kildavin	3	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
19	19	SHIP CONSTRUCTION SINGLE STAGE	Carlow	5 & 6 Staplestown Road, Carlow	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
20	20	SHIP CONSTRUCTION RENEWAL	Carlow	Bog Lane, Borris, Co. Carlow	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
21	21	SHIP CONSTRUCTION	Carlow	The Laurels, Carlow Town	5	*N/A	""	""	""	""	""	Q2-2018
22	22	SHIP CONSTRUCTION	Carlow	Ard na Greine, Tullow	16	*N/A	""	""	""	""	""	Q4-2018
23	23	SHIP CONSTRUCTION	Carlow	Dublin Road, Tullow	21	*N/A	""	""	""	""	""	Q3-2019
24	24	SHIP CONSTRUCTION	Carlow	Bagenalstown	20	*N/A	""	""	""	""	""	Q3-2020
25	25	SHIP CONSTRUCTION	Carlow	Bilboa	2	*N/A	""	""	""	""	""	Q3-2018
26	26	SHIP CONSTRUCTION	Carlow	Slate Row, Hacketstown	4	*N/A	""	""	""	""	""	Q4-2018
27	27	SHIP CONSTRUCTION	Carlow	Mount Leinster Park, Carlow	4	*N/A	""	""	""	""	""	Q4-2017
28	28	SHIP CONSTRUCTION	Carlow	Myshall	4	*N/A	""	""	""	""	""	Q1-2018
29	29	SHIP CONSTRUCTION	Carlow	Pound Lane, Borris	4	*N/A	""	""	""	""	""	Q3-2017
30	30	SHIP CONSTRUCTION	Carlow	Rathvilly	10	*N/A	""	""	""	""	""	Q2-2017
31	31	SHIP CONSTRUCTION	Carlow	Moneybeg, Bagenalstown	24	*N/A	""	""	""	""	""	Q3-2017
32	32	SHIP CONSTRUCTION	Carlow	Paulville, Tullow (SRD)	1	*N/A	""	""	""	""	""	Q3-2017
33	33	SHIP CONSTRUCTION	Carlow	Maryborough St., Carlow	5	*N/A	""	""	""	""	""	Q1-2018
34	34	SHIP CONSTRUCTION	Carlow	Drumin, St. Mullins (SRD)	1	*N/A	""	""	""	""	""	Q1-2019
35	35	SHIP CONSTRUCTION	Carlow	Pound Lane, Borris	9	*N/A	""	""	""	""	""	Q2-2021
36	36	SHIP CONSTRUCTION	Carlow	Barrack Street, Carlow	7	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
37	37	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	22	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
38	38	CAS CONSTRUCTION TURNKEY	Carlow	Pollerton Big, Carlow	6	Tintean Housing Association Ltd	""	""	""	""	""	Q4-2020
39	39	CAS CONSTRUCTION	Carlow	Gleann na Bearu, Royal Oak Road, Bagenalstown	6	Respond	""	""	""	""	Q4-2020	""
40	40	CAS CONSTRUCTION	Carlow	Ballincarrig, Wexford Road	6	Tintean Housing Association Ltd	""	""	""	""	""	Q4-2016
41	41	CAS CONSTRUCTION	Carlow	Homefield, Blackbog Road, Carlow	3	Carlow Voluntary Housing Association	""	""	""	""	""	Q2-2021
42	42	CALF Turnkey	Carlow	7 units, Rivercourt, Carlow (Phase 1)	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2019
43	43	CALF Turnkey	Carlow	7 units, Rivercourt, Carlow (Phase 2)	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
44	44	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 1)	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
45	45	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 2)	35	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
46	46	CALF Turnkey	Carlow	Barrett Street, Bagnalstown, Co. Carlow (Phase 1)	10	Tintean Housing Association Ltd	""	""	""	""	""	Q1-2018
47	47	CALF Turnkey	Carlow	Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 1)	15	Tuath Housing Association	""	""	""	""	""	Q4-2018
48	48	CALF Turnkey	Carlow	Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 2)	12	Tuath Housing Association	""	""	""	""	""	Q2-2019
49	49	CALF Turnkey	Carlow	Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 3)	10	Tuath Housing Association	""	""	""	""	""	Q2-2019
50	50	CALF Turnkey	Carlow	Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 4)	6	Tuath Housing Association	""	""	""	""	""	Q3-2019
51	51	CALF Turnkey	Carlow	Browneshill Rise, Browneshill Road, Chapelstown, Carlow (Phase 5)	16	Tuath Housing Association	""	""	""	""	""	Q4-2019
52	52	CALF Turnkey	Carlow	Browneshill Wood, Browneshill Road, Chapelstown, Carlow (Phase 1)	14	Tuath Housing Association	""	""	""	""	""	Q4-2018
53	53	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 1)*	17	Tuath Housing Association	""	""	""	""	""	Q3-2021
54	54	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 2)*	15	Tuath Housing Association	""	""	""	""	""	Q4-2021
55	55	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 3)*	31	Tuath Housing Association	""	""	""	""	Q2-2019	""
56	56	CALF Turnkey	Carlow	Greenhills, Leighlin Road, Graiguecullen, Carlow (Phase 1)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
57	57	CALF Turnkey	Carlow	Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 1)	3	Tuath Housing Association	""	""	""	""	""	Q4-2020
58	58	CALF Turnkey	Carlow	Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
59	59	CALF Turnkey	Carlow	Rivercourt,  Carlow  (Phase 1)	28	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
60	60	CALF Turnkey	Carlow	Rivercourt,  Carlow  (Phase 2)*	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2018	""
61	61	CALF Turnkey	Carlow	Sleaty Street, Graigcullen, Carlow  (Phase 1)	26	Clúid Housing	""	""	""	""	""	Q1-2019
62	62	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
63	63	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 2)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
64	64	CALF Turnkey	Carlow	Tanner Hall, Athy Road, Carlow (Phase 1)	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
65	65	CALF Turnkey	Carlow	The Millrace, Burrin, Co. Carlow (Phase 1)*	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
66	66	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	3	*N/A	""	""	""	""	""	Q4-2019
67	67	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	4	*N/A	""	""	""	""	""	Q3-2020
68	68	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	3	*N/A	""	""	""	""	""	Q4-2020
69	69	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	4	*N/A	""	""	""	""	""	Q4-2021
70	70	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff 	4	*N/A	""	""	""	""	Q1-2021	""
71	71	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	8	*N/A	""	""	""	""	Q4-2021	""
72	72	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
73	73	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
74	74	SHIP CONSTRUCTION TURNKEY	Cavan	Lakeland Close, Swellan, Cavan Town	2	*N/A	""	""	""	""	""	Q4-2020
75	75	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell, Co. Cavan	8	*N/A	""	""	""	""	Q2-2021	""
76	76	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell, Co. Cavan	12	*N/A	""	""	""	""	Q2-2021	""
77	77	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell, Co. Cavan	11	*N/A	""	""	""	""	Q2-2021	""
78	78	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell, Co. Cavan	12	*N/A	""	""	""	""	Q2-2021	""
79	79	SHIP CONSTRUCTION TURNKEY	Cavan	Clankee Court, Lisdrumskea, Shercock	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
80	80	SHIP CONSTRUCTION TURNKEY	Cavan	Abhainn Dubh, Rosehill, Mullagh	4	*N/A	""	""	""	""	""	Q4-2021
81	81	SHIP CONSTRUCTION RENEWAL	Cavan	Derrylurgan, Ballyjamesduff	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
82	82	SHIP CONSTRUCTION	Cavan	Rosehill, Mullagh (Phase 6)	8	*N/A	""	""	""	""	""	Q1-2019
83	83	SHIP CONSTRUCTION	Cavan	Butlersbridge	4	*N/A	""	""	""	""	""	Q1-2018
84	84	SHIP CONSTRUCTION	Cavan	Woodlands, Ballyhaise	8	*N/A	""	""	""	""	""	Q4-2018
85	85	SHIP CONSTRUCTION	Cavan	Butlersbridge	2	*N/A	""	""	""	""	""	Q2-2017
86	86	SHIP CONSTRUCTION	Cavan	Clones Road, Butlersbridge	2	*N/A	""	""	""	""	""	Q3-2020
87	87	SHIP CONSTRUCTION	Cavan	Corstruce, Ballinagh	4	*N/A	""	""	""	""	""	Q2-2021
88	88	SHIP CONSTRUCTION	Cavan	Main Street, Mullagh	19	*N/A	""	""	""	""	Q4-2020	""
89	89	SHIP CONSTRUCTION	Cavan	Elm Grove, Main St, Cavan Town	13	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
90	90	SHIP CONSTRUCTION	Cavan	Cavan Road, Ballinagh	15	*N/A	""	""	""	""	Q2-2021	""
91	91	SHIP CONSTRUCTION	Cavan	Main St., Butlersbridge	6	*N/A	""	""	""	""	Q2-2021	""
92	92	SHIP CONSTRUCTION	Cavan	Cluain Dara, Kingscourt	3	*N/A	""	""	""	""	""	Q4-2021
93	93	SHIP CONSTRUCTION	Cavan	Fairymount Close, Kingscourt, Co. Cavan	3	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
94	94	SHIP CONSTRUCTION	Cavan	St. Bridgets Terrace, Cavan Town (Infill)	20	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
95	95	SHIP CONSTRUCTION	Cavan	Lime Park, Bailieborough	12	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
96	96	SHIP CONSTRUCTION	Cavan	Duckin Stool, Main Street, Belturbet	3	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
97	97	SHIP CONSTRUCTION	Cavan	The Widow's Row, Widow's House Lane, Belturbet	8	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
98	98	SHIP CONSTRUCTION	Cavan	8 Units @ Ashgrove, Derrylurgan, Ballyjamesduff	8	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
99	99	SHIP CONSTRUCTION	Cavan	Lime Park, Bailieborough	18	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
100	100	SHIP CONSTRUCTION	Cavan	Lime Park, Bailieborough	15	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
101	101	CAS CONSTRUCTION TURNKEY	Cavan	Castlemanor Village, Cavan Town	29	Túath Housing Association Ltd	""	""	""	""	""	Q3-2019
102	102	CAS CONSTRUCTION	Cavan	St. Killian's Housing Association Ltd., Mullagh, Co. Cavan	4	St. Killian's Housing Association, Mullagh, Co. Cavan	""	""	""	""	Q1-2021	""
103	103	CALF Turnkey	Cavan	16 Units, Fairgreen Park, Mullagh, Co. Cavan (Phase 1)	16	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2021
104	104	CALF Turnkey	Cavan	Cluain Dara, Kingscourt, Co Cavan (Phase 1)	16	Clúid Housing	""	""	""	""	""	Q4-2016
105	105	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Cavan (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q2-2018
106	106	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Cavan (Phase 2)	5	Tuath Housing Association	""	""	""	""	""	Q3-2018
107	107	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Cavan (Phase 3)	2	Tuath Housing Association	""	""	""	""	""	Q4-2018
108	108	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 1)	12	Tuath Housing Association	""	""	""	""	Q2-2021	""
109	109	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 2)	13	Tuath Housing Association	""	""	""	""	Q2-2021	""
110	110	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 1)	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2019
111	111	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 1)	5	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
112	112	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 2)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
113	113	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 3)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
114	114	CALF Turnkey	Cavan	The Gallops, Cavan Town, Co. Cavan (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q4-2020
115	115	CALF Turnkey	Cavan	The Gallops, Cavan Town, Co. Cavan (Phase 2)*	22	Clúid Housing	""	""	""	""	Q4-2019	""
116	116	SHIP CONSTRUCTION TURNKEY	Clare	River View, School Road, Corofin	2	*N/A	""	""	""	""	""	Q4-2018
117	117	SHIP CONSTRUCTION TURNKEY	Clare	Cloughleigh Road + Shallee Drive, Ennis	4	*N/A	""	""	""	""	""	Q4-2020
118	118	SHIP CONSTRUCTION TURNKEY	Clare	Shantraud Woods, Killaloe	4	*N/A	""	""	""	""	Q3-2020	""
119	119	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	45	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
120	120	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	16	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
121	121	SHIP CONSTRUCTION SINGLE STAGE	Clare	Cappagh Lodge, Sixmilebridge	2	*N/A	""	""	""	""	""	Q4-2020
122	122	SHIP CONSTRUCTION SINGLE STAGE	Clare	St. Michaels Place, Kilmihil	2	*N/A	""	""	""	""	""	Q4-2020
123	123	SHIP CONSTRUCTION SINGLE STAGE	Clare	Madden's Terrace, Clarecastle	2	*N/A	""	""	""	""	Q2-2021	""
124	124	SHIP CONSTRUCTION SINGLE STAGE	Clare	Dun na Mara, Doonbeg	2	*N/A	""	""	""	""	""	Q2-2021
125	125	SHIP CONSTRUCTION SINGLE STAGE	Clare	St Senan’s Terrace, Kilrush -No5-No 6	2	*N/A	""	""	""	""	""	Q3-2021
126	126	SHIP CONSTRUCTION	Clare	Roslevan, Ennis	8	*N/A	""	""	""	""	""	Q2-2020
127	127	SHIP CONSTRUCTION	Clare	Feakle	13	*N/A	""	""	""	""	""	Q4-2019
128	128	SHIP CONSTRUCTION	Clare	Glor Srutha, Knockbrack Lower, Clonlara	9	*N/A	""	""	""	""	""	Q4-2019
129	129	SHIP CONSTRUCTION	Clare	Seaview Park, Quilty	18	*N/A	""	""	""	""	""	Q4-2020
130	130	SHIP CONSTRUCTION	Clare	Ashline, Kilrush Road, Ennis	40	*N/A	""	""	""	""	Q3-2020	""
131	131	SHIP CONSTRUCTION	Clare	Ballard Rd,Miltown Malbay	27	*N/A	""	""	""	""	Q3-2020	""
132	132	SHIP CONSTRUCTION	Clare	Doonaun, Tulla	25	*N/A	""	""	""	""	Q4-2020	""
133	133	SHIP CONSTRUCTION	Clare	Boheraroan, Newmarket-on-Fergus	18	*N/A	""	""	""	""	Q4-2020	""
134	134	SHIP CONSTRUCTION	Clare	Feakle Rd., Scariff	18	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
135	135	SHIP CONSTRUCTION	Clare	Kilkee Road, Doonbeg	8	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
136	136	SHIP CONSTRUCTION	Clare	Tulla Road, Roslevan, Ennis	8	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
137	137	SHIP CONSTRUCTION	Clare	7, 8, 17 St Senan's Terrace, Kilrush 	3	*N/A	""	""	""	""	""	Q4-2019
138	138	SHIP CONSTRUCTION	Clare	Drumcliffe Road, Ennis	26	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
139	139	SHIP CONSTRUCTION	Clare	Deerpark, Ennistymon	30	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.	""	""	""	""	""
140	140	SHIP CONSTRUCTION	Clare	Ballyliddan West, Sixmilebridge	15	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
141	141	CAS CONSTRUCTION TURNKEY	Clare	Haggard View, Clarecastle	2	Anvers Housing Association Ltd	""	""	""	""	""	Q2-2018
142	142	CAS CONSTRUCTION TURNKEY	Clare	Haggard View, Clarecastle	2	Anvers Housing Association Ltd	""	""	""	""	""	Q1-2018
143	143	CAS CONSTRUCTION	Clare	Cahercalla, Ennis (Phase 2)	15	Cuan an Chlair Ltd	""	""	""	""	""	Q4-2020
144	144	CAS CONSTRUCTION	Clare	Laurel Lodge, Clare Road, Ennis	3	Society of Saint Vincent de Paul	""	""	""	""	""	Q4-2016
145	145	CAS CONSTRUCTION	Clare	Monaskeha Heights	4	Newgrove Housing Association Ltd	""	""	""	""	""	Q3-2019
146	146	CAS CONSTRUCTION	Clare	Roo East	4	Thomond Housing Association Ltd	""	""	""	""	""	Q4-2018
147	147	CAS CONSTRUCTION	Clare	9 Elmwood, Ballycannon Heights, Meelick	4	Thomond Housing Association Ltd	""	""	""	""	""	Q1-2019
148	148	CAS CONSTRUCTION	Clare	Teach Rua, Edenvale Ennis	4	Newgrove Housing Association Ltd	""	""	""	""	""	Q2-2021
149	149	CALF Turnkey	Clare	Abbey View, Limerick Road, Ennis, Co. Clare (Phase 1)	9	Clúid Housing	""	""	""	""	Q4-2021	""
150	150	CALF Turnkey	Clare	Abbey View, Limerick Road, Ennis, Co. Clare (Phase 2)*	15	Clúid Housing	""	""	""	""	Q4-2021	""
151	151	CALF Turnkey	Clare	Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q2-2018
152	152	CALF Turnkey	Clare	Acha Bhile, Loughville, Lahinch Road, Ennis, Co Clare  (Phase 2)	18	Clúid Housing	""	""	""	""	""	Q4-2018
153	153	CALF Turnkey	Clare	Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 1)*	2	Clúid Housing	""	""	""	""	""	Q3-2020
154	154	CALF Turnkey	Clare	Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 2)*	2	Clúid Housing	""	""	""	""	Q2-2019	""
155	155	CALF Turnkey	Clare	Cluain Fia, Crusheen, Co. Clare (Phase 1)*	2	Clúid Housing	""	""	""	""	""	Q2-2020
156	156	CALF Turnkey	Clare	Cluain Fia, Crusheen, Co. Clare (Phase 2)*	2	Clúid Housing	""	""	""	""	""	Q4-2020
157	157	CALF Turnkey	Clare	Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 1)	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
158	158	CALF Turnkey	Clare	Cluain Ros Leamhan, Roslevan, Tulla Road, Ennis, Co. Clare (Phase 2)	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2019
159	159	CALF Turnkey	Clare	Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 1)*	29	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
160	160	CALF Turnkey	Clare	Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 2)*	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
161	161	CALF Turnkey	Clare	Limerick Rd, Ennis, Co. Clare (Phase 1)*	18	Inis Housing Association	""	""	""	""	Q1-2022	""
162	162	CALF Turnkey	Clare	Lios Anama, Sixmilebridge, Clare (Phase 1)	28	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2017
163	163	CALF Construction	Clare	Revised - Bruachlan, Westbury, Co Clare (Phase 1)	22	Co - Operative Housing Ireland Society Limited	""	""	""	Q2-2021	""	""
164	164	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 1)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
165	165	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 2)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
166	166	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 3)*	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
167	167	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 4)*	21	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
168	168	CALF Turnkey	Clare	Sycamore Drive, Ennis, Co. Clare (Phase 1)*	3	Clúid Housing	""	""	""	""	""	Q4-2019
169	169	CALF Turnkey	Clare	Sycamore Drive, Ennis, Co. Clare (Phase 2)*	2	Clúid Housing	""	""	""	""	""	Q4-2020
170	170	CALF Turnkey	Clare	Tullyvarraga, Shannon, Co. Clare (Phase 1)*	31	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
171	171	CALF Turnkey	Clare	Tullyvarraga, Shannon, Co. Clare (Phase 2)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
172	172	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 1)	20	*N/A	""	""	""	""	""	Q2-2021
173	173	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 2)	31	*N/A	""	""	""	""	""	Q3-2021
174	174	SHIP DIALOG	Cork City	Arus Mhuire	30	*N/A	""	""	""	""	""	Q4-2018
175	175	SHIP DIALOG	Cork City	Barrack Street	32	*N/A	""	""	""	""	Q1-2019	""
176	176	SHIP DIALOG	Cork City	FaranFerris	5	*N/A	""	""	""	""	""	Q4-2019
177	177	SHIP DIALOG	Cork City	High Street	9	*N/A	""	""	""	""	""	Q4-2019
178	178	SHIP DIALOG	Cork City	Tramore Road	4	*N/A	""	""	""	""	""	Q4-2018
179	179	SHIP DIALOG	Cork City	Whites Street	43	*N/A	""	""	""	""	""	Q4-2019
180	180	SHIP DIALOG	Cork City	Woods Street	16	*N/A	""	""	""	""	Q1-2019	""
181	181	SHIP DIALOG	Cork City	Church Road, Blackrock	43	*N/A	""	""	""	""	""	Q3-2018
182	182	SHIP DIALOG	Cork City	1-5, Ard Aoibhinn, Banduff, Mayfield	5	*N/A	""	""	""	""	""	Q3-2018
183	183	SHIP DIALOG	Cork City	Corcorans Quay	3	*N/A	""	""	""	""	Q2-2018	""
184	184	SHIP DIALOG	Cork City	Blarney Street	25	*N/A	""	""	""	""	""	Q4-2019
185	185	SHIP DIALOG	Cork City	Ballinure Road, Cork City	5	*N/A	""	""	""	""	""	Q4-2020
186	186	SHIP DIALOG	Cork City	Moss Lane, Riverway, Cork	5	*N/A	""	""	""	""	Q1-2019	""
187	187	SHIP DIALOG	Cork City	Gerald Griffin Street, Cork	13	*N/A	""	""	""	""	""	Q4-2020
188	188	SHIP DIALOG	Cork City	Lower John Street, Cork	17	*N/A	""	""	""	""	""	Q4-2020
189	189	SHIP DIALOG	Cork City	Skehard Road, Blackrock, Cork	16	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
190	190	SHIP DIALOG	Cork City	Coach Street, Cork	13	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
191	191	SHIP DIALOG	Cork City	Shanakiel Road, Cork	20	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
192	192	SHIP DIALOG	Cork City	Spring Lane, Blackpool, Cork	8	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
193	193	SHIP DIALOG	Cork City	Glen Ryan Road, Cork	9	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
194	194	SHIP DIALOG	Cork City	Pouladuff Road, Cork 	11	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
195	195	SHIP DIALOG	Cork City	Watercourse Road, Blackpool, Cork	37	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
196	196	SHIP DIALOG	Cork City	Denroche's Cross, Glasheen Road, Cork	43	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
197	197	SHIP DIALOG	Cork City	Wolsey Court, Blackpool, Cork	49	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
198	198	SHIP DIALOG	Cork City	Sunview, South Douglas Road, Douglas, Cork	25	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
199	199	SHIP DIALOG	Cork City	Former Bolands Mill, Old Mallow Road	57	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
200	200	SHIP CONSTRUCTION TURNKEY	Cork City	1-4 Marble Lane	4	*N/A	""	""	""	""	""	Q4-2017
201	201	SHIP CONSTRUCTION TURNKEY	Cork City	Sheridan Park, Tramore Road	28	*N/A	""	""	""	""	""	Q4-2016
202	202	SHIP CONSTRUCTION TURNKEY	Cork City	37-39 Dublin Street, Blackpool, Cork	5	*N/A	""	""	""	""	""	Q2-2018
203	203	SHIP CONSTRUCTION TURNKEY	Cork City	6-10, Ard Aoibhinn, Banduff, Mayfield	5	*N/A	""	""	""	""	""	Q4-2018
204	204	SHIP CONSTRUCTION TURNKEY	Cork City	2 Deanrock Cottages, Togher	4	*N/A	""	""	""	""	""	Q4-2018
205	205	SHIP CONSTRUCTION TURNKEY	Cork City	258 & 259 Blarney Street, Cork	2	*N/A	""	""	""	""	""	Q1-2018
206	206	SHIP CONSTRUCTION TURNKEY	Cork City	1 & 2 The Groves, Skehard Road, Cork	2	*N/A	""	""	""	""	""	Q2-2018
207	207	SHIP CONSTRUCTION TURNKEY	Cork City	3B & 9B South Terrace Court, South Terrace, Cork	2	*N/A	""	""	""	""	""	Q4-2018
208	208	SHIP CONSTRUCTION TURNKEY	Cork City	Ballinlough Road / Knockrea Lawn, Ballinlough, Cork	6	*N/A	""	""	""	""	""	Q2-2019
209	209	SHIP CONSTRUCTION TURNKEY	Cork City	Ard na Ri, Banduff Road, Cork	10	*N/A	""	""	""	""	""	Q4-2019
210	210	SHIP CONSTRUCTION TURNKEY	Cork City	Gearney's Boreen, Commons Road, Cork	3	*N/A	""	""	""	""	""	Q4-2019
211	211	SHIP CONSTRUCTION TURNKEY	Cork City	Ard na Ri, Banduff Road, Cork	10	*N/A	""	""	""	""	""	Q4-2019
212	212	SHIP CONSTRUCTION TURNKEY	Cork City	Eagle Valley, Sarsfield Road	1	*N/A	""	""	""	""	""	Q4-2019
213	213	SHIP CONSTRUCTION TURNKEY	Cork City	Knockfree Avenue, Glengarriff Road, Fairhill, Cork	2	*N/A	""	""	""	""	""	Q4-2019
214	214	SHIP CONSTRUCTION TURNKEY	Cork City	3-10 Herbert Lawn, Belmont, Rochestown, Cork	8	*N/A	""	""	""	""	""	Q4-2019
215	215	SHIP CONSTRUCTION TURNKEY	Cork City	Elton Wood & Herbert Lawn, Rochestown, Cork 	8	*N/A	""	""	""	""	""	Q4-2019
216	216	SHIP CONSTRUCTION TURNKEY	Cork City	Aspen Drive, Maryborough Hill, Cork 	29	*N/A	""	""	""	""	""	Q4-2019
217	217	SHIP CONSTRUCTION TURNKEY	Cork City	5 Fairfield Heights, Upper Fairhill, Cork 	3	*N/A	""	""	""	""	""	Q4-2020
218	218	SHIP CONSTRUCTION TURNKEY	Cork City	Ringcroft Avenue, Ringmahon Road, Mahon	2	*N/A	""	""	""	""	""	Q4-2020
219	219	SHIP CONSTRUCTION TURNKEY	Cork City	Cluain Ard, Waterloo Road, Blarney, Cork	3	*N/A	""	""	""	""	""	Q4-2020
220	220	SHIP CONSTRUCTION RAPID VOLUMETRIC	Cork City	Clover Hill Court, Bessboro Road, Mahon, Cork	51	*N/A	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
221	221	SHIP CONSTRUCTION	Cork City	Poulavone, Ballincollig	64	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
222	222	SHIP CONSTRUCTION	Cork City	The Meadows, Knocknacullen	1	*N/A	""	""	""	""	""	Q3-2016
223	223	SHIP CONSTRUCTION	Cork City	Boyces Street	14	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
224	224	SHIP CONSTRUCTION	Cork City	Shandon Street/John Philpott Curran Street	9	*N/A	""	""	""	""	""	Q4-2020
225	225	SHIP CONSTRUCTION	Cork City	St. Johns Well	6	*N/A	""	""	""	""	""	Q4-2019
226	226	SHIP CONSTRUCTION	Cork City	Churchfield Place East	3	*N/A	""	""	""	""	""	Q4-2018
227	227	SHIP CONSTRUCTION	Cork City	Deanrock, Togher	8	*N/A	""	""	""	""	""	Q4-2018
228	228	SHIP CONSTRUCTION	Cork City	Cappanoole	2	*N/A	""	""	""	""	""	Q4-2016
229	229	SHIP CONSTRUCTION	Cork City	Madonna House, Ballincollig	6	*N/A	""	Stage 2 approved Q4-2019, full design/tender being prepared.	""	""	""	""
230	230	SHIP CONSTRUCTION	Cork City	Bramble Cottages	4	*N/A	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
231	231	SHIP CONSTRUCTION	Cork City	Errigal Heights, The Glen, Cork City	28	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
232	232	SHIP CONSTRUCTION	Cork City	Glenamoy Lawn, Mayfield, Cork	3	*N/A	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
233	233	SHIP CONSTRUCTION	Cork City	Deanrock, Togher	7	*N/A	""	""	""	""	""	Q1-2019
234	234	SHIP CONSTRUCTION	Cork City	Hollywood Estate Infill Housing, Blarney Road, Cork	7	*N/A	""	Stage 2 approved Q4-2019, full design/tender being prepared.	""	""	""	""
235	235	SHIP CONSTRUCTION	Cork City	Deanrock, Togher	50	*N/A	""	""	""	""	""	Q3-2019
236	236	SHIP CONSTRUCTION	Cork City	Westside, Model Farm Road, Cork	41	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
237	237	SHIP CONSTRUCTION	Cork City	Gerald Griffin Apartments - Block 7, North Monastery Road / St. Vincent's Road, Cork	6	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
238	238	SHIP CONSTRUCTION	Cork City	16A Kerry Road (former Slí Gartan), Mayfield, Cork 	1	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
239	239	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 1B	29	*N/A	""	""	""	""	""	Q4-2017
240	240	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 2A	47	*N/A	""	""	""	""	""	Q4-2019
241	241	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 1C	41	*N/A	""	""	Stage 3 approved Q2-2020, the scheme is now approved to proceed to tender.	""	""	""
242	242	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 2B	38	*N/A	""	""	Stage 3 approved Q2-2020, the scheme is now approved to proceed to tender.	""	""	""
243	243	REGENERATION	Cork City	CNWQR Knocknaheeney Phase 2C	24	*N/A	""	""	""	""	""	Q4-2020
244	244	REGENERATION	Cork City	Foyle Avenue Infill Housing Development, Knocknaheeny, Cork	2	*N/A	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
245	245	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 3B	62	*N/A	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
246	246	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 4A	43	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
247	247	CAS CONSTRUCTION	Cork City	Edel House, Grattan Street	37	Good Shepherd Services Ltd	""	""	""	""	""	Q4-2020
248	248	CAS CONSTRUCTION	Cork City	Saint Vincent's Convent, Vincent's Ave/St. Mary's Street	25	Respond	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
249	249	CAS CONSTRUCTION	Cork City	Ceanncora Lawn, Ballinlough	1	Cork Mental Health Voluntary Housing Association Ltd	""	""	""	""	""	Q3-2018
250	250	CAS CONSTRUCTION	Cork City	St. Joachim & Anne's, Anglesea Street	8	Simon Community : Cork Simon	""	""	""	""	""	Q4-2020
251	251	CAS CONSTRUCTION	Cork City	27-29 Dublin Street, Blackpool	10	Respond	""	""	""	""	""	Q3-2018
252	252	CAS CONSTRUCTION	Cork City	Ard na Ri, Closes Green, Farranree, Cork	20	Farranree Sheltered Housing Association	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
253	253	CAS CONSTRUCTION	Cork City	Apts 2 & 3 Cois Coille, Tivoli, Cork	2	Galtan Ltd	""	""	""	""	""	Q4-2021
254	254	CAS CONSTRUCTION	Cork City	Eastville, Albert Road, Cork	1	Galtan Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
255	255	CAS CONSTRUCTION	Cork City	Aras Lean, Murphy’s Farm, Bishopstown, Co. Cork	25	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
256	256	CALF Turnkey	Cork City	12,14,15 Model Quarters, Tower, Blarney, Co Cork  (Phase 1)	3	Circle Voluntary Housing Association Ltd	""	""	""	""	Q2-2019	""
257	257	CALF Turnkey	Cork City	20 and 21 Kyle Street  (Phase 1)	6	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
258	258	CALF Turnkey	Cork City	40-41 Grand Parade, Cork City (Phase 1)	7	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
259	259	CALF Turnkey	Cork City	5 units, Shandon Street, Cork (Phase 1)	5	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q3-2019
260	260	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 1)*	2	Tuath Housing Association	""	""	""	""	Q1-2020	""
261	261	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 2)*	2	Tuath Housing Association	""	""	""	""	Q1-2020	""
262	262	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 3)*	2	Tuath Housing Association	""	""	""	""	Q1-2020	""
263	263	CALF Turnkey	Cork City	Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 1)*	37	Tuath Housing Association	""	""	""	""	""	Q4-2019
264	264	CALF Turnkey	Cork City	Bishops Avenue, Farrenferris, Fairhill, Cork (Phase 2)*	49	Tuath Housing Association	""	""	""	""	""	Q4-2020
265	265	CALF Turnkey	Cork City	Block 10 Jacobs Island, Mahon, Cork (Phase 1)	59	Respond	""	""	""	Q1-2022	""	""
266	266	CALF Turnkey	Cork City	Boherboy Road, Silversprings Hill, Cork City  (Phase 1)*	15	Respond	""	""	""	Q4-2021	""	""
267	267	CALF Turnkey	Cork City	Brocklesby Street, Blackpool, Cork City (Phase 1)*	42	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
268	268	CALF Turnkey	Cork City	Convent Gardens, Blackrock Villas, Blackrock, Co. Cork (Phase 1)	1	Tuath Housing Association	""	""	""	""	""	Q4-2019
269	269	CALF Turnkey	Cork City	Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q4-2020
270	270	CALF Turnkey	Cork City	Crawford Gate, Bessboro, Blackrock, Co. Cork (Phase 2)	2	Tuath Housing Association	""	""	""	""	""	Q4-2020
271	271	CALF Turnkey	Cork City	Croppy Boy, Fairhill, Cork (Phase 1)	7	Tuath Housing Association	""	""	""	""	""	Q3-2020
272	272	CALF Turnkey	Cork City	Croppy Boy, Fairhill, Cork (Phase 2)*	14	Tuath Housing Association	""	""	""	""	""	Q4-2020
273	273	CALF Turnkey	Cork City	Emerald View, Old Mallow Road, Cork City (Phase 1)	6	Focus Housing Association CLG	""	""	""	""	""	Q4-2021
274	274	CALF Turnkey	Cork City	Evergreen Road, Turners Cross, Cork  (Phase 1)*	28	Respond	""	""	""	""	Q1-2021	""
275	275	CALF Turnkey	Cork City	Fairfield Meadows, Upper Fair Hill, Cork (Phase 1)*	18	Focus Housing Association CLG	""	""	""	Q3-2021	""	""
276	276	CALF Turnkey	Cork City	Glanmire Village, Glanmire, Cork (Phase 1)	3	Focus Housing Association CLG	""	""	""	""	Q2-2020	""
277	277	CALF Construction	Cork City	Green Lane, Blackpool, Cork City (Phase 1)	112	Clúid Housing	""	""	""	""	Q4-2021	""
278	278	CALF Turnkey	Cork City	Haig Gardens, Boreenamanna Road and Wallace Avenue, Ballintemple (Phase 1)*	27	Respond	""	""	""	""	Q2-2021	""
279	279	CALF Turnkey	Cork City	Hereford Place, Ballymacthomas Street, Cork City (Phase 1)*	19	Respond	""	""	""	""	Q1-2020	""
280	280	CALF Turnkey	Cork City	Inniscarra Road, Coolroe, Ballincollig, Cork (Phase 1)	21	Tuath Housing Association	""	""	""	Q4-2021	""	""
281	281	CALF Turnkey	Cork City	Lancaster Gate, Western Road, Cork (Phase 1)	15	Clúid Housing	""	""	""	""	Q3-2021	""
282	282	CALF Turnkey	Cork City	Leeside Apartments, Bachelors Quay, Cork City (Phase 1)	72	Clúid Housing	""	""	""	""	""	Q4-2018
283	283	CALF Turnkey	Cork City	Leeside Apartments, Bachelors Quay, Cork City (Phase 2)	6	Clúid Housing	""	""	""	""	""	Q3-2019
284	284	CALF Turnkey	Cork City	Link Road, Ballincollig, Cork (Phase 1)*	40	Respond	""	""	""	""	Q3-2021	""
285	285	CALF Construction	Cork City	Lower Glanmire Road, Cork City (Phase 1)	8	Galtan Ltd	""	""	""	""	""	Q4-2019
286	286	CALF Construction	Cork City	Lr. Glanmire Road & 2 Braemer, Cork (Phase 1)	3	Galtan Ltd	""	""	""	""	""	Q1-2018
287	287	CALF Construction	Cork City	Lr. Glanmire Road & 2 Braemer, Cork (Phase 2)	3	Galtan Ltd	""	""	""	""	""	Q4-2018
288	288	CALF Turnkey	Cork City	"Maryborough Ridge & Blackrock  Villas
 (Phase 1)*"	57	Tuath Housing Association	""	""	""	""	""	Q4-2019
289	289	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 1)	14	Tuath Housing Association	""	""	""	""	Q3-2021	""
290	290	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 2)	14	Tuath Housing Association	""	""	""	""	Q3-2021	""
291	291	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 3)	14	Tuath Housing Association	""	""	""	""	Q3-2021	""
292	292	CALF Turnkey	Cork City	Millerd Street, Cork (Phase 1)	25	Respond	""	""	""	""	""	Q4-2020
293	293	CALF Turnkey	Cork City	Millfield Cottages, Blackpool, Cork City (Phase 1)*	18	Respond	""	""	""	Q1-2022	""	""
294	294	CALF Turnkey	Cork City	North Abbey Street, Cork City  (Phase 1)	6	Respond	""	""	""	""	""	Q4-2018
295	295	CALF Turnkey	Cork City	Phase 2, 42 Grand Parade, Cork City (Phase 1)	9	Focus Housing Association CLG	""	""	""	""	Q4-2021	""
296	296	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 1)	18	Respond	""	""	""	""	""	Q4-2020
297	297	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 2)	31	Respond	""	""	""	""	""	Q4-2021
298	298	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 3)*	24	Respond	""	""	""	""	Q1-2020	""
299	299	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 4)	7	Respond	""	""	""	""	Q1-2020	""
300	300	CALF Turnkey	Cork City	Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 1)	31	Tuath Housing Association	""	""	""	""	""	Q4-2018
301	301	CALF Turnkey	Cork City	Revised-The Meadows, Knocknacullen East, Gurranabraher, Cork  (Phase 2)	21	Tuath Housing Association	""	""	""	""	""	Q4-2019
302	302	CALF Turnkey	Cork City	Riverside Farm, Model Farm Road, Bishopstown, Cork (Phase 1)*	48	Respond	""	""	""	Q4-2021	""	""
303	303	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 1)*	22	Respond	""	""	""	""	Q4-2020	""
304	304	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 2)*	19	Respond	""	""	""	""	Q4-2020	""
305	305	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 3)	24	Respond	""	""	""	""	Q4-2020	""
306	306	CALF Turnkey	Cork City	Springville House, Bulls Lane, Blackrock Road, Cork (Phase 1)	35	Tuath Housing Association	""	""	""	""	Q4-2020	""
307	307	CALF Construction	Cork City	St Dominics, Middle Glanmire Road, Montenotte, Cork (Phase 1)	27	Tuath Housing Association	""	""	""	""	Q1-2021	""
308	308	CALF Turnkey	Cork City	The Meadows (Phase 2) Gurranabraher, Cork City  (Phase 1)	17	Tuath Housing Association	""	""	""	""	""	Q4-2019
309	309	CALF Turnkey	Cork City	The Oaks, Frankfield, Douglas, Cork City (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2021
310	310	CALF Turnkey	Cork City	 Tower Street, Cork City (Phase 1)	2	Threshold Ltd	""	""	""	Q2-2021	""	""
311	311	CALF Turnkey	Cork City	Woodside, Kerry Pike, Cork (Phase 1)*	22	Clúid Housing	""	""	""	""	""	Q4-2020
312	312	SHIP CONSTRUCTION TURNKEY	Cork County	Church Road/Station Road, Carrigtwohill	18	*N/A	""	""	""	""	""	Q2-2018
313	313	SHIP CONSTRUCTION TURNKEY	Cork County	Inis Alainn & Castleoaks, Bandon	11	*N/A	""	""	""	""	""	Q4-2017
314	314	SHIP CONSTRUCTION TURNKEY	Cork County	Gleann Tuairigh, Youghal	3	*N/A	""	""	""	""	""	Q4-2018
315	315	SHIP CONSTRUCTION TURNKEY	Cork County	Millview Road, Kanturk	11	*N/A	""	""	""	""	""	Q4-2019
316	316	SHIP CONSTRUCTION TURNKEY	Cork County	Clondulane, Fermoy	2	*N/A	""	""	""	""	""	Q4-2017
317	317	SHIP CONSTRUCTION TURNKEY	Cork County	College Wood, Cobh	31	*N/A	""	""	""	""	""	Q4-2017
318	318	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas	12	*N/A	""	""	""	""	""	Q4-2017
319	319	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	4	*N/A	""	""	""	""	""	Q4-2019
320	320	SHIP CONSTRUCTION TURNKEY	Cork County	CulAird Carraigtwohill	29	*N/A	""	""	""	""	""	Q4-2017
321	321	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas	12	*N/A	""	""	""	""	""	Q1-2017
322	322	SHIP CONSTRUCTION TURNKEY	Cork County	Castletreasure, Douglas	16	*N/A	""	""	""	""	""	Q1-2017
323	323	SHIP CONSTRUCTION TURNKEY	Cork County	Claragh Road, Millstreet	5	*N/A	""	""	""	""	""	Q2-2021
324	324	SHIP CONSTRUCTION TURNKEY	Cork County	St. Mary’s Road, Dunmanway	7	*N/A	""	""	""	""	""	Q3-2020
325	325	SHIP CONSTRUCTION TURNKEY	Cork County	Glanworth, Fermoy	13	*N/A	""	""	""	""	Q1-2020	""
326	326	SHIP CONSTRUCTION TURNKEY	Cork County	Quartertown, Mallow	5	*N/A	""	""	""	""	""	Q4-2019
327	327	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	8	*N/A	""	""	""	""	""	Q4-2019
328	328	SHIP CONSTRUCTION TURNKEY	Cork County	Beacon Point, Baltimore	6	*N/A	""	""	""	""	""	Q2-2019
329	329	SHIP CONSTRUCTION TURNKEY	Cork County	Corrin View, Fermoy	6	*N/A	""	""	""	""	""	Q2-2019
330	330	SHIP CONSTRUCTION TURNKEY	Cork County	No. 43 & No. 50 Chapel Court, Skibbereen 	2	*N/A	""	""	""	""	""	Q3-2018
331	331	SHIP CONSTRUCTION TURNKEY	Cork County	Cul Na Smear, Bandon	14	*N/A	""	""	""	""	""	Q4-2018
332	332	SHIP CONSTRUCTION TURNKEY	Cork County	Glen Dara, Ard Cashel, Watergrasshill	6	*N/A	""	""	""	""	""	Q4-2018
333	333	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	9	*N/A	""	""	""	""	""	Q2-2019
334	334	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	15	*N/A	""	""	""	""	""	Q4-2020
335	335	SHIP CONSTRUCTION TURNKEY	Cork County	Lismire	4	*N/A	""	""	""	""	""	Q4-2018
336	336	SHIP CONSTRUCTION TURNKEY	Cork County	Rylane, Mount Rivers	3	*N/A	""	""	""	""	""	Q4-2020
337	337	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	17	*N/A	""	""	""	""	""	Q4-2020
338	338	SHIP CONSTRUCTION TURNKEY	Cork County	Seafield, Bantry, 	3	*N/A	""	""	""	""	Q3-2018	""
339	339	SHIP CONSTRUCTION TURNKEY	Cork County	Parklands, Youghal	13	*N/A	""	""	""	""	""	Q4-2018
340	340	SHIP CONSTRUCTION TURNKEY	Cork County	Oliver Plunkett Place, Doneraile	2	*N/A	""	""	""	""	""	Q4-2019
341	341	SHIP CONSTRUCTION TURNKEY	Cork County	No.9 and No.10  Chapel Court, Skibbereen,	2	*N/A	""	""	""	""	""	Q4-2018
342	342	SHIP CONSTRUCTION TURNKEY	Cork County	Tir Cluain, Midleton	8	*N/A	""	""	""	""	""	Q4-2018
343	343	SHIP CONSTRUCTION TURNKEY	Cork County	College Mews, Cobh	6	*N/A	""	""	""	""	""	Q4-2018
344	344	SHIP CONSTRUCTION TURNKEY	Cork County	Rathcormac	4	*N/A	""	""	""	""	""	Q4-2018
345	345	SHIP CONSTRUCTION TURNKEY	Cork County	Fairgreen, Mallow	10	*N/A	""	""	""	""	""	Q4-2019
346	346	SHIP CONSTRUCTION TURNKEY	Cork County	Tir Cluain, Midleton	14	*N/A	""	""	""	""	""	Q3-2019
347	347	SHIP CONSTRUCTION TURNKEY	Cork County	Church Road/Station Road, Carrigtwohill	7	*N/A	""	""	""	""	""	Q3-2018
348	348	SHIP CONSTRUCTION TURNKEY	Cork County	Canon St, Rathcormac	3	*N/A	""	""	""	""	Q1-2019	""
349	349	SHIP CONSTRUCTION TURNKEY	Cork County	Percival St, Kanturk	2	*N/A	""	""	""	""	""	Q4-2018
350	350	SHIP CONSTRUCTION TURNKEY	Cork County	9 & 9a Main Street, Boherbue	2	*N/A	""	""	""	""	""	Q4-2018
351	351	SHIP CONSTRUCTION TURNKEY	Cork County	Parklands, Youghal	6	*N/A	""	""	""	""	""	Q2-2019
352	352	SHIP CONSTRUCTION TURNKEY	Cork County	Rathcormac	4	*N/A	""	""	""	""	""	Q2-2019
353	353	SHIP CONSTRUCTION TURNKEY	Cork County	Inis Fáil, Curraclough, Bandon	13	*N/A	""	""	""	""	""	Q4-2019
354	354	SHIP CONSTRUCTION TURNKEY	Cork County	Maple Woods, Midleton	6	*N/A	""	""	""	""	""	Q4-2018
355	355	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	22	*N/A	""	""	""	""	Q4-2017	""
356	356	SHIP CONSTRUCTION TURNKEY	Cork County	St. Mary’s Road, Dunmanway	6	*N/A	""	""	""	""	""	Q3-2020
357	357	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	3	*N/A	""	""	""	""	""	Q4-2021
358	358	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	7	*N/A	""	""	""	""	Q2-2019	""
359	359	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	12	*N/A	""	""	""	""	""	Q4-2020
360	360	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	11	*N/A	""	""	""	""	""	Q1-2021
361	361	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	17	*N/A	""	""	""	""	""	Q2-2021
362	362	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Cairn, Station Road, Carrigtwohill	2	*N/A	""	""	""	""	""	Q3-2019
363	363	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	6	*N/A	""	""	""	""	""	Q2-2020
364	364	SHIP CONSTRUCTION TURNKEY	Cork County	Gleann Orga, Ballinhassig	4	*N/A	""	""	""	""	""	Q4-2019
365	365	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	8	*N/A	""	""	""	""	""	Q4-2020
366	366	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Ard, Cobh	6	*N/A	""	""	""	""	""	Q3-2019
367	367	SHIP CONSTRUCTION TURNKEY	Cork County	Baltimore, West Cork	12	*N/A	""	""	""	""	""	Q4-2019
368	368	SHIP CONSTRUCTION TURNKEY	Cork County	Chapel Court, Skibbereen	2	*N/A	""	""	""	""	""	Q4-2019
369	369	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Ard, Freemount	4	*N/A	""	""	""	""	""	Q4-2019
370	370	SHIP CONSTRUCTION TURNKEY	Cork County	Glengarriff	5	*N/A	""	""	""	""	""	Q4-2019
371	371	SHIP CONSTRUCTION TURNKEY	Cork County	The Cove, Glandore	4	*N/A	""	""	""	""	""	Q4-2019
372	372	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	7	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
373	373	SHIP CONSTRUCTION TURNKEY	Cork County	An Tui, Lisgoold, Leamlara	3	*N/A	""	""	""	""	""	Q4-2019
374	374	SHIP CONSTRUCTION TURNKEY	Cork County	Millstreet Road, Macroom	12	*N/A	""	""	""	""	""	Q4-2020
375	375	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	14	*N/A	""	""	""	""	""	Q4-2019
376	376	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Cairn, Station Road, Carrigtwohill	12	*N/A	""	""	""	""	""	Q4-2020
377	377	SHIP CONSTRUCTION TURNKEY	Cork County	Glenbeg The Beeches, Boherbue	4	*N/A	""	""	""	""	""	Q4-2019
378	378	SHIP CONSTRUCTION TURNKEY	Cork County	Chapel Court, Skibbereen	3	*N/A	""	""	""	""	""	Q4-2019
379	379	SHIP CONSTRUCTION TURNKEY	Cork County	Millview Road, Kanturk	4	*N/A	""	""	""	""	""	Q1-2021
380	380	SHIP CONSTRUCTION TURNKEY	Cork County	An Tui, Lisgoold, Leamlara	1	*N/A	""	""	""	""	""	Q2-2020
381	381	SHIP CONSTRUCTION TURNKEY	Cork County	Bruhenny, Churchtown	6	*N/A	""	""	""	""	""	Q4-2019
382	382	SHIP CONSTRUCTION TURNKEY	Cork County	Ard Bhaile, Buttevant	6	*N/A	""	""	""	Stage 4 approved Q4-2019, the scheme is fully approved.	""	""
383	383	SHIP CONSTRUCTION TURNKEY	Cork County	Cecilstown, Mallow	2	*N/A	""	""	""	Stage 4 approved Q4-2019, the scheme is fully approved.	""	""
384	384	SHIP CONSTRUCTION TURNKEY	Cork County	Ballymacmoy, Killavullen, Co. Cork	13	*N/A	""	""	""	Stage 4 approved Q4-2019, the scheme is fully approved.	""	""
385	385	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A	""	""	""	""	""	Q2-2021
386	386	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	8	*N/A	""	""	""	""	""	Q3-2019
387	387	SHIP CONSTRUCTION TURNKEY	Cork County	Gortnaclohy, Skibbereen, Co. Cork	34	*N/A	""	""	""	Stage 4 approved Q4-2019, the scheme is fully approved.	""	""
388	388	SHIP CONSTRUCTION TURNKEY	Cork County	Castle Heights, Carrigaline	3	*N/A	""	""	""	""	""	Q4-2020
389	389	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Cairn, Station Road, Carrigtwohill	7	*N/A	""	""	""	""	""	Q4-2019
390	390	SHIP CONSTRUCTION TURNKEY	Cork County	The Court, Ard Cashel, Watergrasshill	4	*N/A	""	""	""	""	""	Q4-2019
391	391	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	12	*N/A	""	""	""	""	Q1-2021	""
392	392	SHIP CONSTRUCTION TURNKEY	Cork County	Millview Road, Kanturk	10	*N/A	""	""	""	""	""	Q4-2020
393	393	SHIP CONSTRUCTION TURNKEY	Cork County	Glenbeg, The Beeches, Boherbue	8	*N/A	""	""	""	""	""	Q4-2020
394	394	SHIP CONSTRUCTION TURNKEY	Cork County	Oliver Plunkett Place, Doneraile	3	*N/A	""	""	""	""	""	Q4-2020
395	395	SHIP CONSTRUCTION TURNKEY	Cork County	Inis Fáil, Curraclough, Bandon	17	*N/A	""	""	""	""	""	Q3-2020
396	396	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	10	*N/A	""	""	""	""	Q1-2020	""
397	397	SHIP CONSTRUCTION TURNKEY	Cork County	St. Mary’s Road, Dunmanway	7	*N/A	""	""	""	""	""	Q4-2019
398	398	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Cairn, Station Road, Carrigtwohill	7	*N/A	""	""	""	""	""	Q4-2020
399	399	SHIP CONSTRUCTION TURNKEY	Cork County	An Goritin Rua, Millstreet Road, Macroom	14	*N/A	""	""	""	""	""	Q2-2021
400	400	SHIP CONSTRUCTION TURNKEY	Cork County	Lyraneag, Rockchapel,	2	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
401	401	SHIP CONSTRUCTION TURNKEY	Cork County	Cluain Reidh, Ballyvourney	1	*N/A	""	""	""	""	""	Q4-2019
402	402	SHIP CONSTRUCTION TURNKEY	Cork County	Curragh, Upper Aghada	2	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
403	403	SHIP CONSTRUCTION TURNKEY	Cork County	Glebe Manor, Whitegate	12	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
404	404	SHIP CONSTRUCTION TURNKEY	Cork County	Eyeries, Castletownbere	6	*N/A	""	""	""	""	Q4-2020	""
405	405	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmorna, Mallow	1	*N/A	""	""	""	""	""	Q4-2020
406	406	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A	""	""	""	""	""	Q1-2021
407	407	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	20	*N/A	""	""	""	""	""	Q4-2020
408	408	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	18	*N/A	""	""	""	""	""	Q2-2021
409	409	SHIP CONSTRUCTION TURNKEY	Cork County	Drakes Point, Knocknagore, Crosshaven	5	*N/A	""	""	""	""	""	Q3-2021
410	410	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale	14	*N/A	""	""	""	""	""	Q4-2020
411	411	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	6	*N/A	""	""	""	""	Q1-2020	""
412	412	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	18	*N/A	""	""	""	""	Q1-2020	""
413	413	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale	19	*N/A	""	""	""	""	""	Q4-2021
414	414	SHIP CONSTRUCTION TURNKEY	Cork County	Oliver Plunkett Place, Doneraile	1	*N/A	""	""	""	""	""	Q3-2020
415	415	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	8	*N/A	""	""	""	""	""	Q3-2020
416	416	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	4	*N/A	""	""	""	""	""	Q1-2021
417	417	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale, Phase 2, Co. Cork	17	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
418	418	SHIP CONSTRUCTION TURNKEY	Cork County	Ard Cashel, Watergrasshill, Co. Cork	6	*N/A	""	""	""	""	Q3-2021	""
419	419	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A	""	""	""	""	""	Q2-2021
420	420	SHIP CONSTRUCTION TURNKEY	Cork County	Courtbrack, Tower	1	*N/A	""	""	""	""	""	Q4-2021
421	421	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	10	*N/A	""	""	""	Stage 4 approved Q2-2018, the scheme is fully approved.	""	""
422	422	SHIP CONSTRUCTION TURNKEY	Cork County	An Tui, Liosgoold	2	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
423	423	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	26	*N/A	""	""	""	Stage 4 approved Q3-2016, the scheme is fully approved.	""	""
424	424	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	4	*N/A	""	""	""	""	""	Q4-2021
425	425	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	7	*N/A	""	""	""	""	""	Q2-2021
426	426	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	10	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
427	427	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville, Co. Cork	12	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
428	428	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	21	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
429	429	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	11	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
430	430	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	14	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
431	431	SHIP CONSTRUCTION TURNKEY	Cork County	Derrymihin, Castletownbere, Co. Cork	16	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
432	432	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A	""	""	""	""	""	Q4-2021
433	433	SHIP CONSTRUCTION TURNKEY	Cork County	The Meadows, Dunmanway, Co. Cork	4	N/A	""	""	""	""	Q4-2021	""
434	434	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	7	N/A	""	""	""	Stage 4 approved Q2-2018, the scheme is fully approved.	""	""
435	435	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Model Village, Dripsey	6	*N/A	""	""	""	""	""	Q4-2020
436	436	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Castletreasure Grove, Douglas	2	*N/A	""	""	""	""	""	Q4-2019
437	437	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Seaview Cottages, Derrymihan, Castletownbere	3	*N/A	""	""	""	""	""	Q4-2020
438	438	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Curraleigh, Inniscarra	1	*N/A	""	""	""	""	""	Q3-2019
439	439	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Cuirt Na Slini, Cloyne, East Cork 	2	*N/A	""	""	""	""	Q3-2021	""
440	440	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Main St. Dunmanway	1	*N/A	""	""	""	""	""	Q4-2021
441	441	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Thomas Kent Street, Cobh	1	*N/A	""	""	""	""	""	Q4-2020
442	442	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Croke Place, Garranmacgarrett, Kilbrin, kanturk	2	*N/A	""	""	""	""	Q3-2020	""
443	443	SHIP CONSTRUCTION SINGLE STAGE	Cork County	High St., Sleaveen Hill, Macroom, Co. Cork	1	*N/A	""	""	""	""	Q2-2021	""
444	444	SHIP CONSTRUCTION SINGLE STAGE	Cork County	49 Masseytown, Macroom, Co. Cork 	1	*N/A	""	""	""	""	Q2-2021	""
445	445	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Carrig Rossa Phase 2, Rossmore	2	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
446	446	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Fana Na gCann, Co. Cork	2	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
447	447	SHIP CONSTRUCTION SINGLE STAGE	Cork County	3 Knockbrogan Park, Bandon	1	*N/A	""	""	""	""	""	Q4-2021
448	448	SHIP CONSTRUCTION	Cork County	Downeen Cross, Rosscarbery	7	*N/A	""	""	""	""	""	Q4-2019
449	449	SHIP CONSTRUCTION	Cork County	Ard Na Greine, Cortmacsherry	17	*N/A	""	""	""	""	Q3-2019	""
450	450	SHIP CONSTRUCTION	Cork County	Station Road, Blarney	18	*N/A	""	""	""	""	""	Q4-2020
451	451	SHIP CONSTRUCTION	Cork County	Bluepool, Kanturk	12	*N/A	""	""	""	""	""	Q4-2020
452	452	SHIP CONSTRUCTION	Cork County	Tower View/Cúirt na Silíní, Cloyne, East Cork	7	*N/A	""	""	""	""	""	Q3-2019
453	453	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	51	*N/A	""	""	""	""	""	Q4-2021
454	454	SHIP CONSTRUCTION	Cork County	Newtown House , Bantry	1	*N/A	""	""	""	""	""	Q4-2021
455	455	SHIP CONSTRUCTION	Cork County	Fairfield, Masseytown, Macroom	7	*N/A	""	""	""	""	""	Q4-2018
456	456	SHIP CONSTRUCTION	Cork County	12 & 14 Droum, Castletownbere	2	*N/A	""	""	""	""	""	Q4-2018
457	457	SHIP CONSTRUCTION	Cork County	Kilnagleary, Carrigaline (Phase 4)	15	*N/A	""	""	""	""	Q4-2019	""
458	458	SHIP CONSTRUCTION	Cork County	Oliver Plunkett Hill, Fermoy	10	*N/A	""	""	""	""	""	Q2-2017
459	459	SHIP CONSTRUCTION	Cork County	Townsend Street, Skibbereen	6	*N/A	""	""	""	""	Q3-2019	""
460	460	SHIP CONSTRUCTION	Cork County	Forest View, Mallow	10	*N/A	""	""	""	""	""	Q4-2020
461	461	SHIP CONSTRUCTION	Cork County	11/10 Harbour Hill, Cobh	1	*N/A	""	""	""	""	""	Q2-2018
462	462	SHIP CONSTRUCTION	Cork County	Kilnagleary Carrigaline	10	*N/A	""	""	""	""	""	Q4-2018
463	463	SHIP CONSTRUCTION	Cork County	Kilnagleary Carrigaline	16	*N/A	""	""	""	""	""	Q1-2019
464	464	SHIP CONSTRUCTION	Cork County	Kilnagleary Carrigaline	18	*N/A	""	""	""	""	""	Q1-2019
465	465	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	5	*N/A	""	""	""	""	Q3-2020	""
466	466	SHIP CONSTRUCTION	Cork County	Richmond Court, Bandon	6	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
467	467	SHIP CONSTRUCTION	Cork County	Brigown Road, Mitchelstown	8	*N/A	""	Stage 2 approved Q3-2018, full design/tender being prepared.	""	""	""	""
468	468	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	8	*N/A	""	""	Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.	""	""	""
469	469	SHIP CONSTRUCTION	Cork County	Kilnagleary Carrigaline	5	*N/A	""	""	""	""	""	Q4-2018
470	470	SHIP CONSTRUCTION	Cork County	Tudor Grove, Ballincollig	16	*N/A	""	""	""	""	""	Q4-2019
471	471	SHIP CONSTRUCTION	Cork County	Pound Lane, Kilworth 	7	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
472	472	SHIP CONSTRUCTION	Cork County	Knocknagown, Rylane	1	*N/A	""	""	""	""	""	Q3-2021
473	473	SHIP CONSTRUCTION	Cork County	Uplands (Phase 2), College Road,  Fermoy	11	*N/A	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
474	474	SHIP CONSTRUCTION	Cork County	Lissoran, Ballinspittle	4	*N/A	""	""	""	""	""	Q4-2021
475	475	SHIP CONSTRUCTION	Cork County	Tower View/Cúirt na Silíní, Cloyne, East Cork	2	*N/A	""	""	""	""	Q3-2018	""
476	476	SHIP CONSTRUCTION	Cork County	Convent Road, Doneraile	17	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
477	477	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	13	*N/A	""	""	""	""	Q3-2020	""
478	478	SHIP CONSTRUCTION	Cork County	Chapel Lane, Ballydehob, Co. Cork	12	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
479	479	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	16	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
480	480	SHIP CONSTRUCTION	Cork County	Old Barrack Road, Bantry, Co. Cork	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
481	481	SHIP CONSTRUCTION	Cork County	Coastguard Cottages, Lower Roads, Crosshaven, Co. Cork	27	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
482	482	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	6	N/A	""	""	""	""	Q3-2019	""
483	483	CAS CONSTRUCTION TURNKEY	Cork County	Ardmanagh, Schull	12	Túath Housing Association Ltd	""	""	""	""	Q1-2021	""
484	484	CAS CONSTRUCTION	Cork County	Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay	18	Cluid Housing Association	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
485	485	CAS CONSTRUCTION	Cork County	Cuan Barra, Kilmore, Ballingeary	3	Coiste Tithe Uibh Laoire Teoranta	""	""	""	""	""	Q3-2018
486	486	CAS CONSTRUCTION	Cork County	Caim Hill, Townlands, Rosscarbery	9	Rosscarbery Housing Association Ltd	""	""	""	""	""	Q1-2019
487	487	CAS CONSTRUCTION	Cork County	Avenue House, Bandon	9	Bandon Geriatric ? Community Council	""	""	""	""	""	Q1-2018
488	488	CAS CONSTRUCTION	Cork County	Church View, Love Lane, Charleville	4	Charleville Care Project Ltd	""	""	""	""	""	Q4-2019
489	489	CAS CONSTRUCTION	Cork County	Fellowship House, Togher	31	Tabor Lodge Addiction ? Housing Services Ltd	""	""	""	""	""	Q2-2018
490	490	CAS CONSTRUCTION	Cork County	Masseytown, Macroom	14	Túath Housing Association Ltd	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
491	491	CAS CONSTRUCTION	Cork County	Baile Bhuire, Macroom	3	*N/A	""	""	""	""	Q2-2020	""
492	492	CAS CONSTRUCTION	Cork County	Charleville, Church View, Love Lane, Charleville	9	Charleville Care Project Ltd	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
493	493	CAS CONSTRUCTION	Cork County	St. Michaels, 36 Main Street, Bandon, Co. Cork	6	Bandon Geriatric ? Community Council	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
494	494	CAS CONSTRUCTION	Cork County	Distillery Lane, Distillery Walk, Midleton	7	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
495	495	CAS CONSTRUCTION	Cork County	Mardyke, Skibbereen	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
496	496	CAS CONSTRUCTION	Cork County	Daniel O’Brien Terrace, Buttevant	7	Túath Housing Association Ltd	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
497	497	CAS CONSTRUCTION	Cork County	Lisheen Field, Kilbarry Road, Dunmanway, Co. Cork	16	Cluid Housing Association	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
498	498	CALF Turnkey	Cork County	21 units, Brookhill, Carrigaline, Cork (Phase 1)	21	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
499	499	CALF Turnkey	Cork County	3 units, Mullavale, Castletownroche, Co. Cork (Phase 1)	3	Respond	""	""	""	""	""	Q2-2019
500	500	CALF Turnkey	Cork County	Beach Road, Passage West, Co. Cork (Phase 1)	3	Clúid Housing	""	""	""	""	""	Q4-2017
501	501	CALF Turnkey	Cork County	Brookhill (5 Units), Carrigaline, Cork (Phase 1)	5	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
502	502	CALF Turnkey	Cork County	Brookhill, Carrigaline, Co. Cork (Phase 1)	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
503	503	CALF Turnkey	Cork County	Brookhill, Carrigaline, Co. Cork (Phase 1)*	31	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2020
504	504	CALF Turnkey	Cork County	Brookhill, Carrigaline, Co. Cork (Phase 2)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
505	505	CALF Turnkey	Cork County	Cascade Apartments, Castlelake, Carrigtwohill, Cork (Phase 1)	95	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2021	""
506	506	CALF Turnkey	Cork County	Castle Heights, Kilmoney, Carrigaline, Co Cork (Phase 1)	8	Clúid Housing	""	""	""	""	Q2-2021	""
507	507	CALF Turnkey	Cork County	Castle Heights, Kilmoney, Carrigaline, Co Cork (Phase 2)	4	Clúid Housing	""	""	""	""	Q2-2021	""
508	508	CALF Turnkey	Cork County	Chapel Court, Skibbereen, Cork (Phase 1)	8	Clúid Housing	""	""	""	""	Q3-2021	""
509	509	CALF Turnkey	Cork County	Chapel Court, Skibbereen, Cork (Phase 2)	8	Clúid Housing	""	""	""	""	Q3-2021	""
510	510	CALF Turnkey	Cork County	Church Hill, Carrigaline, Co Cork (Phase 1)*	37	Respond	""	""	""	""	Q3-2021	""
511	511	CALF Turnkey	Cork County	Cluain Reidh, Ballymakeera, Co. Cork (Phase 1)	10	Clúid Housing	""	""	""	""	""	Q3-2020
512	512	CALF Turnkey	Cork County	College Manor, Cobh (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q4-2016
513	513	CALF Turnkey	Cork County	Coolroe, Ballincollig, Co. Cork (Phase 1)*	24	Respond	""	""	""	""	""	Q4-2020
514	514	CALF Turnkey	Cork County	Coolroe, Ballincollig, Co. Cork (Phase 2)	20	Respond	""	""	""	""	""	Q1-2021
515	515	CALF Construction	Cork County	Duntahane, Fermoy, Co. Cork (Phase 1)	46	Respond	""	""	""	""	""	Q4-2020
516	516	CALF Construction	Cork County	Firgrove Harrisons lane (Phase 1)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2017
517	517	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 1)	14	Clúid Housing	""	""	""	""	Q4-2020	""
518	518	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 2)	13	Clúid Housing	""	""	""	""	Q4-2020	""
519	519	CALF Turnkey	Cork County	Hazel View, Hazel Brooke, Spa Glen, Mallow, Co Cork (Phase 1)	12	Clúid Housing	""	""	""	Q4-2021	""	""
520	520	CALF Turnkey	Cork County	Market Green, Knockgriffin, Midleton, Co. Cork (Phase 1)	20	Respond	""	""	""	""	""	Q4-2019
521	521	CALF Turnkey	Cork County	Market Green, Knockgriffin, Midleton, Co. Cork (Phase 2)*	22	Respond	""	""	""	""	""	Q4-2020
522	522	CALF Turnkey	Cork County	Mullavale, Castletownroche, Co. Cork (Phase 1)	6	Respond	""	""	""	""	""	Q4-2018
523	523	CALF Construction	Cork County	Post Tender - Radharc An tSaile, Cappagh, Ballynacubby, Kinsale, Co Cork (Phase 1)	40	Clúid Housing	""	""	""	""	""	Q3-2020
524	524	CALF Turnkey	Cork County	Shambles Lane, Thomas Davis Street, Mallow, Co Cork (Phase 1)	6	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
525	525	CALF Turnkey	Cork County	Sunville, Church Road, Carrigaline, Co. Cork (Phase 1)	6	Focus Housing Association CLG	""	""	""	""	""	Q4-2020
526	526	CALF Turnkey	Cork County	Tanners Field, Bandon, Co Cork  (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q3-2019
527	527	CALF Turnkey	Cork County	The Miles, Clonakilty, Co Cork  (Phase 1)	38	Clúid Housing	""	""	""	Q3-2021	""	""
528	528	CALF Turnkey	Cork County	Ticknock, Cobh, Cork (Phase 1)	8	Respond	""	""	""	""	""	Q4-2018
529	529	CALF Turnkey	Cork County	Togher Cross, Lehenaghmore, Co. Cork (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q4-2019
530	530	CALF Turnkey	Cork County	Weston, Carrigaline, Co. Cork (Phase 1)	7	Respond	""	""	""	""	""	Q2-2018
531	531	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 1)	20	*N/A	""	""	""	""	""	Q2-2021
532	532	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 2)	32	*N/A	""	""	""	""	""	Q4-2021
533	533	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 1)	35	*N/A	""	""	""	""	""	Q2-2021
534	534	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 2)	15	*N/A	""	""	""	""	""	Q4-2021
535	535	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 1)	37	*N/A	""	""	""	""	""	Q2-2021
536	536	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 2)	13	*N/A	""	""	""	""	""	Q3-2021
537	537	SHIP CONSTRUCTION TURNKEY	DLR	Hazelbrook, Nutgrove, Churchtown	28	*N/A	""	""	""	""	""	Q4-2017
538	538	SHIP CONSTRUCTION TURNKEY	DLR	Dunedin Terrace, Monkstown	14	*N/A	""	""	""	""	""	Q4-2018
539	539	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	22	*N/A	""	""	""	""	""	Q1-2021
540	540	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	16	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
541	541	SHIP CONSTRUCTION TURNKEY	DLR	George's Street Upper, Dun Laoghaire	5	*N/A	""	""	""	""	""	Q1-2021
542	542	SHIP CONSTRUCTION TURNKEY	DLR	HazelBrook Square, Nutgrove, Churchtown	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
543	543	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	17	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
544	544	SHIP CONSTRUCTION RAPID	DLR	Rockville Green (Glenamuck Cottages)	13	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
545	545	SHIP CONSTRUCTION RAPID	DLR	George's Place	12	*N/A	""	""	""	""	""	Q2-2018
546	546	SHIP CONSTRUCTION RAPID	DLR	Ballyogan Square, Ballyogan	67	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
547	547	SHIP CONSTRUCTION	DLR	Park House, 66 George's Street, Dun Laoghaire	4	*N/A	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
548	548	SHIP CONSTRUCTION	DLR	132 Pottery Road, Dun Laoghaire	4	*N/A	""	""	""	""	""	Q3-2018
549	549	SHIP CONSTRUCTION	DLR	Temple Road	3	*N/A	""	""	""	""	""	Q2-2018
550	550	SHIP CONSTRUCTION	DLR	Assistant Harbour Master House	2	*N/A	""	""	""	""	""	Q3-2017
551	551	SHIP CONSTRUCTION	DLR	The Brambles Park Close Sallynoggin	10	*N/A	""	""	""	""	""	Q2-2018
552	552	SHIP CONSTRUCTION	DLR	49 The Mews Sallynoggin Park	4	*N/A	""	""	""	""	""	Q4-2017
553	553	SHIP CONSTRUCTION	DLR	Shanganagh Park Lodge	1	*N/A	""	""	""	""	""	Q2-2016
554	554	SHIP CONSTRUCTION	DLR	Rosemount Court	44	*N/A	""	""	""	""	""	Q4-2018
555	555	SHIP CONSTRUCTION	DLR	Broadford Rise	21	*N/A	""	""	""	""	""	Q4-2021
556	556	SHIP CONSTRUCTION	DLR	Fitzgerald Park	33	*N/A	""	""	""	""	""	Q4-2018
557	557	SHIP CONSTRUCTION	DLR	Rochestown House (Phase 3)	14	*N/A	""	""	""	""	""	Q3-2018
558	558	SHIP CONSTRUCTION	DLR	St Michael's Terrace	4	*N/A	""	""	""	""	""	Q3-2017
559	559	SHIP CONSTRUCTION	DLR	Clontibret House	4	*N/A	""	""	""	""	""	Q4-2016
560	560	SHIP CONSTRUCTION	DLR	Cromlech Close	15	*N/A	""	""	""	""	""	Q3-2016
561	561	SHIP CONSTRUCTION	DLR	Rochestown House (Phase 2)	34	*N/A	""	""	""	""	""	Q3-2016
562	562	SHIP CONSTRUCTION	DLR	Ballyogan Avenue, Ballyogan	2	*N/A	""	""	""	""	""	Q2-2021
563	563	SHIP CONSTRUCTION	DLR	St. Laurence’s Park, Stillorgan	89	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
564	564	SHIP CONSTRUCTION	DLR	Fitzgerald Park	17	*N/A	""	""	""	""	""	Q1-2019
565	565	SHIP CONSTRUCTION	DLR	Moyola Court, Churchtown Lower, Dublin 14	4	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
566	566	SHIP CONSTRUCTION	DLR	Shanganagh Castle	200	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
567	567	SHIP CONSTRUCTION	DLR	37A Rollins Villas, Sallynoggin, Co. Dublin 	1	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
568	568	SHIP CONSTRUCTION	DLR	Old Coastguard Cottages, Coal Harbour, Harbour Road	4	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
569	569	SHIP CONSTRUCTION	DLR	Cross Avenue, Dún Laoghaire, Co. Dublin	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
570	570	CAS CONSTRUCTION	DLR	30 Obelisk Walk, Blackrock	4	St. John of God Housing Association Ltd	""	""	""	""	""	Q4-2021
571	571	CALF Construction	DLR	Abbeyview House, Monkstown, Dublin (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q4-2020
572	572	CALF Turnkey	DLR	Ardilea Crescent, Ardilea, Clonskeagh, Dublin 14, Co. Dublin (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2021
573	573	CALF Turnkey	DLR	Ardilea Crescent, Clonskeagh, Dublin 14 (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q4-2018
574	574	CALF Turnkey	DLR	Ballybetagh Road, Kilternan, Co Dublin (Phase 1)*	22	Clanmil Housing Association Ireland	""	""	""	""	Q3-2021	""
575	575	CALF Turnkey	DLR	Belarmine Drive, Belarmine, Stepaside, Dublin 18 (Phase 1)*	6	Clúid Housing	""	""	""	""	""	Q4-2019
576	576	CALF Turnkey	DLR	Bishops Gate, Enniskerry Rd., Dublin 18 (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q4-2019
577	577	CALF Turnkey	DLR	Bishops Gate, Kilternan, Dublin 18  (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q3-2018
578	578	CALF Turnkey	DLR	Bishops Gate, Kilternan, Dublin 18  (Phase 2)*	2	Clúid Housing	""	""	""	""	""	Q3-2018
579	579	CALF Turnkey	DLR	Block C, Abbey Road, Monkstown, (Phase 1)*	3	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2018
580	580	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 1)*	80	Clúid Housing	""	""	""	""	Q4-2019	""
581	581	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 2)*	61	Clúid Housing	""	""	""	""	Q4-2019	""
582	582	CALF Turnkey	DLR	Clay Farm (Block E3), Ballyogan Road, Leopardstown, Dublin 18 (Phase 1)*	24	The Iveagh Trust	""	""	""	""	""	Q4-2019
583	583	CALF Turnkey	DLR	Clays Farm, Ballyogan Road (Phase 1)  (Phase 1)*	44	The Iveagh Trust	""	""	""	""	""	Q2-2019
584	584	CALF Turnkey	DLR	Egremont, Church Road, Killiney, Co. Dublin (Phase 1)*	2	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2019	""
585	585	CALF Turnkey	DLR	Egremont, Church Road, Killiney, Co. Dublin (Phase 2)*	2	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2019	""
586	586	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 1)	9	Respond	""	""	""	""	""	Q4-2021
587	587	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 2)	22	Respond	""	""	""	""	Q3-2019	""
588	588	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 3)	22	Respond	""	""	""	""	Q3-2019	""
589	589	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 1)	18	Tuath Housing Association	""	""	""	""	""	Q4-2021
590	590	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 2)	16	Tuath Housing Association	""	""	""	""	Q3-2019	""
591	591	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 3)	18	Tuath Housing Association	""	""	""	""	Q3-2019	""
592	592	CALF Turnkey	DLR	Eustace Court, Upper Glenageary Road, Dun Laoghaire, Rathdown, Co. Dublin (Phase 1)	4	St John of God Housing Association Ltd	""	""	""	""	""	Q4-2019
593	593	CALF Turnkey	DLR	Garrison Mews, The Ramparts, Cabinteely, Co. Dublin (Phase 1)*	5	Focus Housing Association CLG	""	""	""	""	""	Q4-2020
594	594	CALF Turnkey	DLR	Greenbank House, Upper Glenageary Road, Dun Laoghaire, Co. Dublin (Phase 1)	1	St John of God Housing Association Ltd	""	""	""	""	""	Q4-2018
595	595	CALF Turnkey	DLR	Hyde Road, Belmont, Stepaside, Co. Dublin (Phase 1)*	8	Respond	""	""	""	""	""	Q4-2018
596	596	CALF Turnkey	DLR	Johnstown Place,Johnstown Road, Cabinteely, Dublin 18 (Formerly Johnstown Court) (Phase 1)*	51	Clúid Housing	""	""	""	""	""	Q2-2021
597	597	CALF Turnkey	DLR	Knockrabo, Mount Anville Road, Goatstown, Dublin 14 (Phase 1)*	6	Oaklee Housing	""	""	""	""	""	Q4-2020
598	598	CALF Turnkey	DLR	Marine Walk, Marine Road, Dun Laoghaire (Phase 1)*	2	Oaklee Housing	""	""	""	""	""	Q4-2020
599	599	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 1)*	14	Tuath Housing Association	""	""	""	""	""	Q1-2021
600	600	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 2)*	18	Tuath Housing Association	""	""	""	""	""	Q2-2021
601	601	CALF Turnkey	DLR	Oakton Court, Ballybrack, Co. Dublin (Phase 1)	5	Circle Voluntary Housing Association Ltd	""	""	""	""	Q4-2021	""
602	602	CALF Turnkey	DLR	Our Ladys Grove, Goatstown, Dublin 14 (Phase 1)*	2	Respond	""	""	""	""	""	Q4-2018
603	603	CALF Turnkey	DLR	Rockville Hall, Glenamuck Road, Dunlaoghaire, Dublin 18 (Phase 1)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
604	604	CALF Turnkey	DLR	Stillorgan Gate, Kilmacud Road Upper, Co Dublin  (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q4-2017
605	605	CALF Turnkey	DLR	Stillorgan Gate, Kilmacud Road Upper, Stillorgan, Co. Dublin (Phase 1)*	2	Clúid Housing	""	""	""	""	""	Q4-2018
606	606	CALF Turnkey	DLR	The Avenue, Glenside,  Carrickmines Green, Dublin 18 (Phase 1)*	5	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2018
607	607	CALF Turnkey	DLR	The Glen, Glenamuck Road, Carrickmines, Dublin 18 (Phase 1)*	48	Respond	""	""	""	""	Q1-2021	""
608	608	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)	59	Respond	""	""	""	""	Q3-2020	""
609	609	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)*	6	Respond	""	""	""	""	Q3-2020	""
610	610	CALF Turnkey	DLR	Woodbank, Dublin Rd, Shankill, Co Dublin  (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q3-2017
611	611	SHIP DIALOG	Donegal	Drumrooske West	36	*N/A	""	""	""	""	Q2-2021	""
612	612	SHIP DIALOG	Donegal	Convent Road, Carndonagh	21	*N/A	""	""	""	""	Q1-2021	""
613	613	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
614	614	SHIP DIALOG	Donegal	Donegal Road, Ballybofey	14	*N/A	""	""	""	""	Q1-2021	""
615	615	SHIP DIALOG	Donegal	Admiran, Stranorlar	52	*N/A	""	""	""	""	Q4-2021	""
616	616	SHIP DIALOG	Donegal	Rockview, Carrickboy, Ballyshannon	5	*N/A	""	""	""	""	Q1-2021	""
617	617	SHIP DIALOG	Donegal	Ardaravan, Buncrana	4	*N/A	""	""	""	""	Q4-2020	""
618	618	SHIP DIALOG	Donegal	Glencrow, Moville	35	*N/A	""	""	""	""	Q2-2021	""
619	619	SHIP DIALOG	Donegal	Ballyraine, Letterkenny	25	*N/A	""	""	""	""	Q3-2021	""
620	620	SHIP DIALOG	Donegal	Lough Fern Heights, Milford	17	*N/A	""	""	""	""	Q1-2021	""
621	621	SHIP DIALOG	Donegal	Convent Road, Carndonagh	18	N/A	""	""	""	""	Q1-2021	""
622	622	SHIP DIALOG	Donegal	Convent Road, Carndonagh	14	N/A	""	""	""	""	Q1-2021	""
623	623	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
624	624	SHIP CONSTRUCTION TURNKEY	Donegal	Gleann Na Greine, Mullindrait, Stranorlar	21	*N/A	""	""	""	""	""	Q2-2018
625	625	SHIP CONSTRUCTION TURNKEY	Donegal	Crievesmith, Letterkenny	18	*N/A	""	""	""	""	""	Q4-2018
626	626	SHIP CONSTRUCTION TURNKEY	Donegal	Crievesmith, Letterkenny	8	*N/A	""	""	""	""	""	Q1-2019
627	627	SHIP CONSTRUCTION TURNKEY	Donegal	Carnamuggagh, Letterkenny	30	*N/A	""	""	""	""	""	Q4-2020
628	628	SHIP CONSTRUCTION TURNKEY	Donegal	Heathhill, Newtowncunningham	10	*N/A	""	""	""	""	""	Q4-2019
629	629	SHIP CONSTRUCTION TURNKEY	Donegal	Crievesmith, Letterkenny	10	*N/A	""	""	""	""	""	Q2-2019
630	630	SHIP CONSTRUCTION TURNKEY	Donegal	Hattersly Park, Carndonagh	21	*N/A	""	""	""	""	Q3-2021	""
631	631	SHIP CONSTRUCTION TURNKEY	Donegal	Brookfield, Donegal Town	8	*N/A	""	""	""	""	Q4-2020	""
632	632	SHIP CONSTRUCTION TURNKEY	Donegal	Stáisiún an Chúirt, Falcarragh	6	*N/A	""	""	""	""	""	Q4-2019
633	633	SHIP CONSTRUCTION TURNKEY	Donegal	Stáisiún an Chúirt, Falcarragh	6	*N/A	""	""	""	""	""	Q4-2020
634	634	SHIP CONSTRUCTION TURNKEY	Donegal	Heathhill, Newtowncunningham	7	*N/A	""	""	""	""	""	Q3-2020
635	635	SHIP CONSTRUCTION TURNKEY	Donegal	Brookfield, Donegal Town	12	*N/A	""	""	""	""	Q4-2020	""
636	636	SHIP CONSTRUCTION TURNKEY	Donegal	Brookfield, Donegal Town	14	*N/A	""	""	""	""	Q4-2020	""
637	637	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Figart, Dunfanaghy	8	*N/A	""	""	""	""	""	Q4-2019
638	638	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Loughanure Annagry	1	*N/A	""	""	""	""	Q1-2021	""
639	639	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Meenderrynasloe, Annagry	1	*N/A	""	""	""	""	Q1-2021	""
640	640	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Knockamany Malin	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
641	641	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Largymore, Kilcar	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
642	642	SHIP CONSTRUCTION	Donegal	Meadow Hill, Raphoe	11	*N/A	""	""	""	""	Q3-2020	""
643	643	SHIP CONSTRUCTION	Donegal	Radharc na Tra Breige, Malin (Phase 3)	8	*N/A	""	""	""	""	""	Q4-2019
644	644	SHIP CONSTRUCTION	Donegal	Cois Abhainn, St Johnston (Phase 2)	6	*N/A	""	""	""	""	""	Q4-2020
645	645	SHIP CONSTRUCTION	Donegal	Emerald Drive, Killybegs (Phase 6)	9	*N/A	""	""	""	""	""	Q4-2019
646	646	SHIP CONSTRUCTION	Donegal	Long Lane, Letterkenny	29	*N/A	""	""	""	""	""	Q2-2021
647	647	SHIP CONSTRUCTION	Donegal	Rockytown, Buncrana (Phase 1)	21	*N/A	""	""	""	""	Q4-2019	""
648	648	SHIP CONSTRUCTION	Donegal	Manorcunningham (Phase 2)	8	*N/A	""	""	""	""	""	Q4-2018
649	649	SHIP CONSTRUCTION	Donegal	Abbots Wood, Carndonagh (Ph 2)	4	*N/A	""	""	""	""	""	Q4-2018
650	650	SHIP CONSTRUCTION	Donegal	Pound Street, Dunfanaghy	4	*N/A	""	""	""	""	Q3-2020	""
651	651	SHIP CONSTRUCTION	Donegal	Ardara (Phase 3)	8	*N/A	""	""	""	""	""	Q2-2017
652	652	SHIP CONSTRUCTION	Donegal	Newtoncunningham	7	*N/A	""	""	""	""	""	Q4-2018
653	653	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A	""	""	""	""	""	Q2-2021
654	654	SHIP CONSTRUCTION	Donegal	Ard Connell, Ardara (SRD)	1	*N/A	""	""	""	""	""	Q1-2017
655	655	SHIP CONSTRUCTION	Donegal	Manorcunningham (Phase 1)	2	*N/A	""	""	""	""	""	Q2-2017
656	656	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
657	657	SHIP CONSTRUCTION	Donegal	Trusk Road, Ballybofey	19	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
658	658	SHIP CONSTRUCTION	Donegal	Crana Crescent, Buncrana	16	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
659	659	SHIP CONSTRUCTION	Donegal	Drumacrin, Bundoran	42	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
660	660	SHIP CONSTRUCTION	Donegal	Gallow's Lane, Lifford	29	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
661	661	SHIP CONSTRUCTION	Donegal	Chapel Road, Dungloe	45	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
662	662	SHIP CONSTRUCTION	Donegal	Kilmacrennan, Letterkenny	34	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
663	663	CAS CONSTRUCTION TURNKEY	Donegal	Ballaghderg, Letterkenny	14	Respond	""	""	""	""	""	Q4-2020
664	664	CAS CONSTRUCTION	Donegal	Glenrowan House, Drumkeen, Stranorlar	5	Apex Housing Association	""	""	""	""	Q4-2020	""
665	665	CAS CONSTRUCTION	Donegal	Cois Locha, Meenmore, Dungloe	15	County Donegal Parents and Friends Housing Association Ltd	""	""	""	""	Q3-2020	""
666	666	CAS CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	10	Oaklee Housing Trust	""	""	""	""	""	Q4-2020
667	667	CAS CONSTRUCTION	Donegal	Dunshenny House, Derry Road, Carndonagh	5	Apex Housing Association	""	""	""	""	""	Q2-2018
668	668	CAS CONSTRUCTION	Donegal	Raphoe Road, Castlefinn	34	Habinteg Housing Association (Ireland) Ltd	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
669	669	CALF Turnkey	Donegal	Ard na Gréine, Glencar Scotch, Letterkenny, Co. Donegal  (Phase 1)*	18	Clúid Housing	""	""	""	""	Q2-2021	""
670	670	CALF Turnkey	Donegal	Ballaghderg, Letterkenny, Co Donegal  (Phase 1)*	33	Respond	""	""	""	""	""	Q1-2021
671	671	CALF Turnkey	Donegal	Forge Road, Donegal (Phase 1)	4	Clúid Housing	""	""	""	""	""	Q3-2016
672	672	CALF Construction	Donegal	Post Tender - Ernedale Ballyshannon (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q4-2018
673	673	SHIP CONSTRUCTION TURNKEY	Dublin City	Prospect Hill	58	*N/A	""	""	""	""	""	Q4-2017
674	674	SHIP CONSTRUCTION TURNKEY	Dublin City	Parkside, Balgriffin, Dublin 13	16	*N/A	""	""	""	""	""	Q4-2018
675	675	SHIP CONSTRUCTION TURNKEY	Dublin City	Hampton Wood, Finglas	47	*N/A	""	""	""	""	""	Q4-2018
676	676	SHIP CONSTRUCTION TURNKEY	Dublin City	Hampton Wood, Finglas	45	*N/A	""	""	""	""	""	Q4-2019
677	677	SHIP CONSTRUCTION TURNKEY	Dublin City	88-89 Drimnagh Road Dublin 12	24	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
678	678	SHIP CONSTRUCTION TURNKEY	Dublin City	St. Pancras, Harolds Cross, Dublin 6	4	*N/A	""	""	""	""	""	Q2-2021
679	679	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Belcamp B, Dublin 17	12	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
680	680	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Bunratty Road	78	*N/A	""	""	""	""	Q4-2019	""
681	681	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Bonham Street Dublin  8 	57	*N/A	""	""	""	""	Q4-2019	""
682	682	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Cork Street/Chamber Street Dublin 8	55	*N/A	""	""	""	""	Q1-2020	""
683	683	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Springvale Chapelizod Dublin 8	71	*N/A	""	""	""	""	Q1-2020	""
684	684	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Cromcastle & Woodville, Coolock, Dublin 5	156	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.	""	""	""	""	""
685	685	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	Crumlin Road - Rafters Lane, Dublin 12	47	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
686	686	SHIP CONSTRUCTION RAPID VOLUMETRIC	Dublin City	St. Andrews Court, Dublin 2	37	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
687	687	SHIP CONSTRUCTION RAPID	Dublin City	Belcamp H, Dublin 17	38	*N/A	""	""	""	""	""	Q4-2017
688	688	SHIP CONSTRUCTION RAPID	Dublin City	Cherry Orchard, Ballyfermot	24	*N/A	""	""	""	""	""	Q4-2017
689	689	SHIP CONSTRUCTION RAPID	Dublin City	Mourne Road, Drimnagh	29	*N/A	""	""	""	""	""	Q4-2017
690	690	SHIP CONSTRUCTION RAPID	Dublin City	St Helena's Drive, Finglas	39	*N/A	""	""	""	""	""	Q3-2017
691	691	SHIP CONSTRUCTION RAPID	Dublin City	Poppintree, Ballymun	22	*N/A	""	""	""	""	""	Q2-2016
692	692	SHIP CONSTRUCTION RAPID	Dublin City	Rapids at Ballyfermot, Rathvilly, Woodbank Drive	53	*N/A	""	""	""	""	""	Q4-2018
693	693	SHIP CONSTRUCTION RAPID	Dublin City	Rapids at Ballyfermot, Rathvilly, Woodbank Drive	13	*N/A	""	""	""	""	""	Q3-2018
694	694	SHIP CONSTRUCTION RAPID	Dublin City	Rapids at Ballyfermot, Rathvilly, Woodbank Drive	3	*N/A	""	""	""	""	""	Q3-2018
695	695	SHIP CONSTRUCTION RAPID	Dublin City	Rapids at Ballyfermot, Rathvilly, Woodbank Drive	19	*N/A	""	""	""	""	""	Q4-2019
696	696	SHIP CONSTRUCTION	Dublin City	Hampton Wood	25	*N/A	""	""	""	""	""	Q4-2016
697	697	SHIP CONSTRUCTION	Dublin City	Cornamona, Ballyfermot, Dublin 12	61	*N/A	""	""	""	""	Q2-2019	""
698	698	SHIP CONSTRUCTION	Dublin City	Infirmary Road, Dublin 7	38	*N/A	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
699	699	SHIP CONSTRUCTION	Dublin City	North King Street, - Sean Foster Place, Dublin 7	30	*N/A	""	""	""	""	Q2-2019	""
700	700	SHIP CONSTRUCTION	Dublin City	Ballybough Road, Dublin 1	5	*N/A	""	""	""	""	""	Q4-2018
701	701	SHIP CONSTRUCTION	Dublin City	St. Finbar's Court, Kilkieran Road, Dublin 7	46	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
702	702	SHIP CONSTRUCTION	Dublin City	Dominick Street (East side)	72	*N/A	""	""	""	""	Q1-2018	""
703	703	SHIP CONSTRUCTION	Dublin City	Sackville Avenue Cottages	14	*N/A	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
704	704	SHIP CONSTRUCTION	Dublin City	O'Devaney Gardens - Phase 1A	56	*N/A	""	""	""	""	Q3-2018	""
705	705	SHIP CONSTRUCTION	Dublin City	Priory Hall	9	*N/A	""	""	""	""	""	Q1-2017
706	706	SHIP CONSTRUCTION	Dublin City	Priory Hall	24	*N/A	""	""	""	""	""	Q4-2019
707	707	SHIP CONSTRUCTION	Dublin City	Ballybough Road, Dublin 1	2	*N/A	""	""	""	""	""	Q4-2019
708	708	SHIP CONSTRUCTION	Dublin City	Glin Court, Coolock, Dublin 17	32	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
709	709	SHIP CONSTRUCTION	Dublin City	Kildonan Road	75	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
710	710	SHIP CONSTRUCTION	Dublin City	Lands at Emmet Road	112	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
711	711	SHIP CONSTRUCTION	Dublin City	St. Anne's Court, All Saints Drive, Raheny, Dublin 5	102	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
712	712	REGENERATION	Dublin City	St Teresa's Gardens Margaret Kennedy Road Project	54	*N/A	""	""	""	""	""	Q4-2020
713	713	REGENERATION	Dublin City	Dolphin House, Dublin 8	100	*N/A	""	""	""	""	""	Q3-2018
714	714	REGENERATION	Dublin City	Charlemont	79	*N/A	""	""	""	""	""	Q4-2017
715	715	REGENERATION	Dublin City	Maxwell Road	9	*N/A	""	""	""	""	""	Q2-2016
716	716	REGENERATION	Dublin City	Buttercup, Darndale	19	*N/A	""	""	""	""	""	Q4-2017
717	717	REGENERATION	Dublin City	Buttercup, Darndale	9	*N/A	""	""	""	""	""	Q1-2018
718	718	REGENERATION	Dublin City	Buttercup, Darndale	7	*N/A	""	""	""	""	""	Q2-2018
719	719	REGENERATION	Dublin City	St. Bricins Park	11	*N/A	""	""	""	""	""	Q4-2018
720	720	REGENERATION	Dublin City	Dolphin House Phase 1b	35	*N/A	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
721	721	REGENERATION	Dublin City	Dorset Street, Dublin 7	97	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
722	722	REGENERATION	Dublin City	Matt Talbot Court	92	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
723	723	REGENERATION	Dublin City	Constitution Hill Dublin 7	130	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
724	724	REGENERATION	Dublin City	Pearse House, Sandwith Street Lower, Dublin 2 (Blocks L,M,N &P)	75	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
725	725	REGENERATION	Dublin City	Bluebell Phase 1A	140	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
726	726	REGENERATION	Dublin City	Liberties Cluster Phase 1, School Street, The Liberties, Dublin 8	115	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
727	727	CAS CONSTRUCTION TURNKEY	Dublin City	Block 70, The Plaza, Parkwest, Dublin 12 	43	Túath Housing Association Ltd	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
728	728	CAS CONSTRUCTION TURNKEY	Dublin City	Apartments 1-3, 42 North Strand Road, Dublin 3	3	Peter McVerry Trust Ltd	""	""	""	""	""	Q4-2020
729	729	CAS CONSTRUCTION TURNKEY	Dublin City	5A & 5B Willow Park Crescent	2	Túath Housing Association Ltd	""	""	""	""	""	Q3-2020
730	730	CAS CONSTRUCTION TURNKEY	Dublin City	Abbottstown Avenue, Finglas West, Dublin 11 	4	North ? East Housing Association Ltd	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
731	731	CAS CONSTRUCTION SINGLE STAGE	Dublin City	61 & 63 Rathoath Avenue, Finglas, Dublin 11	6	Arlington Novas Ireland Ltd	""	""	""	""	Q4-2020	""
732	732	CAS CONSTRUCTION SINGLE STAGE	Dublin City	88 Lower Drumcondra Road, Dublin 9 	6	Peter McVerry Trust Ltd	""	""	""	""	Q4-2021	""
733	733	CAS CONSTRUCTION RENEWAL	Dublin City	8 North Frederick Street, Dublin 1	12	Peter McVerry Trust Ltd	""	""	""	""	""	Q4-2021
734	734	CAS CONSTRUCTION	Dublin City	Beech Hill	19	Royal Hospital Donnybrook Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2018
735	735	CAS CONSTRUCTION	Dublin City	Ellis Court, Dublin	22	Túath Housing Association Ltd	""	""	""	""	Q3-2019	""
736	736	CAS CONSTRUCTION	Dublin City	Martanna House, High Park, Grace Park Road,Dublin 9	8	Respond	""	""	""	""	""	Q4-2018
737	737	CAS CONSTRUCTION	Dublin City	1 - 2 Rafter's Lane, Dublin 12	11	Walkinston Housing Association Ltd (WALK)	""	""	""	""	""	Q4-2019
738	738	CAS CONSTRUCTION	Dublin City	180-187 Townsend Street, Dublin 2	20	Peter McVerry Trust Ltd	""	""	Stage 3 approved Q4-2018, the scheme is now approved to proceed to tender.	""	""	""
739	739	CAS CONSTRUCTION	Dublin City	26 New Street South, Dublin 8	8	Peter McVerry Trust Ltd	""	""	""	""	""	Q1-2021
740	740	CAS CONSTRUCTION	Dublin City	Broome Lodge, Dunmanus, Dublin 7	10	Cluid Housing Association	""	""	""	""	""	Q4-2017
741	741	CAS CONSTRUCTION	Dublin City	St Agatha's Court, North William Street, Dublin 1	11	Peter McVerry Trust Ltd	""	""	""	""	""	Q2-2017
742	742	CAS CONSTRUCTION	Dublin City	55B Arbour Hill, Dublin 7	14	Simon Community : Dublin Simon	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
743	743	CAS CONSTRUCTION	Dublin City	St. Michael's Estate, Inchicore, Dublin 8 - Housing Pilot Project 	52	Circle Voluntary Housing Association Ltd	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
744	744	CAS CONSTRUCTION	Dublin City	Shaw Street, Dublin 2	12	Peter McVerry Trust Ltd	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
745	745	CAS CONSTRUCTION	Dublin City	13A Casement Drive, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd	""	""	""	""	Q4-2021	""
746	746	CAS CONSTRUCTION	Dublin City	Sarsfield Road, Ballyfermot, Dublin 10	6	Respond	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
747	747	CAS CONSTRUCTION	Dublin City	25-26 Ushers Island Ushers Quay Dublin 8	0	Simon Community : Dublin Simon	""	""	""	""	Q4-2021	""
748	748	CAS CONSTRUCTION	Dublin City	53a Keeper Road, Drimnagh, Dublin 12	9	Respond	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
749	749	CAS CONSTRUCTION	Dublin City	Barnamore Grove, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
750	750	CAS CONSTRUCTION	Dublin City	Berryfield Drive, Finglas, Dublin 11	10	Arlington Novas Ireland Ltd	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
751	751	CAS CONSTRUCTION	Dublin City	5-7 Halston Street, Dublin 7	12	Peter McVerry Trust Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
752	752	CAS CONSTRUCTION	Dublin City	307a Casement Road, Finglas, Dublin 11	1	Arlington Novas Ireland Ltd	""	Stage 2 approved Q3-2019, full design/tender being prepared.	""	""	""	""
753	753	CALF Turnkey	Dublin City	25-27 Bow Lane West, Dublin 8 (Phase 1)	27	Focus Housing Association CLG	""	""	""	Q1-2022	""	""
754	754	CALF Construction	Dublin City	3 units, Block A Jamestown Court, Dublin 8 (Phase 1)	3	ALONE	""	""	""	""	""	Q4-2020
755	755	CALF Turnkey	Dublin City	9 units Dorset Street, Dublin 1 (Phase 1)	9	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2020
756	756	CALF Turnkey	Dublin City	An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 1)	14	Tuath Housing Association	""	""	""	""	""	Q4-2016
757	757	CALF Turnkey	Dublin City	An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 2)	21	Tuath Housing Association	""	""	""	""	""	Q1-2017
758	758	CALF Turnkey	Dublin City	An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 3)	10	Tuath Housing Association	""	""	""	""	""	Q2-2017
759	759	CALF Turnkey	Dublin City	An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 4)	3	Tuath Housing Association	""	""	""	""	""	Q3-2017
760	760	CALF Turnkey	Dublin City	An Riasc, Finglas, Phase 1,2,3 and 4 (Phase 5)	1	Tuath Housing Association	""	""	""	""	""	Q4-2018
761	761	CALF Construction	Dublin City	Annamore Court, Ballyfermot (Phase 1)	70	The Iveagh Trust	""	""	""	""	""	Q2-2017
762	762	CALF Turnkey	Dublin City	Aughrim Street, Stoneybatter, Dublin 7 (Phase 1)	4	Clanmil Housing Association Ireland	""	""	""	""	""	Q2-2021
763	763	CALF Turnkey	Dublin City	Balfe Road, Crumlin, Dublin 12 (Phase 1)*	16	Respond	""	""	""	""	""	Q4-2018
764	764	CALF Construction	Dublin City	 Ballygall Road East Phase 2 (Phase 1)	11	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q1-2016
765	765	CALF Construction	Dublin City	Bethany House, Gilford Road, Sandymount, Dublin 4 (Phase 1)	62	Clúid Housing	""	""	""	""	Q4-2021	""
766	766	CALF Turnkey	Dublin City	Blackbanks View, 754 Howth Road, Raheny, Dublin 5 (Phase 1)*	40	Clúid Housing	""	""	""	""	""	Q1-2021
767	767	CALF Turnkey	Dublin City	Block A Northbank, Castleforbes, Dublin 1  (Phase 1)*	26	Tuath Housing Association	""	""	""	""	""	Q2-2018
768	768	CALF Construction	Dublin City	Block A, Jamestown Court, Dublin 8 (Phase 1)	9	ALONE	""	""	""	""	""	Q4-2020
769	769	CALF Turnkey	Dublin City	Bluebell Avenue, Bluebell, Dublin 12 (Phase 1)*	52	Respond	""	""	""	""	Q4-2019	""
770	770	CALF Turnkey	Dublin City	Bluebell Avenue, Dublin 12 (Phase 1)	7	Tuath Housing Association	""	""	""	""	""	Q4-2018
771	771	CALF Construction	Dublin City	"Broome Lodge,
Dunmanus Court, Cabra (Phase 1)"	33	Clúid Housing	""	""	""	""	""	Q4-2017
772	772	CALF Turnkey	Dublin City	Camac Park, Bluebell, Dublin 12 (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q2-2020
773	773	CALF Turnkey	Dublin City	Camac Park, Bluebell, Dublin 12 (Phase 1)	3	Tuath Housing Association	""	""	""	""	""	Q4-2021
774	774	CALF Turnkey	Dublin City	Canal Meadows, Bluebell, Dublin 12 (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q1-2019
775	775	CALF Turnkey	Dublin City	Chanel College, Coolock Village, Malahide Road, Dublin 5  (Phase 1)*	16	Respond	""	""	""	""	""	Q4-2017
776	776	CALF Turnkey	Dublin City	Chanel Manor Apartments, Coolock, Dublin 5. (Phase 1)*	65	Respond	""	""	""	""	Q2-2019	""
777	777	CALF Turnkey	Dublin City	Chanel Manor, Coolock, Dublin 5 (Phase 1)*	22	Respond	""	""	""	""	Q4-2020	""
778	778	CALF Turnkey	Dublin City	Clongriffin, Dublin 13 (Phase 1)*	84	The Iveagh Trust	""	""	""	""	""	Q2-2019
779	779	CALF Turnkey	Dublin City	Connaught Street, Phibsborough, Dublin 7 (Phase 1)	20	Focus Housing Association CLG	""	""	""	""	Q2-2021	""
780	780	CALF Turnkey	Dublin City	Cromwellsfort Court, Cromwellsfort Road, Walkinstown, Dublin 12 (Phase 1)*	12	Oaklee Housing	""	""	""	""	""	Q3-2020
781	781	CALF Turnkey	Dublin City	Crumlin Village, Dublin 12 (Phase 1)	3	Clúid Housing	""	""	""	""	""	Q2-2017
782	782	CALF Turnkey	Dublin City	Crumlin Village, Dublin 12 (Phase 2)	2	Clúid Housing	""	""	""	""	""	Q3-2017
783	783	CALF Construction	Dublin City	Dolphin Park, Rialto, Dublin 8 (Phase 1)	43	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2019
784	784	CALF Turnkey	Dublin City	Donnybrook Gardens, Lands of Greenfield Park, Donnybrook, Dublin 4 (Phase 1)*	4	RHD Housing	""	""	""	""	""	Q2-2021
785	785	CALF Turnkey	Dublin City	Elanora Court, Long Mile Road, Walkinstown, Dublin 12 (Phase 1)*	153	Respond	""	""	""	""	Q3-2020	""
786	786	CALF Construction	Dublin City	Harolds Cross, Dublin 6 (Phase 1)	28	Focus Housing Association CLG	""	""	""	""	""	Q4-2016
787	787	CALF Turnkey	Dublin City	Lough Conn Road, Ballyfermot, Dublin 10 (Phase 1)	1	Tuath Housing Association	""	""	""	""	""	Q4-2019
788	788	CALF Turnkey	Dublin City	Lough Conn Road, Ballyfermot, Dublin 10 (Phase 2)	4	Tuath Housing Association	""	""	""	""	""	Q4-2020
789	789	CALF Turnkey	Dublin City	Merville Court, Merville Avenue, Fairview (Phase 1)	5	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2017
790	790	CALF Turnkey	Dublin City	Millrose House, Bluebell Avenue, Dublin 12 (Phase 1)	8	Clúid Housing	""	""	""	""	""	Q4-2017
791	791	CALF Turnkey	Dublin City	Mountjoy Square North, Dublin 1 (Phase 1)	31	Respond	""	""	""	""	""	Q4-2019
792	792	CALF Turnkey	Dublin City	Newtown Cottages Malahide Road Coolock Dublin 17 (Phase 1)	3	Clanmil Housing Association Ireland	""	""	""	""	Q3-2020	""
793	793	CALF Construction	Dublin City	North Great Charles Street, Dublin 1 (Phase 1)	52	Clúid Housing	""	""	""	Q4-2021	""	""
794	794	CALF Construction	Dublin City	North King Street, Dublin 7  (Phase 1)	30	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2019	""
795	795	CALF Turnkey	Dublin City	Old School House Lane, Magenta Crescent, Santry, Dublin 9 (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q4-2019
796	796	CALF Construction	Dublin City	Orchard Lawns, Ballyfermot (Phase 1)	36	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2018
797	797	CALF Construction	Dublin City	Orchard Lawns, Ballyfermot (Phase 2)	36	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
798	798	CALF Turnkey	Dublin City	Park West Campus, Kileen Road, Dublin 12 (Phase 1)	41	Tuath Housing Association	""	""	""	""	Q4-2020	""
799	799	CALF Construction	Dublin City	Post Tender - Wad River Close Phase 2, Ballymun, Dublin 9  (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q4-2019
800	800	CALF Construction	Dublin City	Post Tender Johns Lane West Dublin 8 (Phase 1)	31	Focus Housing Association CLG	""	""	""	""	""	Q4-2018
801	801	CALF Construction	Dublin City	POST TENDER, Poplar Row, Ballybough, Dublin 3 (Phase 1)	29	Oaklee Housing	""	""	""	""	""	Q4-2019
802	802	CALF Turnkey	Dublin City	Ravensdale Court, Kimmage, Dublin 12. (Phase 1)	12	Tuath Housing Association	""	""	""	""	Q4-2020	""
803	803	CALF Construction	Dublin City	Revised - Dominic Place, Dublin (Phase 1)	9	The Paddy McGrath Housing Project	""	""	""	""	""	Q3-2020
804	804	CALF Construction	Dublin City	Revised Post Tender - Raleigh Square, Crumlin (Phase 1)	33	Tuath Housing Association	""	""	""	""	""	Q4-2019
805	805	CALF Construction	Dublin City	Revised, St Mary’s Mansions, Dublin 1 (Phase 1)	80	Clúid Housing	""	""	""	""	""	Q4-2019
806	806	CALF Construction	Dublin City	Richmond Road, Dublin 9 (Phase 1)	40	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
807	807	CALF Turnkey	Dublin City	Royal Canal Crescent, Rathborne Park, Rathborne, Dublin15 (Phase 1)*	16	Clúid Housing	""	""	""	""	""	Q4-2020
808	808	CALF Turnkey	Dublin City	Royal Canal Park, Ashtown, Dublin 15 (Phase 1)*	46	Respond	""	""	""	""	""	Q4-2020
809	809	CALF Construction	Dublin City	Sean Mc Dermott Street, Dublin 1 (Phase 1)	8	Simon Community: Dublin Simon	""	""	""	Q1-2022	""	""
810	810	CALF Turnkey	Dublin City	St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)	44	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2019
811	811	CALF Turnkey	Dublin City	St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 1)	6	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2020
812	812	CALF Turnkey	Dublin City	St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 2)	42	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q2-2020
813	813	CALF Turnkey	Dublin City	St Agnes Convent, Armagh Road, Crumlin, Dublin 12 (Phase 3)	11	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2020
814	814	CALF Turnkey	Dublin City	St Canice’s Hall, Ballygall Road West, Finglas, Dublin 11 (Phase 1)*	32	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
815	815	CALF Turnkey	Dublin City	Stormanstown Hall, Ballymun Road, (revised) (Phase 1)	42	Oaklee Housing	""	""	""	""	""	Q3-2018
816	816	CALF Turnkey	Dublin City	Sundrive Mews, Kimmage, Dublin 12 (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q4-2019
817	817	CALF Turnkey	Dublin City	Thornwood, Beaumont (Phase 1)	28	Tuath Housing Association	""	""	""	""	""	Q2-2016
818	818	CALF Turnkey	Dublin City	Thornwood, Beaumont (Phase 2)	18	Tuath Housing Association	""	""	""	""	""	Q4-2016
819	819	CALF Turnkey	Dublin City	Thornwood, Beaumont (Phase 3)	14	Tuath Housing Association	""	""	""	""	""	Q1-2017
820	820	CALF Turnkey	Dublin City	Thornwood, Beaumont (Phase 4)	8	Tuath Housing Association	""	""	""	""	""	Q1-2017
821	821	CALF Turnkey	Dublin City	Tonlegee Road, Dublin 5  (Phase 1)	47	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2018
822	822	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Dublin City	Ayrfield, Malahide Road	150	*N/A	""	""	""	""	""	Q2-2021
823	823	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Dublin City	Scribblestown	70	*N/A	""	""	""	""	""	Q4-2020
824	824	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Ready Mix Site, East Wall, Dublin 3	68	*N/A	""	Q4-2021	""	""	""	""
825	825	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Shangan Road, Ballymun, Dublin 9*	93	*N/A	""	Q4-2021	""	""	""	""
826	826	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Collins Avenue, Whitehall, Dublin 9	83	*N/A	""	Q4-2021	""	""	""	""
827	827	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
828	828	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
829	829	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
830	830	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
831	831	SHIP CONSTRUCTION TURNKEY	Fingal	Blackmills Grove, Blakestown Road, Mulhuddard	10	*N/A	""	""	""	""	""	Q2-2017
832	832	SHIP CONSTRUCTION TURNKEY	Fingal	Balgriffin Grove, Malahide Road, Balgriffin	6	*N/A	""	""	""	""	""	Q1-2017
833	833	SHIP CONSTRUCTION TURNKEY	Fingal	Hansfield, Ongar, Dublin 15	36	*N/A	""	""	""	""	""	Q3-2017
834	834	SHIP CONSTRUCTION TURNKEY	Fingal	Hansfield, Ongar, Dublin 15	16	*N/A	""	""	""	""	""	Q1-2018
835	835	SHIP CONSTRUCTION TURNKEY	Fingal	Hansfield, Ongar, Dublin 15	16	*N/A	""	""	""	""	""	Q2-2018
836	836	SHIP CONSTRUCTION TURNKEY	Fingal	Ravenswood, North Road, Finglas	2	Peter McVerry Trust Ltd	""	""	""	""	""	Q4-2018
837	837	SHIP CONSTRUCTION TURNKEY	Fingal	Boroimhe, Swords	6	*N/A	""	""	""	""	""	Q3-2018
838	838	SHIP CONSTRUCTION TURNKEY	Fingal	Cnoc Dubh, Ballyboughal	6	*N/A	""	""	""	""	""	Q4-2018
839	839	SHIP CONSTRUCTION TURNKEY	Fingal	Kenure Gate, Park Road, Rush	4	*N/A	""	""	""	""	""	Q4-2018
840	840	SHIP CONSTRUCTION TURNKEY	Fingal	Glaslinn, Donabate	3	*N/A	""	""	""	""	""	Q4-2018
841	841	SHIP CONSTRUCTION TURNKEY	Fingal	Bremore Pastures Park, Balbriggan	4	*N/A	""	""	""	""	""	Q4-2018
842	842	SHIP CONSTRUCTION TURNKEY	Fingal	Northwood Green, Santry, Dublin 9	37	*N/A	""	""	""	""	""	Q4-2018
843	843	SHIP CONSTRUCTION TURNKEY	Fingal	Hollytown Cottages	4	*N/A	""	""	""	""	""	Q4-2019
844	844	SHIP CONSTRUCTION TURNKEY	Fingal	Cnoc Dubh Ballyboughal Co. Dublin	5	*N/A	""	""	""	""	""	Q3-2019
845	845	SHIP CONSTRUCTION TURNKEY	Fingal	Rahillion, Donabate	1	*N/A	""	""	""	""	""	Q4-2019
846	846	SHIP CONSTRUCTION TURNKEY	Fingal	Bay Meadows Avenue/Square, Hollystown Dublin 15	12	*N/A	""	""	""	""	""	Q4-2020
847	847	SHIP CONSTRUCTION TURNKEY	Fingal	Bay Meadows, Hollystown, Dublin 15	10	*N/A	""	""	""	""	""	Q3-2020
848	848	SHIP CONSTRUCTION TURNKEY	Fingal	Killhedge Lane, Dun Emer, Lusk	7	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
849	849	SHIP CONSTRUCTION SINGLE STAGE	Fingal	Outlands, Rathbeale Road, Swords	11	*N/A	""	""	""	Stage 4 approved Q3-2019, the scheme is fully approved.	""	""
850	850	SHIP CONSTRUCTION RAPID	Fingal	Avondale, Mulhuddart, Dublin 15	42	*N/A	""	""	""	""	""	Q4-2019
851	851	SHIP CONSTRUCTION RAPID	Fingal	Pinewood, Balbriggan	20	*N/A	""	""	""	""	""	Q2-2018
852	852	SHIP CONSTRUCTION RAPID	Fingal	Wellview, Mulhuddart	20	*N/A	""	""	""	""	""	Q4-2017
853	853	SHIP CONSTRUCTION RAPID	Fingal	Church Road, Mulhuddart, Dublin 15	22	*N/A	""	""	""	""	""	Q4-2019
854	854	SHIP CONSTRUCTION RAPID	Fingal	Church Fields, Phase 2B, Mulhuddart, Dublin 15.	67	*N/A	""	""	""	""	Q4-2021	""
855	855	SHIP CONSTRUCTION	Fingal	Rivermeade, St. Margarets	2	*N/A	""	""	""	""	""	Q2-2019
856	856	SHIP CONSTRUCTION	Fingal	Rowlestown	10	*N/A	""	""	""	""	""	Q2-2019
857	857	SHIP CONSTRUCTION	Fingal	Racecourse Commons, Lusk	5	*N/A	""	""	""	""	""	Q2-2018
858	858	SHIP CONSTRUCTION	Fingal	Castlelands, Park View, Balbriggan (Phase 3)	24	*N/A	""	""	""	""	""	Q1-2019
859	859	SHIP CONSTRUCTION	Fingal	Rathbeale Road, Swords	24	*N/A	""	""	""	""	""	Q2-2020
860	860	SHIP CONSTRUCTION	Fingal	The Grange, Ballyboughal	2	*N/A	""	""	""	""	""	Q3-2017
861	861	SHIP CONSTRUCTION	Fingal	Cappaghfinn (Phase 1)	14	*N/A	""	""	""	""	""	Q2-2016
862	862	SHIP CONSTRUCTION	Fingal	St. Cronan's Green, Swords	14	*N/A	""	""	""	""	""	Q2-2016
863	863	SHIP CONSTRUCTION	Fingal	St. Cronan's Cottages, Swords - Infill	1	*N/A	""	""	""	""	""	Q2-2016
864	864	SHIP CONSTRUCTION	Fingal	Racecourse Commons, Lusk	25	*N/A	""	""	""	""	""	Q4-2017
865	865	SHIP CONSTRUCTION	Fingal	The Grange, Ballyboughal	6	*N/A	""	""	""	""	""	Q4-2018
866	866	SHIP CONSTRUCTION	Fingal	Racecourse Commons, Lusk	15	*N/A	""	""	""	""	""	Q1-2018
867	867	SHIP CONSTRUCTION	Fingal	Redevelopment of Community Centre, Pinewood, Balbriggan	2	*N/A	""	""	""	""	""	Q3-2019
868	868	SHIP CONSTRUCTION	Fingal	Racecourse Commons, Lusk	4	*N/A	""	""	""	""	""	Q3-2018
869	869	SHIP CONSTRUCTION	Fingal	Racecourse Commons, Lusk	25	*N/A	""	""	""	""	""	Q4-2018
870	870	SHIP CONSTRUCTION	Fingal	Tucketts Lane, Howth	8	*N/A	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
871	871	SHIP CONSTRUCTION	Fingal	Wellview	20	*N/A	""	""	""	""	Q3-2020	""
872	872	SHIP CONSTRUCTION	Fingal	Rowlestown	6	*N/A	""	""	""	""	""	Q4-2019
873	873	SHIP CONSTRUCTION	Fingal	Rowlestown	6	*N/A	""	""	""	""	""	Q4-2019
874	874	SHIP CONSTRUCTION	Fingal	Cappaghfinn, Cappagh Road Finglas - Phase 3	69	*N/A	""	""	""	""	Q1-2021	""
875	875	SHIP CONSTRUCTION	Fingal	Rowlestown	4	*N/A	""	""	""	""	""	Q3-2019
876	876	SHIP CONSTRUCTION	Fingal	Leonards Garage, Lusk	10	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
877	877	SHIP CONSTRUCTION	Fingal	Katie Hunt's Cottage, Church Road, Lusk	5	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
878	878	SHIP CONSTRUCTION	Fingal	North Street, Swords	8	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
879	879	CAS CONSTRUCTION	Fingal	Killhedge Lane Dun Emer	31	Túath Housing Association Ltd	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
880	880	CAS CONSTRUCTION	Fingal	Ravenswood, North Road, Finglas	6	Peter McVerry Trust Ltd	""	""	""	""	""	Q4-2018
881	881	CAS CONSTRUCTION	Fingal	22 College Street, Baldoyle	4	Cluid Housing Association	""	""	""	""	""	Q4-2021
882	882	CAS CONSTRUCTION	Fingal	Darcystown, Ringfort, Balrothery	9	North ? East Housing Association Ltd	""	""	""	""	""	Q3-2017
883	883	CAS CONSTRUCTION	Fingal	Estuary Road, Malahide	8	Society of Saint Vincent de Paul	""	""	""	""	""	Q2-2018
884	884	CAS CONSTRUCTION	Fingal	Garristown	6	North ? East Housing Association Ltd	""	""	""	""	Q3-2021	""
885	885	CAS CONSTRUCTION	Fingal	63 Hollystown Park, Holystown, Dublin 15	5	Daughters Of Charity Of St Vincent De Paul	""	""	""	""	""	Q4-2021
886	886	CALF Turnkey	Fingal	4 units, Taylor Hill, Balbriggan, Co. Dublin (Phase 1)	4	Clúid Housing	""	""	""	""	""	Q4-2018
887	887	CALF Turnkey	Fingal	Allendale Square, Clonsilla, Dublin 15 (Phase 1)*	28	Respond	""	""	""	""	""	Q2-2020
888	888	CALF Turnkey	Fingal	An Muileann, Kettles Lane, Swords, Dublin (Phase 1)	24	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2019
889	889	CALF Turnkey	Fingal	Barnwell Woods, Hansfield, Dublin 15 (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2018
890	890	CALF Turnkey	Fingal	Barnwell Woods, Hansfield, Dublin 15 (Phase 2)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2018
891	891	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dubin 15 (Phase 1)	29	Tuath Housing Association	""	""	""	""	""	Q4-2020
892	892	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dubin 15 (Phase 2)	12	Tuath Housing Association	""	""	""	""	""	Q4-2020
893	893	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 1)*	17	Tuath Housing Association	""	""	""	""	""	Q2-2021
894	894	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 2)	21	Tuath Housing Association	""	""	""	""	""	Q4-2021
895	895	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 1)*	36	Tuath Housing Association	""	""	""	""	Q3-2020	""
896	896	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 2)*	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
897	897	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 1)*	29	Respond	""	""	""	""	""	Q2-2021
898	898	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 2)*	30	Respond	""	""	""	""	""	Q4-2021
899	899	CALF Turnkey	Fingal	Castlegrange Park (2) Clonsilla (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q2-2016
900	900	CALF Turnkey	Fingal	Castlegrange Park (2) Clonsilla (Phase 2)	7	Tuath Housing Association	""	""	""	""	""	Q3-2016
901	901	CALF Turnkey	Fingal	Castlegrange Park (2) Clonsilla (Phase 3)	7	Tuath Housing Association	""	""	""	""	""	Q4-2016
902	902	CALF Turnkey	Fingal	Castlegrange Park (2) Clonsilla (Phase 4)	21	Tuath Housing Association	""	""	""	""	""	Q1-2017
903	903	CALF Turnkey	Fingal	Castlegrange Park (2) Clonsilla (Phase 5)	8	Tuath Housing Association	""	""	""	""	""	Q2-2017
904	904	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 1)*	90	Respond	""	""	""	""	""	Q4-2021
905	905	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 2)*	48	Respond	""	""	""	""	""	Q4-2021
906	906	CALF Turnkey	Fingal	Cois Sruthan, Ballyboughal, Co.Dublin (Phase 1)*	17	Oaklee Housing	""	""	""	""	""	Q3-2020
907	907	CALF Turnkey	Fingal	Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q4-2019
908	908	CALF Turnkey	Fingal	Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 2)*	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
909	909	CALF Turnkey	Fingal	"Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin

 (Phase 1)*"	10	Clúid Housing	""	""	""	""	""	Q2-2020
910	910	CALF Turnkey	Fingal	"Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin

 (Phase 2)*"	5	Clúid Housing	""	""	""	""	""	Q4-2020
911	911	CALF Turnkey	Fingal	Dunsoghly, Dublin 11 (Phase 1)*	19	Clúid Housing	""	""	""	""	""	Q4-2020
912	912	CALF Turnkey	Fingal	Knightsgate, Rush, Co. Dublin (Phase 1)*	38	Clúid Housing	""	""	""	""	""	Q4-2019
913	913	CALF Turnkey	Fingal	Knightsgate, Rush, Co. Dublin (phase 2) (Phase 1)	19	Clúid Housing	""	""	""	""	""	Q3-2020
914	914	CALF Construction	Fingal	Ladyswell Road & Church Road, Mulhuddart, Dublin 15  (Phase 1)	65	Clúid Housing	""	""	""	""	""	Q4-2021
915	915	CALF Turnkey	Fingal	Lanesborough Close, Finglas, Dublin 11 (Phase 1)*	21	Clúid Housing	""	""	""	""	""	Q4-2018
916	916	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 1)*	14	Clúid Housing	""	""	""	""	""	Q4-2021
917	917	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 2)*	4	Clúid Housing	""	""	""	""	Q3-2020	""
918	918	CALF Turnkey	Fingal	Martello Place, Balbriggan, Co Dublin  (Phase 1)	18	Respond	""	""	""	""	""	Q3-2018
919	919	CALF Turnkey	Fingal	Millers Glen, Oldtown, Swords, Co. Dublin (Phase 1)*	28	The Iveagh Trust	""	""	""	""	""	Q4-2020
920	920	CALF Turnkey	Fingal	Millers Glen, Phase 3, Oldtown, Swords (Phase 1)*	14	The Iveagh Trust	""	""	""	""	""	Q4-2019
921	921	CALF Turnkey	Fingal	Norseman's Court, Norseman's Walk, Lusk Village, Lusk, Co. Dublin (Phase 1)*	18	Clúid Housing	""	""	""	""	""	Q4-2020
922	922	CALF Turnkey	Fingal	Northwood Green, Santry, Dublin 9 (Phase 1)*	6	Respond	""	""	""	""	""	Q4-2018
923	923	CALF Turnkey	Fingal	Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 1)	48	Respond	""	""	""	""	""	Q4-2019
924	924	CALF Turnkey	Fingal	Northwood, Ballymun Cross, Santry, Dublin 9 (Phase 2)*	7	Respond	""	""	""	""	""	Q2-2020
925	925	CALF Construction	Fingal	Old Coolock Lane, Santry, Dublin 9 (Phase 1)	28	Circle Voluntary Housing Association Ltd	""	""	""	Q1-2019	""	""
926	926	CALF Turnkey	Fingal	Old Corduff Road, Blanchardstown, Dublin 15 (Phase 1)	17	Respond	""	""	""	""	""	Q4-2020
927	927	CALF Turnkey	Fingal	Old Corduff Road, Blanchardstown, Dublin 15 (Phase 2)*	10	Respond	""	""	""	""	""	Q2-2021
928	928	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 1)	30	Respond	""	""	""	Q3-2021	""	""
929	929	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 2)	30	Respond	""	""	""	Q3-2021	""	""
930	930	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 3)	39	Respond	""	""	""	Q3-2021	""	""
931	931	CALF Turnkey	Fingal	Pappan Grove, Northwood, Santry, Dublin 9 (Phase 1)*	35	Tuath Housing Association	""	""	""	""	""	Q3-2019
932	932	CALF Turnkey	Fingal	Phoenix Park Avenue, Castleknock, Dublin 15 (Phase 1)*	31	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2019
933	933	CALF Turnkey	Fingal	Riverwood Square, Porterstown, Dublin 15 (Phase 1)*	24	Clúid Housing	""	""	""	""	""	Q3-2021
934	934	CALF Turnkey	Fingal	Semple Woods, Donabate, Co. Dublin (Phase 1)*	7	Tuath Housing Association	""	""	""	""	""	Q4-2020
935	935	CALF Turnkey	Fingal	Semple Woods, Donabate, Co. Dublin (Phase 2)*	3	Tuath Housing Association	""	""	""	""	Q4-2019	""
936	936	CALF Turnkey	Fingal	Semple Woods, Donabate, North County Dublin (Phase 1)*	30	Tuath Housing Association	""	""	""	""	""	Q4-2019
937	937	CALF Turnkey	Fingal	St Josephs, Clonsilla, Dublin 15 (Phase 1)*	28	Clúid Housing	""	""	""	""	""	Q4-2021
938	938	CALF Turnkey	Fingal	St Marnock’s Bay, Portmarnock, Co Dublin   (Phase 1)*	10	Clúid Housing	""	""	""	""	""	Q4-2017
939	939	CALF Turnkey	Fingal	St Werburghs Court Drynam Rd Swords Co Dublin (Phase 1)*	18	Tuath Housing Association	""	""	""	""	""	Q4-2017
940	940	CALF Turnkey	Fingal	Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 1)*	3	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2019
941	941	CALF Turnkey	Fingal	Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 2)*	8	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2021
942	942	CALF Turnkey	Fingal	Taylor Hill Crescent, Balbriggan, Co. Dublin (Phase 1)	4	Clúid Housing	""	""	""	""	""	Q4-2018
943	943	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)	21	Clúid Housing	""	""	""	""	""	Q2-2020
944	944	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*	31	Clúid Housing	""	""	""	""	""	Q4-2018
945	945	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*	24	Clúid Housing	""	""	""	""	""	Q4-2019
946	946	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*	7	Clúid Housing	""	""	""	""	""	Q4-2021
947	947	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 2)	1	Clúid Housing	""	""	""	""	""	Q4-2020
948	948	CALF Turnkey	Fingal	The Forge, Lusk, Co. Dublin (Phase 1)	8	Oaklee Housing	""	""	""	""	""	Q4-2019
949	949	CALF Turnkey	Fingal	The Hermitage, Balgriffin, Co Dublin  (Phase 1)*	54	Clúid Housing	""	""	""	""	""	Q4-2017
950	950	CALF Turnkey	Fingal	Waterside, Malahide, Dublin (Phase 1)	5	Clúid Housing	""	""	""	""	""	Q4-2020
951	951	CALF Turnkey	Fingal	Weavers Wood, Clonsilla Road, Clonsilla, Dublin 15  (Phase 1)*	33	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2018
952	952	CALF Turnkey	Fingal	Weston, Feltrim Road, Swords, North County Dublin (Phase 1)	24	Oaklee Housing	""	""	""	""	""	Q4-2019
953	953	CALF Turnkey	Fingal	Weston, Feltrim Road, Swords, North County Dublin (Phase 2)*	10	Oaklee Housing	""	""	""	""	""	Q3-2020
954	954	CALF Turnkey	Fingal	 Wrens Hill, (Formerly The Galleries),  Donabate, Co. Dublin (Phase 1)	43	Oaklee Housing	""	""	""	""	""	Q4-2019
955	955	SHIP CONSTRUCTION TURNKEY	Galway City	Radharc na Gréine, (Glasshouse Site) Monivea Road	6	*N/A	""	""	""	""	""	Q3-2019
956	956	SHIP CONSTRUCTION TURNKEY	Galway City	Radharc na Gréine, (Glasshouse Site) Monivea Road	16	*N/A	""	""	""	""	""	Q4-2019
957	957	SHIP CONSTRUCTION TURNKEY	Galway City	Radharc na Gréine, (Glasshouse Site) Monivea Road	7	*N/A	""	""	""	""	""	Q4-2019
958	958	SHIP CONSTRUCTION TURNKEY	Galway City	Radharc na Gréine, (Glasshouse Site) Monivea Road	13	*N/A	""	""	""	""	""	Q3-2020
959	959	SHIP CONSTRUCTION TURNKEY	Galway City	Radharc na Gréine, (Glasshouse Site) Monivea Road	8	*N/A	""	""	""	""	""	Q4-2020
960	960	SHIP CONSTRUCTION TURNKEY	Galway City	Garraí Caol, (Coast Road Site) Dublin Road	26	*N/A	""	""	""	""	Q1-2020	""
961	961	SHIP CONSTRUCTION TURNKEY	Galway City	Garraí Caol, (Coast Road Site) Dublin Road	22	*N/A	""	""	""	""	Q1-2020	""
962	962	SHIP CONSTRUCTION	Galway City	Ard Cré, Ballymoneen Road (Phase 2)	78	*N/A	""	""	""	""	""	Q4-2020
963	963	SHIP CONSTRUCTION	Galway City	Ard Cré, Ballymoneen Road (Phase 1)	14	*N/A	""	""	""	""	""	Q2-2018
964	964	SHIP CONSTRUCTION	Galway City	An Cliathán, Old Monivea Road, Ballybaan Mór	15	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
965	965	SHIP CONSTRUCTION	Galway City	Garraí Beag, Monivea Road, Ballybaan More	58	*N/A	""	""	""	""	Q1-2020	""
966	966	SHIP CONSTRUCTION	Galway City	Headford Road, Castlegar	24	*N/A	Stage 1 approved Q3-2018, outline design and costs being prepared.	""	""	""	""	""
967	967	SHIP CONSTRUCTION	Galway City	Keeraun, Ballymoneen Road	63	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
968	968	SHIP CONSTRUCTION	Galway City	Tirellan Heights, Headford Road	1	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
969	969	SHIP CONSTRUCTION	Galway City	Merlin Park Lands, Galway City	18	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
970	970	SHIP CONSTRUCTION	Galway City	1 Munster Avenue, Galway city	4	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
971	971	CAS CONSTRUCTION	Galway City	97/98 Rockfield	4	Carraig Dubh Housing Association	""	""	""	""	""	Q1-2018
972	972	CAS CONSTRUCTION	Galway City	Cul Garrai, Rahoon	6	Peter Triest Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
973	973	CAS CONSTRUCTION	Galway City	47 Forster Street, Galway City (Domestic Violence Refuge)	9	Cope Galway	""	""	""	""	""	Q4-2019
974	974	CAS CONSTRUCTION	Galway City	Doughiska, Galway City	7	Respond	Stage 1 approved Q2-2019, outline design and costs being prepared.	""	""	""	""	""
975	975	CAS CONSTRUCTION	Galway City	111 Upper Newcastle Road, Galway City	10	Simon Community : North West Simon	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
976	976	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 1)*	52	Respond	""	""	""	""	Q2-2021	""
977	977	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 2)	49	Respond	""	""	""	""	Q2-2021	""
978	978	CALF Turnkey	Galway City	Belmont, Renmore, Galway City (Phase 1)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
979	979	CALF Turnkey	Galway City	Block C, Sraith Fhada, Doughiska, Galway (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q4-2020
980	980	CALF Turnkey	Galway City	Block D, Sraith Fhada, Doughiska, Galway (Phase 1)	14	Tuath Housing Association	""	""	""	""	""	Q4-2019
981	981	CALF Turnkey	Galway City	Boireann Beag, Ros Cam, Galway (Phase 1)	16	Clúid Housing	""	""	""	""	""	Q4-2016
982	982	CALF Turnkey	Galway City	Breacan, Letteragh Road, Galway City (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2019
983	983	CALF Turnkey	Galway City	Briar Hill, Old Monivea Road, Ballybrit, Galway (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
984	984	CALF Turnkey	Galway City	Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 1)	7	Respond	""	""	""	""	""	Q4-2019
985	985	CALF Turnkey	Galway City	Caireal Mor (Phase 2), Headford Road, Castlegar, Galway (Phase 2)*	8	Respond	""	""	""	""	""	Q3-2020
986	986	CALF Turnkey	Galway City	Caireal Mor, Castlegar Road, Galway (Phase 1)	10	Respond	""	""	""	""	""	Q4-2019
987	987	CALF Turnkey	Galway City	Caireal Mor, Castlegar Road, Galway (Phase 2)	71	Respond	""	""	""	""	""	Q4-2020
988	988	CALF Turnkey	Galway City	Cnoc na Ri, Clybaun Road, Galway  (Phase 1)*	2	Clúid Housing	""	""	""	""	""	Q3-2017
989	989	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City  (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q4-2020
990	990	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City  (Phase 2)	10	Clúid Housing	""	""	""	""	""	Q2-2021
991	991	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City, Co. Galway (Phase 1)*	17	Clúid Housing	""	""	""	""	""	Q4-2021
992	992	CALF Turnkey	Galway City	Cuirt Bhoirne, Roscam, Co Galway (Phase 1)*	12	Clúid Housing	""	""	""	""	Q3-2020	""
993	993	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 1)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2021
994	994	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 2)*	6	Tuath Housing Association	""	""	""	""	Q4-2019	""
995	995	CALF Turnkey	Galway City	Gaelcarrig, Letteragh, Galway City (Phase 1)*	40	Respond	""	""	""	""	Q3-2020	""
996	996	CALF Turnkey	Galway City	Gaelcarrig, Letteragh, Galway City (Phase 2)	43	Respond	""	""	""	""	Q3-2020	""
997	997	CALF Turnkey	Galway City	Glenn Na Mona, Ballymoneen Road, Kncoknacarra, Galway (Phase 1)*	16	Clúid Housing	""	""	""	""	Q1-2021	""
998	998	CALF Turnkey	Galway City	Leana Mor, Cappagh Road, Galway (Phase 1)*	14	Respond	""	""	""	""	Q2-2021	""
999	999	CALF Turnkey	Galway City	Leana Mor, Cappagh Road, Galway (Phase 2)*	28	Respond	""	""	""	""	Q2-2021	""
1000	1000	CALF Turnkey	Galway City	Leana Theas, Cappagh Road, Galway City (Phase 1)*	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
1001	1001	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 1)*	10	Clúid Housing	""	""	""	""	""	Q3-2021
1002	1002	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 2)	13	Clúid Housing	""	""	""	""	""	Q4-2021
1003	1003	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 3)	16	Clúid Housing	""	""	""	""	Q3-2020	""
1004	1004	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 4)*	25	Clúid Housing	""	""	""	""	Q3-2020	""
1005	1005	CALF Turnkey	Galway City	Maigh Rua, Doughiska, Galway  (Phase 1)	23	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2017
1006	1006	CALF Turnkey	Galway City	Maoilin, Ballymoneen Road, Galway (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q1-2017
1007	1007	CALF Turnkey	Galway City	Maoilin, Ballymoneen Road, Galway (Phase 2)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2017
1008	1008	CALF Turnkey	Galway City	Maoilin, Ballymoneen Road, Knocknacarra, Galway CIty (Phase 1)*	3	Tuath Housing Association	""	""	""	""	""	Q3-2018
1009	1009	CALF Turnkey	Galway City	Reilean, Roscam, Block 5 Galway (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q2-2017
1010	1010	CALF Turnkey	Galway City	Reilean, Roscam,Block 4 Galway (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q2-2017
1011	1011	CALF Turnkey	Galway City	Revised Murrough, Renmore, Galway  (Phase 1)*	20	Clúid Housing	""	""	""	""	""	Q1-2019
1012	1012	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 1)	56	*N/A	""	""	""	""	""	Q2-2021
1013	1013	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 2)	18	*N/A	""	""	""	""	""	Q3-2021
1014	1014	SHIP CONSTRUCTION TURNKEY	Galway County	Lorro Gate, Prospect, Athenry	14	*N/A	""	""	""	""	""	Q4-2017
1015	1015	SHIP CONSTRUCTION TURNKEY	Galway County	Arvough, Kinvara	6	*N/A	""	""	""	""	""	Q4-2017
1016	1016	SHIP CONSTRUCTION TURNKEY	Galway County	Castlecourt, Abbey Street, Portumna	10	*N/A	""	""	""	""	""	Q4-2017
1017	1017	SHIP CONSTRUCTION TURNKEY	Galway County	Ashthorn Avenue, Headford	10	*N/A	""	""	""	""	""	Q4-2018
1018	1018	SHIP CONSTRUCTION TURNKEY	Galway County	Cuirt na hAbhann, Claregalway 	8	*N/A	""	""	""	""	""	Q4-2018
1019	1019	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	19	*N/A	""	""	""	""	""	Q4-2019
1020	1020	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	17	*N/A	""	""	""	""	""	Q4-2019
1021	1021	SHIP CONSTRUCTION TURNKEY	Galway County	Arvough, Kinvara	4	*N/A	""	""	""	""	""	Q4-2019
1022	1022	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	10	*N/A	""	""	""	""	""	Q4-2020
1023	1023	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	15	*N/A	""	""	""	""	""	Q4-2020
1024	1024	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	8	*N/A	""	""	""	""	""	Q4-2020
1025	1025	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	10	*N/A	""	""	""	""	""	Q4-2020
1026	1026	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	7	*N/A	""	""	""	""	""	Q4-2020
1027	1027	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	9	*N/A	""	""	""	""	""	Q1-2021
1028	1028	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	10	*N/A	""	""	""	""	""	Q1-2021
1029	1029	SHIP CONSTRUCTION TURNKEY	Galway County	Garraí Mhic Aodha, Tubber Road, Gort (Phase 1)	9	*N/A	""	""	""	""	""	Q4-2021
1030	1030	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	9	*N/A	""	""	""	""	""	Q4-2021
1031	1031	SHIP CONSTRUCTION TURNKEY	Galway County	Garraí Mhic Aodha, Tubber Road, Gort (Phase 2)	18	*N/A	""	""	""	""	""	Q4-2021
1032	1032	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	14	*N/A	""	""	""	""	Q4-2021	""
1033	1033	SHIP CONSTRUCTION TURNKEY	Galway County	Garraí Glas, Ballydavid South, Athenry	7	N/A	""	""	""	""	Q2-2021	""
1034	1034	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	13	*N/A	""	""	""	""	Q4-2021	""
1035	1035	SHIP CONSTRUCTION SINGLE STAGE	Galway County	Corralough, Williamstown (SRD)	1	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1036	1036	SHIP CONSTRUCTION RENEWAL	Galway County	Dunlo Hill, Ballinasloe	11	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1037	1037	SHIP CONSTRUCTION	Galway County	Esker Fields, Ballinasloe	2	*N/A	""	""	""	""	""	Q4-2019
1038	1038	SHIP CONSTRUCTION	Galway County	Garbally Drive, Ballinasloe	10	*N/A	""	""	""	""	""	Q3-2019
1039	1039	SHIP CONSTRUCTION	Galway County	Na Clocha Rua, An Cheathrú Rua	4	*N/A	""	""	""	""	""	Q4-2019
1040	1040	SHIP CONSTRUCTION	Galway County	Ardrahan (SRD)	1	*N/A	""	""	""	""	""	Q4-2017
1041	1041	SHIP CONSTRUCTION	Galway County	Callowfinish, Carna (SRD)	1	*N/A	""	""	""	""	""	Q2-2018
1042	1042	SHIP CONSTRUCTION	Galway County	Waterdale, Claregalway (SRD)	1	*N/A	""	""	""	""	""	Q4-2018
1043	1043	SHIP CONSTRUCTION	Galway County	Corndulla (SRD)	1	*N/A	""	""	""	""	""	Q1-2019
1044	1044	SHIP CONSTRUCTION	Galway County	Cill Ciarán (SRD)	1	*N/A	""	""	""	""	""	Q3-2018
1045	1045	SHIP CONSTRUCTION	Galway County	Kinvara (SRD)	1	*N/A	""	""	""	""	""	Q3-2018
1046	1046	SHIP CONSTRUCTION	Galway County	Cnoc na Carraige, Roundstone	8	*N/A	""	""	""	""	""	Q4-2020
1047	1047	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	18	*N/A	""	""	""	""	Q4-2020	""
1048	1048	SHIP CONSTRUCTION	Galway County	Bridge Court, Ahascragh, Ballinasloe	18	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1049	1049	SHIP CONSTRUCTION	Galway County	Caisleán Raithlín, Ardrahan	10	*N/A	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
1050	1050	SHIP CONSTRUCTION	Galway County	Barrack Street, Loughrea	5	*N/A	""	""	""	""	""	Q3-2021
1051	1051	SHIP CONSTRUCTION	Galway County	Gilmartin Road, Tuam	24	*N/A	""	""	""	""	""	Q3-2019
1052	1052	SHIP CONSTRUCTION	Galway County	Garraí Ghuaire, Cartron, Kinvara	10	*N/A	""	""	""	""	Q3-2021	""
1053	1053	SHIP CONSTRUCTION	Galway County	Gilmartin Road, Tuam	16	*N/A	""	""	""	""	""	Q4-2018
1054	1054	SHIP CONSTRUCTION	Galway County	Fána Bhuí, Tuam (Phase 1 )	16	*N/A	""	""	""	""	""	Q4-2021
1055	1055	SHIP CONSTRUCTION	Galway County	Gilmartin Road, Tuam	19	*N/A	""	""	""	""	""	Q4-2019
1056	1056	SHIP CONSTRUCTION	Galway County	Cnoc na Carraige, Roundstone	6	*N/A	""	""	""	""	""	Q1-2021
1057	1057	SHIP CONSTRUCTION	Galway County	Ballyglass, Ardrahan (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1058	1058	SHIP CONSTRUCTION	Galway County	Woodpark, Portumna (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1059	1059	SHIP CONSTRUCTION	Galway County	Carrowmore West, Clontuskert, Ballinasloe (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1060	1060	SHIP CONSTRUCTION	Galway County	Woodfield, Dunmore (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1061	1061	SHIP CONSTRUCTION	Galway County	Knockaloura West, Brownsgrove, Tuam (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1062	1062	SHIP CONSTRUCTION	Galway County	Creggaturlough, Craughwell (SRD)	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
1063	1063	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	8	*N/A	""	""	""	""	Q4-2020	""
1064	1064	SHIP CONSTRUCTION	Galway County	Fána Bhuí, Tuam (Phase 2)	10	*N/A	""	""	""	""	Q4-2020	""
1065	1065	SHIP CONSTRUCTION	Galway County	Fána Bhuí, Tuam (Phase 3)	22	*N/A	""	""	""	""	Q4-2020	""
1066	1066	SHIP CONSTRUCTION	Galway County	Ballymoe	8	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1067	1067	SHIP CONSTRUCTION	Galway County	Droim na Gaoithe, Baile Chláir (Claregalway)	45	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1068	1068	SHIP CONSTRUCTION	Galway County	Cosmona, Loughrea	40	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1069	1069	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 2)	11	Cluid Housing Association	""	""	""	""	Q4-2020	""
1070	1070	CAS CONSTRUCTION	Galway County	Rossaveal Cottages, Ros a Mhíl, South Connemara	8	Tearmann Eanna Teoranta	Stage 1 approved Q4-2016, outline design and costs being prepared.	""	""	""	""	""
1071	1071	CAS CONSTRUCTION	Galway County	Cregboy, Claregalway	14	Claregalway and District Day Care Centre	""	""	""	""	""	Q3-2019
1072	1072	CAS CONSTRUCTION	Galway County	Eanach Mheain, Carraroe	13	Tearmann Eanna Teoranta	""	Stage 2 approved Q4-2018, full design/tender being prepared.	""	""	""	""
1073	1073	CAS CONSTRUCTION	Galway County	Mountbellew	5	Túath Housing Association Ltd	""	Stage 2 approved Q4-2019, full design/tender being prepared.	""	""	""	""
1074	1074	CAS CONSTRUCTION	Galway County	Springfield, Parkmore, Ballinasloe	4	Peter Triest Housing Association Ltd	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1075	1075	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 1)	13	Cluid Housing Association	""	""	""	""	""	Q2-2016
1076	1076	CAS CONSTRUCTION	Galway County	Dunlo Hill, Ballinasloe	18	Cluid Housing Association	""	""	""	""	""	Q3-2020
1077	1077	CAS CONSTRUCTION	Galway County	Aggard More, Craughwell	4	Peter Triest Housing Association Ltd	""	""	""	""	""	Q4-2019
1078	1078	CAS CONSTRUCTION	Galway County	The Old Post Office, Inverin	4	Tearmann Eanna Teoranta	""	""	""	""	""	Q4-2020
1079	1079	CAS CONSTRUCTION	Galway County	Shannon Road, Portumna	4	Carraig Dubh Housing Association	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1080	1080	CALF Turnkey	Galway County	Cnoc na Si, Portumna, Co Galway (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2018
1081	1081	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 1)	24	Clúid Housing	""	""	""	Q4-2021	""	""
1082	1082	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 2)	14	Clúid Housing	""	""	""	Q4-2021	""	""
1083	1083	CALF Turnkey	Galway County	Dolphin Street, Loughrea, Co Galway (Phase 1)	8	Sophia Housing Association Ltd	""	""	""	Q4-2021	""	""
1084	1084	CALF Turnkey	Galway County	Dunloe Street, Ballinasloe, Co. Galway (Phase 1)	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1085	1085	CALF Turnkey	Galway County	Oranhill, Oranmore, Co. Galway (Phase 1)*	22	Clúid Housing	""	""	""	Q1-2021	""	""
1086	1086	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q4-2020
1087	1087	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 2)	12	Clúid Housing	""	""	""	""	""	Q1-2021
1088	1088	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 3)*	16	Clúid Housing	""	""	""	""	""	Q2-2021
1089	1089	CALF Construction	Galway County	Spiddal Cottages, Co Galway (Phase 1)	23	Clúid Housing	""	""	""	""	""	Q3-2017
1090	1090	CALF Turnkey	Galway County	Weir Road, Tuam, Co Galway (Phase 1)	5	Sophia Housing Association Ltd	""	""	""	""	Q3-2021	""
1091	1091	SHIP CONSTRUCTION TURNKEY	Kerry	Ard Na Si, Lispole	2	*N/A	""	""	""	""	""	Q1-2018
1092	1092	SHIP CONSTRUCTION TURNKEY	Kerry	1-4 Steeple Meadow View, Milltown	4	*N/A	""	""	""	""	""	Q4-2017
1093	1093	SHIP CONSTRUCTION TURNKEY	Kerry	Meadow Park, Milltown	9	*N/A	""	""	""	""	""	Q2-2018
1094	1094	SHIP CONSTRUCTION TURNKEY	Kerry	Ard Na Si, Lispole	5	*N/A	""	""	""	""	""	Q3-2018
1095	1095	SHIP CONSTRUCTION TURNKEY	Kerry	Ardmoniel Heights, Killorglin	3	*N/A	""	""	""	""	""	Q4-2018
1096	1096	SHIP CONSTRUCTION TURNKEY	Kerry	47 Woodview, Cahirdown, Listowel	1	*N/A	""	""	""	""	""	Q2-2018
1097	1097	SHIP CONSTRUCTION TURNKEY	Kerry	Dromin Upper, Listowel	8	*N/A	""	""	""	""	""	Q4-2020
1098	1098	SHIP CONSTRUCTION TURNKEY	Kerry	Ard Na Si, Lispole	3	*N/A	""	""	""	""	""	Q4-2018
1099	1099	SHIP CONSTRUCTION TURNKEY	Kerry	Ardmoniel Heights, Killorglin - Phase 2	1	*N/A	""	""	""	""	""	Q2-2019
1100	1100	SHIP CONSTRUCTION TURNKEY	Kerry	Ballygologue, Road, Listowel	2	*N/A	""	""	""	""	""	Q4-2019
1101	1101	SHIP CONSTRUCTION TURNKEY	Kerry	Cnoc an Cairn, Chapel Lane, Dingle	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1102	1102	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Pinewood Estate, Killarney	6	*N/A	""	""	""	""	""	Q4-2019
1103	1103	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Glannagilliagh, Caragh Lake, Killorglin (SRD)	1	*N/A	""	""	""	""	Q2-2021	""
1104	1104	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Carrigcannon, Lyreacrumpane (SRD)	1	*N/A	""	""	""	""	Q2-2021	""
1105	1105	SHIP CONSTRUCTION SINGLE STAGE	Kerry	Rahinnane, Ventry (SRD)	1	*N/A	""	""	""	""	Q2-2021	""
1106	1106	SHIP CONSTRUCTION RAPID	Kerry	Rathmore/Barraduff	20	*N/A	""	""	""	""	""	Q2-2021
1107	1107	SHIP CONSTRUCTION	Kerry	Cois Gallain, Killorglin	14	*N/A	""	""	""	""	""	Q4-2019
1108	1108	SHIP CONSTRUCTION	Kerry	Ardbhearna, Kenmare	22	*N/A	""	""	""	""	""	Q4-2018
1109	1109	SHIP CONSTRUCTION	Kerry	Bill Kinnerk Road, Tralee	4	*N/A	""	""	""	""	""	Q1-2018
1110	1110	SHIP CONSTRUCTION	Kerry	Cuirt Eaglaise, Milltown	8	*N/A	""	""	""	""	""	Q4-2019
1111	1111	SHIP CONSTRUCTION	Kerry	Killeen, Tralee	21	*N/A	""	""	""	""	""	Q3-2019
1112	1112	SHIP CONSTRUCTION	Kerry	Lixnaw	4	*N/A	""	""	""	""	""	Q4-2017
1113	1113	SHIP CONSTRUCTION	Kerry	The Park, Killarney	20	*N/A	""	""	""	""	""	Q1-2018
1114	1114	SHIP CONSTRUCTION	Kerry	Courthouse Lawn, Listowel	7	*N/A	""	""	""	""	""	Q4-2019
1115	1115	SHIP CONSTRUCTION	Kerry	Dreenagh, Ballyheigue (SRD)	1	*N/A	""	""	""	""	""	Q1-2017
1116	1116	SHIP CONSTRUCTION	Kerry	Glenach, Ballybunion	20	*N/A	""	""	""	""	""	Q1-2021
1117	1117	SHIP CONSTRUCTION	Kerry	Callinafercy, Milltown	1	*N/A	""	""	""	""	""	Q4-2018
1118	1118	SHIP CONSTRUCTION	Kerry	Cahernaboshina, Ventry	1	*N/A	""	""	""	""	""	Q4-2018
1119	1119	SHIP CONSTRUCTION	Kerry	An Carrigin, Tralee	28	*N/A	""	""	""	""	""	Q4-2020
1120	1120	SHIP CONSTRUCTION	Kerry	Pinewood Estate, Killarney	1	*N/A	""	""	""	""	""	Q4-2018
1121	1121	SHIP CONSTRUCTION	Kerry	Drom West, Glenbeigh	1	*N/A	""	""	""	""	""	Q4-2020
1122	1122	SHIP CONSTRUCTION	Kerry	Meanus, Killorglin	1	*N/A	""	""	""	""	""	Q3-2019
1123	1123	SHIP CONSTRUCTION	Kerry	Tullig Beg, Killorglin	1	*N/A	""	""	""	""	""	Q3-2019
1124	1124	SHIP CONSTRUCTION	Kerry	Owngarry, Killorglin	1	*N/A	""	""	""	""	""	Q4-2019
1125	1125	SHIP CONSTRUCTION	Kerry	Lohercannon, Tralee	61	*N/A	""	""	""	""	Q3-2020	""
1126	1126	SHIP CONSTRUCTION	Kerry	BallinaKilly Lower, Glenbeigh	1	*N/A	""	""	""	""	""	Q4-2020
1127	1127	SHIP CONSTRUCTION	Kerry	Ashgrove, Listowel	1	*N/A	""	""	""	""	""	Q3-2017
1128	1128	SHIP CONSTRUCTION	Kerry	Cullenagh Upper, Beaufort	1	*N/A	""	""	""	""	""	Q1-2021
1129	1129	SHIP CONSTRUCTION	Kerry	Farranwilliam, Ardfert	22	*N/A	""	""	""	""	""	Q3-2021
1130	1130	SHIP CONSTRUCTION	Kerry	Ballyrickard, Tralee	21	*N/A	""	""	""	""	Q3-2020	""
1131	1131	SHIP CONSTRUCTION	Kerry	Croogorts, Tralee	30	*N/A	""	""	""	""	Q3-2020	""
1132	1132	SHIP CONSTRUCTION	Kerry	Rock Rd., Killarney	10	*N/A	""	""	""	""	Q3-2020	""
1133	1133	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 4)	14	*N/A	""	""	""	""	""	Q1-2021
1134	1134	SHIP CONSTRUCTION	Kerry	Baile an Gharraí, Lixnaw (Phase 2)	10	*N/A	""	""	""	""	""	Q2-2021
1135	1135	SHIP CONSTRUCTION	Kerry	Woodview Place, Tarbert	22	*N/A	""	""	""	""	Q2-2021	""
1136	1136	SHIP CONSTRUCTION	Kerry	Marconi South, Ballybunion	14	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1137	1137	SHIP CONSTRUCTION	Kerry	Rahoonane, Tralee (New Site)	8	*N/A	""	""	""	""	Q2-2021	""
1138	1138	SHIP CONSTRUCTION	Kerry	Rusheen, Ballylongford	7	*N/A	""	""	""	""	Q4-2021	""
1139	1139	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 5)	14	*N/A	""	""	Stage 3 approved Q4-2020, the scheme is now approved to proceed to tender.	""	""	""
1140	1140	SHIP CONSTRUCTION	Kerry	Matt Talbot Road, Tralee	27	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1141	1141	SHIP CONSTRUCTION	Kerry	Locke's Shop, Mitchel's Rd, Tralee	8	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1142	1142	SHIP CONSTRUCTION	Kerry	Marian Terrace, Ballyheigue	9	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1143	1143	SHIP CONSTRUCTION	Kerry	Bridge Rd, Abbeydorney	1	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1144	1144	SHIP CONSTRUCTION	Kerry	Hawley Park Apartments, Tralee	16	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1145	1145	REGENERATION	Kerry	Croilar Na Mistaelach, Tralee	11	*N/A	""	""	""	""	""	Q4-2018
1146	1146	REGENERATION	Kerry	Urban Terrace, Tralee	2	*N/A	""	""	""	""	""	Q4-2016
1147	1147	REGENERATION	Kerry	Clonmore Road, Tralee	3	*N/A	""	""	""	""	""	Q4-2016
1148	1148	REGENERATION	Kerry	St Martin's Park, Tralee	4	*N/A	""	""	""	""	""	Q4-2018
1149	1149	REGENERATION	Kerry	Dingle Road, Tralee	1	*N/A	""	""	""	""	""	Q2-2018
1150	1150	CAS CONSTRUCTION TURNKEY	Kerry	Firies Hall, Firies	14	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1151	1151	CAS CONSTRUCTION TURNKEY	Kerry	Turnkey at Firies Hall, Firies, Co Kerry	4	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1152	1152	CAS CONSTRUCTION	Kerry	Armagh House, Killarney	6	Cluid Housing Association	""	""	""	""	""	Q1-2021
1153	1153	CAS CONSTRUCTION	Kerry	22 College Road, Castleisland	4	Kerry Emigrant Support Housing Association Ltd	""	""	""	""	""	Q4-2018
1154	1154	CAS CONSTRUCTION	Kerry	Chamfers Place (Mitchels road, Tralee)	18	Cluid Housing Association	""	""	""	""	Q2-2021	""
1155	1155	CAS CONSTRUCTION	Kerry	The Parsonage, Caherciveen	5	Caherciveen Social Services (Housing) Ltd	""	""	""	""	""	Q4-2018
1156	1156	CAS CONSTRUCTION	Kerry	The Presentation Convent, Rathmore	4	Social Action Group Rathmore	""	""	""	""	""	Q3-2020
1157	1157	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 1)	28	Clúid Housing	""	""	""	""	Q4-2020	""
1158	1158	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 2)*	26	Clúid Housing	""	""	""	""	Q4-2020	""
1159	1159	CALF Turnkey	Kerry	Barraduff, Killarney, Co Kerry (Phase 1)*	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2021	""
1160	1160	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 1)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1161	1161	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 2)*	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1162	1162	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 3)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1163	1163	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 4)*	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
1164	1164	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 1)*	12	Clúid Housing	""	""	""	""	Q3-2020	""
1165	1165	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 2)	26	Clúid Housing	""	""	""	""	Q3-2020	""
1166	1166	CALF Turnkey	Kerry	Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 1)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1167	1167	CALF Turnkey	Kerry	Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 2)	23	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1168	1168	CALF Turnkey	Kerry	Cathair Lakes Farrantoreen Road, Killorglin, Co Kerry (Phase 1)	5	Clúid Housing	""	""	""	""	""	Q2-2016
1169	1169	CALF Turnkey	Kerry	Deerpark Avenue, Tralee, Co. Kerry (Phase 1)	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
1170	1170	CALF Turnkey	Kerry	Derreen, Killarney, Co Kerry  (Phase 1)*	61	Clúid Housing	""	""	""	""	""	Q3-2020
1171	1171	CALF Turnkey	Kerry	Doon Road, Lisloose, Tralee, Co. Kerry (Phase 1)*	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2020
1172	1172	CALF Turnkey	Kerry	Dromcairn, Tralee, Co. Kerry (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q4-2020
1173	1173	CALF Turnkey	Kerry	Dun Alainn, Listowel, Co. Kerry (Phase 1)*	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2021	""
1174	1174	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 1)	14	Respond	""	""	""	""	""	Q4-2018
1175	1175	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 2)	2	Respond	""	""	""	""	""	Q4-2019
1176	1176	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 3)	5	Respond	""	""	""	""	""	Q2-2020
1177	1177	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 4)	1	Respond	""	""	""	""	""	Q2-2021
1178	1178	CALF Turnkey	Kerry	Fortfield, Tralee, Co. Kerry (Phase 1)*	15	Clúid Housing	""	""	""	""	""	Q4-2019
1179	1179	CALF Turnkey	Kerry	Hunters Lodge, Hunters Wood, Ballyseedy, Tralee, Co. Kerry (Phase 1)	10	Clúid Housing	""	""	""	""	Q3-2021	""
1180	1180	CALF Turnkey	Kerry	Killeen, Abbeydorney Road, Tralee, Co. Kerry (Phase 1)*	17	Clúid Housing	""	""	""	""	""	Q4-2019
1181	1181	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 1)*	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
1182	1182	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 2)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1183	1183	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 3)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1184	1184	CALF Turnkey	Kerry	Lios Ard, Lisloose, Tralee, Co. Kerry (Phase 1)	28	Clúid Housing	""	""	""	""	""	Q3-2021
1185	1185	CALF Turnkey	Kerry	Moanmore, Pound Road, Castleisland, Co. Kerry (Phase 1)*	14	Clúid Housing	""	""	""	""	""	Q4-2021
1186	1186	CALF Turnkey	Kerry	Oakwood, Coolegrean, Killarney, Co. Kerry (Coill na Darach) (Phase 1)	59	Clúid Housing	""	""	""	""	""	Q3-2019
1187	1187	CALF Turnkey	Kerry	Orglan Heights, Ardmoneel, Killorglin (Phase 1)*	30	Clúid Housing	""	""	""	Q3-2021	""	""
1188	1188	CALF Turnkey	Kerry	Sruthan na Saili, Derreen, Co. Kerry (Phase 1)*	22	Clúid Housing	""	""	""	""	""	Q4-2020
1189	1189	CALF Turnkey	Kerry	The Grove, Dingle, Co. Kerry (Phase 1)*	20	Clúid Housing	""	""	""	""	""	Q3-2020
1190	1190	SHIP CONSTRUCTION TURNKEY	Kildare	Bodkin Place, Kilmeague	16	*N/A	""	""	""	""	""	Q4-2017
1191	1191	SHIP CONSTRUCTION TURNKEY	Kildare	Drogheda Street, Monasterevin	6	*N/A	""	""	""	""	""	Q4-2017
1192	1192	SHIP CONSTRUCTION TURNKEY	Kildare	Oaktree, Tully Road, Kildare Town	8	*N/A	""	""	""	""	""	Q3-2018
1193	1193	SHIP CONSTRUCTION TURNKEY	Kildare	Moore Abbey Court, Monasterevin	2	*N/A	""	""	""	""	""	Q1-2018
1194	1194	SHIP CONSTRUCTION TURNKEY	Kildare	Drogheda Street, Monasterevin	7	*N/A	""	""	""	""	""	Q1-2018
1195	1195	SHIP CONSTRUCTION TURNKEY	Kildare	Moss Brook, Prosperous	2	*N/A	""	""	""	""	""	Q1-2018
1196	1196	SHIP CONSTRUCTION TURNKEY	Kildare	Hawthorn Manor, Brockagh, Coill Dubh	2	*N/A	""	""	""	""	""	Q4-2018
1197	1197	SHIP CONSTRUCTION TURNKEY	Kildare	Whitethorn Park, Allenwood	2	*N/A	""	""	""	""	""	Q3-2018
1198	1198	SHIP CONSTRUCTION TURNKEY	Kildare	The Pike, Castledermot	6	*N/A	""	""	""	""	""	Q4-2018
1199	1199	SHIP CONSTRUCTION TURNKEY	Kildare	Grove Lane, Robertstown	3	*N/A	""	""	""	""	""	Q1-2020
1200	1200	SHIP CONSTRUCTION TURNKEY	Kildare	Brookes Mill, Prosperous	5	*N/A	""	""	""	""	""	Q4-2018
1201	1201	SHIP CONSTRUCTION TURNKEY	Kildare	The Green, Elsmore Naas	5	*N/A	""	""	""	""	""	Q4-2018
1202	1202	SHIP CONSTRUCTION TURNKEY	Kildare	Oakwood Park, Derrinturn 	10	*N/A	""	""	""	""	""	Q1-2019
1203	1203	SHIP CONSTRUCTION TURNKEY	Kildare	Oakwood Park, Derrinturn 	16	*N/A	""	""	""	""	""	Q3-2020
1204	1204	SHIP CONSTRUCTION TURNKEY	Kildare	Beech Park Wood, Leixlip	4	*N/A	""	""	""	""	""	Q3-2019
1205	1205	SHIP CONSTRUCTION TURNKEY	Kildare	Oaktree, Tully Road, Kildare Town	18	*N/A	""	""	""	""	""	Q2-2019
1206	1206	SHIP CONSTRUCTION TURNKEY	Kildare	Oakwood Park, Derrinturn 	10	*N/A	""	""	""	""	""	Q3-2019
1207	1207	SHIP CONSTRUCTION TURNKEY	Kildare	Oaktree, Tully Road, Kildare Town	20	*N/A	""	""	""	""	""	Q3-2019
1208	1208	SHIP CONSTRUCTION TURNKEY	Kildare	Cluain Dara, Derrinturn, Kildare	1	*N/A	""	""	""	""	""	Q2-2019
1209	1209	SHIP CONSTRUCTION TURNKEY	Kildare	Hawthorn Manor, Brockagh, Coill Dubh	3	*N/A	""	""	""	""	""	Q4-2019
1210	1210	SHIP CONSTRUCTION TURNKEY	Kildare	School Walk, Allenwood	4	*N/A	""	""	""	""	""	Q4-2019
1211	1211	SHIP CONSTRUCTION TURNKEY	Kildare	Stoneleigh, Naas	6	*N/A	""	""	""	""	""	Q4-2019
1212	1212	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q1-2020
1213	1213	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q3-2020
1214	1214	SHIP CONSTRUCTION TURNKEY	Kildare	Barrack Close, Ballymore Eustace	2	*N/A	""	""	""	""	""	Q2-2020
1215	1215	SHIP CONSTRUCTION TURNKEY	Kildare	Hawthorn Manor, Brockagh, Coill Dubh	6	*N/A	""	""	""	""	""	Q2-2020
1216	1216	SHIP CONSTRUCTION TURNKEY	Kildare	Brookes Mill Prosperous	1	*N/A	""	""	""	""	""	Q4-2019
1217	1217	SHIP CONSTRUCTION TURNKEY	Kildare	Greenfield House, Maynooth	1	*N/A	""	""	""	""	""	Q4-2019
1218	1218	SHIP CONSTRUCTION TURNKEY	Kildare	Crockaun Way, Brownstown Manor, The Curragh	10	*N/A	""	""	""	""	""	Q4-2020
1219	1219	SHIP CONSTRUCTION TURNKEY	Kildare	Railway House, Dublin Road, Naas 	3	*N/A	""	""	""	""	""	Q3-2020
1220	1220	SHIP CONSTRUCTION TURNKEY	Kildare	Loughminane Green, Kildare Town 	2	*N/A	""	""	""	""	""	Q4-2020
1221	1221	SHIP CONSTRUCTION TURNKEY	Kildare	Crockaun Way, Brownstown Manor, The Curragh	26	*N/A	""	""	""	""	""	Q4-2020
1222	1222	SHIP CONSTRUCTION TURNKEY	Kildare	Crockaun Way, Brownstown Manor, The Curragh	9	*N/A	""	""	""	""	""	Q4-2020
1223	1223	SHIP CONSTRUCTION TURNKEY	Kildare	Barrack Close, Ballymore Eustace	2	*N/A	""	""	""	""	""	Q3-2020
1224	1224	SHIP CONSTRUCTION TURNKEY	Kildare	Hawthorn Manor, Brockagh, Coill Dubh	9	*N/A	""	""	""	""	""	Q3-2020
1225	1225	SHIP CONSTRUCTION TURNKEY	Kildare	Temple Mills, Rathangan	2	*N/A	""	""	""	""	""	Q4-2020
1226	1226	SHIP CONSTRUCTION TURNKEY	Kildare	Longstone, Craddockstown, Naas	5	*N/A	""	""	""	""	""	Q4-2020
1227	1227	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	4	*N/A	""	""	""	""	""	Q4-2020
1228	1228	SHIP CONSTRUCTION TURNKEY	Kildare	Hawthorn Manor, Brockagh, Coill Dubh	6	*N/A	""	""	""	""	""	Q4-2020
1229	1229	SHIP CONSTRUCTION TURNKEY	Kildare	Oakwood Park, Derrinturn	3	*N/A	""	""	""	""	""	Q4-2020
1230	1230	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	2	*N/A	""	""	""	""	""	Q4-2020
1231	1231	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q2-2021
1232	1232	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A	""	""	""	""	""	Q2-2021
1233	1233	SHIP CONSTRUCTION TURNKEY	Kildare	Main Street, Robertstown	2	*N/A	""	""	""	""	""	Q4-2020
1234	1234	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A	""	""	""	""	""	Q1-2021
1235	1235	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield Clane	1	*N/A	""	""	""	""	""	Q2-2021
1236	1236	SHIP CONSTRUCTION TURNKEY	Kildare	Old Mill Race, Monasterevin	9	*N/A	""	""	""	""	Q4-2019	""
1237	1237	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	13	*N/A	""	""	""	""	""	Q3-2021
1238	1238	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	10	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1239	1239	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A	""	""	""	""	""	Q2-2021
1240	1240	SHIP CONSTRUCTION TURNKEY	Kildare	Newtown, Ardclough Rd, Celbridge	49	*N/A	""	""	""	""	Q2-2021	""
1241	1241	SHIP CONSTRUCTION TURNKEY	Kildare	Kildare Road, Rathangan	9	*N/A	""	""	""	""	Q1-2021	""
1242	1242	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield, Clane	2	*N/A	""	""	""	""	""	Q3-2021
1243	1243	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A	""	""	""	""	""	Q4-2021
1244	1244	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A	""	""	""	""	""	Q4-2021
1245	1245	SHIP CONSTRUCTION TURNKEY	Kildare	Millstream Court, Kilcullen	1	*N/A	""	""	""	""	""	Q4-2021
1246	1246	SHIP CONSTRUCTION TURNKEY	Kildare	Williams Grove, Ardclough	2	*N/A	""	""	""	""	""	Q4-2021
1247	1247	SHIP CONSTRUCTION SINGLE STAGE	Kildare	Patrician Avenue, Naas	3	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1248	1248	SHIP CONSTRUCTION RAPID	Kildare	Old Greenfield Road, Maynooth	47	*N/A	Stage 1 approved Q4-2017, outline design and costs being prepared.	""	""	""	""	""
1249	1249	SHIP CONSTRUCTION	Kildare	Athgarvan Village	18	*N/A	""	""	""	""	Q3-2021	""
1250	1250	SHIP CONSTRUCTION	Kildare	Rathasker Road, Naas	48	*N/A	Stage 1 approved Q1-2016, outline design and costs being prepared.	""	""	""	""	""
1251	1251	SHIP CONSTRUCTION	Kildare	Dunmurry Rise, Bishopsland, Kildare Town	32	*N/A	""	""	""	""	""	Q3-2019
1252	1252	SHIP CONSTRUCTION	Kildare	Anne Street, Prosperous	12	*N/A	""	""	""	""	""	Q3-2020
1253	1253	SHIP CONSTRUCTION	Kildare	Beechgrove, Rathangan	18	*N/A	""	""	""	""	""	Q4-2019
1254	1254	SHIP CONSTRUCTION	Kildare	Kilcock (Phase 2.1)	6	*N/A	""	""	""	""	""	Q4-2017
1255	1255	SHIP CONSTRUCTION	Kildare	Athgarvan Road, Newbridge	13	*N/A	""	""	""	""	""	Q3-2018
1256	1256	SHIP CONSTRUCTION	Kildare	Newtown House, Leixlip	4	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
1257	1257	SHIP CONSTRUCTION	Kildare	Coill Dubh	10	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1258	1258	SHIP CONSTRUCTION	Kildare	Ardclough Road, Celbridge	39	*N/A	Stage 1 approved Q4-2017, outline design and costs being prepared.	""	""	""	""	""
1259	1259	SHIP CONSTRUCTION	Kildare	Kilcock (Phase 2.2)	13	*N/A	""	""	""	""	""	Q1-2018
1260	1260	SHIP CONSTRUCTION	Kildare	Ambassador Site, Kill	33	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1261	1261	SHIP CONSTRUCTION	Kildare	Carbury	5	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1262	1262	SHIP CONSTRUCTION	Kildare	St. Evins Park Monasterevin	16	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1263	1263	SHIP CONSTRUCTION	Kildare	Castle Park, Athy	4	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
1264	1264	SHIP CONSTRUCTION	Kildare	Oldtown Mill, Celbridge	57	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
1265	1265	SHIP CONSTRUCTION	Kildare	Old Caragh Road, Nass	58	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1266	1266	CAS CONSTRUCTION	Kildare	Craddockstown, Naas	3	KARE Promoting Inclusion for People with Intellectual Disabilities	""	Stage 2 approved Q2-2018, full design/tender being prepared.	""	""	""	""
1267	1267	CAS CONSTRUCTION	Kildare	El Kantara, Newbridge	2	KARE Promoting Inclusion for People with Intellectual Disabilities	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
1268	1268	CAS CONSTRUCTION	Kildare	Jigginstown House, Naas	12	Homeless Care Ltd	""	""	""	""	""	Q2-2021
1269	1269	CAS CONSTRUCTION	Kildare	St. John's Convent, New Street, Rathangan	27	Sophia Housing Association Ltd	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
1270	1270	CAS CONSTRUCTION	Kildare	Dominican Lands, Athy	30	Cluid Housing Association	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
1271	1271	CALF Turnkey	Kildare	1 unit, Loughlion Green, Kildare Town (Phase 1)	1	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
1272	1272	CALF Turnkey	Kildare	15 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	15	Clúid Housing	""	""	""	""	""	Q4-2021
1273	1273	CALF Turnkey	Kildare	2 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	2	Clúid Housing	""	""	""	""	""	Q4-2021
1274	1274	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 1)*	30	Tuath Housing Association	""	""	""	""	Q3-2021	""
1275	1275	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 2)*	4	Tuath Housing Association	""	""	""	""	Q3-2021	""
1276	1276	CALF Turnkey	Kildare	Bellingsfield, Naas, Kildare (Phase 1)*	10	Respond	""	""	""	""	""	Q4-2018
1277	1277	CALF Turnkey	Kildare	Carton Grove, Maynooth, Co. Kildare (Phase 1)*	5	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2018
1278	1278	CALF Turnkey	Kildare	Castle Farm, Jigginstown, Naas, Co. Kildare (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q4-2019
1279	1279	CALF Turnkey	Kildare	Castle Farm, Naas, Co. Kildare (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q2-2019
1280	1280	CALF Construction	Kildare	Castlefen, Castlesize, Sallins, Co. Kildare (Phase 1)	29	Tuath Housing Association	""	""	""	""	Q1-2020	""
1281	1281	CALF Turnkey	Kildare	Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 1)*	6	Cill Dara Housing Association	""	""	""	""	""	Q4-2019
1282	1282	CALF Turnkey	Kildare	Cathedral Apartments, Firecastle Lane, Kildare Town, Co. Kildare (Phase 2)*	11	Cill Dara Housing Association	""	""	""	""	""	Q4-2019
1283	1283	CALF Turnkey	Kildare	Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 1)*	26	Tuath Housing Association	""	""	""	""	""	Q4-2019
1284	1284	CALF Turnkey	Kildare	Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 2)*	17	Tuath Housing Association	""	""	""	""	""	Q4-2021
1285	1285	CALF Turnkey	Kildare	Elsmore, Jigginstown, Nass, Co. Kildare (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q4-2018
1286	1286	CALF Turnkey	Kildare	Elsmore, Jigginstown, Nass, Co. Kildare (Phase 2)*	3	Tuath Housing Association	""	""	""	""	""	Q3-2019
1287	1287	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 1)	18	Tuath Housing Association	""	""	""	""	""	Q1-2019
1288	1288	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q1-2019
1289	1289	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 3)	6	Tuath Housing Association	""	""	""	""	""	Q1-2019
1290	1290	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 4)	6	Tuath Housing Association	""	""	""	""	""	Q2-2019
1291	1291	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 5)	4	Tuath Housing Association	""	""	""	""	""	Q2-2019
1292	1292	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 6)	5	Tuath Housing Association	""	""	""	""	""	Q3-2019
1293	1293	CALF Turnkey	Kildare	Fenton Green, Kilcock, Co Kildare  (Phase 7)*	18	Tuath Housing Association	""	""	""	""	""	Q4-2019
1294	1294	CALF Construction	Kildare	Flinters Field (Phase 2), Athy, Co. Kildare (Phase 1)	35	Respond	""	""	""	""	Q1-2021	""
1295	1295	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 1)*	21	Clúid Housing	""	""	""	""	""	Q1-2021
1296	1296	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 2)	19	Clúid Housing	""	""	""	""	""	Q2-2021
1297	1297	CALF Turnkey	Kildare	Hawthorn Manor, Brockagh, Coill Dubh, Co. Kildare (Phase 1)*	5	Oaklee Housing	""	""	""	""	""	Q4-2019
1298	1298	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 1 (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q1-2021
1299	1299	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 2 (Phase 1)*	4	Clúid Housing	""	""	""	""	Q2-2019	""
1300	1300	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	31	Clúid Housing	""	""	""	""	""	Q4-2019
1301	1301	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	27	Clúid Housing	""	""	""	""	""	Q3-2021
1302	1302	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	3	Clúid Housing	""	""	""	""	""	Q4-2021
1303	1303	CALF Turnkey	Kildare	Leinster Square, Dublin Street, Kildare Town, Co Kildare (Phase 1)*	4	Clanmil Housing Association Ireland	""	""	""	""	""	Q3-2021
1304	1304	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 1)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1305	1305	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 2)*	17	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1306	1306	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 3)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
1307	1307	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 4)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1308	1308	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 5)*	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
1309	1309	CALF Turnkey	Kildare	Main Street, Prosperous, Clane, Co. Kildare (Phase 1)*	16	Clanmil Housing Association Ireland	""	""	""	""	Q4-2020	""
1310	1310	CALF Turnkey	Kildare	Mariavilla and Elsmore, Kildare (Phase 1)*	15	Tuath Housing Association	""	""	""	""	""	Q4-2019
1311	1311	CALF Turnkey	Kildare	Mariavilla, Maynooth, Co. Kildare (Phase 1)*	11	Tuath Housing Association	""	""	""	""	""	Q4-2021
1312	1312	CALF Turnkey	Kildare	Melitta Road, Co. Kildare (Phase 1)	4	Clanmil Housing Association Ireland	""	""	""	Q2-2021	""	""
1313	1313	CALF Turnkey	Kildare	Millfield Manor, Newbridge, Co. Kildare (Phase 1)*	19	Clúid Housing	""	""	""	""	""	Q3-2018
1314	1314	CALF Turnkey	Kildare	Morristown, Newbridge, Co Kildare (Phase 1)	14	Clúid Housing	""	""	""	""	""	Q1-2018
1315	1315	CALF Turnkey	Kildare	Morristown, Newbridge, Co. Kildare (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q2-2018
1316	1316	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 1)*	9	Tuath Housing Association	""	""	""	""	Q4-2019	""
1317	1317	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 2)*	18	Tuath Housing Association	""	""	""	""	Q4-2019	""
1318	1318	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 1)*	13	Tuath Housing Association	""	""	""	Q1-2022	""	""
1319	1319	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 2)	24	Tuath Housing Association	""	""	""	Q1-2022	""	""
1320	1320	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 3)*	2	Tuath Housing Association	""	""	""	Q1-2022	""	""
1321	1321	CALF Turnkey	Kildare	Oakpark, Craddockstown, Kildare (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q4-2020
1322	1322	CALF Turnkey	Kildare	Oaktree, Tully Road, Kildare Town (Phase 1)*	10	Tuath Housing Association	""	""	""	""	""	Q2-2018
1323	1323	CALF Turnkey	Kildare	Oaktree, Tully Road, Kildare Town (Phase 2)*	7	Tuath Housing Association	""	""	""	""	""	Q3-2018
1324	1324	CALF Turnkey	Kildare	Phase 2, White Oaks, Newbridge, Kildare (Phase 1)	36	Clúid Housing	""	""	""	""	""	Q4-2019
1325	1325	CALF Turnkey	Kildare	"Revised Rye Abbey, Kilcock, Co Kildare (apts)
 (Phase 1)"	33	Clúid Housing	""	""	""	""	""	Q2-2017
1326	1326	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 1)*	32	Clúid Housing	""	""	""	""	Q2-2021	""
1327	1327	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 2)*	24	Clúid Housing	""	""	""	""	Q2-2021	""
1328	1328	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 3)	8	Clúid Housing	""	""	""	""	Q2-2021	""
1329	1329	CALF Turnkey	Kildare	Robertstown, Naas , Co.Kildare (Phase 1)	5	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2020
1330	1330	CALF Turnkey	Kildare	Roseberry Hill, Newbridge (Phase 1)	13	Tuath Housing Association	""	""	""	""	""	Q2-2017
1331	1331	CALF Turnkey	Kildare	Roseberry Hill, Newbridge (Phase 2)	16	Tuath Housing Association	""	""	""	""	""	Q4-2017
1332	1332	CALF Turnkey	Kildare	Roseberry Hill, Newbridge (Phase 3)	16	Tuath Housing Association	""	""	""	""	""	Q1-2018
1333	1333	CALF Turnkey	Kildare	Rye Abbey, Kilcock - revised (houses) (Phase 1)	4	Clúid Housing	""	""	""	""	""	Q2-2017
1334	1334	CALF Turnkey	Kildare	The Arches, Castlefarm, Naas, Co. Kildare (Phase 1)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2020
1335	1335	CALF Turnkey	Kildare	The Paddocks, Morristown, Newbridge, Kildare (Phase 1)*	5	Clúid Housing	""	""	""	""	""	Q4-2019
1336	1336	CALF Turnkey	Kildare	The Paddocks, Morristown, Newbridge, Kildare (Phase 2)*	3	Clúid Housing	""	""	""	""	""	Q4-2020
1337	1337	CALF Turnkey	Kildare	The Paddocks, Morristown, Newbridge, Kildare (Phase 3)*	16	Clúid Housing	""	""	""	""	""	Q2-2021
1338	1338	CALF Turnkey	Kildare	The Paddocks, Newbridge, Co Kildare (Phase 1)	18	Clúid Housing	""	""	""	""	""	Q4-2020
1339	1339	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 1)	26	Clúid Housing	""	""	""	""	""	Q3-2021
1340	1340	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 2)	33	Clúid Housing	""	""	""	""	""	Q4-2021
1341	1341	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)	18	Respond	""	""	""	""	""	Q4-2019
1342	1342	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)*	18	Respond	""	""	""	""	""	Q2-2021
1343	1343	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 2)	32	Respond	""	""	""	""	""	Q2-2020
1344	1344	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 3) (Phase 1)	20	Respond	""	""	""	""	Q4-2019	""
1345	1345	CALF Turnkey	Kildare	Westfield, Leixlip, Co. Kildare (Phase 1)*	20	Respond	""	""	""	""	""	Q4-2021
1346	1346	CALF Turnkey	Kildare	White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 1)*	14	Clúid Housing	""	""	""	""	""	Q4-2018
1347	1347	CALF Turnkey	Kildare	White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 2)	24	Clúid Housing	""	""	""	""	""	Q4-2018
1348	1348	CALF Turnkey	Kildare	White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 3)	20	Clúid Housing	""	""	""	""	""	Q1-2019
1349	1349	CALF Turnkey	Kildare	White Oaks, Rickardstown, Newbridge, Co. Kildare (Phase 4)	2	Clúid Housing	""	""	""	""	""	Q4-2019
1350	1350	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2021
1351	1351	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 2)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2021
1352	1352	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 3)*	4	Tuath Housing Association	""	""	""	""	Q2-2020	""
1353	1353	CALF Turnkey	Kildare	Willouise, Sallins, Kildare (Phase 1)	31	Tuath Housing Association	""	""	""	""	""	Q4-2020
1354	1354	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Kildare	Craddockstown, Naas (Phase 1)	36	*N/A	""	""	""	""	""	Q2-2020
1355	1355	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Kildare	Craddockstown, Naas (Phase 2)	38	*N/A	""	""	""	""	""	Q3-2020
1356	1356	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Kildare	Butterstream, Clane	77	*N/A	""	""	""	""	""	Q4-2021
1357	1357	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Kildare	Ardrew, Athy, Co. Kildare	73	*N/A	""	Q4-2021	""	""	""	""
1358	1358	SHIP CONSTRUCTION TURNKEY	Kilkenny	Togher Way, Urlingford	11	*N/A	""	""	""	""	""	Q2-2017
1359	1359	SHIP CONSTRUCTION TURNKEY	Kilkenny	Newpark, Castlecomer Road, Kilkenny	7	*N/A	""	""	""	""	""	Q1-2017
1360	1360	SHIP CONSTRUCTION TURNKEY	Kilkenny	Abbeygate, Ferrybank	8	*N/A	""	""	""	""	""	Q1-2018
1361	1361	SHIP CONSTRUCTION TURNKEY	Kilkenny	Togher Way, Urlingford	5	*N/A	""	""	""	""	""	Q4-2017
1362	1362	SHIP CONSTRUCTION TURNKEY	Kilkenny	Abbeygate, Ferrybank	1	*N/A	""	""	""	""	""	Q3-2018
1363	1363	SHIP CONSTRUCTION TURNKEY	Kilkenny	Togher Way, Urlingford (Phase 3)	18	*N/A	""	""	""	""	""	Q4-2018
1364	1364	SHIP CONSTRUCTION TURNKEY	Kilkenny	New Road, Mooncoin	4	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1365	1365	SHIP CONSTRUCTION TURNKEY	Kilkenny	Chapel Street, Mooncoin	2	*N/A	""	""	""	""	Q3-2018	""
1366	1366	SHIP CONSTRUCTION TURNKEY	Kilkenny	Ogenty, Gowran	12	*N/A	""	""	""	""	""	Q4-2018
1367	1367	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Court, Hebron Road, Kilkenny	8	*N/A	""	""	""	""	Q3-2020	""
1368	1368	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Oakridge, Ferrybank, Co. Kilkenny	4	*N/A	""	""	""	""	""	Q2-2020
1369	1369	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Green, Hebron Road, Kilkenny	52	*N/A	""	""	""	""	Q3-2020	""
1370	1370	SHIP CONSTRUCTION TURNKEY	Kilkenny	Blackwater Grove, Kilmacow	14	*N/A	""	""	""	""	""	Q2-2021
1371	1371	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank, Co. Kilkenny	5	*N/A	""	""	""	""	""	Q4-2021
1372	1372	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank, Co. Kilkenny	10	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1373	1373	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Group Home Cloghabrody, Thomastown	4	*N/A	""	""	""	""	""	Q3-2020
1374	1374	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Inchacarron, Mullinavat	2	*N/A	""	""	""	Stage 4 approved Q2-2019, the scheme is fully approved.	""	""
1375	1375	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Shanganny, Jenkinstown	2	*N/A	""	""	""	""	Q4-2020	""
1376	1376	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	6	*N/A	""	""	""	""	""	Q2-2021
1377	1377	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Old Fire Station, Graiguenamanagh	2	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1378	1378	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	2	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
1379	1379	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Haggardsgreen, Callan	1	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1380	1380	SHIP CONSTRUCTION	Kilkenny	Blackstaff House, Callan	4	*N/A	""	""	""	""	""	Q4-2019
1381	1381	SHIP CONSTRUCTION	Kilkenny	Barna, Freshford	1	*N/A	""	""	""	""	""	Q2-2018
1382	1382	SHIP CONSTRUCTION	Kilkenny	10 Golf Links Road, Kilkenny	6	*N/A	""	""	""	""	Q4-2021	""
1383	1383	SHIP CONSTRUCTION	Kilkenny	Main Street, Piltown	17	*N/A	""	""	""	""	""	Q4-2020
1384	1384	SHIP CONSTRUCTION	Kilkenny	Station Road, Ballyragget	22	*N/A	""	""	""	""	""	Q2-2021
1385	1385	SHIP CONSTRUCTION	Kilkenny	Bolton, Callan	38	*N/A	""	""	""	""	""	Q3-2020
1386	1386	SHIP CONSTRUCTION	Kilkenny	Donaguile, Castlecomer	33	*N/A	""	""	""	""	""	Q2-2021
1387	1387	SHIP CONSTRUCTION	Kilkenny	Rosehill, Kells Road, Kilkenny	6	*N/A	""	""	""	""	""	Q1-2017
1388	1388	SHIP CONSTRUCTION	Kilkenny	Gaol Road, Kilkenny	10	*N/A	""	""	""	""	""	Q3-2016
1389	1389	SHIP CONSTRUCTION	Kilkenny	Greensbridge House	5	*N/A	""	""	""	""	""	Q4-2018
1390	1390	SHIP CONSTRUCTION	Kilkenny	The Broguemaker, Kilkenny	18	*N/A	""	""	""	""	""	Q2-2021
1391	1391	SHIP CONSTRUCTION	Kilkenny	Ladywell, Thomastown, Co. Kilkenny	25	*N/A	""	""	""	""	Q4-2021	""
1392	1392	SHIP CONSTRUCTION	Kilkenny	Crokers Hill, Kennyswell Road, Kilkenny	88	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
1393	1393	SHIP CONSTRUCTION	Kilkenny	Canal Road, Johnstown, Co. Kilkenny Project 1	5	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1394	1394	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstown Project 2	2	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1395	1395	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstown Project 3	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1396	1396	SHIP CONSTRUCTION	Kilkenny	Ladywell, Newtown, Thomastown	33	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1397	1397	SHIP CONSTRUCTION	Kilkenny	Weather Station, Granges Road, Kilkenny	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1398	1398	CAS CONSTRUCTION TURNKEY	Kilkenny	Golf Links Road, Kilkenny	15	Respond	""	""	""	""	""	Q3-2019
1399	1399	CAS CONSTRUCTION	Kilkenny	Kingsriver, Ennisnag	4	Kingsriver Housing Association Limited	""	""	""	""	Q2-2021	""
1400	1400	CAS CONSTRUCTION	Kilkenny	Garrin Green	6	SOS Kilkenny Housing Association Ltd	""	""	""	""	""	Q4-2018
1401	1401	CAS CONSTRUCTION	Kilkenny	Hazelbrook, Newrath	2	Waterford Dove Housing Association	""	""	""	""	""	Q1-2018
1402	1402	CAS CONSTRUCTION	Kilkenny	Good Shepherd Centre - Wing 1952	12	The Good Shepherd Centre (Kilkenny) Ltd	""	""	""	""	""	Q4-2018
1403	1403	CAS CONSTRUCTION	Kilkenny	Brooke House, Thomastown	5	Camphill Communities of Ireland	""	""	""	""	""	Q3-2017
1404	1404	CAS CONSTRUCTION	Kilkenny	Friary Walk, Callan	12	Cluid Housing Association	""	""	""	""	""	Q3-2016
1405	1405	CAS CONSTRUCTION	Kilkenny	Garden Cottage, The Workhouse, Callan	1	Camphill Communities of Ireland	""	""	""	""	""	Q4-2017
1406	1406	CAS CONSTRUCTION	Kilkenny	Red Barn, Patrick Street, Ballyragget	11	Good Shepherd Services Ltd	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
1407	1407	CAS CONSTRUCTION	Kilkenny	Smith's Road, Ballyraggett	4	Oaklee Housing Trust	""	""	""	""	""	Q4-2018
1408	1408	CAS CONSTRUCTION	Kilkenny	8/9 Kilkenny Street, Castlecomer	3	Good Shepherd Services Ltd	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
1409	1409	CAS CONSTRUCTION	Kilkenny	19/21 Blackmill Street, Kilkenny	12	Good Shepherd Services Ltd	""	""	""	""	Q4-2021	""
1410	1410	CAS CONSTRUCTION	Kilkenny	Brother Thomas Place, Church Lane, Kilkenny	12	Good Shepherd Services Ltd	""	""	""	""	Q2-2021	""
1411	1411	CAS CONSTRUCTION	Kilkenny	Bridge Street, Callan	6	Good Shepherd Services Ltd	""	""	""	""	""	Q4-2019
1412	1412	CAS CONSTRUCTION	Kilkenny	Grennan Villa, Thomastown	5	Camphill Communities of Ireland	""	""	""	""	Q3-2020	""
1413	1413	CAS CONSTRUCTION	Kilkenny	Fiennes Court, William Street, Kilkenny	7	Good Shepherd Services Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1414	1414	CAS CONSTRUCTION	Kilkenny	The Round House, Kells, Co. Kilkenny	4	SOS Kilkenny Housing Association Ltd	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
1415	1415	CAS CONSTRUCTION	Kilkenny	Ladywell Street, Thomastown, Co. Kilkenny	6	Good Shepherd Services Ltd	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1416	1416	CAS CONSTRUCTION	Kilkenny	Dinan lodge,Suttonsrath, Jenkinstown, Co. Kilkenny	4	Kilkenny Voluntary Housing Association	Stage 1 approved Q4-2020, outline design and costs being prepared.	""	""	""	""	""
1417	1417	CAS CONSTRUCTION	Kilkenny	Maudlin Street, Thomastown, Co. Kilkenny	10	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1418	1418	CAS CONSTRUCTION	Kilkenny	Mill Street, Callan, Co. Kilkenny	12	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1419	1419	CAS CONSTRUCTION	Kilkenny	Prague House Hall, Freshford, Co. Kilkenny	8	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1420	1420	CALF Turnkey	Kilkenny	Castlehyde, Rosbercon (Phase 1)	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
1421	1421	CALF Turnkey	Kilkenny	Castlehyde, Rosbercon (Phase 2)	6	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
1422	1422	CALF Turnkey	Kilkenny	Cois Na Bearu, Graiguenemanagh, Kilkenny (Phase 1)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
1423	1423	CALF Turnkey	Kilkenny	Golf Links Road, Kilkenny (Phase 1)*	39	Respond	""	""	""	""	""	Q4-2019
1424	1424	CALF Turnkey	Kilkenny	Logan Square, Thomastown, Co Kilkenny (Phase 1)*	16	Oaklee Housing	""	""	""	""	""	Q2-2017
1425	1425	CALF Turnkey	Kilkenny	Love Lane, Castlecomer, Co. Kilkenny (Phase 1)	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2019
1426	1426	CALF Turnkey	Kilkenny	Margaret’s Field, Callan Road, Kilkenny City (Phase 1)	40	Respond	""	""	""	""	""	Q2-2021
1427	1427	CALF Turnkey	Kilkenny	Nuncio Road, Kilkenny (Phase 1)	28	Respond	""	""	""	""	""	Q4-2020
1428	1428	CALF Turnkey	Kilkenny	Nuncio Road, Kilkenny (Phase 2)*	22	Respond	""	""	""	""	Q4-2018	""
1429	1429	CALF Turnkey	Kilkenny	O’Loughlin Court, Kilkenny  (Phase 1)	2	Respond	""	""	""	""	""	Q4-2018
1430	1430	CALF Turnkey	Kilkenny	Orchard Close, Kilkenny (Phase 1)*	23	Clúid Housing	""	""	""	""	Q4-2020	""
1431	1431	CALF Construction	Kilkenny	Park Lane, Friary Walk, Callan, Co Kilkenny (Phase 1)*	16	Clúid Housing	""	""	""	""	""	Q2-2019
1432	1432	CALF Turnkey	Kilkenny	Side Road, Moneenroe, Castlecomer, Co. Kilkenny (Phase 1)	9	Oaklee Housing	""	""	""	""	""	Q3-2018
1433	1433	CALF Construction	Kilkenny	Walkin St Kilkenny (Phase 1)	27	Oaklee Housing	""	""	""	""	""	Q4-2019
1434	1434	SHIP CONSTRUCTION TURNKEY	Laois	Priory, Borris in Ossory	6	*N/A	""	""	""	""	""	Q4-2020
1435	1435	SHIP CONSTRUCTION TURNKEY	Laois	Priory, Borris in Ossory	5	*N/A	""	""	""	""	Q2-2020	""
1436	1436	SHIP CONSTRUCTION TURNKEY	Laois	Clonaslee	7	*N/A	""	""	""	""	""	Q4-2020
1437	1437	SHIP CONSTRUCTION TURNKEY	Laois	Church Ave., Stradbally	20	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1438	1438	SHIP CONSTRUCTION TURNKEY	Laois	Bruach Na Habhainn, Killeen, Maganey	4	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1439	1439	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan, Co Laois	2	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1440	1440	SHIP CONSTRUCTION TURNKEY	Laois	Market Square, Portarlington	18	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1441	1441	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard Ballylynan	3	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1442	1442	SHIP CONSTRUCTION TURNKEY	Laois	Church Avenue, Stradbally	11	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1443	1443	SHIP CONSTRUCTION SINGLE STAGE	Laois	Harpurs Lane, Portlaoise	1	*N/A	""	""	""	""	""	Q4-2019
1444	1444	SHIP CONSTRUCTION SINGLE STAGE	Laois	Hillview, Portlaoise	2	*N/A	""	""	""	""	""	Q4-2020
1445	1445	SHIP CONSTRUCTION SINGLE STAGE	Laois	Coolroe, Ballybrittas	1	*N/A	""	""	""	""	Q4-2020	""
1446	1446	SHIP CONSTRUCTION SINGLE STAGE	Laois	The Orchard, Stradbally	6	*N/A	""	""	""	""	""	Q1-2020
1447	1447	SHIP CONSTRUCTION	Laois	Moore Street, Rathdowney	6	*N/A	""	""	""	""	Q3-2020	""
1448	1448	SHIP CONSTRUCTION	Laois	Ballymorris Road, Portarlington	22	*N/A	""	""	""	""	""	Q2-2021
1449	1449	SHIP CONSTRUCTION	Laois	Gleann na Glaise, Ballyroan	10	*N/A	""	""	""	""	Q4-2020	""
1450	1450	SHIP CONSTRUCTION	Laois	Pattison Est. Mountmellick	10	*N/A	""	""	""	""	Q4-2020	""
1451	1451	SHIP CONSTRUCTION	Laois	Shannon Street, Mountrath	6	*N/A	""	""	""	""	""	Q2-2021
1452	1452	SHIP CONSTRUCTION	Laois	Conniberry Way, Old Knockmay Road, Portlaoise	33	*N/A	""	""	""	""	""	Q2-2018
1453	1453	SHIP CONSTRUCTION	Laois	Harbour Court, Mountmellick	6	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
1454	1454	SHIP CONSTRUCTION	Laois	Mooreville, Rathdowney	7	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1455	1455	SHIP CONSTRUCTION	Laois	Sean Doire, Cork Road, Durrow	22	*N/A	""	""	""	""	Q4-2020	""
1456	1456	SHIP CONSTRUCTION	Laois	St Kieran's Park, Errill	14	*N/A	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
1457	1457	SHIP CONSTRUCTION	Laois	Clonrooske, Knockmay	11	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
1458	1458	SHIP CONSTRUCTION	Laois	Carraig Glas, Stradbally	26	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1459	1459	SHIP CONSTRUCTION	Laois	Iona,Abbeyleix Rd., Portlaoise	9	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1460	1460	SHIP CONSTRUCTION	Laois	Ballyadams	1	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1461	1461	SHIP CONSTRUCTION	Laois	Doonane	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1462	1462	SHIP CONSTRUCTION	Laois	Durrow	18	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1463	1463	CAS CONSTRUCTION	Laois	Presentation Convent & Lands, Portlaoise, 	51	Sophia Housing Association Ltd	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1464	1464	CAS CONSTRUCTION	Laois	County Hotel, Portlaoise	10	Cluid Housing Association	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
1465	1465	CALF Turnkey	Laois	Ballickmoyler, Graiguecullen, Laois (Phase 1)*	20	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1466	1466	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 1)	12	Clúid Housing	""	""	""	""	Q2-2021	""
1467	1467	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 2)	20	Clúid Housing	""	""	""	""	Q2-2021	""
1468	1468	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 3)	14	Clúid Housing	""	""	""	""	Q2-2021	""
1469	1469	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 1)"	4	Clúid Housing	""	""	""	""	""	Q3-2019
1470	1470	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 2)"	6	Clúid Housing	""	""	""	""	""	Q4-2019
1471	1471	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 3)"	5	Clúid Housing	""	""	""	""	""	Q2-2020
1472	1472	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 4)*"	9	Clúid Housing	""	""	""	""	""	Q1-2021
1473	1473	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 5)*"	6	Clúid Housing	""	""	""	""	""	Q3-2021
1474	1474	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 1)*	9	Tuath Housing Association	""	""	""	""	""	Q3-2020
1475	1475	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 2)*	8	Tuath Housing Association	""	""	""	""	""	Q3-2020
1476	1476	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 3)	10	Tuath Housing Association	""	""	""	""	""	Q4-2020
1477	1477	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 4)	9	Tuath Housing Association	""	""	""	""	""	Q1-2021
1478	1478	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 1)	14	Clúid Housing	""	""	""	""	Q4-2018	""
1479	1479	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 2)*	6	Clúid Housing	""	""	""	""	Q4-2018	""
1480	1480	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 3)	12	Clúid Housing	""	""	""	""	Q4-2018	""
1481	1481	CALF Turnkey	Laois	Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 1)	17	Tuath Housing Association	""	""	""	""	""	Q3-2018
1482	1482	CALF Turnkey	Laois	Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 2)	9	Tuath Housing Association	""	""	""	""	""	Q4-2018
1483	1483	CALF Turnkey	Laois	Corrig Glen, Station Road, Portarlington, Co. Laois (Phase 3)	13	Tuath Housing Association	""	""	""	""	""	Q4-2018
1484	1484	CALF Turnkey	Laois	Doirinn Alainn, Ballylynan, Co. Laois (Phase 1)	2	North & East Housing Association Ltd	""	""	""	""	""	Q3-2020
1485	1485	CALF Turnkey	Laois	Doirinn Alainn, Ballylynan, Co. Laois (Phase 2)	4	North & East Housing Association Ltd	""	""	""	""	""	Q4-2020
1486	1486	CALF Turnkey	Laois	Doirinn Alainn, Ballylynan, Co. Laois (Phase 3)*	6	North & East Housing Association Ltd	""	""	""	""	""	Q2-2021
1487	1487	CALF Turnkey	Laois	Droimnin, Stradbally, Co Laois  (Phase 1)	6	Clúid Housing	""	""	""	""	""	Q3-2018
1488	1488	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 1)	13	Clúid Housing	""	""	""	""	Q3-2021	""
1489	1489	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 2)	24	Clúid Housing	""	""	""	""	Q3-2021	""
1490	1490	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 3)	30	Clúid Housing	""	""	""	""	Q3-2021	""
1491	1491	CALF Turnkey	Laois	Harpurs Lane, Portlaoise, Co. Laois (Phase 1)*	44	Respond	""	""	""	""	Q2-2021	""
1492	1492	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 1)	10	Clúid Housing	""	""	""	""	""	Q3-2021
1493	1493	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 2)	10	Clúid Housing	""	""	""	""	Q3-2018	""
1494	1494	CALF Construction	Laois	Kirwan Park, Mountmellick, Co Laois  (Phase 1)	2	Clúid Housing	""	""	""	""	""	Q2-2018
1495	1495	CALF Turnkey	Laois	Knockmay Mews, Old Knockmay Road, Portlaoise, Co. Laois (Phase 1)	3	Tuath Housing Association	""	""	""	""	""	Q3-2020
1496	1496	CALF Turnkey	Laois	Lake Drive, Kilminchy, Portlaoise, Co. Laois (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1497	1497	CALF Turnkey	Laois	Main Street, Stradbally, Co. Laois (Phase 1)	16	North & East Housing Association Ltd	""	""	""	""	""	Q3-2020
1498	1498	CALF Turnkey	Laois	Phase 2 The Glen, Kilnacourt, Portarlington, Co Laois (Phase 1)	18	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1499	1499	CALF Turnkey	Laois	Phase 3 The Glen, Kilnacourt, Portarlington, Co Laois. (Phase 1)	8	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2021
1500	1500	CALF Construction	Laois	POST TENDER - Cluinin  Mountrath, Co. Laois (Phase 1)	11	Oaklee Housing	""	""	""	""	""	Q1-2018
1501	1501	CALF Turnkey	Laois	Rathillion, Killeshin, Co. Laois (Phase 1)*	4	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1502	1502	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 1)	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
1503	1503	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 2)	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
1504	1504	CALF Turnkey	Laois	South Dublin Road, Portlaoise, Co. Laois (Phase 3)*	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q1-2020	""
1505	1505	CALF Turnkey	Laois	Spa Street, Droughill, Portarlington, Co. Laois (Phase 1)*	26	Oaklee Housing	""	""	""	""	Q4-2020	""
1506	1506	CALF Turnkey	Laois	The Glen, Kilnacourt, Portarlington, Co. Laois (Phase 1)	18	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2020
1507	1507	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 1)*	15	Clúid Housing	""	""	""	""	Q1-2020	""
1508	1508	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 2)*	40	Clúid Housing	""	""	""	""	Q1-2020	""
1509	1509	CALF Turnkey	Laois	The Meadows, Mountrath Road, Portlaoise, Co. Laois (Phase 1)*	48	Clúid Housing	""	""	""	Q3-2021	""	""
1510	1510	CALF Turnkey	Laois	The Springs, Kilminchy, Portlaoise, Co Laois (Phase 1)*	24	Clúid Housing	""	""	""	""	Q2-2021	""
1511	1511	CALF Turnkey	Laois	The Springs, Kilminchy, Portlaoise, Co Laois (Phase 2)	19	Clúid Housing	""	""	""	""	Q2-2021	""
1512	1512	CALF Turnkey	Laois	Wilton Lawns, Portarlington, Co. Laois (Phase 1)	2	Respond	""	""	""	Q1-2021	""	""
1513	1513	SHIP CONSTRUCTION TURNKEY	Leitrim	Roosky	7	*N/A	""	""	""	""	""	Q4-2019
1514	1514	SHIP CONSTRUCTION TURNKEY	Leitrim	Drumshanbo	9	*N/A	""	""	""	""	""	Q3-2019
1515	1515	SHIP CONSTRUCTION TURNKEY	Leitrim	Church Lane, Ballinamore	9	*N/A	""	""	""	""	""	Q4-2021
1516	1516	SHIP CONSTRUCTION TURNKEY	Leitrim	Druminshingore, Newtowngore	2	*N/A	""	""	""	""	""	Q4-2021
1517	1517	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	5	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
1518	1518	SHIP CONSTRUCTION TURNKEY	Leitrim	Oakgrove, Kinlough	5	*N/A	""	""	""	""	""	Q4-2020
1519	1519	SHIP CONSTRUCTION TURNKEY	Leitrim	Ard na Drise, Mohill	3	*N/A	""	""	""	""	""	Q4-2020
1520	1520	SHIP CONSTRUCTION TURNKEY	Leitrim	Ard na Drise, Mohill	2	*N/A	""	""	""	""	""	Q1-2021
1521	1521	SHIP CONSTRUCTION TURNKEY	Leitrim	Lough Meen Estate, Drumkeerin	2	*N/A	""	""	""	""	""	Q4-2021
1522	1522	SHIP CONSTRUCTION TURNKEY	Leitrim	Commons Lane, Manorhamilton	4	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
1523	1523	SHIP CONSTRUCTION TURNKEY	Leitrim	Cluain Oir, Liscara, Carrick on Shannon	2	*N/A	""	""	""	""	""	Q2-2021
1524	1524	SHIP CONSTRUCTION TURNKEY	Leitrim	Manorhamilton & Carrigallen	2	*N/A	""	""	""	""	""	Q3-2021
1525	1525	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Breffni Cres., 53 St. Patricks Park Site, Carrick on Shannon	2	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1526	1526	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Druminshingore Td., Newtowngore	3	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1527	1527	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Dromahair Td., Dromahair	4	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1528	1528	SHIP CONSTRUCTION RENEWAL	Leitrim	Sean McDermott St., Manorhamilton	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1529	1529	SHIP CONSTRUCTION	Leitrim	Autumn View, Summerhill, Carrick on Shannon	27	*N/A	""	""	""	""	""	Q4-2021
1530	1530	SHIP CONSTRUCTION	Leitrim	Taobh Tire, Manorhamilton (Phase 2)	7	*N/A	""	""	""	""	""	Q4-2018
1531	1531	SHIP CONSTRUCTION	Leitrim	Taobh Tire, Manorhamilton (Phase 3)	5	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1532	1532	SHIP CONSTRUCTION	Leitrim	Townparks, Carrick on Shannon	12	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1533	1533	SHIP CONSTRUCTION	Leitrim	Lahard, Ballinamore	10	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1534	1534	CAS CONSTRUCTION	Leitrim	Ballinamore	2	Society of Saint Vincent de Paul	""	""	""	""	""	Q4-2017
1535	1535	CALF Turnkey	Leitrim	Cnoc an Luir, Drumshanbo, Co. Leitrim (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q4-2019
1536	1536	SHIP CONSTRUCTION TURNKEY	Limerick	Woodlawn Park, Ballysimon Road, Limerick	9	*N/A	""	""	""	""	""	Q4-2019
1537	1537	SHIP CONSTRUCTION TURNKEY	Limerick	Woodlawn Park, Ballysimon Road, Limerick	1	*N/A	""	""	""	""	""	Q4-2019
1538	1538	SHIP CONSTRUCTION TURNKEY	Limerick	Carraig Desmond, Newcastle West	8	*N/A	""	""	""	""	""	Q4-2019
1539	1539	SHIP CONSTRUCTION TURNKEY	Limerick	Knocklong	2	*N/A	""	""	""	""	""	Q4-2020
1540	1540	SHIP CONSTRUCTION TURNKEY	Limerick	Carraig Desmond, Newcastle West	2	*N/A	""	""	""	""	""	Q4-2019
1541	1541	SHIP CONSTRUCTION TURNKEY	Limerick	Redgate Close, Old Cratloe Road, Limerick City	14	*N/A	""	""	""	""	Q1-2020	""
1542	1542	SHIP CONSTRUCTION TURNKEY	Limerick	The Orchard, Main Street, Pallaskenry	8	*N/A	""	""	""	""	Q1-2020	""
1543	1543	SHIP CONSTRUCTION TURNKEY	Limerick	Gortboy, Charleville Road, kiImallock	33	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1544	1544	SHIP CONSTRUCTION TURNKEY	Limerick	The Orchard, Main Street, Pallaskenry	8	*N/A	""	""	""	""	Q1-2020	""
1545	1545	SHIP CONSTRUCTION TURNKEY	Limerick	Knocklong	5	*N/A	""	""	""	""	Q2-2021	""
1546	1546	SHIP CONSTRUCTION RAPID	Limerick	Faha View, Patrickswell	16	*N/A	""	""	""	""	""	Q4-2019
1547	1547	SHIP CONSTRUCTION RAPID	Limerick	Old Christians Site, Rathbane	43	*N/A	""	""	""	""	""	Q2-2021
1548	1548	SHIP CONSTRUCTION RAPID	Limerick	Barnakyle, Patrickswell (Site 2)	24	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
1549	1549	SHIP CONSTRUCTION	Limerick	Patrick’s Villas, Castleconnell	4	*N/A	""	""	""	""	""	Q4-2020
1550	1550	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhill Road 	14	*N/A	""	""	""	""	Q1-2020	""
1551	1551	SHIP CONSTRUCTION	Limerick	Gough Place, Rosbrien Road, Limerick	17	*N/A	""	""	""	""	Q4-2020	""
1552	1552	SHIP CONSTRUCTION	Limerick	Burke Avenue, Limerick City	12	*N/A	""	""	""	""	""	Q4-2019
1553	1553	SHIP CONSTRUCTION	Limerick	Fannings Corner, Limerick City	3	*N/A	""	""	""	""	""	Q4-2019
1554	1554	SHIP CONSTRUCTION	Limerick	Wallers Well, Limerick City (Phase 2)	13	*N/A	""	""	""	""	""	Q4-2020
1555	1555	SHIP CONSTRUCTION	Limerick	Clonmacken, Limerick City	43	*N/A	""	""	""	""	Q3-2019	""
1556	1556	SHIP CONSTRUCTION	Limerick	Glenview Drive, Hospital	20	*N/A	""	""	""	""	Q3-2020	""
1557	1557	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	7	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1558	1558	SHIP CONSTRUCTION	Limerick	Hasset Villas, Thomondgate	3	*N/A	""	""	""	""	""	Q4-2018
1559	1559	SHIP CONSTRUCTION	Limerick	Kilmurry Court, Garryowen	7	*N/A	""	""	""	""	""	Q4-2019
1560	1560	SHIP CONSTRUCTION	Limerick	Rathbane Road, Limerick City	2	*N/A	""	""	""	""	""	Q1-2019
1561	1561	SHIP CONSTRUCTION	Limerick	Sycamore Avenue, Limerick City	5	*N/A	""	""	""	""	""	Q3-2019
1562	1562	SHIP CONSTRUCTION	Limerick	Lower Carey's Road, Limerick City	11	*N/A	""	""	""	""	""	Q1-2021
1563	1563	SHIP CONSTRUCTION	Limerick	Kileely Road, Moyross	5	*N/A	""	""	""	""	""	Q2-2021
1564	1564	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	2	*N/A	""	""	""	""	""	Q4-2017
1565	1565	SHIP CONSTRUCTION	Limerick	Knocklong	12	*N/A	""	""	""	""	Q3-2021	""
1566	1566	SHIP CONSTRUCTION	Limerick	Colbert Terrace, Abbeyfeale	4	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1567	1567	SHIP CONSTRUCTION	Limerick	St. Michael's Court, Watergate Flats, 	9	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
1568	1568	SHIP CONSTRUCTION	Limerick	Ballygrennan Road, Limerick City	2	*N/A	""	""	""	""	""	Q4-2017
1569	1569	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhills Road	3	*N/A	""	""	""	""	Q2-2020	""
1570	1570	SHIP CONSTRUCTION	Limerick	Clueing Dara, Broadford, Limerick	18	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1571	1571	SHIP CONSTRUCTION	Limerick	Sycamore Crescent, Newcastle West, Co Limerick	21	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
1572	1572	SHIP CONSTRUCTION	Limerick	Radharc an Ghleanna, Mountcollins	4	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1573	1573	SHIP CONSTRUCTION	Limerick	O’Connor Park, Ardagh, Co. Limerick	8	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1574	1574	SHIP CONSTRUCTION	Limerick	Church Glen, Ballylanders, Co. Limerick	9	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
1575	1575	SHIP CONSTRUCTION	Limerick	Radharc Cillin, Kilfinane, Co. Limerick	10	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
1576	1576	SHIP CONSTRUCTION	Limerick	Ballycummin Road, Raheen, Co. Limerick	19	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1577	1577	REGENERATION	Limerick	Lord Edward Street, P2: Main Contract	79	*N/A	""	""	""	""	""	Q4-2017
1578	1578	REGENERATION	Limerick	Lord Edward Street, P2: Main Contract	2	*N/A	""	""	""	""	""	Q1-2017
1579	1579	REGENERATION	Limerick	Sheep / Athlunkards Street	8	Túath Housing Association Ltd	""	""	Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.	""	""	""
1580	1580	REGENERATION	Limerick	Churchfield	19	*N/A	""	""	""	""	""	Q1-2018
1581	1581	REGENERATION	Limerick	Churchfield (Phase 2)	38	Cluid Housing Association	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1582	1582	REGENERATION	Limerick	Cosgrave Park	30	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1583	1583	REGENERATION	Limerick	Orchard Site	27	Oaklee Housing Trust	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
1584	1584	REGENERATION	Limerick	176 & 177 Cliona Park	2	*N/A	""	""	""	""	""	Q2-2016
1585	1585	REGENERATION	Limerick	Cliona Park (Phase 2)	10	*N/A	""	""	""	""	""	Q2-2017
1586	1586	REGENERATION	Limerick	8-10 Gaol Lane	3	*N/A	""	""	""	""	""	Q4-2016
1587	1587	REGENERATION	Limerick	1 3 Weston Gardens	3	*N/A	""	""	""	""	""	Q2-2016
1588	1588	REGENERATION	Limerick	2016 Moyross Rebuild	6	*N/A	""	""	""	""	""	Q4-2016
1589	1589	REGENERATION	Limerick	2016 Southhill Rebuild	8	*N/A	""	""	""	""	""	Q4-2016
1590	1590	REGENERATION	Limerick	2016 St. Mary's Park Rebuild	9	*N/A	""	""	""	""	""	Q4-2016
1591	1591	REGENERATION	Limerick	Ballinacurra Weston Vacant Refurbs, Lot 1 & 2**	14	*N/A	""	""	""	""	""	Q4-2016
1592	1592	REGENERATION	Limerick	St. Mary's Park Infills	15	*N/A	""	""	""	""	""	Q4-2018
1593	1593	REGENERATION	Limerick	Cliona Park (Phase 3)	18	Túath Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1594	1594	REGENERATION	Limerick	45A-46A Cliona Park	2	*N/A	""	""	""	""	""	Q3-2021
1595	1595	REGENERATION	Limerick	Dalgaish Park	27	*N/A	""	""	Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.	""	""	""
1596	1596	REGENERATION	Limerick	2017 St Mary's Park Rebuild	1	*N/A	""	""	""	""	""	Q4-2017
1597	1597	REGENERATION	Limerick	2017 Ballinacurra Weston Rebuild	1	*N/A	""	""	""	""	""	Q4-2017
1598	1598	REGENERATION	Limerick	2017 Southill Rebuilds	13	*N/A	""	""	""	""	""	Q4-2017
1599	1599	REGENERATION	Limerick	2017 Moyross Rebuild	1	*N/A	""	""	""	""	""	Q4-2017
1600	1600	REGENERATION	Limerick	Churchfield	23	*N/A	""	""	""	""	""	Q2-2018
1601	1601	REGENERATION	Limerick	St. Mary's Park Infills	4	*N/A	""	""	""	""	""	Q1-2019
1602	1602	REGENERATION	Limerick	Infills Carew Park, Southhill and Moyross 	38	Peter McVerry Trust Ltd	""	""	""	""	Q1-2021	""
1603	1603	REGENERATION	Limerick	2019 Rebuilds (Southill, Moyross, St Mary's Park and Ballinacurra Weston)	8	*N/A	""	""	""	""	""	Q4-2019
1604	1604	CAS CONSTRUCTION TURNKEY	Limerick	Carebright Community, Ardykeohane, Bruff	6	Carebright Ltd	""	""	""	""	""	Q1-2019
1605	1605	CAS CONSTRUCTION TURNKEY	Limerick	Barrack Mews, Brennan's Row, Cathedral Place	2	Arlington Novas Ireland Ltd	""	""	""	""	""	Q4-2019
1606	1606	CAS CONSTRUCTION TURNKEY	Limerick	Barrack Mews, Brennan's Row, Cathedral place	3	Arlington Novas Ireland Ltd	""	""	""	""	""	Q1-2020
1607	1607	CAS CONSTRUCTION TURNKEY	Limerick	Barrack Mews, Brennan's Row, Cathedral place	1	Arlington Novas Ireland Ltd	""	""	""	""	""	Q2-2020
1608	1608	CAS CONSTRUCTION	Limerick	Towerfield Crescent, Croom	16	Croom Voluntary Housing Association Ltd	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
1609	1609	CAS CONSTRUCTION	Limerick	Cappamore	10	Cappamore Housing Association Ltd	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1610	1610	CAS CONSTRUCTION	Limerick	Speakers Corner, Limerick City	4	Simon Community : Midwest Simon	""	""	""	""	""	Q3-2018
1611	1611	CAS CONSTRUCTION	Limerick	Cuan Mhuire, Bruree	6	Cuan Mhuire Teoranta	""	""	""	""	""	Q3-2018
1612	1612	CAS CONSTRUCTION	Limerick	Mirth, Thomondgate	18	Associated Charities Trust Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1613	1613	CAS CONSTRUCTION	Limerick	Cois na Feile, Abbeyfeale 	12	Cluid Housing Association	""	""	""	""	""	Q4-2016
1614	1614	CAS CONSTRUCTION	Limerick	2/3 Mallow Street	12	Peter McVerry Trust Ltd	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
1615	1615	CAS CONSTRUCTION	Limerick	St. Pauls Convent, Kilfinane	9	Sophia Housing Association Ltd	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
1616	1616	CAS CONSTRUCTION	Limerick	McGarry House, 7 Alphonsus Street	8	Arlington Novas Ireland Ltd	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1617	1617	CAS CONSTRUCTION	Limerick	47 & 48 Main Street, Croom, Limerick	4	Croom Voluntary Housing Association Ltd	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
1618	1618	CAS CONSTRUCTION	Limerick	58 Henry Street	5	Simon Community : Midwest Simon	""	""	""	""	Q1-2021	""
1619	1619	CAS CONSTRUCTION	Limerick	28/29 Lower Gerald Griffin Street, Limerick	4	Peter McVerry Trust Ltd	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1620	1620	CAS CONSTRUCTION	Limerick	42 St Joseph's Street, Limerick	3	Peter McVerry Trust Ltd	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1621	1621	CALF Turnkey	Limerick	19 and 20 Castleview Shopping Centre Castleconnell  Limerick (Phase 1)	2	Focus Housing Association CLG	""	""	""	""	""	Q4-2021
1622	1622	CALF Turnkey	Limerick	Ballygrennan Close, Moyross, Limerick  (Phase 1)	2	Respond	""	""	""	""	""	Q4-2018
1623	1623	CALF Turnkey	Limerick	Ballygrennan Close, Moyross, Limerick  (Phase 2)	2	Respond	""	""	""	""	""	Q4-2018
1624	1624	CALF Turnkey	Limerick	Ballygrennan Close, Moyross, Limerick  (Phase 3)	2	Respond	""	""	""	""	""	Q4-2018
1625	1625	CALF Turnkey	Limerick	Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 1)	46	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
1626	1626	CALF Turnkey	Limerick	Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 2)*	25	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
1627	1627	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 1)*	52	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1628	1628	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 2)	28	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1629	1629	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 3)*	23	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1630	1630	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 4)*	34	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1631	1631	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 1)*	35	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1632	1632	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 2)	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
1633	1633	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 3)*	21	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
1634	1634	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 4)*	20	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
1635	1635	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 5)*	22	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
1636	1636	CALF Turnkey	Limerick	Cluain Ard, Fedamore, Co Limerick  (Phase 1)	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2018
1637	1637	CALF Turnkey	Limerick	Cluain Ard, Fedamore, Co Limerick  (Phase 2)	2	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2018
1638	1638	CALF Turnkey	Limerick	Cois Carraig, Clarina Village, Clarina, Co. Limerick (Phase 1)	18	Clúid Housing	""	""	""	""	""	Q4-2020
1639	1639	CALF Turnkey	Limerick	Dromsally Woods, Cappamore, Co. Limerick (Phase 1)	5	Focus Housing Association CLG	""	""	""	""	Q3-2020	""
1640	1640	CALF Construction	Limerick	Hyde Road, Limerick City (Phase 1)	20	Clúid Housing	""	""	""	""	""	Q1-2018
1641	1641	CALF Turnkey	Limerick	Laurelville, Mill Road, Corbally, Limerick (Phase 1)	4	Clúid Housing	""	""	""	""	Q3-2018	""
1642	1642	CALF Turnkey	Limerick	Laurelville, Mill Road, Corbally, Limerick (Phase 2)*	9	Clúid Housing	""	""	""	""	Q3-2018	""
1643	1643	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 1)	8	Clúid Housing	""	""	""	""	""	Q2-2021
1644	1644	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 2)*	23	Clúid Housing	""	""	""	""	Q3-2018	""
1645	1645	CALF Turnkey	Limerick	Newtown, Castletroy, Limerick (Phase 1)*	31	Clúid Housing	""	""	""	Q2-2021	""	""
1646	1646	CALF Turnkey	Limerick	Old Dublin Road, Rhebogue, Limerick (Phase 1)*	16	Focus Housing Association CLG	""	""	""	""	Q1-2021	""
1647	1647	CALF Turnkey	Limerick	Phase 2 Newtown Meadows, Castletroy, Limerick (Phase 1)*	32	Clúid Housing	""	""	""	Q4-2021	""	""
1648	1648	CALF Turnkey	Limerick	Revised - Ard Aulin, Mungret, Co Limerick (Phase 1)	7	Clúid Housing	""	""	""	""	""	Q2-2017
1649	1649	CALF Turnkey	Limerick	Toormore, Main Street, Bruree, Co. Limerick (Phase 1)	16	Clúid Housing	""	""	""	""	""	Q2-2021
1650	1650	CALF Construction	Limerick	Turragh Crescent, Cappamore, Limerick (Phase 1)	15	Clúid Housing	""	""	""	Q3-2021	""	""
1651	1651	CALF Turnkey	Limerick	Woodfield Manor, Cloonyscrehane, Newcastle West (Phase 1)*	19	Clúid Housing	""	""	""	""	Q3-2020	""
1652	1652	CALF Turnkey	Limerick	Woodfield Manor, Cloonyscrehane, Newcastle West (Phase 2)	11	Clúid Housing	""	""	""	""	Q3-2020	""
1653	1653	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	14	*N/A	""	""	""	""	""	Q4-2017
1654	1654	SHIP CONSTRUCTION TURNKEY	Longford	Knock, Lanesborough	4	*N/A	""	""	""	""	""	Q3-2018
1655	1655	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	2	*N/A	""	""	""	""	""	Q1-2018
1656	1656	SHIP CONSTRUCTION TURNKEY	Longford	Ballinamuck	7	*N/A	""	""	""	""	""	Q4-2018
1657	1657	SHIP CONSTRUCTION TURNKEY	Longford	Ballinamuck	4	*N/A	""	""	""	""	""	Q3-2019
1658	1658	SHIP CONSTRUCTION TURNKEY	Longford	Ballinamuck	6	*N/A	""	""	""	""	""	Q4-2019
1659	1659	SHIP CONSTRUCTION TURNKEY	Longford	Rock View, Cloondara	5	*N/A	""	""	""	""	""	Q4-2018
1660	1660	SHIP CONSTRUCTION TURNKEY	Longford	Greville Court, Granard	14	*N/A	""	""	""	""	""	Q4-2019
1661	1661	SHIP CONSTRUCTION TURNKEY	Longford	Knock, Lanesborough	29	*N/A	""	""	""	""	""	Q4-2018
1662	1662	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	2	*N/A	""	""	""	""	""	Q4-2019
1663	1663	SHIP CONSTRUCTION TURNKEY	Longford	Carragh, Granard	4	*N/A	""	""	""	""	""	Q3-2019
1664	1664	SHIP CONSTRUCTION TURNKEY	Longford	Church Street, Edgeworthstown	5	*N/A	""	""	""	""	""	Q3-2020
1665	1665	SHIP CONSTRUCTION TURNKEY	Longford	Smithfield, Legan	18	*N/A	""	""	""	""	""	Q3-2020
1666	1666	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	4	*N/A	""	""	""	""	""	Q4-2019
1667	1667	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	4	*N/A	""	""	""	""	""	Q2-2019
1668	1668	SHIP CONSTRUCTION TURNKEY	Longford	Carragh, Granard	6	*N/A	""	""	""	""	""	Q4-2019
1669	1669	SHIP CONSTRUCTION TURNKEY	Longford	Carragh, Granard	4	*N/A	""	""	""	""	""	Q2-2019
1670	1670	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	4	*N/A	""	""	""	""	""	Q3-2019
1671	1671	SHIP CONSTRUCTION TURNKEY	Longford	 Abhainn Glas, Edgeworthstown	4	*N/A	""	""	""	""	""	Q4-2019
1672	1672	SHIP CONSTRUCTION TURNKEY	Longford	Caislean Breac, Newtownforbes	2	*N/A	""	""	""	""	""	Q4-2019
1673	1673	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	4	*N/A	""	""	""	""	""	Q1-2020
1674	1674	SHIP CONSTRUCTION TURNKEY	Longford	Carragh, Granard	4	*N/A	""	""	""	""	""	Q4-2019
1675	1675	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	2	*N/A	""	""	""	""	""	Q4-2019
1676	1676	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	6	*N/A	""	""	""	""	""	Q4-2020
1677	1677	SHIP CONSTRUCTION TURNKEY	Longford	Carragh, Granard	7	*N/A	""	""	""	""	""	Q4-2019
1678	1678	SHIP CONSTRUCTION TURNKEY	Longford	Slí Corglass, Legga	4	*N/A	""	""	""	""	""	Q1-2021
1679	1679	SHIP CONSTRUCTION TURNKEY	Longford	Radharc Na Muileann, Knock, Lanesborough	2	*N/A	""	""	""	""	""	Q4-2019
1680	1680	SHIP CONSTRUCTION TURNKEY	Longford	Pearse Drive, Longford Town	1	*N/A	""	""	""	""	""	Q4-2019
1681	1681	SHIP CONSTRUCTION TURNKEY	Longford	Cartrons, Kenagh	5	*N/A	""	""	""	""	""	Q4-2020
1682	1682	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	4	*N/A	""	""	""	""	""	Q3-2020
1683	1683	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	8	*N/A	""	""	""	""	""	Q1-2021
1684	1684	SHIP CONSTRUCTION TURNKEY	Longford	Mill Race Park, Drumlish	1	*N/A	""	""	""	""	""	Q4-2020
1685	1685	SHIP CONSTRUCTION TURNKEY	Longford	Campbell's Drive, Campbell's Lane, Longford	6	*N/A	""	""	""	""	""	Q3-2021
1686	1686	SHIP CONSTRUCTION TURNKEY	Longford	O'Hara Site, Connaught Rd.,Longford	14	*N/A	""	""	""	""	Q1-2021	""
1687	1687	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	2	*N/A	""	""	""	""	""	Q4-2020
1688	1688	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill (Phase 2)	4	*N/A	""	""	""	""	""	Q4-2021
1689	1689	SHIP CONSTRUCTION TURNKEY	Longford	Slí Corglass, Legga	4	*N/A	""	""	""	""	""	Q2-2021
1690	1690	SHIP CONSTRUCTION TURNKEY	Longford	Campbell's Drive, Campbell's Lane, Longford	4	*N/A	""	""	""	""	""	Q2-2021
1691	1691	SHIP CONSTRUCTION TURNKEY	Longford	Slí Corglass, Legga 	1	*N/A	""	""	""	""	""	Q3-2021
1692	1692	SHIP CONSTRUCTION TURNKEY	Longford	Campbell's Lane, Longford	5	*N/A	""	""	""	""	""	Q2-2021
1693	1693	SHIP CONSTRUCTION TURNKEY	Longford	St. Patricks Ct., Ballinamuck	8	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1694	1694	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	12	N/A	""	""	""	""	""	Q3-2021
1695	1695	SHIP CONSTRUCTION TURNKEY	Longford	Campbell's Drive, Campbell's Lane, Longford	6	N/A	""	""	""	""	""	Q4-2021
1696	1696	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	4	N/A	""	""	""	""	""	Q4-2021
1697	1697	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	3	N/A	""	""	""	""	""	Q4-2021
1698	1698	SHIP CONSTRUCTION TURNKEY	Longford	Campbell's Drive, Campbell's Lane Longford	2	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1699	1699	SHIP CONSTRUCTION SINGLE STAGE	Longford	24B Congress Terrace, Longford	1	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1700	1700	SHIP CONSTRUCTION	Longford	Rathcline Road, Lanesborough	4	*N/A	""	""	""	""	""	Q3-2019
1701	1701	SHIP CONSTRUCTION	Longford	Edgeworthstown Road, Ballymahon	4	*N/A	""	""	""	""	""	Q1-2018
1702	1702	SHIP CONSTRUCTION	Longford	Daroge, Ballymahon	1	*N/A	""	""	""	""	""	Q4-2019
1703	1703	SHIP CONSTRUCTION	Longford	'Rose Cottage', Ballinalee	6	*N/A	""	""	""	""	""	Q4-2021
1704	1704	SHIP CONSTRUCTION	Longford	St.Rita's, Park Road, Longford	14	*N/A	""	Stage 2 approved Q1-2020, full design/tender being prepared.	""	""	""	""
1705	1705	SHIP CONSTRUCTION	Longford	Fairgreen View, Longford Town	1	*N/A	""	""	""	""	""	Q2-2021
1706	1706	SHIP CONSTRUCTION	Longford	Cranleymore, Abbeylara	3	*N/A	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
1707	1707	SHIP CONSTRUCTION	Longford	Cloonahard, Edgeworthstown	1	*N/A	""	""	""	""	""	Q2-2021
1708	1708	SHIP CONSTRUCTION	Longford	Woodlands Path, Keenagh	4	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1709	1709	SHIP CONSTRUCTION	Longford	Clough Dillons, Keenagh	4	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1710	1710	SHIP CONSTRUCTION	Longford	Radharc Na Muileann, Lanesborough	22	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1711	1711	SHIP CONSTRUCTION	Longford	Drynan, Ballymahon	13	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1712	1712	SHIP CONSTRUCTION	Longford	Cnoc Na Gréine, Granard	6	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1713	1713	CALF Turnkey	Longford	Cartrun Breac, Lisbrack Rd, Longford (Phase 1)	7	Clúid Housing	""	""	""	""	""	Q1-2017
1714	1714	CALF Construction	Longford	Colmcille Terrace, Granard, Co. Longford. (Phase 1)	21	Tuath Housing Association	""	""	""	Q2-2018	""	""
1715	1715	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Louth	Ravel Ardee Road, Dunleer	80	*N/A	""	""	""	""	""	Q2-2020
1716	1716	SHIP CONSTRUCTION TURNKEY	Louth	Brabazon Hall, Termonfeckin, Drogheda	5	*N/A	""	""	""	""	""	Q4-2019
1717	1717	SHIP CONSTRUCTION TURNKEY	Louth	‘Gort Bui’, Ballymakenny Road, Drogheda	13	*N/A	""	""	""	""	""	Q4-2020
1718	1718	SHIP CONSTRUCTION TURNKEY	Louth	Green Gates Manor, Haynestown, Dundalk	44	*N/A	""	""	""	""	""	Q2-2020
1719	1719	SHIP CONSTRUCTION TURNKEY	Louth	Wadman Park, Haynestown, Dundalk	16	*N/A	""	""	""	""	""	Q3-2020
1720	1720	SHIP CONSTRUCTION TURNKEY	Louth	‘Gort Bui’, Ballymakenny Road, Drogheda	9	*N/A	""	""	""	""	""	Q4-2020
1721	1721	SHIP CONSTRUCTION TURNKEY	Louth	‘Gort Bui’, Ballymakenny Road, Drogheda	10	*N/A	""	""	""	""	""	Q1-2021
1722	1722	SHIP CONSTRUCTION TURNKEY	Louth	‘Gort Bui’, Ballymakenny Road, Drogheda	9	*N/A	""	""	""	""	""	Q2-2021
1723	1723	SHIP CONSTRUCTION TURNKEY	Louth	‘Gort Bui’, Ballymakenny Road, Drogheda	8	*N/A	""	""	""	""	""	Q2-2021
1724	1724	SHIP CONSTRUCTION TURNKEY	Louth	Wadman Park, Haynestown, Dundalk	17	*N/A	""	""	""	""	""	Q4-2020
1725	1725	SHIP CONSTRUCTION TURNKEY	Louth	Bridgegate Close, Bridgegate, Ardee	1	*N/A	""	""	""	""	""	Q4-2020
1726	1726	SHIP CONSTRUCTION TURNKEY	Louth	Termon River, Termonfeckin	2	*N/A	""	""	""	""	""	Q4-2020
1727	1727	SHIP CONSTRUCTION TURNKEY	Louth	Glyde View, Tallanstown	2	*N/A	""	""	""	""	""	Q2-2021
1728	1728	SHIP CONSTRUCTION TURNKEY	Louth	Wadman Park, Haynestown, Dundalk	29	*N/A	""	""	""	""	""	Q4-2020
1729	1729	SHIP CONSTRUCTION TURNKEY	Louth	Termon River, Termonfeckin	1	*N/A	""	""	""	""	""	Q4-2021
1730	1730	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	8	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1731	1731	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1732	1732	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1733	1733	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	17	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
1734	1734	SHIP CONSTRUCTION SINGLE STAGE	Louth	55/57 Bothar Brugha, Drogheda	3	*N/A	""	""	""	""	""	Q4-2017
1735	1735	SHIP CONSTRUCTION SINGLE STAGE	Louth	Moneymore, Drogheda	1	*N/A	""	""	""	""	Q2-2020	""
1736	1736	SHIP CONSTRUCTION SINGLE STAGE	Louth	Gort Uaine, Clogherhead	1	*N/A	""	""	""	""	Q3-2020	""
1737	1737	SHIP CONSTRUCTION SINGLE STAGE	Louth	School Lane, Dunleer	1	*N/A	""	""	""	""	Q3-2020	""
1738	1738	SHIP CONSTRUCTION SINGLE STAGE	Louth	Doire Beag, Collon	6	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1739	1739	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	4	*N/A	""	""	""	""	""	Q1-2018
1740	1740	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	7	*N/A	""	""	""	""	""	Q4-2016
1741	1741	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	5	*N/A	""	""	""	""	""	Q2-2017
1742	1742	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	3	*N/A	""	""	""	""	""	Q3-2017
1743	1743	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	7	*N/A	""	""	""	""	""	Q4-2017
1744	1744	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	1	*N/A	""	""	""	""	""	Q3-2018
1745	1745	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	1	*N/A	""	""	""	""	""	Q3-2018
1746	1746	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	2	*N/A	""	""	""	""	""	Q4-2019
1747	1747	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	2	*N/A	""	""	""	""	""	Q2-2017
1748	1748	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	1	*N/A	""	""	""	""	""	Q3-2017
1749	1749	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	4	*N/A	""	""	""	""	""	Q4-2017
1750	1750	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	2	*N/A	""	""	""	""	""	Q1-2019
1751	1751	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 4	1	*N/A	""	""	""	""	""	Q3-2018
1752	1752	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 1	1	*N/A	""	""	""	""	""	Q1-2020
1753	1753	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	1	*N/A	""	""	""	""	""	Q2-2018
1754	1754	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	1	*N/A	""	""	""	""	""	Q1-2019
1755	1755	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	1	*N/A	""	""	""	""	""	Q4-2018
1756	1756	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 4	1	*N/A	""	""	""	""	""	Q4-2018
1757	1757	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	2	*N/A	""	""	""	""	""	Q2-2019
1758	1758	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	2	*N/A	""	""	""	""	""	Q2-2019
1759	1759	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q1-2019
1760	1760	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	3	*N/A	""	""	""	""	""	Q4-2019
1761	1761	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6	1	*N/A	""	""	""	""	""	Q3-2019
1762	1762	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	4	*N/A	""	""	""	""	""	Q3-2019
1763	1763	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6	2	*N/A	""	""	""	""	""	Q4-2019
1764	1764	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q1-2020
1765	1765	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q2-2020
1766	1766	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q2-2020
1767	1767	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - 26 Castle Road, Dundalk	1	*N/A	""	""	""	""	""	Q4-2021
1768	1768	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q4-2020
1769	1769	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6	1	*N/A	""	""	""	""	""	Q3-2020
1770	1770	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6 - 6 Moorehall, Ardee	1	*N/A	""	""	""	""	""	Q4-2021
1771	1771	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 4	5	*N/A	""	""	""	""	""	Q1-2019
1772	1772	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	4	*N/A	""	""	""	""	""	Q3-2018
1773	1773	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 4	4	*N/A	""	""	""	""	""	Q4-2018
1774	1774	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 3	5	*N/A	""	""	""	""	""	Q4-2018
1775	1775	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 2	1	*N/A	""	""	""	""	""	Q3-2019
1776	1776	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A	""	""	""	""	""	Q2-2020
1777	1777	SHIP CONSTRUCTION	Louth	Woodlands, Dunleer	4	*N/A	""	""	""	""	""	Q4-2016
1778	1778	SHIP CONSTRUCTION	Louth	Boice Court (Phase 2), Drogheda	72	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
1779	1779	SHIP CONSTRUCTION	Louth	Father Finn Park (Phase 2)	17	*N/A	""	""	""	""	""	Q2-2021
1780	1780	SHIP CONSTRUCTION	Louth	Mount Avenue, Dundalk	93	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
1781	1781	SHIP CONSTRUCTION	Louth	Muirhevnamor, Dundalk (Phase 1)	11	*N/A	""	""	""	""	Q1-2021	""
1782	1782	SHIP CONSTRUCTION	Louth	Ballymakenny Road East (Site1b), Ballymakenny, Drogheda	80	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1783	1783	SHIP CONSTRUCTION	Louth	Rathmullen Park, Drogheda	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1784	1784	REGENERATION	Louth	Cox's Demesne Phase 2a	14	*N/A	""	""	""	""	""	Q4-2016
1785	1785	REGENERATION	Louth	Cox's Demesne Phase 2b	22	*N/A	""	""	""	""	Q1-2020	""
1786	1786	CAS CONSTRUCTION TURNKEY	Louth	Liscorrie, Bog Road, Drogheda	12	Túath Housing Association Ltd	""	""	""	""	""	Q2-2021
1787	1787	CAS CONSTRUCTION	Louth	6 Slieveroe Crescent, Dundalk	1	Cluid Housing Association	""	""	""	""	""	Q4-2021
1788	1788	CAS CONSTRUCTION	Louth	Barrack Street, Dundalk	21	Simon Community : Dundalk Simon	""	""	""	""	Q4-2021	""
1789	1789	CAS CONSTRUCTION	Louth	McArdle Green (Moneymore), Drogheda	1	North ? East Housing Association Ltd	""	""	""	""	""	Q4-2018
1790	1790	CAS CONSTRUCTION	Louth	Tierney Street, Ardee	7	Oaklee Housing Trust	""	""	Stage 3 approved Q1-2018, the scheme is now approved to proceed to tender.	""	""	""
1791	1791	CAS CONSTRUCTION	Louth	Tredagh View, Drogheda	1	Respond	""	""	""	""	""	Q1-2017
1792	1792	CAS CONSTRUCTION	Louth	Coulter Park, Dundalk	7	Túath Housing Association Ltd	""	""	""	""	Q3-2021	""
1793	1793	CAS CONSTRUCTION	Louth	Four Winds, Mullacapple, Collon	1	St. John of God Housing Association Ltd	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
1794	1794	CAS CONSTRUCTION	Louth	St. John's Home, Peter's Hill, Drogheda	4	North ? East Housing Association Ltd	""	""	Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.	""	""	""
1795	1795	CAS CONSTRUCTION	Louth	Riverwell Close, Dundalk	1	Respond	""	Stage 2 approved Q2-2019, full design/tender being prepared.	""	""	""	""
1796	1796	CAS CONSTRUCTION	Louth	Highfield, Newry Road, Dundalk (Domestic Violence Refuge)	12	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1797	1797	CAS CONSTRUCTION	Louth	10-16 The Alleys, St. Peter's Place, Drogheda	14	Peter McVerry Trust Ltd	Stage 1 approved Q1-2020, outline design and costs being prepared.	""	""	""	""	""
1798	1798	CALF Turnkey	Louth	2 units An Rian, Termonfeckin Rd., Drogheda, Co. Louth (Phase 1)	2	North & East Housing Association Ltd	""	""	""	""	""	Q2-2019
1799	1799	CALF Turnkey	Louth	Aston Village, Drogheda (Phase 1)*	8	Respond	""	""	""	""	""	Q3-2018
1800	1800	CALF Construction	Louth	Bishops Court, Dundalk, Co Louth  (Phase 1)	2	Tuath Housing Association	""	""	""	""	""	Q3-2020
1801	1801	CALF Turnkey	Louth	Carlinn Drive, Mullaharlin Road, Dundalk, Co. Louth (Phase 1)	6	Clúid Housing	""	""	""	""	""	Q4-2020
1802	1802	CALF Turnkey	Louth	Castle Court, Castlebellingham, Louth (Phase 1)	4	Clúid Housing	""	""	""	""	""	Q1-2017
1803	1803	CALF Turnkey	Louth	Castle Court, Castlebellingham, Louth (Phase 2)	10	Clúid Housing	""	""	""	""	""	Q1-2017
1804	1804	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q1-2018
1805	1805	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 2)*	20	Tuath Housing Association	""	""	""	""	""	Q1-2018
1806	1806	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 3)	8	Tuath Housing Association	""	""	""	""	""	Q3-2018
1807	1807	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 4)	15	Tuath Housing Association	""	""	""	""	""	Q3-2018
1808	1808	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 5)	6	Tuath Housing Association	""	""	""	""	""	Q4-2018
1809	1809	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 6)*	22	Tuath Housing Association	""	""	""	""	""	Q4-2018
1810	1810	CALF Turnkey	Louth	Castleguard, Ardee, Co. Louth (Phase 7)	22	Tuath Housing Association	""	""	""	""	""	Q2-2019
1811	1811	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 1)*	16	Tuath Housing Association	""	""	""	""	""	Q1-2021
1812	1812	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 2)	10	Tuath Housing Association	""	""	""	""	""	Q2-2021
1813	1813	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 3)	16	Tuath Housing Association	""	""	""	""	""	Q4-2021
1814	1814	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 4)	11	Tuath Housing Association	""	""	""	""	""	Q4-2021
1815	1815	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 5)	12	Tuath Housing Association	""	""	""	""	Q1-2020	""
1816	1816	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q1-2021
1817	1817	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 2)*	15	Clúid Housing	""	""	""	""	""	Q3-2021
1818	1818	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 3)	15	Clúid Housing	""	""	""	""	""	Q4-2021
1819	1819	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 4)	13	Clúid Housing	""	""	""	""	""	Q4-2021
1820	1820	CALF Turnkey	Louth	Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 1)*	13	Tuath Housing Association	""	""	""	""	""	Q4-2018
1821	1821	CALF Turnkey	Louth	Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 2)	8	Tuath Housing Association	""	""	""	""	""	Q1-2019
1822	1822	CALF Turnkey	Louth	Cois Cuain, Upper Point Road, Dundalk, Co. Louth (Phase 3)	7	Tuath Housing Association	""	""	""	""	""	Q2-2019
1823	1823	CALF Turnkey	Louth	Coulter Place Armagh Road (Phase 1)	10	Clúid Housing	""	""	""	""	""	Q1-2017
1824	1824	CALF Turnkey	Louth	Coulter Place Armagh Road (Phase 2)	12	Clúid Housing	""	""	""	""	""	Q3-2017
1825	1825	CALF Turnkey	Louth	Donore Road, Drogheda, Co. Louth (Phase 1)	66	Clúid Housing	""	""	""	""	Q2-2021	""
1826	1826	CALF Turnkey	Louth	Dowdallshill, Dundalk, Co. Louth (Phase 1)*	13	North & East Housing Association Ltd	""	""	""	""	""	Q3-2020
1827	1827	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth (Phase 1)*	65	Respond	""	""	""	""	Q4-2020	""
1828	1828	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth(Glenview) (Phase 1)*	14	Respond	""	""	""	""	""	Q1-2019
1829	1829	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth(Glenview) (Phase 2)*	14	Respond	""	""	""	""	""	Q4-2019
1830	1830	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 1)*	87	Clúid Housing	""	""	""	""	Q4-2020	""
1831	1831	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 2)	43	Clúid Housing	""	""	""	""	Q4-2020	""
1832	1832	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 1)*	11	Tuath Housing Association	""	""	""	""	""	Q2-2019
1833	1833	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 2)*	14	Tuath Housing Association	""	""	""	""	""	Q2-2019
1834	1834	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 3)*	15	Tuath Housing Association	""	""	""	""	""	Q2-2019
1835	1835	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 4)*	47	Tuath Housing Association	""	""	""	""	""	Q3-2019
1836	1836	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 5)*	24	Tuath Housing Association	""	""	""	""	""	Q4-2019
1837	1837	CALF Turnkey	Louth	Dundoogan, Haynestown, Dundalk, Co. Louth (Phase 6)*	1	Tuath Housing Association	""	""	""	""	""	Q4-2020
1838	1838	CALF Turnkey	Louth	Fairways Gardens, Dundalk Co Louth (Phase 1)	8	Clúid Housing	""	""	""	""	""	Q4-2021
1839	1839	CALF Construction	Louth	Fire Station Site, Scarlett St, Drogheda (Phase 1)	15	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
1840	1840	CALF Turnkey	Louth	Halliday Mills, Quay Street, Dundalk, Co. Louth (Phase 1)*	85	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
1841	1841	CALF Turnkey	Louth	Harbour Grove, Dundalk, Co. Louth (Phase 1)	8	North & East Housing Association Ltd	""	""	""	""	""	Q2-2020
1842	1842	CALF Turnkey	Louth	Harbour View, Coulter Place, Dundalk (Phase 1)	24	Clúid Housing	""	""	""	""	""	Q3-2021
1843	1843	CALF Turnkey	Louth	Knock Shee Close, Blackrock, Co. Louth (Phase 1)	1	Clúid Housing	""	""	""	""	""	Q4-2020
1844	1844	CALF Turnkey	Louth	Knock Shee, Old Golf Links Road, Blackrock, Co Louth  (Phase 1)	3	Clúid Housing	""	""	""	""	""	Q4-2017
1845	1845	CALF Turnkey	Louth	Knockshee Close, Blackrock, Co. Louth (Phase 1)	3	Clúid Housing	""	""	""	""	""	Q2-2020
1846	1846	CALF Turnkey	Louth	Liscorrie, Bog Lane, Drogheda (Phase 1)	41	Tuath Housing Association	""	""	""	""	""	Q4-2017
1847	1847	CALF Turnkey	Louth	Lismullen Grove, Dundalk, Co. Louth (Phase 1)*	15	Tuath Housing Association	""	""	""	""	""	Q4-2020
1848	1848	CALF Turnkey	Louth	Lismullen Grove, Dundalk, Co. Louth (Phase 2)	8	Tuath Housing Association	""	""	""	""	""	Q1-2021
1849	1849	CALF Turnkey	Louth	Mount Hamilton, Dundalk, Co. Louth (Phase 1)	20	Clúid Housing	""	""	""	""	""	Q4-2019
1850	1850	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 1)*	55	Clúid Housing	""	""	""	""	Q3-2020	""
1851	1851	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 2)	39	Clúid Housing	""	""	""	""	Q3-2020	""
1852	1852	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 1)*	17	Respond	""	""	""	""	Q4-2020	""
1853	1853	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 2)*	23	Respond	""	""	""	""	Q4-2020	""
1854	1854	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 3)*	46	Respond	""	""	""	""	Q4-2020	""
1855	1855	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 4)*	47	Respond	""	""	""	""	Q4-2020	""
1856	1856	CALF Turnkey	Louth	Oriel Heights, Collon, Co. Louth (Phase 1)*	13	North & East Housing Association Ltd	""	""	""	Q3-2021	""	""
1857	1857	CALF Construction	Louth	Post Tender - Clos na Manach, Carlingford, Co Louth (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q2-2018
1858	1858	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 1)	20	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1859	1859	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Clanmil (Phase 2)*	25	Clanmil Housing Association Ireland	""	""	""	""	Q1-2019	""
1860	1860	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q4-2019
1861	1861	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 2)*	16	Tuath Housing Association	""	""	""	""	Q1-2019	""
1862	1862	CALF Turnkey	Louth	Racecourse Meadows, Dundalk, Co. Louth - Tuath (Phase 3)*	19	Tuath Housing Association	""	""	""	""	Q1-2019	""
1863	1863	CALF Turnkey	Louth	Rath na Gloine, Commons Road, Louth (Phase 1)	3	Clúid Housing	""	""	""	""	""	Q3-2016
1864	1864	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 1)	3	North & East Housing Association Ltd	""	""	""	""	""	Q4-2018
1865	1865	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 2)	6	North & East Housing Association Ltd	""	""	""	""	""	Q2-2019
1866	1866	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 3)	3	North & East Housing Association Ltd	""	""	""	""	""	Q3-2019
1867	1867	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 4)	14	North & East Housing Association Ltd	""	""	""	""	""	Q3-2019
1868	1868	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 5)	12	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
1869	1869	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Phase 6)	16	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
1870	1870	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q2-2018
1871	1871	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q3-2018
1872	1872	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 3)	4	Tuath Housing Association	""	""	""	""	""	Q3-2018
1873	1873	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 4)	15	Tuath Housing Association	""	""	""	""	""	Q4-2018
1874	1874	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 5)	6	Tuath Housing Association	""	""	""	""	""	Q2-2019
1875	1875	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 6)	4	Tuath Housing Association	""	""	""	""	""	Q4-2019
1876	1876	CALF Turnkey	Louth	Rathmullen Road, Drogheda, Co. Louth (Tuath) (Phase 7)	12	Tuath Housing Association	""	""	""	""	""	Q3-2020
1877	1877	CALF Turnkey	Louth	Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q4-2017
1878	1878	CALF Turnkey	Louth	Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 2)	15	Clúid Housing	""	""	""	""	""	Q3-2019
1879	1879	CALF Turnkey	Louth	Revised - 43 Units at Mount Hamilton, Dundalk, Co Louth (Phase 3)	16	Clúid Housing	""	""	""	""	""	Q4-2019
1880	1880	CALF Turnkey	Louth	Scotch Hall, Drogheda, Co Louth  (Phase 1)	21	Respond	""	""	""	Q3-2021	""	""
1881	1881	CALF Construction	Louth	Slieve Row Crescent, Dundalk (Phase 1)	1	Clúid Housing	""	""	""	""	""	Q2-2016
1882	1882	CALF Turnkey	Louth	Termon River, Baltray Road, Termonfeckin, Co. Louth (Phase 1)	1	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
1883	1883	CALF Turnkey	Louth	Termon River, Baltray Road, Termonfeckin, Drogheda, Co.Louth (Phase 1)*	1	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
1884	1884	CALF Turnkey	Louth	Tullybrook, Drogheda, Co. Louth  (Phase 1)*	85	Clúid Housing	""	""	""	""	Q1-2021	""
1885	1885	SHIP CONSTRUCTION TURNKEY	Mayo	Carrabeg, Newport Road, Castlebar	2	*N/A	""	""	""	""	""	Q4-2018
1886	1886	SHIP CONSTRUCTION TURNKEY	Mayo	Cois Abhainn, Bonniconlon	2	*N/A	""	""	""	""	""	Q2-2019
1887	1887	SHIP CONSTRUCTION TURNKEY	Mayo	Chapel Street, Louisburgh	3	*N/A	""	""	""	""	""	Q4-2019
1888	1888	SHIP CONSTRUCTION TURNKEY	Mayo	Bunree, Ballina	3	*N/A	""	""	""	""	Q4-2019	""
1889	1889	SHIP CONSTRUCTION TURNKEY	Mayo	Heathervale, Castlebar - Phase 2	9	*N/A	""	""	""	""	""	Q4-2020
1890	1890	SHIP CONSTRUCTION TURNKEY	Mayo	Friars Court, Ballina	2	*N/A	""	""	""	""	""	Q4-2019
1891	1891	SHIP CONSTRUCTION TURNKEY	Mayo	Riverside Drive, Ballina	3	*N/A	""	""	""	""	""	Q4-2019
1892	1892	SHIP CONSTRUCTION TURNKEY	Mayo	Davitt Terrace, Castlebar	4	*N/A	""	""	""	""	""	Q4-2019
1893	1893	SHIP CONSTRUCTION TURNKEY	Mayo	Chapel St., Louisburgh	2	*N/A	""	""	""	""	""	Q4-2020
1894	1894	SHIP CONSTRUCTION TURNKEY	Mayo	Ard Rua, Claremorris	7	*N/A	""	""	""	""	""	Q4-2019
1895	1895	SHIP CONSTRUCTION TURNKEY	Mayo	Silver Springs, Claremorris	20	*N/A	""	""	""	""	Q3-2020	""
1896	1896	SHIP CONSTRUCTION TURNKEY	Mayo	Barley Hill, Bohola	3	*N/A	""	""	""	""	""	Q4-2020
1897	1897	SHIP CONSTRUCTION TURNKEY	Mayo	Main St., Charlestown	2	*N/A	""	""	""	""	""	Q4-2021
1898	1898	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Pound Road, Castlebar	6	*N/A	""	""	""	""	""	Q4-2019
1899	1899	SHIP CONSTRUCTION SINGLE STAGE	Mayo	The Boreen, Crossmolina	3	*N/A	""	""	""	""	""	Q4-2021
1900	1900	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Deel Court, Crossmolina	3	*N/A	""	""	""	""	""	Q4-2021
1901	1901	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Kilmaine	6	*N/A	""	""	""	""	""	Q4-2019
1902	1902	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Knockroe, Moygownagh	3	*N/A	""	""	""	""	""	Q4-2021
1903	1903	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Low Park, Charlestown	3	*N/A	""	""	""	""	""	Q4-2021
1904	1904	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Pollranny, Achill Sound	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1905	1905	SHIP CONSTRUCTION	Mayo	Knocknageeha, Newport	1	*N/A	""	""	""	""	""	Q2-2019
1906	1906	SHIP CONSTRUCTION	Mayo	Áit Aoibhinn, Kilkelly Road, Knock (Phase 3)	4	*N/A	""	""	""	""	""	Q3-2018
1907	1907	SHIP CONSTRUCTION	Mayo	Kilmeena (Phase 2)	4	*N/A	""	""	""	""	""	Q3-2018
1908	1908	SHIP CONSTRUCTION	Mayo	Knockmore, Ballina	8	*N/A	""	""	""	""	""	Q1-2019
1909	1909	SHIP CONSTRUCTION	Mayo	Radharc an tSaillin, Binghamstown, Belmullet (Phase 2)	4	*N/A	""	""	""	""	""	Q2-2019
1910	1910	SHIP CONSTRUCTION	Mayo	Sliabh Rua, Foxford (Phase 3)	10	*N/A	""	""	""	""	""	Q4-2019
1911	1911	SHIP CONSTRUCTION	Mayo	Woodlands, Balla (Phase 3)	4	*N/A	""	""	""	""	""	Q4-2019
1912	1912	SHIP CONSTRUCTION	Mayo	Slinaunroe, Clogher (SRD)	1	*N/A	""	""	""	""	""	Q2-2017
1913	1913	SHIP CONSTRUCTION	Mayo	Abbeyquarter, Ballyhaunis	18	*N/A	""	""	""	""	""	Q4-2020
1914	1914	SHIP CONSTRUCTION	Mayo	Tonragee West, Achill (Phase 2)	5	*N/A	""	""	""	""	""	Q4-2019
1915	1915	SHIP CONSTRUCTION	Mayo	Sli na Roba, Friarsquarter, Ballinrobe	16	*N/A	""	""	""	""	""	Q4-2020
1916	1916	SHIP CONSTRUCTION	Mayo	Marian Crescent, Ballina	4	*N/A	""	""	""	""	""	Q2-2018
1917	1917	SHIP CONSTRUCTION	Mayo	Tubberhill, Westport (Phase 3)	21	*N/A	""	""	""	""	""	Q1-2018
1918	1918	SHIP CONSTRUCTION	Mayo	Parke, Castlebar	8	*N/A	""	""	""	""	""	Q4-2019
1919	1919	SHIP CONSTRUCTION	Mayo	Killavally	10	*N/A	""	""	""	""	""	Q4-2019
1920	1920	SHIP CONSTRUCTION	Mayo	Lios na Circa, Saleen, Castlebar - Phase 2	22	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
1921	1921	SHIP CONSTRUCTION	Mayo	Kilkelly Road, Swinford	27	*N/A	""	""	""	""	""	Q4-2020
1922	1922	SHIP CONSTRUCTION	Mayo	Barhauve, Rossport (SRD)	1	*N/A	""	""	""	""	""	Q2-2018
1923	1923	SHIP CONSTRUCTION	Mayo	Glaggaun, Ballycroy (SRD)	1	*N/A	""	""	""	""	""	Q4-2017
1924	1924	SHIP CONSTRUCTION	Mayo	Glengad, Pollatomish (SRD)	1	*N/A	""	""	""	""	""	Q2-2018
1925	1925	SHIP CONSTRUCTION	Mayo	Gorthbrack, Inver (SRD)	1	*N/A	""	""	""	""	""	Q1-2018
1926	1926	SHIP CONSTRUCTION	Mayo	Cross	15	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1927	1927	SHIP CONSTRUCTION	Mayo	Bonniconlon	5	*N/A	""	""	""	""	""	Q4-2021
1928	1928	SHIP CONSTRUCTION	Mayo	Cloonkeadagh Road, Kiltimagh	21	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
1929	1929	SHIP CONSTRUCTION	Mayo	Rehins Fort, Ballina	20	*N/A	""	""	""	""	Q3-2021	""
1930	1930	SHIP CONSTRUCTION	Mayo	Murrevagh, Mulranney	14	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
1931	1931	SHIP CONSTRUCTION	Mayo	50 Units @ Golf Course Rd., Westport	50	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
1932	1932	SHIP CONSTRUCTION	Mayo	Ballyglass, Carnacon, Claremorris	5	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1933	1933	SHIP CONSTRUCTION	Mayo	Lios na Circe, Saleen, Castlebar - Phase 3	14	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
1934	1934	SHIP CONSTRUCTION	Mayo	7 St. Patrick's Terrace, Westport	1	*N/A	""	""	""	""	""	Q3-2017
1935	1935	SHIP CONSTRUCTION	Mayo	Atlantic Drive ,Belmullet	4	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1936	1936	SHIP CONSTRUCTION	Mayo	Liskilleen, Ballinrobe,	1	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1937	1937	SHIP CONSTRUCTION	Mayo	Walsh St., Ballina	9	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.	""	""	""	""	""
1938	1938	SHIP CONSTRUCTION	Mayo	Main Street, Ballyvary	12	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
1939	1939	SHIP CONSTRUCTION	Mayo	Rehins Fort, Foxford Rd., Ballina	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
1940	1940	SHIP CONSTRUCTION	Mayo	AchilL Sound	20	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1941	1941	CAS CONSTRUCTION	Mayo	Admiral Browne Road, Foxford (Phase 2)	4	Society of Saint Vincent de Paul	""	""	""	""	""	Q1-2018
1942	1942	CAS CONSTRUCTION	Mayo	Killosheehan, Ballinrobe	6	Society of Saint Vincent de Paul	""	""	""	""	""	Q4-2018
1943	1943	CAS CONSTRUCTION	Mayo	Admiral Browne Road, Foxford	8	Society of Saint Vincent de Paul	""	""	""	""	""	Q3-2016
1944	1944	CAS CONSTRUCTION	Mayo	Logmore, Belmullet	7	Irish Wheelchair Association Ltd	""	""	""	""	""	Q2-2017
1945	1945	CAS CONSTRUCTION	Mayo	Mount St Mary's Convent, Westport	17	Túath Housing Association Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
1946	1946	CAS CONSTRUCTION	Mayo	Ellison House, Ellison St., Castlebar	8	Peter McVerry Trust Ltd	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
1947	1947	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 1)	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
1948	1948	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 2)	4	Tuath Housing Association	""	""	""	""	Q3-2020	""
1949	1949	CALF Turnkey	Mayo	Glenlara, Westport, Co Mayo  (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
1950	1950	CALF Turnkey	Mayo	Humbert Way, Castlebar, Co. Mayo (Phase 1)	20	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2020	""
1951	1951	CALF Turnkey	Mayo	Monamore, Lodge Road, Westport, Co. Mayo (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2019
1952	1952	CALF Turnkey	Mayo	The Sycamores, Ballina (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q2-2021
1953	1953	CAS CONSTRUCTION TURNKEY	Meath	Knightsbrook Close, Effernock, Trim, Co Meath	2	Túath Housing Association Ltd	""	""	""	""	""	Q4-2021
1954	1954	SHIP CONSTRUCTION TURNKEY	Meath	Cois Glaisin, Johnstown, Navan	19	*N/A	""	""	""	""	""	Q4-2018
1955	1955	SHIP CONSTRUCTION TURNKEY	Meath	Cluain Adain, Clonmagadden, Navan	16	*N/A	""	""	""	""	""	Q4-2018
1956	1956	SHIP CONSTRUCTION TURNKEY	Meath	Dun Eimear, Bettystown	8	*N/A	""	""	""	""	""	Q3-2019
1957	1957	SHIP CONSTRUCTION TURNKEY	Meath	Bracken Hill, Kilmessan	3	*N/A	""	""	""	""	""	Q4-2019
1958	1958	SHIP CONSTRUCTION TURNKEY	Meath	Cluain Adain, Clonmagadden, Navan	4	*N/A	""	""	""	""	""	Q3-2019
1959	1959	SHIP CONSTRUCTION TURNKEY	Meath	Cois Glaisin Walk, Johnstown, Navan	5	*N/A	""	""	""	""	""	Q4-2018
1960	1960	SHIP CONSTRUCTION TURNKEY	Meath	Cois Glaisin Walk, Johnstown, Navan	4	*N/A	""	""	""	""	""	Q3-2019
1961	1961	SHIP CONSTRUCTION TURNKEY	Meath	Cois Glaisin, Johnstown, Navan 	8	*N/A	""	""	""	""	""	Q2-2019
1962	1962	SHIP CONSTRUCTION TURNKEY	Meath	Cois na Mara, Bettystown	2	*N/A	""	""	""	""	""	Q3-2019
1963	1963	SHIP CONSTRUCTION TURNKEY	Meath	Dun Eimear, Bettystown	14	*N/A	""	""	""	""	""	Q4-2019
1964	1964	SHIP CONSTRUCTION TURNKEY	Meath	Cherry Hill Court, Kells	2	*N/A	""	""	""	""	""	Q4-2019
1965	1965	SHIP CONSTRUCTION TURNKEY	Meath	Broadmeadow Vale, Rathoath	2	*N/A	""	""	""	""	""	Q4-2019
1966	1966	SHIP CONSTRUCTION TURNKEY	Meath	Cois Glaisin, Johnstown, Navan	11	*N/A	""	""	""	""	""	Q4-2020
1967	1967	SHIP CONSTRUCTION TURNKEY	Meath	Cluain Adain, Clonmagadden, Navan	15	*N/A	""	""	""	""	""	Q4-2020
1968	1968	SHIP CONSTRUCTION TURNKEY	Meath	The Brambles, Longford rd., Duleek	16	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
1969	1969	SHIP CONSTRUCTION TURNKEY	Meath	26 Willow Green, Dunshaughlin	1	*N/A	""	""	""	""	""	Q3-2020
1970	1970	SHIP CONSTRUCTION TURNKEY	Meath	Seoid na Tra, Bettytown	2	*N/A	""	""	""	""	""	Q3-2020
1971	1971	SHIP CONSTRUCTION TURNKEY	Meath	Dun Eimear, Bettystown	1	*N/A	""	""	""	""	""	Q4-2020
1972	1972	SHIP CONSTRUCTION TURNKEY	Meath	Connaught Street, Athboy	7	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1973	1973	SHIP CONSTRUCTION SINGLE STAGE	Meath	Proudstown Road, Navan	4	*N/A	""	""	""	""	""	Q4-2018
1974	1974	SHIP CONSTRUCTION SINGLE STAGE	Meath	The Belfry, Trim	3	*N/A	""	""	""	""	""	Q4-2019
1975	1975	SHIP CONSTRUCTION SINGLE STAGE	Meath	Broville, Corballis, Laytown	1	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1976	1976	SHIP CONSTRUCTION SINGLE STAGE	Meath	11 Glenidan Court, Enfield	1	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
1977	1977	SHIP CONSTRUCTION RAPID	Meath	Kilmainhamwood	4	*N/A	""	""	""	""	""	Q4-2019
1978	1978	SHIP CONSTRUCTION RAPID	Meath	Cortown	10	*N/A	""	""	""	""	""	Q4-2019
1979	1979	SHIP CONSTRUCTION RAPID	Meath	Oldcastle	16	*N/A	""	""	""	""	""	Q4-2019
1980	1980	SHIP CONSTRUCTION	Meath	Bettystown (Phase 2)	15	*N/A	""	""	""	""	""	Q4-2020
1981	1981	SHIP CONSTRUCTION	Meath	St. Oliver's Park, Ratoath	17	*N/A	""	""	""	""	""	Q4-2019
1982	1982	SHIP CONSTRUCTION	Meath	Riverside (Townparks), Kells	40	*N/A	""	""	""	""	""	Q4-2020
1983	1983	SHIP CONSTRUCTION	Meath	Cherry Court, Summerhill	19	*N/A	""	""	""	""	""	Q1-2019
1984	1984	SHIP CONSTRUCTION	Meath	Connaught Grove, Athboy	32	*N/A	""	""	""	""	""	Q2-2018
1985	1985	SHIP CONSTRUCTION	Meath	Carlanstown	13	*N/A	""	""	""	""	""	Q4-2020
1986	1986	SHIP CONSTRUCTION	Meath	Donore	21	*N/A	""	""	""	""	Q4-2020	""
1987	1987	SHIP CONSTRUCTION	Meath	Dunshaughlin	26	*N/A	""	""	""	""	""	Q4-2021
1988	1988	SHIP CONSTRUCTION	Meath	Bettystown (Phase 1)	16	*N/A	""	""	""	""	""	Q3-2017
1989	1989	SHIP CONSTRUCTION	Meath	Farganstown, Navan	84	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
1990	1990	SHIP CONSTRUCTION	Meath	Blackhill Crescent, Donacarney	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1991	1991	SHIP CONSTRUCTION	Meath	Archdeaconary Glebe, Kells	20	*N/A	""	Stage 2 approved Q1-2020, full design/tender being prepared.	""	""	""	""
1992	1992	SHIP CONSTRUCTION	Meath	Nangle Court, Navan	16	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1993	1993	SHIP CONSTRUCTION	Meath	Castle Street, Ashbourne - Dept of Education Site	74	*N/A	""	Stage 2 approved Q1-2020, full design/tender being prepared.	""	""	""	""
1994	1994	SHIP CONSTRUCTION	Meath	Church View, Rathmolyon	22	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
1995	1995	SHIP CONSTRUCTION	Meath	Church Street, Kells, Co. Meath	3	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
1996	1996	SHIP CONSTRUCTION	Meath	Haggard Street, Trim, Co. Meath	4	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
1997	1997	SHIP CONSTRUCTION	Meath	Pitcher Lane, Kells, Co. Meath	4	*N/A	Stage 1 approved Q3-2019, outline design and costs being prepared.	""	""	""	""	""
1998	1998	SHIP CONSTRUCTION	Meath	Swan Lane, Balreask	6	*N/A	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
1999	1999	SHIP CONSTRUCTION	Meath	Carrick St., Kells	43	*N/A	Stage 1 approved Q1-2019, outline design and costs being prepared.	""	""	""	""	""
2000	2000	SHIP CONSTRUCTION	Meath	Lagore, Dunshaughlin	42	*N/A	""	""	Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.	""	""	""
2001	2001	SHIP CONSTRUCTION	Meath	Convent Lands, Kildalkey, Athboy	26	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
2002	2002	SHIP CONSTRUCTION	Meath	Ratholdren Court, Navan	26	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2003	2003	SHIP CONSTRUCTION	Meath	Brews Hill, Navan	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2004	2004	CAS CONSTRUCTION TURNKEY	Meath	Bridge Street, Ashbourne, Co Meath  	20	Peter McVerry Trust Ltd	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2005	2005	CAS CONSTRUCTION TURNKEY	Meath	Gainsfield, (Gort Fionnbarra) Commons Road, Navan Co. Meath	6	Túath Housing Association Ltd	""	""	""	""	""	Q2-2021
2006	2006	CAS CONSTRUCTION	Meath	Blackcastle, Slane Road, Navan	17	Túath Housing Association Ltd	""	""	""	""	""	Q4-2018
2007	2007	CAS CONSTRUCTION	Meath	Women's Refuge, Tailteann Drive, Windtown, Navan	8	Meath Women’s Housing Association CLG	Stage 1 approved Q2-2020, outline design and costs being prepared.	""	""	""	""	""
2008	2008	CAS CONSTRUCTION	Meath	Park Avenue, Oldcastle	5	Society of Saint Vincent de Paul	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
2009	2009	CALF Turnkey	Meath	18 units Churchfields, Ashbourne, Co. Meath (Phase 1)	18	Tuath Housing Association	""	""	""	""	""	Q4-2018
2010	2010	CALF Turnkey	Meath	5 units Dunville, Athlumney, Navan, Co. Meath (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q1-2019
2011	2011	CALF Turnkey	Meath	6 Units Seabury Lawns, Mornington, Co Meath (Phase 1)	6	Clúid Housing	""	""	""	""	""	Q1-2018
2012	2012	CALF Turnkey	Meath	Applewood Court, Beaufort Place, Navan, Co. Meath (Phase 1)*	21	Tuath Housing Association	""	""	""	""	Q3-2020	""
2013	2013	CALF Turnkey	Meath	Ardmore Rise, Bettystown, Co Meath  (Phase 1)	1	North & East Housing Association Ltd	""	""	""	""	""	Q4-2018
2014	2014	CALF Turnkey	Meath	Ashewood, Ashbourne, Co Meath (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q4-2021
2015	2015	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 1)*	63	Respond	""	""	""	""	Q1-2020	""
2016	2016	CALF Turnkey	Meath	Blackcastle, Slane Road, Navan, Co. Meath (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q4-2018
2017	2017	CALF Turnkey	Meath	Broadmeadow Vale, Ratoath, Meath (Phase 1)*	1	Tuath Housing Association	""	""	""	""	""	Q2-2019
2018	2018	CALF Turnkey	Meath	Broadmeadow Vale, Ratoath, Meath (Phase 2)*	1	Tuath Housing Association	""	""	""	""	""	Q2-2019
2019	2019	CALF Turnkey	Meath	Broadmeadow Vale, Ratoath, Meath (Phase 3)*	10	Tuath Housing Association	""	""	""	""	""	Q4-2019
2020	2020	CALF Turnkey	Meath	Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 1)*	24	Tuath Housing Association	""	""	""	""	Q1-2021	""
2021	2021	CALF Turnkey	Meath	Bryanstown Wood, Beamore Road, Drogheda, Co. Meath (Phase 2)*	4	Tuath Housing Association	""	""	""	""	Q1-2021	""
2022	2022	CALF Turnkey	Meath	Ceamach Close, Donacarney, Co Meath  (Phase 1)	7	Clúid Housing	""	""	""	""	""	Q2-2018
2023	2023	CALF Turnkey	Meath	Ceamach Close, Donacarney, Co Meath  (Phase 2)*	9	Clúid Housing	""	""	""	""	""	Q3-2018
2024	2024	CALF Turnkey	Meath	Cherryvalley, Rathmoylan, Co Meath (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q4-2017
2025	2025	CALF Turnkey	Meath	Churchfields, Ashbourne, Co Meath (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q2-2017
2026	2026	CALF Turnkey	Meath	Churchfields, Ashbourne, Meath (Phase 1)*	10	Tuath Housing Association	""	""	""	""	""	Q4-2018
2027	2027	CALF Turnkey	Meath	Churchfields, Ashbourne, Meath (Phase 2)*	3	Tuath Housing Association	""	""	""	""	""	Q2-2019
2028	2028	CALF Turnkey	Meath	Churchfields, Ashbourne, Meath (Phase 3)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2019
2029	2029	CALF Turnkey	Meath	Commons Road, Navan, Co Meath  (Phase 1)	12	North & East Housing Association Ltd	""	""	""	""	""	Q4-2019
2030	2030	CALF Turnkey	Meath	Commons, Duleek, Co. Meath (Phase 1)*	22	North & East Housing Association Ltd	""	""	""	""	Q1-2021	""
2031	2031	CALF Turnkey	Meath	Dun Eimear, Bettystown, Co. Meath (Phase 1)*	12	Clúid Housing	""	""	""	""	""	Q4-2019
2032	2032	CALF Turnkey	Meath	Dun Eimear, Bettystown, Co. Meath (Phase 2)*	11	Clúid Housing	""	""	""	""	""	Q4-2019
2033	2033	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q1-2018
2034	2034	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 2)*	8	Tuath Housing Association	""	""	""	""	""	Q1-2018
2035	2035	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 3)*	10	Tuath Housing Association	""	""	""	""	""	Q2-2018
2036	2036	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 4)*	6	Tuath Housing Association	""	""	""	""	""	Q2-2018
2037	2037	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 5)*	18	Tuath Housing Association	""	""	""	""	""	Q2-2018
2038	2038	CALF Turnkey	Meath	Dunville, Athlumney, Co Meath  (Phase 6)	12	Tuath Housing Association	""	""	""	""	""	Q3-2018
2039	2039	CALF Turnkey	Meath	Eastham Square, Bettystown, Meath (Phase 1)*	5	Clúid Housing	""	""	""	""	""	Q1-2019
2040	2040	CALF Turnkey	Meath	Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)*	1	Tuath Housing Association	""	""	""	""	""	Q3-2018
2041	2041	CALF Turnkey	Meath	Frederick Manor, Ashbourne, Co. Meath (Phase 1)*	11	Clúid Housing	""	""	""	""	""	Q1-2021
2042	2042	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 1)	20	Tuath Housing Association	""	""	""	""	""	Q4-2019
2043	2043	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 2)	18	Tuath Housing Association	""	""	""	""	""	Q4-2020
2044	2044	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 3)	7	Tuath Housing Association	""	""	""	""	""	Q1-2021
2045	2045	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 4)	9	Tuath Housing Association	""	""	""	""	""	Q2-2021
2046	2046	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 1)	19	Tuath Housing Association	""	""	""	""	""	Q4-2021
2047	2047	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 2)	15	Tuath Housing Association	""	""	""	""	Q4-2020	""
2048	2048	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 3)	15	Tuath Housing Association	""	""	""	""	Q4-2020	""
2049	2049	CALF Turnkey	Meath	Grangehall, Dunshaughlin (Phase 1)	7	Tuath Housing Association	""	""	""	""	""	Q2-2018
2050	2050	CALF Turnkey	Meath	Kellets Grove, Dunshauglin, Co Meath  (Phase 1)*	6	Tuath Housing Association	""	""	""	""	""	Q1-2018
2051	2051	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q3-2021
2052	2052	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 2)	5	Tuath Housing Association	""	""	""	""	""	Q3-2021
2053	2053	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 3)	6	Tuath Housing Association	""	""	""	""	""	Q4-2021
2054	2054	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 1)*	11	Tuath Housing Association	""	""	""	""	Q3-2021	""
2055	2055	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 2)*	11	Tuath Housing Association	""	""	""	""	Q3-2021	""
2056	2056	CALF Turnkey	Meath	Maudelins Brook, Duleek, Co.Meath (Phase 1)*	20	Respond	""	""	""	""	""	Q4-2019
2057	2057	CALF Turnkey	Meath	Maydenhayes, Donacarney, Co. Meath (Phase 1)*	12	Clúid Housing	""	""	""	""	""	Q3-2021
2058	2058	CALF Turnkey	Meath	Mill Lane, Flower Hill, Navan, Co Meath (Phase 1)	20	Oaklee Housing	""	""	""	""	""	Q4-2016
2059	2059	CALF Turnkey	Meath	Millrace Court, Emmet Street, Trim, Co Meath  (Phase 1)	11	North & East Housing Association Ltd	""	""	""	""	""	Q2-2018
2060	2060	CALF Turnkey	Meath	Millteog, Athboy Road, Trim, Co. Meath (Phase 1)*	16	Oaklee Housing	""	""	""	""	""	Q4-2019
2061	2061	CALF Turnkey	Meath	Millteog, Athboy Road, Trim, Co. Meath (Phase 2)*	9	Oaklee Housing	""	""	""	""	""	Q2-2020
2062	2062	CALF Turnkey	Meath	Milltown, Ashbourne, Co Meath (Phase 1)	11	Clúid Housing	""	""	""	""	""	Q1-2017
2063	2063	CALF Turnkey	Meath	Milltown, Ashbourne, Co Meath (Phase 2)	36	Clúid Housing	""	""	""	""	""	Q4-2017
2064	2064	CALF Turnkey	Meath	Milltown, Ashbourne, Co Meath (Phase 3)	20	Clúid Housing	""	""	""	""	""	Q4-2017
2065	2065	CALF Turnkey	Meath	Moydervey Manor, Longwood, Trim, Co. Meath (Phase 1)*	13	Tuath Housing Association	""	""	""	""	""	Q4-2020
2066	2066	CALF Turnkey	Meath	Narrow Ways, Bettystown, Co. Meath (Phase 1)	12	Tuath Housing Association	""	""	""	""	Q2-2021	""
2067	2067	CALF Turnkey	Meath	Oldbridge Manor, Drogheda, Co. Meath (Phase 1)*	29	Tuath Housing Association	""	""	""	""	""	Q4-2020
2068	2068	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 1)	3	Tuath Housing Association	""	""	""	""	""	Q4-2018
2069	2069	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 10)	5	Tuath Housing Association	""	""	""	""	""	Q4-2020
2070	2070	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 2)	6	Tuath Housing Association	""	""	""	""	""	Q2-2019
2071	2071	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 3)	2	Tuath Housing Association	""	""	""	""	""	Q3-2019
2072	2072	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 4)	5	Tuath Housing Association	""	""	""	""	""	Q3-2019
2073	2073	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 5)	4	Tuath Housing Association	""	""	""	""	""	Q4-2019
2074	2074	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 6)	6	Tuath Housing Association	""	""	""	""	""	Q1-2020
2075	2075	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 7)	3	Tuath Housing Association	""	""	""	""	""	Q1-2020
2076	2076	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 8)	4	Tuath Housing Association	""	""	""	""	""	Q3-2020
2077	2077	CALF Turnkey	Meath	Revised - Fitzherbert Wood, Slane Road, Navan, Co Meath  (Phase 9)	6	Tuath Housing Association	""	""	""	""	""	Q3-2020
2078	2078	CALF Turnkey	Meath	Royal Oaks, Enfield, Co Meath (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q2-2017
2079	2079	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q4-2020
2080	2080	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 2)*	14	Clúid Housing	""	""	""	""	""	Q2-2021
2081	2081	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 3)	16	Clúid Housing	""	""	""	""	Q4-2019	""
2082	2082	CALF Turnkey	Meath	Ruxton Oaks, Navan, Co. Meath (Phase 1)*	20	Clúid Housing	""	""	""	""	""	Q4-2021
2083	2083	CALF Turnkey	Meath	Seabury Lawns, Mornington, Co. Meath (Phase 1)	25	Clúid Housing	""	""	""	""	""	Q3-2017
2084	2084	CALF Turnkey	Meath	St Marys Dunboyne, Co. Meath (Phase 1)	16	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2021
2085	2085	CALF Turnkey	Meath	Station Road, Dunboyne, Co. Meath (Phase 1)	24	Respond	""	""	""	""	""	Q4-2018
2086	2086	CALF Turnkey	Meath	The Bungalows, Dunshauglin, Co. Meath (Phase 1)*	8	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2020
2087	2087	CALF Turnkey	Meath	The Maudelins (Phase 2), Main Street, Duleek, Co. Meath (Phase 1)*	30	Respond	""	""	""	""	""	Q4-2020
2088	2088	CALF Turnkey	Meath	The Maudlins, Trim, Co. Meath (Phase 1)	9	Clúid Housing	""	""	""	""	""	Q1-2021
2089	2089	CALF Turnkey	Meath	The Way, Broadmeadow Vale, Ratoath, Co. Meath (Phase 1)	2	Tuath Housing Association	""	""	""	""	""	Q4-2019
2090	2090	CALF Turnkey	Meath	The Willows, Dunshaughlin, Co. Meath (Phase 1)*	96	Clúid Housing	""	""	""	""	Q2-2021	""
2091	2091	CALF Turnkey	Meath	Tubberclaire, Navan, Co Meath (Phase 1)	8	Clúid Housing	""	""	""	""	""	Q2-2016
2092	2092	CALF Turnkey	Meath	Tubberclaire, Navan, Co Meath (Phase 2)	7	Clúid Housing	""	""	""	""	""	Q3-2016
2093	2093	CALF Turnkey	Meath	Tubberclaire, Navan, Co Meath (Phase 3)	8	Clúid Housing	""	""	""	""	""	Q4-2016
2094	2094	CALF Turnkey	Meath	Whitefield Hall, Bettystown, Co. Meath (Phase 1)	14	Tuath Housing Association	""	""	""	""	""	Q2-2020
2095	2095	CALF Turnkey	Meath	Whitefield Hall, Bettystown, Co. Meath (Phase 2)	13	Tuath Housing Association	""	""	""	""	""	Q3-2020
2096	2096	CALF Turnkey	Meath	Whitefield Hall, Bettystown, Co. Meath (Phase 3)	2	Tuath Housing Association	""	""	""	""	""	Q3-2021
2097	2097	SHIP CONSTRUCTION TURNKEY	Monaghan	Drumbear Wood, Monaghan Town	12	*N/A	""	""	""	""	""	Q4-2017
2098	2098	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan Town	6	*N/A	""	""	""	""	""	Q4-2017
2099	2099	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan Town (Phase 2)	8	*N/A	""	""	""	""	""	Q2-2017
2100	2100	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockroe Glen, Monaghan Town (Phase 1)	8	*N/A	""	""	""	""	""	Q2-2017
2101	2101	SHIP CONSTRUCTION TURNKEY	Monaghan	Killycard, Bree, Castleblaney	4	*N/A	""	""	""	""	""	Q2-2019
2102	2102	SHIP CONSTRUCTION TURNKEY	Monaghan	The Meadows, Smithborough	5	*N/A	""	""	""	""	""	Q4-2017
2103	2103	SHIP CONSTRUCTION TURNKEY	Monaghan	Maple Grove, Smithborough	11	*N/A	""	""	""	""	""	Q4-2018
2104	2104	SHIP CONSTRUCTION TURNKEY	Monaghan	Plás an Bhrí, Rosevale, Bree, Castleblayney	26	*N/A	""	""	""	""	""	Q4-2020
2105	2105	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard na Radhairc, Carrickmacross	6	*N/A	""	""	""	""	""	Q4-2021
2106	2106	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill an Ri, Carrickmacross	6	*N/A	""	""	""	""	""	Q4-2020
2107	2107	SHIP CONSTRUCTION TURNKEY	Monaghan	The Meadows, Smithborough	5	*N/A	""	""	""	""	""	Q3-2019
2108	2108	SHIP CONSTRUCTION TURNKEY	Monaghan	Drummond Radhairc, Carrickmacross	1	*N/A	""	""	""	""	""	Q3-2019
2109	2109	SHIP CONSTRUCTION TURNKEY	Monaghan	Cnoc na Greine, Tydavnet	6	*N/A	""	""	""	""	""	Q4-2020
2110	2110	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill Darach, Bree, Castleblayney	30	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
2111	2111	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill an Ri, Carrickmacross	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2112	2112	SHIP CONSTRUCTION TURNKEY	Monaghan	Knockcarrick, Annyalla	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2113	2113	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard na Radhairc, Carrickmacross	35	*N/A	""	""	""	""	Q3-2019	""
2114	2114	SHIP CONSTRUCTION SINGLE STAGE	Monaghan	Folly Court, Ballybay	6	*N/A	""	""	""	""	""	Q4-2021
2115	2115	SHIP CONSTRUCTION	Monaghan	Bree, Castleblayney	8	*N/A	""	""	""	""	""	Q2-2019
2116	2116	SHIP CONSTRUCTION	Monaghan	Latlorcan, Monaghan Town	43	*N/A	""	""	""	""	""	Q4-2019
2117	2117	SHIP CONSTRUCTION	Monaghan	Fermanagh St., Clones	3	*N/A	""	""	""	""	""	Q4-2020
2118	2118	SHIP CONSTRUCTION	Monaghan	Fermanagh St., Clones	3	*N/A	""	""	""	""	""	Q4-2020
2119	2119	SHIP CONSTRUCTION	Monaghan	Fermanagh St., Clones	3	*N/A	""	""	""	""	Q3-2019	""
2120	2120	SHIP CONSTRUCTION	Monaghan	Fermanagh St., Clones	6	*N/A	""	""	""	""	Q3-2019	""
2121	2121	SHIP CONSTRUCTION	Monaghan	2a & 3 Analore St., Clones	2	*N/A	""	""	""	""	Q3-2019	""
2122	2122	SHIP CONSTRUCTION	Monaghan	Abbey Gatehouse, Analore St., Clones	4	*N/A	""	""	""	""	Q3-2019	""
2123	2123	SHIP CONSTRUCTION	Monaghan	Lui Na Greine, Scotstown	6	*N/A	""	""	""	""	""	Q4-2021
2124	2124	SHIP CONSTRUCTION	Monaghan	Latlorcan, Monaghan	16	*N/A	""	""	""	""	""	Q4-2018
2125	2125	SHIP CONSTRUCTION	Monaghan	12 Church St., Ballybay	2	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2126	2126	SHIP CONSTRUCTION	Monaghan	63 Fermanagh St., Clones	3	*N/A	""	""	""	""	Q1-2020	""
2127	2127	SHIP CONSTRUCTION	Monaghan	Church Hill, Clones	2	*N/A	""	""	""	""	Q2-2021	""
2128	2128	SHIP CONSTRUCTION	Monaghan	13 McCurtain Street, Clones	1	*N/A	""	""	""	""	Q1-2021	""
2129	2129	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	26	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
2130	2130	SHIP CONSTRUCTION	Monaghan	Ballybay Courtyard, Ballybay	7	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2131	2131	CAS CONSTRUCTION	Monaghan	Drumillard, Castleblayney (Phase 2)	2	Castleblayney Care Housing Association Ltd	""	""	""	""	Q1-2021	""
2132	2132	CAS CONSTRUCTION	Monaghan	Liseggerton, Clones	19	Oaklee Housing Trust	""	""	""	""	""	Q2-2021
2133	2133	CAS CONSTRUCTION	Monaghan	Convent Lands, Carrickmacross	7	Respond	""	""	""	""	""	Q2-2017
2134	2134	CAS CONSTRUCTION	Monaghan	Birch Court Apts., 34 Main Street, Ballybay	4	North ? East Housing Association Ltd	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2135	2135	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 1)"	11	Tuath Housing Association	""	""	""	""	""	Q4-2020
2136	2136	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 2)"	6	Tuath Housing Association	""	""	""	""	""	Q2-2021
2137	2137	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 3)"	8	Tuath Housing Association	""	""	""	""	""	Q3-2021
2138	2138	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 4)"	8	Tuath Housing Association	""	""	""	""	Q2-2019	""
2139	2139	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 5)"	5	Tuath Housing Association	""	""	""	""	Q2-2019	""
2140	2140	CALF Turnkey	Monaghan	Drumbear Wood, Monaghan, Co. Monaghan  (Phase 1)*	17	Co - Operative Housing Ireland Society Limited	""	""	""	Q4-2021	""	""
2141	2141	CALF Turnkey	Monaghan	Kingscourt Road, Carrickmacross, Co Monaghan  (Phase 1)	50	Respond	""	""	""	""	""	Q4-2019
2142	2142	CALF Turnkey	Monaghan	Lakeview Apartments, Drummond Radhairc, Carrickmacross, Co Monaghan (Phase 1)*	12	North & East Housing Association Ltd	""	""	""	""	Q3-2019	""
2143	2143	CALF Turnkey	Monaghan	Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 1)*	20	Tuath Housing Association	""	""	""	Q2-2021	""	""
2144	2144	CALF Turnkey	Monaghan	Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 2)*	21	Tuath Housing Association	""	""	""	Q2-2021	""	""
2145	2145	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 1)	7	Tuath Housing Association	""	""	""	""	""	Q2-2021
2146	2146	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 2)	6	Tuath Housing Association	""	""	""	""	Q3-2019	""
2147	2147	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 3)	6	Tuath Housing Association	""	""	""	""	Q3-2019	""
2148	2148	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 4)	14	Tuath Housing Association	""	""	""	""	Q3-2019	""
2149	2149	CALF Construction	Monaghan	Post Tender - Liseggerton Road, Clones (Phase 1)	6	Oaklee Housing	""	""	""	""	""	Q4-2018
2150	2150	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 1)	8	Tuath Housing Association	""	""	""	""	Q3-2020	""
2151	2151	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 2)*	8	Tuath Housing Association	""	""	""	""	Q3-2020	""
2152	2152	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 1)*	7	Tuath Housing Association	""	""	""	""	Q2-2021	""
2153	2153	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 2)	7	Tuath Housing Association	""	""	""	""	Q2-2021	""
2154	2154	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	2	*N/A	""	""	""	""	""	Q3-2020
2155	2155	SHIP CONSTRUCTION TURNKEY	Offaly	Mill Race, Ferbane	5	*N/A	""	""	""	""	""	Q4-2017
2156	2156	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Spideoga, Cloghan	6	*N/A	""	""	""	""	""	Q2-2019
2157	2157	SHIP CONSTRUCTION TURNKEY	Offaly	Frankford, Kilcormac	12	*N/A	""	""	""	""	""	Q4-2018
2158	2158	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	4	*N/A	""	""	""	""	""	Q4-2019
2159	2159	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Greine, Cloneygowan	4	*N/A	""	""	""	""	""	Q4-2019
2160	2160	SHIP CONSTRUCTION TURNKEY	Offaly	Main Street, Daingean	8	*N/A	""	""	""	""	""	Q4-2021
2161	2161	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Greine, Clonygowan	2	*N/A	""	""	""	""	""	Q2-2021
2162	2162	SHIP CONSTRUCTION TURNKEY	Offaly	Coolgarry, Walsh Island 	4	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
2163	2163	SHIP CONSTRUCTION TURNKEY	Offaly	Mucklagh, Tullamore	8	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
2164	2164	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	2	*N/A	""	""	""	""	""	Q1-2021
2165	2165	SHIP CONSTRUCTION TURNKEY	Offaly	Bog Road, Portarlington	28	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
2166	2166	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	4	*N/A	""	""	""	""	""	Q2-2021
2167	2167	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield (formerly McCauley Dr.), Birr	29	*N/A	""	""	""	Stage 4 approved Q4-2020, the scheme is fully approved.	""	""
2168	2168	SHIP CONSTRUCTION SINGLE STAGE	Offaly	78 & 110 Church Hill, Tullamore	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2169	2169	SHIP CONSTRUCTION RAPID	Offaly	Woodfield, Birr	5	*N/A	""	""	""	""	""	Q4-2021
2170	2170	SHIP CONSTRUCTION	Offaly	Chancery Lane, Tullamore	14	*N/A	""	""	""	""	""	Q3-2020
2171	2171	SHIP CONSTRUCTION	Offaly	Circular Road, Daingean	9	*N/A	""	""	Stage 3 approved Q1-2021, the scheme is now approved to proceed to tender.	""	""	""
2172	2172	SHIP CONSTRUCTION	Offaly	Kylebeg, Banagher (Phase 2)	18	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2173	2173	SHIP CONSTRUCTION	Offaly	Blundell Wood, Edenderry	33	*N/A	""	""	""	""	""	Q4-2019
2174	2174	SHIP CONSTRUCTION	Offaly	Beechgrove, Belmont	7	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2175	2175	SHIP CONSTRUCTION	Offaly	Raheen ,Clara	38	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
2176	2176	SHIP CONSTRUCTION	Offaly	Elderberry Drive, Moneygall	4	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2177	2177	SHIP CONSTRUCTION	Offaly	Sr. Senan Avenue, Edenderry	4	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
2178	2178	SHIP CONSTRUCTION	Offaly	Dargan Drive, Chancery Lane, Tullamore (Phase 2)	20	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2179	2179	SHIP CONSTRUCTION	Offaly	1 Newbridge St., Birr	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2180	2180	SHIP CONSTRUCTION	Offaly	Sycamore Drive, Ballycumber	8	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2181	2181	SHIP CONSTRUCTION	Offaly	Circular Road, Daingean Phase 2	9	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2182	2182	CAS CONSTRUCTION	Offaly	Mountbolus	4	Mid Offaly Housing Association Ltd	""	""	""	""	""	Q4-2019
2183	2183	CAS CONSTRUCTION	Offaly	Killane Court, Edenderry	2	Túath Housing Association Ltd	""	""	""	""	""	Q2-2021
2184	2184	CAS CONSTRUCTION	Offaly	Scurragh, Birr (AKA Camcor Green)	6	Cluid Housing Association	""	""	""	""	""	Q4-2019
2185	2185	CAS CONSTRUCTION	Offaly	Clonminch, Tullamore	19	Oaklee Housing Trust	""	""	""	""	Q1-2021	""
2186	2186	CAS CONSTRUCTION	Offaly	Presentation Convent, Portarlington	39	Sophia Housing Association Ltd	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2187	2187	CAS CONSTRUCTION	Offaly	Clonamore Hotel, Tullamore	17	Sophia Housing Association Ltd	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
2188	2188	CALF Turnkey	Offaly	3 units, An Corran, Crinkle, Birr, Co. Offaly (Phase 1)	3	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2021
2189	2189	CALF Construction	Offaly	Kearney’s Field, Tullamore, Co. Offaly (Phase 1)	41	Oaklee Housing	""	""	""	""	Q2-2021	""
2190	2190	CALF Construction	Offaly	Killane Drive, Edenderry, Co Offaly (Phase 1)	25	Tuath Housing Association	""	""	""	""	""	Q2-2021
2191	2191	CALF Turnkey	Offaly	Rahan Road, Tullamore, Co. Offaly (Phase 1)*	26	Clúid Housing	""	""	""	""	Q4-2020	""
2192	2192	CALF Turnkey	Offaly	The Hawthorns, Arden Road, Tullamore, Co. Offaly (Phase 1)	16	Clúid Housing	""	""	""	""	Q1-2020	""
2193	2193	SHIP CONSTRUCTION TURNKEY	Roscommon	Monksland, Athlone	10	*N/A	""	""	""	""	""	Q3-2018
2194	2194	SHIP CONSTRUCTION TURNKEY	Roscommon	Station Road, Termon, Boyle	10	*N/A	""	""	""	""	""	Q1-2019
2195	2195	SHIP CONSTRUCTION TURNKEY	Roscommon	Lisroyne Court, Strokestown	10	*N/A	""	""	""	""	""	Q4-2019
2196	2196	SHIP CONSTRUCTION TURNKEY	Roscommon	Warren Grove, Boyle	4	*N/A	""	""	""	""	""	Q4-2018
2197	2197	SHIP CONSTRUCTION TURNKEY	Roscommon	Monksfield, Monksland	2	*N/A	""	""	""	""	""	Q4-2020
2198	2198	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland,	27	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2199	2199	SHIP CONSTRUCTION SINGLE STAGE	Roscommon	The Meadows, Castlerea 	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2200	2200	SHIP CONSTRUCTION RENEWAL	Roscommon	Ardnanagh ,Roscommon Town	1	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
2201	2201	SHIP CONSTRUCTION	Roscommon	Cloonfad	3	*N/A	""	""	""	""	""	Q2-2021
2202	2202	SHIP CONSTRUCTION	Roscommon	Greenfields, Blackstick Road, Roscommon Town	6	*N/A	""	""	""	""	""	Q3-2017
2203	2203	SHIP CONSTRUCTION	Roscommon	River Oaks, Ballaghaderreen	10	*N/A	""	""	""	""	""	Q4-2017
2204	2204	SHIP CONSTRUCTION	Roscommon	Silveroe Meadows, Boyle	12	*N/A	""	""	""	""	""	Q4-2020
2205	2205	SHIP CONSTRUCTION	Roscommon	Cluain Fraoigh, Cloonbeirne	7	*N/A	""	""	""	""	""	Q1-2021
2206	2206	SHIP CONSTRUCTION	Roscommon	Old Tuam Road,  Monksland, Athlone	2	*N/A	""	""	""	""	""	Q4-2020
2207	2207	SHIP CONSTRUCTION	Roscommon	Meadowbrook, Ballyclare Td., Ballyleague	16	*N/A	""	""	""	""	""	Q4-2021
2208	2208	SHIP CONSTRUCTION	Roscommon	Lisroyne Td., Strokestown	10	*N/A	""	""	""	""	""	Q4-2021
2209	2209	SHIP CONSTRUCTION	Roscommon	Windmill Road, Elphin Road	10	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2210	2210	SHIP CONSTRUCTION	Roscommon	Lakeview Heights, Bellspark Td., Boyle	6	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
2211	2211	SHIP CONSTRUCTION	Roscommon	Lisnamult, Ardnanagh Td., Roscommon Town	13	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2212	2212	CALF Turnkey	Roscommon	Castle View Apartments, Block B, Roscommon Town (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
2213	2213	CALF Turnkey	Roscommon	Monksland, Athlone, Co. Roscommon (Phase 1)*	35	Tuath Housing Association	""	""	""	""	Q4-2019	""
2214	2214	CALF Turnkey	Roscommon	Revised - Monksfield Park, Bealnamulla, Athlone (Phase 1)	13	Clúid Housing	""	""	""	""	""	Q3-2018
2215	2215	CALF Turnkey	Roscommon	River Oaks, Kilcolman, Ballaghaderreen, Co. Roscommon (Phase 1)	12	Respond	""	""	""	""	""	Q1-2018
2216	2216	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Roscommon	The Walk, Roscommon Town	53	*N/A	""	""	""	""	""	Q2-2021
2217	2217	SHIP CONSTRUCTION TURNKEY	Sligo	Fairgreen Square, Ballisodare	2	*N/A	""	""	""	""	""	Q4-2019
2218	2218	SHIP CONSTRUCTION TURNKEY	Sligo	Ursuline Convent	14	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2219	2219	SHIP CONSTRUCTION TURNKEY	Sligo	Ursuline Convent	16	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2220	2220	SHIP CONSTRUCTION TURNKEY	Sligo	Ursuline Convent	30	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2221	2221	SHIP CONSTRUCTION TURNKEY	Sligo	Ursuline Convent	13	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2222	2222	SHIP CONSTRUCTION SINGLE STAGE	Sligo	St. Joseph's Terrace, Sligo	1	*N/A	""	""	""	""	""	Q4-2019
2223	2223	SHIP CONSTRUCTION	Sligo	Collooney	18	*N/A	""	""	""	""	""	Q4-2019
2224	2224	SHIP CONSTRUCTION	Sligo	Knappagh Road, Sligo	28	*N/A	""	""	""	""	""	Q4-2020
2225	2225	SHIP CONSTRUCTION	Sligo	Caltragh, Culleens	1	*N/A	""	""	""	""	""	Q4-2018
2226	2226	SHIP CONSTRUCTION	Sligo	Fr. Flanagan Terrace	14	*N/A	""	""	""	""	""	Q3-2018
2227	2227	SHIP CONSTRUCTION	Sligo	Daghloonagh, Keash - SRD	1	*N/A	""	""	""	""	""	Q4-2016
2228	2228	SHIP CONSTRUCTION	Sligo	Rosses Point	14	*N/A	""	""	""	""	""	Q4-2019
2229	2229	SHIP CONSTRUCTION	Sligo	Fr. Flanagan Terrace	8	*N/A	""	""	""	""	""	Q4-2017
2230	2230	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 1)	10	*N/A	""	""	""	""	""	Q4-2021
2231	2231	SHIP CONSTRUCTION	Sligo	Dromore West 	10	*N/A	""	""	""	""	""	Q4-2021
2232	2232	SHIP CONSTRUCTION	Sligo	Robbers' Lane, Maugheraboy, Sligo	62	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2233	2233	SHIP CONSTRUCTION	Sligo	House at Ballinode	1	*N/A	""	""	""	""	""	Q4-2018
2234	2234	SHIP CONSTRUCTION	Sligo	SRD at Crowagh, Dromore West	1	*N/A	""	""	""	""	""	Q4-2021
2235	2235	SHIP CONSTRUCTION	Sligo	Gormley Park, Bunnanadden	6	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2236	2236	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 2) & The Green Rd,	19	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
2237	2237	CAS CONSTRUCTION	Sligo	Cuan Iosa, Ballymote	8	Society of Saint Vincent de Paul	""	""	""	""	""	Q3-2020
2238	2238	CAS CONSTRUCTION	Sligo	Killeshin, First Sea Road, Sligo	5	Newgrove Housing Association Ltd	""	""	""	""	Q4-2020	""
2239	2239	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Sligo	Rathellen, Finisklin, Co. Sligo	63	*N/A	""	Q4-2021	""	""	""	""
2240	2240	SHIP CONSTRUCTION TURNKEY	South Dublin	Ardsolus, Kingswood, Dublin 24	2	*N/A	""	""	""	""	""	Q4-2018
2241	2241	SHIP CONSTRUCTION TURNKEY	South Dublin	White Pines, Stocking Avenue, Rathfarnham, Dublin 16	26	*N/A	""	""	""	""	""	Q4-2018
2242	2242	SHIP CONSTRUCTION TURNKEY	South Dublin	Shackleton Park / Gandon Park, Adamstown	22	*N/A	""	""	""	""	""	Q4-2019
2243	2243	SHIP CONSTRUCTION TURNKEY	South Dublin	Gandon Park, Adamstown, Lucan	12	*N/A	""	""	""	""	""	Q4-2019
2244	2244	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	37 Greenfort Gardens, Clondalkin	2	*N/A	""	""	""	""	""	Q4-2021
2245	2245	SHIP CONSTRUCTION RAPID	South Dublin	Killininny Road, Firhouse (Old Mill, Old Bawn)	24	*N/A	""	""	""	""	""	Q4-2018
2246	2246	SHIP CONSTRUCTION RAPID	South Dublin	St Cuthbert's, Clondalkin (Phase 1)	63	*N/A	""	""	""	""	""	Q3-2019
2247	2247	SHIP CONSTRUCTION RAPID	South Dublin	St. Aidan's Brookfield, Tallaght	47	*N/A	""	""	""	""	""	Q2-2018
2248	2248	SHIP CONSTRUCTION RAPID	South Dublin	St. Marks Avenue, Clondalkin	41	*N/A	""	""	""	""	Q3-2020	""
2249	2249	SHIP CONSTRUCTION RAPID	South Dublin	St. Aidan's Brookfield, Tallaght	22	*N/A	""	""	""	""	""	Q3-2018
2250	2250	SHIP CONSTRUCTION RAPID	South Dublin	St. Aidan's Brookfield, Tallaght	21	*N/A	""	""	""	""	""	Q4-2018
2251	2251	SHIP CONSTRUCTION RAPID	South Dublin	Riversdale, Clondalkin, Dublin 22	22	*N/A	""	""	""	""	Q4-2020	""
2252	2252	SHIP CONSTRUCTION RAPID	South Dublin	Riverside Cottages, Templeogue	10	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2253	2253	SHIP CONSTRUCTION RAPID	South Dublin	Riversdale, Clondalkin, Dublin 22	21	*N/A	""	""	""	""	Q4-2020	""
2254	2254	SHIP CONSTRUCTION	South Dublin	Killinarden, Tallaght	17	*N/A	""	""	""	""	""	Q4-2018
2255	2255	SHIP CONSTRUCTION	South Dublin	Letts Field, Neilstown, Clondalkin	37	*N/A	""	""	""	""	""	Q4-2018
2256	2256	SHIP CONSTRUCTION	South Dublin	Owendoher, Ballyboden,  Rathfarnham	40	*N/A	""	""	""	""	""	Q1-2019
2257	2257	SHIP CONSTRUCTION	South Dublin	Dromcarra, Tallaght	14	*N/A	""	""	""	""	""	Q4-2018
2258	2258	SHIP CONSTRUCTION	South Dublin	Fortunestown (MacUilliam)	28	*N/A	""	""	""	""	""	Q4-2018
2259	2259	SHIP CONSTRUCTION	South Dublin	Mayfield Estate, Clondalkin	17	*N/A	""	""	""	""	""	Q2-2018
2260	2260	SHIP CONSTRUCTION	South Dublin	St Marks Green, Clondalkin	11	*N/A	""	""	""	""	""	Q3-2018
2261	2261	SHIP CONSTRUCTION	South Dublin	Balgaddy F, Griffeen Avenue, Lucan Co. Dublin	69	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
2262	2262	SHIP CONSTRUCTION	South Dublin	St Finians	2	*N/A	""	""	""	""	""	Q3-2016
2263	2263	SHIP CONSTRUCTION	South Dublin	Suncroft, Tallaght	10	*N/A	""	""	""	""	""	Q4-2016
2264	2264	SHIP CONSTRUCTION	South Dublin	Belgard Road	3	*N/A	""	""	""	""	""	Q1-2016
2265	2265	SHIP CONSTRUCTION	South Dublin	St. Catherine’s, Knockmore Avenue, Killinarden, Tallaght	12	*N/A	""	""	""	""	Q4-2020	""
2266	2266	SHIP CONSTRUCTION	South Dublin	Homeville, Knocklyon, Dublin 16	16	*N/A	""	""	""	""	Q4-2020	""
2267	2267	SHIP CONSTRUCTION	South Dublin	Killinarden, Tallaght	9	*N/A	""	""	""	""	""	Q1-2019
2268	2268	SHIP CONSTRUCTION	South Dublin	Nangor Road, Clondalkin, Dublin 22	93	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2269	2269	SHIP CONSTRUCTION	South Dublin	Grand Canal, Lindisfarne, Clondalkin,	19	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2270	2270	CAS CONSTRUCTION TURNKEY	South Dublin	Oakridge, Ballynakelly,Edge, Newcastle, Co. Dublin	3	Túath Housing Association Ltd	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2271	2271	CAS CONSTRUCTION TURNKEY	South Dublin	3 Cornerpark Rise	1	Arlington Novas Ireland Ltd	""	""	""	""	""	Q4-2021
2272	2272	CAS CONSTRUCTION	South Dublin	Collinstown Grove, Clondalkin	4	Túath Housing Association Ltd	""	""	""	""	""	Q1-2020
2273	2273	CALF Turnkey	South Dublin	2 properties Tullyhall, Lucan, County Dublin (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q2-2019
2274	2274	CALF Turnkey	South Dublin	6 units Elder Heath, Kiltipper Road, Tallaght, Dublin 24 (Phase 1)*	6	Clúid Housing	""	""	""	""	""	Q4-2019
2275	2275	CALF Turnkey	South Dublin	Ardsolus, Old Naas Road, Dublin 22 (Phase 1)	10	Respond	""	""	""	""	""	Q3-2019
2276	2276	CALF Turnkey	South Dublin	Aylmer Heath, Newcastle, Co. Dublin 22 (Phase 1)	32	Respond	""	""	""	""	""	Q4-2020
2277	2277	CALF Turnkey	South Dublin	Ballynakelly, Newcastle, Co. Dublin (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q4-2018
2278	2278	CALF Turnkey	South Dublin	Ballynakelly, Newcastle, Co. Dublin (Phase 2)	4	Tuath Housing Association	""	""	""	""	""	Q1-2019
2279	2279	CALF Turnkey	South Dublin	Balrothery, Castletymon Road, Dublin Road (Phase 1)*	13	Clúid Housing	""	""	""	""	""	Q4-2019
2280	2280	CALF Turnkey	South Dublin	Broadfield Grove, Rathcoole, Co. Dublin (Phase 1)*	14	Oaklee Housing	""	""	""	""	""	Q3-2017
2281	2281	CALF Turnkey	South Dublin	Burgage Gardens, Newcastle, Co. Dublin (Phase 1)*	4	Respond	""	""	""	""	""	Q2-2020
2282	2282	CALF Turnkey	South Dublin	Burgage, Newcastle, Co. Dublin 22 (Phase 1)	10	Respond	""	""	""	""	""	Q4-2019
2283	2283	CALF Turnkey	South Dublin	Burgage, Newcastle, Co. Dublin 22 (Phase 2)	26	Respond	""	""	""	""	""	Q2-2020
2284	2284	CALF Turnkey	South Dublin	Citywest Quarter, Citywest, Dublin 24 (Phase 1)*	32	Tuath Housing Association	""	""	""	""	""	Q2-2021
2285	2285	CALF Turnkey	South Dublin	Citywest Village House, Citywest Village, D24 (Phase 1)*	36	Fold Housing Association Ireland Ltd	""	""	""	""	Q1-2020	""
2286	2286	CALF Turnkey	South Dublin	Cloverhill Lodge, Cloverhill Rd, Clondalkin, D22 (Phase 1)*	40	Oaklee Housing	""	""	""	""	Q2-2021	""
2287	2287	CALF Turnkey	South Dublin	Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 1)	45	Tuath Housing Association	""	""	""	""	""	Q4-2020
2288	2288	CALF Turnkey	South Dublin	Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 2)	15	Tuath Housing Association	""	""	""	""	""	Q4-2020
2289	2289	CALF Turnkey	South Dublin	Cloverhill Road, Raheen, Clondalkin, Dublin 22 (Phase 3)*	23	Tuath Housing Association	""	""	""	""	""	Q4-2020
2290	2290	CALF Turnkey	South Dublin	Cuil Duin Green, Cuil Duin, Citywest, Dublin 24 (Phase 1)*	24	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2020
2291	2291	CALF Turnkey	South Dublin	De Selby Heights, Tallaght, Dublin 24 (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q4-2019
2292	2292	CALF Turnkey	South Dublin	Dodderbrook (Apartments), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*	6	Clúid Housing	""	""	""	""	""	Q1-2018
2293	2293	CALF Turnkey	South Dublin	Dodderbrook (Houses), Oldcourt Road, Ballycullen, Dublin 24 (Phase 1)*	8	Clúid Housing	""	""	""	""	""	Q1-2018
2294	2294	CALF Turnkey	South Dublin	Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q4-2019
2295	2295	CALF Turnkey	South Dublin	Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 2)*	9	Clúid Housing	""	""	""	""	""	Q1-2021
2296	2296	CALF Turnkey	South Dublin	Dodderbrook, Oldcourt Road, Ballycllen, Dublin 24 (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q3-2018
2297	2297	CALF Turnkey	South Dublin	Edenbrook, Citywest, Dublin 24 (Phase 1)	17	Tuath Housing Association	""	""	""	""	""	Q4-2019
2298	2298	CALF Turnkey	South Dublin	Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 1)*	18	Clúid Housing	""	""	""	""	""	Q1-2018
2299	2299	CALF Turnkey	South Dublin	Elder Heath, Kiltipper Road, Tallaght, Dublin 24  (Phase 2)*	10	Clúid Housing	""	""	""	""	""	Q2-2018
2300	2300	CALF Construction	South Dublin	Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 1)	40	Clúid Housing	""	""	""	""	Q3-2020	""
2301	2301	CALF Turnkey	South Dublin	Finians Way, Newcastle South, Newcastle, Co. Dublin (Phase 1)*	2	Clanmil Housing Association Ireland	""	""	""	""	""	Q4-2021
2302	2302	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 1)	32	Respond	""	""	""	""	""	Q3-2021
2303	2303	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 2)	38	Respond	""	""	""	""	""	Q3-2021
2304	2304	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 3)*	24	Respond	""	""	""	""	""	Q4-2021
2305	2305	CALF Turnkey	South Dublin	Graydon, Newcastle, Co. Dublin (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q4-2021
2306	2306	CALF Turnkey	South Dublin	Green Lane, Rathcoole, Co. Dublin (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q4-2020
2307	2307	CALF Turnkey	South Dublin	Green Lane, Rathcoole, Co. Dublin (Phase 2)*	9	Tuath Housing Association	""	""	""	""	""	Q4-2020
2308	2308	CALF Turnkey	South Dublin	Hallwell, Tubber Lane, Adamstown, Co Dublin (Phase 1)*	45	The Iveagh Trust	""	""	""	""	""	Q4-2021
2309	2309	CALF Turnkey	South Dublin	Kingswood, Old Ballymount Road, Tallaght, Dublin 24 (Phase 1)*	24	Respond	""	""	""	""	""	Q4-2021
2310	2310	CALF Turnkey	South Dublin	Millford Manor, Clondalkin - Apartments (Phase 1)*	13	Clúid Housing	""	""	""	""	""	Q2-2018
2311	2311	CALF Turnkey	South Dublin	Millford Manor, Clondalkin - Apartments (Phase 2)	12	Clúid Housing	""	""	""	""	""	Q4-2018
2312	2312	CALF Turnkey	South Dublin	Millford Manor, Clondalkin - Houses (Phase 1)	25	Clúid Housing	""	""	""	""	""	Q1-2017
2313	2313	CALF Turnkey	South Dublin	Millford Manor, Clondalkin - Houses (Phase 2)	15	Clúid Housing	""	""	""	""	""	Q3-2017
2314	2314	CALF Turnkey	South Dublin	Millford Manor, Cloverhill Road, Clondalkin, Dublin 22 (Phase 1)*	2	Clúid Housing	""	""	""	""	""	Q4-2018
2315	2315	CALF Turnkey	South Dublin	Mountain Gate, Kiltipper Rd., Dublin 24 (Phase 1)*	22	Co - Operative Housing Ireland Society Limited	""	""	""	Q3-2021	""	""
2316	2316	CALF Turnkey	South Dublin	Moyglas, Lucan, Co Dublin (Phase 1)	13	Respond	""	""	""	""	""	Q1-2016
2317	2317	CALF Turnkey	South Dublin	Moyglas, Lucan, Co Dublin (Phase 2)*	1	Respond	""	""	""	""	""	Q2-2017
2318	2318	CALF Turnkey	South Dublin	New Bancroft, Tallaght, Dublin 24 (Phase 1)*	16	Clúid Housing	""	""	""	""	""	Q3-2017
2319	2319	CALF Construction	South Dublin	Old Lucan Road, Palmerstown, Dublin 20 (Phase 1)	4	Tuath Housing Association	""	""	""	Q3-2021	""	""
2320	2320	CALF Turnkey	South Dublin	Palmerstown Avenue, Dublin 20 (Phase 1)	7	Respond	""	""	""	""	""	Q4-2020
2321	2321	CALF Turnkey	South Dublin	Palmerstown Way, Clondalkin, Dublin 22 (Phase 1)*	6	Tuath Housing Association	""	""	""	""	""	Q3-2018
2322	2322	CALF Turnkey	South Dublin	Phase 2, Aylmer Drive, Aylmer Heath, Newcastle, Co. Dublin (Phase 1)*	17	Respond	""	""	""	""	""	Q2-2021
2323	2323	CALF Turnkey	South Dublin	Raheen House, Old Nangor Road, Clondalkin, Dublin 22 (Phase 1)	9	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2019
2324	2324	CALF Turnkey	South Dublin	Rathmill Meadows and Green, Rathcoole, Co. Dublin (Phase 1)*	11	Oaklee Housing	""	""	""	""	""	Q4-2019
2325	2325	CALF Turnkey	South Dublin	Sallypark, Clondalkin, Dublin 22 (Phase 1)*	85	Clúid Housing	""	""	""	""	Q4-2020	""
2326	2326	CALF Turnkey	South Dublin	San Guida, New Road, Clondalkin, Dublin 22 (Phase 1)*	21	Clúid Housing	""	""	""	""	Q3-2021	""
2327	2327	CALF Turnkey	South Dublin	Scholarstown Road, Rathfarnham, Dublin 16 (Phase 1)*	7	Circle Voluntary Housing Association Ltd	""	""	""	""	Q2-2019	""
2328	2328	CALF Turnkey	South Dublin	Scholarstown Road, Rathfarnham, Dublin 16 (Phase 2)*	7	Circle Voluntary Housing Association Ltd	""	""	""	""	Q2-2019	""
2329	2329	CALF Turnkey	South Dublin	Scholarstown Wood (Apartments), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*	6	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2018
2330	2330	CALF Turnkey	South Dublin	Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 1)*	3	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2017
2331	2331	CALF Turnkey	South Dublin	Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 2)*	4	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2018
2332	2332	CALF Turnkey	South Dublin	Scholarstown Wood (Houses), Scholarstown Road, Rathfarnham, Dublin 16  (Phase 3)*	1	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2019
2333	2333	CALF Turnkey	South Dublin	Shackleton Park, Lucan, Co. Dublin (Phase 1)*	8	Clúid Housing	""	""	""	""	""	Q2-2019
2334	2334	CALF Turnkey	South Dublin	Somerton, Lucan, Co. Dublin (Phase 1)*	32	Respond	""	""	""	""	""	Q4-2019
2335	2335	CALF Construction	South Dublin	St. Catherine’s, Knockmore Avenue, Killinarden, Tallaght, Dublin 24 (Phase 1)	2	Sophia Housing Association Ltd	""	""	""	""	Q2-2021	""
2336	2336	CALF Turnkey	South Dublin	St. Johns, Firhouse, Dublin 24 (Phase 1)*	10	Respond	""	""	""	""	""	Q4-2019
2337	2337	CALF Turnkey	South Dublin	Station Road, Clondalkin, Co. Dublin (Phase 1)	5	Respond	""	""	""	""	""	Q3-2017
2338	2338	CALF Turnkey	South Dublin	Stone Masons Court, Fortunestown Lane, Citywest Dublin (Phase 1)*	12	Clúid Housing	""	""	""	""	""	Q2-2019
2339	2339	CALF Turnkey	South Dublin	Temple Court, Temple Woods, Greenhills Road, Dublin 12 (Phase 1)*	6	Tuath Housing Association	""	""	""	""	""	Q4-2018
2340	2340	CALF Turnkey	South Dublin	The Mews, Citywest Village, Citywest, Dublin 24 (Phase 1)*	22	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2020
2341	2341	CALF Turnkey	South Dublin	The Rise, Citywest Village, Citywest, Dublin 24 (Phase 1)*	13	Fold Housing Association Ireland Ltd	""	""	""	""	""	Q4-2019
2342	2342	CALF Construction	South Dublin	The Weir, Whitestown Way, Tallaght, Dublin 24 (Phase 1)	81	Clúid Housing	""	""	""	""	Q2-2021	""
2343	2343	CALF Turnkey	South Dublin	Tullyhall, Lucan, Co Dublin (Phase 1)*	2	Tuath Housing Association	""	""	""	""	""	Q3-2017
2344	2344	CALF Turnkey	South Dublin	Tullyhall, Lucan, Co Dublin (Phase 2)*	2	Tuath Housing Association	""	""	""	""	""	Q4-2018
2345	2345	CALF Turnkey	South Dublin	Westpark, Garters Lane, Saggert, Co Dublin  (Phase 1)	28	Clúid Housing	""	""	""	""	""	Q4-2018
2346	2346	CALF Turnkey	South Dublin	Westpark, Garters Lane, Saggert, Co Dublin  (Phase 2)	28	Clúid Housing	""	""	""	""	""	Q2-2019
2347	2347	CALF Turnkey	South Dublin	Westpark, Garters Lane, Saggert, Co Dublin  (Phase 3)	28	Clúid Housing	""	""	""	""	""	Q4-2019
2348	2348	CALF Turnkey	South Dublin	Wilkins Court, Limekiln Lane, Dublin 12 (Phase 1)*	6	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2019
2349	2349	CALF Turnkey	South Dublin	Wilkins View, Greenhills, Dublin 12 (Phase 1)*	3	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q2-2018
2350	2350	CALF Turnkey	South Dublin	Willowview, Ballyboden Road, Rathfarnham, Dublin 14 (Phase 1)*	12	Clúid Housing	""	""	""	""	""	Q2-2021
2351	2351	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	South Dublin	Corkage Grange (part of Kilcarbery)	109	*N/A	""	""	""	""	""	Q4-2020
2352	2352	SHIP CONSTRUCTION TURNKEY	Tipperary	Cloneen Road, Fethard	6	*N/A	""	""	""	""	""	Q2-2019
2353	2353	SHIP CONSTRUCTION TURNKEY	Tipperary	Strylea, Fethard	3	*N/A	""	""	""	""	""	Q4-2020
2354	2354	SHIP CONSTRUCTION TURNKEY	Tipperary	Ardan, Borrisokane	9	*N/A	""	""	""	""	""	Q4-2018
2355	2355	SHIP CONSTRUCTION TURNKEY	Tipperary	An Grianan, Killenaule, Thurles	4	*N/A	""	""	""	""	""	Q4-2018
2356	2356	SHIP CONSTRUCTION TURNKEY	Tipperary	Ardan, Borrisokane	4	*N/A	""	""	""	""	""	Q2-2019
2357	2357	SHIP CONSTRUCTION TURNKEY	Tipperary	An Grianan, Killenaule, Thurles	5	*N/A	""	""	""	""	""	Q4-2019
2358	2358	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	18	*N/A	""	""	""	""	Q3-2020	""
2359	2359	SHIP CONSTRUCTION TURNKEY	Tipperary	Ma Charoin, Manna South, Templemore	13	*N/A	""	""	""	""	Q1-2021	""
2360	2360	SHIP CONSTRUCTION TURNKEY	Tipperary	Cloneen Road, Fethard	5	*N/A	""	""	""	""	""	Q3-2019
2361	2361	SHIP CONSTRUCTION TURNKEY	Tipperary	Cloneen Road, Fethard	6	*N/A	""	""	""	""	""	Q4-2019
2362	2362	SHIP CONSTRUCTION TURNKEY	Tipperary	Glencree, Newport	3	*N/A	""	""	""	""	""	Q4-2019
2363	2363	SHIP CONSTRUCTION TURNKEY	Tipperary	Cloneen Road, Fethard	4	*N/A	""	""	""	""	""	Q4-2019
2364	2364	SHIP CONSTRUCTION TURNKEY	Tipperary	An Grianan, Killenaule, Thurles	5	*N/A	""	""	""	""	""	Q4-2019
2365	2365	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	23	*N/A	""	""	""	""	Q3-2020	""
2366	2366	SHIP CONSTRUCTION TURNKEY	Tipperary	Rosanna Close, Tipperary Town	18	*N/A	""	""	""	""	""	Q4-2020
2367	2367	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	10	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2368	2368	SHIP CONSTRUCTION TURNKEY	Tipperary	Rosanna Close, Tipperary Town	1	*N/A	""	""	""	""	Q3-2020	""
2369	2369	SHIP CONSTRUCTION TURNKEY	Tipperary	Hazel Close, Carrick on Suir	14	*N/A	""	""	""	""	""	Q4-2021
2370	2370	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor	2	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2371	2371	SHIP CONSTRUCTION TURNKEY	Tipperary	Cois Abhainn, Mullinahone	3	*N/A	""	""	""	""	""	Q4-2021
2372	2372	SHIP CONSTRUCTION TURNKEY	Tipperary	Glentara, Roscrea	2	*N/A	""	""	""	""	""	Q4-2021
2373	2373	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	11	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2374	2374	SHIP CONSTRUCTION SINGLE STAGE	Tipperary	Mulkear View, Newport, Tipperary	3	*N/A	""	""	""	""	""	Q4-2018
2375	2375	SHIP CONSTRUCTION SINGLE STAGE	Tipperary	Grange Road, Ballina	4	*N/A	""	""	""	""	""	Q4-2020
2376	2376	SHIP CONSTRUCTION RENEWAL	Tipperary	Boherclough Street, Cashel	9	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
2377	2377	SHIP CONSTRUCTION	Tipperary	Ard na Greine, Clonmel	2	*N/A	""	""	""	""	Q4-2020	""
2378	2378	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A	""	""	""	""	""	Q1-2021
2379	2379	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A	""	""	""	""	""	Q4-2021
2380	2380	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	10	*N/A	""	""	""	""	""	Q4-2021
2381	2381	SHIP CONSTRUCTION	Tipperary	Treacy Park, Carrick on Suir	1	*N/A	""	""	""	""	""	Q3-2018
2382	2382	SHIP CONSTRUCTION	Tipperary	Templetouhy	10	*N/A	""	""	""	""	""	Q4-2021
2383	2383	SHIP CONSTRUCTION	Tipperary	Abbey Street, Cahir	10	*N/A	""	""	""	""	Q3-2020	""
2384	2384	SHIP CONSTRUCTION	Tipperary	Borrisokane	14	*N/A	""	""	""	""	""	Q4-2021
2385	2385	SHIP CONSTRUCTION	Tipperary	Portroe, Nenagh	14	*N/A	""	""	""	""	Q4-2021	""
2386	2386	SHIP CONSTRUCTION	Tipperary	Cloughjordan	2	*N/A	""	""	""	""	""	Q2-2021
2387	2387	SHIP CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	26	*N/A	""	""	""	""	""	Q3-2020
2388	2388	SHIP CONSTRUCTION	Tipperary	Gortataggart, Thurles	2	*N/A	""	""	""	""	""	Q4-2018
2389	2389	SHIP CONSTRUCTION	Tipperary	Kilcooly Way, Gortnahoe	5	*N/A	""	""	""	""	""	Q3-2020
2390	2390	SHIP CONSTRUCTION	Tipperary	Lacey Avenue, Templemore	3	*N/A	""	""	""	""	""	Q3-2016
2391	2391	SHIP CONSTRUCTION	Tipperary	Mitchel St., Thurles	1	*N/A	""	""	""	""	""	Q4-2021
2392	2392	SHIP CONSTRUCTION	Tipperary	Borrisoleigh	1	*N/A	""	""	""	""	""	Q4-2016
2393	2393	SHIP CONSTRUCTION	Tipperary	Lower Ballingarry	1	*N/A	""	""	""	""	""	Q2-2016
2394	2394	SHIP CONSTRUCTION	Tipperary	Poulamaleen, Faugheen	1	*N/A	""	""	""	""	""	Q2-2016
2395	2395	SHIP CONSTRUCTION	Tipperary	Cormack Drive, Nenagh	12	*N/A	""	""	""	""	Q3-2020	""
2396	2396	SHIP CONSTRUCTION	Tipperary	Lacey Avenue, Templemore	1	*N/A	""	""	""	""	""	Q3-2017
2397	2397	SHIP CONSTRUCTION	Tipperary	Borrisoleigh	1	*N/A	""	""	""	""	""	Q4-2018
2398	2398	SHIP CONSTRUCTION	Tipperary	Bansha	14	*N/A	""	""	""	""	Q3-2021	""
2399	2399	SHIP CONSTRUCTION	Tipperary	Ned Hayes Drive, Twomileborris, Thurles	22	*N/A	""	""	""	""	Q3-2021	""
2400	2400	SHIP CONSTRUCTION	Tipperary	Donohill	8	*N/A	""	""	""	""	Q3-2021	""
2401	2401	SHIP CONSTRUCTION	Tipperary	Mullinahone	10	*N/A	""	""	""	""	Q1-2021	""
2402	2402	SHIP CONSTRUCTION	Tipperary	Ballyclerihan	14	*N/A	""	""	""	""	Q3-2021	""
2403	2403	SHIP CONSTRUCTION	Tipperary	Ard Alainn, Moyne	9	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2404	2404	SHIP CONSTRUCTION	Tipperary	Ardcroney	4	*N/A	""	""	Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.	""	""	""
2405	2405	SHIP CONSTRUCTION	Tipperary	Comeragh Drive, Clonmel	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2406	2406	SHIP CONSTRUCTION	Tipperary	Church Street, Templemore	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2407	2407	SHIP CONSTRUCTION	Tipperary	Woodview Close, Castle Crescent,  Nenagh	10	*N/A	""	""	Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.	""	""	""
2408	2408	SHIP CONSTRUCTION	Tipperary	Grove Street. Roscrea	6	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2409	2409	SHIP CONSTRUCTION	Tipperary	William Street, Clonmel	4	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2410	2410	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	26	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2411	2411	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A	""	""	""	""	""	Q2-2021
2412	2412	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A	""	""	""	""	Q2-2020	""
2413	2413	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	1	*N/A	""	""	""	""	Q4-2020	""
2414	2414	SHIP CONSTRUCTION	Tipperary	Mountain View, Cahir	23	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2415	2415	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	20	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2416	2416	SHIP CONSTRUCTION	Tipperary	Borrisokane	2	*N/A	""	""	""	""	Q3-2020	""
2417	2417	SHIP CONSTRUCTION	Tipperary	Mountain View Drive, Cahir	20	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2418	2418	CAS CONSTRUCTION TURNKEY	Tipperary	Monastery Close, Templemore Road, Thurles	15	Thurles Lions Trust Housing Assoc.	""	""	""	""	""	Q2-2019
2419	2419	CAS CONSTRUCTION TURNKEY	Tipperary	Drummin Village, Nenagh	8	Nenagh Voluntary Housing Association	""	""	""	""	""	Q4-2020
2420	2420	CAS CONSTRUCTION TURNKEY	Tipperary	Kichham Street, Carrick en Suir	12	Túath Housing Association Ltd	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2421	2421	CAS CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	9	Cluid Housing Association	""	""	""	""	Q2-2021	""
2422	2422	CAS CONSTRUCTION	Tipperary	Stanwix House, Kickham Street, Thurles	19	Thurles Lions Trust Housing Assoc.	""	""	""	""	Q2-2021	""
2423	2423	CAS CONSTRUCTION	Tipperary	Main Street, Templemore	14	Templemore Voluntary Housing Association	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
2424	2424	CAS CONSTRUCTION	Tipperary	Deerpark Road, Ashwell's Lot	2	SPADE – St. Patrick’s Dwellings for the Elderly	""	""	""	""	Q2-2021	""
2425	2425	CALF Turnkey	Tipperary	Abbey Court Lodges, Old Dublin Road, Nenagh, Co Tipperary (Phase 1)	16	Focus Housing Association CLG	""	""	""	""	Q4-2021	""
2426	2426	CALF Turnkey	Tipperary	An Duiche, Tipperary Town, Co. Tipperary (Phase 1)	41	Respond	""	""	""	""	""	Q4-2019
2427	2427	CALF Turnkey	Tipperary	An Duiche, Tipperary Town, Co. Tipperary (Phase 2)	2	Respond	""	""	""	""	""	Q4-2019
2428	2428	CALF Turnkey	Tipperary	Ashbury, Roscrea, Co Tipperary (Phase 1)	12	Clúid Housing	""	""	""	""	""	Q2-2017
2429	2429	CALF Turnkey	Tipperary	Ashgrove, Monadreen, Thurles, Co Tipperary  (Phase 1)	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
2430	2430	CALF Turnkey	Tipperary	Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
2431	2431	CALF Turnkey	Tipperary	Ashgrove, Monadreen, Thurles, Co. Tipperary (Phase 2)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
2432	2432	CALF Turnkey	Tipperary	Ballygraigue Court, Ballygraigue Road, Nenagh (Phase 1)	5	Clúid Housing	""	""	""	""	Q4-2020	""
2433	2433	CALF Turnkey	Tipperary	Mill Street, Carrick on Suir, Co. Tipperary (Phase 1)	22	Tuath Housing Association	""	""	""	""	""	Q3-2020
2434	2434	CALF Turnkey	Tipperary	The Avenue, Drummin Village, Nenagh, Co. Tipperary (Phase 1)	13	Focus Housing Association CLG	""	""	""	""	""	Q4-2020
2435	2435	CALF Turnkey	Tipperary	Wallers Lot, East Cashel, Co. Tipperary (Phase 1)*	40	Tuath Housing Association	""	""	""	""	Q4-2021	""
2436	2436	SHIP CONSTRUCTION TURNKEY	Waterford	Kilrush, Dungarvan	8	*N/A	""	""	""	""	""	Q3-2018
2437	2437	SHIP CONSTRUCTION TURNKEY	Waterford	Gibbethill, Gracedieu	5	*N/A	""	""	""	""	""	Q3-2018
2438	2438	SHIP CONSTRUCTION TURNKEY	Waterford	Carrickphierish, Gracedieu, Waterford	31	*N/A	""	""	""	""	""	Q4-2018
2439	2439	SHIP CONSTRUCTION TURNKEY	Waterford	Shandon, Dungarvan	5	*N/A	""	""	""	""	""	Q3-2018
2440	2440	SHIP CONSTRUCTION TURNKEY	Waterford	Airport Road, Waterford City	33	*N/A	""	""	""	""	""	Q4-2018
2441	2441	SHIP CONSTRUCTION TURNKEY	Waterford	Kilrush, Dungarvan	10	*N/A	""	""	""	""	""	Q4-2018
2442	2442	SHIP CONSTRUCTION TURNKEY	Waterford	Kilrush, Dungarvan	21	*N/A	""	""	""	""	""	Q4-2018
2443	2443	SHIP CONSTRUCTION TURNKEY	Waterford	Lacken Road, Waterford	20	*N/A	""	""	""	""	""	Q3-2019
2444	2444	SHIP CONSTRUCTION TURNKEY	Waterford	Lacken Road, Waterford	14	*N/A	""	""	""	""	""	Q4-2019
2445	2445	SHIP CONSTRUCTION TURNKEY	Waterford	Lacken Road, Waterford	6	*N/A	""	""	""	""	""	Q2-2020
2446	2446	SHIP CONSTRUCTION TURNKEY	Waterford	Lacken Road, Waterford	15	*N/A	""	""	""	""	""	Q3-2020
2447	2447	SHIP CONSTRUCTION TURNKEY	Waterford	Estuary Heights, Shandon, Dungarvan	6	*N/A	""	""	""	""	""	Q3-2019
2448	2448	SHIP CONSTRUCTION TURNKEY	Waterford	Estuary Heights, Shandon, Dungarvan	8	*N/A	""	""	""	""	""	Q4-2019
2449	2449	SHIP CONSTRUCTION TURNKEY	Waterford	Estuary Heights, Shandon, Dungarvan	6	*N/A	""	""	""	""	""	Q4-2019
2450	2450	SHIP CONSTRUCTION TURNKEY	Waterford	Mount Suir, Gracedieu, Carrickphierish	18	*N/A	""	""	""	""	""	Q4-2019
2451	2451	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow	2	*N/A	""	""	""	""	""	Q3-2020
2452	2452	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	19	*N/A	""	""	""	""	""	Q4-2020
2453	2453	SHIP CONSTRUCTION TURNKEY	Waterford	7A and 8A Barnes Lane, The Glen, Waterford	2	*N/A	""	""	""	""	""	Q4-2019
2454	2454	SHIP CONSTRUCTION TURNKEY	Waterford	Sherlock Walk, Gracedieu, Waterford	2	*N/A	""	""	""	""	""	Q2-2020
2455	2455	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	13	*N/A	""	""	""	""	""	Q1-2021
2456	2456	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	10	*N/A	""	""	""	""	""	Q2-2021
2457	2457	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	23	*N/A	""	""	""	""	""	Q2-2021
2458	2458	SHIP CONSTRUCTION TURNKEY	Waterford	The Courtyard, Morrissons Road, Waterford City	8	*N/A	""	""	""	""	""	Q2-2021
2459	2459	SHIP CONSTRUCTION TURNKEY	Waterford	Bounds Court, Airport Road, Waterford	15	N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2460	2460	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main Street, Aglish; Bye Lane, Kilmacthomas, Co. Waterford	6	N/A	""	""	""	""	""	Q4-2021
2461	2461	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main St, Aglish;Bye Lane, Kilmacthomas	3	*N/A	""	""	""	""	Q1-2021	""
2462	2462	SHIP CONSTRUCTION SINGLE STAGE	Waterford	Apt 1 and Apt 2 Rivercourt, Grattan Quay, Waterford City	2	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
2463	2463	SHIP CONSTRUCTION RAPID	Waterford	Ballygunner, Waterford City	49	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2464	2464	SHIP CONSTRUCTION RAPID	Waterford	Ballynaneashagh, Waterford City	22	*N/A	""	Stage 2 approved Q2-2020, full design/tender being prepared.	""	""	""	""
2465	2465	SHIP CONSTRUCTION	Waterford	An Garran, Crobally Upper, Tramore	50	*N/A	""	""	Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.	""	""	""
2466	2466	SHIP CONSTRUCTION	Waterford	Alms Houses, Tallow	4	*N/A	""	""	""	""	""	Q4-2018
2467	2467	SHIP CONSTRUCTION	Waterford	Ardmore Park/Priory Lawn (Saviours Green), Ballybeg	5	*N/A	""	""	""	""	""	Q3-2020
2468	2468	SHIP CONSTRUCTION	Waterford	Ballinroad, Dungarvan	21	*N/A	""	""	""	""	""	Q2-2020
2469	2469	SHIP CONSTRUCTION	Waterford	Barrack Street, Cappoquin	4	*N/A	""	""	""	""	""	Q4-2017
2470	2470	SHIP CONSTRUCTION	Waterford	Coolfin Woods, Portlaw	12	*N/A	""	""	""	""	""	Q2-2019
2471	2471	SHIP CONSTRUCTION	Waterford	Larchville, Waterford City	5	*N/A	""	""	""	""	""	Q2-2021
2472	2472	SHIP CONSTRUCTION	Waterford	Patrick Street, Tramore	2	*N/A	""	""	""	""	""	Q3-2018
2473	2473	SHIP CONSTRUCTION	Waterford	Doyles Street, Waterford City	4	*N/A	""	""	""	""	""	Q4-2021
2474	2474	SHIP CONSTRUCTION	Waterford	Old Cinema Site, Dungarvan	15	*N/A	""	""	""	""	""	Q4-2016
2475	2475	SHIP CONSTRUCTION	Waterford	The Glen, Bridge St, Waterford	17	*N/A	""	""	""	""	Q3-2021	""
2476	2476	SHIP CONSTRUCTION	Waterford	Clarendon Court, Penrose Lane, Waterford	24	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.	""	""	""	""	""
2477	2477	SHIP CONSTRUCTION	Waterford	Summerland Square, Waterford	12	*N/A	""	""	Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.	""	""	""
2478	2478	SHIP CONSTRUCTION	Waterford	Bath St, Waterford City	4	*N/A	""	""	""	""	""	Q4-2019
2479	2479	SHIP CONSTRUCTION	Waterford	Graigueshoneen, Kilmacthomas	16	*N/A	""	""	""	""	Q4-2020	""
2480	2480	SHIP CONSTRUCTION	Waterford	Mount Esker, Ballytruckle Road, Waterford City	14	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2481	2481	SHIP CONSTRUCTION	Waterford	Newgate Street, Waterford City	36	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.	""	""	""	""	""
2482	2482	SHIP CONSTRUCTION	Waterford	Fountain Street, Ferrybank, Waterford	14	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
2483	2483	SHIP CONSTRUCTION	Waterford	Meeting House Lane, Waterford City	6	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
2484	2484	SHIP CONSTRUCTION	Waterford	50-53 Ballytruckle Road, Waterford	11	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2485	2485	CAS CONSTRUCTION	Waterford	Convent Hill, Tramore	10	Society of Saint Vincent de Paul	""	""	""	""	""	Q1-2017
2486	2486	CAS CONSTRUCTION	Waterford	Wadding Manor, Ferrybank	10	Respond	""	""	""	""	""	Q2-2021
2487	2487	CAS CONSTRUCTION	Waterford	The Paddocks, Williamstown Rd. Waterford 	9	Anvers Housing Association Ltd	""	""	""	""	""	Q4-2020
2488	2488	CALF Turnkey	Waterford	Kilbarry, Waterford (Phase 1)	69	Respond	""	""	""	""	""	Q3-2020
2489	2489	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 1)	26	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2021
2490	2490	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 2)	31	Circle Voluntary Housing Association Ltd	""	""	""	""	Q3-2019	""
2491	2491	CALF Construction	Waterford	St Johns College, Waterford (Phase 1)	36	Respond	""	""	""	""	""	Q1-2016
2492	2492	CALF Turnkey	Waterford	The Walk, Fairfield Park, Kilcohan, Waterford (Phase 1)	40	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q4-2019
2493	2493	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 1)	24	*N/A	""	""	""	""	""	Q2-2021
2494	2494	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 2)	34	*N/A	""	""	""	""	""	Q3-2021
2495	2495	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2496	2496	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2497	2497	SHIP DIALOG	Westmeath	Lissywollen, Athlone	38	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2498	2498	SHIP DIALOG	Westmeath	Lissywollen, Athlone	22	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2499	2499	SHIP CONSTRUCTION TURNKEY	Westmeath	Belvedere Hills, Mullingar	21	*N/A	""	""	""	""	""	Q4-2017
2500	2500	SHIP CONSTRUCTION TURNKEY	Westmeath	Cloon Lara, Mullingar	12	*N/A	""	""	""	""	""	Q2-2019
2501	2501	SHIP CONSTRUCTION TURNKEY	Westmeath	Abbeybrook, Kilbeggan	7	*N/A	""	""	""	""	""	Q1-2019
2502	2502	SHIP CONSTRUCTION TURNKEY	Westmeath	Coill Rua, Mullingar	6	*N/A	""	""	""	""	""	Q4-2019
2503	2503	SHIP CONSTRUCTION TURNKEY	Westmeath	Rathgarve Green, Castlepollard	3	*N/A	""	""	""	""	""	Q1-2020
2504	2504	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friars Street, Mullingar	4	*N/A	""	""	""	""	Q3-2020	""
2505	2505	SHIP CONSTRUCTION TURNKEY	Westmeath	Rathgarve Green, Castlepollard	5	*N/A	""	""	""	""	""	Q4-2020
2506	2506	SHIP CONSTRUCTION TURNKEY	Westmeath	Oakcrest, Ballinderry, Mullingar	8	*N/A	""	""	""	""	Q2-2021	""
2507	2507	SHIP CONSTRUCTION TURNKEY	Westmeath	St. Marys Place, Athlone	9	*N/A	""	""	""	""	Q2-2021	""
2508	2508	SHIP CONSTRUCTION TURNKEY	Westmeath	Rathgarve Green, Castlepollard	1	*N/A	""	""	""	""	""	Q2-2021
2509	2509	SHIP CONSTRUCTION TURNKEY	Westmeath	Bellaugh, Athlone	17	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2510	2510	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	7	*N/A	""	""	""	""	Q2-2021	""
2511	2511	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	10	*N/A	""	""	""	""	Q2-2021	""
2512	2512	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	11	*N/A	""	""	""	""	Q2-2021	""
2513	2513	SHIP CONSTRUCTION TURNKEY	Westmeath	Athboy Rd, Delvin	6	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2514	2514	SHIP CONSTRUCTION TURNKEY	Westmeath	Kileenboylegan, Moate	6	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2515	2515	SHIP CONSTRUCTION RAPID	Westmeath	O'Growney Green, Mullingar	22	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2516	2516	SHIP CONSTRUCTION RAPID	Westmeath	Dalton Park, Mullingar	17	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2517	2517	SHIP CONSTRUCTION RAPID	Westmeath	Water Street, Castlepollard	8	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2518	2518	SHIP CONSTRUCTION RAPID	Westmeath	Ennell Court, Mullingar (Phase 1)	15	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2519	2519	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	8	*N/A	""	""	""	""	""	Q2-2021
2520	2520	SHIP CONSTRUCTION	Westmeath	St. Laurence's Terrace, Mullingar	9	*N/A	""	""	""	""	""	Q4-2018
2521	2521	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	1	*N/A	""	""	""	""	""	Q1-2018
2522	2522	SHIP CONSTRUCTION	Westmeath	Arcadia, Athlone	21	*N/A	""	""	""	""	""	Q2-2020
2523	2523	SHIP CONSTRUCTION	Westmeath	Ennell Court (Phase 2)	3	*N/A	""	""	""	""	""	Q2-2016
2524	2524	SHIP CONSTRUCTION	Westmeath	Grange Crescent, Mullingar	2	*N/A	""	""	""	""	""	Q1-2016
2525	2525	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	31	*N/A	""	""	""	""	Q2-2021	""
2526	2526	SHIP CONSTRUCTION	Westmeath	Quinlan Park, Athlone	10	*N/A	""	""	""	""	Q4-2021	""
2527	2527	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A	""	""	""	""	""	Q2-2021
2528	2528	SHIP CONSTRUCTION	Westmeath	Arcadia, Athlone (Phase 2)	24	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
2529	2529	SHIP CONSTRUCTION	Westmeath	Canal Avenue, Mullingar	32	*N/A	""	Stage 2 approved Q4-2020, full design/tender being prepared.	""	""	""	""
2530	2530	SHIP CONSTRUCTION	Westmeath	Arcadia, Athlone	12	*N/A	""	""	""	""	""	Q3-2020
2531	2531	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	4	*N/A	""	""	""	""	""	Q3-2021
2532	2532	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A	""	""	""	""	""	Q4-2021
2533	2533	SHIP CONSTRUCTION	Westmeath	Kilmacaugh Rd, Athlone	1	N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2534	2534	SHIP CONSTRUCTION	Westmeath	Cornamaddy, Athlone	108	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2535	2535	SHIP CONSTRUCTION	Westmeath	Water Street, Castlepollard 	1	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2536	2536	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	10	Túath Housing Association Ltd	""	""	""	""	""	Q1-2021
2537	2537	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	17	Túath Housing Association Ltd	""	""	""	""	Q4-2019	""
2538	2538	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	9	Túath Housing Association Ltd	""	""	""	""	Q4-2019	""
2539	2539	CAS CONSTRUCTION	Westmeath	Farran, Mullingar	4	Túath Housing Association Ltd	""	""	""	""	""	Q3-2021
2540	2540	CALF Turnkey	Westmeath	Ashe Road, Mullingar, Co. Westmeath (Phase 1)*	18	Clúid Housing	""	""	""	Q2-2021	""	""
2541	2541	CALF Turnkey	Westmeath	Athlone Road, Moate, Co. Westmeath (Phase 1)*	14	Oaklee Housing	""	""	""	""	""	Q2-2021
2542	2542	CALF Turnkey	Westmeath	Bower Hill, Lower Road, Athlone, Co. Westmeath (Phase 1)*	15	Clúid Housing	""	""	""	Q3-2021	""	""
2543	2543	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 1)*	37	Respond	""	""	""	""	Q4-2021	""
2544	2544	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 2)*	62	Respond	""	""	""	""	Q4-2021	""
2545	2545	CALF Turnkey	Westmeath	Cluain Mullen, Castlepollard, Co. Westmeath (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q4-2020
2546	2546	CALF Turnkey	Westmeath	Cluain Mullen, Castlepollard, Westmeath (Phase 1)	2	Tuath Housing Association	""	""	""	""	""	Q2-2017
2547	2547	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 1)*	13	Clúid Housing	""	""	""	""	""	Q4-2020
2548	2548	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 2)*	23	Clúid Housing	""	""	""	""	""	Q1-2021
2549	2549	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 3)	8	Clúid Housing	""	""	""	""	""	Q2-2021
2550	2550	CALF Construction	Westmeath	Farran, Mullingar, Co. Westmeath (Phase 1)	10	Tuath Housing Association	""	""	""	""	""	Q3-2021
2551	2551	CALF Turnkey	Westmeath	Garran Geal, Kinnegad, Westmeath (Phase 1)*	24	Tuath Housing Association	""	""	""	""	Q4-2020	""
2552	2552	CALF Turnkey	Westmeath	Ghairdin Beag, Main Street, Rathwire, Killucan, Co. Westmeath (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q4-2020
2553	2553	CALF Turnkey	Westmeath	Rahanine, Rochfortbridge, Co Westmeath (Phase 1)*	12	Tuath Housing Association	""	""	""	""	""	Q2-2021
2554	2554	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q1-2021
2555	2555	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 2)	4	Tuath Housing Association	""	""	""	""	Q3-2019	""
2556	2556	CALF Turnkey	Westmeath	Springfield Cottages, Mullingar, Co. Westmeath (Phase 1)*	13	Clúid Housing	""	""	""	Q2-2021	""	""
2557	2557	CALF Turnkey	Westmeath	The Orchard, Athlone, Co. Westmeath (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q4-2019
2558	2558	CALF Turnkey	Westmeath	The Orchard, Athlone, Co. Westmeath (Phase 2)*	14	Tuath Housing Association	""	""	""	""	""	Q2-2020
2559	2559	CALF Turnkey	Westmeath	The Orchard, Athlone, Co. Westmeath (Phase 3)	10	Tuath Housing Association	""	""	""	""	""	Q2-2020
2560	2560	SHIP CONSTRUCTION TURNKEY	Wexford	Madeira Oaks, Wexford	8	*N/A	""	""	""	""	""	Q3-2017
2561	2561	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan Road, Gorey	8	*N/A	""	""	""	""	""	Q1-2018
2562	2562	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	11	*N/A	""	""	""	""	""	Q4-2018
2563	2563	SHIP CONSTRUCTION TURNKEY	Wexford	Rath an Duin, Castlebridge	3	*N/A	""	""	""	""	""	Q3-2018
2564	2564	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan Road, Gorey	2	*N/A	""	""	""	""	""	Q2-2019
2565	2565	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	10	*N/A	""	""	""	""	""	Q1-2019
2566	2566	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan Road, Gorey	10	*N/A	""	""	""	""	""	Q4-2018
2567	2567	SHIP CONSTRUCTION TURNKEY	Wexford	Glen Aoibhinn, Ardamine, Gorey	5	*N/A	""	""	""	""	""	Q4-2018
2568	2568	SHIP CONSTRUCTION TURNKEY	Wexford	Glen Aoibhinn, Ardamine, Gorey	2	*N/A	""	""	""	""	""	Q1-2019
2569	2569	SHIP CONSTRUCTION TURNKEY	Wexford	Whitewater Estuary, Ballyhack	3	*N/A	""	""	""	""	""	Q3-2020
2570	2570	SHIP CONSTRUCTION TURNKEY	Wexford	Riverchapel Lane, Gorey	4	*N/A	""	""	""	""	""	Q4-2019
2571	2571	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	4	*N/A	""	""	""	""	""	Q2-2019
2572	2572	SHIP CONSTRUCTION TURNKEY	Wexford	Glen Aoibhinn, Ardamine, Gorey	3	*N/A	""	""	""	""	""	Q4-2019
2573	2573	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	10	*N/A	""	""	""	""	""	Q3-2019
2574	2574	SHIP CONSTRUCTION TURNKEY	Wexford	St. Martin's Road, Rosslare Harbour	4	*N/A	""	""	""	""	""	Q4-2019
2575	2575	SHIP CONSTRUCTION TURNKEY	Wexford	Clonattin Upper, Gorey	8	*N/A	""	""	""	""	""	Q4-2020
2576	2576	SHIP CONSTRUCTION TURNKEY	Wexford	Airhill, Belvedere Rd, Wexford	7	*N/A	""	""	""	""	""	Q3-2021
2577	2577	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan Road, Gorey	2	*N/A	""	""	""	""	""	Q4-2019
2578	2578	SHIP CONSTRUCTION TURNKEY	Wexford	Michael Street, New Ross 	3	*N/A	""	""	""	""	""	Q2-2021
2579	2579	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	14	*N/A	""	""	""	""	""	Q4-2020
2580	2580	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan Road, Gorey	1	*N/A	""	""	""	""	""	Q3-2019
2581	2581	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	4	*N/A	""	""	""	""	Q4-2019	""
2582	2582	SHIP CONSTRUCTION TURNKEY	Wexford	No.'s 64 & 74 Chapelwood, Kilmuckridge	2	*N/A	""	""	""	""	""	Q1-2020
2583	2583	SHIP CONSTRUCTION TURNKEY	Wexford	5 The Break Ayelsbridge, Riverchapel	1	*N/A	""	""	""	""	""	Q1-2020
2584	2584	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	10	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
2585	2585	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	1	*N/A	""	""	""	""	""	Q1-2020
2586	2586	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Gorey - Phase 2	4	*N/A	""	""	""	""	""	Q4-2021
2587	2587	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	5	*N/A	""	""	""	""	""	Q2-2021
2588	2588	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	5	*N/A	""	""	""	""	""	Q4-2021
2589	2589	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	6	*N/A	""	""	""	""	""	Q4-2021
2590	2590	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A	""	""	""	""	""	Q2-2021
2591	2591	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross, Co. Wexford	22	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2592	2592	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	29	*N/A	""	""	""	Stage 4 approved Q2-2020, the scheme is fully approved.	""	""
2593	2593	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	12	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
2594	2594	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor	3	*N/A	""	""	""	""	Q2-2021	""
2595	2595	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor	3	*N/A	""	""	""	""	Q2-2021	""
2596	2596	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor	4	*N/A	""	""	""	""	Q2-2021	""
2597	2597	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor	3	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2598	2598	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A	""	""	""	""	""	Q2-2021
2599	2599	SHIP CONSTRUCTION TURNKEY	Wexford	Clonard Little, Wexford 	9	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2600	2600	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross, Co. Wexford	21	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2601	2601	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	9	*N/A	""	""	""	Stage 4 approved Q3-2020, the scheme is fully approved.	""	""
2602	2602	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	8	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2603	2603	SHIP CONSTRUCTION	Wexford	SN Castlemoyle, New Ross	1	*N/A	""	""	""	""	""	Q4-2019
2604	2604	SHIP CONSTRUCTION	Wexford	Cloghulatagh, Taghmon	18	*N/A	""	""	""	""	""	Q4-2020
2605	2605	SHIP CONSTRUCTION	Wexford	Coolcotts, Clonard	7	*N/A	""	""	""	""	""	Q4-2019
2606	2606	SHIP CONSTRUCTION	Wexford	Creagh, Gorey	10	*N/A	""	""	""	""	""	Q1-2019
2607	2607	SHIP CONSTRUCTION	Wexford	Danescastle	10	*N/A	""	""	""	""	""	Q1-2019
2608	2608	SHIP CONSTRUCTION	Wexford	Slippery Green, Wexford	10	*N/A	""	""	""	""	""	Q3-2019
2609	2609	SHIP CONSTRUCTION	Wexford	Whiterock Hill, Wexford	22	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2610	2610	SHIP CONSTRUCTION	Wexford	Cois Mara	2	*N/A	""	""	""	""	""	Q3-2018
2611	2611	SHIP CONSTRUCTION	Wexford	Killeens, Wexford	40	*N/A	""	""	""	""	Q2-2020	""
2612	2612	SHIP CONSTRUCTION	Wexford	Oilgate, Enniscorthy	2	*N/A	""	""	""	""	""	Q2-2018
2613	2613	SHIP CONSTRUCTION	Wexford	Cherryorchard, Enniscorthy	8	*N/A	""	""	""	""	""	Q3-2018
2614	2614	SHIP CONSTRUCTION	Wexford	Ross Road, Enniscorthy	1	*N/A	""	""	""	""	""	Q4-2021
2615	2615	SHIP CONSTRUCTION	Wexford	Baile Eoghain, Gorey	5	*N/A	""	""	""	""	""	Q4-2018
2616	2616	SHIP CONSTRUCTION	Wexford	Baile an Trá, Riverchapel (Courtown Ardamine)	10	*N/A	""	""	""	""	""	Q2-2016
2617	2617	SHIP CONSTRUCTION	Wexford	Shanna Court, Coolcotts	8	*N/A	""	""	""	""	""	Q1-2016
2618	2618	SHIP CONSTRUCTION	Wexford	Francis Street, Wexford	1	*N/A	""	""	""	""	""	Q1-2017
2619	2619	SHIP CONSTRUCTION	Wexford	Commodore Barry	1	*N/A	""	""	""	""	""	Q2-2016
2620	2620	SHIP CONSTRUCTION	Wexford	Glentire, The Ballagh, Enniscorthy	6	*N/A	""	""	""	""	Q2-2019	""
2621	2621	SHIP CONSTRUCTION	Wexford	Rosetown, Rosslare, Co Wexford, Phase 1	23	*N/A	""	""	""	""	Q2-2019	""
2622	2622	SHIP CONSTRUCTION	Wexford	Carley's Bridge, Enniscorthy	17	*N/A	""	""	""	""	Q2-2019	""
2623	2623	SHIP CONSTRUCTION	Wexford	Creagh, Gorey	12	*N/A	Stage 1 approved Q2-2018, outline design and costs being prepared.	""	""	""	""	""
2624	2624	SHIP CONSTRUCTION	Wexford	Baile Eoghain, Gorey	4	*N/A	""	""	""	""	""	Q4-2018
2625	2625	SHIP CONSTRUCTION	Wexford	Wexford Street, Gorey	30	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2626	2626	SHIP CONSTRUCTION	Wexford	Bullawn, Irishtown, New Ross	3	*N/A	""	""	""	""	Q3-2021	""
2627	2627	SHIP CONSTRUCTION	Wexford	Ballyhine, Barntown	7	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2628	2628	SHIP CONSTRUCTION	Wexford	Whiterock Hill, Wexford	22	*N/A	""	""	Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.	""	""	""
2629	2629	SHIP CONSTRUCTION	Wexford	Doire Moling estate at Monamolin, Gorey, Co. Wexford	5	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
2630	2630	SHIP CONSTRUCTION	Wexford	20 Francis Street, Wexford	2	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2631	2631	SHIP CONSTRUCTION	Wexford	Ballygillane Big, Rosslare Harbour, Co. Wexford	5	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2632	2632	SHIP CONSTRUCTION	Wexford	Grogan’s Road, Wexford Town 	3	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2633	2633	CAS CONSTRUCTION TURNKEY	Wexford	Clonattin, Gorey	6	Túath Housing Association Ltd	""	""	""	""	""	Q2-2021
2634	2634	CAS CONSTRUCTION	Wexford	Rathangan	7	Rathangan Senior Citizens Housing Association Ltd	""	""	""	""	""	Q3-2017
2635	2635	CAS CONSTRUCTION	Wexford	Wexford Women's Refuge, Maudlintown	12	*N/A	""	Stage 2 approved Q3-2020, full design/tender being prepared.	""	""	""	""
2636	2636	CALF Turnkey	Wexford	24 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)	8	Tuath Housing Association	""	""	""	""	""	Q3-2020
2637	2637	CALF Turnkey	Wexford	24 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 2)	16	Tuath Housing Association	""	""	""	""	""	Q4-2020
2638	2638	CALF Turnkey	Wexford	67 units, Coolcotts, Wexford (Phase 1)*	67	Clúid Housing	""	""	""	""	Q3-2020	""
2639	2639	CALF Turnkey	Wexford	9 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q2-2021
2640	2640	CALF Turnkey	Wexford	 Ard Uisce, Wexford Town (Phase 1)	5	Tuath Housing Association	""	""	""	""	""	Q4-2017
2641	2641	CALF Turnkey	Wexford	 Ard Uisce, Whiterock, Wexford  (Phase 1)	1	Tuath Housing Association	""	""	""	""	""	Q1-2018
2642	2642	CALF Turnkey	Wexford	Ard Uisce, Whiterock, Wexford (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q1-2018
2643	2643	CALF Turnkey	Wexford	Ard Uisce, Whiterock, Wexford (Phase 1)*	6	Tuath Housing Association	""	""	""	""	""	Q1-2017
2644	2644	CALF Turnkey	Wexford	Ballyboggan, Castlebridge, Co Wexford (Phase 1)	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
2645	2645	CALF Turnkey	Wexford	Clonard, Wexford (Phase 1)*	10	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
2646	2646	CALF Turnkey	Wexford	Fearach Cnoic, Greenville, Enniscorthy, Co. Wexford (Phase 1)*	10	Clanmil Housing Association Ireland	""	""	""	""	Q3-2018	""
2647	2647	CALF Turnkey	Wexford	Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 1)	34	Oaklee Housing	""	""	""	""	""	Q4-2018
2648	2648	CALF Turnkey	Wexford	Fearach Cnoic, Greenville, The Moyne, Enniscorthy (Phase 2)	6	Oaklee Housing	""	""	""	""	""	Q2-2019
2649	2649	CALF Turnkey	Wexford	Forgelands, Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)*	18	Tuath Housing Association	""	""	""	""	""	Q3-2021
2650	2650	CALF Turnkey	Wexford	Fort Road, Ramsfort Park, Gorey, Co. Wexford (Phase 1)*	11	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2020
2651	2651	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey (Phase 1)	9	Tuath Housing Association	""	""	""	""	""	Q4-2019
2652	2652	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey (Phase 2)	9	Tuath Housing Association	""	""	""	""	""	Q1-2020
2653	2653	CALF Turnkey	Wexford	Greenville, Enniscorthy, Co. Wexford (Phase 1)*	6	Oaklee Housing	""	""	""	""	""	Q2-2019
2654	2654	CALF Turnkey	Wexford	Hunters Green, Gorey (Phase 1)	7	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2016
2655	2655	CALF Turnkey	Wexford	Hunters Green, Gorey (Phase 2)	11	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2016
2656	2656	CALF Turnkey	Wexford	Hunters Green, Gorey (Phase 3)	11	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q1-2017
2657	2657	CALF Turnkey	Wexford	Hunters Green, Gorey (Phase 4)	9	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2017
2658	2658	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 1)	14	Tuath Housing Association	""	""	""	""	""	Q4-2020
2659	2659	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 2)	14	Tuath Housing Association	""	""	""	""	""	Q4-2020
2660	2660	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 3)	16	Tuath Housing Association	""	""	""	""	""	Q1-2021
2661	2661	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 4)*	27	Tuath Housing Association	""	""	""	""	""	Q2-2021
2662	2662	CALF Turnkey	Wexford	Meadowfields Enniscorthy, Co. Wexford (Phase 1)	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2016
2663	2663	CALF Turnkey	Wexford	Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 1)*	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q2-2019
2664	2664	CALF Turnkey	Wexford	Meadowfields Phase 3, Enniscorthy, Co. Wexford (Phase 2)*	14	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
2665	2665	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 1)	12	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
2666	2666	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 2)*	13	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
2667	2667	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q4-2020
2668	2668	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 2)*	14	Tuath Housing Association	""	""	""	""	""	Q4-2020
2669	2669	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 3)*	8	Tuath Housing Association	""	""	""	""	""	Q1-2021
2670	2670	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 4)*	8	Tuath Housing Association	""	""	""	""	""	Q2-2021
2671	2671	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 1)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
2672	2672	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 2)	19	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2021
2673	2673	CALF Turnkey	Wexford	Páirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 1)*	16	Clúid Housing	""	""	""	""	""	Q3-2021
2674	2674	CALF Turnkey	Wexford	Páirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 2)	14	Clúid Housing	""	""	""	""	""	Q3-2021
2675	2675	CALF Turnkey	Wexford	Páirc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 3)*	22	Clúid Housing	""	""	""	""	""	Q4-2021
2676	2676	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 1)	24	Tuath Housing Association	""	""	""	""	Q2-2021	""
2677	2677	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 2)	20	Tuath Housing Association	""	""	""	""	Q2-2021	""
2678	2678	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 3)*	24	Tuath Housing Association	""	""	""	""	Q2-2021	""
2679	2679	CALF Turnkey	Wexford	Tobar Mhuire, Creagh, Gorey, Wexford (Phase 1)*	17	Clúid Housing	""	""	""	""	Q4-2021	""
2680	2680	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Wicklow	Convent Lands (Phase 1)	23	*N/A	""	""	""	""	""	Q2-2020
2681	2681	SHIP CONSTRUCTION TURNKEY	Wicklow	Mill Court, Tinahely 	2	*N/A	""	""	""	""	""	Q2-2018
2682	2682	SHIP CONSTRUCTION TURNKEY	Wicklow	No. 7 Mill Court, Tinahely 	1	*N/A	""	""	""	""	""	Q4-2018
2683	2683	SHIP CONSTRUCTION TURNKEY	Wicklow	Heatherside, Vale Road, Arklow	10	*N/A	""	""	""	""	""	Q2-2019
2684	2684	SHIP CONSTRUCTION TURNKEY	Wicklow	Fernhill, Arklow	1	*N/A	""	""	""	""	""	Q3-2018
2685	2685	SHIP CONSTRUCTION TURNKEY	Wicklow	Mill Court, Tinahely 	1	*N/A	""	""	""	""	""	Q1-2019
2686	2686	SHIP CONSTRUCTION TURNKEY	Wicklow	Woodview Cottages, Rathnew	2	*N/A	""	""	""	""	""	Q4-2019
2687	2687	SHIP CONSTRUCTION TURNKEY	Wicklow	Bollarney Woods, Wicklow Town	10	*N/A	""	""	""	""	""	Q3-2019
2688	2688	SHIP CONSTRUCTION TURNKEY	Wicklow	Mill Court, Tinahely 	1	*N/A	""	""	""	""	""	Q2-2019
2689	2689	SHIP CONSTRUCTION TURNKEY	Wicklow	Heatherside, Vale Road, Arklow	15	*N/A	""	""	""	""	""	Q3-2019
2690	2690	SHIP CONSTRUCTION TURNKEY	Wicklow	Heatherside, Vale Road, Arklow	4	*N/A	""	""	""	""	""	Q4-2019
2691	2691	SHIP CONSTRUCTION TURNKEY	Wicklow	Heatherside, Vale Road, Arklow	2	*N/A	""	""	""	""	""	Q4-2019
2692	2692	SHIP CONSTRUCTION TURNKEY	Wicklow	Bollarney Woods, Wicklow Town	14	*N/A	""	""	""	""	""	Q4-2019
2693	2693	SHIP CONSTRUCTION TURNKEY	Wicklow	Bollarney Woods, Wicklow Town	6	*N/A	""	""	""	""	""	Q2-2020
2694	2694	SHIP CONSTRUCTION TURNKEY	Wicklow	Heatherside, Vale Road, Arklow	9	*N/A	""	""	""	""	""	Q4-2019
2695	2695	SHIP CONSTRUCTION TURNKEY	Wicklow	Kirvin Hill, Broomhall, Rathnew	2	*N/A	""	""	""	""	""	Q2-2019
2696	2696	SHIP CONSTRUCTION TURNKEY	Wicklow	Weaver Square, Baltinglass, Co. Wicklow	2	*N/A	""	""	""	Stage 4 approved Q1-2020, the scheme is fully approved.	""	""
2697	2697	SHIP CONSTRUCTION TURNKEY	Wicklow	Carraig Beag, WicklowTown	5	*N/A	""	""	""	""	""	Q3-2020
2698	2698	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	2	*N/A	""	""	""	""	""	Q4-2020
2699	2699	SHIP CONSTRUCTION TURNKEY	Wicklow	The Birches, Ballinaclash	2	*N/A	""	""	""	""	""	Q2-2021
2700	2700	SHIP CONSTRUCTION TURNKEY	Wicklow	Bollarney Woods Phase 2	2	*N/A	""	""	""	""	""	Q2-2020
2701	2701	SHIP CONSTRUCTION TURNKEY	Wicklow	Bollarney Woods Phase 2	1	*N/A	""	""	""	""	""	Q4-2020
2702	2702	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	2	*N/A	""	""	""	""	""	Q1-2021
2703	2703	SHIP CONSTRUCTION TURNKEY	Wicklow	Vartry Heights, Roundwood, Co. Wicklow	3	*N/A	""	""	""	Stage 4 approved Q1-2021, the scheme is fully approved.	""	""
2704	2704	SHIP CONSTRUCTION TURNKEY	Wicklow	Avonmore View, Rathdrum	13	*N/A	""	""	""	Stage 4 approved Q2-2021, the scheme is fully approved.	""	""
2705	2705	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	1	*N/A	""	""	""	""	""	Q2-2021
2706	2706	SHIP CONSTRUCTION TURNKEY	Wicklow	95 Waverley Drive, Broomhall, Rathnew	1	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2707	2707	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	2	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2708	2708	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	3	N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2709	2709	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	4	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2710	2710	SHIP CONSTRUCTION SINGLE STAGE	Wicklow	Church Lane, Newcastle	1	*N/A	""	""	""	Stage 4 approved Q3-2021, the scheme is fully approved.	""	""
2711	2711	SHIP CONSTRUCTION RAPID	Wicklow	Sli na Slainte, Whitehall, Baltinglass	7	*N/A	""	""	""	""	""	Q4-2019
2712	2712	SHIP CONSTRUCTION RAPID	Wicklow	Merrymeeting View, Rathnew	46	*N/A	""	""	""	""	""	Q2-2021
2713	2713	SHIP CONSTRUCTION RAPID	Wicklow	Coolattin Oaks, Carnew (Phase 4)	22	*N/A	""	""	""	""	""	Q4-2020
2714	2714	SHIP CONSTRUCTION RAPID	Wicklow	Shillelagh Phase 4	20	*N/A	""	Stage 2 approved Q2-2021, full design/tender being prepared.	""	""	""	""
2715	2715	SHIP CONSTRUCTION RAPID	Wicklow	Ashtown Lane, Wicklow Town	40	*N/A	""	""	""	""	Q3-2020	""
2716	2716	SHIP CONSTRUCTION RAPID	Wicklow	Ard na Greine, West Ward, Bray	31	*N/A	""	""	""	""	Q2-2020	""
2717	2717	SHIP CONSTRUCTION RAPID	Wicklow	Avondale Heights, Rathdrum	20	*N/A	""	""	""	""	Q3-2021	""
2718	2718	SHIP CONSTRUCTION RAPID	Wicklow	Sheehan Court, Back Street, Arklow	7	*N/A	""	""	""	""	Q2-2021	""
2719	2719	SHIP CONSTRUCTION RAPID	Wicklow	Mountainview, Moneycarroll, Newtownmountkennedy, Co. Wicklow	22	*N/A	""	""	""	""	Q3-2020	""
2720	2720	SHIP CONSTRUCTION RAPID	Wicklow	Sli na Slainte, Whitehall, Baltinglass	27	*N/A	""	""	""	""	""	Q1-2020
2721	2721	SHIP CONSTRUCTION RAPID	Wicklow	Three Trouts, Greystones	40	*N/A	Stage 1 approved Q4-2019, outline design and costs being prepared.	""	""	""	""	""
2722	2722	SHIP CONSTRUCTION RAPID	Wicklow	Greenhill Road, Wicklow Town	36	*N/A	""	""	""	""	Q2-2021	""
2723	2723	SHIP CONSTRUCTION RAPID	Wicklow	Cedar Court, Schools Road, Bray	14	*N/A	""	""	""	Stage 4 approved Q4-2021, the scheme is fully approved.	""	""
2724	2724	SHIP CONSTRUCTION RAPID	Wicklow	Coolattin Oaks, Carnew (Phase 4)	8	*N/A	""	""	""	""	""	Q1-2021
2725	2725	SHIP CONSTRUCTION RAPID	Wicklow	Rathnew, Merrymeeting, Co. Wicklow (Phase 2)	21	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2726	2726	SHIP CONSTRUCTION RAPID	Wicklow	Tinahely, Lugduff, Co Wicklow	20	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2727	2727	SHIP CONSTRUCTION RAPID	Wicklow	Carrigoona, Bray	20	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.	""	""	""	""	""
2728	2728	SHIP CONSTRUCTION RAPID	Wicklow	Lott Lane, Kilcoole	75	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.	""	""	""	""	""
2729	2729	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow (Phase 3)	10	*N/A	""	""	""	""	Q4-2019	""
2730	2730	SHIP CONSTRUCTION	Wicklow	10A & 10 B Castle Villas, Greystones	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2731	2731	SHIP CONSTRUCTION	Wicklow	Druids Brook, Kilcoole	2	*N/A	""	""	""	""	""	Q3-2019
2732	2732	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow	17	*N/A	""	""	""	""	""	Q3-2019
2733	2733	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow (Phase 2)	37	*N/A	""	""	""	""	""	Q4-2021
2734	2734	SHIP CONSTRUCTION	Wicklow	FCA Hall, Wicklow Town	8	*N/A	""	""	""	""	""	Q4-2020
2735	2735	SHIP CONSTRUCTION	Wicklow	Kilmantain Place, Bray	4	*N/A	""	""	""	""	""	Q4-2020
2736	2736	SHIP CONSTRUCTION	Wicklow	O'Byrne Road, Bray	1	*N/A	""	""	""	""	""	Q4-2018
2737	2737	SHIP CONSTRUCTION	Wicklow	St Mary's Rd., Arklow (Old Library Site)	7	*N/A	""	""	""	""	""	Q4-2018
2738	2738	SHIP CONSTRUCTION	Wicklow	Jameson Heights,  Kilmacanogue	20	*N/A	""	""	""	""	""	Q4-2020
2739	2739	SHIP CONSTRUCTION	Wicklow	Avondale Heights, Rathdrum	20	*N/A	""	""	""	""	""	Q4-2018
2740	2740	SHIP CONSTRUCTION	Wicklow	Kilbride Lane, Bray (Murphy's Lands)	23	*N/A	""	""	""	""	""	Q4-2020
2741	2741	SHIP CONSTRUCTION	Wicklow	16A Oak Drive, Blessington	1	*N/A	""	""	""	""	""	Q3-2019
2742	2742	SHIP CONSTRUCTION	Wicklow	Carrig Eden, 1 Marine Road, Greystones (Phases 1 and 2)	35	*N/A	""	""	""	""	""	Q4-2020
2743	2743	SHIP CONSTRUCTION	Wicklow	Farrankelly, Greystones (Phase 2)	24	*N/A	""	""	""	""	""	Q2-2020
2744	2744	SHIP CONSTRUCTION	Wicklow	Blackhills, Glenealy, Co. Wicklow	2	*N/A	""	""	""	""	Q4-2021	""
2745	2745	SHIP CONSTRUCTION	Wicklow	Age Friendly Apartments at Main St, Kilcoole, Greystones	4	*N/A	""	Stage 2 approved Q3-2021, full design/tender being prepared.	""	""	""	""
2746	2746	SHIP CONSTRUCTION	Wicklow	Mill Road, Killincarrig, Greystones	2	*N/A	""	Stage 2 approved Q1-2021, full design/tender being prepared.	""	""	""	""
2747	2747	SHIP CONSTRUCTION	Wicklow	Carraig Eden, Greysones (Phase 3)	14	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2748	2748	SHIP CONSTRUCTION	Wicklow	Kilbride Lane, Bray (Murphy's Lands)	19	*N/A	""	""	""	""	""	Q2-2021
2749	2749	SHIP CONSTRUCTION	Wicklow	Knockroe, Delgany, Co. Wicklow	2	*N/A	""	Stage 2 approved Q4-2021, full design/tender being prepared.	""	""	""	""
2750	2750	SHIP CONSTRUCTION	Wicklow	Ard Rua, Barndarraig, Arklow, Co. Wicklow	12	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.	""	""	""	""	""
2751	2751	CAS CONSTRUCTION TURNKEY	Wicklow	Rathcoran Square, Baltinglass	8	Peter McVerry Trust Ltd	""	""	""	""	""	Q2-2021
2752	2752	CAS CONSTRUCTION TURNKEY	Wicklow	Apt 1 & 2 Carrigbrae House, The Friary, Church Road, Bray	2	Ark Housing Association Limited	""	""	""	""	""	Q4-2020
2753	2753	CAS CONSTRUCTION SINGLE STAGE	Wicklow	Hollybrook Park, Bray, Co. Wicklow	4	St. John of God Housing Association Ltd	""	""	""	Stage 4 approved Q3-2019, the scheme is fully approved.	""	""
2754	2754	CALF Turnkey	Wicklow	Abbey St, Wicklow  (Phase 1)	6	Tuath Housing Association	""	""	""	""	""	Q4-2018
2755	2755	CALF Turnkey	Wicklow	Adelaide Apartments, St Laurence’s Terrace, Bray, Co. Wicklow (Phase 1)*	18	Respond	""	""	""	""	Q2-2021	""
2756	2756	CALF Turnkey	Wicklow	Avondale Grange, Ballygannon, Rathdrum, Co. Wicklow (Phase 1)*	36	Respond	""	""	""	""	Q2-2021	""
2757	2757	CALF Turnkey	Wicklow	Ballinahinch Woods, Ashford, Co. Wicklow (Phase 1)*	9	Clúid Housing	""	""	""	""	""	Q4-2019
2758	2758	CALF Turnkey	Wicklow	Ballinahinch Woods, Ashford, Co. Wicklow (Phase 2)*	8	Clúid Housing	""	""	""	""	""	Q3-2020
2759	2759	CALF Turnkey	Wicklow	Ballinahinch Woods, Ashford, Co. Wicklow (Phase 3)*	4	Clúid Housing	""	""	""	""	""	Q4-2020
2760	2760	CALF Turnkey	Wicklow	Fairgreen Manor, Dunlavin, Co. Wicklow (Phase 1)*	40	Circle Voluntary Housing Association Ltd	""	""	""	""	""	Q3-2021
2761	2761	CALF Turnkey	Wicklow	Glenheron, Greystones, Co Wicklow  (Phase 1)*	5	Tuath Housing Association	""	""	""	""	""	Q2-2018
2762	2762	CALF Turnkey	Wicklow	Glenheron, Greystones, Co. Wicklow (Phase 1)*	8	Tuath Housing Association	""	""	""	""	""	Q4-2018
2763	2763	CALF Turnkey	Wicklow	Glenheron, Greystones, Co. Wicklow (Phase 2)*	7	Tuath Housing Association	""	""	""	""	""	Q2-2019
2764	2764	CALF Turnkey	Wicklow	Glenheron, Greystones, Co. Wicklow (Phase 3)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2019
2765	2765	CALF Turnkey	Wicklow	Glenheron, Greystones, County Wicklow (Phase 1)	2	Tuath Housing Association	""	""	""	""	""	Q4-2020
2766	2766	CALF Turnkey	Wicklow	Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 1)*	15	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2018
2767	2767	CALF Turnkey	Wicklow	Hazelbrook Rise, Ballybeg, Rathnew, Co. Wicklow (Phase 2)	73	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q3-2019
2768	2768	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 1)	11	Tuath Housing Association	""	""	""	""	Q2-2021	""
2769	2769	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 2)	12	Tuath Housing Association	""	""	""	""	Q2-2021	""
2770	2770	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 3)	13	Tuath Housing Association	""	""	""	""	Q2-2021	""
2771	2771	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 4)	17	Tuath Housing Association	""	""	""	""	Q2-2021	""
2772	2772	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 5)*	35	Tuath Housing Association	""	""	""	""	Q2-2021	""
2773	2773	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)	11	Tuath Housing Association	""	""	""	""	""	Q3-2020
2774	2774	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)	15	Tuath Housing Association	""	""	""	""	""	Q4-2021
2775	2775	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)	14	Tuath Housing Association	""	""	""	""	""	Q3-2020
2776	2776	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)	13	Tuath Housing Association	""	""	""	""	Q4-2020	""
2777	2777	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 3)	13	Tuath Housing Association	""	""	""	""	""	Q4-2020
2778	2778	CALF Turnkey	Wicklow	Lower Main Street, Arklow, Co. Wicklow (Phase 1)	4	Clanmil Housing Association Ireland	""	""	""	""	Q2-2021	""
2779	2779	CALF Turnkey	Wicklow	Meadow Gate, Marlton Road, Wicklow Town (Phase 1)*	4	Tuath Housing Association	""	""	""	""	""	Q4-2020
2780	2780	CALF Turnkey	Wicklow	Oak Springs, Rathdrum, County Wicklow  (Phase 1)*	5	Tuath Housing Association	""	""	""	""	Q3-2020	""
2781	2781	CALF Turnkey	Wicklow	Phase 2, Hazelbrook, Rathnew, Co. Wicklow (Phase 1)	56	Co - Operative Housing Ireland Society Limited	""	""	""	""	""	Q4-2019
2782	2782	CALF Turnkey	Wicklow	Phase 2, Southern Cross, Bray, Co. Wicklow (Phase 1)	80	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2020	""
2783	2783	CALF Turnkey	Wicklow	Phase 3, Southern Cross, Bray, Co. Wicklow (Phase 1)*	80	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q4-2020	""
2784	2784	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 1)*	16	Respond	""	""	""	""	""	Q4-2020
2785	2785	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 2)*	24	Respond	""	""	""	""	""	Q2-2021
2786	2786	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 3)	16	Respond	""	""	""	""	""	Q3-2021
2787	2787	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 1)*"	30	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
2788	2788	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 2)*"	18	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q2-2021	""
2789	2789	CALF Turnkey	Wicklow	Ternlee, Coldross Lane, Kilcoole, Co. Wicklow (Phase 1)*	4	Clúid Housing	""	""	""	""	""	Q2-2019
2790	2790	CALF Turnkey	Wicklow	Ternlee, Coldross Lane, Kilcoole, Co. Wicklow (Phase 2)*	2	Clúid Housing	""	""	""	""	""	Q4-2019
2791	2791	CALF Turnkey	Wicklow	The Meadows, Ballynerrin, Wicklow Town (Phase 1)*	7	Tuath Housing Association	""	""	""	""	""	Q4-2018
2792	2792	CALF Turnkey	Wicklow	The Old Rectory, Blessington, Co. Wicklow (Phase 1)*	45	Co - Operative Housing Ireland Society Limited	""	""	""	""	Q3-2020	""
2793	2793	CALF Turnkey	Wicklow	Viewmount, Rathdrum, County Wicklow (Phase 1)	4	Tuath Housing Association	""	""	""	""	""	Q2-2020
2794	2794	CALF Turnkey	Wicklow	Woodpark, Rathdrum, Co. Wicklow (Phase 1)*	4	Tuath Housing Association	""	""	""	""	""	Q3-2019
2795	2795	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Wicklow	Convent Lands (Phase 2)	28	*N/A	""	""	""	""	""	Q3-2020
2796	2796	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Wicklow	Burgage More, Blessington, Co. Wicklow	106	*N/A	""	Q4-2021	""	""	""	""