﻿_id	no_	Funding Programme	LA	scheme_project_name	no__of_units	Approved Housing Body	Stage 1 Capital Appraisal	Stage 2 Pre Planning	Stage 3 Pre Tender design	stage_4_tender_report_or_final_turnkey_calf_approval	On Site	Completed
1	1	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	16	*N/A						Q4-2021
2	2	SHIP CONSTRUCTION TURNKEY	Carlow	Carrigbrook, Tullow Road, Carlow	13	*N/A						Q2-2021
3	3	SHIP CONSTRUCTION TURNKEY	Carlow	Granville Court, Granby Row,Carlow	4	*N/A						Q4-2021
4	4	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Brownbog, Hackettstown	1	*N/A						Q4-2022
5	5	SHIP CONSTRUCTION SINGLE STAGE	Carlow	St. Mary?s Court, Carlow	4	*N/A						Q4-2022
6	6	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Drumphea, Garryhill, Bagenalstown	1	*N/A					Q3-2022	
7	7	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Constable Hill, Hackettstown	1	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
8	8	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Old Leighlin Road, Carlow	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
9	9	SHIP CONSTRUCTION SINGLE STAGE	Carlow	Bahana, Glynn	5	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
10	10	SHIP CONSTRUCTION RENEWAL	Carlow	Barrack Street, Carlow	8	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.					
11	11	SHIP CONSTRUCTION RENEWAL	Carlow	Bog Lane, Borris	1	*N/A						Q2-2022
12	12	SHIP CONSTRUCTION RENEWAL	Carlow	2a Chapel Street, Graiguecullen, Carlow	1	*N/A					Q2-2022	
13	13	SHIP CONSTRUCTION RENEWAL	Carlow	24 Church Street, Graiguecullen, Carlow 	1	*N/A					Q2-2022	
14	14	SHIP CONSTRUCTION RENEWAL	Carlow	Breens Shop Units, Main Street, Borris	2	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
15	15	SHIP CONSTRUCTION RENEWAL	Carlow	22a Burrin Street, Co. Carlow	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
16	16	SHIP CONSTRUCTION RENEWAL	Carlow	11 Bourlum Wood, Green Road, Co. Carlow	1	*N/A						Q4-2022
17	17	SHIP CONSTRUCTION	Carlow	Pound Lane, Borris	9	*N/A						Q2-2021
18	18	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	10	*N/A						Q4-2022
19	19	SHIP CONSTRUCTION	Carlow	41-42 Dublin Street & Cox's Lane, Carlow 	12	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
20	20	SHIP CONSTRUCTION	Carlow	Fr. Flood Park, Rathvilly	10	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
21	21	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	6	*N/A						Q4-2022
22	22	SHIP CONSTRUCTION	Carlow	Gleann na Bearu, Bagenalstown	6	*N/A					Q3-2021	
23	23	CAS CONSTRUCTION	Carlow	Gleann na Bearu, Royal Oak Road, Bagenalstown	6	Respond					Q4-2020	
24	24	CAS CONSTRUCTION	Carlow	Homefield, Blackbog Road, Carlow	3	Carlow Voluntary Housing Association						Q2-2021
25	25	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 1)	22	Co - Operative Housing Ireland Society Limited						Q2-2021
26	26	CALF Turnkey	Carlow	Ballickmoyler, Graigcullen, Carlow (Phase 2)	35	Co - Operative Housing Ireland Society Limited						Q4-2021
27	27	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 1)*	17	Tuath Housing Association						Q3-2021
28	28	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 2)*	15	Tuath Housing Association						Q4-2021
29	29	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 3)*	21	Tuath Housing Association						Q1-2022
30	30	CALF Turnkey	Carlow	Cois Dara, Tullow Road, Chapelstown, Carlow  (Phase 4)	10	Tuath Housing Association						Q2-2022
31	31	CALF Turnkey	Carlow	Granite Court, Ballyknockan, Fenagh, Co Carlow (Phase 1)	8	Co - Operative Housing Ireland Society Limited						Q4-2022
32	32	CALF Turnkey	Carlow	Mill Race, Paupish Lane, Carlow, Co. Carlow (Phase 2)	6	Tuath Housing Association						Q2-2021
33	33	CALF Turnkey	Carlow	Rivercourt,  Carlow  (Phase 2)*	19	Co - Operative Housing Ireland Society Limited						Q1-2022
34	34	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 1)	7	Co - Operative Housing Ireland Society Limited					Q2-2021	
35	35	CALF Turnkey	Carlow	Sli Na Ri, Moneybeg, Bagenalstown, Co. Carlow (Phase 2)*	12	Co - Operative Housing Ireland Society Limited					Q2-2021	
36	36	CALF Turnkey	Carlow	The Millrace, Burrin, Co. Carlow (Phase 1)*	22	Co - Operative Housing Ireland Society Limited						Q4-2021
37	37	SHIP CONSTRUCTION TURNKEY	Cavan	Ashgrove, Derrylurgan, Ballyjamesduff	4	*N/A						Q4-2021
38	38	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	4	*N/A					Q4-2022	
39	39	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	8	*N/A				Stage 4 approved Q2-2020, the scheme is fully approved.		
40	40	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A				Stage 4 approved Q2-2020, the scheme is fully approved.		
41	41	SHIP CONSTRUCTION TURNKEY	Cavan	Woodlands, Killyfinla, Ballyjamesduff	10	*N/A				Stage 4 approved Q2-2020, the scheme is fully approved.		
42	42	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	7	*N/A						Q2-2022
43	43	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	11	*N/A						Q4-2022
44	44	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	11	*N/A					Q2-2021	
45	45	SHIP CONSTRUCTION TURNKEY	Cavan	Mullaghduff, Ballyconnell	11	*N/A					Q2-2021	
46	46	SHIP CONSTRUCTION TURNKEY	Cavan	Clankee Court, Lisdrumskea, Shercock	2	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
47	47	SHIP CONSTRUCTION TURNKEY	Cavan	Abhainn Dubh, Rosehill, Mullagh	4	*N/A						Q4-2021
48	48	SHIP CONSTRUCTION TURNKEY	Cavan	Kilnavara Heights, Cavan Town	2	*N/A						Q4-2022
49	49	SHIP CONSTRUCTION TURNKEY	Cavan	Errigal, Cootehill	6	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
50	50	SHIP CONSTRUCTION TURNKEY	Cavan	Taoibh Coille, Yew Park, Virginia	4	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
51	51	SHIP CONSTRUCTION	Cavan	Corstruce, Ballinagh	4	*N/A						Q2-2021
52	52	SHIP CONSTRUCTION	Cavan	Main Street, Mullagh	19	*N/A					Q4-2020	
53	53	SHIP CONSTRUCTION	Cavan	Elm Grove, Main St, Cavan Town	13	*N/A					Q1-2022	
54	54	SHIP CONSTRUCTION	Cavan	Cavan Road, Ballinagh	15	*N/A						Q4-2022
55	55	SHIP CONSTRUCTION	Cavan	Main St., Butlersbridge	6	*N/A						Q3-2022
56	56	SHIP CONSTRUCTION	Cavan	Cluain Dara, Kingscourt	3	*N/A						Q4-2021
57	57	SHIP CONSTRUCTION	Cavan	Fairymount Close, Kingscourt, Co. Cavan	3	*N/A					Q1-2022	
58	58	SHIP CONSTRUCTION	Cavan	St. Bridgets Terrace, Cavan Town (Infill)	20	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
59	59	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	12	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
60	60	SHIP CONSTRUCTION	Cavan	Duckin Stool, Main Street, Belturbet	3	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
61	61	SHIP CONSTRUCTION	Cavan	The Widow's Row, Widow's House Lane, Belturbet	9	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
62	62	SHIP CONSTRUCTION	Cavan	Derrylurgan, Ballyjamesduff	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
63	63	SHIP CONSTRUCTION	Cavan	8 Units @ Ashgrove, Derrylurgan, Ballyjamesduff	8	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
64	64	SHIP CONSTRUCTION	Cavan	Dunaree, Kingscourt Town Centre	3	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
65	65	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	18	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
66	66	SHIP CONSTRUCTION	Cavan	Peile na Teile, Beckscourt, Bailieborough	15	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
67	67	SHIP CONSTRUCTION	Cavan	Main St Lower, Kilnaleck, Co Cavan	2	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
68	68	SHIP CONSTRUCTION	Cavan	157 Barrack Road, Kilnaleck	4	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
69	69	SHIP CONSTRUCTION	Cavan	Main St., Kilnaleck	7	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
70	70	SHIP CONSTRUCTION	Cavan	Kilnavara Cavan Town	5	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
71	71	SHIP CONSTRUCTION	Cavan	Portaliffe, Killeshandra	8	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
72	72	CAS CONSTRUCTION TURNKEY	Cavan	Loreto Lodge, Loreto Wood, Cavan Town	7	North ? East Housing Association Ltd						Q4-2022
73	73	CAS CONSTRUCTION RENEWAL	Cavan	16 River St., Cavan	1	Society of Saint Vincent de Paul	Stage 1 approved Q2-2022, outline design and costs being prepared.					
74	74	CAS CONSTRUCTION	Cavan	St. Killian's Housing Association Ltd., Mullagh, Co. Cavan	4	St. Killian's Housing Association, Mullagh, Co. Cavan						Q4-2022
75	75	CAS CONSTRUCTION	Cavan	29 Bridge Street Cavan	6	Society of Saint Vincent de Paul	Stage 1 approved Q3-2022, outline design and costs being prepared.					
76	76	CALF Turnkey	Cavan	16 Units, Fairgreen Park, Mullagh, Co. Cavan (Phase 1)	16	Clanmil Housing Association Ireland						Q4-2021
77	77	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 1)	12	Tuath Housing Association						Q2-2022
78	78	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 2)	5	Tuath Housing Association						Q4-2022
79	79	CALF Turnkey	Cavan	Drumalee Manor, Drumalee, Co. Cavan (Phase 3)	8	Tuath Housing Association					Q2-2021	
80	80	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 1)	5	Co - Operative Housing Ireland Society Limited						Q4-2022
81	81	CALF Turnkey	Cavan	Rampart View, Virginia, Co. Cavan (Phase 3)	6	Co - Operative Housing Ireland Society Limited						Q2-2021
82	82	CALF Turnkey	Cavan	The Gallops, Cavan Town, Co. Cavan (Phase 2)	22	Cl�id Housing						Q2-2022
83	83	SHIP CONSTRUCTION TURNKEY	Clare	Shantraud Woods, Killaloe	4	*N/A						Q1-2022
84	84	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	20	N/A						Q4-2022
85	85	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	12	N/A						Q2-2022
86	86	SHIP CONSTRUCTION TURNKEY	Clare	Main St., Mountshannon	4	*N/A						Q3-2022
87	87	SHIP CONSTRUCTION TURNKEY	Clare	Cluain Greine, Drumcliff Rd., Ennis 	23	*N/A						Q4-2022
88	88	SHIP CONSTRUCTION TURNKEY	Clare	Clarehill, Clarecastle, Co Clare	6	N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
89	89	SHIP CONSTRUCTION TURNKEY	Clare	Shanakyle Road, Kilrush	16	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
90	90	SHIP CONSTRUCTION TURNKEY	Clare	Clarehill, Clarecastle, Co Clare	7	N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
91	91	SHIP CONSTRUCTION TURNKEY	Clare	Shanakyle Road, Kilrush	10	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
92	92	SHIP CONSTRUCTION SINGLE STAGE	Clare	Dun na Mara, Doonbeg	2	*N/A						Q2-2021
93	93	SHIP CONSTRUCTION SINGLE STAGE	Clare	St Senan?s Terrace, Kilrush -No5-No 6	2	*N/A						Q3-2021
94	94	SHIP CONSTRUCTION RENEWAL	Clare	Nagles Terrace, Kilrush	3	N/A						Q4-2022
95	95	SHIP CONSTRUCTION	Clare	Ashline, Kilrush Road, Ennis	40	*N/A						Q2-2022
96	96	SHIP CONSTRUCTION	Clare	Ballard Rd,Miltown Malbay	27	*N/A						Q4-2022
97	97	SHIP CONSTRUCTION	Clare	Doonaun, Tulla	25	*N/A						Q2-2022
98	98	SHIP CONSTRUCTION	Clare	Boheraroan, Newmarket-on-Fergus	18	*N/A						Q1-2022
99	99	SHIP CONSTRUCTION	Clare	Ballyminogue,Feakle Rd., Scariff	18	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
100	100	SHIP CONSTRUCTION	Clare	Madden's Terrace, Clarecastle	5	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
101	101	SHIP CONSTRUCTION	Clare	Kilkee Road, Doonbeg	8	*N/A			Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.			
102	102	SHIP CONSTRUCTION	Clare	Tulla Road, Roslevan, Ennis (Fannings site)	8	*N/A						Q4-2022
103	103	SHIP CONSTRUCTION	Clare	Drumcliffe Road, Ennis	26	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
104	104	SHIP CONSTRUCTION	Clare	Deerpark, Ennistymon	30	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
105	105	SHIP CONSTRUCTION	Clare	Ballyliddan West, Sixmilebridge	15	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
106	106	SHIP CONSTRUCTION	Clare	Gort Road Ennis	20	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
107	107	CAS CONSTRUCTION TURNKEY	Clare	Market Sq., Ennis	14	Peter McVerry Trust Ltd				Stage 4 approved Q1-2022, the scheme is fully approved.		
108	108	CAS CONSTRUCTION SINGLE STAGE	Clare	20 Dooneen Park, Kilrush	2	Banner Housing Association Ltd					Q4-2022	
109	109	CAS CONSTRUCTION RENEWAL	Clare	17 Kincora Park, Ennis	1	Society of Saint Vincent de Paul					Q2-2022	
110	110	CAS CONSTRUCTION	Clare	Teach Rua, Edenvale Ennis	4	Newgrove Housing Association Ltd						Q2-2021
111	111	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 1)	20	*N/A						Q2-2021
112	112	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Clare	Shannon East (Phase 2)	31	*N/A						Q3-2021
113	113	CALF Turnkey	Clare	"An C?san Gheall, Limerick Rd, Ennis, Co Clare

 (Phase 1)*"	18	Inis Housing Association					Q1-2022	
114	114	CALF Turnkey	Clare	4 units, Ballyminogue, Scarrif, Co. Clare (Phase 1)	4	Focus Housing Association CLG				Q4-2022		
115	115	CALF Turnkey	Clare	Cahercalla, Drumbiggle, Ennis, Co. Clare (Phase 2)*	2	Cl�id Housing						Q1-2022
116	116	CALF Turnkey	Clare	Cluain Na Laoi, Kilkishen, Co. Clare (Phase 1)*	16	Circle Voluntary Housing Association Ltd				Q4-2022		
117	117	CALF Turnkey	Clare	Gleann Cora, Newmarket on Fergus, Co. Clare (Phase 2)*	2	Co - Operative Housing Ireland Society Limited						Q3-2021
118	118	CALF Turnkey	Clare	Hogan?s Place, Limerick Road, Ennis, Co. Clare (formerly Abbey View) (Phase 1)	9	Cl�id Housing						Q4-2022
119	119	CALF Turnkey	Clare	Hogan?s Place, Limerick Road, Ennis, Co. Clare (formerly Abbey View) (Phase 2)*	15	Cl�id Housing					Q4-2021	
120	120	CALF Turnkey	Clare	Radharc an Chnoic, Tulla, Co. Clare (Phase 1)*	2	Cl�id Housing					Q4-2020	
121	121	CALF Construction	Clare	Revised - Bruachlan, Westbury, Co Clare (Phase 1)	22	Co - Operative Housing Ireland Society Limited				Q2-2021		
122	122	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 1)	14	Co - Operative Housing Ireland Society Limited						Q4-2021
123	123	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 2)*	15	Co - Operative Housing Ireland Society Limited						Q1-2022
124	124	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 3)*	24	Co - Operative Housing Ireland Society Limited						Q2-2022
125	125	CALF Turnkey	Clare	Roslevan, Tulla Road, Ennis, County Clare (Phase 4)*	16	Co - Operative Housing Ireland Society Limited						Q3-2022
126	126	SHIP DIALOG	Cork City	Barrack Street	32	*N/A					Q1-2019	
127	127	SHIP DIALOG	Cork City	Woods Street	16	*N/A					Q1-2019	
128	128	SHIP DIALOG	Cork City	Corkeran's Quay	3	*N/A					Q2-2018	
129	129	SHIP DIALOG	Cork City	Skehard Road, Blackrock, Cork	16	*N/A						Q2-2022
130	130	SHIP DIALOG	Cork City	Coach Street, Cork	13	*N/A					Q3-2021	
131	131	SHIP DIALOG	Cork City	Shanakiel Road, Cork	20	*N/A						Q3-2022
132	132	SHIP DIALOG	Cork City	Spring Lane, Blackpool, Cork	8	*N/A						Q4-2022
133	133	SHIP DIALOG	Cork City	Glen Ryan Road, Cork	9	*N/A				Stage 4 approved Q2-2019, the scheme is fully approved.		
134	134	SHIP DIALOG	Cork City	Pouladuff Road, Cork 	11	*N/A						Q2-2022
135	135	SHIP DIALOG	Cork City	Watercourse Road, Blackpool, Cork	37	*N/A						Q4-2022
136	136	SHIP DIALOG	Cork City	Denroche's Cross, Glasheen Road, Cork	43	*N/A					Q1-2021	
137	137	SHIP DIALOG	Cork City	Wolsey Court, Blackpool, Cork	49	*N/A			Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.			
138	138	SHIP DIALOG	Cork City	Sunview, South Douglas Road, Douglas, Cork	25	*N/A						Q3-2022
139	139	SHIP DIALOG	Cork City	Former Bolands Mill, Old Mallow Road	54	*N/A					Q4-2021	
140	140	SHIP DIALOG	Cork City	KILLEENS, CO CORK	12	*N/A			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
141	141	SHIP DIALOG	Cork City	Church Road, Black Rock, Cork	30	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
142	142	SHIP DIALOG	Cork City	Kinsale road Cork City	47	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
143	143	SHIP DIALOG	Cork City	Ballincrokig, Ballyvolane	72	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
144	144	SHIP DIALOG	Cork City	Greenvalley, Douglas, Cork City	27	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
145	145	SHIP DIALOG	Cork City	21-22 Dominick Street, Shandon, Cork City	9	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
146	146	SHIP DIALOG	Cork City	Hawkes Road, Bishopstown Road, Bishopstown, Cork City	29	*N/A						Q4-2022
147	147	SHIP DIALOG	Cork City	Lower John Street	3	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
148	148	SHIP DIALOG	Cork City	Killeens, Co. Cork	32	N/A			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
149	149	SHIP CONSTRUCTION RENEWAL	Cork City	38 Gould Street	1	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
150	150	SHIP CONSTRUCTION RENEWAL	Cork City	1 Evenus Ville, Albert Road, Cork City	1	*N/A					Q3-2022	
151	151	SHIP CONSTRUCTION RENEWAL	Cork City	Ard na Ri, Pouladuff Road, Cork City	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
152	152	SHIP CONSTRUCTION RENEWAL	Cork City	Mount Eden Road, Cork City	1	*N/A						Q4-2022
153	153	SHIP CONSTRUCTION RENEWAL	Cork City	21 St Anthony's Road	1	*N/A						Q4-2022
154	154	SHIP CONSTRUCTION RENEWAL	Cork City	26 Watercourse Road 	1	*N/A						Q4-2022
155	155	SHIP CONSTRUCTION RENEWAL	Cork City	22 Summerstown Grove	1	*N/A						Q4-2022
156	156	SHIP CONSTRUCTION RENEWAL	Cork City	2A Fairhill	1	*N/A						Q4-2022
157	157	SHIP CONSTRUCTION RENEWAL	Cork City	99 Ballinderry Park	1	*N/A						Q4-2022
158	158	SHIP CONSTRUCTION DESIGN BUILD	Cork City	Clover Hill Court, Bessboro Road, Mahon, Cork	90	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
159	159	SHIP CONSTRUCTION	Cork City	Poulavone, Ballincollig	64	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
160	160	SHIP CONSTRUCTION	Cork City	Boyces Street	14	*N/A				Stage 4 approved Q3-2021, the scheme is fully approved.		
161	161	SHIP CONSTRUCTION	Cork City	Madonna House, Ballincollig	6	*N/A		Stage 2 approved Q4-2019, full design/tender being prepared.				
162	162	SHIP CONSTRUCTION	Cork City	Bramble Cottages	4	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
163	163	SHIP CONSTRUCTION	Cork City	Errigal Heights, The Glen, Cork City	28	*N/A		Stage 2 approved Q2-2020, full design/tender being prepared.				
164	164	SHIP CONSTRUCTION	Cork City	Glenamoy Lawn, Mayfield, Cork	3	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
165	165	SHIP CONSTRUCTION	Cork City	Hollywood Estate Infill Housing, Blarney Road, Cork	7	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
166	166	SHIP CONSTRUCTION	Cork City	Westside, Model Farm Road, Cork	43	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
167	167	SHIP CONSTRUCTION	Cork City	16A Kerry Road (former Sl� Gartan), Mayfield, Cork 	1	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
168	168	SHIP CONSTRUCTION	Cork City	Boyces street	37	*N/A		Stage 2 approved Q1-2018, full design/tender being prepared.				
169	169	SHIP CONSTRUCTION	Cork City	15 Loughview terrace, The Lough, Glasheen Cork City	1	*N/A					Q3-2022	
170	170	SHIP CONSTRUCTION	Cork City	85A Gate Lodge Blackrock	1	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
171	171	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 1C	41	*N/A					Q4-2022	
172	172	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 2B	38	*N/A					Q4-2022	
173	173	REGENERATION	Cork City	Foyle Avenue Infill Housing Development, Knocknaheeny, Cork	2	*N/A					Q3-2022	
174	174	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 3B	62	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
175	175	REGENERATION	Cork City	CNWQR Knocknaheeny Phase 4A	43	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
176	176	CAS CONSTRUCTION SINGLE STAGE	Cork City	Eastville, Albert Road, Cork	1	Galtan Ltd						Q1-2022
177	177	CAS CONSTRUCTION SINGLE STAGE	Cork City	14 Glanmire Road Cork	2	Galtan Ltd						Q1-2022
178	178	CAS CONSTRUCTION RENEWAL	Cork City	92 Ballyhooley Road 	6	?glaigh N�isi�nta na h�ireann (O.N.E.)				Stage 4 approved Q4-2022, the scheme is fully approved.		
179	179	CAS CONSTRUCTION	Cork City	Ard na Ri, Closes Green, Farranree, Cork	20	Farranree Sheltered Housing Association		Stage 2 approved Q3-2022, full design/tender being prepared.				
180	180	CAS CONSTRUCTION	Cork City	Apts 2 & 3 Cois Coille, Tivoli, Cork	2	Galtan Ltd						Q4-2021
181	181	CAS CONSTRUCTION	Cork City	Aras Lean, Murphy?s Farm, Bishopstown, Co. Cork	15	Citizens Housing Association		Stage 2 approved Q3-2022, full design/tender being prepared.				
182	182	CAS CONSTRUCTION	Cork City	Gardiners Hill, St Lukes, Cork 	3	Focus Ireland	Stage 1 approved Q1-2022, outline design and costs being prepared.					
183	183	CAS CONSTRUCTION	Cork City	88 Sundays Well	2	Galtan Ltd		Stage 2 approved Q3-2022, full design/tender being prepared.				
184	184	CALF Turnkey	Cork City	3 units, Model Quarters, Tower, Blarney, Co Cork  (Phase 1)	3	Circle Voluntary Housing Association Ltd					Q2-2019	
185	185	CALF Turnkey	Cork City	16 homes at Grand Parade, Cork City (Phase 1)	16	Focus Housing Association CLG						Q4-2022
186	186	CALF Turnkey	Cork City	6 units at Kyle Street  (Phase 1)	6	Focus Housing Association CLG					Q2-2021	
187	187	CALF Turnkey	Cork City	 Aylesbury, Ballintemple, Cork City (Phase 1)*	8	Respond						Q4-2022
188	188	CALF Turnkey	Cork City	 Aylesbury, Ballintemple, Cork City (Phase 2)	8	Respond						Q4-2022
189	189	CALF Turnkey	Cork City	Baker Street, Ballincollig, Co Cork (Phase 1)*	14	Cl�id Housing					Q3-2022	
190	190	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 1)*	3	Tuath Housing Association						Q2-2022
191	191	CALF Turnkey	Cork City	Barters Wood, Tower, Cork (Phase 2)*	3	Tuath Housing Association						Q2-2022
192	192	CALF Turnkey	Cork City	Block 10 Jacobs Island, Mahon, Cork (Phase 1)	69	Respond					Q4-2022	
193	193	CALF Turnkey	Cork City	Boherboy Road, Silversprings Hill, Cork City  (Phase 1)*	15	Respond					Q1-2022	
194	194	CALF Turnkey	Cork City	Brocklesby Street, Blackpool, Cork City (Phase 1)*	42	Focus Housing Association CLG				Q1-2022		
195	195	CALF Construction	Cork City	Crann Darach, Middle Glanmire Road, Montenotte, Cork (formerly St Dominics) (Phase 1)	27	Tuath Housing Association						Q4-2022
196	196	CALF Turnkey	Cork City	Daltons Avenue, Cornmarket Street, Cork City (Phase 1)*	14	Tuath Housing Association				Q3-2022		
197	197	CALF Turnkey	Cork City	Evergreen Road, Turners Cross, Cork  (Phase 1)*	28	Respond						Q4-2022
198	198	CALF Turnkey	Cork City	Fairfield Meadows, Upper Fair Hill, Cork (Phase 1)*	18	Focus Housing Association CLG				Q4-2022		
199	199	CALF Turnkey	Cork City	"Glanmire Village, Glanmire, Cork
 (Phase 1)"	3	Focus Housing Association CLG						Q2-2022
200	200	CALF Construction	Cork City	Green Lane, Blackpool, Cork City (Phase 1)	112	Cl�id Housing					Q4-2021	
201	201	CALF Turnkey	Cork City	Haig Gardens, Boreenamanna Road and Wallace Avenue, Ballintemple (Glenanaar) (Phase 1)*	27	Respond						Q4-2022
202	202	CALF Turnkey	Cork City	Hereford Place, Ballymacthomas Street, Cork City (Phase 1)*	19	Respond						Q4-2022
203	203	CALF Turnkey	Cork City	Lancaster Gate, Western Road, Cork (Phase 1)	15	Cl�id Housing						Q4-2022
204	204	CALF Turnkey	Cork City	Link Road, Ballincollig, Cork (Phase 1)*	40	Respond					Q3-2021	
205	205	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 1)	22	Tuath Housing Association						Q4-2022
206	206	CALF Turnkey	Cork City	Miles Stream, Shanakiel, Cork (Phase 2)	20	Tuath Housing Association						Q4-2022
207	207	CALF Turnkey	Cork City	Millfield Cottages, Blackpool, Cork City (Phase 1)*	18	Respond					Q3-2022	
208	208	CALF Turnkey	Cork City	Newton Heights, Boherboy Road, Lotamore, Cork   (Phase 1)	8	Cl�id Housing						Q4-2022
209	209	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 2)	31	Respond						Q4-2021
210	210	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 3)	20	Respond						Q3-2022
211	211	CALF Turnkey	Cork City	Redforge Road, Blackpool, Cork City (Phase 4)*	11	Respond					Q1-2020	
212	212	CALF Turnkey	Cork City	Riverside Farm, Model Farm Road, Bishopstown, Cork (Phase 1)*	48	Respond				Q3-2022		
213	213	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 1)*	22	Respond						Q2-2022
214	214	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 2)*	19	Respond						Q4-2022
215	215	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork (Phase 3)	24	Respond						Q4-2022
216	216	CALF Turnkey	Cork City	Sarsfield Road, Doughcloyne, Wilton, Cork City (Phase 1)	4	Respond						Q4-2022
217	217	CALF Turnkey	Cork City	Springville House, Bulls Lane, Blackrock Road, Cork (Phase 1)	35	Tuath Housing Association						Q4-2022
218	218	CALF Turnkey	Cork City	Strawberry Hill, Blarney Street, Cork (Phase 1)*	16	Respond				Q1-2022		
219	219	CALF Turnkey	Cork City	Summerville Place, Sunday?s Well, Cork (Phase 1)	10	Respond						Q4-2022
220	220	CALF Turnkey	Cork City	The Oaks, Frankfield, Douglas, Cork City (Phase 1)*	2	Tuath Housing Association						Q4-2021
221	221	SHIP CONSTRUCTION TURNKEY	Cork County	Claragh Road, Millstreet	5	*N/A						Q2-2021
222	222	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	6	*N/A					Q4-2017	
223	223	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	3	*N/A						Q4-2021
224	224	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	5	*N/A						Q2-2022
225	225	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	11	*N/A						Q1-2021
226	226	SHIP CONSTRUCTION TURNKEY	Cork County	Mill Road, Avoncore, Bloomfield, Midleton	17	*N/A						Q2-2021
227	227	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	5	*N/A						Q3-2022
228	228	SHIP CONSTRUCTION TURNKEY	Cork County	Millview Road, Kanturk	4	*N/A						Q1-2021
229	229	SHIP CONSTRUCTION TURNKEY	Cork County	Ard an Bhaile, Creggane, Buttevant	6	*N/A						Q4-2022
230	230	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A						Q2-2021
231	231	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	12	*N/A						Q2-2022
232	232	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	16	*N/A					Q4-2017	
233	233	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	10	*N/A					Q1-2020	
234	234	SHIP CONSTRUCTION TURNKEY	Cork County	An Goritin Rua, Millstreet Road, Macroom	14	*N/A						Q2-2021
235	235	SHIP CONSTRUCTION TURNKEY	Cork County	Lyraneag, Rockchapel,	2	*N/A				Stage 4 approved Q2-2020, the scheme is fully approved.		
236	236	SHIP CONSTRUCTION TURNKEY	Cork County	Eyeries, Castletownbere	6	*N/A						Q4-2022
237	237	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A						Q1-2021
238	238	SHIP CONSTRUCTION TURNKEY	Cork County	Spa Glen,Ballyviniter, Mallow	18	*N/A						Q2-2021
239	239	SHIP CONSTRUCTION TURNKEY	Cork County	Drakes Point, Knocknagore, Crosshaven	5	*N/A						Q3-2021
240	240	SHIP CONSTRUCTION TURNKEY	Cork County	Scarteen, Newmarket	11	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
241	241	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	6	*N/A					Q1-2020	
242	242	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	6	*N/A					Q1-2020	
243	243	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale	19	*N/A						Q4-2021
244	244	SHIP CONSTRUCTION TURNKEY	Cork County	Clarendon Brooks, Carrs Hill, Douglas	4	*N/A						Q1-2021
245	245	SHIP CONSTRUCTION TURNKEY	Cork County	Abbeyfort, Kinsale (Phase 2)	17	*N/A						Q3-2022
246	246	SHIP CONSTRUCTION TURNKEY	Cork County	Ard Cashel, Watergrasshill	6	*N/A						Q1-2022
247	247	SHIP CONSTRUCTION TURNKEY	Cork County	Lios Ard, Ballyhooly	6	*N/A						Q2-2021
248	248	SHIP CONSTRUCTION TURNKEY	Cork County	Courtbrack, Tower	1	*N/A						Q4-2021
249	249	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	10	*N/A						Q4-2022
250	250	SHIP CONSTRUCTION TURNKEY	Cork County	Lisgoold, An Tui 	2	*N/A						Q2-2022
251	251	SHIP CONSTRUCTION TURNKEY	Cork County	Crann Ard, Fermoy	26	*N/A					Q4-2017	
252	252	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	4	*N/A						Q4-2021
253	253	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	7	*N/A						Q2-2021
254	254	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	3	*N/A						Q1-2022
255	255	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	5	*N/A						Q2-2022
256	256	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	4	*N/A						Q3-2022
257	257	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	12	*N/A						Q3-2022
258	258	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	5	*N/A						Q4-2022
259	259	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	4	*N/A						Q4-2021
260	260	SHIP CONSTRUCTION TURNKEY	Cork County	The Meadows, Dunmanway	4	N/A						Q3-2022
261	261	SHIP CONSTRUCTION TURNKEY	Cork County	Sweetfields, Youghal	7	N/A						Q1-2022
262	262	SHIP CONSTRUCTION TURNKEY	Cork County	Caherdaniel, Bantry	12	*N/A					Q1-2020	
263	263	SHIP CONSTRUCTION TURNKEY	Cork County	Dromdiah Park, Killeagh Gardens, Killeagh	10	*N/A						Q4-2022
264	264	SHIP CONSTRUCTION TURNKEY	Cork County	Meenane, Watergrasshill	7	*N/A						Q2-2022
265	265	SHIP CONSTRUCTION TURNKEY	Cork County	The Pastures, Charleville	7	*N/A						Q2-2022
266	266	SHIP CONSTRUCTION TURNKEY	Cork County	The Meadows, Dunmanway (Phase 2)	8	*N/A						Q3-2022
267	267	SHIP CONSTRUCTION TURNKEY	Cork County	Reanrour East, Bantry 	5	*N/A					Q4-2022	
268	268	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull, Co. Cork Phase 3	2	*N/A						Q4-2022
269	269	SHIP CONSTRUCTION TURNKEY	Cork County	Dromahane, Mallow, Co. Cork	6	N/A						Q4-2022
270	270	SHIP CONSTRUCTION TURNKEY	Cork County	Foxglove Close, Charleville, Co. Cork 	12	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
271	271	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	11	N/A						Q4-2022
272	272	SHIP CONSTRUCTION TURNKEY	Cork County	Copper Point, Schull	4	N/A						Q4-2022
273	273	SHIP CONSTRUCTION TURNKEY	Cork County	Pike Road, Fermoy, Co Cork	25	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
274	274	SHIP CONSTRUCTION TURNKEY	Cork County	Boatyard, Carrigaline, Co. Cork 	2	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
275	275	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	5	N/A						Q4-2022
276	276	SHIP CONSTRUCTION TURNKEY	Cork County	Dromahane, Mallow	3	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
277	277	SHIP CONSTRUCTION TURNKEY	Cork County	Kilmoney, Carrigaline	9	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
278	278	SHIP CONSTRUCTION SINGLE STAGE	Cork County	2A Glenview, Lyre, Banteer	1	*N/A					Q2-2022	
279	279	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Cuirt Na Slini, Cloyne, East Cork 	2	*N/A						Q4-2022
280	280	SHIP CONSTRUCTION SINGLE STAGE	Cork County	81 Belmont Place, Cobh,	1	*N/A						Q4-2022
281	281	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Main St. Dunmanway	1	*N/A						Q4-2021
282	282	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Croke Place, Garranmacgarrett, Kilbrin, kanturk	2	*N/A					Q1-2022	
283	283	SHIP CONSTRUCTION SINGLE STAGE	Cork County	High St., Sleaveen Hill, Macroom	1	*N/A						Q2-2022
284	284	SHIP CONSTRUCTION SINGLE STAGE	Cork County	49 Masseytown, Macroom	1	*N/A						Q2-2022
285	285	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Aisling Gheal, Hospital Hill, Kanturk	1	*N/A				Stage 4 approved Q1-2020, the scheme is fully approved.		
286	286	SHIP CONSTRUCTION SINGLE STAGE	Cork County	Carrig Rossa Phase 2, Rossmore	2	*N/A				Stage 4 approved Q2-2020, the scheme is fully approved.		
287	287	SHIP CONSTRUCTION SINGLE STAGE	Cork County	3 Knockbrogan Park, Bandon	1	*N/A						Q4-2021
288	288	SHIP CONSTRUCTION SINGLE STAGE	Cork County	87 Belmont, Cobh	1	*N/A						Q3-2022
289	289	SHIP CONSTRUCTION SINGLE STAGE	Cork County	33 Market Place, Kanturk, Co. Cork	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
290	290	SHIP CONSTRUCTION SINGLE STAGE	Cork County	4 Church View Ballindangan	1	*N/A						Q4-2022
291	291	SHIP CONSTRUCTION	Cork County	Ard Na Greine, Cortmacsherry	17	*N/A					Q3-2019	
292	292	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	51	*N/A						Q4-2021
293	293	SHIP CONSTRUCTION	Cork County	Newtown House , Bantry	1	*N/A						Q4-2021
294	294	SHIP CONSTRUCTION	Cork County	Kilnagleary, Carrigaline (Phase 4)	15	*N/A						Q4-2022
295	295	SHIP CONSTRUCTION	Cork County	Townsend Street, Skibbereen	6	*N/A						Q2-2022
296	296	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	5	*N/A						Q3-2022
297	297	SHIP CONSTRUCTION	Cork County	Richmond Court, Bandon	6	*N/A					Q2-2022	
298	298	SHIP CONSTRUCTION	Cork County	Brigown Road, Mitchelstown	8	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
299	299	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	8	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
300	300	SHIP CONSTRUCTION	Cork County	Pound Lane, Kilworth 	7	*N/A					Q1-2022	
301	301	SHIP CONSTRUCTION	Cork County	Avoncore, Midleton (Rae Avoncore)	4	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
302	302	SHIP CONSTRUCTION	Cork County	Knocknagown, Rylane	1	*N/A						Q3-2021
303	303	SHIP CONSTRUCTION	Cork County	Uplands (Phase 2), College Road,  Fermoy	11	*N/A		Stage 2 approved Q3-2019, full design/tender being prepared.				
304	304	SHIP CONSTRUCTION	Cork County	Lissoran, Ballinspittle	4	*N/A						Q4-2021
305	305	SHIP CONSTRUCTION	Cork County	Convent Road, Doneraile	17	*N/A						Q4-2022
306	306	SHIP CONSTRUCTION	Cork County	Kearney's field Dunmanway	13	*N/A						Q3-2022
307	307	SHIP CONSTRUCTION	Cork County	Mill Road, Kanturk, Co. Cork	13	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
308	308	SHIP CONSTRUCTION	Cork County	Chapel Lane, Ballydehob, Co. Cork	12	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
309	309	SHIP CONSTRUCTION	Cork County	Sleaveen East, Macroom	16	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
310	310	SHIP CONSTRUCTION	Cork County	Pl�s an Iarnr�id (Railway Place), Old Barrack Road, Bantry, Co. Cork	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
311	311	SHIP CONSTRUCTION	Cork County	Coastguard Cottages, Lower Roads, Crosshaven, Co. Cork	33	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
312	312	SHIP CONSTRUCTION	Cork County	Beechgrove, Clonakilty	6	N/A						Q2-2022
313	313	SHIP CONSTRUCTION	Cork County	Avoncore, Midleton (Rae Avoncore)	6	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
314	314	SHIP CONSTRUCTION	Cork County	Porter?s Lane, Youghal, Co. 	6	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
315	315	CAS CONSTRUCTION TURNKEY	Cork County	Ardmanagh, Schull	12	T�ath Housing Association Ltd				Stage 4 approved Q2-2022, the scheme is fully approved.		
316	316	CAS CONSTRUCTION TURNKEY	Cork County	1-10 Vickerys Inn, New Street Bantry	10	Peter McVerry Trust Ltd						Q4-2022
317	317	CAS CONSTRUCTION TURNKEY	Cork County	Main Street, Charleville, Co. Cork	9	Peter McVerry Trust Ltd						Q4-2022
318	318	CAS CONSTRUCTION TURNKEY	Cork County	Mullavale, Castletownroche	8	Respond						Q4-2022
319	319	CAS CONSTRUCTION TURNKEY	Cork County	Church Place, Oliver Plunkett Hill, Fermoy, Co Cork	7	Focus Ireland				Stage 4 approved Q3-2022, the scheme is fully approved.		
320	320	CAS CONSTRUCTION TURNKEY	Cork County	Main Street, Charleville, Co. Cork	1	Peter McVerry Trust Ltd				Stage 4 approved Q2-2022, the scheme is fully approved.		
321	321	CAS CONSTRUCTION RENEWAL	Cork County	8 Harbour Row, Cobh	5	?glaigh N�isi�nta na h�ireann (O.N.E.)						Q3-2022
322	322	CAS CONSTRUCTION	Cork County	Sisters of Mercy Church and Convent at Knocknamuck, Bantry Bay	18	Cluid Housing Association					Q1-2022	
323	323	CAS CONSTRUCTION	Cork County	Masseytown, Macroom	19	T�ath Housing Association Ltd		Stage 2 approved Q3-2022, full design/tender being prepared.				
324	324	CAS CONSTRUCTION	Cork County	Baile Bhuire, Macroom	3	Comhlacht Tithe Soisialta Agus ? Forbairt An Tsulain Teoranta						Q3-2022
325	325	CAS CONSTRUCTION	Cork County	Charleville, Church View, Love Lane, Charleville	9	Charleville Care Project Ltd				Stage 4 approved Q4-2022, the scheme is fully approved.		
326	326	CAS CONSTRUCTION	Cork County	St. Michaels, 36 Main Street, Bandon, Co. Cork	6	Bandon Geriatric ? Community Council			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
327	327	CAS CONSTRUCTION	Cork County	Distillery Lane, Distillery Walk, Midleton	6	Midleton Lions Clubs Housing Association Limited	Stage 1 approved Q1-2020, outline design and costs being prepared.					
328	328	CAS CONSTRUCTION	Cork County	Mardyke, Skibbereen	8	The Skibbereen Geriatric Society Limited	Stage 1 approved Q1-2020, outline design and costs being prepared.					
329	329	CAS CONSTRUCTION	Cork County	Daniel O?Brien Terrace, Buttevant	9	T�ath Housing Association Ltd				Stage 4 approved Q4-2022, the scheme is fully approved.		
330	330	CAS CONSTRUCTION	Cork County	Lisheen Field, Kilbarry Road, Dunmanway, Co. Cork	16	Cluid Housing Association	Stage 1 approved Q2-2020, outline design and costs being prepared.					
331	331	CAS CONSTRUCTION	Cork County	102 Main Street, Mallow, Co. Cork	3	Peter McVerry Trust Ltd	Stage 1 approved Q4-2022, outline design and costs being prepared.					
332	332	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 1)	20	*N/A						Q2-2021
333	333	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	The Miles, Clonakilty (Phase 2)	32	*N/A						Q4-2021
334	334	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 1)	35	*N/A						Q2-2021
335	335	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Poundhill, Skibbereen (Phase 2)	15	*N/A						Q4-2021
336	336	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 1)	37	*N/A						Q2-2021
337	337	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Cork County	Oakwood, Macroom (Phase 2)	13	*N/A						Q3-2021
338	338	CALF Turnkey	Cork County	Barnahely, Ringaskiddy, Cork (Phase 1)	2	Circle Voluntary Housing Association Ltd					Q4-2021	
339	339	CALF Turnkey	Cork County	Cascade Apartments, Castlelake, Carrigtwohill, Cork (Phase 1)	95	Co - Operative Housing Ireland Society Limited						Q4-2022
340	340	CALF Turnkey	Cork County	Castle Heights, Kilmoney, Carrigaline, Co. Cork (Phase 1)	12	Cl�id Housing						Q4-2022
341	341	CALF Turnkey	Cork County	Cedar Court, Rathgoggin North, Charleville, Cork (Phase 1)	11	Tuath Housing Association					Q2-2022	
342	342	CALF Turnkey	Cork County	Cedar Court, Rathgoggin North, Charleville, Cork (Phase 2)*	23	Tuath Housing Association					Q2-2022	
343	343	CALF Turnkey	Cork County	Church Hill, Carrigaline, Co Cork (Phase 1)*	37	Respond					Q3-2021	
344	344	CALF Turnkey	Cork County	Cooline, Cobh, Co Cork (Phase 1)	17	Co - Operative Housing Ireland Society Limited						Q4-2022
345	345	CALF Turnkey	Cork County	Cooline, Cobh, Co Cork (Phase 2)	15	Co - Operative Housing Ireland Society Limited						Q4-2022
346	346	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 1)	14	Cl�id Housing						Q3-2022
347	347	CALF Turnkey	Cork County	Harbour Heights, Passage West, Co Cork (Phase 2)	13	Cl�id Housing						Q4-2022
348	348	CALF Turnkey	Cork County	Hazel View, Hazel Brooke, Spa Glen, Mallow, Co Cork (Phase 1)	12	Cl�id Housing					Q4-2021	
349	349	CALF Turnkey	Cork County	Lough Beg, Loughbeg, Ringaskiddy, Cork (Phase 1)*	15	Respond				Q2-2022		
350	350	CALF Turnkey	Cork County	Shortcastle St, Mallow, Co Cork  (Phase 1)	8	Focus Housing Association CLG				Q3-2022		
351	351	CALF Turnkey	Cork County	Shambles Lane, Thomas Davis Street, Mallow, Co Cork (Phase 1)	6	Focus Housing Association CLG						Q4-2022
352	352	CALF Turnkey	Cork County	Westview, Coolroe, Ballincollig, Co. Cork (Phase 2)	20	Respond						Q1-2021
353	353	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	22	*N/A						Q1-2021
354	354	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	16	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
355	355	SHIP CONSTRUCTION TURNKEY	DLR	George's Street Upper, Dun Laoghaire, Co. Dublin	5	*N/A						Q1-2021
356	356	SHIP CONSTRUCTION TURNKEY	DLR	HazelBrook Square, Nutgrove, Churchtown	2	*N/A						Q4-2022
357	357	SHIP CONSTRUCTION TURNKEY	DLR	Kilternan Close	17	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
358	358	SHIP CONSTRUCTION TURNKEY	DLR	Dun Gaoithe, Sandyford, Dublin 18	2	N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
359	359	SHIP CONSTRUCTION SINGLE STAGE	DLR	5 Corrig Road, Dalkey, Co Dublin	2	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
360	360	SHIP CONSTRUCTION DESIGN BUILD	DLR	Ballyogan Square, Ballyogan	67	*N/A				Stage 4 approved Q3-2021, the scheme is fully approved.		
361	361	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	35	*N/A					Q3-2022	
362	362	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	104	*N/A					Q3-2022	
363	363	SHIP CONSTRUCTION DESIGN BUILD	DLR	Shanganagh Castle	61	*N/A					Q3-2022	
364	364	SHIP CONSTRUCTION	DLR	Park House, 66 George's Street, Dun Laoghaire	4	*N/A					Q3-2022	
365	365	SHIP CONSTRUCTION	DLR	Broadford Rise	21	*N/A						Q4-2021
366	366	SHIP CONSTRUCTION	DLR	Ballyogan Avenue, Ballyogan	2	*N/A						Q2-2021
367	367	SHIP CONSTRUCTION	DLR	St. Laurence?s Park, Stillorgan, Co. Dublin	88	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
368	368	SHIP CONSTRUCTION	DLR	Moyola Court, Churchtown Lower, Dublin 14	4	*N/A					Q3-2022	
369	369	SHIP CONSTRUCTION	DLR	Site at Roebuck Road, Clonskeagh, Dublin 14	4	*N/A		Stage 2 approved Q2-2021, full design/tender being prepared.				
370	370	SHIP CONSTRUCTION	DLR	37A Rollins Villas, Sallynoggin, Co. Dublin 	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
371	371	SHIP CONSTRUCTION	DLR	Old Coastguard Cottages, Coal Harbour, Harbour Road	4	*N/A					Q2-2022	
372	372	SHIP CONSTRUCTION	DLR	Cross Avenue, D�n Laoghaire, Co. Dublin	4	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
373	373	SHIP CONSTRUCTION	DLR	Infill Site Adjacent to 4 Rockville Drive, Glenamuck, Co. Dublin	1	N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
374	374	SHIP CONSTRUCTION	DLR	Blackglen Road, Sandyford, Dublin 18	98	N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
375	375	CAS CONSTRUCTION SINGLE STAGE	DLR	58-59 Patrick Street, D�n Laoghaire, Co. Dublin	8	Peter McVerry Trust Ltd						Q4-2022
376	376	CAS CONSTRUCTION	DLR	30 Obelisk Walk, Blackrock	4	St. John of God Housing Association Ltd						Q4-2021
377	377	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	DLR	Ballay, Dublin 16	58	N/A	Q2-2022					
378	378	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	DLR	Lambs Cross, Sandyford, Dublin 18.	25	N/A	Q2-2022					
379	379	CALF Turnkey	DLR	Ardilea Crescent, Ardilea, Clonskeagh, Dublin 14, Co. Dublin (Phase 1)*	2	Tuath Housing Association						Q4-2021
380	380	CALF Turnkey	DLR	Ballybetagh Road, Kilternan, Co Dublin (Phase 1)*	22	Clanmil Housing Association Ireland					Q3-2021	
381	381	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 1)*	80	Cl�id Housing					Q4-2019	
382	382	CALF Turnkey	DLR	Cherrywood Town Centre, Dublin 18 (Phase 2)*	61	Cl�id Housing					Q4-2019	
383	383	CALF Turnkey	DLR	Egremont, Church Road, Killiney, Co. Dublin (Phase 1)*	4	Circle Voluntary Housing Association Ltd					Q4-2019	
384	384	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 1)	9	Respond						Q4-2021
385	385	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 2)	22	Respond						Q1-2022
386	386	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 18 (Phase 3)	22	Respond						Q1-2022
387	387	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 1)	18	Tuath Housing Association						Q4-2021
388	388	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 2)	16	Tuath Housing Association						Q1-2022
389	389	CALF Construction	DLR	Enniskerry Road, Sandyford, Dublin 19 (Phase 3)	18	Tuath Housing Association						Q1-2022
390	390	CALF Turnkey	DLR	Johnstown Place,Johnstown Road, Cabinteely, Dublin 18 (Formerly Johnstown Court) (Phase 1)*	51	Cl�id Housing						Q2-2021
391	391	CALF Turnkey	DLR	Kiln View, Clay Farm Way, Leopardstown, Co Dublin (Phase 1)*	55	The Iveagh Trust					Q4-2020	
392	392	CALF Turnkey	DLR	Lisieux Manor, Murphystown Road, Leopardstown, Dublin 18 (Phase 1)*	133	Respond					Q4-2022	
393	393	CALF Construction	DLR	Loughlinstown View(formerly Cromlech Fields) Loughlinstown, Ballybrack, Dublin (Phase 1)	34	Co - Operative Housing Ireland Society Limited				Q2-2021		
394	394	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 1)*	14	Tuath Housing Association						Q1-2021
395	395	CALF Turnkey	DLR	Mount Eagle, Kilgobbin Road, Sandyford, Dublin 18 (Phase 2)*	18	Tuath Housing Association						Q2-2021
396	396	CALF Turnkey	DLR	Oakton Court, Ballybrack, Co. Dublin (Phase 1)	5	Circle Voluntary Housing Association Ltd						Q4-2022
397	397	CALF Turnkey	DLR	Phase 2, Elmwood, Johnstown Road, Cabinteely, Dun Laoghaire, Co. Dublin (Phase 1)*	58	Cl�id Housing						Q1-2022
398	398	CALF Turnkey	DLR	The Glen, Glenamuck Road, Carrickmines, Dublin 18 (Phase 1)*	48	Respond					Q1-2021	
399	399	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)	30	Respond					Q3-2020	
400	400	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 1)*	2	Respond					Q3-2020	
401	401	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 2)	29	Respond					Q3-2020	
402	402	CALF Turnkey	DLR	Whinsfield, Sandyford Road, Dublin 18 (Phase 2)*	4	Respond					Q3-2020	
403	403	SHIP DIALOG	Donegal	Drumrooske West	36	*N/A				Stage 4 approved Q3-2019, the scheme is fully approved.		
404	404	SHIP DIALOG	Donegal	Brookfield, Donegal Town	8	*N/A						Q1-2022
405	405	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A				Stage 4 approved Q1-2020, the scheme is fully approved.		
406	406	SHIP DIALOG	Donegal	Donegal Road, Ballybofey	14	*N/A				Stage 4 approved Q4-2020, the scheme is fully approved.		
407	407	SHIP DIALOG	Donegal	Admiran, Stranorlar	52	*N/A		Stage 2 approved Q4-2019, full design/tender being prepared.				
408	408	SHIP DIALOG	Donegal	Rockview, Carrickboy, Ballyshannon	5	*N/A						Q4-2022
409	409	SHIP DIALOG	Donegal	Glencrow, Moville	35	*N/A		Stage 2 approved Q2-2020, full design/tender being prepared.				
410	410	SHIP DIALOG	Donegal	Ballyraine, Letterkenny	25	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
411	411	SHIP DIALOG	Donegal	Brookfield, Donegal Town	12	*N/A						Q4-2022
412	412	SHIP DIALOG	Donegal	Brookfield, Donegal Town	14	*N/A						Q4-2022
413	413	SHIP DIALOG	Donegal	Meadowfield, Convoy	12	*N/A				Stage 4 approved Q1-2020, the scheme is fully approved.		
414	414	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Loughanure Annagry	1	*N/A						Q3-2022
415	415	SHIP CONSTRUCTION SINGLE STAGE	Donegal	SRD Meenderrynasloe, Annagry	1	*N/A						Q3-2022
416	416	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Knockamany Malin	1	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
417	417	SHIP CONSTRUCTION SINGLE STAGE	Donegal	Largymore, Kilcar	1	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
418	418	SHIP CONSTRUCTION SINGLE STAGE	Donegal	The Meadows, Buncrana	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
419	419	SHIP CONSTRUCTION	Donegal	Meadow Hill, Raphoe	11	*N/A					Q3-2020	
420	420	SHIP CONSTRUCTION	Donegal	Long Lane, Letterkenny	29	*N/A						Q2-2021
421	421	SHIP CONSTRUCTION	Donegal	Rockytown, Buncrana (Phase 1)	21	*N/A						Q2-2022
422	422	SHIP CONSTRUCTION	Donegal	Pound Street, Dunfanaghy	4	*N/A						Q3-2022
423	423	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A						Q2-2021
424	424	SHIP CONSTRUCTION	Donegal	Railway Park, Drumrooske, Donegal Town	24	*N/A					Q1-2022	
425	425	SHIP CONSTRUCTION	Donegal	Trusk Road, Ballybofey	19	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
426	426	SHIP CONSTRUCTION	Donegal	Crana Crescent, Buncrana	16	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
427	427	SHIP CONSTRUCTION	Donegal	Drumacrin, Bundoran	42	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
428	428	SHIP CONSTRUCTION	Donegal	Gallow's Lane, Lifford	29	*N/A					Q4-2022	
429	429	SHIP CONSTRUCTION	Donegal	Chapel Road, Dungloe	45	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
430	430	SHIP CONSTRUCTION	Donegal	Kilmacrennan, Letterkenny	34	*N/A		Stage 2 approved Q2-2021, full design/tender being prepared.				
431	431	SHIP CONSTRUCTION	Donegal	Rockytown, Buncrana (Phase 2)	58	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
432	432	CAS CONSTRUCTION RENEWAL	Donegal	Cois Locha Dungloe	11	Cluid Housing Association					Q3-2020	
433	433	CAS CONSTRUCTION	Donegal	Glenrowan House, Drumkeen, Stranorlar	5	Apex Housing Association					Q4-2020	
434	434	CAS CONSTRUCTION	Donegal	Cois Locha, Meenmore, Dungloe	15	County Donegal Parents and Friends Housing Association Ltd						Q4-2022
435	435	CAS CONSTRUCTION	Donegal	Raphoe Road, Castlefinn	34	Habinteg Housing Association (Ireland) Ltd		Stage 2 approved Q3-2020, full design/tender being prepared.				
436	436	CALF Turnkey	Donegal	Ard na Gr�ine, Glencar Scotch, Letterkenny, Co. Donegal  (Phase 1)	12	Cl�id Housing					Q2-2021	
437	437	CALF Turnkey	Donegal	Ard na Gr�ine, Glencar Scotch, Letterkenny, Co. Donegal  (Phase 2)*	6	Cl�id Housing					Q2-2021	
438	438	CALF Turnkey	Donegal	Ballaghderg, Letterkenny, Co Donegal  (Phase 1)*	33	Respond						Q1-2021
439	439	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	113	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
440	440	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	87	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
441	441	SHIP DIALOG	Dublin City	O'Devaney Gardens - SH from Mixed Tenure Project	75	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
442	442	SHIP CONSTRUCTION TURNKEY	Dublin City	88-89 Drimnagh Road Dublin 12	24	*N/A						Q4-2022
443	443	SHIP CONSTRUCTION TURNKEY	Dublin City	St. Pancras, Harolds Cross, Dublin 6	4	*N/A						Q2-2021
444	444	SHIP CONSTRUCTION TURNKEY	Dublin City	Core 4, Block 4 Charlemont Square, Dublin 2	15	*N/A						Q2-2022
445	445	SHIP CONSTRUCTION TURNKEY	Dublin City	Moss Street/Gloucester Street, Dublin 2	21	*N/A						Q4-2022
446	446	SHIP CONSTRUCTION SINGLE STAGE	Dublin City	31 Croftwood Drive, Cherry Orchard, Dublin 10 	2	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
447	447	SHIP CONSTRUCTION RENEWAL	Dublin City	25 St James's Terrace, Dublin 8	1	*N/A						Q4-2022
448	448	SHIP CONSTRUCTION RENEWAL	Dublin City	77A The Coombe, Dublin 8	1	*N/A						Q4-2022
449	449	SHIP CONSTRUCTION RENEWAL	Dublin City	77 The Coombe, Dublin 8	1	*N/A						Q4-2022
450	450	SHIP CONSTRUCTION RENEWAL	Dublin City	27 Berryfield Road, Finglas, Dublin 11	1	*N/A						Q4-2022
451	451	SHIP CONSTRUCTION RENEWAL	Dublin City	51 Seville Place, North Dock, Dublin 1	1	*N/A						Q4-2022
452	452	SHIP CONSTRUCTION RENEWAL	Dublin City	78 The Coombe, Dublin 8	1	*N/A						Q4-2022
453	453	SHIP CONSTRUCTION RENEWAL	Dublin City	31 Cromcastle Drive, Kilmore West, Dublin 5	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
454	454	SHIP CONSTRUCTION RENEWAL	Dublin City	197 Larkhill Road, Dublin 9	1	*N/A						Q4-2022
455	455	SHIP CONSTRUCTION RENEWAL	Dublin City	4 Ravensdale Road, East Wall, Dublin 3	1	*N/A						Q4-2022
456	456	SHIP CONSTRUCTION RENEWAL	Dublin City	8 O'Dwyer Road, Walkinstown, Dublin 12	1	*N/A						Q4-2022
457	457	SHIP CONSTRUCTION RENEWAL	Dublin City	78 Ratoath Avenue, Finglas South, Dublin 11	1	*N/A						Q4-2022
458	458	SHIP CONSTRUCTION RENEWAL	Dublin City	6 St. Brendan's Park, Coolock, Dublin 5	1	*N/A						Q4-2022
459	459	SHIP CONSTRUCTION RENEWAL	Dublin City	66 Montpelier Hill, Stoneybatter, Dublin 7	1	*N/A						Q4-2022
460	460	SHIP CONSTRUCTION RENEWAL	Dublin City	466 South Circular Road, Dublin 8 - Apt. No's. 1, 2, 4 & 7	4	*N/A						Q4-2022
461	461	SHIP CONSTRUCTION RENEWAL	Dublin City	15 Parkview Green, Finglas, Dublin 11	1	*N/A						Q4-2022
462	462	SHIP CONSTRUCTION RENEWAL	Dublin City	175 Finglas Park, Finglas, Dublin 11	1	*N/A						Q4-2022
463	463	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Bunratty Road	78	*N/A					Q4-2019	
464	464	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Bonham Street Dublin  8 	57	*N/A					Q4-2019	
465	465	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Cork Street/Chamber Street Dublin 8	55	*N/A					Q1-2020	
466	466	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Springvale Chapelizod Dublin 8	71	*N/A					Q1-2020	
467	467	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	Cromcastle & Woodville, Coolock, Dublin 5	156	*N/A	Stage 1 approved Q1-2021, outline design and costs being prepared.					
468	468	SHIP CONSTRUCTION DESIGN BUILD	Dublin City	St. Andrews Court, Dublin 2	37	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.					
469	469	SHIP CONSTRUCTION	Dublin City	Cornamona, Ballyfermot, Dublin 12	61	*N/A					Q2-2019	
470	470	SHIP CONSTRUCTION	Dublin City	Infirmary Road, Dublin 7	38	*N/A			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
471	471	SHIP CONSTRUCTION	Dublin City	North King Street, - Sean Foster Place, Dublin 7	30	*N/A						Q4-2022
472	472	SHIP CONSTRUCTION	Dublin City	St. Finbar's Court, Kilkieran Road, Dublin 7	46	*N/A			Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.			
473	473	SHIP CONSTRUCTION	Dublin City	Dominick Street (East side)	72	*N/A						Q4-2022
474	474	SHIP CONSTRUCTION	Dublin City	O'Devaney Gardens - Phase 1A	56	*N/A						Q4-2022
475	475	SHIP CONSTRUCTION	Dublin City	Glin Court, Coolock, Dublin 17	32	*N/A			Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.			
476	476	SHIP CONSTRUCTION	Dublin City	Kildonan Road, Finglas, Dublin 11	75	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.					
477	477	SHIP CONSTRUCTION	Dublin City	Lands at Emmet Road	117	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
478	478	SHIP CONSTRUCTION	Dublin City	Sarsfield Lands, Sarsfield Road, Ballyfermot, Dublin 10	176	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
479	479	SHIP CONSTRUCTION	Dublin City	St. Anne's Court, All Saints Drive, Raheny, Dublin 5	102	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
480	480	REGENERATION	Dublin City	Dolphin House Phase 1b, Dolphins Barn, Rialto, Dublin 8	31	*N/A	Stage 1 approved Q4-2019, outline design and costs being prepared.					
481	481	REGENERATION	Dublin City	Dorset Street, Dublin 7	163	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
482	482	REGENERATION	Dublin City	Matt Talbot Court, Matt Talbot Street, Dublin 1	29	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
483	483	REGENERATION	Dublin City	Constitution Hill Dublin 7	46	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
484	484	REGENERATION	Dublin City	Pearse House, Sandwith Street Lower, Dublin 2 (Blocks L,M,N &P)	75	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
485	485	REGENERATION	Dublin City	Bluebell Phase 1A, Bluebell Road, Dublin 12	140	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
486	486	REGENERATION	Dublin City	School Street Thomas Court Bawn, The liberties, Dublin 8	115	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
487	487	REGENERATION	Dublin City	Oliver Bond House, Oliver Bond Street, Dublin 8	48	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
488	488	REGENERATION	Dublin City	Glovers Court, York Street, Dublin 2	50	N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
489	489	REGENERATION	Dublin City	Ballybough House Pilot Amalgamation Project	1	*N/A						Q3-2022
490	490	REGENERATION	Dublin City	Matt Talbot Court, Matt Talbot Street, Dublin 1	63	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
491	491	REGENERATION	Dublin City	Constitution Hill, Dublin 7	78	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
492	492	CAS CONSTRUCTION TURNKEY	Dublin City	Block 70, The Plaza, Parkwest, Dublin 12 	43	T�ath Housing Association Ltd						Q2-2022
493	493	CAS CONSTRUCTION TURNKEY	Dublin City	9-40 Walker Grove, Parkside, Dublin 13	32	T�ath Housing Association Ltd						Q3-2022
494	494	CAS CONSTRUCTION TURNKEY	Dublin City	Huband Road, Bluebell, Dublin 12	6	Tiglin Challenge				Stage 4 approved Q4-2022, the scheme is fully approved.		
495	495	CAS CONSTRUCTION TURNKEY	Dublin City	64-69 St James Court, Dublin 8	6	Peter McVerry Trust Ltd						Q4-2022
496	496	CAS CONSTRUCTION SINGLE STAGE	Dublin City	61 & 63 Rathoath Avenue, Finglas, Dublin 11	6	Arlington Novas Ireland Ltd						Q4-2022
497	497	CAS CONSTRUCTION RENEWAL	Dublin City	8 North Frederick Street, Dublin 1	12	Peter McVerry Trust Ltd						Q4-2021
498	498	CAS CONSTRUCTION RENEWAL	Dublin City	190 -192 Moore Haven, Drumcondra Road Upper, Dublin 9.	8	DePaul Housing				Stage 4 approved Q1-2022, the scheme is fully approved.		
499	499	CAS CONSTRUCTION RENEWAL	Dublin City	Unit A - D, 133 Upper Rathmines Road, Dublin 6	4	HAIL					Q4-2022	
500	500	CAS CONSTRUCTION RENEWAL	Dublin City	Units A-D, 14 Walkinstown Green, Dublin 12	4	HAIL					Q4-2022	
501	501	CAS CONSTRUCTION RENEWAL	Dublin City	Unit A-C, 340 Ballyfermot Road, Dublin 10	3	HAIL					Q4-2022	
502	502	CAS CONSTRUCTION	Dublin City	Ellis Court, Dublin	22	T�ath Housing Association Ltd						Q4-2022
503	503	CAS CONSTRUCTION	Dublin City	180-187 Townsend Street, Dublin 2	20	Peter McVerry Trust Ltd					Q4-2022	
504	504	CAS CONSTRUCTION	Dublin City	26 New Street South, Dublin 8	8	Peter McVerry Trust Ltd						Q1-2021
505	505	CAS CONSTRUCTION	Dublin City	55B Arbour Hill, Dublin 7	14	Simon Community : Dublin Simon				Stage 4 approved Q4-2022, the scheme is fully approved.		
506	506	CAS CONSTRUCTION	Dublin City	St. Michael's Estate, Inchicore, Dublin 8 - Housing Pilot Project 	52	Circle Voluntary Housing Association Ltd					Q3-2022	
507	507	CAS CONSTRUCTION	Dublin City	Shaw Street, Dublin 2	12	Peter McVerry Trust Ltd			Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.			
508	508	CAS CONSTRUCTION	Dublin City	13A Casement Drive, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
509	509	CAS CONSTRUCTION	Dublin City	Sarsfield Road, Ballyfermot, Dublin 10	6	Respond		Stage 2 approved Q1-2022, full design/tender being prepared.				
510	510	CAS CONSTRUCTION	Dublin City	25-26 Ushers Island Ushers Quay Dublin 8		Simon Community : Dublin Simon					Q4-2021	
511	511	CAS CONSTRUCTION	Dublin City	Barnamore Grove, Finglas, Dublin 11	2	Arlington Novas Ireland Ltd			Stage 3 approved Q4-2021, the scheme is now approved to proceed to tender.			
512	512	CAS CONSTRUCTION	Dublin City	88 Lower Drumcondra Road, Dublin 9 	6	Peter McVerry Trust Ltd	Stage 1 approved Q3-2020, outline design and costs being prepared.					
513	513	CAS CONSTRUCTION	Dublin City	5-7 Halston Street, Dublin 7	12	Peter McVerry Trust Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.					
514	514	CAS CONSTRUCTION	Dublin City	307a Casement Road, Finglas, Co. Dublin 	1	Arlington Novas Ireland Ltd			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
515	515	CAS CONSTRUCTION	Dublin City	29-30 Fishamble Street, Dublin 8	10	Peter McVerry Trust Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
516	516	CAS CONSTRUCTION	Dublin City	26-28 Upper Sherrard Street, Dublin 1	12	Peter McVerry Trust Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
517	517	PUBLIC PRIVATE PARTNERSHIP (Bundle 1)	Dublin City	Ayrfield, Malahide Road	150	*N/A						Q2-2021
518	518	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Ready Mix Site, East Wall, Dublin 3	68	*N/A			Q4-2022			
519	519	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Shangan Road, Ballymun, Dublin 9*	93	*N/A			Q4-2022			
520	520	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Dublin City	Collins Avenue, Whitehall, Dublin 9	83	*N/A			Q4-2022			
521	521	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Collins Avenue, Bring Centre, Dublin 9	99	N/A	Q2-2022					
522	522	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Marrowbone Lane/Forbes Lane (Depot)	78	N/A	Q2-2022					
523	523	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Basin View Flats	100	N/A	Q2-2022					
524	524	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Site 5 Ballymun - Main Street to the south of Santry Cross	56	N/A	Q2-2022					
525	525	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Sites 15, 16 and 17 Ballymun ? Balcurris	20	N/A	Q2-2022					
526	526	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Site 18 Ballymun - Balcurris	50	N/A	Q2-2022					
527	527	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Croke Villas	75	N/A	Q2-2022					
528	528	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Church of the Annunciation, Finglas	100	N/A	Q2-2022					
529	529	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Stanley Street (Depot)	110	N/A	Q2-2022					
530	530	PUBLIC PRIVATE PARTNERSHIP (Bundle 4)	Dublin City	Wellmount Road, Cardiffsbridge Road, Finglas	100	N/A	Q2-2022					
531	531	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dublin City	Barry Road, Finglas, Dublin 11	70	N/A	Q2-2022					
532	532	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Dublin City	Cherry Orchard Avenue, Ballyfermot, Dublin 10	100	N/A	Q2-2022					
533	533	CALF Turnkey	Dublin City	25-27 Bow Lane West, Dublin 8 (Phase 1)	27	Focus Housing Association CLG				Q1-2022		
534	534	CALF Turnkey	Dublin City	75 Old Cabra Road, Dublin 7  (Phase 1)	6	Circle Voluntary Housing Association Ltd						Q4-2022
535	535	CALF Turnkey	Dublin City	Aughrim Street, Stoneybatter, Dublin 7 (Phase 1)	4	Clanmil Housing Association Ireland						Q2-2021
536	536	CALF Construction	Dublin City	Bethany House, Gilford Road, Sandymount, Dublin 4 (Phase 1)	62	Cl�id Housing					Q4-2021	
537	537	CALF Turnkey	Dublin City	Blackbanks Vie5w, 754 Howth Road, Raheny, Dublin  (Phase 1)*	40	Cl�id Housing						Q1-2021
538	538	CALF Turnkey	Dublin City	Bluebell Avenue, Bluebell, Dublin 12 (Phase 1)*	52	Respond						Q2-2022
539	539	CALF Turnkey	Dublin City	Camac Park, Bluebell, Dublin 12 (Phase 1)	3	Tuath Housing Association						Q4-2021
540	540	CALF Turnkey	Dublin City	Chanel Manor Apartments, Coolock, Dublin 5. (Phase 1)*	65	Respond					Q2-2019	
541	541	CALF Turnkey	Dublin City	Chanel Manor, Coolock, Dublin 5 (Phase 1)*	22	Respond					Q4-2020	
542	542	CALF Turnkey	Dublin City	Charlemont Gate, Griffith Avenue, Dublin 9 (Phase 1)*	35	Cl�id Housing						Q2-2022
543	543	CALF Turnkey	Dublin City	Clonshaugh Road, Clonshaugh, Dublin 17 (Phase 1)	9	North and East Housing Association CLG						Q4-2022
544	544	CALF Turnkey	Dublin City	Connaught Street, Phibsborough, Dublin 7 (Phase 1)	20	Focus Housing Association CLG						Q4-2022
545	545	CALF Turnkey	Dublin City	Donnybrook Gardens, Lands of Greenfield Park, Donnybrook, Dublin 4 (Phase 1)*	4	RHD Housing						Q2-2021
546	546	CALF Turnkey	Dublin City	Elanora Court, Long Mile Road, Walkinstown, Dublin 12 (Phase 1)*	153	Respond					Q3-2020	
547	547	CALF Turnkey	Dublin City	Hillside Manor, Lucan Road, Chapelizod, Dublin 20 (Phase 1)*	30	Cl�id Housing					Q4-2020	
548	548	CALF Turnkey	Dublin City	Longboat Quay, Sir John Rogerson Quay, Dublin 2 (Phase 1)*	15	Tuath Housing Association						Q4-2022
549	549	CALF Turnkey	Dublin City	Newtown Cottages Malahide Road Coolock Dublin 17 (Phase 1)	3	Clanmil Housing Association Ireland						Q4-2022
550	550	CALF Construction	Dublin City	North Great Charles Street, Dublin 1 (Phase 1)	52	Cl�id Housing				Q4-2021		
551	551	CALF Construction	Dublin City	North King Street, Dublin 7  (Phase 1)	30	Co - Operative Housing Ireland Society Limited					Q4-2019	
552	552	CALF Turnkey	Dublin City	Park West Campus, Kileen Road, Dublin 12 (Phase 1)	43	Tuath Housing Association						Q2-2022
553	553	CALF Construction	Dublin City	"Railway Street, Dublin 1
 (Phase 1)"	47	Circle Voluntary Housing Association Ltd					Q3-2022	
554	554	CALF Turnkey	Dublin City	Ravensdale Court, Kimmage, Dublin 12. (Phase 1)	12	Tuath Housing Association						Q2-2022
555	555	CALF Turnkey	Dublin City	Richmond Avenue, Dublin 3 (Phase 1)	35	Focus Housing Association CLG				Q1-2022		
556	556	CALF Turnkey	Dublin City	St Canice?s Hall, Ballygall Road West, Finglas, Dublin 11 (Phase 1)*	32	Co - Operative Housing Ireland Society Limited						Q2-2021
557	557	SHIP DIALOG	Fingal	Killhedge Lane, Dun Emer, Lusk	7	*N/A						Q4-2022
558	558	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
559	559	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
560	560	SHIP DIALOG	Fingal	Ballymastone, Donabate	40	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
561	561	SHIP DIALOG	Fingal	Ballymastone, Donabate	30	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
562	562	SHIP CONSTRUCTION SINGLE STAGE	Fingal	Bowden Court (Outlands), Rathbeale Road, Swords	11	*N/A					Q1-2022	
563	563	SHIP CONSTRUCTION SINGLE STAGE	Fingal	50 Sheepmoor Avenue, Blanchardstown, D15	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
564	564	SHIP CONSTRUCTION SINGLE STAGE	Fingal	169a Clonsilla Road, Blanchardstown, Dublin 15	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
565	565	SHIP CONSTRUCTION RENEWAL	Fingal	St Ita's, Portrane Avenue, Protrane, Co. Dublin	3	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
566	566	SHIP CONSTRUCTION RENEWAL	Fingal	St Ita's, Portrane Avenue, Protrane, Co. Dublin	9	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
567	567	SHIP CONSTRUCTION	Fingal	Wellview	20	*N/A						Q4-2022
568	568	SHIP CONSTRUCTION	Fingal	Cappaghfinn, Cappagh Road Finglas - Phase 3	60	*N/A						Q4-2022
569	569	SHIP CONSTRUCTION	Fingal	Church Fields, Phase 2B, Mulhuddart, Dublin 15. - part 1	49	*N/A						Q4-2022
570	570	SHIP CONSTRUCTION	Fingal	Ballough PLace (Leonards Garage), Lusk	10	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
571	571	SHIP CONSTRUCTION	Fingal	Katie Hunt's Cottage, Church Road, Lusk	5	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
572	572	SHIP CONSTRUCTION	Fingal	30-32 North Street, Swords	13	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
573	573	SHIP CONSTRUCTION	Fingal	Seatown Apartments, Seatown Road, Swords	36	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
574	574	SHIP CONSTRUCTION	Fingal	Church Fields Phase 3, Mulhuddart, Dublin 15	40	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
575	575	SHIP CONSTRUCTION	Fingal	Church Fields, Phase 2B, Mulhuddart, Dublin 15  - part 2	18	*N/A					Q4-2021	
576	576	SHIP CONSTRUCTION	Fingal	Cappaghfinn, Cappagh Road Finglas - Phase 3	9	*N/A					Q1-2021	
577	577	CAS CONSTRUCTION RENEWAL	Fingal	44 Alderwood, Hollystown Dublin 15	5	Marillac Housing Association						Q4-2022
578	578	CAS CONSTRUCTION RENEWAL	Fingal	Abbeyglen, 47 Dublin Road, Swords	5	Praxis Housing Association						Q4-2022
579	579	CAS CONSTRUCTION	Fingal	Killhedge Lane Dun Emer	31	T�ath Housing Association Ltd				Stage 4 approved Q4-2022, the scheme is fully approved.		
580	580	CAS CONSTRUCTION	Fingal	22 College Street, Baldoyle	4	Cluid Housing Association						Q4-2021
581	581	CAS CONSTRUCTION	Fingal	Garristown	6	North ? East Housing Association Ltd		Stage 2 approved Q4-2020, full design/tender being prepared.				
582	582	CAS CONSTRUCTION	Fingal	63 Hollystown Park, Holystown, Dublin 15	5	Daughters Of Charity Of St Vincent De Paul						Q4-2021
583	583	CAS CONSTRUCTION	Fingal	Kenure Park, Rush, Co. Dublin	4	Prosper Fingal Housing Assocaition Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
584	584	CAS CONSTRUCTION	Fingal	Marian House, Convent Lane, Balbriggan, Co. Dublin	19	North ? East Housing Association Ltd	Stage 1 approved Q4-2022, outline design and costs being prepared.					
585	585	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 1)*	17	Tuath Housing Association						Q2-2021
586	586	CALF Turnkey	Fingal	Bellingsmore, Hollywoodrath, Dublin 15  (Phase 2)	21	Tuath Housing Association						Q4-2021
587	587	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 1)*	36	Tuath Housing Association						Q4-2022
588	588	CALF Turnkey	Fingal	Beresford, Oakstown, Donabate, Co. Dublin (Phase 2)*	4	Tuath Housing Association					Q3-2020	
589	589	CALF Turnkey	Fingal	Blackwood Square, Northwood Avenue, Santry Dublin 9 (Phase 1)*	33	Tuath Housing Association						Q4-2022
590	590	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 1)*	29	Respond						Q2-2021
591	591	CALF Turnkey	Fingal	Carrs Lane, Malahide Road, Dublin 17 (Phase 2)*	30	Respond						Q4-2021
592	592	CALF Turnkey	Fingal	Castleland Park, Castleland, Balbriggan, Co. Dublin. (Phase 1)	23	Tuath Housing Association						Q4-2022
593	593	CALF Turnkey	Fingal	Chapel Hill, Chapel Lane, Garristown, Co. Dublin (Phase 1)*	2	Clanmil Housing Association Ireland						Q4-2022
594	594	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 1)*	90	Respond						Q4-2021
595	595	CALF Turnkey	Fingal	Charlestown Centre, Charlestown Place & St., Margarets Road, Dublin 11 (Phase 2)*	48	Respond						Q4-2021
596	596	CALF Turnkey	Fingal	Cobbe Court, Portrane Road, Donabate, Co. Dublin (Phase 1)*	12	Tuath Housing Association						Q4-2022
597	597	CALF Turnkey	Fingal	Drynam Heath, Feltrim Road, Swords, Co. Dublin (Phase 2)*	6	Tuath Housing Association						Q2-2021
598	598	CALF Turnkey	Fingal	Dun Si, St Marnocks Bay, Portmarnock, Co Dublin  (Phase 1)*	18	Cl�id Housing					Q4-2020	
599	599	CALF Turnkey	Fingal	"Hansfield View, 7 Hansfield Square, Hansfield, Dublin 15.
(formerly Station View, Station Road, Dublin 15) (Phase 1)*"	22	Tuath Housing Association						Q4-2022
600	600	CALF Construction	Fingal	Ladyswell Road & Church Road, Mulhuddart, Dublin 15  (Phase 1)	65	Cl�id Housing						Q4-2021
601	601	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 1)*	14	Cl�id Housing						Q4-2021
602	602	CALF Turnkey	Fingal	Lusk Village, Lusk, Co. Dublin, Phase 2  (Phase 2)*	4	Cl�id Housing						Q3-2022
603	603	CALF Turnkey	Fingal	Mariners Way, Rush, Co. Dublin  (Phase 1)*	6	Respond					Q1-2020	
604	604	CALF Turnkey	Fingal	Mariners Way, Rush, Co. Dublin  (Phase 2)*	9	Respond					Q1-2020	
605	605	CALF Construction	Fingal	Old Coolock Lane, Santry, Dublin 9 (Phase 1)	28	Circle Voluntary Housing Association Ltd				Q1-2019		
606	606	CALF Turnkey	Fingal	Old Corduff Road, Blanchardstown, Dublin 15 (Phase 2)*	10	Respond						Q2-2021
607	607	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 1)	30	Respond				Q3-2021		
608	608	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 2)	30	Respond				Q3-2021		
609	609	CALF Turnkey	Fingal	Oldtown, Swords, Co Dublin (Phase 3)	39	Respond				Q3-2021		
610	610	CALF Turnkey	Fingal	Ravens Mill, Church Road, Rowlestown, Co. Dublin (Phase 1)*	38	Tuath Housing Association						Q4-2022
611	611	CALF Turnkey	Fingal	Riverwood Square, Porterstown, Dublin 15 (Phase 1)*	24	Cl�id Housing						Q3-2021
612	612	CALF Turnkey	Fingal	Semple Woods, Donabate, Co. Dublin (Phase 2)*	3	Tuath Housing Association					Q4-2019	
613	613	CALF Turnkey	Fingal	St Josephs, Clonsilla, Dublin 15 (Phase 1)*	28	Cl�id Housing						Q4-2021
614	614	CALF Turnkey	Fingal	Station Manor, Station Road, Portmarnock, Co. Dublin (Phase 2)*	8	Circle Voluntary Housing Association Ltd						Q4-2021
615	615	CALF Turnkey	Fingal	Taylor Hill, Balbriggan, Co. Dublin (Phase 1)*	7	Cl�id Housing						Q4-2021
616	616	SHIP CONSTRUCTION TURNKEY	Galway City	Garra� Caol, (Coast Road Site) Dublin Road	26	*N/A						Q4-2022
617	617	SHIP CONSTRUCTION TURNKEY	Galway City	Garra� Caol, (Coast Road Site) Dublin Road	22	*N/A					Q1-2020	
618	618	SHIP CONSTRUCTION RENEWAL	Galway City	Merchants Road Lower, Galway City	12	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
619	619	SHIP CONSTRUCTION	Galway City	An Cliath�n, Old Monivea Road, Ballybaan M�r	15	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
620	620	SHIP CONSTRUCTION	Galway City	Garra� Beag, Monivea Road, Ballybaan More	58	*N/A					Q1-2020	
621	621	SHIP CONSTRUCTION	Galway City	Keeraun, Ballymoneen Road	63	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
622	622	SHIP CONSTRUCTION	Galway City	211 Tirellan Heights, Headford Road	1	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
623	623	SHIP CONSTRUCTION	Galway City	Merlin Park Lands, Galway City	18	*N/A		Stage 2 approved Q2-2021, full design/tender being prepared.				
624	624	SHIP CONSTRUCTION	Galway City	1 Munster Avenue, Galway city	4	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
625	625	SHIP CONSTRUCTION	Galway City	Clybaun Road, Knocknacarra	28	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
626	626	SHIP Accel MMC	Galway City	Ballyburke, Knocknacarra, Galway City	90	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
627	627	CAS CONSTRUCTION	Galway City	Cul Garrai, Rahoon	6	Peter Triest Housing Association Ltd				Stage 4 approved Q3-2021, the scheme is fully approved.		
628	628	CAS CONSTRUCTION	Galway City	Doughiska, Galway City	7	Respond	Stage 1 approved Q2-2019, outline design and costs being prepared.					
629	629	CAS CONSTRUCTION	Galway City	111 Upper Newcastle Road, Galway City	10	Simon Community : North West Simon			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
630	630	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 1)	56	*N/A						Q2-2021
631	631	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Galway City	Ballyburke (Phase 2)	18	*N/A						Q3-2021
632	632	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 1)*	28	Respond					Q2-2021	
633	633	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 2)	24	Respond					Q2-2021	
634	634	CALF Turnkey	Galway City	Ballybanemor Road, Ballybrit, Galway (Phase 3)*	49	Respond					Q2-2021	
635	635	CALF Turnkey	Galway City	Briar Hill, Old Monivea Road, Ballybrit, Galway (Phase 1)	7	Co - Operative Housing Ireland Society Limited						Q2-2022
636	636	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City  (Phase 2)	10	Cl�id Housing						Q2-2021
637	637	CALF Turnkey	Galway City	Creig Ard, Roscam, Galway City, Co. Galway (Phase 1)*	17	Cl�id Housing						Q4-2021
638	638	CALF Turnkey	Galway City	Cuirt Bhoirne, Roscam, Co Galway (Phase 1)*	12	Cl�id Housing						Q4-2022
639	639	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 1)*	4	Tuath Housing Association						Q4-2021
640	640	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 2)*	3	Tuath Housing Association						Q3-2022
641	641	CALF Turnkey	Galway City	Fanan, Letteragh Road, Galway (Phase 3)*	3	Tuath Housing Association						Q4-2022
642	642	CALF Turnkey	Galway City	Gaelcarrig, Letteragh, Galway City (Phase 1)*	83	Respond						Q4-2022
643	643	CALF Turnkey	Galway City	Garrai Sheain, Roscam, Galway (Phase 1)	9	Co - Operative Housing Ireland Society Limited					Q2-2022	
644	644	CALF Turnkey	Galway City	Gleann Na Mona, Knocknacarra, Galway (Phase 1)*	16	Cl�id Housing						Q4-2022
645	645	CALF Turnkey	Galway City	Leana Mor, Cappagh Road, Galway (Phase 1)*	28	Respond					Q2-2021	
646	646	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 1)*	10	Cl�id Housing						Q3-2021
647	647	CALF Turnkey	Galway City	Letteragh Road, Rahoon, Galway City (Phase 2)	13	Cl�id Housing						Q4-2021
648	648	CALF Turnkey	Galway City	Phase 3 and 4 Cnocan Glas, Letteragh Road, Rahoon, Galway City (Phase 1)*	16	Cl�id Housing					Q1-2022	
649	649	CALF Turnkey	Galway City	Phase 3 and 4 Cnocan Glas, Letteragh Road, Rahoon, Galway City (Phase 2)*	25	Cl�id Housing					Q1-2022	
650	650	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	9	*N/A						Q1-2021
651	651	SHIP CONSTRUCTION TURNKEY	Galway County	Kylebroughlan, Moycullen 	10	*N/A						Q1-2021
652	652	SHIP CONSTRUCTION TURNKEY	Galway County	Garra� Mhic Aodha, Tubber Road, Gort	9	*N/A						Q4-2021
653	653	SHIP CONSTRUCTION TURNKEY	Galway County	Tullahill, Loughrea	9	*N/A						Q4-2021
654	654	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corr�n Eiscir Riada)	2	*N/A						Q4-2022
655	655	SHIP CONSTRUCTION TURNKEY	Galway County	Garra� Mhic Aodha, Tubber Road, Gort	18	*N/A						Q4-2021
656	656	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	14	*N/A						Q3-2022
657	657	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corr�n Eiscir Riada)	15	*N/A						Q4-2022
658	658	SHIP CONSTRUCTION TURNKEY	Galway County	Garra� Glas, Ballydavid South, Athenry	7	N/A						Q4-2022
659	659	SHIP CONSTRUCTION TURNKEY	Galway County	Gort an Choirce, Tubber Road, Gort	5	*N/A						Q2-2022
660	660	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	13	*N/A						Q4-2022
661	661	SHIP CONSTRUCTION TURNKEY	Galway County	Circular Road & Dublin Road, Tuam	8	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
662	662	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	15	*N/A						Q4-2022
663	663	SHIP CONSTRUCTION TURNKEY	Galway County	Cullairbaun, Athenry	16	*N/A					Q4-2021	
664	664	SHIP CONSTRUCTION TURNKEY	Galway County	Kilgarve, Ballinasloe	33	*N/A					Q3-2022	
665	665	SHIP CONSTRUCTION TURNKEY	Galway County	Limehill, Dunlo, Ballinasloe (Corr�n Eiscir Riada)	15	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
666	666	SHIP CONSTRUCTION TURNKEY	Galway County	Circular Road & Dublin Road Tuam	2	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
667	667	SHIP CONSTRUCTION TURNKEY	Galway County	Carraigweir, Tuam	4	*N/A						Q4-2022
668	668	SHIP CONSTRUCTION TURNKEY	Galway County	Lough na Carra, Williamstown	7	*N/A						Q4-2022
669	669	SHIP CONSTRUCTION TURNKEY	Galway County	Lough na Carra, Williamstown	7	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
670	670	SHIP CONSTRUCTION TURNKEY	Galway County	Apt 6 & 7 Ballydavid South, Athenry Co Galway 	2	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
671	671	SHIP CONSTRUCTION SINGLE STAGE	Galway County	Claremount, Oughterard	4	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
672	672	SHIP CONSTRUCTION RENEWAL	Galway County	Dunlo Hill, Ballinasloe	15	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
673	673	SHIP CONSTRUCTION	Galway County	Weir Road, Tuam	29	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
674	674	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	18	*N/A						Q4-2022
675	675	SHIP CONSTRUCTION	Galway County	Bridge Court, Ahascragh, Ballinasloe	18	*N/A					Q2-2022	
676	676	SHIP CONSTRUCTION	Galway County	Caisle�n Raithl�n, Ardrahan	10	*N/A		Stage 2 approved Q2-2019, full design/tender being prepared.				
677	677	SHIP CONSTRUCTION	Galway County	Barrack Street, Loughrea	5	*N/A						Q3-2021
678	678	SHIP CONSTRUCTION	Galway County	Garra� Ghuaire, Cartron, Kinvara	10	*N/A						Q4-2022
679	679	SHIP CONSTRUCTION	Galway County	Fana Bhu�, Tuam	16	*N/A						Q4-2021
680	680	SHIP CONSTRUCTION	Galway County	Cnoc na Carraige, Roundstone	6	*N/A						Q1-2021
681	681	SHIP CONSTRUCTION	Galway County	Ballyglass, Ardrahan (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
682	682	SHIP CONSTRUCTION	Galway County	Woodpark, Portumna (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
683	683	SHIP CONSTRUCTION	Galway County	Carrowmore West, Clontuskert, Ballinasloe (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
684	684	SHIP CONSTRUCTION	Galway County	Woodfield, Dunmore (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
685	685	SHIP CONSTRUCTION	Galway County	Knockaloura West, Brownsgrove, Tuam (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
686	686	SHIP CONSTRUCTION	Galway County	Creggaturlough, Craughwell (SRD)	1	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
687	687	SHIP CONSTRUCTION	Galway County	Gort na gCloch, Hospital Road, Clifden	8	*N/A						Q4-2022
688	688	SHIP CONSTRUCTION	Galway County	Fana Bhu�, Tuam	16	*N/A						Q4-2022
689	689	SHIP CONSTRUCTION	Galway County	Fana Bhu�, Tuam	16	*N/A						Q4-2022
690	690	SHIP CONSTRUCTION	Galway County	Ballymoe	8	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
691	691	SHIP CONSTRUCTION	Galway County	Droim na Gaoithe, Baile Chl�ir (Claregalway)	45	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
692	692	SHIP CONSTRUCTION	Galway County	Cosmona, Loughrea	40	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
693	693	SHIP CONSTRUCTION	Galway County	Barkhill, Woodford	2	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
694	694	SHIP CONSTRUCTION	Galway County	St. Joseph's, Ballinasloe	8	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
695	695	CAS CONSTRUCTION	Galway County	Letterfrack (Phase 2)	11	Cluid Housing Association						Q1-2022
696	696	CAS CONSTRUCTION	Galway County	Eanach Mheain, Carraroe	13	Tearmann Eanna Teoranta		Stage 2 approved Q4-2018, full design/tender being prepared.				
697	697	CAS CONSTRUCTION	Galway County	Mountbellew	5	T�ath Housing Association Ltd			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
698	698	CAS CONSTRUCTION	Galway County	Springfield, Parkmore, Ballinasloe	4	Peter Triest Housing Association Ltd		Stage 2 approved Q4-2021, full design/tender being prepared.				
699	699	CAS CONSTRUCTION	Galway County	Shannon Road, Portumna	4	Carraig Dubh Housing Association		Stage 2 approved Q1-2021, full design/tender being prepared.				
700	700	CALF Turnkey	Galway County	Cuil na Canalach, Ballinasloe, Co Galway (Phase 1)	7	Co - Operative Housing Ireland Society Limited						Q4-2022
701	701	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 1)	24	Cl�id Housing					Q1-2022	
702	702	CALF Turnkey	Galway County	Cuirt Dun Leo, Dunlo, Ballinasloe, Co Galway (Phase 2)	14	Cl�id Housing					Q1-2022	
703	703	CALF Turnkey	Galway County	Gort na Fuinse, Headford, Co. Galway (Phase 1)*	11	Cl�id Housing						Q4-2022
704	704	CALF Turnkey	Galway County	Gort na Fuinse, Headford, Co. Galway (Phase 2)	14	Cl�id Housing					Q2-2021	
705	705	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 2)	12	Cl�id Housing						Q1-2021
706	706	CALF Turnkey	Galway County	Riveroaks, Claregalway, Co Galway  (Phase 3)*	16	Cl�id Housing						Q2-2021
707	707	CALF Turnkey	Galway County	Vicars Choral, Tuam, Co Galway (Phase 1)	9	Co - Operative Housing Ireland Society Limited						Q4-2022
708	708	SHIP CONSTRUCTION TURNKEY	Kerry	Cnoc an Cairn, Chapel Lane, Dingle	2	*N/A						Q1-2022
709	709	SHIP CONSTRUCTION TURNKEY	Kerry	The Green, Ballinageragh, Lixnaw, Co Kerry	13	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
710	710	SHIP CONSTRUCTION TURNKEY	Kerry	Main Street, Ballyheigue	5	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
711	711	SHIP CONSTRUCTION TURNKEY	Kerry	Spa Road, Dingle	11	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
712	712	SHIP CONSTRUCTION TURNKEY	Kerry	44A, 44B & 46A Cnoc an Cairn, Dingle	3	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
713	713	SHIP CONSTRUCTION SINGLE STAGE	Kerry	SRD at Glannagilliagh, Caragh Lake, Killorglin	1	*N/A						Q2-2022
714	714	SHIP CONSTRUCTION SINGLE STAGE	Kerry	SRD at Carrigcannon, Lyreacrumpane	1	*N/A				Stage 4 approved Q3-2019, the scheme is fully approved.		
715	715	SHIP CONSTRUCTION SINGLE STAGE	Kerry	SRD at Rahinnane, Ventry	1	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
716	716	SHIP CONSTRUCTION DESIGN BUILD	Kerry	Rathmore/Barraduff	20	*N/A						Q2-2021
717	717	SHIP CONSTRUCTION	Kerry	Glenach, Ballybunion	20	*N/A						Q1-2021
718	718	SHIP CONSTRUCTION	Kerry	Lohercannon, Tralee	61	*N/A						Q4-2022
719	719	SHIP CONSTRUCTION	Kerry	Cullenagh Upper, Beaufort	1	*N/A						Q1-2021
720	720	SHIP CONSTRUCTION	Kerry	Farranwilliam, Ardfert	22	*N/A						Q3-2021
721	721	SHIP CONSTRUCTION	Kerry	Ballyrickard (Cluain na Geise), Tralee	21	*N/A						Q3-2022
722	722	SHIP CONSTRUCTION	Kerry	Croogorts, Tralee (Cruaghoirt)	30	*N/A						Q3-2022
723	723	SHIP CONSTRUCTION	Kerry	Rock Rd., Killarney	10	*N/A						Q2-2022
724	724	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 4)	14	*N/A						Q1-2021
725	725	SHIP CONSTRUCTION	Kerry	Baile an Gharra�, Lixnaw (Phase 2)	10	*N/A						Q2-2021
726	726	SHIP CONSTRUCTION	Kerry	Woodview Place, Tarbert	22	*N/A					Q2-2021	
727	727	SHIP CONSTRUCTION	Kerry	Marconi South, Ballybunion (Gl�r na Toinne)	14	*N/A					Q3-2021	
728	728	SHIP CONSTRUCTION	Kerry	Rahoonane, Tralee (New Site)	8	*N/A						Q3-2022
729	729	SHIP CONSTRUCTION	Kerry	Rusheen, Ballylongford (Carraig an Phoill)	7	*N/A					Q4-2021	
730	730	SHIP CONSTRUCTION	Kerry	Gortamullin, Kenmare (Phase 5) (Ard Bhearna)	14	*N/A					Q2-2022	
731	731	SHIP CONSTRUCTION	Kerry	Aras na Cluana (former Locke's Shop), Mitchel's Rd, Tralee 	8	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
732	732	SHIP CONSTRUCTION	Kerry	Marian Terrace, Ballyheigue	9	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
733	733	SHIP CONSTRUCTION	Kerry	6 Bridge Road, Abbeydorney	1	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
734	734	SHIP CONSTRUCTION	Kerry	Clogharesta Apartments Hawley Park,Tralee	16	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
735	735	SHIP CONSTRUCTION	Kerry	SRD at Emlaghmore, Caherciveen, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
736	736	SHIP CONSTRUCTION	Kerry	SRD at Garfinny, Dingle, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
737	737	SHIP CONSTRUCTION	Kerry	SRD at Gortadrislig, Lixnaw, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
738	738	SHIP CONSTRUCTION	Kerry	SRD at Kells, Caherciveen, Co Kerry	1	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
739	739	SHIP CONSTRUCTION	Kerry	Banshagh, Killorglin, Co. Kerry	80	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
740	740	SHIP Accel MMC	Kerry	Matt Talbot Road, Tralee	27	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
741	741	SHIP Accel MMC	Kerry	Garryruth, Tralee, Co Kerry	19	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
742	742	SHIP Accel MMC	Kerry	Lohercannon Phase 2, Tralee	94	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
743	743	SHIP Accel MMC	Kerry	Ballybeg, Dingle, Co Kerry	37	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
744	744	CAS CONSTRUCTION TURNKEY	Kerry	Firies Hall, Firies	14	Peter McVerry Trust Ltd						Q4-2022
745	745	CAS CONSTRUCTION TURNKEY	Kerry	Firies Hall, Firies	4	Peter McVerry Trust Ltd						Q4-2022
746	746	CAS CONSTRUCTION RENEWAL	Kerry	Ardmoneel, Killorglin, Co. Kerry	4	St. John of God Housing Association Ltd				Stage 4 approved Q2-2022, the scheme is fully approved.		
747	747	CAS CONSTRUCTION	Kerry	Armagh House, Killarney	6	Cluid Housing Association						Q1-2021
748	748	CAS CONSTRUCTION	Kerry	Chamfers Place (Mitchels road, Tralee)	18	Cluid Housing Association					Q2-2021	
749	749	CAS CONSTRUCTION	Kerry	Mary O'Donoghue Avenue, Cahirciveen, Co Kerry.	7	Caherciveen Social Services (Housing) Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
750	750	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 1)	28	Cl�id Housing						Q3-2022
751	751	CALF Turnkey	Kerry	Ard Na Greine, Knockavota, Milltown, Co. Kerry (Phase 2)*	26	Cl�id Housing						Q4-2022
752	752	CALF Turnkey	Kerry	Barraduff Phase 6, Killarney, Co Kerry  (Phase 1)	9	Co - Operative Housing Ireland Society Limited					Q2-2022	
753	753	CALF Turnkey	Kerry	Barraduff Phase 6, Killarney, Co Kerry  (Phase 2)*	16	Co - Operative Housing Ireland Society Limited					Q2-2022	
754	754	CALF Turnkey	Kerry	Barraduff, Killarney, Co Kerry (Phase 1)*	3	Co - Operative Housing Ireland Society Limited						Q2-2022
755	755	CALF Turnkey	Kerry	Barraduff, Killarney, Co. Kerry (Phase 4)*	13	Co - Operative Housing Ireland Society Limited						Q1-2021
756	756	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 1)*	12	Cl�id Housing						Q3-2022
757	757	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 2)	10	Cl�id Housing					Q3-2020	
758	758	CALF Turnkey	Kerry	Cahirdown Wood, Listowel, Co. Kerry (Phase 3)	16	Cl�id Housing					Q3-2020	
759	759	CALF Turnkey	Kerry	Cashen Court, Dun Alainn, Listowel, Co Kerry (Phase 1)	39	Co - Operative Housing Ireland Society Limited						Q4-2021
760	760	CALF Turnkey	Kerry	Dun Alainn, Listowel, Co. Kerry (Phase 1)*	10	Co - Operative Housing Ireland Society Limited						Q2-2022
761	761	CALF Turnkey	Kerry	 Dun Ard, Doon Road, Ballybunnion, Co Kerry (Phase 4)	1	Respond						Q2-2021
762	762	CALF Turnkey	Kerry	Hunters Lodge, Hunters Wood, Ballyseedy, Tralee, Co. Kerry (Phase 1)	10	Cl�id Housing					Q3-2021	
763	763	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 1)*	12	Co - Operative Housing Ireland Society Limited						Q3-2021
764	764	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 2)	8	Co - Operative Housing Ireland Society Limited						Q4-2021
765	765	CALF Turnkey	Kerry	Lawlors Hill, (formerly Commons East)  Ardfert, Co. Kerry (Phase 3)	10	Co - Operative Housing Ireland Society Limited						Q2-2022
766	766	CALF Turnkey	Kerry	Lios Ard, Lisloose, Tralee, Co. Kerry (Phase 1)	28	Cl�id Housing						Q3-2021
767	767	CALF Turnkey	Kerry	Moanmore, Pound Road, Castleisland, Co. Kerry (Phase 1)*	14	Cl�id Housing						Q4-2021
768	768	CALF Turnkey	Kerry	Orglan Heights, Ardmoneel, Killorglin (Phase 1)*	30	Cl�id Housing				Q3-2021		
769	769	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A						Q2-2021
770	770	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A						Q2-2021
771	771	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A						Q1-2021
772	772	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield, Clane	1	*N/A						Q2-2021
773	773	SHIP CONSTRUCTION TURNKEY	Kildare	Old Mill Race, Monasterevin	14	*N/A						Q4-2022
774	774	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	13	*N/A						Q3-2021
775	775	SHIP CONSTRUCTION TURNKEY	Kildare	Hemmingway Park, Clane	10	*N/A						Q4-2022
776	776	SHIP CONSTRUCTION TURNKEY	Kildare	Coolaghknock Green, Kildare Town	2	*N/A						Q2-2021
777	777	SHIP CONSTRUCTION TURNKEY	Kildare	Newtown, Ardclough Rd, Celbridge	26	*N/A						Q3-2022
778	778	SHIP CONSTRUCTION TURNKEY	Kildare	Kildare Road, Rathangan	9	*N/A					Q1-2021	
779	779	SHIP CONSTRUCTION TURNKEY	Kildare	Abbotsfield, Clane	2	*N/A						Q3-2021
780	780	SHIP CONSTRUCTION TURNKEY	Kildare	The Willows, Allenwood	1	*N/A						Q4-2021
781	781	SHIP CONSTRUCTION TURNKEY	Kildare	Fitzgerald Close, Greenfield, Maynooth	1	*N/A						Q4-2021
782	782	SHIP CONSTRUCTION TURNKEY	Kildare	Williams Grove, Ardclough	2	*N/A						Q4-2021
783	783	SHIP CONSTRUCTION TURNKEY	Kildare	Millstream Court, Kilcullen	1	*N/A						Q4-2021
784	784	SHIP CONSTRUCTION TURNKEY	Kildare	Newtown, Ardclough Rd, Celbridge	23	*N/A						Q4-2022
785	785	SHIP CONSTRUCTION TURNKEY	Kildare	Harristown Drive, Kildangan	1	*N/A						Q4-2022
786	786	SHIP CONSTRUCTION TURNKEY	Kildare	Hillfort Drive, Kill, Kildare	6	*N/A						Q4-2022
787	787	SHIP CONSTRUCTION TURNKEY	Kildare	An Lumann, Straffan	2	*N/A						Q4-2022
788	788	SHIP CONSTRUCTION SINGLE STAGE	Kildare	Patrician Avenue, Naas	2	*N/A				Stage 4 approved Q3-2021, the scheme is fully approved.		
789	789	SHIP CONSTRUCTION SINGLE STAGE	Kildare	Shamrock Stores, Geraldine Rd, Athy	2	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
790	790	SHIP CONSTRUCTION RENEWAL	Kildare	25 St. Corbans Place, Naas 	1	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
791	791	SHIP CONSTRUCTION RENEWAL	Kildare	1 Maddenstown Terrace, The Curragh, Kildare	1	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
792	792	SHIP CONSTRUCTION	Kildare	Athgarvan Village	18	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
793	793	SHIP CONSTRUCTION	Kildare	Newtown House, Leixlip	4	*N/A		Stage 2 approved Q2-2020, full design/tender being prepared.				
794	794	SHIP CONSTRUCTION	Kildare	Coill Dubh	10	*N/A					Q4-2022	
795	795	SHIP CONSTRUCTION	Kildare	Ardclough Road, Celbridge	39	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
796	796	SHIP CONSTRUCTION	Kildare	Ambassador Site, Kill	33	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
797	797	SHIP CONSTRUCTION	Kildare	Carbury	5	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.					
798	798	SHIP CONSTRUCTION	Kildare	St. Evins Park Monasterevin	16	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.					
799	799	SHIP CONSTRUCTION	Kildare	Castle Park, Athy	5	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
800	800	SHIP CONSTRUCTION	Kildare	Old Caragh Road, Nass	58	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
801	801	SHIP Accel MMC	Kildare	Old Greenfield Road, Maynooth	65	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
802	802	CAS CONSTRUCTION	Kildare	Craddockstown, Naas	3	KARE Promoting Inclusion for People with Intellectual Disabilities		Stage 2 approved Q2-2018, full design/tender being prepared.				
803	803	CAS CONSTRUCTION	Kildare	El Kantara, Newbridge	3	KARE Promoting Inclusion for People with Intellectual Disabilities			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
804	804	CAS CONSTRUCTION	Kildare	Jigginstown House, Naas	12	Homeless Care Ltd						Q2-2021
805	805	CAS CONSTRUCTION	Kildare	St. John's Convent, New Street, Rathangan	27	Sophia Housing Association Ltd	Stage 1 approved Q4-2019, outline design and costs being prepared.					
806	806	CAS CONSTRUCTION	Kildare	Dominican Lands, Athy	34	Cluid Housing Association		Stage 2 approved Q2-2022, full design/tender being prepared.				
807	807	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Kildare	Butterstream, Clane	77	*N/A						Q4-2021
808	808	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Kildare	Ardrew, Athy, Co. Kildare	73	*N/A			Q4-2022			
809	809	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Kildare	Oldtown Mill, Celbridge	57	N/A	Q2-2022					
810	810	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Kildare	Collaghknock Glebe, Kildare Town	85	N/A	Q2-2022					
811	811	CALF Turnkey	Kildare	1 unit, Loughlion Green, Kildare Town (Phase 1)	1	Co - Operative Housing Ireland Society Limited						Q3-2021
812	812	CALF Turnkey	Kildare	15 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	15	Cl�id Housing						Q4-2021
813	813	CALF Turnkey	Kildare	2 units, Ledwill Park, Kilcock, Co. Kildare (Phase 1)	2	Cl�id Housing						Q4-2021
814	814	CALF Turnkey	Kildare	Baille Park, Old Dublin Road,  Celbridge, Co. Kildare (Phase 1)	6	Co - Operative Housing Ireland Society Limited					Q4-2020	
815	815	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 1)*	13	Tuath Housing Association						Q4-2022
816	816	CALF Turnkey	Kildare	Belin Woods, Newbridge, Co. Kildare (Phase 2)*	21	Tuath Housing Association						Q4-2022
817	817	CALF Construction	Kildare	Castlefen, Castlesize, Sallins, Co. Kildare (Phase 1)	29	Tuath Housing Association						Q3-2022
818	818	CALF Turnkey	Kildare	Elsmore Place, Whitethorn Village, Naas, Co. Kildare (Phase 1)*	12	Tuath Housing Association						Q4-2022
819	819	CALF Turnkey	Kildare	Elsmore, Jigginstown and Oakpark, Craddockstown, Naas, Kildare (Phase 2)*	17	Tuath Housing Association						Q4-2021
820	820	CALF Construction	Kildare	Flinters Field, Athy, Co. Kildare (Phase 1)	23	Respond					Q1-2021	
821	821	CALF Construction	Kildare	Flinters Field, Athy, Co. Kildare (Phase 2)	12	Respond					Q1-2021	
822	822	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 1)*	21	Cl�id Housing						Q1-2021
823	823	CALF Turnkey	Kildare	Grand Canal Wood, Allenwood, Co. Kildare (Phase 2)	19	Cl�id Housing						Q2-2021
824	824	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 1 (Phase 1)*	4	Cl�id Housing						Q1-2021
825	825	CALF Turnkey	Kildare	Kilbelin Abbey, Kildare, Phase 2 (Phase 1)*	4	Cl�id Housing					Q2-2019	
826	826	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	27	Cl�id Housing						Q3-2021
827	827	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	3	Cl�id Housing						Q4-2021
828	828	CALF Turnkey	Kildare	Ledwill Park, Kilcock, Co. Kildare (Phase 1)*	20	Cl�id Housing						Q4-2022
829	829	CALF Turnkey	Kildare	Leinster Square, Dublin Street, Kildare Town, Co Kildare (Phase 1)*	4	Clanmil Housing Association Ireland						Q3-2021
830	830	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 3)*	16	Co - Operative Housing Ireland Society Limited						Q1-2021
831	831	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 4)	16	Co - Operative Housing Ireland Society Limited						Q2-2021
832	832	CALF Turnkey	Kildare	Loughlion, Kildare Town, Kildare (Phase 5)*	16	Co - Operative Housing Ireland Society Limited						Q3-2021
833	833	CALF Turnkey	Kildare	Main Street, Prosperous, Clane, Co. Kildare (Phase 1)*	16	Clanmil Housing Association Ireland					Q4-2020	
834	834	CALF Turnkey	Kildare	Mariavilla, Maynooth, Co. Kildare (Phase 1)*	11	Tuath Housing Association						Q4-2021
835	835	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 1)*	15	Tuath Housing Association						Q4-2022
836	836	CALF Turnkey	Kildare	Mullen Park and Carton Grove, Maynooth, Co. Kildare (Phase 2)*	12	Tuath Housing Association					Q4-2019	
837	837	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 1)*	13	Tuath Housing Association					Q4-2020	
838	838	CALF Turnkey	Kildare	Newtown, Kill, Co. Kildare (Phase 2)*	2	Tuath Housing Association					Q4-2020	
839	839	CALF Turnkey	Kildare	Oak Park, Naas, Co. Kildare (Phase 1)	26	Tuath Housing Association						Q4-2022
840	840	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 1)	30	Cl�id Housing						Q4-2022
841	841	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 2)	24	Cl�id Housing					Q2-2021	
842	842	CALF Turnkey	Kildare	Riverside Green, Riverside Manor, Kilcullen, Co. Kildare (Phase 3)*	10	Cl�id Housing					Q2-2021	
843	843	CALF Turnkey	Kildare	The Court (Block A) Westfield, Green Lane, Leixlip, Co. Kildare (Phase 1)*	20	Respond						Q4-2022
844	844	CALF Turnkey	Kildare	The Paddocks, Morristown, Newbridge, Kildare (Phase 3)*	16	Cl�id Housing						Q2-2021
845	845	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 1)	26	Cl�id Housing						Q3-2021
846	846	CALF Turnkey	Kildare	The Paddocks, Newbridge, Kildare  (Phase 2)	33	Cl�id Housing						Q4-2021
847	847	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 1)*	18	Respond						Q2-2021
848	848	CALF Turnkey	Kildare	The Vestry, Glebelands, Athy, Co. Kildare (Phase 3) (Phase 1)	20	Respond					Q4-2019	
849	849	CALF Turnkey	Kildare	Tinnycross Park, Ballymore Eustace, Co. Kildare (Phase 1)*	4	Tuath Housing Association						Q4-2022
850	850	CALF Turnkey	Kildare	Tinnycross Park, Ballymore Eustace, Co. Kildare (Phase 2)*	5	Tuath Housing Association					Q3-2021	
851	851	CALF Turnkey	Kildare	Walkers Gate, Kildare Town, Co. Kildare (Phase 1)*	10	Tuath Housing Association						Q4-2022
852	852	CALF Turnkey	Kildare	Walkers Gate, Kildare Town, Co. Kildare (Phase 2)*	30	Tuath Housing Association					Q3-2021	
853	853	CALF Turnkey	Kildare	Westfield, Leixlip, Co. Kildare (Phase 1)*	20	Respond						Q4-2021
854	854	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 1)*	12	Tuath Housing Association						Q4-2021
855	855	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 2)*	4	Tuath Housing Association						Q4-2021
856	856	CALF Turnkey	Kildare	Whitethorn, Naas, Co. Kildare (Phase 3)*	4	Tuath Housing Association						Q3-2022
857	857	SHIP CONSTRUCTION TURNKEY	Kilkenny	New Road, Mooncoin	4	*N/A						Q4-2022
858	858	SHIP CONSTRUCTION TURNKEY	Kilkenny	Chapel Street, Mooncoin	2	*N/A						Q4-2022
859	859	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Court, Hebron Road, Kilkenny	8	*N/A						Q1-2022
860	860	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Green, Hebron Road, Kilkenny	26	*N/A						Q1-2022
861	861	SHIP CONSTRUCTION TURNKEY	Kilkenny	Blackwater Grove, Kilmacow	14	*N/A						Q2-2021
862	862	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank	5	*N/A						Q4-2021
863	863	SHIP CONSTRUCTION TURNKEY	Kilkenny	Piltown, Kilkenny	4	*N/A					Q2-2021	
864	864	SHIP CONSTRUCTION TURNKEY	Kilkenny	Limegrove, Ferrybank	10	*N/A						Q1-2022
865	865	SHIP CONSTRUCTION TURNKEY	Kilkenny	Pennefeather Green, Hebron Road, Kilkenny	26	*N/A						Q2-2022
866	866	SHIP CONSTRUCTION TURNKEY	Kilkenny	Marnellsmeadows, Callan Road, Kilkenny	20	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
867	867	SHIP CONSTRUCTION TURNKEY	Kilkenny	Abbeygate, Ferrybank	21	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
868	868	SHIP CONSTRUCTION TURNKEY	Kilkenny	Berkely Drive, Mount Sion Road, Ferrybank	5	*N/A						Q4-2022
869	869	SHIP CONSTRUCTION TURNKEY	Kilkenny	Old Creamery Site, Kilmacow	8	*N/A					Q2-2022	
870	870	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Inchacarron, Mullinavat	2	*N/A						Q4-2022
871	871	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Shanganny, Jenkinstown	2	*N/A						Q2-2022
872	872	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	6	*N/A						Q2-2021
873	873	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Old Fire Station, Graiguenamanagh	2	*N/A						Q4-2022
874	874	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Ayrfield, Granges Road, Kilkenny	2	*N/A						Q1-2022
875	875	SHIP CONSTRUCTION SINGLE STAGE	Kilkenny	Haggardsgreen, Callan	1	*N/A					Q2-2022	
876	876	SHIP CONSTRUCTION RENEWAL	Kilkenny	18 Wolfe Tone Street, Kilkenny	1	*N/A					Q3-2022	
877	877	SHIP CONSTRUCTION	Kilkenny	10 Golf Links Road, Kilkenny	6	*N/A					Q1-2022	
878	878	SHIP CONSTRUCTION	Kilkenny	Station Road, Ballyragget	22	*N/A						Q2-2021
879	879	SHIP CONSTRUCTION	Kilkenny	Donaguile, Castlecomer	33	*N/A						Q2-2021
880	880	SHIP CONSTRUCTION	Kilkenny	The Broguemaker, Kilkenny	18	*N/A						Q2-2021
881	881	SHIP CONSTRUCTION	Kilkenny	Ladywell, Thomastown	25	*N/A					Q4-2021	
882	882	SHIP CONSTRUCTION	Kilkenny	Crokers Hill, Kennyswell Road, Kilkenny	88	*N/A					Q4-2022	
883	883	SHIP CONSTRUCTION	Kilkenny	Canal Road, Johnstown - Project 1	5	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.					
884	884	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstow - Project 2	2	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.					
885	885	SHIP CONSTRUCTION	Kilkenny	Canal Road Johnstown - Project 3	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.					
886	886	SHIP CONSTRUCTION	Kilkenny	Ladywell, Newtown, Thomastown	33	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
887	887	SHIP CONSTRUCTION	Kilkenny	Weather Station, Granges Road, Kilkenny	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
888	888	CAS CONSTRUCTION TURNKEY	Kilkenny	Tinnypark, Callan Road, Kilkenny	6	SOS Kilkenny Housing Association Ltd						Q3-2022
889	889	CAS CONSTRUCTION TURNKEY	Kilkenny	70-71 Upper Patrick Street, Kilkenny	4	Clanmill Housing Association Ireland				Stage 4 approved Q1-2022, the scheme is fully approved.		
890	890	CAS CONSTRUCTION SINGLE STAGE	Kilkenny	Miltown Lodge Phase 2, Johnswell Road, Kilkenny	1	SOS Kilkenny Housing Association Ltd						Q2-2022
891	891	CAS CONSTRUCTION	Kilkenny	Kingsriver, Ennisnag	2	Kingsriver Housing Association Limited						Q2-2022
892	892	CAS CONSTRUCTION	Kilkenny	19/21 Blackmill Street, Kilkenny	12	Good Shepherd Services Ltd					Q4-2021	
893	893	CAS CONSTRUCTION	Kilkenny	Brother Thomas Place, Church Lane, Kilkenny	12	Good Shepherd Services Ltd						Q3-2022
894	894	CAS CONSTRUCTION	Kilkenny	Grennan Villa, Thomastown	5	Camphill Communities of Ireland						Q3-2022
895	895	CAS CONSTRUCTION	Kilkenny	St. John of God Convent, College Road, Kilkenny	21	Sophia Housing Association Ltd	Stage 1 approved Q1-2022, outline design and costs being prepared.					
896	896	CAS CONSTRUCTION	Kilkenny	Mill Street, Callan	12	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.					
897	897	CAS CONSTRUCTION	Kilkenny	Prague House Hall, Freshford	4	Kilkenny Voluntary Housing Association	Stage 1 approved Q2-2021, outline design and costs being prepared.					
898	898	CALF Turnkey	Kilkenny	Cois Na Bearu, Graiguenemanagh, Kilkenny (Phase 1)	14	Co - Operative Housing Ireland Society Limited						Q1-2021
899	899	CALF Turnkey	Kilkenny	Margaret?s Field, Callan Road, Kilkenny City (Phase 1)	40	Respond						Q2-2021
900	900	CALF Turnkey	Kilkenny	Orchard Close, Kilkenny (Phase 1)*	23	Cl�id Housing						Q3-2022
901	901	SHIP CONSTRUCTION TURNKEY	Laois	Priory, Borris in Ossory	5	*N/A						Q3-2022
902	902	SHIP CONSTRUCTION TURNKEY	Laois	Church Avenue, Stradbally	20	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
903	903	SHIP CONSTRUCTION TURNKEY	Laois	Bruach Na Habhainn, Killeen, Maganey	3	*N/A						Q1-2022
904	904	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	2	N/A						Q1-2022
905	905	SHIP CONSTRUCTION TURNKEY	Laois	Market Square, Portarlington	18	N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
906	906	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	2	*N/A						Q4-2022
907	907	SHIP CONSTRUCTION TURNKEY	Laois	Church Avenue, Stradbally	11	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
908	908	SHIP CONSTRUCTION TURNKEY	Laois	Bruach Na Habhainn, Killeen, Maganey	1	*N/A				Stage 4 approved Q3-2021, the scheme is fully approved.		
909	909	SHIP CONSTRUCTION TURNKEY	Laois	The Orchard, Ballylynan	1	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
910	910	SHIP CONSTRUCTION SINGLE STAGE	Laois	Coolroe, Ballybrittas	1	*N/A						Q2-2022
911	911	SHIP CONSTRUCTION RENEWAL	Laois	Iona,Abbeyleix Rd., Portlaoise	7	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
912	912	SHIP CONSTRUCTION RENEWAL	Laois	Oldcourt Ballylynan	1	N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
913	913	SHIP CONSTRUCTION	Laois	Moore Street, Rathdowney	6	*N/A					Q3-2020	
914	914	SHIP CONSTRUCTION	Laois	Ballymorris Road, Portarlington	22	*N/A						Q2-2021
915	915	SHIP CONSTRUCTION	Laois	Gleann na Glaise, Ballyroan	10	*N/A						Q3-2022
916	916	SHIP CONSTRUCTION	Laois	Pattison Est. Mountmellick	10	*N/A						Q4-2022
917	917	SHIP CONSTRUCTION	Laois	Shannon Street, Mountrath	6	*N/A						Q2-2021
918	918	SHIP CONSTRUCTION	Laois	Harbour Court, Mountmellick	6	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
919	919	SHIP CONSTRUCTION	Laois	Mooreville, Rathdowney	7	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
920	920	SHIP CONSTRUCTION	Laois	Sean Doire, Cork Road, Durrow	22	*N/A						Q4-2022
921	921	SHIP CONSTRUCTION	Laois	St Kieran's Park, Errill	14	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
922	922	SHIP CONSTRUCTION	Laois	Clonrooske, Knockmay	12	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
923	923	SHIP CONSTRUCTION	Laois	Carraig Glas, Stradbally	26	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
924	924	SHIP CONSTRUCTION	Laois	Ballyadams	1	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
925	925	SHIP CONSTRUCTION	Laois	Doonane	12	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
926	926	SHIP CONSTRUCTION	Laois	Durrow	18	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
927	927	SHIP CONSTRUCTION	Laois	15 Units at Bracklone Street, Portarlington	15	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
928	928	SHIP CONSTRUCTION	Laois	Moanbaun, Mountrath 	15	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
929	929	CAS CONSTRUCTION	Laois	Presentation Convent & Lands, Portlaoise, 	52	Sophia Housing Association Ltd			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
930	930	CAS CONSTRUCTION	Laois	County Hotel, Portlaoise	10	Cluid Housing Association	Stage 1 approved Q3-2020, outline design and costs being prepared.					
931	931	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 1)	34	Cl�id Housing					Q2-2021	
932	932	CALF Turnkey	Laois	Ballymorris Green, Portarlington, Co Laois (Phase 2)	12	Cl�id Housing					Q2-2021	
933	933	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 4)*"	9	Cl�id Housing						Q1-2021
934	934	CALF Turnkey	Laois	"Bellingham, Portlaoise
 (Phase 5)*"	6	Cl�id Housing						Q3-2021
935	935	CALF Turnkey	Laois	Borris Road, Portlaoise, Co. Laois (Phase 4)	9	Tuath Housing Association						Q1-2021
936	936	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 1)	14	Cl�id Housing						Q4-2022
937	937	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 2)*	12	Cl�id Housing					Q4-2018	
938	938	CALF Turnkey	Laois	Clonroosk Abbey, Portlaoise, Co. Laois (Phase 3)	6	Cl�id Housing					Q4-2018	
939	939	CALF Turnkey	Laois	Doirin Alainn, Ballylinan, Co. Laois (Phase 1)	9	North and East Housing Association CLG						Q4-2022
940	940	CALF Turnkey	Laois	Doirinn Alainn, Ballylynan, Co. Laois (Phase 3)*	6	North and East Housing Association CLG						Q2-2021
941	941	CALF Turnkey	Laois	Droughill Lawn, Portarlington, Co. Laois (Phase 1)*	26	Oaklee Housing						Q2-2022
942	942	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 1)	13	Cl�id Housing						Q4-2022
943	943	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 2)	16	Cl�id Housing					Q3-2021	
944	944	CALF Turnkey	Laois	Goldencroft, Portlaoise, Co. Laois (Phase 3)	38	Cl�id Housing					Q3-2021	
945	945	CALF Turnkey	Laois	Harpurs Lane, Portlaoise, Co. Laois (Phase 1)*	44	Respond					Q2-2021	
946	946	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 1)	10	Cl�id Housing						Q3-2021
947	947	CALF Turnkey	Laois	Holdbrook, Portlaoise, Co. Laois (Phase 2)	10	Cl�id Housing						Q4-2022
948	948	CALF Turnkey	Laois	Lake Drive, Kilminchy, Portlaoise, Co. Laois (Phase 1)	10	Co - Operative Housing Ireland Society Limited						Q2-2021
949	949	CALF Turnkey	Laois	Phase 2 The Glen, Kilnacourt, Portarlington, Co Laois (Phase 1)	18	Co - Operative Housing Ireland Society Limited						Q2-2021
950	950	CALF Turnkey	Laois	Phase 3 The Glen, Kilnacourt, Portarlington, Co Laois. (Phase 1)	8	Co - Operative Housing Ireland Society Limited						Q3-2021
951	951	CALF Construction	Laois	Radharc Darach, Ballyfin Road, Portlaoise, Co. Laois (Phase 1)	54	Cl�id Housing				Q2-2022		
952	952	CALF Turnkey	Laois	Rathillion, Killeshin, Co. Laois (Phase 1)*	4	Co - Operative Housing Ireland Society Limited						Q2-2021
953	953	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 1)*	15	Cl�id Housing						Q3-2022
954	954	CALF Turnkey	Laois	The Maltings and Roselawn, Portlaoise, Co. Laois (Phase 2)*	40	Cl�id Housing						Q4-2022
955	955	CALF Turnkey	Laois	The Meadows, Mountrath Road, Portlaoise, Co. Laois (Phase 1)*	48	Cl�id Housing					Q1-2022	
956	956	CALF Turnkey	Laois	The Springs, Kilminchy, Portlaoise, Co Laois (Phase 1)*	43	Cl�id Housing						Q4-2022
957	957	SHIP CONSTRUCTION TURNKEY	Leitrim	Church Lane, Ballinamore	9	*N/A						Q4-2021
958	958	SHIP CONSTRUCTION TURNKEY	Leitrim	Druminshingore, Newtowngore	2	*N/A						Q4-2021
959	959	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	5	*N/A						Q4-2022
960	960	SHIP CONSTRUCTION TURNKEY	Leitrim	Ard na Drise, Mohill	2	*N/A						Q1-2021
961	961	SHIP CONSTRUCTION TURNKEY	Leitrim	Lough Meen Estate, Drumkeerin	2	*N/A						Q4-2021
962	962	SHIP CONSTRUCTION TURNKEY	Leitrim	Commons Lane, Manorhamilton	4	*N/A						Q4-2022
963	963	SHIP CONSTRUCTION TURNKEY	Leitrim	Cluain Oir, Liscara, Carrick on Shannon	2	*N/A						Q2-2021
964	964	SHIP CONSTRUCTION TURNKEY	Leitrim	Manorhamilton & Carrigallen	2	*N/A						Q3-2021
965	965	SHIP CONSTRUCTION TURNKEY	Leitrim	Druminshingore Td., Newtowngore	3	*N/A						Q2-2022
966	966	SHIP CONSTRUCTION TURNKEY	Leitrim	Lisnagot, Carrick on Shannon	3	*N/A						Q4-2022
967	967	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	8	*N/A						Q4-2022
968	968	SHIP CONSTRUCTION TURNKEY	Leitrim	Carraig Breac, Drumshanbo	4	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
969	969	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Breffni Cres., 53 St. Patricks Park Site, Carrick on Shannon	2	*N/A						Q4-2022
970	970	SHIP CONSTRUCTION SINGLE STAGE	Leitrim	Dromahair Td., Dromahair	4	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
971	971	SHIP CONSTRUCTION RENEWAL	Leitrim	Sean McDermott St., Manorhamilton	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
972	972	SHIP CONSTRUCTION	Leitrim	Autumn View, Summerhill, Carrick on Shannon	27	*N/A						Q4-2021
973	973	SHIP CONSTRUCTION	Leitrim	Taobh Tire, Manorhamilton (Phase 3)	5	*N/A					Q1-2022	
974	974	SHIP CONSTRUCTION	Leitrim	Pairceanna an Bhaile, Townparks, Carrick on Shannon	7	*N/A						Q4-2022
975	975	SHIP CONSTRUCTION	Leitrim	Lahard, Ballinamore	10	*N/A					Q2-2022	
976	976	SHIP CONSTRUCTION	Leitrim	Kilboderry Td., Carrick on Shannon	18	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
977	977	SHIP CONSTRUCTION	Leitrim	Pairceanna an Bhaile, Townparks, Carrick on Shannon	5	*N/A					Q1-2022	
978	978	SHIP CONSTRUCTION TURNKEY	Limerick	Redgate Close, Old Cratloe Road, Limerick City	13	*N/A						Q3-2022
979	979	SHIP CONSTRUCTION TURNKEY	Limerick	Gortboy, Charleville Road, KiImallock	24	*N/A						Q1-2022
980	980	SHIP CONSTRUCTION TURNKEY	Limerick	Knocklong	4	*N/A						Q4-2022
981	981	SHIP CONSTRUCTION TURNKEY	Limerick	Gortboy, Charleville Road, KiImallock	9	*N/A						Q4-2022
982	982	SHIP CONSTRUCTION TURNKEY	Limerick	Broad Street, Limerick	13	*N/A						Q4-2022
983	983	SHIP CONSTRUCTION TURNKEY	Limerick	Laurelville, Mill Rd, Corbally	2	*N/A						Q4-2022
984	984	SHIP CONSTRUCTION TURNKEY	Limerick	Woodfield Manor, Cloonyscrehane, Newcastlewest	17	*N/A						Q4-2022
985	985	SHIP CONSTRUCTION TURNKEY	Limerick	8 Maypole Crescent, Knocklong, Co Limerick	1	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
986	986	SHIP CONSTRUCTION TURNKEY	Limerick	Knocklong	1	N/A					Q2-2021	
987	987	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 14 Marian Place Janesboro	1	N/A						Q4-2022
988	988	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 24 Shanabooley Road, Ballynanty Beg, Limerick	1	N/A					Q4-2022	
989	989	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 31 Shanabooley Road, Ballynanty Beg, Limerick	1	N/A					Q3-2022	
990	990	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 5 Bishops Street, St Marys Parish	1	N/A						Q4-2022
991	991	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 79 Lenihan Avenue, Prospect, Limerick	1	N/A					Q3-2022	
992	992	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 85 O' Dwyers Villas Thomondgate, Limerick	1	N/A					Q4-2022	
993	993	SHIP CONSTRUCTION RENEWAL	Limerick	LOT 2: 9 Downey Street, Killalee, Limerick	1	N/A						Q4-2022
994	994	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 17 Cedar Court , Kennedy Park, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
995	995	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 19 Br Cill Mhuire, Garryowen, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
996	996	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 2 Quinns Cottages Rosbrien Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
997	997	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 23, Monabraher Road, Ballynanty Beg, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
998	998	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 26 Clarke Avenue, Janesboro, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
999	999	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 3 Walnut Court Kennedy Park. Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1000	1000	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 30 Island Road, Blank, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1001	1001	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 4 Oakley Lawn, Caherconlish, County Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1002	1002	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 4 St Mary's Terrace Ballinacurra Road Ballinacurra, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1003	1003	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 44 Greenhill Rd., Garryowen, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1004	1004	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 5 Clonconane Road, Ballynanty Beg, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1005	1005	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 6 Raheen Sq. Ballinacurra Weston, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1006	1006	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: 7 Aster Court, Keyes Park, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1007	1007	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 3: Roseville, Janesboro, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1008	1008	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 15 Churchview Askeaton County Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1009	1009	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 24 St Marys Park Rathkeale County Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1010	1010	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 5 Fairgreen Tce Bruff County Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1011	1011	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 9 St Munchins Tce Bruree  County Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1012	1012	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 20 Sharwood, Newcastle West, Co Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1013	1013	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 19 Kylefea, Croom, Co Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1014	1014	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 2 Fairview Cottages, Mulgrave Street, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1015	1015	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 6 Chestnut Court, Kennedy Park, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1016	1016	SHIP CONSTRUCTION RENEWAL	Limerick	Lot 5: 273 Hyde Road, Prospect, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1017	1017	SHIP CONSTRUCTION DESIGN BUILD	Limerick	Old Christians Site, Rathbane	43	*N/A						Q2-2021
1018	1018	SHIP CONSTRUCTION DESIGN BUILD	Limerick	Barnakyle, Patrickswell (Site 2)	24	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1019	1019	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhill Road 	14	*N/A						Q1-2022
1020	1020	SHIP CONSTRUCTION	Limerick	Gough Place, Rosbrien Road, Limerick	17	*N/A						Q4-2022
1021	1021	SHIP CONSTRUCTION	Limerick	Clonmacken, Limerick City	43	*N/A					Q3-2019	
1022	1022	SHIP CONSTRUCTION	Limerick	Deerpark, Adare	13	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1023	1023	SHIP CONSTRUCTION	Limerick	Glenview Drive, Hospital	20	*N/A					Q3-2020	
1024	1024	SHIP CONSTRUCTION	Limerick	Clare Street, Limerick City	7	*N/A					Q1-2022	
1025	1025	SHIP CONSTRUCTION	Limerick	Lower Carey's Road, Limerick City	11	*N/A						Q1-2021
1026	1026	SHIP CONSTRUCTION	Limerick	Kileely Road, Moyross	5	*N/A						Q2-2021
1027	1027	SHIP CONSTRUCTION	Limerick	Station Close, Knocklong	12	*N/A						Q4-2022
1028	1028	SHIP CONSTRUCTION	Limerick	Ballysimon, Greenhills Road	3	*N/A						Q1-2022
1029	1029	SHIP CONSTRUCTION	Limerick	Clueing Dara, Broadford	11	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1030	1030	SHIP CONSTRUCTION	Limerick	Sycamore Crescent, Newcastle West, Co Limerick	21	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1031	1031	SHIP CONSTRUCTION	Limerick	Radharc an Ghleanna, Mountcollins	4	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1032	1032	SHIP CONSTRUCTION	Limerick	O?Connor Park, Ardagh, Co. Limerick	10	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1033	1033	SHIP CONSTRUCTION	Limerick	Church Glen, Ballylanders, Co. Limerick	9	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1034	1034	SHIP CONSTRUCTION	Limerick	Radharc Cillin, Kilfinane, Co. Limerick	10	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
1035	1035	SHIP CONSTRUCTION	Limerick	Brugh na Deise, Bruff, Co Limerick	17	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1036	1036	SHIP CONSTRUCTION	Limerick	(Formerly Whelan's Pub), 52 New Road, Thomandgate, Limerick	6	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1037	1037	SHIP CONSTRUCTION	Limerick	Deerpark, Adare	18	*N/A		Stage 2 approved Q4-2020, full design/tender being prepared.				
1038	1038	SHIP CONSTRUCTION	Limerick	Sycamore Crescent, Newcastle West, Co Limerick	10	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1039	1039	SHIP CONSTRUCTION	Limerick	Meadowbrook, Mill Rd, Limerick	7	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1040	1040	SHIP CONSTRUCTION	Limerick	Mulchaire Drive, Annacotty, Co Limerick.	6	N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1041	1041	SHIP CONSTRUCTION	Limerick	Clueing Dara, Broadford	8	N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1042	1042	SHIP Accel MMC	Limerick	Ballycummin Road, Raheen, Co. Limerick	19	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1043	1043	REGENERATION	Limerick	Sheep / Athlunkards Street	8	T�ath Housing Association Ltd					Q4-2022	
1044	1044	REGENERATION	Limerick	Churchfield	37	Cluid Housing Association					Q1-2022	
1045	1045	REGENERATION	Limerick	Cosgrave Park	30	*N/A					Q1-2022	
1046	1046	REGENERATION	Limerick	Orchard Site	27	Oaklee Housing Trust			Stage 3 approved Q2-2021, the scheme is now approved to proceed to tender.			
1047	1047	REGENERATION	Limerick	Cliona Park Phase 3	18	T�ath Housing Association Ltd					Q4-2021	
1048	1048	REGENERATION	Limerick	45A-46A Cliona Park	2	*N/A						Q3-2021
1049	1049	REGENERATION	Limerick	Dalgaish Park	27	*N/A					Q1-2022	
1050	1050	REGENERATION	Limerick	Cliona Park Phase 4	20	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1051	1051	REGENERATION	Limerick	Lot 4: 1 Collins Avenue, Kincora Park, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1052	1052	REGENERATION	Limerick	Lot 4: 14 Lenihan Avenue Prospect, Limerick Derelict Sites, Limerick,	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1053	1053	REGENERATION	Limerick	Lot 4: 25 Lenihan Avenue Prospect, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1054	1054	REGENERATION	Limerick	Lot 4: 28 Crecora Avenue Ballinacurra Weston, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1055	1055	REGENERATION	Limerick	Lot 4: 57 Ash Avenue John Carew Park, Limerick Derelict Sites, Limerick,	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1056	1056	REGENERATION	Limerick	Lot 4: 108 Cosgrave Park, Moyross, Limerick Derelict Sites, Limerick,	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1057	1057	REGENERATION	Limerick	Lot 4: 11 St Colmcille Street St Marys Park. Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1058	1058	REGENERATION	Limerick	Lot 4: 9 St Colmcille Street St Marys Park, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1059	1059	REGENERATION	Limerick	Lot 4: 11 Aster Court, Limerick	1	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1060	1060	CAS CONSTRUCTION TURNKEY	Limerick	1-6 New Road, Thomondgate, Limerick	6	Peter McVerry Trust Ltd				Stage 4 approved Q4-2022, the scheme is fully approved.		
1061	1061	CAS CONSTRUCTION	Limerick	Towerfield Crescent, Croom	16	Croom Voluntary Housing Association Ltd			Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.			
1062	1062	CAS CONSTRUCTION	Limerick	Cappamore (Creamery Site)	10	Cappamore Housing Association Ltd			Stage 3 approved Q3-2021, the scheme is now approved to proceed to tender.			
1063	1063	CAS CONSTRUCTION	Limerick	Mirth, Thomondgate	18	Associated Charities Trust Ltd					Q3-2022	
1064	1064	CAS CONSTRUCTION	Limerick	2/3 Mallow Street	12	Peter McVerry Trust Ltd				Stage 4 approved Q4-2022, the scheme is fully approved.		
1065	1065	CAS CONSTRUCTION	Limerick	St. Pauls Convent, Kilfinane	9	Sophia Housing Association Ltd			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1066	1066	CAS CONSTRUCTION	Limerick	McGarry House, 7 Alphonsus Street	8	Arlington Novas Ireland Ltd			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
1067	1067	CAS CONSTRUCTION	Limerick	47 & 48 Main Street, Croom, Limerick	5	Croom Voluntary Housing Association Ltd				Stage 4 approved Q3-2022, the scheme is fully approved.		
1068	1068	CAS CONSTRUCTION	Limerick	58 Henry Street, Limerick	5	Simon Community : Midwest Simon			Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.			
1069	1069	CAS CONSTRUCTION	Limerick	Ballygrennan Close, Moyross (7 units)	7	Respond	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1070	1070	CAS CONSTRUCTION	Limerick	Infills Carew Park, Southhill and Moyross	14	Peter McVerry Trust Ltd						Q4-2022
1071	1071	CAS CONSTRUCTION	Limerick	28/29 Lower Gerald Griffin Street, Limerick	4	Peter McVerry Trust Ltd			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
1072	1072	CAS CONSTRUCTION	Limerick	42 St Joseph's Street, Limerick	4	Peter McVerry Trust Ltd		Stage 2 approved Q4-2022, full design/tender being prepared.				
1073	1073	CAS CONSTRUCTION	Limerick	Quinns Cross, Skehacreggaun, Mungret, Limerik.	35	Cluid Housing Association	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1074	1074	CAS CONSTRUCTION	Limerick	Nunan's Corner, Tullaha, Broadford, Co Limerick	7	Broadford Voluntary Housing and Community Childcare CLG	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1075	1075	CAS CONSTRUCTION	Limerick	Sisters Of Mercy Convent, Doon, Co Limerick	23	Ballyhoura Rural Services CLG		Stage 2 approved Q4-2022, full design/tender being prepared.				
1076	1076	CAS CONSTRUCTION	Limerick	Infills Carew Park, Southhill and Moyross	24	Peter McVerry Trust Ltd				Stage 4 approved Q1-2020, the scheme is fully approved.		
1077	1077	CAS CONSTRUCTION	Limerick	Athea, Galeside	4	Athea Voluntary Housing CLG			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1078	1078	CAS CONSTRUCTION	Limerick	Cloverfield, Glin, Co Limerick	10	Glin Homes for the Elderly Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1079	1079	CAS CONSTRUCTION	Limerick	Gortmore, Feenagh, Co Limerick	8	Corran ? Deel Voluntary Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1080	1080	CALF Turnkey	Limerick	2 units, Castleview Shopping Centre Castleconnell  Limerick (Phase 1)	2	Focus Housing Association CLG						Q4-2021
1081	1081	CALF Construction	Limerick	3 Focus Units in County Limerick (Phase 1)	3	Focus Housing Association CLG				Q3-2022		
1082	1082	CALF Turnkey	Limerick	Baunacloka Heights, Mungret Gate, Mungret, Co. Limerick (Phase 2)*	25	Co - Operative Housing Ireland Society Limited						Q2-2021
1083	1083	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 1)*	52	Co - Operative Housing Ireland Society Limited						Q4-2021
1084	1084	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 2)	32	Co - Operative Housing Ireland Society Limited						Q4-2022
1085	1085	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 3)	10	Co - Operative Housing Ireland Society Limited						Q4-2022
1086	1086	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 4)*	19	Co - Operative Housing Ireland Society Limited						Q4-2022
1087	1087	CALF Turnkey	Limerick	Bloodmill Road, Singland, Limerick (Phase 5)	24	Co - Operative Housing Ireland Society Limited						Q4-2022
1088	1088	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 1)*	35	Co - Operative Housing Ireland Society Limited						Q4-2021
1089	1089	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 2)	12	Co - Operative Housing Ireland Society Limited						Q2-2022
1090	1090	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 3)*	29	Co - Operative Housing Ireland Society Limited						Q4-2022
1091	1091	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 4)*	12	Co - Operative Housing Ireland Society Limited						Q4-2022
1092	1092	CALF Turnkey	Limerick	Clonmacken, Condell Road, Limerick (Phase 5)*	22	Co - Operative Housing Ireland Society Limited						Q4-2022
1093	1093	CALF Turnkey	Limerick	Dromsally Woods, Cappamore, Co. Limerick (Phase 1)	5	Focus Housing Association CLG						Q4-2022
1094	1094	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 1)	8	Cl�id Housing						Q2-2021
1095	1095	CALF Turnkey	Limerick	Mungret Gate, Baunacloka, Mungret, Limerick (Phase 2)*	23	Cl�id Housing						Q2-2022
1096	1096	CALF Turnkey	Limerick	Newtown, Castletroy, Limerick (Phase 1)*	31	Cl�id Housing					Q3-2022	
1097	1097	CALF Turnkey	Limerick	Old Dublin Road, Rhebogue, Limerick (Phase 1)*	16	Focus Housing Association CLG						Q2-2022
1098	1098	CALF Turnkey	Limerick	Phase 2 Newtown Meadows, Castletroy, Limerick (Phase 1)*	32	Cl�id Housing					Q4-2022	
1099	1099	CALF Turnkey	Limerick	The Orchard, Main Street, Pallaskenry, Co Limerick (Phase 1)	10	Focus Housing Association CLG					Q2-2019	
1100	1100	CALF Turnkey	Limerick	The Orchard, Main Street, Pallaskenry, Co Limerick (Phase 2)	6	Focus Housing Association CLG					Q2-2019	
1101	1101	CALF Turnkey	Limerick	Toormore, Main Street, Bruree, Co. Limerick (Phase 1)	16	Cl�id Housing						Q2-2021
1102	1102	CALF Construction	Limerick	Turragh Crescent, Cappamore, Limerick (Phase 1)	15	Cl�id Housing				Q3-2021		
1103	1103	CALF Turnkey	Limerick	Woodfield Manor, Cloonyscrehane, Newcastle West, Co Limerick (Phase 1)*	11	Cl�id Housing						Q4-2022
1104	1104	SHIP CONSTRUCTION TURNKEY	Longford	Sl� Corglass, Legga	4	*N/A						Q1-2021
1105	1105	SHIP CONSTRUCTION TURNKEY	Longford	Richmond St., Longford Town	23	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1106	1106	SHIP CONSTRUCTION TURNKEY	Longford	Farnagh Hill, Longford Town	8	*N/A						Q1-2021
1107	1107	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	6	*N/A						Q3-2021
1108	1108	SHIP CONSTRUCTION TURNKEY	Longford	O'Hara Site, (St Michael's Court) Connaught Rd.,Longford 	14	*N/A						Q4-2022
1109	1109	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	4	*N/A						Q4-2021
1110	1110	SHIP CONSTRUCTION TURNKEY	Longford	Sl� Corglass, Legga	4	*N/A						Q2-2021
1111	1111	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	4	*N/A						Q2-2021
1112	1112	SHIP CONSTRUCTION TURNKEY	Longford	Sl� Corglass, Legga	1	*N/A						Q3-2021
1113	1113	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	5	*N/A						Q2-2021
1114	1114	SHIP CONSTRUCTION TURNKEY	Longford	St. Patricks Ct., Ballinamuck	8	*N/A						Q4-2022
1115	1115	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	12	N/A						Q3-2021
1116	1116	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane	6	N/A						Q4-2021
1117	1117	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	4	N/A						Q4-2021
1118	1118	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	3	N/A						Q4-2021
1119	1119	SHIP CONSTRUCTION TURNKEY	Longford	Alder Field, Farnagh Hill	1	N/A						Q4-2022
1120	1120	SHIP CONSTRUCTION TURNKEY	Longford	Campbell?s Lane, Longford Town	2	N/A						Q4-2022
1121	1121	SHIP CONSTRUCTION TURNKEY	Longford	Caislean Breac, Newtownforbes	2	*N/A						Q3-2022
1122	1122	SHIP CONSTRUCTION TURNKEY	Longford	Forthill, Aughnacliffe	13	N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1123	1123	SHIP CONSTRUCTION TURNKEY	Longford	Farrells , Ballinalee	4	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1124	1124	SHIP CONSTRUCTION TURNKEY	Longford	Woodlawn Path, Keenagh	5	N/A					Q3-2022	
1125	1125	SHIP CONSTRUCTION TURNKEY	Longford	Longford Rd., Ballinalee	14	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1126	1126	SHIP CONSTRUCTION SINGLE STAGE	Longford	2 Legion Terrace, Longford 	4	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1127	1127	SHIP CONSTRUCTION SINGLE STAGE	Longford	Woodview, Newtownforbes	2	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1128	1128	SHIP CONSTRUCTION	Longford	'Rose Cottage', Ballinalee	6	*N/A						Q4-2021
1129	1129	SHIP CONSTRUCTION	Longford	St.Rita's, Park Road, Longford	11	*N/A		Stage 2 approved Q1-2020, full design/tender being prepared.				
1130	1130	SHIP CONSTRUCTION	Longford	Fairgreen View, Longford Town	1	*N/A						Q2-2021
1131	1131	SHIP CONSTRUCTION	Longford	Cranleymore, Abbeylara	3	*N/A			Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.			
1132	1132	SHIP CONSTRUCTION	Longford	Cloonahard, Edgeworthstown	1	*N/A						Q2-2021
1133	1133	SHIP CONSTRUCTION	Longford	Woodlands Path, Keenagh	4	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1134	1134	SHIP CONSTRUCTION	Longford	Clough Dillons, Keenagh	4	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
1135	1135	SHIP CONSTRUCTION	Longford	Radharc Na Muileann, Lanesborough	10	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1136	1136	SHIP CONSTRUCTION	Longford	24B Congress Terrace, Longford	2	N/A			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
1137	1137	SHIP CONSTRUCTION	Longford	Cnoc Na Gr�ine, Granard	6	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1138	1138	SHIP CONSTRUCTION	Longford	Radharc Na Muileann, Lanesborough	12	N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1139	1139	SHIP CONSTRUCTION	Longford	Lamagh, Newtownforbes 	6	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1140	1140	CAS CONSTRUCTION	Longford	Comcille Terrace, Granard 	11	T�ath Housing Association Ltd			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1141	1141	CALF Construction	Longford	Colmcille Terrace, Granard, Co Longford (Phase 1)	8	Tuath Housing Association				Q3-2022		
1142	1142	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	10	*N/A						Q1-2021
1143	1143	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	9	*N/A						Q2-2021
1144	1144	SHIP CONSTRUCTION TURNKEY	Louth	?Gort Bui?, Ballymakenny Road, Drogheda	8	*N/A						Q2-2021
1145	1145	SHIP CONSTRUCTION TURNKEY	Louth	Glyde View, Tallanstown	2	*N/A						Q2-2021
1146	1146	SHIP CONSTRUCTION TURNKEY	Louth	Termon River, Termonfeckin	1	*N/A						Q4-2021
1147	1147	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	8	*N/A						Q4-2022
1148	1148	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A					Q1-2022	
1149	1149	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	5	*N/A					Q1-2022	
1150	1150	SHIP CONSTRUCTION TURNKEY	Louth	Ellwood, Ballymakenny Road, Drogheda	17	*N/A					Q1-2022	
1151	1151	SHIP CONSTRUCTION TURNKEY	Louth	Tullybrook Place, Slane Road, Drogheda	3	*N/A						Q4-2022
1152	1152	SHIP CONSTRUCTION TURNKEY	Louth	Cuirt Na Gcloch, Stoneylane, Ardee	14	*N/A						Q4-2022
1153	1153	SHIP CONSTRUCTION TURNKEY	Louth	Park Green, Coulter Place, Armagh Road, Dundalk	24	N/A						Q4-2022
1154	1154	SHIP CONSTRUCTION SINGLE STAGE	Louth	Moneymore, Drogheda	1	*N/A					Q2-2020	
1155	1155	SHIP CONSTRUCTION SINGLE STAGE	Louth	Gort Uaine, Clogherhead	1	*N/A					Q3-2020	
1156	1156	SHIP CONSTRUCTION SINGLE STAGE	Louth	School Lane, Dunleer	1	*N/A					Q3-2020	
1157	1157	SHIP CONSTRUCTION SINGLE STAGE	Louth	Doire Beag, Collon	6	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1158	1158	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 5 - Dundalk	1	*N/A						Q1-2021
1159	1159	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 6	1	*N/A						Q1-2021
1160	1160	SHIP CONSTRUCTION RENEWAL	Louth	CPO Bundle 7	3	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1161	1161	SHIP CONSTRUCTION	Louth	Boice Court (Phase 2), Drogheda	72	*N/A			Stage 3 approved Q2-2022, the scheme is now approved to proceed to tender.			
1162	1162	SHIP CONSTRUCTION	Louth	Father Finn Park (Phase 2)	17	*N/A						Q2-2021
1163	1163	SHIP CONSTRUCTION	Louth	Mount Avenue, Dundalk	93	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1164	1164	SHIP CONSTRUCTION	Louth	Muirhevnamor, Dundalk (Phase 1)	11	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1165	1165	SHIP CONSTRUCTION	Louth	Rathmullen Park, Drogheda	6	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1166	1166	REGENERATION	Louth	Cox's Demesne Phase 2b	22	*N/A						Q3-2022
1167	1167	CAS CONSTRUCTION TURNKEY	Louth	Liscorrie, Bog Road, Drogheda	12	T�ath Housing Association Ltd						Q2-2021
1168	1168	CAS CONSTRUCTION RENEWAL	Louth	Kincora House	8	Peter McVerry Trust Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1169	1169	CAS CONSTRUCTION RENEWAL	Louth	3 Paradise Place, Drogheda, Co. Louth	4	Peter McVerry Trust Ltd	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1170	1170	CAS CONSTRUCTION	Louth	5 Slieveroe Crescent, Dundalk	1	Cluid Housing Association						Q4-2021
1171	1171	CAS CONSTRUCTION	Louth	Barrack Street, Dundalk	30	Simon Community : Dundalk Simon		Stage 2 approved Q4-2022, full design/tender being prepared.				
1172	1172	CAS CONSTRUCTION	Louth	Coulter Park, Dundalk	10	T�ath Housing Association Ltd			Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.			
1173	1173	CAS CONSTRUCTION	Louth	Four Winds, Mullacapple, Collon	4	St. John of God Housing Association Ltd						Q3-2022
1174	1174	CAS CONSTRUCTION	Louth	St. John's Home, Peter's Hill, Drogheda	4	North ? East Housing Association Ltd			Stage 3 approved Q3-2020, the scheme is now approved to proceed to tender.			
1175	1175	CAS CONSTRUCTION	Louth	Highfield, Newry Road, Dundalk	12	Women's Aid (Dundalk) CLG	Stage 1 approved Q2-2020, outline design and costs being prepared.					
1176	1176	CAS CONSTRUCTION	Louth	10-16 The Alleys, St. Peter's Place, Drogheda	14	Peter McVerry Trust Ltd		Stage 2 approved Q2-2022, full design/tender being prepared.				
1177	1177	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Louth	Ballymakenny East	80	N/A	Q2-2022					
1178	1178	CALF Turnkey	Louth	Bellewsbridge Road, Dundalk, Co. Louth (Phase 1)	5	Circle Voluntary Housing Association Ltd						Q4-2022
1179	1179	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 1)*	16	Tuath Housing Association						Q1-2021
1180	1180	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 2)	10	Tuath Housing Association						Q2-2021
1181	1181	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 3)	16	Tuath Housing Association						Q4-2021
1182	1182	CALF Turnkey	Louth	Cathedral View, Ramparts, Dundalk, Co. Louth (Phase 4)	11	Tuath Housing Association						Q4-2021
1183	1183	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 1)	12	Cl�id Housing						Q1-2021
1184	1184	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 2)*	15	Cl�id Housing						Q3-2021
1185	1185	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 3)	15	Cl�id Housing						Q4-2021
1186	1186	CALF Turnkey	Louth	Clonmore Close, Ardee, Co. Louth (Phase 4)	13	Cl�id Housing						Q4-2021
1187	1187	CALF Turnkey	Louth	Connolly Field, Dundalk, Co. Louth (Phase 1)*	30	Fold Housing Association Ireland Ltd				Q2-2022		
1188	1188	CALF Turnkey	Louth	Connolly Field, Dundalk, Co. Louth (Phase 2)	40	Fold Housing Association Ireland Ltd				Q2-2022		
1189	1189	CALF Turnkey	Louth	Donore Road, Drogheda, Co. Louth (Phase 1)	66	Cl�id Housing					Q2-2021	
1190	1190	CALF Turnkey	Louth	Drybridge, Drogheda, Co. Louth (Phase 1)	16	North and East Housing Association CLG					Q1-2022	
1191	1191	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth (Phase 1)*	49	Respond					Q4-2020	
1192	1192	CALF Turnkey	Louth	Dublin Road, Dundalk, Co. Louth (Phase 2)	16	Respond					Q4-2020	
1193	1193	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 1)*	47	Cl�id Housing						Q4-2022
1194	1194	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 2)	14	Cl�id Housing					Q4-2020	
1195	1195	CALF Turnkey	Louth	Duiche Roden (formerly The Kitchen Garden)Desmesne Road, Dundalk, Co. Louth (Phase 3)	69	Cl�id Housing					Q4-2020	
1196	1196	CALF Turnkey	Louth	Fairways Gardens, Dundalk Co Louth (Phase 1)	8	Cl�id Housing						Q4-2021
1197	1197	CALF Turnkey	Louth	Halliday Mills, Quay Street, Dundalk, Co. Louth (Phase 1)*	85	Co - Operative Housing Ireland Society Limited						Q4-2021
1198	1198	CALF Turnkey	Louth	Harbour View, Coulter Place, Dundalk (Phase 1)	24	Cl�id Housing						Q3-2021
1199	1199	CALF Turnkey	Louth	Lismullen Grove, Dundalk, Co. Louth (Phase 2)	8	Tuath Housing Association						Q1-2021
1200	1200	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 1)*	55	Cl�id Housing						Q1-2022
1201	1201	CALF Turnkey	Louth	Newfoundwell Road, Drogheda, Co Louth (Phase 2)	39	Cl�id Housing					Q3-2020	
1202	1202	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 1)*	17	Respond					Q4-2020	
1203	1203	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 2)*	23	Respond					Q4-2020	
1204	1204	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 3)*	46	Respond					Q4-2020	
1205	1205	CALF Turnkey	Louth	Newtown, Marsh Road, Drogheda, Co. Louth (Phase 4)*	47	Respond					Q4-2020	
1206	1206	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 2)"	10	Tuath Housing Association						Q2-2022
1207	1207	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 3)*"	13	Tuath Housing Association						Q4-2022
1208	1208	CALF Turnkey	Louth	"Racecourse Meadows, Dundalk, Co. Louth - Tuathduiche
 (Phase 4)*"	12	Tuath Housing Association					Q1-2019	
1209	1209	CALF Turnkey	Louth	Tierney Street, Ardee, Co. Louth (Phase 1)	11	Circle Voluntary Housing Association Ltd					Q3-2021	
1210	1210	CALF Turnkey	Louth	Tullybrook, Drogheda, Co. Louth  (Phase 1)*	85	Cl�id Housing					Q1-2021	
1211	1211	SHIP CONSTRUCTION TURNKEY	Mayo	Bunree, Ballina	3	*N/A						Q4-2022
1212	1212	SHIP CONSTRUCTION TURNKEY	Mayo	Silver Springs, Claremorris	20	*N/A						Q4-2022
1213	1213	SHIP CONSTRUCTION TURNKEY	Mayo	Main St., Charlestown	2	*N/A						Q4-2021
1214	1214	SHIP CONSTRUCTION TURNKEY	Mayo	Aidan St., Kiltimagh	2	N/A						Q4-2022
1215	1215	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Market Street, Swinford	3	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1216	1216	SHIP CONSTRUCTION SINGLE STAGE	Mayo	The Boreen, Crossmolina	3	*N/A						Q4-2021
1217	1217	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Deel Court, Crossmolina	3	*N/A						Q4-2021
1218	1218	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Knockroe, Moygownagh	3	*N/A						Q4-2021
1219	1219	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Low Park, Charlestown	3	*N/A						Q4-2021
1220	1220	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Church Manor, Ballina	3	N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1221	1221	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Mount St., Claremorris 	6	N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1222	1222	SHIP CONSTRUCTION SINGLE STAGE	Mayo	Lower Charles St., Castlebar	4	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1223	1223	SHIP CONSTRUCTION RENEWAL	Mayo	Main St., Hollymount	1	N/A						Q4-2022
1224	1224	SHIP CONSTRUCTION DESIGN BUILD	Mayo	Murrevagh, Mulranney	16	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1225	1225	SHIP CONSTRUCTION	Mayo	Lios na Circa, Saleen, Castlebar - Phase 2	22	*N/A					Q1-2022	
1226	1226	SHIP CONSTRUCTION	Mayo	Cross	8	*N/A		Stage 2 approved Q2-2021, full design/tender being prepared.				
1227	1227	SHIP CONSTRUCTION	Mayo	Bonniconlon	5	*N/A						Q4-2021
1228	1228	SHIP CONSTRUCTION	Mayo	Cloonkeadagh Road, Kiltimagh	21	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1229	1229	SHIP CONSTRUCTION	Mayo	Rehins Fort, Ballina	32	*N/A						Q4-2022
1230	1230	SHIP CONSTRUCTION	Mayo	50 Units @ Golf Course Rd., Westport	50	*N/A					Q4-2022	
1231	1231	SHIP CONSTRUCTION	Mayo	Ballyglass, Carnacon, Claremorris	9	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
1232	1232	SHIP CONSTRUCTION	Mayo	Atlantic Drive ,Belmullet	4	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1233	1233	SHIP CONSTRUCTION	Mayo	Liskilleen, Ballinrobe,	1	*N/A						Q4-2022
1234	1234	SHIP CONSTRUCTION	Mayo	Main Street, Ballyvary	12	*N/A		Stage 2 approved Q1-2022, full design/tender being prepared.				
1235	1235	SHIP CONSTRUCTION	Mayo	Rehins Fort, Ballina	18	*N/A					Q3-2021	
1236	1236	SHIP CONSTRUCTION	Mayo	Polranny, Achill Sound	20	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
1237	1237	CAS CONSTRUCTION TURNKEY	Mayo	Black Oak Rise, Newport	22	T�ath Housing Association Ltd					Q3-2022	
1238	1238	CAS CONSTRUCTION TURNKEY	Mayo	Apt 1-8 Tone Street, Ballina	8	Peter McVerry Trust Ltd						Q4-2022
1239	1239	CAS CONSTRUCTION RENEWAL	Mayo	20 NewLine , Castlebar	2	Mayo Mental Health Association				Stage 4 approved Q2-2022, the scheme is fully approved.		
1240	1240	CAS CONSTRUCTION	Mayo	Kilbride, Swinford	4	Sophia Housing Association Ltd	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1241	1241	CAS CONSTRUCTION	Mayo	Mount St Mary's Convent, Westport	17	T�ath Housing Association Ltd	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1242	1242	CAS CONSTRUCTION	Mayo	Ellison House, Ellison St., Castlebar	8	Peter McVerry Trust Ltd		Stage 2 approved Q4-2022, full design/tender being prepared.				
1243	1243	CAS CONSTRUCTION	Mayo	Chapel Road,  Ballinrobe 	8	Sophia Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1244	1244	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 1)	4	Tuath Housing Association					Q3-2020	
1245	1245	CALF Turnkey	Mayo	Chestnut Grove, Castlebar, Co. Mayo (Phase 2)	4	Tuath Housing Association					Q3-2020	
1246	1246	CALF Turnkey	Mayo	Humbert Way, Castlebar, Co. Mayo (Phase 1)	20	Co - Operative Housing Ireland Society Limited						Q4-2022
1247	1247	CALF Turnkey	Mayo	The Sycamores, Ballina (Phase 1)	11	Cl�id Housing						Q2-2021
1248	1248	SHIP CONSTRUCTION TURNKEY	Meath	The Brambles, Longford Rd., Duleek	13	*N/A						Q3-2022
1249	1249	SHIP CONSTRUCTION TURNKEY	Meath	Connaught Street, Athboy	5	*N/A						Q4-2022
1250	1250	SHIP CONSTRUCTION TURNKEY	Meath	Lynfield, Town Parks, Oldcastle Road, Kells	12	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1251	1251	SHIP CONSTRUCTION TURNKEY	Meath	Connaught Street, Athboy	2	*N/A						Q2-2022
1252	1252	SHIP CONSTRUCTION TURNKEY	Meath	23-24 Dunville Avenue, Navan	2	*N/A						Q4-2022
1253	1253	SHIP CONSTRUCTION TURNKEY	Meath	Bakery Lane, Navan	4	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1254	1254	SHIP CONSTRUCTION TURNKEY	Meath	The Brambles, Longford Rd., Duleek	3	*N/A						Q4-2022
1255	1255	SHIP CONSTRUCTION TURNKEY	Meath	17 The Glebe, Rathmolyon	1	*N/A						Q4-2022
1256	1256	SHIP CONSTRUCTION RENEWAL	Meath	Carrick St., Kells	49	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1257	1257	SHIP CONSTRUCTION RENEWAL	Meath	Broville, Corballis, Laytown	1	*N/A						Q4-2022
1258	1258	SHIP CONSTRUCTION RENEWAL	Meath	11 Glenidan Court, Enfield	1	*N/A						Q1-2022
1259	1259	SHIP CONSTRUCTION RENEWAL	Meath	25 Carrick Street, Kells	1	*N/A						Q3-2022
1260	1260	SHIP CONSTRUCTION RENEWAL	Meath	26 The Drive, Athlumney Abbey, Navan	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1261	1261	SHIP CONSTRUCTION RENEWAL	Meath	5 O'Carolan Park, Nobber	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1262	1262	SHIP CONSTRUCTION RENEWAL	Meath	52 Troytown Heights, Navan	1	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1263	1263	SHIP CONSTRUCTION	Meath	Staleen Park, Donore	21	*N/A						Q4-2022
1264	1264	SHIP CONSTRUCTION	Meath	Dunshaughlin	26	*N/A						Q4-2021
1265	1265	SHIP CONSTRUCTION	Meath	Gort na Glaise, Farganstown, Navan	84	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1266	1266	SHIP CONSTRUCTION	Meath	Blackhill Crescent, Donacarney	2	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1267	1267	SHIP CONSTRUCTION	Meath	Archdeaconary Glebe, Kells	22	*N/A		Stage 2 approved Q1-2020, full design/tender being prepared.				
1268	1268	SHIP CONSTRUCTION	Meath	Nangle Court, Navan	15	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1269	1269	SHIP CONSTRUCTION	Meath	Castle Street, Ashbourne	74	*N/A					Q4-2022	
1270	1270	SHIP CONSTRUCTION	Meath	Church View, Rathmolyon	22	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1271	1271	SHIP CONSTRUCTION	Meath	Haggard Street, Trim	4	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1272	1272	SHIP CONSTRUCTION	Meath	Pitcher Lane, Kells	5	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1273	1273	SHIP CONSTRUCTION	Meath	Swan Lane, Balreask	6	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1274	1274	SHIP CONSTRUCTION	Meath	Lagore, Dunshaughlin	42	*N/A					Q3-2022	
1275	1275	SHIP CONSTRUCTION	Meath	Convent Lands, Kildalkey, Athboy	28	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1276	1276	SHIP CONSTRUCTION	Meath	Ratholdren Court, Navan	27	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1277	1277	SHIP CONSTRUCTION	Meath	Brews Hill, Navan	12	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1278	1278	SHIP CONSTRUCTION	Meath	Newtown, Drumconrath	1	*N/A	Stage 1 approved Q2-2020, outline design and costs being prepared.					
1279	1279	SHIP CONSTRUCTION	Meath	New Lane, Abbey Lands, Navan	4	*N/A	Stage 1 approved Q1-2020, outline design and costs being prepared.					
1280	1280	SHIP CONSTRUCTION	Meath	Ashewood, Ashbourne	75	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1281	1281	CAS CONSTRUCTION TURNKEY	Meath	Gainsfield, (Gort Fionnbarra) Commons Road, Navan	6	T�ath Housing Association Ltd						Q2-2021
1282	1282	CAS CONSTRUCTION TURNKEY	Meath	6-7 Knightsbrook Close, Iffernock, Trim	2	T�ath Housing Association Ltd						Q4-2021
1283	1283	CAS CONSTRUCTION TURNKEY	Meath	4-5 Oak Hall, Carlanstown	2	T�ath Housing Association Ltd						Q4-2022
1284	1284	CAS CONSTRUCTION	Meath	Women's Refuge, Tailteann Drive, Windtown, Navan	8	Meath Women?s Housing Association CLG	Stage 1 approved Q2-2020, outline design and costs being prepared.					
1285	1285	CAS CONSTRUCTION	Meath	St. Lomans Street, Trim	4	Society of Saint Vincent de Paul	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1286	1286	CAS CONSTRUCTION	Meath	Park Avenue, Church Street, Oldcastle	5	Society of Saint Vincent de Paul	Stage 1 approved Q3-2021, outline design and costs being prepared.					
1287	1287	CALF Turnkey	Meath	Applewood Court, Beaufort Place, Navan, Co. Meath (Phase 1)*	21	Tuath Housing Association					Q3-2020	
1288	1288	CALF Turnkey	Meath	Ashewood, Ashbourne, Co Meath (Phase 1)	11	Cl�id Housing						Q4-2021
1289	1289	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 1)*	34	Respond					Q1-2020	
1290	1290	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 2)	18	Respond					Q1-2020	
1291	1291	CALF Turnkey	Meath	Athboy Road, Navan, Co. Meath (Phase 3)*	11	Respond					Q1-2020	
1292	1292	CALF Turnkey	Meath	Baker Hall, Navan, Co. Meath (Phase 1)	49	Tuath Housing Association						Q4-2022
1293	1293	CALF Turnkey	Meath	Colliers Place, Abbey Road, Commons, Duleek, Co. Meath (Phase 1)*	17	North and East Housing Association CLG						Q2-2022
1294	1294	CALF Turnkey	Meath	Colliers Place, Abbey Road, Commons, Duleek, Co. Meath (Phase 2)	5	North and East Housing Association CLG						Q4-2022
1295	1295	CALF Turnkey	Meath	Frederick Manor, Ashbourne, Co. Meath (Phase 1)*	11	Cl�id Housing						Q1-2021
1296	1296	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 3)	7	Tuath Housing Association						Q1-2021
1297	1297	CALF Turnkey	Meath	Gainsfield, Commons Road, Navan, Co. Meath (Phase 4)	9	Tuath Housing Association						Q2-2021
1298	1298	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 1)	19	Tuath Housing Association						Q4-2021
1299	1299	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 2)	16	Tuath Housing Association						Q2-2022
1300	1300	CALF Turnkey	Meath	Gort Fionnbarra (Gainsfield Phase 2), Commons Road, Navan, Co. Meath (Phase 3)	14	Tuath Housing Association						Q3-2022
1301	1301	CALF Turnkey	Meath	Gort Fionnbarra, Commons Road, Navan, Co. Meath (Phase 1)	2	Tuath Housing Association						Q3-2022
1302	1302	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 1)	5	Tuath Housing Association						Q3-2021
1303	1303	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 2)	5	Tuath Housing Association						Q3-2021
1304	1304	CALF Turnkey	Meath	Knightsbrook Close, Iffernock, Trim, Co. Meath (Phase 3)	6	Tuath Housing Association						Q4-2021
1305	1305	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 1)	8	Tuath Housing Association						Q3-2022
1306	1306	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 2)*	7	Tuath Housing Association						Q3-2022
1307	1307	CALF Turnkey	Meath	Knightsbrook Close, Phase 2, Iffernock, Trim, Co. Meath (Phase 3)*	7	Tuath Housing Association						Q3-2022
1308	1308	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 1)	8	Tuath Housing Association						Q4-2022
1309	1309	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 2)	4	Tuath Housing Association					Q1-2022	
1310	1310	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 3)	16	Tuath Housing Association					Q1-2022	
1311	1311	CALF Turnkey	Meath	Maudlin Vale,  Trim, Co. Meath (Phase 4)	11	Tuath Housing Association					Q1-2022	
1312	1312	CALF Turnkey	Meath	Maydenhayes, Donacarney, Co. Meath (Phase 1)*	12	Cl�id Housing						Q3-2021
1313	1313	CALF Turnkey	Meath	Narrow Ways, Bettystown, Co. Meath (Phase 1)	6	Tuath Housing Association						Q1-2022
1314	1314	CALF Turnkey	Meath	Narrow Ways, Bettystown, Co. Meath (Phase 2)	6	Tuath Housing Association						Q1-2022
1315	1315	CALF Turnkey	Meath	Oak Hall, Ardee Road, Carlanstown, Co. Meath (Phase 1)	8	Tuath Housing Association						Q4-2022
1316	1316	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 2)*	14	Cl�id Housing						Q2-2021
1317	1317	CALF Turnkey	Meath	Royal Oaks, Enfield, Co. Meath (Phase 2) (Phase 3)	16	Cl�id Housing						Q2-2022
1318	1318	CALF Turnkey	Meath	Ruxton Oaks, Navan, Co. Meath (Phase 1)*	20	Cl�id Housing						Q4-2021
1319	1319	CALF Turnkey	Meath	St Marys Dunboyne, Co. Meath (Phase 1)	16	Co - Operative Housing Ireland Society Limited						Q2-2021
1320	1320	CALF Turnkey	Meath	Swanbrook, Trim Road, Co. Meath (Phase 1)	22	Tuath Housing Association					Q1-2022	
1321	1321	CALF Turnkey	Meath	Swanbrook, Trim Road, Co. Meath (Phase 2)	18	Tuath Housing Association					Q1-2022	
1322	1322	CALF Turnkey	Meath	Swanbrook, Trim Road, Co. Meath (Phase 3)	8	Tuath Housing Association					Q1-2022	
1323	1323	CALF Turnkey	Meath	The Arches, Dunshaughlin, Co. Meath (Phase 1)	6	Tuath Housing Association					Q2-2021	
1324	1324	CALF Turnkey	Meath	The Maudlins, Trim, Co. Meath (Phase 1)	9	Cl�id Housing						Q1-2021
1325	1325	CALF Turnkey	Meath	The Willows, Dunshaughlin, Co. Meath (Phase 1)*	24	Cl�id Housing						Q4-2022
1326	1326	CALF Turnkey	Meath	The Willows, Dunshaughlin, Co. Meath (Phase 2)*	72	Cl�id Housing						Q4-2022
1327	1327	CALF Turnkey	Meath	Tubberclaire Meadows, Navan, Co. Meath (Phase 1)*	8	Cl�id Housing						Q4-2022
1328	1328	CALF Turnkey	Meath	Whitefield Hall, Bettystown, Co. Meath (Phase 3)	2	Tuath Housing Association						Q3-2021
1329	1329	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc, Carrickmacross	6	*N/A						Q4-2021
1330	1330	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill Darach, Bree, Castleblayney	16	*N/A						Q4-2022
1331	1331	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill an Ri, Carrickmacross	30	*N/A				Stage 4 approved Q3-2021, the scheme is fully approved.		
1332	1332	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc, Carrickmacross	28	*N/A						Q3-2022
1333	1333	SHIP CONSTRUCTION TURNKEY	Monaghan	Ballinode	22	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1334	1334	SHIP CONSTRUCTION TURNKEY	Monaghan	Ard an Radhairc Carrickmacross	7	*N/A						Q4-2022
1335	1335	SHIP CONSTRUCTION TURNKEY	Monaghan	Coill Darach, Castleblayney	14	*N/A						Q4-2022
1336	1336	SHIP CONSTRUCTION TURNKEY	Monaghan	Cnoc na Gr�ine, Tydavnet	4	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1337	1337	SHIP CONSTRUCTION SINGLE STAGE	Monaghan	Folly Court, Ballybay	6	*N/A						Q4-2021
1338	1338	SHIP CONSTRUCTION RENEWAL	Monaghan	82 & 83 Fermanagh St., Clones	3	*N/A						Q3-2022
1339	1339	SHIP CONSTRUCTION RENEWAL	Monaghan	An Bonnan Bui & Flower Shop, Fermanagh St., Clones	6	*N/A						Q2-2022
1340	1340	SHIP CONSTRUCTION RENEWAL	Monaghan	2a & 3 Analore St., Clones	2	*N/A						Q4-2022
1341	1341	SHIP CONSTRUCTION RENEWAL	Monaghan	Abbey Gatehouse, Analore St., Clones	4	*N/A						Q4-2022
1342	1342	SHIP CONSTRUCTION RENEWAL	Monaghan	63 Fermanagh St., Clones	3	*N/A						Q2-2022
1343	1343	SHIP CONSTRUCTION	Monaghan	Lui Na Greine, Scotstown	6	*N/A						Q4-2021
1344	1344	SHIP CONSTRUCTION	Monaghan	12 Church St., Ballybay	2	*N/A						Q4-2022
1345	1345	SHIP CONSTRUCTION	Monaghan	Church Hill, Clones	2	*N/A						Q4-2022
1346	1346	SHIP CONSTRUCTION	Monaghan	13 McCurtain Street, Clones	1	*N/A					Q1-2021	
1347	1347	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	12	*N/A						Q2-2022
1348	1348	SHIP CONSTRUCTION	Monaghan	An Cl�s, Cornamucklaglass, Ballybay 	7	*N/A					Q2-2022	
1349	1349	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	1	*N/A						Q2-2022
1350	1350	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	5	*N/A						Q3-2022
1351	1351	SHIP CONSTRUCTION	Monaghan	Lecklevera, Monaghan	1	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1352	1352	SHIP CONSTRUCTION	Monaghan	Lui na Greine, Scotstown	8	*N/A						Q4-2022
1353	1353	CAS CONSTRUCTION	Monaghan	Drumillard, Castleblayney (Phase 2)	2	Castleblayney Care Housing Association Ltd					Q1-2021	
1354	1354	CAS CONSTRUCTION	Monaghan	Liseggerton, Clones	19	Oaklee Housing Trust						Q2-2021
1355	1355	CAS CONSTRUCTION	Monaghan	Birch Court Apts., 34 Main Street, Ballybay	4	North ? East Housing Association Ltd				Stage 4 approved Q3-2021, the scheme is fully approved.		
1356	1356	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 2)"	6	Tuath Housing Association						Q2-2021
1357	1357	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 3)"	8	Tuath Housing Association						Q3-2021
1358	1358	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 4)"	8	Tuath Housing Association						Q2-2022
1359	1359	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 5)"	3	Tuath Housing Association						Q2-2022
1360	1360	CALF Turnkey	Monaghan	"Bree, Castleblayney 
 (Phase 6)"	2	Tuath Housing Association					Q2-2019	
1361	1361	CALF Turnkey	Monaghan	Drumbear Wood, Monaghan, Co. Monaghan  (Phase 1)*	17	Co - Operative Housing Ireland Society Limited					Q1-2022	
1362	1362	CALF Turnkey	Monaghan	Lakeview Apartments, Drummond Radhairc, Carrickmacross, Co Monaghan (Phase 1)*	12	North and East Housing Association CLG						Q2-2022
1363	1363	CALF Turnkey	Monaghan	Macartan View,  Latlorcan, Dublin Road, Monaghan (Phase 1)*	41	Tuath Housing Association				Q2-2021		
1364	1364	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 1)	7	Tuath Housing Association						Q2-2021
1365	1365	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 2)	6	Tuath Housing Association					Q3-2019	
1366	1366	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 3)	6	Tuath Housing Association					Q3-2019	
1367	1367	CALF Turnkey	Monaghan	Magheross, Carrickmacross, Co Monaghan (Phase 4)	14	Tuath Housing Association					Q3-2019	
1368	1368	CALF Turnkey	Monaghan	Part 2, Radharc An Bhri, Bree, Castleblayney, Co. Monaghan (Phase 1)*	2	Tuath Housing Association						Q2-2022
1369	1369	CALF Turnkey	Monaghan	Part 2, Radharc An Bhri, Bree, Castleblayney, Co. Monaghan (Phase 2)	8	Tuath Housing Association					Q4-2021	
1370	1370	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 1)	8	Tuath Housing Association					Q3-2020	
1371	1371	CALF Turnkey	Monaghan	Railway View, Kilnacloy, Monaghan, Co. Monaghan (Phase 2)*	8	Tuath Housing Association					Q3-2020	
1372	1372	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 1)*	8	Tuath Housing Association					Q2-2021	
1373	1373	CALF Turnkey	Monaghan	The Meadows, Emy, Emyvale, Co. Monaghan (Phase 2)	6	Tuath Housing Association					Q2-2021	
1374	1374	SHIP CONSTRUCTION TURNKEY	Offaly	Main Street, Daingean	8	*N/A						Q4-2021
1375	1375	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	5	*N/A						Q4-2021
1376	1376	SHIP CONSTRUCTION TURNKEY	Offaly	Cluain na Greine, Clonygowan	2	*N/A						Q2-2021
1377	1377	SHIP CONSTRUCTION TURNKEY	Offaly	Coolgarry, Walsh Island 	4	*N/A						Q4-2022
1378	1378	SHIP CONSTRUCTION TURNKEY	Offaly	Castle View, Mucklagh, Tullamore	8	*N/A						Q2-2022
1379	1379	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	2	*N/A						Q1-2021
1380	1380	SHIP CONSTRUCTION TURNKEY	Offaly	Bog Road, Portarlington	28	*N/A					Q2-2021	
1381	1381	SHIP CONSTRUCTION TURNKEY	Offaly	MacRegol Pairc, Birr	4	*N/A						Q2-2021
1382	1382	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	6	*N/A						Q2-2022
1383	1383	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	5	*N/A						Q1-2022
1384	1384	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	8	*N/A						Q3-2022
1385	1385	SHIP CONSTRUCTION TURNKEY	Offaly	Woodfield, Birr	10	N/A						Q4-2022
1386	1386	SHIP CONSTRUCTION RENEWAL	Offaly	1 Newbridge St., Birr	1	*N/A						Q3-2022
1387	1387	SHIP CONSTRUCTION RENEWAL	Offaly	Church Hill, Tullamore	2	*N/A						Q3-2022
1388	1388	SHIP CONSTRUCTION	Offaly	Beechwood Drive, Circular Road, Daingean	9	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1389	1389	SHIP CONSTRUCTION	Offaly	Kylebeg, Banagher (Phase 2)	18	*N/A					Q3-2021	
1390	1390	SHIP CONSTRUCTION	Offaly	Beechgrove, Belmont	7	*N/A					Q4-2021	
1391	1391	SHIP CONSTRUCTION	Offaly	Raheen ,Clara	38	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1392	1392	SHIP CONSTRUCTION	Offaly	Elderberry Drive, Moneygall	4	*N/A						Q4-2022
1393	1393	SHIP CONSTRUCTION	Offaly	Sr. Senan Avenue, Edenderry	4	*N/A					Q2-2022	
1394	1394	SHIP CONSTRUCTION	Offaly	Dargan Drive, Chancery Lane, Tullamore (Phase 2)	20	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1395	1395	SHIP CONSTRUCTION	Offaly	Sycamore Drive, Ballycumber	10	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1396	1396	SHIP CONSTRUCTION	Offaly	Circular Road, Daingean Phase 2	9	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
1397	1397	CAS CONSTRUCTION	Offaly	Killane Court, Edenderry	2	T�ath Housing Association Ltd						Q2-2021
1398	1398	CAS CONSTRUCTION	Offaly	Clonminch, Tullamore	19	Oaklee Housing Trust						Q4-2022
1399	1399	CAS CONSTRUCTION	Offaly	Presentation Lands, Portarlington	39	Sophia Housing Association Ltd		Stage 2 approved Q1-2021, full design/tender being prepared.				
1400	1400	CAS CONSTRUCTION	Offaly	Clonamore Hotel, Tullamore	17	Sophia Housing Association Ltd					Q3-2022	
1401	1401	CALF Turnkey	Offaly	3 units, An Corran, Crinkle, Birr, Co. Offaly (Phase 1)	3	Co - Operative Housing Ireland Society Limited						Q1-2021
1402	1402	CALF Construction	Offaly	Kearney?s Field, Tullamore, Co. Offaly (Phase 1)	41	Oaklee Housing					Q2-2021	
1403	1403	CALF Construction	Offaly	Killane Drive, Edenderry, Co Offaly (Phase 1)	25	Tuath Housing Association						Q2-2021
1404	1404	CALF Turnkey	Offaly	Main Street, Kilcormac, Birr, Co. Offaly (Phase 1)	3	Circle Voluntary Housing Association Ltd					Q3-2022	
1405	1405	CALF Turnkey	Offaly	Rahan Road, Tullamore, Co. Offaly (aka Jackson?s Hill) (Phase 1)*	26	Cl�id Housing						Q2-2022
1406	1406	CALF Turnkey	Offaly	The Hawthorns, Arden Road, Tullamore, Co. Offaly (Phase 1)	16	Cl�id Housing						Q2-2022
1407	1407	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	11	*N/A					Q3-2022	
1408	1408	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	11	N/A					Q3-2022	
1409	1409	SHIP CONSTRUCTION TURNKEY	Roscommon	Esker Lawns, Old Tuam Rd, Monksland	5	N/A					Q3-2022	
1410	1410	SHIP CONSTRUCTION SINGLE STAGE	Roscommon	The Meadows, Castlerea 	2	*N/A						Q4-2022
1411	1411	SHIP CONSTRUCTION RENEWAL	Roscommon	Elphin Courthouse, Elphin	3	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1412	1412	SHIP CONSTRUCTION RENEWAL	Roscommon	Pound St., Ballaghaderreen	1	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1413	1413	SHIP CONSTRUCTION	Roscommon	Cloonfad	3	*N/A						Q2-2021
1414	1414	SHIP CONSTRUCTION	Roscommon	Cluain Fraoigh, Cloonbeirne	7	*N/A						Q1-2021
1415	1415	SHIP CONSTRUCTION	Roscommon	Sli an Choiste, Monksland	20	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1416	1416	SHIP CONSTRUCTION	Roscommon	Meadowbrook, Ballyclare Td., Ballyleague	16	*N/A						Q4-2021
1417	1417	SHIP CONSTRUCTION	Roscommon	Lisroyne Td., Strokestown	10	*N/A						Q4-2021
1418	1418	SHIP CONSTRUCTION	Roscommon	Windmill Road, Elphin Road	10	*N/A					Q3-2022	
1419	1419	SHIP CONSTRUCTION	Roscommon	Lakeview Heights, Bellspark Td., Boyle	6	*N/A					Q2-2022	
1420	1420	SHIP CONSTRUCTION	Roscommon	Lisnamult, Ardnanagh Td., Roscommon Town	13	*N/A					Q4-2022	
1421	1421	SHIP CONSTRUCTION	Roscommon	Station Rd., Cortober, Carrickk on Shannon	4	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1422	1422	SHIP CONSTRUCTION	Roscommon	Curlew View, Boyle	16	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1423	1423	SHIP CONSTRUCTION	Roscommon	Elphin St, Strokestown	3	N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1424	1424	CAS CONSTRUCTION RENEWAL	Roscommon	2 Tithe na gCarad, Willliamstown Road, Castlerea	4	Sophia Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1425	1425	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Roscommon	The Walk, Roscommon Town	53	*N/A						Q2-2021
1426	1426	CALF Turnkey	Roscommon	Monksland, Athlone, Co. Roscommon (Cloongowna). (Phase 1)*	35	Tuath Housing Association					Q4-2019	
1427	1427	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	12	*N/A					Q2-2021	
1428	1428	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	15	*N/A					Q3-2021	
1429	1429	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	26	*N/A					Q4-2021	
1430	1430	SHIP CONSTRUCTION TURNKEY	Sligo	Seaville, Ursuline Convent	13	*N/A					Q2-2022	
1431	1431	SHIP CONSTRUCTION	Sligo	Carrowbunnaun, Strandhill	42	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1432	1432	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 1)	10	*N/A						Q4-2021
1433	1433	SHIP CONSTRUCTION	Sligo	Dromore West 	10	*N/A						Q4-2021
1434	1434	SHIP CONSTRUCTION	Sligo	Robbers' Lane, Maugheraboy, Sligo	62	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
1435	1435	SHIP CONSTRUCTION	Sligo	SRD at Crowagh, Dromore West	1	*N/A						Q4-2021
1436	1436	SHIP CONSTRUCTION	Sligo	Gormley Park, Bunnanadden	6	*N/A						Q4-2022
1437	1437	SHIP CONSTRUCTION	Sligo	Connolly Park, Tubbercurry (Phase 2) & The Green Rd,	19	*N/A					Q2-2022	
1438	1438	SHIP CONSTRUCTION	Sligo	Geldof Drive & Centre Park, Cranmore, Sligo	30	*N/A	Stage 1 approved Q4-2020, outline design and costs being prepared.					
1439	1439	CAS CONSTRUCTION TURNKEY	Sligo	Avena, Ballisodare, Co Sligo	6	T�ath Housing Association Ltd						Q1-2022
1440	1440	CAS CONSTRUCTION	Sligo	Killeshin, First Sea Road, Sligo	5	Newgrove Housing Association Ltd					Q4-2020	
1441	1441	CAS CONSTRUCTION	Sligo	Summerhill, Tubbercurry, Co Sligo	6	Sophia Housing Association Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1442	1442	CAS CONSTRUCTION	Sligo	Adelaide Street,  Sligo	38	T�ath Housing Association Ltd	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1443	1443	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Sligo	Rathellen, Finisklin, Co. Sligo	63	*N/A			Q4-2022			
1444	1444	CALF Turnkey	Sligo	The Fairways, Tubbercurry, Co. Sligo (Phase 1)	8	Co - Operative Housing Ireland Society Limited				Q4-2022		
1445	1445	SHIP DIALOG	South Dublin	Kilcarbery JV Social	16	*N/A						Q3-2022
1446	1446	SHIP DIALOG	South Dublin	Kilcarbery JV Social	20	*N/A						Q3-2022
1447	1447	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A						Q4-2022
1448	1448	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A						Q4-2022
1449	1449	SHIP DIALOG	South Dublin	Clonburris 1	60	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1450	1450	SHIP DIALOG	South Dublin	Clonburris 2	56	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1451	1451	SHIP DIALOG	South Dublin	Kilcarbery JV Social	5	*N/A						Q4-2022
1452	1452	SHIP DIALOG	South Dublin	Kilcarbery JV Social	15	*N/A						Q4-2022
1453	1453	SHIP DIALOG	South Dublin	Kilcarbery JV Social	18	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1454	1454	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1455	1455	SHIP DIALOG	South Dublin	Kilcarbery JV Social	26	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1456	1456	SHIP DIALOG	South Dublin	Kilcarbery JV Social	5	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1457	1457	SHIP DIALOG	South Dublin	Kilcarbery JV Social	3	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1458	1458	SHIP DIALOG	South Dublin	Kilcarbery JV Social	27	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1459	1459	SHIP DIALOG	South Dublin	Kilcarbery JV Social	28	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1460	1460	SHIP DIALOG	South Dublin	Kilcarbery JV Social	17	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1461	1461	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1462	1462	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1463	1463	SHIP DIALOG	South Dublin	Kilcarbery JV Social	9	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1464	1464	SHIP DIALOG	South Dublin	Kilcarbery JV Social	7	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1465	1465	SHIP DIALOG	South Dublin	Kilcarbery JV Social	11	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1466	1466	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1467	1467	SHIP DIALOG	South Dublin	Kilcarbery JV Social	21	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1468	1468	SHIP DIALOG	South Dublin	Kilcarbery JV Social	4	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1469	1469	SHIP DIALOG	South Dublin	Kilcarbery JV Social	10	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1470	1470	SHIP DIALOG	South Dublin	Kilcarbery JV Social	5	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1471	1471	SHIP DIALOG	South Dublin	Clonburris 1	33	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1472	1472	SHIP CONSTRUCTION TURNKEY	South Dublin	Cloragh Mills, Edmonstown Road, Rathfarnham, Dublin 16	8	*N/A						Q4-2022
1473	1473	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	37 Greenfort Gardens, Clondalkin	2	*N/A						Q4-2021
1474	1474	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	Brady's Court, Old Bawn, Tallaght	12	*N/A					Q3-2022	
1475	1475	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	Pearse Brothers Park, Rathfarnham	10	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1476	1476	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	St Aongus Green, Tallaght, Dublin 24	12	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1477	1477	SHIP CONSTRUCTION SINGLE STAGE	South Dublin	St Ronan's Crescent, Clondalkin	9	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1478	1478	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	St. Marks Avenue, Clondalkin	38	*N/A						Q4-2022
1479	1479	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Balgaddy F, Griffeen Avenue, Lucan Co. Dublin	69	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1480	1480	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riversdale, Clondalkin, Dublin 22	25	*N/A						Q4-2022
1481	1481	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riverside Cottages, Templeogue	10	*N/A						Q4-2022
1482	1482	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Riversdale, Clondalkin, Dublin 22	18	*N/A					Q4-2020	
1483	1483	SHIP CONSTRUCTION DESIGN BUILD	South Dublin	Grand Canal, Lindisfarne, Clondalkin,	19	*N/A					Q4-2022	
1484	1484	SHIP CONSTRUCTION	South Dublin	St. Catherine?s, Knockmore Avenue, Killinarden, Tallaght	12	*N/A						Q4-2022
1485	1485	SHIP CONSTRUCTION	South Dublin	Homeville, Knocklyon, Dublin 16	16	*N/A					Q4-2020	
1486	1486	SHIP CONSTRUCTION	South Dublin	Nangor Road, Clondalkin, Dublin 22	93	*N/A					Q2-2022	
1487	1487	CAS CONSTRUCTION TURNKEY	South Dublin	Oakridge, Ballynakelly,Edge, Newcastle, Co. Dublin	3	T�ath Housing Association Ltd						Q2-2022
1488	1488	CAS CONSTRUCTION TURNKEY	South Dublin	3 Cornerpark Rise	1	Arlington Novas Ireland Ltd						Q4-2021
1489	1489	CAS CONSTRUCTION	South Dublin	Old Nangor Road, Clondalkin	10	Simon Community : Dublin Simon		Stage 2 approved Q4-2016, full design/tender being prepared.				
1490	1490	CAS CONSTRUCTION	South Dublin	Leabeg, Kiltipper, Co. Dublin	10	Peter McVerry Trust Ltd	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1491	1491	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	South Dublin	Clonburris	120	N/A	Q2-2022					
1492	1492	CALF Turnkey	South Dublin	Ballynakelly Rise, Newcastle Boulevard and Graydon Park, Newcastle, County Dublin (Phase 1)*	8	Tuath Housing Association						Q2-2022
1493	1493	CALF Turnkey	South Dublin	Ballynakelly Rise, Newcastle Boulevard and Graydon Park, Newcastle, County Dublin (Phase 2)*	8	Tuath Housing Association						Q3-2022
1494	1494	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 1)*	10	Tuath Housing Association						Q4-2022
1495	1495	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 2)*	9	Tuath Housing Association					Q4-2021	
1496	1496	CALF Turnkey	South Dublin	Barnoaks, Citywest, Dublin 24 (Phase 3)*	27	Tuath Housing Association					Q4-2021	
1497	1497	CALF Turnkey	South Dublin	Citywest Quarter, Citywest, Dublin 24 (Phase 1)*	32	Tuath Housing Association						Q2-2021
1498	1498	CALF Turnkey	South Dublin	Citywest Village House, Citywest Village, D24 (Phase 1)*	36	Fold Housing Association Ireland Ltd						Q1-2022
1499	1499	CALF Turnkey	South Dublin	Cloverhill Lodge, Cloverhill Rd, Clondalkin, D22 (Phase 1)*	40	Oaklee Housing					Q2-2021	
1500	1500	CALF Turnkey	South Dublin	Dodderbrook, Old Court Rd, Ballycullen, Dublin 24 (Phase 2)*	9	Cl�id Housing						Q1-2021
1501	1501	CALF Construction	South Dublin	Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 1)	17	Cl�id Housing					Q3-2020	
1502	1502	CALF Construction	South Dublin	Fernwood Green and Maplewood Heights, Tallaght, Dublin  (Phase 2)	23	Cl�id Housing					Q3-2020	
1503	1503	CALF Turnkey	South Dublin	Finians Way, Newcastle South, Newcastle, Co. Dublin (Phase 1)*	2	Clanmil Housing Association Ireland						Q4-2021
1504	1504	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 1)	32	Respond						Q3-2021
1505	1505	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 2)	38	Respond						Q3-2021
1506	1506	CALF Turnkey	South Dublin	Finnstown, Lucan, Co. Dublin (Phase 3)*	24	Respond						Q4-2021
1507	1507	CALF Turnkey	South Dublin	Graydon, Newcastle, Co. Dublin (Phase 1)*	8	Tuath Housing Association						Q4-2021
1508	1508	CALF Turnkey	South Dublin	Hallwell, Tubber Lane, Adamstown, Co Dublin (Phase 1)*	45	The Iveagh Trust						Q4-2021
1509	1509	CALF Turnkey	South Dublin	Kingswood, Old Ballymount Road, Tallaght, Dublin 24 (Phase 1)*	24	Respond						Q4-2021
1510	1510	CALF Turnkey	South Dublin	Mountain Gate, Kiltipper, Dublin 24 (Phase 1)*	22	Co - Operative Housing Ireland Society Limited					Q1-2020	
1511	1511	CALF Turnkey	South Dublin	Phase 2, Aylmer Drive, Aylmer Heath, Newcastle, Co. Dublin (Phase 1)*	17	Respond						Q2-2021
1512	1512	CALF Turnkey	South Dublin	"Sallymills
(Formerly Sallypark),
 Clondalkin, Dublin 22 (Phase 1)*"	85	Cl�id Housing						Q4-2022
1513	1513	CALF Turnkey	South Dublin	San Guida, New Road, Clondalkin, Dublin 22 (Phase 1)*	21	Cl�id Housing					Q3-2021	
1514	1514	CALF Turnkey	South Dublin	"Scholarstown Road, Rathfarnham, Dublin 16


 (Phase 1)*"	14	Circle Voluntary Housing Association Ltd						Q1-2022
1515	1515	CALF Turnkey	South Dublin	Somerton Gate, Adamstown, Lucan, Co. Dublin (Phase 1)*	36	Cl�id Housing						Q4-2022
1516	1516	CALF Construction	South Dublin	St. Catherine?s, Knockmore Avenue, Killinarden, Tallaght, Dublin 24 (Phase 1)	2	Sophia Housing Association Ltd						Q2-2022
1517	1517	CALF Construction	South Dublin	The Weir, Whitestown Way, Tallaght, Dublin 24 (Phase 1)	81	Cl�id Housing					Q2-2021	
1518	1518	CALF Turnkey	South Dublin	Willowview, Ballyboden Road, Rathfarnham, Dublin 14 (Phase 1)*	12	Cl�id Housing						Q2-2021
1519	1519	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	6	*N/A						Q4-2022
1520	1520	SHIP CONSTRUCTION TURNKEY	Tipperary	Ma Charoin, Manna South, Templemore	3	*N/A						Q4-2022
1521	1521	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	24	*N/A					Q3-2020	
1522	1522	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	10	*N/A						Q4-2022
1523	1523	SHIP CONSTRUCTION TURNKEY	Tipperary	Rosanna Close, Tipperary Town	1	*N/A					Q3-2020	
1524	1524	SHIP CONSTRUCTION TURNKEY	Tipperary	Hazel Close, Carrick on Suir	14	*N/A						Q4-2021
1525	1525	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	2	*N/A				Stage 4 approved Q2-2021, the scheme is fully approved.		
1526	1526	SHIP CONSTRUCTION TURNKEY	Tipperary	Cois Abhainn, Mullinahone	3	*N/A						Q4-2021
1527	1527	SHIP CONSTRUCTION TURNKEY	Tipperary	Glentara, Roscrea	2	*N/A						Q4-2021
1528	1528	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel	11	*N/A						Q4-2022
1529	1529	SHIP CONSTRUCTION TURNKEY	Tipperary	Carrick Beg, Carrick on Suir	22	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1530	1530	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenconnor Road, Clonmel 	2	*N/A						Q4-2022
1531	1531	SHIP CONSTRUCTION TURNKEY	Tipperary	Clogheen Road, Ardfinnan	13	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1532	1532	SHIP CONSTRUCTION TURNKEY	Tipperary	Glenoir, Cullen	7	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1533	1533	SHIP CONSTRUCTION TURNKEY	Tipperary	Ard na Sidhe, Clonmel	4	*N/A						Q4-2022
1534	1534	SHIP CONSTRUCTION TURNKEY	Tipperary	Springfort Meadows, Nenagh	17	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1535	1535	SHIP CONSTRUCTION TURNKEY	Tipperary	Kilsheelan, Clonmel	2	*N/A						Q3-2022
1536	1536	SHIP CONSTRUCTION TURNKEY	Tipperary	Drangan	3	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1537	1537	SHIP CONSTRUCTION TURNKEY	Tipperary	Stradavoher Road, Thurles	29	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1538	1538	SHIP CONSTRUCTION TURNKEY	Tipperary	Kilsheelan, Clonmel	1	*N/A						Q4-2022
1539	1539	SHIP CONSTRUCTION TURNKEY	Tipperary	An Grianan, Killenaule	4	N/A						Q4-2022
1540	1540	SHIP CONSTRUCTION TURNKEY	Tipperary	Glencree, Newport	4	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1541	1541	SHIP CONSTRUCTION TURNKEY	Tipperary	Wheatfields, Glenconnor, Clonmel	34	N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1542	1542	SHIP CONSTRUCTION TURNKEY	Tipperary	Prior Park, Clonmel	11	*N/A					Q3-2022	
1543	1543	SHIP CONSTRUCTION TURNKEY	Tipperary	Ma Charoin, Manna South, Templemore	10	*N/A					Q1-2021	
1544	1544	SHIP CONSTRUCTION TURNKEY	Tipperary	Ard na Sidhe, Clonmel	5	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1545	1545	SHIP CONSTRUCTION TURNKEY	Tipperary	Dun Uisce, Cahir	8	N/A						Q4-2022
1546	1546	SHIP CONSTRUCTION RENEWAL	Tipperary	Ard na Greine, Clonmel	2	*N/A						Q4-2022
1547	1547	SHIP CONSTRUCTION RENEWAL	Tipperary	Boherclough Street, Cashel	9	*N/A					Q3-2022	
1548	1548	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A						Q1-2021
1549	1549	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A						Q4-2021
1550	1550	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	10	*N/A						Q4-2021
1551	1551	SHIP CONSTRUCTION	Tipperary	Templetouhy	10	*N/A						Q4-2021
1552	1552	SHIP CONSTRUCTION	Tipperary	Abbey Street, Cahir	10	*N/A						Q4-2022
1553	1553	SHIP CONSTRUCTION	Tipperary	Borrisokane	14	*N/A						Q4-2021
1554	1554	SHIP CONSTRUCTION	Tipperary	Portroe, Nenagh	14	*N/A					Q4-2021	
1555	1555	SHIP CONSTRUCTION	Tipperary	Cloughjordan	2	*N/A						Q2-2021
1556	1556	SHIP CONSTRUCTION	Tipperary	Mitchel St., Thurles	1	*N/A						Q4-2021
1557	1557	SHIP CONSTRUCTION	Tipperary	Cormack Drive, Nenagh	12	*N/A						Q3-2022
1558	1558	SHIP CONSTRUCTION	Tipperary	Bansha	14	*N/A					Q3-2021	
1559	1559	SHIP CONSTRUCTION	Tipperary	Ned Hayes Drive, Twomileborris, Thurles	22	*N/A						Q4-2022
1560	1560	SHIP CONSTRUCTION	Tipperary	Donohill	8	*N/A					Q3-2021	
1561	1561	SHIP CONSTRUCTION	Tipperary	Mullinahone	10	*N/A						Q4-2022
1562	1562	SHIP CONSTRUCTION	Tipperary	Ballyclerihan	14	*N/A					Q3-2021	
1563	1563	SHIP CONSTRUCTION	Tipperary	Ard Alainn, Moyne	9	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
1564	1564	SHIP CONSTRUCTION	Tipperary	Ardcroney	4	*N/A						Q4-2022
1565	1565	SHIP CONSTRUCTION	Tipperary	Comeragh Drive, Clonmel	2	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1566	1566	SHIP CONSTRUCTION	Tipperary	Church Street, Templemore	2	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1567	1567	SHIP CONSTRUCTION	Tipperary	Woodview Close, Castle Crescent,  Nenagh	10	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1568	1568	SHIP CONSTRUCTION	Tipperary	Grove Street. Roscrea	9	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1569	1569	SHIP CONSTRUCTION	Tipperary	William Street, Clonmel	4	*N/A		Stage 2 approved Q1-2021, full design/tender being prepared.				
1570	1570	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	28	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
1571	1571	SHIP CONSTRUCTION	Tipperary	Knockanrawley	14	*N/A						Q2-2021
1572	1572	SHIP CONSTRUCTION	Tipperary	Mill Road, Thurles	14	*N/A						Q2-2022
1573	1573	SHIP CONSTRUCTION	Tipperary	Mulkear View, Newport	1	*N/A						Q1-2022
1574	1574	SHIP CONSTRUCTION	Tipperary	Mountain View, Cahir	23	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
1575	1575	SHIP CONSTRUCTION	Tipperary	Glencarrick, Roscrea	20	*N/A	Stage 1 approved Q2-2021, outline design and costs being prepared.					
1576	1576	SHIP CONSTRUCTION	Tipperary	William Street, Nenagh	7	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
1577	1577	SHIP CONSTRUCTION	Tipperary	Borrisokane	1	*N/A						Q1-2022
1578	1578	SHIP CONSTRUCTION	Tipperary	Ashbury, Roscrea	10	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1579	1579	SHIP CONSTRUCTION	Tipperary	Fr. Mathew Street, Tipperary Town	4	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1580	1580	SHIP CONSTRUCTION	Tipperary	Puckane, Nenagh	21	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1581	1581	SHIP CONSTRUCTION	Tipperary	Mountain View, Cahir	22	N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1582	1582	CAS CONSTRUCTION TURNKEY	Tipperary	Kichham Street, Carrick en Suir	12	T�ath Housing Association Ltd						Q4-2022
1583	1583	CAS CONSTRUCTION SINGLE STAGE	Tipperary	Deerpark Road, Ashwell's Lot	2	SPADE ? St. Patrick?s Dwellings for the Elderly						Q2-2022
1584	1584	CAS CONSTRUCTION RENEWAL	Tipperary	7 Stradavoher Court, Thurles	2	Arlington Novas Ireland Ltd				Stage 4 approved Q2-2022, the scheme is fully approved.		
1585	1585	CAS CONSTRUCTION RENEWAL	Tipperary	1 and 1A Limerick Road	2	Thurles Lions Trust Housing Assoc.	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1586	1586	CAS CONSTRUCTION	Tipperary	Glenconnor Road, Clonmel	9	Cluid Housing Association						Q4-2022
1587	1587	CAS CONSTRUCTION	Tipperary	Stanwix House, Kickham Street, Thurles	19	Thurles Lions Trust Housing Assoc.						Q4-2022
1588	1588	CAS CONSTRUCTION	Tipperary	Main Street, Templemore	24	Templemore Voluntary Housing Association		Stage 2 approved Q2-2022, full design/tender being prepared.				
1589	1589	CAS CONSTRUCTION	Tipperary	Gort an Oir, Fethard	7	Belmont Park Housing Association Ltd	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1590	1590	CALF Turnkey	Tipperary	Abbey Court Lodges, Old Dublin Road, Nenagh, Co Tipperary (Phase 1)	12	Focus Housing Association CLG						Q1-2022
1591	1591	CALF Turnkey	Tipperary	Abbey Court Lodges, Old Dublin Road, Nenagh, Co Tipperary (Phase 2)	4	Focus Housing Association CLG						Q2-2022
1592	1592	CALF Turnkey	Tipperary	Ballygraigue Court, Ballygraigue Road, Nenagh (Phase 1)	5	Cl�id Housing						Q2-2022
1593	1593	CALF Turnkey	Tipperary	Wallers Lot, East Cashel, Co. Tipperary (Phase 1)*	40	Tuath Housing Association					Q1-2022	
1594	1594	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	13	*N/A						Q1-2021
1595	1595	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	10	*N/A						Q2-2021
1596	1596	SHIP CONSTRUCTION TURNKEY	Waterford	Mount William, Williamstown, Waterford City	23	*N/A						Q2-2021
1597	1597	SHIP CONSTRUCTION TURNKEY	Waterford	The Courtyard, Morrissons Road, Waterford City	8	*N/A						Q2-2021
1598	1598	SHIP CONSTRUCTION TURNKEY	Waterford	Bounds Court, Airport Road, Waterford	15	N/A						Q1-2022
1599	1599	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main St., Aglish; Bye Lane, Kilmacthomas	6	N/A						Q4-2021
1600	1600	SHIP CONSTRUCTION TURNKEY	Waterford	Ormonde House, Dungarvan, Co Waterford	19	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1601	1601	SHIP CONSTRUCTION TURNKEY	Waterford	Brideview Close, Tallow; Main St., Aglish; Bye Lane, Kilmacthomas	3	*N/A						Q3-2022
1602	1602	SHIP CONSTRUCTION TURNKEY	Waterford	Radharc na Siuire, Knockboy	3	*N/A						Q1-2022
1603	1603	SHIP CONSTRUCTION TURNKEY	Waterford	Radharc na Siuire, Knockboy	4	*N/A						Q4-2022
1604	1604	SHIP CONSTRUCTION TURNKEY	Waterford	Bounds Court, Airport Road, Waterford	2	*N/A						Q4-2022
1605	1605	SHIP CONSTRUCTION RENEWAL	Waterford	Clarendon Court, Penrose Lane, Waterford	24	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.					
1606	1606	SHIP CONSTRUCTION RENEWAL	Waterford	Apt 1 and Apt 2 Rivercourt, Grattan Quay, Waterford City	2	*N/A				Stage 4 approved Q1-2021, the scheme is fully approved.		
1607	1607	SHIP CONSTRUCTION RENEWAL	Waterford	Meeting House Lane, Waterford City	6	N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
1608	1608	SHIP CONSTRUCTION RENEWAL	Waterford	29 The Glen, Waterford City	4	*N/A					Q2-2022	
1609	1609	SHIP CONSTRUCTION RENEWAL	Waterford	22 and 23 Thomas Hill, Waterford	3	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1610	1610	SHIP CONSTRUCTION RENEWAL	Waterford	Apts 1-6, The Old Convent, Kilmacthomas	6	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1611	1611	SHIP CONSTRUCTION RENEWAL	Waterford	70 and 71 O'Connell Street, Waterford	5	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1612	1612	SHIP CONSTRUCTION DESIGN BUILD	Waterford	Ballygunner, Waterford City	49	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1613	1613	SHIP CONSTRUCTION DESIGN BUILD	Waterford	Ballynaneashagh, Waterford City	22	*N/A				Stage 4 approved Q3-2022, the scheme is fully approved.		
1614	1614	SHIP CONSTRUCTION	Waterford	An Garr�n, Crobally Upper, Tramore	50	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1615	1615	SHIP CONSTRUCTION	Waterford	Larchville, Waterford City	5	*N/A						Q2-2021
1616	1616	SHIP CONSTRUCTION	Waterford	Doyles Street, Waterford City	4	*N/A						Q4-2021
1617	1617	SHIP CONSTRUCTION	Waterford	The Glen, Bridge St, Waterford	17	*N/A		Stage 2 approved Q3-2018, full design/tender being prepared.				
1618	1618	SHIP CONSTRUCTION	Waterford	Summerland Square, Waterford	12	*N/A			Stage 3 approved Q1-2019, the scheme is now approved to proceed to tender.			
1619	1619	SHIP CONSTRUCTION	Waterford	Graigueshoneen, Kilmacthomas	16	*N/A						Q1-2022
1620	1620	SHIP CONSTRUCTION	Waterford	Mount Esker, Ballytruckle Road, Waterford City	14	*N/A						Q4-2022
1621	1621	SHIP CONSTRUCTION	Waterford	Newgate Street, Waterford City	27	*N/A	Stage 1 approved Q3-2020, outline design and costs being prepared.					
1622	1622	SHIP CONSTRUCTION	Waterford	Fountain Street, Ferrybank, Waterford	14	*N/A			Stage 3 approved Q1-2022, the scheme is now approved to proceed to tender.			
1623	1623	SHIP CONSTRUCTION	Waterford	50-53 Ballytruckle Road, Waterford	11	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1624	1624	SHIP CONSTRUCTION	Waterford	Rossmore, Kilmacthomas	6	*N/A		Stage 2 approved Q3-2022, full design/tender being prepared.				
1625	1625	CAS CONSTRUCTION RENEWAL	Waterford	Wadding Manor, Ferrybank	10	Respond						Q2-2021
1626	1626	CAS CONSTRUCTION	Waterford	Ballycarnane, Tramore	18	Oaklee Housing Trust	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1627	1627	CAS CONSTRUCTION	Waterford	21 Bridge Street, Waterford City	4	Society of Saint Vincent de Paul	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1628	1628	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 1)	24	*N/A						Q2-2021
1629	1629	PUBLIC PRIVATE PARTNERSHIP (Bundle 2)	Waterford	Slievekeale, Waterford City (Phase 2)	34	*N/A						Q3-2021
1630	1630	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 1)	26	Circle Voluntary Housing Association Ltd						Q4-2021
1631	1631	CALF Turnkey	Waterford	Mount Neil, Carrickphierish, Gracedieu, Co. Waterford (Phase 2)	31	Circle Voluntary Housing Association Ltd						Q2-2022
1632	1632	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 1)	6	Oaklee Housing						Q4-2022
1633	1633	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 2)*	7	Oaklee Housing						Q4-2022
1634	1634	CALF Turnkey	Waterford	Ormonde Drive, Kilbarry, Co. Waterford  (Phase 3)	2	Oaklee Housing						Q4-2022
1635	1635	CALF Turnkey	Waterford	Sl� na Coille, Tramore, Co Waterford (Phase 1)*	27	Cl�id Housing						Q3-2022
1636	1636	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
1637	1637	SHIP DIALOG	Westmeath	Lissywollen, Athlone	55	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
1638	1638	SHIP DIALOG	Westmeath	Lissywollen, Athlone	38	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
1639	1639	SHIP DIALOG	Westmeath	Lissywollen, Athlone	22	*N/A				Stage 4 approved Q3-2020, the scheme is fully approved.		
1640	1640	SHIP CONSTRUCTION TURNKEY	Westmeath	Barrack Court, Bellview Road, Austin Friar Street, Mullingar	4	*N/A						Q4-2022
1641	1641	SHIP CONSTRUCTION TURNKEY	Westmeath	Oakcrest, Ballinderry, Mullingar	5	*N/A						Q4-2022
1642	1642	SHIP CONSTRUCTION TURNKEY	Westmeath	St. Marys Place, Athlone	9	*N/A					Q2-2021	
1643	1643	SHIP CONSTRUCTION TURNKEY	Westmeath	Rathgarve Green, Castlepollard	1	*N/A						Q2-2021
1644	1644	SHIP CONSTRUCTION TURNKEY	Westmeath	Bellaugh, Athlone	17	*N/A						Q4-2022
1645	1645	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	7	*N/A						Q2-2022
1646	1646	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	17	*N/A						Q4-2022
1647	1647	SHIP CONSTRUCTION TURNKEY	Westmeath	The Cedars, Lakepoint, Mullingar	4	*N/A						Q4-2022
1648	1648	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friar Street, Mullingar	2	*N/A						Q4-2022
1649	1649	SHIP CONSTRUCTION TURNKEY	Westmeath	Athboy Rd, Delvin	6	*N/A					Q1-2022	
1650	1650	SHIP CONSTRUCTION TURNKEY	Westmeath	Kileenboylegan, Moate	6	*N/A				Stage 4 approved Q4-2021, the scheme is fully approved.		
1651	1651	SHIP CONSTRUCTION TURNKEY	Westmeath	Mount Carmel Drive, Moate	9	N/A					Q2-2022	
1652	1652	SHIP CONSTRUCTION TURNKEY	Westmeath	Austin Friar Street, Mullingar	4	*N/A				Stage 4 approved Q1-2022, the scheme is fully approved.		
1653	1653	SHIP CONSTRUCTION TURNKEY	Westmeath	Oakcrest, Ballinderry, Mullingar	3	*N/A					Q4-2019	
1654	1654	SHIP CONSTRUCTION TURNKEY	Westmeath	Arcadia, Clonbrusk	2	*N/A					Q2-2021	
1655	1655	SHIP CONSTRUCTION RENEWAL	Westmeath	36 Connaught Street, Athlone	3	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1656	1656	SHIP CONSTRUCTION RENEWAL	Westmeath	53 Connaught Street, Athlone	1	*N/A	Stage 1 approved Q4-2022, outline design and costs being prepared.					
1657	1657	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	O'Growney Green, Mullingar	22	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1658	1658	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Dalton Park, Mullingar	17	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1659	1659	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Water Street, Castlepollard	8	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
1660	1660	SHIP CONSTRUCTION DESIGN BUILD	Westmeath	Ennell Court, Mullingar (Phase 1)	15	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1661	1661	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	8	*N/A						Q2-2021
1662	1662	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	19	*N/A						Q4-2022
1663	1663	SHIP CONSTRUCTION	Westmeath	Quinlan Park, Athlone	10	*N/A						Q4-2022
1664	1664	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A						Q2-2021
1665	1665	SHIP CONSTRUCTION	Westmeath	Greally Park, Arcadia, Athlone (Phase 2)	24	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1666	1666	SHIP CONSTRUCTION	Westmeath	Canal Avenue, Mullingar	32	*N/A		Stage 2 approved Q4-2020, full design/tender being prepared.				
1667	1667	SHIP CONSTRUCTION	Westmeath	Bun Daire, Kinnegad (Phase 3)	4	*N/A						Q3-2021
1668	1668	SHIP CONSTRUCTION	Westmeath	Bishopsgate, Mullingar	2	*N/A						Q4-2021
1669	1669	SHIP CONSTRUCTION	Westmeath	Abbey Rd, Athlone	1	N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1670	1670	SHIP CONSTRUCTION	Westmeath	Cornamaddy, Athlone	50	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1671	1671	SHIP CONSTRUCTION	Westmeath	Water Street, Castlepollard 	1	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1672	1672	SHIP CONSTRUCTION	Westmeath	Belvedere Orphanage, Tyrellspass	6	*N/A	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1673	1673	SHIP CONSTRUCTION	Westmeath	Cornamaddy, Athlone	58	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1674	1674	SHIP CONSTRUCTION	Westmeath	Ennell Court, Mullingar	12	*N/A						Q4-2022
1675	1675	SHIP CONSTRUCTION	Westmeath	Abbeylands, Mullingar	1	*N/A		Stage 2 approved Q4-2022, full design/tender being prepared.				
1676	1676	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	10	T�ath Housing Association Ltd						Q1-2021
1677	1677	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	17	T�ath Housing Association Ltd						Q3-2022
1678	1678	CAS CONSTRUCTION TURNKEY	Westmeath	Elm Row, Royal Canal, Mullingar	9	T�ath Housing Association Ltd						Q3-2022
1679	1679	CAS CONSTRUCTION RENEWAL	Westmeath	The Hermitage Building, Retreat Road, Athlone	55	T�ath Housing Association Ltd	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1680	1680	CAS CONSTRUCTION	Westmeath	Farran, Mullingar	4	T�ath Housing Association Ltd						Q3-2021
1681	1681	CALF Turnkey	Westmeath	Ashe Road, Mullingar, Co. Westmeath (Phase 1)*	18	Cl�id Housing					Q2-2021	
1682	1682	CALF Turnkey	Westmeath	Athlone Road, Moate, Co. Westmeath (Phase 1)*	14	Oaklee Housing						Q2-2021
1683	1683	CALF Turnkey	Westmeath	Bower Hill, Lower Road, Athlone, Co. Westmeath (Phase 1)*	15	Cl�id Housing					Q4-2022	
1684	1684	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 1)*	44	Respond					Q4-2021	
1685	1685	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 2)*	39	Respond					Q4-2021	
1686	1686	CALF Turnkey	Westmeath	Charlestown, Mullingar (Phase 3)	16	Respond					Q4-2021	
1687	1687	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 2)*	23	Cl�id Housing						Q1-2021
1688	1688	CALF Turnkey	Westmeath	Coill Rua, Mullingar, Co. Westmeath (Phase 3)	8	Cl�id Housing						Q2-2021
1689	1689	CALF Construction	Westmeath	Farran, Mullingar, Co. Westmeath (Phase 1)	10	Tuath Housing Association						Q3-2021
1690	1690	CALF Turnkey	Westmeath	Garran Gael, Kinnegad, Westmeath (Phase 1)*	24	Tuath Housing Association						Q4-2022
1691	1691	CALF Turnkey	Westmeath	Rahanine, Rochfortbridge, Co Westmeath (Phase 1)*	12	Tuath Housing Association						Q2-2021
1692	1692	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 1)	4	Tuath Housing Association						Q1-2021
1693	1693	CALF Turnkey	Westmeath	Royal Canal, Ardmore Road, Mullingar, Co. Westmeath (Phase 2)	4	Tuath Housing Association						Q2-2022
1694	1694	CALF Turnkey	Westmeath	Springfield Cottages, Mullingar, Co. Westmeath (Phase 1)*	13	Cl�id Housing					Q4-2021	
1695	1695	SHIP CONSTRUCTION TURNKEY	Wexford	Airhill, Belvedere Rd, Wexford	7	*N/A						Q3-2021
1696	1696	SHIP CONSTRUCTION TURNKEY	Wexford	Michael Street, New Ross 	3	*N/A						Q2-2021
1697	1697	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	4	*N/A						Q2-2022
1698	1698	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	10	*N/A						Q3-2022
1699	1699	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Gorey - Phase 2	4	*N/A						Q4-2021
1700	1700	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	5	*N/A						Q2-2021
1701	1701	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	5	*N/A						Q4-2021
1702	1702	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	6	*N/A						Q4-2021
1703	1703	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A						Q2-2021
1704	1704	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross	16	*N/A						Q4-2022
1705	1705	SHIP CONSTRUCTION TURNKEY	Wexford	Tobar Muire, Creagh Gorey	29	*N/A					Q4-2020	
1706	1706	SHIP CONSTRUCTION TURNKEY	Wexford	Ballynaglough, Blackwater	12	*N/A						Q4-2022
1707	1707	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A						Q2-2022
1708	1708	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	4	*N/A						Q2-2022
1709	1709	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A						Q2-2022
1710	1710	SHIP CONSTRUCTION TURNKEY	Wexford	Roxborough Manor, Mulgannon	3	*N/A						Q4-2022
1711	1711	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock, Wexford	2	*N/A						Q2-2021
1712	1712	SHIP CONSTRUCTION TURNKEY	Wexford	Clonard Little, Wexford 	9	*N/A					Q2-2022	
1713	1713	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross	14	*N/A						Q4-2022
1714	1714	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	7	*N/A						Q1-2022
1715	1715	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	4	*N/A						Q2-2022
1716	1716	SHIP CONSTRUCTION TURNKEY	Wexford	Haughton Place, New Ross	12	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1717	1717	SHIP CONSTRUCTION TURNKEY	Wexford	Castlelands, Ferns	20	*N/A					Q4-2020	
1718	1718	SHIP CONSTRUCTION TURNKEY	Wexford	Cluain Beag, Clonard, Wexford	2	*N/A						Q2-2022
1719	1719	SHIP CONSTRUCTION TURNKEY	Wexford	Ard Uisce, Whiterock Hill, Wexford	4	*N/A						Q4-2022
1720	1720	SHIP CONSTRUCTION TURNKEY	Wexford	An Glasan, Greenville Lane, Enniscorthy	8	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1721	1721	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan, Gorey	24	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1722	1722	SHIP CONSTRUCTION TURNKEY	Wexford	Cross Street, New Ross	2	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1723	1723	SHIP CONSTRUCTION TURNKEY	Wexford	Green Hill, Clonhaston, Enniscorthy	8	*N/A						Q4-2022
1724	1724	SHIP CONSTRUCTION TURNKEY	Wexford	Ard an Bhile, Healysland, New Ross	13	*N/A						Q4-2022
1725	1725	SHIP CONSTRUCTION TURNKEY	Wexford	Gleann an Ghairdin, Ballytegan, Gorey	16	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1726	1726	SHIP CONSTRUCTION	Wexford	Whiterock Hill, Wexford - Phase 1	22	*N/A					Q4-2021	
1727	1727	SHIP CONSTRUCTION	Wexford	Killeens, Wexford	60	*N/A	Stage 1 approved Q1-2018, outline design and costs being prepared.					
1728	1728	SHIP CONSTRUCTION	Wexford	Ross Road, Enniscorthy	1	*N/A						Q4-2021
1729	1729	SHIP CONSTRUCTION	Wexford	Glentire, The Ballagh, Enniscorthy	7	*N/A						Q3-2022
1730	1730	SHIP CONSTRUCTION	Wexford	Rosetown, Rosslare - Phase 1	23	*N/A						Q4-2022
1731	1731	SHIP CONSTRUCTION	Wexford	Carley's Bridge, Enniscorthy	17	*N/A						Q1-2022
1732	1732	SHIP CONSTRUCTION	Wexford	Creagh, Gorey	22	*N/A	Stage 1 approved Q2-2018, outline design and costs being prepared.					
1733	1733	SHIP CONSTRUCTION	Wexford	Rosbercon, New Ross	38	*N/A	Stage 1 approved Q2-2022, outline design and costs being prepared.					
1734	1734	SHIP CONSTRUCTION	Wexford	Wexford Street, Gorey	30	*N/A			Stage 3 approved Q4-2022, the scheme is now approved to proceed to tender.			
1735	1735	SHIP CONSTRUCTION	Wexford	Ballyhine, Barntown	7	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1736	1736	SHIP CONSTRUCTION	Wexford	Whiterock Hill, Wexford - Phase 2	22	*N/A			Stage 3 approved Q1-2020, the scheme is now approved to proceed to tender.			
1737	1737	SHIP CONSTRUCTION	Wexford	Rosetown, Rosslare - Phase 2	12	*N/A			Stage 3 approved Q3-2022, the scheme is now approved to proceed to tender.			
1738	1738	SHIP CONSTRUCTION	Wexford	Doire Moling, Monamolin, Gorey, Co. Wexford	5	*N/A	Stage 1 approved Q3-2021, outline design and costs being prepared.					
1739	1739	SHIP CONSTRUCTION	Wexford	Ballygillane Big, Rosslare Harbour	5	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1740	1740	SHIP CONSTRUCTION	Wexford	Grogan?s Road, Wexford Town 	4	*N/A	Stage 1 approved Q4-2021, outline design and costs being prepared.					
1741	1741	CAS CONSTRUCTION TURNKEY	Wexford	Clonattin, Gorey	6	T�ath Housing Association Ltd						Q2-2021
1742	1742	CAS CONSTRUCTION TURNKEY	Wexford	2&3 The Quay, New Ross	6	Peter McVerry Trust Ltd						Q4-2022
1743	1743	CAS CONSTRUCTION RENEWAL	Wexford	Ard na Naoimh, Gorey Hill	4	St. Aidan's Day Care Centre CLG	Stage 1 approved Q1-2022, outline design and costs being prepared.					
1744	1744	CAS CONSTRUCTION	Wexford	Wexford Women's Refuge, Maudlintown	12	Wexford Womens? Refuge CLG				Stage 4 approved Q4-2022, the scheme is fully approved.		
1745	1745	CALF Turnkey	Wexford	67 units, Coolcotts, Wexford (Barr An Aird, Coolcotts) (Phase 1)*	67	Cl�id Housing						Q4-2022
1746	1746	CALF Turnkey	Wexford	9 Units, Gleann an Ghairdin, Gorey, Co. Wexford (Phase 1)	9	Tuath Housing Association						Q2-2021
1747	1747	CALF Turnkey	Wexford	Bridgemeadow, Enniscorthy, Co. Wexford (Phase 1)*	12	Cl�id Housing					Q1-2022	
1748	1748	CALF Turnkey	Wexford	Cuil na Dara, Coolcotts, Wexford  (Phase 1)*	25	Co - Operative Housing Ireland Society Limited					Q2-2022	
1749	1749	CALF Turnkey	Wexford	Forgelands, Enniscorthy Co. Wexford. (Phase 1)	10	Tuath Housing Association						Q3-2022
1750	1750	CALF Turnkey	Wexford	Forgelands, Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 1)*	18	Tuath Housing Association						Q3-2021
1751	1751	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey, Co Wexford (Phase 1)	16	Tuath Housing Association						Q4-2022
1752	1752	CALF Turnkey	Wexford	Gleann an Ghairdin, Gorey, Co Wexford (Phase 2)	8	Tuath Housing Association					Q3-2021	
1753	1753	CALF Construction	Wexford	Hewitsland, New Ross, County Wexford (Phase 1)	48	Cl�id Housing				Q2-2022		
1754	1754	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 3)	16	Tuath Housing Association						Q1-2021
1755	1755	CALF Turnkey	Wexford	Kerlogue Manor, Roxborough, Drinagh, Wexford (Phase 4)*	27	Tuath Housing Association						Q2-2021
1756	1756	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 1)	12	Co - Operative Housing Ireland Society Limited						Q4-2021
1757	1757	CALF Turnkey	Wexford	Mill Heights, Castlebridge, Wexford (Phase 2)*	13	Co - Operative Housing Ireland Society Limited						Q1-2022
1758	1758	CALF Turnkey	Wexford	Moongate, Townspark, Co Wexford (Phase 1)*	17	Co - Operative Housing Ireland Society Limited						Q4-2022
1759	1759	CALF Turnkey	Wexford	Moongate, Townspark, Co Wexford (Phase 2)*	21	Co - Operative Housing Ireland Society Limited					Q2-2022	
1760	1760	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 3)*	8	Tuath Housing Association						Q1-2021
1761	1761	CALF Turnkey	Wexford	Old Forge Road, Milehouse Road, Enniscorthy, Co. Wexford (Phase 4)*	8	Tuath Housing Association						Q2-2021
1762	1762	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 1)*	15	Co - Operative Housing Ireland Society Limited						Q4-2021
1763	1763	CALF Turnkey	Wexford	Pairc na Dara, Coolcotts, Wexford, Co. Wexford (Phase 2)	19	Co - Operative Housing Ireland Society Limited						Q4-2021
1764	1764	CALF Turnkey	Wexford	P�irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 1)*	16	Cl�id Housing						Q3-2021
1765	1765	CALF Turnkey	Wexford	P�irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 2)*	14	Cl�id Housing						Q3-2021
1766	1766	CALF Turnkey	Wexford	P�irc na gCon, Greenville Lane, Enniscorthy, Co. Wexford (Phase 3)	22	Cl�id Housing						Q4-2021
1767	1767	CALF Turnkey	Wexford	"Pairc na Greine, Coolcotts, Wexford phase 2 (Sub phase 2).
 (Phase 1)"	24	Co - Operative Housing Ireland Society Limited					Q2-2022	
1768	1768	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 1)	24	Tuath Housing Association						Q4-2022
1769	1769	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 2)	20	Tuath Housing Association					Q2-2021	
1770	1770	CALF Turnkey	Wexford	Ramstown, Gorey, Wexford (Phase 3)*	24	Tuath Housing Association					Q2-2021	
1771	1771	CALF Turnkey	Wexford	Tobar Mhuire, Creagh, Gorey, Wexford (Phase 1)*	17	Cl�id Housing						Q4-2022
1772	1772	SHIP CONSTRUCTION TURNKEY	Wicklow	The Birches, Ballinaclash	2	*N/A						Q2-2021
1773	1773	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	2	*N/A						Q1-2021
1774	1774	SHIP CONSTRUCTION TURNKEY	Wicklow	Vartry Heights, Roundwood	3	*N/A				Stage 4 approved Q1-2021, the scheme is fully approved.		
1775	1775	SHIP CONSTRUCTION TURNKEY	Wicklow	Avonmore View, Rathdrum	13	*N/A					Q4-2021	
1776	1776	SHIP CONSTRUCTION TURNKEY	Wicklow	Bramble Hill, Lugduff, Tinahely	1	*N/A						Q2-2021
1777	1777	SHIP CONSTRUCTION TURNKEY	Wicklow	95 Waverley Drive, Broomhall, Rathnew	1	*N/A						Q1-2022
1778	1778	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	3	*N/A						Q2-2022
1779	1779	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	3	N/A						Q1-2022
1780	1780	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	1	*N/A						Q2-2022
1781	1781	SHIP CONSTRUCTION TURNKEY	Wicklow	Waverley Drive, Broomhall, Rathnew	2	*N/A						Q2-2022
1782	1782	SHIP CONSTRUCTION SINGLE STAGE	Wicklow	Ballynerrin Upper, Wicklow Town	10	*N/A				Stage 4 approved Q2-2022, the scheme is fully approved.		
1783	1783	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Merrymeeting View, Rathnew	46	*N/A						Q2-2021
1784	1784	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Shillelagh (Phase 4)	20	*N/A					Q4-2022	
1785	1785	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Ashtown Lane, Wicklow Town	40	*N/A						Q2-2022
1786	1786	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Ard na Greine, West Ward, Bray	31	*N/A						Q1-2022
1787	1787	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Avondale Heights, Rathdrum	20	*N/A					Q3-2021	
1788	1788	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Sheehan Court, Back Street, Arklow	7	*N/A						Q3-2022
1789	1789	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Mountainview, Moneycarroll, Newtownmountkennedy	22	*N/A						Q2-2022
1790	1790	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Three Trouts, Greystones	41	*N/A					Q3-2022	
1791	1791	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Cedar Court, Schools Road, Bray	14	*N/A					Q1-2022	
1792	1792	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Coolattin Oaks, Carnew (Phase 4)	8	*N/A						Q1-2021
1793	1793	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Rathnew, Merrymeeting (Phase 2)	21	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1794	1794	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Tinahely, Lugduff	20	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1795	1795	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Carrigoona, Bray	15	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
1796	1796	SHIP CONSTRUCTION DESIGN BUILD	Wicklow	Lott Lane, Kilcoole	80	*N/A		Stage 2 approved Q2-2022, full design/tender being prepared.				
1797	1797	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow	10	*N/A						Q1-2022
1798	1798	SHIP CONSTRUCTION	Wicklow	10A & 10 B Castle Villas, Greystones	2	*N/A					Q4-2022	
1799	1799	SHIP CONSTRUCTION	Wicklow	Delaney Park, Emoclew Road, Arklow (Phase 2)	37	*N/A						Q4-2021
1800	1800	SHIP CONSTRUCTION	Wicklow	Blackhills, Glenealy	2	*N/A					Q4-2021	
1801	1801	SHIP CONSTRUCTION	Wicklow	Age Friendly Apartments at Main St, Kilcoole, Greystones	4	*N/A		Stage 2 approved Q3-2021, full design/tender being prepared.				
1802	1802	SHIP CONSTRUCTION	Wicklow	Mill Road, Killincarrig, Greystones	2	*N/A					Q4-2022	
1803	1803	SHIP CONSTRUCTION	Wicklow	Carraig Eden, Greysones (Phase 3)	14	*N/A		Stage 2 approved Q4-2021, full design/tender being prepared.				
1804	1804	SHIP CONSTRUCTION	Wicklow	Kilbride Lane, Bray (Murphy's Lands)	19	*N/A						Q2-2021
1805	1805	SHIP CONSTRUCTION	Wicklow	Knockroe, Delgany	2	*N/A				Stage 4 approved Q4-2022, the scheme is fully approved.		
1806	1806	SHIP CONSTRUCTION	Wicklow	10A Mill Road, Greystones	2	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1807	1807	SHIP CONSTRUCTION	Wicklow	Mountain View, Blessington	10	*N/A	Stage 1 approved Q3-2022, outline design and costs being prepared.					
1808	1808	CAS CONSTRUCTION TURNKEY	Wicklow	Rathcoran Square, Baltinglass	8	Peter McVerry Trust Ltd						Q2-2021
1809	1809	CAS CONSTRUCTION TURNKEY	Wicklow	Aldborough Manor, Hawkins Wood, Greystones	90	T�ath Housing Association Ltd						Q4-2022
1810	1810	CAS CONSTRUCTION SINGLE STAGE	Wicklow	Hollybrook Park, Bray	4	St. John of God Housing Association Ltd				Stage 4 approved Q3-2019, the scheme is fully approved.		
1811	1811	CAS CONSTRUCTION RENEWAL	Wicklow	4 Wyndham Park, Bray	2	DePaul Housing				Stage 4 approved Q3-2022, the scheme is fully approved.		
1812	1812	PUBLIC PRIVATE PARTNERSHIP (Bundle 3)	Wicklow	Burgage More, Blessington, Co. Wicklow	106	*N/A			Q4-2022			
1813	1813	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Wicklow	Burnaby, Greystones	80	N/A	Q2-2022					
1814	1814	PUBLIC PRIVATE PARTNERSHIP (Bundle 5)	Wicklow	Rehillls, Bray	120	N/A	Q2-2022 					
1815	1815	CALF Turnkey	Wicklow	Adelaide Apartments, St Laurence?s Terrace, Bray, Co. Wicklow (Phase 1)*	18	Respond					Q2-2021	
1816	1816	CALF Turnkey	Wicklow	Aldborough Hall, Hawkins Wood, Greystones, Co. Wicklow (Phase 1)	84	Tuath Housing Association						Q4-2022
1817	1817	CALF Turnkey	Wicklow	Avondale Grange, Ballygannon, Rathdrum, Co. Wicklow (Phase 1)*	36	Respond					Q2-2021	
1818	1818	CALF Turnkey	Wicklow	Fairgreen Manor, Dunlavin, Co. Wicklow (Phase 1)*	40	Circle Voluntary Housing Association Ltd						Q3-2021
1819	1819	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 1)*	14	Tuath Housing Association						Q4-2022
1820	1820	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 2)*	30	Tuath Housing Association						Q4-2022
1821	1821	CALF Turnkey	Wicklow	Hawkins Wood, Greystones and Archers Wood, Delgany, Wicklow (Phase 3)*	16	Tuath Housing Association						Q4-2022
1822	1822	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 1)	11	Tuath Housing Association						Q2-2022
1823	1823	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 2)	12	Tuath Housing Association						Q3-2022
1824	1824	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 3)	17	Tuath Housing Association						Q4-2022
1825	1825	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 4)	9	Tuath Housing Association					Q2-2021	
1826	1826	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 5)	10	Tuath Housing Association					Q2-2021	
1827	1827	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 6)*	12	Tuath Housing Association					Q2-2021	
1828	1828	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow (Phase 7)*	17	Tuath Housing Association					Q2-2021	
1829	1829	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 1)	15	Tuath Housing Association						Q4-2021
1830	1830	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 2)	10	Tuath Housing Association						Q1-2022
1831	1831	CALF Turnkey	Wicklow	Heatherside, Vale Road, Arklow, Co. Wicklow (Phase 3)	3	Tuath Housing Association					Q4-2020	
1832	1832	CALF Turnkey	Wicklow	Meadow Gate, Marlton Road, Co Wicklow (Phase 1)*	6	Tuath Housing Association						Q4-2022
1833	1833	CALF Turnkey	Wicklow	Oak Springs, Rathdrum, County Wicklow  (Phase 1)*	5	Tuath Housing Association						Q3-2022
1834	1834	CALF Turnkey	Wicklow	Phase 2, Southern Cross, Bray, Co. Wicklow (Phase 1)	80	Co - Operative Housing Ireland Society Limited						Q4-2022
1835	1835	CALF Turnkey	Wicklow	Phase 3, Southern Cross, Bray, Co. Wicklow (Phase 1)*	80	Co - Operative Housing Ireland Society Limited					Q4-2020	
1836	1836	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 2)*	24	Respond						Q2-2021
1837	1837	CALF Turnkey	Wicklow	Rathcoran House, Baltinglass, Co. Wicklow (Phase 3)	16	Respond						Q3-2021
1838	1838	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 1)*"	30	Co - Operative Housing Ireland Society Limited						Q2-2022
1839	1839	CALF Turnkey	Wicklow	"Southern Cross, Bray, Co. Wicklow
 (Phase 2)*"	18	Co - Operative Housing Ireland Society Limited						Q3-2022
1840	1840	CALF Turnkey	Wicklow	Vartry Wood, Ashford, Co. Wicklow (Phase 1)*	16	Cl�id Housing						Q4-2022