EIA Location Point
This feature service is used to collect primary information on Environmental Impact Assessments and display the information on the EIA Web Aap. The ‘Environmental Impact... -
Planning Application Sites
This dataset contains the merged Planning Registers of participating Irish Local Authorities and includes all Planning Applications received since 2012. -
Planning Application Points
This dataset contains the merged Planning Registers of participating Irish Local Authorities and includes all Planning Applications received since 2012. -
Social Housing Construction Status Report Q3 2024
The latest Construction Status Report shows that 12,492 social homes are currently onsite with an additional 15,750 homes at design and tender stage, giving a total of 28,242... -
Planning Exemptions - Local Authorities
The dataset represents planning exemption notifications received by local authorities at local authority level. Source:Â Local authority annual data returns. Boundaries:... -
Planning Exemptions - Settlements
The dataset represents planning exemption notifications received by local authorities at settlement level. The dataset includes information on settlements that have received... -
GZT Current Plan
Generalised Zoning Types developed for the Myplan.ie project. This represents a consistent zoning scheme across all local authorities, and complements (rather than replaces)... -
Social Housing Construction Status Report Q2 2024
The Q2 2024 Construction Status Report shows that 10,465 social homes are currently onsite with an additional 16,614 homes at design and tender stage. In Quarter 2 2024, 212 new... -
Social Housing Construction Status Report Q1 2024
The Q1 2024 Construction Status Report shows that 9,179 social homes are currently onsite with an additional 15,848 homes at design and tender stage. In Quarter 1 2024, 121 new... -
Social Housing Construction Status Report Q4 2023
The latest Construction Status Report shows that 7,089 social homes are currently onsite with an additional 15,448 homes at design and tender stage. In Quarter 4 2023, 190 new... -
Social Housing Construction Status Report Q4 2022
The latest Construction Status Report shows that 6,525 social homes were onsite at the end of 2022, with an additional 12,733 homes at design and tender stage. In Quarter 4...